Loading...
HomeMy WebLinkAboutCAG2023-006 - Change Order - #4 - Rodarte Construction, Inc. - Washington Avenue South Stormwater Pump Station - 1/10/25 140 Agreement Routing Form • For Approvals,Signatures and Records Management E1T This form combines&replaces the Request for Mayor's Signature and Contract Cover Sheet forms. W A S H I N G T O N (Print on pink or cherry colored paper) Originator: Department: S.Anderson PW Engineering Date Sent: Date Required: > 1/13/25 0 L al:Authorized to Sign: Date of Council Approva a 0 Director or Designee ❑Mayor 6/06/2023 Budget Account Number: Grant? ❑Yes l7 No D20119.64110.120 Budget? 0 Yes ❑No Type: N/A Vendor Name: Category: Rodarte Construction, Inc. Contract Vendor Number: Sub-Category c Change Order#4 0 Project Name: Washington Avenue South Stormwater Pump Station E L C Project Details:install approximately 110 LF of City provided no-cut fence along 1st Avenue near the Larc property.Supply and install replacement decorative fence panels along BNSF railroad tracks just south of the Smith Street 4.0 crossing removed by others. C d E Agreement Amount:$8,330.01 Basis for Selection of Contractor: Bid W 541 Start Date: N/A Termination Date: 330 Working Days a Local Business? ❑Yes ❑No* *Ifineets requirements per KCC3.70.700,pleosecomplete"Vendor Purchase-Local Exceptions"form on Cityspace. Notice required prior to disclosure? Contract Number: ❑Yes 0 No CAG2023-006 Date Received by City Attorney: Comments Im C .� d d L l0 Cn Date Routed to the Mayor's Office: t%Y Date Routed to the City Clerk's Office. 1/13/25 adaW22373 1 20 Visit Documents.KentWA.gov to obtain copies of all agreements ■ KENT W A 5 M I.G T G. CHANGE ORDER NO. #4 NAME OF CONTRACTOR: Rodarte Construction Inc. ("Contractor") CONTRACT NAME & PROJECT NUMBER: Washington Avenue South Stormwater Puml2 Station ORIGINAL CONTRACT DATE: June 21 2023 This Change Order amends the above-referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: i. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: Install approximately 110 LF of City provided no-cut fence along 1st Avenue near the Larc property. Supply and install replacement decorative fence panels along BNSF railroad tracks just south of the Smith Street crossing removed by others. 2. The contract amount and time for performance provisions of Section II "Time of Completion," and Section III, "Compensation," are hereby modified as follows: Original Contract Sum, $4,063,673.19 (including applicable alternates and WSST) Net Change by Previous Change Orders $109,988.18 (incl. applicable WSST) Current Contract Amount $4,173,661.37 (incl. Previous Change Orders) Current Change Order $7,558.99 Applicable WSST Tax on this Change $771.02 Order Revised Contract Sum $4,181,991.38 CHANGE ORDER - 1 OF 3 Original Time for Completion 330 working days (insert date) Revised Time for Completion under 0 working days prior Change Orders (insert date) Days Required (f) for this Change Order 0 working days Revised Time for Completion 330 working days (insert date) In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the Contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby ratified and affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written below. CONTRACTOR: CITY OF KENT: Digitally signed by Chad Bieren Chad B i e re n 0 to 2025.01.10 13:18:35-08'00' 13y (signature) By (signature) Print Name: 44PF-w Print Name: Chad Bieren P.E. Its 12 n Its Public Works Director (title) (title) DATE: G DATE: EC KP CHANGE ORDER - 2 OF 3 ATTEST: APPROVED AS TO FORM: (applicable if Mayor's signature required) Kent City Clerk Kent Law Department C[In this field,you may enter the electronic filepath where the contract has been saved] CHANGE ORDER - 3 OF 3 File No. 200.2 WASHINGTON CHANGE ORDER WORKSHEET NO. 4 Construction Engineering Division - Public Works Project: Washington Ave Pump Station Project No: 19-3031 Project Engineer: Stephen Lincoln TIB-Aid No: N/A Capital Projects Jason Bryant Contractor: Rodarte Manager: Date: 12/20/2024 I. Proposed Change Install approximately 110 LF of City provided no-cut fence along 1st Ave near the Larc property. Supply and install replacement decorative fence panels along BNSF railroad tracks just south of the Smith St crossing removed by others. II. Reason and Background for Change The City requested Rodarte's subcontractor C&P Fencing install approximately 110 LF of City provided no-cut fence along the BNSF Railroad tracks just south of the Larc property. This fence closes a gap in track access not included under Kent's original 23-3028.1 Railroad Quiet Zone BNSF Railroad Trespass Fencing project. The City of Kent's 23-2028.3 BNSF Quiet Zone project included installation of decorative fence along the railroad tracks. A revision added conduit trenching work requiring temporary removal of two fence panels and a post. These removed materials ended up being stolen from site. The BNSF Quiet Zone Contractor, Global Contractors, LLC, after repeated requests was unable to execute replacement. To prevent further delay, the City requested C&P Fencing supply and install the missing panels. III. Method of Payment NEW PAY ITEMS ❑ Notapplicable Sch. Item Description Total Est. Unit Unit Price Total Estimated Cost of No Item 1 Supply and install additional fence panels, 1 LS $7,558.99 $ 7,558.99 Install modified type 3 fence. F-1 New Pay Items Total: $ 7,558.99 Page 1 DELETE EXISTING PAY ITEMS) per 1-09.5 0 Notapplicable Sch Bid Item No. Item Description Qty Unit Unit Price Cost of Item No. $ - $ - $ Delete Existing Pay Items Total: $ - INCREASE/DECREASE TO EXISTING PAY ITEM(S) ❑ Notapplicable Sch Bid Item No. Item Description Qty Unit Unit Price Cost of Item No. $ - Increase / Decrease to Existing Pay Items Total: $ - *TOTAL ESTIMATED COST OF CHANGE ORDER: $7,558.99 * Total of the Cost of Item Columns IV. WORKING DAYS Original Contract: 330 Due This Change Order: 0 Previous Total: 330 Explanation/3ustification for Additional Working Days: *TOTAL WORKING DAYS: 330 * This Change Order + Previous Total Capital Projects Manager: �� Date: - Jason S' an / Construction Engineering Date. Supervisor: t Z ] on Barry Construction Manager: _ Date: Eric Connor Page 2 CHANGE ORDER PROPOSAL Lblw CONTRACTOR: Rodarte Construction SUBCONTRACTOR:C&P Fencing DATE 1/7/2025 r_c.,rnrwrcrrty. Change Order for Fencing on BNSF Crossing Improvements Based on C&P Qoute. LABOR WORKER'S NAME WORKER'S OCCUPATION REG HRS OT HRS REG RATE OT RATE AMOUNT $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 LABOR SUBTOTAL $0.00 29%OVERHEAD AND PROFIT,BONDING,INSURANCE $0.00 TOTAL LABOR L4.011 EQUIPMENT EQUIPMENT TYPE EQUIPMENT SIZE REGHRS STANDBYHRS REGRATE STNDBYRATE AMOUNT $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 EQUIPMENT SUBTOTAL $0.00 21%OVERHEAD AND PROFIT,BONDING,INSURANCE $0.00 TOTAL EQUIPMENT $0.00 MATERIALS I SERVICE VENDOR/INVOICE#/MATERIAL Unit Quantity Unit Price I AMOUNT $0.00 $0.00 $0.00 $0.00 $0.00 MATERIALS SUBTOTAL $0.00 21%OVERHEAD AND PROFIT,BONDING,INSURANCE $0.00 TOTAL MATERIALS $0.00SUBCONTRACTORS SUB/INVOICE#/WORK PERFORMED Unit Quantity Unit Price AMOUNT C&P Fencina 1 LS 1 $5,316.80 $5,316.80 C&P Fencing 2 LS 1 $1,432.30 $1.432.30 $0.00 $0.00 $0.00 SUBCONTRACTORS SUBTOTALF $6,749.10 12%OVERHEAD AND PROFIT,BONDING,INSURANCEI $809.89 TOTAL SUBCONTRACTORS1 $7,658.99 TOTAL COST $7,558.99 C&P Fencing Invoice 1516 Chinook Avenue Enumclaw WA 98022 Date Invoice# Phone 360-802-1059 Fax 360-450-5464 in12025 1320-3 Bill To Rodarte Construction Inc 17 E Valley Highway East Auburn WA 98092 P.O. No. Terms Project Net 45 Washington Ave S Stormwa.. Quantity Description Rate Amount WASHINGTON AVE S STORMWATER ADDITIONAL FENCING FOR CITY OF KENT 10 if 6 ft Modified Type 3 Non-Cut Chain Link Fence 33.23 332.30 I ea,Install 2 Wire Works Panels 1,100.00 1,100.00 Less Retention -71.62 -71.62 We appreciate your prompt payment. Total $1,360.68 C &P Fencing Invoice 1516 Chinook Avenue Enumclaw WA 98022 Date Invoice# Phone 360-802-1059 Fax 360-450-5464 11/25/2024 1320-2 Bill To Rodarte Construction Inc 17 E Valley Highway East Auburn WA 98092 P.O. No. Terms Project Net 45 Washington Ave S Stormwa... Quantity Description Rate Amount WASHINGTON AVE S STORMWATER PUMP STATION 160 If of 6'Modified Type 3 Non-Cut Chain Link Fence 33.23 5,316.80 Less Retention -265.84 -265.84 We appreciate your prompt payment. Total $5,050.96 Bryant, Jason From: Shields, Brian Sent: Tuesday, March 26, 2024 1:11 PM To: Hallock,Toby Cc: Bryant,Jason; Barry,Jason Subject: RE: Larc Fencing Toby, Do you have the map showing where the fence at LARC goes? I scoured my email earlier and couldn't find it.... Any help would be appreciated! Brian Shields, Capital Projects Manager Construction Management I Public Works Department 220 4th Avenue South, Kent, WA 98032 Main/Cel1 253-293-4973 1 Desk 253-856-6510 bshie1ds5KentWA.gov CITY OF KENT,WASHINGTON KentWA.aov Facebook YouTube From: Barry,Jason<JBarry@kentwa.gov> Sent:Tuesday, March 26, 2024 10:42 AM To:Shields, Brian<BShields@kentwa.gov> Cc: Bryant,Jason<J Bryant@ kentwa.gov> Subject: RE: Larc Fencing Thanks Brian. Is the location laid out in the field or who knows where it's going? What is the footage we're looking to have priced? From:Shields, Brian<BShields kentwa. ov> Sent:Tuesday, March 26, 2024 10:00 AM To: Barry,Jason<JBarrv@kentwa.g-oy> Cc: Bryant,Jason<JBryant@kentwa.gov> Subject: RE: Larc Fencing LARC fencing info. Details in plans. Submittal attached. The extra fence is at KEHOC; Rick knows where it is at, but Scott Schroeder does as well. Everything should be there except tension wire and nuts/bolts. Contractor will want to inventory what they need and include the extra parts in their pricing. 1 Brian Shields, Capita/Projects Manager Construction Management I Public Works Department 220 4th Avenue South, Kent, WA 98032 Main/Cell 253-293-4973 1 Desk 253-856-6510 bsh iel_d_s_@KentWA.goy CITY OF KENT,WASHINGTON KentWA.gov Facebook YouTube From: Barry,Jason<J Barry@ kentwa.gov> Sent:Tuesday, March 26, 2024 9:32 AM To:Shields, Brian<BShields@kentwa.gov> Subject: Larc Fencing Did you get Jason Bryant the info on the added fencing? Jason Barry, Capital Projects Supervisor Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5546 1 Cell 253-797-8462 KENT ]harry@KerntWA.gov w"'.-OTO" www.KentWA.aov PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E- MAIL 2 t 1516 Chinook Avenue, Enumclaw WA 98022 Ph 360-802-1059 Fax 360-450-5464 Contractor License CPFENPF882ME SCS Certification#1670 Enumclaw, WA Date: 8/12/2024 Rodarte Const Project: 2023 RR QZ BNSF Crossing Improvements Kent, WA Attention: Hayden We hereby propose to furnish the materials and perform the labor necessary for the completion of this project: Scope of Work To Be Completed: BID# DESCRIPTION QTY UNIT PRICE EXTENSION 1257 6 FT Coated Modified Type 3 No-Cut Chain Link Fence 129 $ 33.23 $ 4,286.67 Note. All Materials to be supplied by the City of Kent and Picked up by C&P Fencing.Any Materials needed to complete the fence supplied by C&P Fencing will be invoiced at the Washington State DOT Force Account Rate and Formula. TOTAL COST OF THIS ESTIMATE $ 4,286.67 We Acknowledge Addendum Number 0. King County Prevailing Wage Rates. Exclusions:Clearing and grading,concrete saw cutting and core drilling,bonding,surveys,signs,electrical grounding of fences,traffic control,Fall Protection Anchor Points,painting and staining of wood fencing,permits,surveying,labor agreements,staking the fence line,hazardous waste training or removal,temporary fence,concrete mowing strips,post sleeves/setting of post sleeves,damage to irrigation lines,padlocks,knox box,fence removal, sales tax,use tax. SUBMITTALS MUST BE APPROVED AND RETURNED PRIOR TO ORDERING MATERIAL THIS ESTIMATE IS TO BE INCLUDED AS AN EXHIBIT IN THE CONTRACT All material costs over$1,000.00 will be subject to a joint check agreement provided by our supplier C&P Fencing requests that retainage be paid 30 days after their work has been completed,provided that all paperwork,warranties,payroll reports, releases,etc.have been satisfied. "Quote good for 45 days.Materials must be ordered and shipped immediately in order to guarantee price.Material orders not received immediately are subject to any price increase initiated by our suppliers. IN WITNESS OF WHEREOF,the parties have hereunto caused this Agreement to be executed. Respectfully Submitted: Date: 8/12/2024 By: Paul Pohlman, Cell No. 253 740-5841, ppohlman@comcast.net Note: This proposal may be withdrawn by us if not accepted within 45 Days. Accepted Date: Title: Bryant, Jason From: Krier, Rick Sent: Thursday,August 1, 2024 10:05 AM To: Hayden Larson Cc: Barry,Jason; Bryant,Jason Subject: RE: 1st Ave.fence Rev. 3 Washington Ave pump sta. Attachments: IMG_6273 jpg; IMG_6271 jpg Hayden the fabric for this type of fence is a close mesh and is very heavy. I have included a few pictures, if Paul would like to look at it let me know and ill show him the location it is stored at. From: Hayden Larson<hayden@rodarteconstruction.com> Sent:Wednesday,July 31,202412:51 PM To: Krier, Rick<RKrier@kentwa.gov> Subject: Fwd: 1st Ave.fence Rev. 3 Washington Ave pump sta. This message originated outside the City of Kent. Use caution when following links or opening attachments as they can be malicious. Please contact IT Security at ISP@KentWA.uov with any questions. Can you answer his question? Thank You, Hayden Larson Rodarte Construction Inc. 253-204-9494 From: Paul Pohlman<Pcohlman@comcast.net> Sent:Wednesday,July 31, 2024 12:50:08 PM To: Hayden Larson<harden@rodarteconstruction.com> Subject: RE: 1st Ave.fence Rev. 3 Washington Ave pump sta. Hayden, need clarification on the "No Cut Chain Link Fabric" (Not a fencing term). would assume that they mean a 3/8" or a 5/8" Coated Chain Link Fabric but I need to be clear. Thank you, Paul Pohlman Estimator/Project Manager C & P Fencing 1516 ChinookAvenue Enumclaw, WA 98022 Office: 360 802-1059 i Fax: 360 450-5464 Cell 253 740-5841 From: Hayden Larson<harden@rodarteconstruction.com> Sent:Wednesday,July 31,2024 11:38 AM To: Paul Pohlman<ppohlman@comcast.net> Subject: FW: 1st Ave.fence Rev.3 Washington Ave pump sta. Paul, Can you quote the labor to install this? Thanks, Hayden Larson Rodarte Construction Inc. Cell: (253)204-9494 L RODAME CONSTRUCTION INC. 17 East Valley Hwy East Auburn,WA 98092 From: Krier, Rick<RKrier@kentwa.gov> Sent: Monday,July 22, 2024 9:59 AM To: Hayden Larson<harden@rodarteconstruction.com> Cc: Barry,Jason<JBarry@kentwa.go >; Bryant,Jason<}Bryant@kentwa.gov> Subject: 1st Ave.fence Rev. 3 Washington Ave pump sta. Hayden: Please see the attached plans for the added fence on 15t Ave N,The City would like to add this to your existing contract work for the pump sta.This work is for install only,the city will supply the chain link fabric and posts, you would have to pick up the martials at the city's yard on the east hill. Could you please supply the city a quote and schedule as soon as possible. If you have any questions, please call. 253-350-1325 AlIVAiel- City of Kent Sr. Inspector Capital Projects z Bryant, Jason From: Barry,Jason Sent: Monday,August 12, 2024 3:16 PM To: Bryant,Jason Cc: Krier, Rick;Connor, Eric Subject: FW: Larc Fencing - Potential Add to WA Ave PS Looks like we're good to go. Thanks for the help! Jason Jason Barry, Capital Projects Supervisor Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 400e Phone 253-856-5546 1 Cell 253-797-8462 KENT iba,,&KentWA.ao� w" "°" www.KentWA.gov n e PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E- MAIL From: Peterson, Kelly<KPeterson@kentwa.gov> Sent: Monday,August 12, 2024 2:00 PM To:Connor, Eric<EConnor@kentwa.gov> Cc: Barry,Jason<JBarry@kentwa.gov>; Bieren, Chad<CBieren@kentwa.gov> Subject: RE: Larc Fencing-Potential Add to WA Ave PS Please proceed. Thank you, Kelly From: Connor, Eric<EConnor@kentwa.gov> Sent: Monday,August 12, 2024 1:54 PM To: Peterson, Kelly<KPeterson@kentwa.g v_> Cc: Barry,Jason<JBarry@kentwa.gov> Subject: Larc Fencing-Potential Add to WA Ave PS Good afternoon Kelly, Our contractor on Washington Avenue Pump Station was able to get their fencing subcontractor to provide pricing for the fencing that is needed along the Larc Property on 1st Ave. They have proposed to install approximately 129 LF of City of Kent provided fencing for $4,801.07. This includes 12% GC markup. Are you okay with preparing and issuing a change order for this work? 1 Please let me know if you have any questions or need any additional information. Thank you, Eric Eric Connor, Construction Engineering Manager Phone 253-856-SS33 I Cell 253-797-0693 CITY OF KENT,WASHINGTON PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Barry,Jason<JBarrv@kentwa.gov> Sent: Monday,August 12, 202412:57 PM To:Connor, Eric<EConnor@kentwa.gov> Cc: Krier, Rick<RKrierekentwa.gov>; Bryant,Jason<JB ant kentwa. ov> Subject: FW: Fence Looks fair to me Eric. You good? Thanks, Jason Jason Barry, Capital Projects Supervisor Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 �- Phone 253-856-5546 1 Cell 253-797-8462 KENT jbarry@KentWA.gov W/�0-OTON www.KentWA.gov 93 PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E- MAIL From: Bryant,Jason<JBryant@kentwa.gov> Sent: Monday,August 12, 2024 12:05 PM To: Barry,Jason<JBarrv@kentwa.gov> Cc: Krier, Rick<RKrier@kentwa.gov>; Connor, Eric<EConnor@kentwa.gov> Subject: RE: Fence Jason, Attached is the quote for the fence work near LARK. Let us know if you would like to proceed? Thank you, Jason Bryant, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 2S3-856-5541 I Cell 253-261-5663 18rvant@KentWA.g-ov CITY OF KENT,WASHINGTON KentWA.gov YouTube 2 PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Hayden Larson<havden@rodarteconstruction.com> Sent: Monday,August 12,202411:49 AM To: !Crier, Rick<RKrier@kentwa.gov>; Barry,Jason<1Barry@kentwa.gov>; Bryant,Jason<J Bryant kentwa. ov> Subject: RE: Fence This message originated outside the City of Kent. Use caution when following links or opening attachments as they can be malicious. Please contact IT Security at ISP@KentlNA.cou with any questions. See attached Change order for fencing on bnsf. Thanks, Hayden Larson Rodarte Construction Inc. Cell: (253)204-9494 L11 RODARTE CONSTRUCTION INC. 17 East Valley Hwy East Auburn,WA 98092 From: Krier, Rick<RKrier@kentwa.gov> Sent:Wednesday, August 7, 2024 2:11 PM To: Hayden Larson<hayden@rodarteconstruction.com>; Barry,Jason<JBarry@kentwa.gov> Subject: Fence Hayden: any word on the fence for 1 st Ave N Thanks Get Outlook for iOS 3 Bryant, Jason From: Barry,Jason Sent: Wednesday, September 25, 2024 8:37 AM To: Hayden Larson; Bryant,Jason Cc: April Rodarte; Krier, Rick Subject: RE: 1 st Ave.fence Rev. 3 Washington Ave pump sta. Hayden, Can you please get a date confirmation from your subcontractor for installation of this fence? This work is becoming a high priority with our Department management. Please let us know as soon as possible. Thanks, Jason Jason Barry, Capital Projects Supervisor Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-SS6-SS46 I Cell 253-797-8462 K E N T rr [alKentWA.aoy W.Jk °�°" www.KentWA.aov PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E- MAIL From: Hayden Larson<hayden@rodarteconstruction.com> Sent:Tuesday,September 24,2024 1:15 PM To: Bryant,Jason<JBryant@kentwa.gov> Cc:April Rodarte<april@rodarteconstruction.com>; Barry,Jason<JBarry@kentwa.gov>; Krier, Rick <RKrier@kentwa.gov> Subject: Re: 1st Ave.fence Rev. 3 Washington Ave pump sta. { This message originated outside the City of Kent. Use caution when following links or opening 1 attachments as they can be malicious. Please contact IT Security at ISPOKentWA.gov with any questions. I have not. Thank You, Hayden Larson Rodarte Construction Inc. 253-204-9494 From: Bryant,Jason<JBrvant@kentwa.gov> Sent:Tuesday,September 24,2024 8:46:25 AM To: Hayden Larson<hayden@rodarteconstruction.com> 1 Cc.April Rodarte<april@rodarteconstruction.com>; Barry,Jason <JBarry@kentwa.gov>; Krier, Rick <R Krie r@ ken_twa_gav> Subject: RE: 1st Ave.fence Rev. 3 Washington Ave pump sta. Hayden, Have you heard back from the fence sub? Thank you, Jason Bryant, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5541 1 Cell 253-261-5663 ]Bryant@ KentWA.aov CITY OF KENT,WASHINGTON KentWA.gov Facebook _ YouTube PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Bryant,Jason Sent: Friday,September 13, 2024 7:43 AM To: Hayden Larson<hayden@rodarteconstruction.com> Cc:April Rodarte<april@rodarteconstruction.corn>; Barry,Jason<J8arry@kentwa.gov>; Krier, Rick <RKrier@kentwa.gov> Subject: FW: 1st Ave.fence Rev. 3 Washington Ave pump sta. Hayden, Have you heard back from the fence sub contractor? We would like to get this done. I recall there was a little bit of clearing that was necessary. Is the sub going to be able to take care of that as well? Thank you, Jason Bryant, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5541 1 Cell 253-261-5663 ]Bryant@KentWA.00v CITY OF KENT,WASHINGTON KentWA.gov Facebook ', -:r YouTube PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Bryant,Jason Sent: Friday, September 6, 202411:30 AM To: Hayden Larson <hayden@rodarteconstruction.com> Cc: Krier, Rick<RKrier@kentwa.gov>; Barry,Jason<J Bar ry@kentwa.eov>;April Rodarte <a ril rodarteconstruction.com> Subject: FW: 1st Ave.fence Rev. 3 Washington Ave pump sta. 2 Hayden, Have you heard back from the fence sub contractor? We would like to get this done. I recall there was a little bit of clearing that was necessary. Is the sub going to be able to take care of that as well? Thank you, Jason Bryant, capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-SSG-SS41 I Cell 253-261-5663 ]]swanL@ KentWA.aou CITY OF KENT,WASHINGTON KentWA.gov Facebook 7 i,:r..� YouTube PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Krier, Rick<RKrier@kentwa.gov> Sent: Monday,July 22, 2024 9:59 AM To: Hayden Larson<hayden@rodarteconstruction.com> Cc: Barry,Jason<1Barry@kentwa.gov>; Bryant,Jason<JBryant@kentwa.goy> Subject: 1st Ave.fence Rev. 3 Washington Ave pump sta. Hayden: Please see the attached plans for the added fence on 15Y Ave N,The City would like to add this to your existing contract work for the pump sta.This work is for install only,the city will supply the chain link fabric and posts, you would have to pick up the martials at the city's yard on the east hill. Could you please supply the city a quote and schedule as soon as possible. If you have any questions, please call. 253-350-1325 Z65WAI,i- City of Kent Sr. Inspector Capital Projects 3