HomeMy WebLinkAboutCAG2024-400 - Original - WSDOT - Local Agency Federal Aid Project Prospectus - 224th Corridor (Stage 2) - 8/23/24 FOR CITY OF KENT OFFICIAL USE ONLY
Sup/Mgr:
Agreement Routing Form DirAsst:
• For Approvals,Signatures and Records Management Dir/Dep:
KENT This form combines&replaces the Request for Mayor's Signature and Contract Cover (Optional)
WASHING-ON Sheet forms. (Print on pink or cherry colored paper)
Originator: Department:
Abdulnaser Almaroof Public Works
Date Sent: Date Required:
> 08/21/2024 08/27/2024
0
C Mayor or Designee to Sign. Date of Council Approval:
M
Q Interlocal Agreement Uploaded to Website 07/18/2023
Budget Account Number: Grant? Yes❑✓ No❑
R90110(675)
Budget?❑✓ Yes[—]NoType N/A
Vendor Name: Category:
Contract
Vendor Number: Sub-Category:
c Original
0
W Project Name: 224th Corridor Completion (Stage 2) S. 216th St. 99th Ave S. to 108th Ave S.
Project Details:
0- Project will widen 216th to 3 lanes with shoulders, curb, gutter
c sidewalks and planter strips.
-W
c
a Basis for Selection of Contractor:
Agreement Amount: 2,QQQ,000 N/A
E
+y *Memo to Mayor must be attached
i Start Date: N/A Termination Date: N/A
a�
Q Local Business?❑Yes❑No*If meets requirements per KCC3.70.100,please complete'Vendor Purchase-Local Exceptions"form on Cityspace.
Business License Verification: ❑Yes❑In-Process❑Exempt(KCC 5.01.045) ❑Authorized Signer Verified
Notice required prior to disclosure? Contract Number:
❑Yes❑No CAG2024-400
Comments:
a This prospectus is to obligate $2,000,000 of State MAWA funds.
a Cn
c is
Cn
0
3 �
ar
a,
D 8/22/24 ate Received:City Attorney; g/21/24 Date Routed:Mayor's Office City Clerk's Office $/23/24
adccW22373_1_20 Visit Documents.KentWA.gov to obtain copies of all agreements
rev.20221201
8/21/24,3:35 PM Accept Grant Funding through the Washington Department of Transportation Highways and Local Programs Office-Authorize-Cit...
City of Kent ,U, Approved
Washington 18 Z��3j"OOPM
KEMT Action Item
"'`°"'" 3612
Accept Grant Funding through the Washington Department of Transportation Highways
and Local Programs Office - Authorize
Information
Department: Public Works Department Sponsors:
Category: Grant/Donation
Attachments
Printout
Kent TPB v23 MMoM Multimodal
Kent vE23 LEGE MAW 224th Corridor Award Letter
2023 Freight Mobility Letter Kent - 76th Ave S (South Phase)
WSDOT Meeker Street - Kent Elementary Separated Bikeway
2023 Ped Bike Safety Letter Kent SR99
2023 Connecting Communities State Letter Kent
2023 SRTS Federal Funding Letter Kent
Budget Impact
BUDGET IMPACT:
Meet Me on Meeker Multimodal Improvements: No new impacts, prior Council allocation of
$500,000 will be used for grant match.
224th Corridor Completion: Local matching funds of $5,600,000 and prior grant awards were
previously allocated by Council.
76th Avenue S (South Phase): Local funds of $9,980,000 and prior grant awards were
previously allocated by Council.
Meeker Street - Kent Elementary Separated Bikeway: Local match funds of $24,000 and
prior grant awards were previously allocated by Council.
SR 99 Pedestrian Hybrid Beacon: Estimated $62,000 match is proposed from the Street Fund.
Willis Street Road Diet: Estimated $307,000 match is proposed from the Street Fund.
Meeker Street and 64th Ave S Improvements: Estimated $326,000 in local match proposed
from Street Fund, along with prior grant award and local match of $36,000 from B&O funds.
Motion
MOTION: I move to authorize the Mayor to accept grant funding through the
Washington State Department of Transportation Highways and Local Programs Office
in the amount of $40,469,000, amend the budget, authorize expenditure of grant funds
https:Hkentwa.igm2.com/Citizens/Detail_LegiFile.aspx?Meeting ID=5125&MediaPosition=&ID=3612&CssClass=&Print=Yes 1/5
8/21/24, 3:35 PM Accept Grant Funding through the Washington Department of Transportation Highways and Local Programs Office-Authorize-Cit...
and matching funds to complete the projects and authorize the Mayor to sign all
necessary documents subject to final terms and conditions acceptable to the City
Attorney and Public Works Director.
Summary
SUMMARY: Each year, the City is eligible to apply for multiple grant opportunities. Each grant
has specific eligibility requirements and evaluation criteria to award funding, often including prior
adoption in the City's Transportation Master Plan (TMP) and six-year Transportation Improvement
Program (TIP). At the beginning of each grant cycle, staff present potential projects or programs
to Council for grant requests. The following notices of award are from 2022 requests to the State
Legislature as noted below:
Move Ahead Washington Transportation Budget for Meet Me on Meeker Multimodal
Improvements, in the amount of $10,000,000.
In 2023, the Washington State Legislature approved Move Ahead Washington, providing
transportation funding over a 16-year period starting July 1, 2023. The Move Ahead Washington
funding supports new transportation projects and programs statewide. Legislators worked with
constituents to identify projects that meet communities goals. Inclusion of the Meet Me on
Meeker project reflects the Legislature's commitment to advancing multimodal transportation in
Kent.
The project will add a two-way bike facility on West Meeker Street, and enhanced pedestrian
crossing facilities between Kent Elementary and the Interurban Trail. The project will be built to
the Meet Me on Meeker Street design standards adopted by Council in 2016. The improvements
will support the link between neighborhoods and downtown Kent, providing transportation users
of all modes with pedestrian crossing facilities, lighting, and separated bicycle facilities.
Construction is expected to start in 2024.
Move Ahead Washington Transportation Budget for the 224t" Corridor Completion, in
the amount of $20,600,000.
The project will complete widening of S 218th and S 216th Streets from 94th Place S to 108th
Avenue SE (SR 515/13enson Highway), including a new two-way left turn lane, planted pedestrian
buffers, sidewalks, street lighting and underground utilities. The improvements will support the
link between neighborhoods and the valley for users of all modes.
The overall project estimate is $26,200,000, with match coming from the Street Fund, Traffic
Impact Fees, and Local Improvement District #363.
State Transportation Budget for the 76t" Avenue S (South Phase), in the amount of
$5,000,000.
The project will construct drainage and road improvements on 76th Avenue S from S 220th
Street to S 223rd Street. The roadway will be raised above the FEMA base flood elevation with a
full width concrete roadway; undersized culverts will be replaced with three bridges, one on 76th
Avenue S and two for access to existing businesses; Mill Creek will be widened and improved
with new habitat measures; new storm and water systems, planter strips, sidewalks, street
lighting and street channelization.
The overall project estimate is $17,980,000, including a local contribution of 56% ($9,980,000),
with construction anticipated to begin in winter 2023/2024. Council previously approved required
match funds from the B&O, Drainage Utility and Street funds.
https:Hkentwa.igm2.com/Citizens/Detail_LegiFile.aspx?Meeting ID=5125&MediaPosition=&ID=3612&CssClass=&Print=Yes 2/5
8/21/24,3:35 PM Accept Grant Funding through the Washington Department of Transportation Highways and Local Programs Office-Authorize-Cit...
Pedestrian & Bicycle Safety Program Budget for the Meeker Street - Kent Elementary
Separated Bikeway, in the amount of $1,807,000.
In 2022, the City applied for grant funding from the Washington State Department of
Transportation (WSDOT) Pedestrian & Bicycle Safety Program to construct a separated bikeway
along the frontage of Kent Elementary School. The project award for Kent is one of 28 awarded
across the state for the 2023-25 biennium.
The project will add a new, two-way separated bike facility on the south side of the street along
with other Meet Me on Meeker street standards from 64th Avenue S to 750 feet east of 64th
Avenue S. The project will narrow the roadway to three lanes and include construction of raised
median islands, buffer between the two-way bike path and travel lanes, street lighting,
landscaping, and pedestrian amenities. The improvements will support the link between
neighborhoods and downtown Kent, and promote active transportation use for people of all ages
and abilities.
The overall project estimate is $2,610,000, including a local contribution of 310/0 ($803,000),
with design underway this fall. Council previously approved required match funds from the B&O
and Street funds.
Pedestrian & Bicycle Safety Program grant for the SR 99 Pedestrian Hybrid Beacon at
24800 to 25000 Block, in the amount of $559,000.
The City applied for grant funding from the Washington State Department of Transportation
(WSDOT) Pedestrian & Bicycle Safety Program in 2022 to design and construct a Pedestrian
Hybrid Beacon (PHB) at the 24800 to 25000 block of SR 99, or Pacific Highway South. The
project award for Kent is one of 28 awarded across the state for the 2023-25 biennium. The
project will add a PHB-enhanced crosswalk and associated lighting and signage. The
improvements will support local commercial and pedestrian activity.
The total project cost estimate is $621,000, including a local contribution of 10% ($62,000), with
design to begin in 2023. Staff proposes to allocate match funds from the Street Fund.
Connecting Communities Pilot Program grant - Willis Street Road Diet, in the amount of
$623,000.
This project was nominated by a working group from the Washington State Department of
Transportation (WSDOT) and Puget Sound Regional Council (PSRC) for a new pilot program,
authorized by the Washington State Legislature, that is focused on connecting communities
across state highways. The project was previously submitted to WSDOT as part of a Highway
Safety Improvement Program (HSIP) grant application. The project award for Kent is one of five
awarded to cities across the state as part of the pilot program for the 2023-25 biennium.
The project will add an RRFB-enhanced crosswalk at 2nd Avenue and reconfigure the roadway
from 2nd Avenue to Central Avenue by narrowing the roadway to one, westbound lane. The
improvements will support local commercial and pedestrian activity, and implement a top project
identified in the 2022 Local Road Safety Plan.
The total project cost estimate is $990,000, including an estimated local contribution of 310/0
($307,000), with design to begin in 2023. Staff proposes to allocate match funds from the Street
Fund.
Safe Routes to School Program Funding for the Meeker Street and 64th Ave S Transit &
Non-Motorized Intersection Improvements grant in the amount of $1,880,000.
https:Hkentwa.igm2.com/Citizens/Detail_LegiFile.aspx?Meeting ID=5125&MediaPosition=&ID=3612&CssClass=&Print=Yes 3/5
8/21/24,3:35 PM Accept Grant Funding through the Washington Department of Transportation Highways and Local Programs Office-Authorize-Cit...
In 2022 the City applied for grant funding from the Washington State Department of
Transportation (WSDOT) Safe Routes to Schools Program to construct transit and non-motorized
improvements at the W Meeker Street and 64th Ave S intersection, which serves as the principal
access point for Kent Elementary School for all students and employees by bus, walking, biking,
rolling, or by private car.
The project will reconstruct the intersection, adding curb and bus bulb-outs to decrease the
pedestrian crossing distance. The project includes bus stop improvements on the north and south
side of W Meeker Street east of 64th Avenue S, and signal improvements including transit signal
priority. The project will be built to the Meet Me on Meeker Street design standards.
The overall project is estimated to cost $2,464,000, including a local contribution of 24%
($584,000), with design already under way, enabled by a prior grant award. Council previously
approved required match funds from the B&O fund. Staff proposes to budget and appropriate the
local match for the construction portion of the project from the Street Fund.
Meeting History
Jun 20, 2023 4.00 PM Video Committee of Committee of the Whole - Regular
the Whole Meeting
Paine provided details on the Transportation Grant Awards as follows:
Each year, the City is eligible to apply for multiple grant opportunities. Each grant has specific eligibility requirements and evaluation
criteria to award funding, often including prior adoption in the City's Transportation Master Plan (TMP) and six-year Transportation
Improvement Program (TIP). At the beginning of each grant cycle, staff present potential projects or programs to Council for grant
requests. The following notices of award are from 2022 requests to the State Legislature as noted below:
Move Ahead Washington Transportation Budget for Meet Me on Meeker Multimodal Improvements, in the amount of$10,000,000.
Move Ahead Washington Transportation Budget for the 224th Corridor Completion, in the amount of$20,600,000.
State Transportation Budget for the 76th Avenue S (South Phase), in the amount of$5,000,000.
Pedestrian & Bicycle Safety Program Budget for the Meeker Street - Kent Elementary Separated Bikeway, in the amount of
$1,807,000.
Pedestrian & Bicycle Safety Program grant for the SR 99 Pedestrian Hybrid Beacon at 24800 to 25000 Block, in the amount of
$559,000.
Connecting Communities Pilot Program grant- Willis Street Road Diet, in the amount of$623,000.
Safe Routes to School Program Funding for the Meeker Street and 64th Ave S Transit & Non-Motorized Intersection Improvements
grant in the amount of$1,880,000.
RESULT: MOTION PASSES [UNANIMOUS]
MOVER: Brenda Fincher, Councilmember
SECONDER: Satwinder Kaur, Councilmember
AYES: Bill Boyce, Brenda Fincher, Satwinder Kaur, Marli Larimer, Les Thomas, Toni Troutner
Jul 18, 2023 7:00 PM Video City Council City Council Regular Meeting
Meeting
RESULT: APPROVED [UNANIMOUS]
MOVER: Bill Boyce, Council President
SECONDER: Les Thomas, Councilmember
AYES: Bill Boyce, Brenda Fincher, Satwinder Kaur, Marli Larimer, Toni Troutner, Les Thomas, Zandria Michaud
Discussion
https:Hkentwa.igm2.com/Citizens/Detail_LegiFile.aspx?Meeting ID=5125&MediaPosition=&ID=3612&CssClass=&Print=Yes 4/5
8/21/24,3:35 PM Accept Grant Funding through the Washington Department of Transportation Highways and Local Programs Office-Authorize-Cit...
Add Comment
Powered by Granicus
https:Hkentwa.igm2.com/Citizens/Detail_LegiFile.aspx?Meeting ID=5125&MediaPosition=&ID=3612&CssClass=&Print=Yes 5/5
AM
Washington State Local Agency Federal Aid
Department of Transportation
Project Prospectus
Prefix Route ( ) Date 8/15/2024
Federal Aid DUNS Number 020253613
Project Number
Local Agency 22-3010 r WSDOT 1 Federal Employer 91-6001254
Project Number ` Use Only J Tax ID Number
Agency CAAgency Federal Program Title
City of Kent 0✓ Yes ❑No ❑20.205 ❑Other State
Project Title Start Latitude N47.408691 Start Longitude W-122.208684
224th Corridor Completion(Stage 2) - S 216th Str End Latitude N47.408211 End Lon itude W-122.197139
Project Termini From-To Nearest City Name Project Zip Code(+4)
99th Ave S 108th Ave S Kent,WA 98032-5895
Begin Mile Post End Mile Post Length of Project Award Type
N/A N/A 2900 feet ❑Local❑Local Forces❑✓ State❑Railroad
Route ID Begin Mile Point End Mile Point City Number County Number County Name
1244 N/A N/A 0615 17 King
WSDOT Region Legislative District(s) Congressional District(s) Urban Area Number
Northwest Region 47th 8th 80389
Total Local Agency Phase Start
Phase Estimated Cost Funding Federal Funds Date
Nearest Hundred Dollar Nearest Hundred Dollar Nearest Hundred Dollar Month Year
P.E. 2000000 2000000 8 2024
R/W 2000000 2000000 9 2024
Const. 10000000 10000000 10 2025
Total 14000000 14000000
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width Number of Lanes
22 2
Currently a two lane roadway with limited sidewalks.
Description of Proposed Work
Description of Proposed Work(Attach additional sheet(s)if necessary)
Complete widening of S 218th and S 216th Streets from the Kent Valley to SR 515
(Benson Hwy)to meet modern standards,including a new two-way left-turn lane,
planted pedestrian buffers, sidewalks, street lighting and underground utilities.
Local Agency Contact Person Title Phone
Mark Madfai Design Engineering Supervisor 253-856-5521
Mailing Address City State ��ZipCode
220 4th Ave. S Kent WA 98032
By �K -
Project Prospectus Approving Authority
Title Public Works Director Date 61)11/.7
DOT Form 140-101 Pagel
Revised 01/2022 Previous Editions Obsolete
�Agency Project Title Date
Kent 224th Corridor Completion(Stage 2) - S 216 8/15/2024
Type of Proposed Work
Project Type(Check all that Apply) Roadway Width Number of Lanes
❑New Construction ❑ Path/Trail ❑3-R 40 3
[VI Reconstruction ❑Pedestrian / Facilities ❑2-R
❑Railroad ❑Parking ❑Other
❑Bridge
Geometric Design Data
Description Through Route Crossroad
❑ Principal Arterial ❑ Principal Arterial
Federal ❑ Minor Arterial ❑✓ Urban ❑ Minor Arterial
❑✓ Urban El Collector ❑Collector
Functional ❑ Rural ❑Rural
Classification ❑ NHS ❑✓ Major Collector ❑NHS ❑ Major Collector
❑ Minor Collector ❑✓ Minor Collector
❑ Local Access ❑ Local Access
Terrain ❑ Flat ❑Roll ❑ Mountain ❑ Flat ❑ Roll ❑ Mountain
Posted Speed 25 mph 25 mph
Design Speed 25 mph
Existing ADT 4500
Design Year ADT
Design Year
Design Hourly Volume (DHV)
Performance of Work
Preliminary Engineering Will Be Performed By Others Agency
City of Kent % 100 ova
Construction Will Be Performed By Contract Agency
Contractor 100 % %
Environmental Classification
❑Class I - Environmental Impact Statement (EIS) ❑Class II - Categorically Excluded (CE)
❑ Project Involves NEPA/SEPA Section 404 ❑Projects Requiring Documentation
Interagency Agreement (Documented CE)
❑Class III - Environmental Assessment (EA)
❑Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
No major environmental impacts anticipated. Work will be in accordance with terms and conditions of SEPA.
DOT Form 140-101 Page 2
Revised 01/2022 Previous Editions Obsolete
Agency Project Title Date
City of Kent 224th Corridor Completion (Stage 2) - S 216 1/11/2024
Right of Way
❑ No Right of Way Needed ❑✓ Right of Way Needed
*All construction required by the ❑✓ No Relocation ❑ Relocation Required
contract can be accomplished
within the existing right of way.
Utilities Railroad
❑ No utility work required [✓ No railroad work required
❑✓ All utility work will be completed prior to the start ❑All railroad work will be completed prior to the start of
of the construction contract the construction contract
❑All utility work will be completed in coordination ❑All the railroad work will be completed in coordination
with the construction contract with the construction contract
Description of Utility Relocation orAdjustments and Existing Major Structures Involved in the Project
Existing overhead power and communication lines will be undergrounded in advance of the project.
FAA Involvement
Is any airport located within 3.2 kilometers (2 miles)of the proposed project? ❑Yes [4 No
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it's
designee, and is not inconsistent with the agency's comprehensive plan for community development.
By
Date 08/23/2024 May it/Chair Orson
DOT Form 140-101 Page 3