HomeMy WebLinkAboutCAG2024-145 - Change Order - #1 - 2J Remodel Solutions, LLC - Fire Station 74 Remodel - 06/04/2024 FOR CITY OF KENT OFFICIAL USE ONLY Sup/Mgr: kWZ,
kmz
Agreement Routing Form Dir. Assist: K
• For Approvals,Signatures and Records Management
KE N T This form combines&replaces the Request for Mayor's Signature and Contract Cover
WASHINcroN Sheet forms. Dir/Dep Dir: BI
Originator: Department:
Leah Bryant for Kris Zorer Parks, Recreation & Community Services
Date Sent: Date Required:
> 06/03/2024 6/6/2024
0
CL Authorized to Sign: Date of Council Approval:
QDirector or Designee NA
Budget Account Number: G ra n t?1:1 Ye s F71No
F20105. 64190. 9422
Budget?W]YesF—]No Type: N/A
Vendor Name: Category:
2J REMODEL SOLUTIONS LLC Contract
Vendor Number: Sub-Category:
= 2546558 Change Order
0 e Order 1 FAC24- 6 Station 74 Office Remodel - Chan
Project Name: g
3- Project Details:Repair walls as needed. (scrape, mud,tape,texture)Prime mud spots and roll walls 2 coats. Floor and
0 ceiling will be masked off as needed for overspray of texture and paint.
C
*, Tax increased from 10.1%to 10.2%on April 1,2024. Additional$13.00 included for the tax increase
C
40
40 Agreement Amount: $1 831 .30 Basis for Selection of Contractor: Other
47 `Memo to Mayor must be attached
3- Start Date: 3/21/2024 Termination Date: 6/30/2024
Im
Q Local Business?F--]YeslzNo* If meets requirements per KCC3.70.100,please complete"Vendor Purchase-Local Exceptions'form on Cityspace.
Business License Verification:Yes In-Process Exempt(KCC 5.01.045)
Notice required prior to disclosure? Contract Number:
FTesQNo CAG2024-145
Comments:
cp Change Order 1
C
a)
H
•� i
N 3
f0
C
V1
Date Routed to the City Clerk's Office: 6/4/24
,c«w»373__,0 Visit Documents.KentWA.gov to obtain copies of all agreements
rev.20210513
•
KEN T
WASHINGTON
CHANGE ORDER NO. #1
NAME OF CONTRACTOR: 2J Remodel Solutions, LLC ("Contractor")
CONTRACT NAME & PROJECT NUMBER: FAC24-6 Station 74 Office Remodel
ORIGINAL CONTRACT DATE: 3/21/2024
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Repair walls as needed. (scrape, mud, tape, texture) Prime mud spots
and roll walls 2 coats. Floor and ceiling will be masked off as needed for
overspray of texture and paint.
Tax increased from 10.1% to 10.2% on April 1, 2024. Additional $13.00
included for the tax increase
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $14,313.00
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $0
(incl. applicable WSST)
Current Contract Amount $14,313.00
(incl. Previous Change Orders)
Current Change Order $1650.00
Applicable WSST Tax on this Change $168.30 + $13.00 (increase)
Order
Revised Contract Sum $16,144.30
CHANGE ORDER - 1 OF 3
Original Time for Completion 5/31/2024
(insert date)
Revised Time for Completion under NA
prior Change Orders
(insert date)
Days Required (f) for this Change Order 30 calendar days
Revised Time for Completion 06/30/2024
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
MW Brims L.eve eIt�
B /:Jayme Selivano (Jun 3,202416:13 PDT) By:Brian Levenhagen(Jun 4,2024 8:53 PDT)
Print Name:Jayme Selivanoff Print Name: Brian Levenhagen
Its Owner Its: Deputy Parks Director
DATE: J u n 3,2024 DATE: Jun 4, 2024
CHANGE ORDER - 2 OF 3
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent City Clerk Kent Law Department
[In this field,you may enter the electronic filepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
Exhibit A
Station 74 Wall Project December 3, 2023
Jaron Mitchell /Jayme Selivanoff Estimate
2J Remodel Solutions, LLC
Mobile 2532045693
2jremodel@gmail.com
License #: 2JREMRS798KO
Project
Station 74 Wall Project
24523 116th Ave SE
kent, WA 98030
Description Cost
Summary 13,000.00
Demo:Cut hallway wall for new door install.Cut out any flooring,trim and sheetrock for new wall install.Associated disposal fees included in this cost.
Construction:Move or eliminate outlets as needed to accomodate new wall location.New electrical switch locations will be installed as needed for both
sides of room.Frame out wall with metal framing and bottom plate attached to the concrete slab.Doorway will be framed as needed for new door.
Customer supplied door will be installed.Sheetrock will be installed to the framed wall.The wall will go up to the ceiling grid but not attached.Wall will
be mud/taped,sanded,textured,primed and painted to match existing walls.New trim will be installed as needed.All materials(Except the new door)
needed to complete this job are included in this cost.
`All work will be paid proper prevailing wage.
'Contractor will pull proper permits as needed for this project.
Change Orders
Summary 1,650.00
Repair walls as needed.(scrape,mud,tape,texture)
Prime mud spots and roll walls 2 coats.
Floor and ceiling will be masked off as needed for overspray of texture and paint.
Materials included in this cost.
Project Total 14,650.00
Tax 1,479.65
Total with Tax 16,129.65
We appreciate your business and look forward to working with you. 10.2%TAX $1,494.30
Total with Tax $16,144.30
2J Remodel Solutions, LLC, License#: 2JREMRS798KO 1
[2J REMODEL SOLUTIONS]
CHANGE ORDER CONTRACT
Project Name: Station 74 Wall Project
Location: 24523 116th Ave SE kent,WA 98030
Date: 6/2/24
Change Order#: 1
Proposed Changes: Repair existing office walls as needed. (scrape, mud, tape, texture) Prime
mud spots and roll walls 2 coats. Floor, ceiling, and surrounding cabinetry will be masked off as
needed for oversprU of texture and paint. Materials included in this cost.
Timeframe For Changes &Effect On Overall Schedule: 1 Day
Estimated Price Of Changes: $ 1,650+Tax
Original Contract Price: $ 14,313.00
New Contract Price If Current Change Order Approved: $ 16,129.65
This Change Order is:
[ ] Approved[ ] Not Approved
Signed:
Date: Date: 6/2/24
2J Remodel Solutions
Customer Name Contractor Name
Signature: 0-1,ItDyhel-ZOI-er Signature:
Kristopher Zor r(Jun 3,202413:54 PDT) Kent Parks(Jun 3,202417:00 PDT)
Email: kzorer@kentwa.gov Email: parkscontracts@kentwa.gov
Signature: "Oli5S41 NOCOrmlGK
Melissa McCormick(Jun 4,202410:42 PDT)
Email: cityclerk@kentwa.gov
06032024-2J Remodel Solutions-St 74 Remodel
- Change Order 1
Final Audit Report 2024-06-04
Created: 2024-06-03
By: Leah Bryant(Ibryant@kentwa.gov)
Status: Signed
Transaction ID: CBJCHBCAABAAzokKnAnQTmGyimOJWwPyEkEVPOIawFZc
"06032024-2J Remodel Solutions-St 74 Remodel - Change Ord
er 1 " History
Document created by Leah Bryant(Ibryant@kentwa.gov)
2024-06-03-6:59:20 PM GMT
Document emailed to kzorer@kentwa.gov for signature
2024-06-03-7:02:48 PM GMT
Email viewed by kzorer@kentwa.gov
2024-06-03-8:53:21 PM GMT
dp Signer kzorer@kentwa.gov entered name at signing as Kristopher Zorer
2024-06-03-8:54:41 PM GMT
dp Document e-signed by Kristopher Zorer(kzorer@kentwa.gov)
Signature Date:2024-06-03-8:54:43 PM GMT-Time Source:server
Document emailed to 2jremodel@gmail.com for signature
2024-06-03-8:54:44 PM GMT
Email viewed by 2jremodel@gmail.com
2024-06-03-11:11:51 PM GMT
d4 Signer 2jremodel@gmail.com entered name at signing as Jayme Selivanoff
2024-06-03-11:13:41 PM GMT
�p Document e-signed by Jayme Selivanoff(2jremodel@gmail.com)
Signature Date:2024-06-03-11:13:43 PM GMT-Time Source:server
Document emailed to Kent Parks (parkscontracts@kentwa.gov) for signature
2024-06-03-11:13:44 PM GMT
Powered by
Adobe
�� KENT Acrobat Sign
Email viewed by Kent Parks (parkscontracts@kentwa.gov)
2024-06-03-11:21:58 PM GMT
d4 Document e-signed by Kent Parks (parkscontracts@kentwa.gov)
Signature Date:2024-06-04-0:00:15 AM GMT-Time Source:server
Document emailed to bjlevenhagen@kentwa.gov for signature
2024-06-04-0:00:16 AM GMT
Email viewed by bjlevenhagen@kentwa.gov
2024-06-04-3:52:44 PM GMT
d Signer bjlevenhagen@kentwa.gov entered name at signing as Brian Levenhagen
2024-06-04-3:53:13 PM GMT
da Document e-signed by Brian Levenhagen (bjlevenhagen@kentwa.gov)
Signature Date:2024-06-04-3:53:15 PM GMT-Time Source:server
Document emailed to Kim Komoto (kkomoto@kentwa.gov)for signature
2024-06-04-3:53:17 PM GMT
Email viewed by Kim Komoto (kkomoto@kentwa.gov)
2024-06-04-5:17:09 PM GMT
Document e-signed by Kim Komoto (kkomoto@kentwa.gov)
Signature Date:2024-06-04-5:17:20 PM GMT-Time Source:server
Document emailed to cityclerk@kentwa.gov for signature
2024-06-04-5:17:22 PM GMT
Email viewed by cityclerk@kentwa.gov
2024-06-04-5:26:29 PM GMT
da Signer cityclerk@kentwa.gov entered name at signing as Melissa McCormick
2024-06-04-5:42:36 PM GMT
Document e-signed by Melissa McCormick (cityclerk@kentwa.gov)
Signature Date:2024-06-04-5:42:38 PM GMT-Time Source:server
Agreement completed.
2024-06-04-5:42:38 PM GMT
Powered by
Adobe
�� KENT Acrobat Sign