HomeMy WebLinkAboutCAG2024-139 - Change Order - #1 - Bayley Construction LP - FAC23-09C KEHOC Warehouse & Office Building - 05/06/2024 FOR CITY OF KENT OFFICIAL USE ONLY Sup/Mgr: WM
Agreement Routing Form Dir. Assist:
• For Approvals,Signatures and Records Management
KENT This form combines&replaces the Request for Mayor's Signature and Contract Cover
WASHINGTON Sheet forms. Dir/Dep Dir:
Originator: Department:
Leah Bryant for Nate Harper Parks, Recreation & Community Services
Date Sent: Date Required:
> 05/02/2024 5/10/2024
0
Q Authorized to Sign: Date of Council Approval:
QQDirector or Designee 3/5/2024
Budget Account Number: Grant? Yes❑✓ No
F20098.64110.9476
Budget?w]YesEl No Type: N/A
Vendor Name: Category:
Bayley Construction LP Contract
Vendor Number: Sub-Category:
2548901 Change Order
FAC23-09C KEHOC Warehouse and & Office Building
Project Name: g
oProject Details:City of Kent tax rate increased from 10.1% to 10.2%, a .1% increase
c equaling $25,857.40 on the current balance of the contract
c
a
Agreement Amount: 25 857.40 Basis for Selection of Contractor: Bid
(D *Memo to Mayor must be attached
3- Start Date: March 2024 Termination Date: 7/31/2026
CA
Q Local Business?F—]Yes7No* If meets requirements per KCC3.70.700,pleosecomplete"VendorPurchase-Locol Exceptions"form onCityspoce.
Business License Verification:YesElln-ProcessElExempt(KCC 5.01.045)
Notice required prior to disclosure? Contract Number:
F—]YesONo CAG2024-139
Comments:
p1
C
n
30
a,
N
•� i
� 3
� a+
fC
C
t/f
Date Routed to the City Clerk's Office: 5/6/24
adccW22313_1_20 Visit Documents.KentWA.gov to obtain copies of all agreements
rev.20210513
•
KEN T
WASHINGTON
CHANGE ORDER NO. #1
NAME OF CONTRACTOR: Bayley Construction LP ("Contractor")
CONTRACT NAME & PROJECT NUMBER: FAC2309-C-KEHOC Warehouse and Office
ORIGINAL CONTRACT DATE: FInsert Date Original Contract was Signed]
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
City of Kent tax rate increased from 10.1% to 10.2%, a .1% increase
equaling $25,857.40 on the current balance of the contract
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $29,900,294.10
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $0
(incl. applicable WSST)
Current Contract Amount $29,900,294.10
(incl. Previous Change Orders)
Current Change Order $0
Applicable WSST Tax on this Change $25,857.40
Order
Revised Contract Sum $29,926,151.50
CHANGE ORDER - 1 OF 3
Original Time for Completion 7/31/2026
(insert date)
Revised Time for Completion under NA
prior Change Orders
(insert date)
Days Required (f) for this Change Order 0 calendar days
Revised Time for Completion 7/31/2026
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
St��Gce�z G��
By:StephO Grasso(May 3,202411:06 PDT) By:Juli arascondola(May 6,202411:46 PDT)
Print Name: Stephen Grasso Print Name: Julie Parascondola
Its CEO Its: Parks Director
DATE: May 3, 2024 DATE: May 6,2024
CHANGE ORDER - 2 OF 3
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent City Clerk Kent Law Department
[In this field,you may enter the electronic filepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
Signature• NX MDDYG Signature• Melissa MGCOi'MiOl�
Will Moore(May 3,2024 07:06 PDT) Melissa McCormick(May 6,202414:35 PDT)
Email: wmoore@kentwa.gov Email: cityclerk@kentwa.gov
FAC23-09C-KEHOC Warehouse and & Office
Building - CO 1
Final Audit Report 2024-05-06
Created: 2024-05-02
By: Leah Bryant(Ibryant@kentwa.gov)
Status: Signed
Transaction ID: CBJCHBCAABAAHuQGZewJe_phtLXjUOCrRxWdVbSA6UAf
"FAC23-09C-KEHOC Warehouse and & Office Building - CO 1 "
History
Document created by Leah Bryant(Ibryant@kentwa.gov)
2024-05-02-11:06:23 PM GMT
Document emailed to wmoore@kentwa.gov for signature
2024-05-02-11:08:15 PM GMT
Email viewed by wmoore@kentwa.gov
2024-05-03-2:04:13 PM GMT
dp Signer wmoore@kentwa.gov entered name at signing as Will Moore
2024-05-03-2:06:28 PM GMT
dp Document e-signed by Will Moore (wmoore@kentwa.gov)
Signature Date:2024-05-03-2:06:30 PM GMT-Time Source:server
Document emailed to steveg@bayley.net for signature
2024-05-03-2:06:32 PM GMT
Email viewed by steveg@bayley.net
2024-05-03-2:13:09 PM GMT
d4 Signer steveg@bayley.net entered name at signing as Stephen Grasso
2024-05-03-6:06:51 PM GMT
�p Document e-signed by Stephen Grasso (steveg@bayley.net)
Signature Date:2024-05-03-6:06:53 PM GMT-Time Source:server
Document emailed to Julie Parascondola Qparascondola@kentwa.gov) for signature
2024-05-03-6:06:55 PM GMT
Powered by
Adobe
�� KENT Acrobat Sign
Email viewed by Julie Parascondola Oparascondola@kentwa.gov)
2024-05-06-6:46:40 PM GMT
dp Document e-signed by Julie Parascondola Qparascondola@kentwa.gov)
Signature Date:2024-05-06-6:46:56 PM GMT-Time Source:server
C'► Document emailed to Kim Komoto (kkomoto@kentwa.gov)for signature
2024-05-06-6:46:57 PM GMT
Email viewed by Kim Komoto (kkomoto@kentwa.gov)
2024-05-06-7:48:03 PM GMT
dg Document e-signed by Kim Komoto (kkomoto@kentwa.gov)
Signature Date:2024-05-06-7:48:11 PM GMT-Time Source:server
Document emailed to cityclerk@kentwa.gov for signature
2024-05-06-7:48:13 PM GMT
Email viewed by cityclerk@kentwa.gov
2024-05-06-9:34:50 PM GMT
Signer cityclerk@kentwa.gov entered name at signing as Melissa McCormick
2024-05-06-9:35:13 PM GMT
Document e-signed by Melissa McCormick (cityclerk@kentwa.gov)
Signature Date:2024-05-06-9:35:15 PM GMT-Time Source:server
Agreement completed.
2024-05-06-9:35:15 PM GMT