HomeMy WebLinkAboutCAG2023-595 - Change Order - #4 - Larson Berger Companies Construction, LLC - FAC23-27 City of Kent Courtroom Refurbishment - 04/24/2024 FOR CITY OF KENT OFFICIAL USE ONLY Sup/Mgr: NL
NH
Agreement Routing Form
• For Approvals,Signatures and Records Management
KE N T This form combines&replaces the Request for Mayor's Signature and Contract Cover
WASHINGTON Sheet forms.
Originator: Department:
Leah Bryant for Nate Harper Parks, Recreation & Community Services
Date Sent: Date Required:
> 04/23/2024 4/30/2024
0
CL Authorized to Sign: Date of Council Approval:
Q Director or Designee 11/7/2023
Budget Account Number: Grant? Yes WINo
F00056.64110.9412
Budget?w]YesEl No Type: N/A
Vendor Name: Category:
Larson Berger Companies-Construction,LLC,DBA LBC Contract
Construction
Vendor Number: Sub-Category:
= 2536711 Change Order
R0 Cit of Kent Courtroom Refurbishment FAC23-27
Project Name: y
cProject Details:City of Kent tax rate increased from 10.1% to 10.2%, a .1% increase
= equaling $430.91 on the current balance of the contract.
c
40
40 Agreement Amount: 430.9 1 Basis for Selection of Contractor: Bid
`Memo to Mayor must be attached
Start Date: November 2023 Termination Date: 8/31/2024
Im
Q Local Business?F--]YeslzNo* If meets requirements per KCC3.70.100,please complete"Vendor Purchase-Local Exceptions'form on Cityspace.
Business License Verification:YesEl In-ProcessEl Exempt(KCC 5.01.045)
Notice required prior to disclosure? Contract Number:
FTesONo CAG2023-595
Comments:
a1
G
3
N �
H
•� i
N 3
f0
C
V1
Date Routed to the City Clerk's Office: 4/25/24
,c«w»373__,0 Visit Documents.KentWA.gov to obtain copies of all agreements
rev.20210513
•
KEN T
WASHINGTON
CHANGE ORDER NO. 4
NAME OF CONTRACTOR:Larson Berger Companies - Construction, LLC, DBA LBC Construction
("Contractor")
CONTRACT NAME & PROJECT NUMBER: City of Kent Courtroom Refurbishment FAC23-27
ORIGINAL CONTRACT DATE: 11/28/2023
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
City of Kent tax rate increased from 10.1% to 10.2%, a .1% increase equaling $430.91 on the
current balance of the contract.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $678,216.00
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $61,825.04
(incl. applicable WSST)
Current Contract Amount $740,041.04
(incl. Previous Change Orders)
Current Change Order $0
Applicable WSST Tax on this Change $430.91
Order
Revised Contract Sum $740,471.95
CHANGE ORDER - 1 OF 3
Original Time for Completion 8/31/2024
(insert date)
Revised Time for Completion under NA
prior Change Orders
(insert date)
Days Required (f) for this Change Order 0 calendar days
Revised Time for Completion 8/31/2024
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
By: By:Brian Levenhagen(Apr 24,202 12:54 PDT)
Print Name: Nathan Larson Print Name: Brian Levenhagen
Its Vice President Its: Deputy Parks Director
DATE: Apr 24,2024 DATE: Apr 24,2024
CHANGE ORDER - 2 OF 3
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent City Clerk Kent Law Department
[In this field,you may enter the electronic filepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
Signature: NATfEN C t A?PER Signature: Melissa MGCOi'MiOl�
NATHEN C HARPER(Apr 24,202407:02 PDT) Melissa McCormick(Apr 25,202408:38 PDT)
Email: nharper@kentwa.gov Email: cityclerk@kentwa.gov
FAC23-27-Courtroom Renovation -LBC C04
Final Audit Report 2024-04-25
Created: 2024-04-23
By: Leah Bryant(Ibryant@kentwa.gov)
Status: Signed
Transaction ID: CBJCHBCAABAAuYiOicyMecyvg_oYxXT7SbTcZcKg4CTE
"FAC23-27-Courtroom Renovation -LBC C04" History
Document created by Leah Bryant(Ibryant@kentwa.gov)
2024-04-23-10:32:51 PM GMT
Document emailed to nharper@kentwa.gov for signature
2024-04-23-10:37:44 PM GMT
Email viewed by nharper@kentwa.gov
2024-04-24-2:01:23 PM GMT
dp Signer nharper@kentwa.gov entered name at signing as NATHEN C HARPER
2024-04-24-2:02:55 PM GMT
�p Document e-signed by NATHEN C HARPER(nharper@kentwa.gov)
Signature Date:2024-04-24-2:02:57 PM GMT-Time Source:server
Document emailed to Nathan Larson (nathan@larsonbergercc.com)for signature
2024-04-24-2:02:59 PM GMT
Email viewed by Nathan Larson (nathan@larsonbergercc.com)
2024-04-24-2:35:48 PM GMT
d4 Document e-signed by Nathan Larson (nathan@larsonbergercc.com)
Signature Date:2024-04-24-2:38:11 PM GMT-Time Source:server
Document emailed to bjlevenhagen@kentwa.gov for signature
2024-04-24-2:38:13 PM GMT
Email viewed by bjlevenhagen@kentwa.gov
2024-04-24-7:54:26 PM GMT
Signer bjlevenhagen@kentwa.gov entered name at signing as Brian Levenhagen
2024-04-24-7:54:40 PM GMT
Powered by
Adobe
ENT Acrobat Sign
�p Document e-signed by Brian Levenhagen (bjlevenhagen@kentwa.gov)
Signature Date:2024-04-24-7:54:42 PM GMT-Time Source:server
Document emailed to Kim Komoto (kkomoto@kentwa.gov) for signature
2024-04-24-7:54:43 PM GMT
Email viewed by Kim Komoto (kkomoto@kentwa.gov)
2024-04-24-8:37:04 PM GMT
Document e-signed by Kim Komoto (kkomoto@kentwa.gov)
Signature Date:2024-04-24-8:37:11 PM GMT-Time Source:server
Document emailed to cityclerk@kentwa.gov for signature
2024-04-24-8:37:13 PM GMT
Email viewed by cityclerk@kentwa.gov
2024-04-25-3:36:30 PM GMT
�p Signer cityclerk@kentwa.gov entered name at signing as Melissa McCormick
2024-04-25-3:38:47 PM GMT
�c Document e-signed by Melissa McCormick (cityclerk@kentwa.gov)
Signature Date:2024-04-25-3:38:49 PM GMT-Time Source:server
Agreement completed.
2024-04-25-3:38:49 PM GMT
Powered by
Adobe
` ENT Acrobat Sign