HomeMy WebLinkAboutCAG2023-280 - Change Order - #1 - Modern Painting Group, LLC - Kent City Hall Annex Exterior Painting - 06/20/2023 FOR CITY OF KENT OFFICIAL USE ONLY Sup/Mgr: WAI
WM
Agreement Routing Form
• For Approvals,Signatures and Records Management
KE N T This form combines&replaces the Request for Mayor's Signature and Contract Cover
WASHINGTON Sheet forms.
Originator: Department:
Leah Bryant for Nate Harper Parks, Recreation & Community Services
Date Sent: Date Required:
> 06/20/2023 ASAP
0
CL Authorized to Sign: Date of Council Approval:
QDirector or Designee NA
Budget Account Number: G ra n t?1:1 Ye s F71No
F20107.64110.9419
Budget?W]YesEl No Type: N/A
Vendor Name: Category:
Modern Painting Group, LLC Contract
Vendor Number: Sub-Category:
= 2477196 Change Order
0 Kent City Hall Annex Exterior Painting
Project Name: y g
3- Project Details:Change order 1 to demo 4 structural columns that were rotted, rebuild the
0
= columns to their original design, and cover with plywood and finish with
*,, exterior trim.
c
40
40 Agreement Amount: $3 303.00 Basis for Selection of Contractor: Other
`Memo to Mayor must be attached
Start Date: June 2023 Termination Date: 9/30/2023
Im
Q Local Business?F--]YeslzNo* If meets requirements per KCC3.70.100,please complete"Vendor Purchase-Local Exceptions'form on Cityspace.
Business License Verification:YesEl In-ProcessEl Exempt(KCC 5.01.045)
Notice required prior to disclosure? Contract Number:
FTesONo CAG2023-280
Comments:
a1
G
3
4)
H
•� i
N 3
f0
C
V1
Date Routed to the City Clerk's Office: 6/20/23
,c«W»373__,0 Visit Documents.KentWA.gov to obtain copies of all agreements
rev.20210513
40*
KENT
WASHINGTON
CHANGE ORDER NO. #1
NAME OF CONTRACTOR: Modern Painting Group ("Contractor")
CONTRACT NAME & PROJECT NUMBER: Kent City Hall Annex Exterior Painting
ORIGINAL CONTRACT DATE: 5/1/2023
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Change order 1 to demo 4 structural columns that were rotted, rebuild
the columns to their original design, and cover with plywood and finish
with exterior trim.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $31,048.20
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $0
(incl. applicable WSST)
Current Contract Amount $31,048.20
(incl. Previous Change Orders)
Current Change Order $3,000.00
Applicable WSST Tax on this Change $303.00
Order
Revised Contract Sum $34,351.20
CHANGE ORDER - 1 OF 3
Original Time for Completion 9/30/223
(insert date)
Revised Time for Completion under NA
prior Change Orders
(insert date)
Days Required (f) for this Change Order 0 calendar days
Revised Time for Completion 9/30/2023
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
&dMOnd saw PyW Moore
By Edmond Sokoli(Jun 20,202314:16 PDT) By:Will Moore(Jun 20,202314:10 PDT)
7 Edmond oko[i 7 Will Moore
Print Name: Print Name:
Its owner Its Facilities Superintendent
DATE: DATE
J u n 20,2023 (title) J u n 20, 2023(title)
CHANGE ORDER - 2 OF 3
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
ec� AIAO
Kent City Clerk Kent Law Department
[In this field,you may enter the electronic filepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
Exhibit A
MODERN PAINTING GROUP
www.themodernpainting.com
DATE: 6/05/23
Modern Painting Group Customer:
9721 2271h Pl SW City of Kent—IT Annex
Edmond, WA 98020 400 W Gowe St
(206) 390 7956 Kent, WA 98032
Change Order
LICENSED BONDED INSURER
Project Scope of Work
o Demo four (4) columns — Structural
o Remove all material that was affected by rot damage
o Prep area to receive new material
o Rebuild columns to it's original design
o Cover with exterior plywood
o Install exterior trim
o Remove all debris from site
o Dump fee included
Scope Cost Tax Total
Demo & Rebuild four columns $750.00 ea $303.00 $3,303.00
X
Labor& Materials 4 Pieces
=$3,000.00
Prevailing Wage Rates
1
Signature: Kim Komafo
Kim Komoto(Jun 20,2023 14:46 PDT)
Email: cityclerk@kentwa.gov
FAC-062023-Modern Painting Group - IT Annex
C01
Final Audit Report 2023-06-20
Created: 2023-06-20
By: Leah Bryant(Ibryant@kentwa.gov)
Status: Signed
Transaction ID: CBJCHBCAABAA1ewQLyOvC1WL2AzKjcGryg3V_RFhir3C
"FAC-062023-Modern Painting Group - IT Annex COV History
Document created by Leah Bryant(Ibryant@kentwa.gov)
2023-06-20-6:01:27 PM GMT
Document emailed to wmoore@kentwa.gov for signature
2023-06-20-6:04:09 PM GMT
Email viewed by wmoore@kentwa.gov
2023-06-20-9:10:24 PM GMT
Signer wmoore@kentwa.gov entered name at signing as Will Moore
2023-06-20-9:10:51 PM GMT
Document e-signed by Will Moore (wmoore@kentwa.gov)
Signature Date:2023-06-20-9:10:53 PM GMT-Time Source:server
Document emailed to edmond@themodernpainting.com for signature
2023-06-20-9:10:55 PM GMT
Email viewed by edmond@themodernpainting.com
2023-06-20-9:15:48 PM GMT
d4 Signer edmond@themodernpainting.com entered name at signing as Edmond Sokoli
2023-06-20-9:16:37 PM GMT
Document e-signed by Edmond Sokoli (edmond@themodernpainting.com)
Signature Date:2023-06-20-9:16:39 PM GMT-Time Source:server
Document emailed to Kim Komoto (kkomoto@kentwa.gov)for signature
2023-06-20-9:16:40 PM GMT
Powered by
Adobe
�� KENT Acrobat Sign
Email viewed by Kim Komoto (kkomoto@kentwa.gov)
2023-06-20-9:22:17 PM GMT
dp Document e-signed by Kim Komoto (kkomoto@kentwa.gov)
Signature Date:2023-06-20-9:22:26 PM GMT-Time Source:server
Document emailed to cityclerk@kentwa.gov for signature
2023-06-20-9:22:28 PM GMT
Email viewed by cityclerk@kentwa.gov
2023-06-20-9:43:54 PM GMT
d Signer cityclerk@kentwa.gov entered name at signing as Kim Komoto
2023-06-20-9:46:30 PM GMT
d4 Document e-signed by Kim Komoto (cityclerk@kentwa.gov)
Signature Date:2023-06-20-9:46:32 PM GMT-Time Source:server
Agreement completed.