HomeMy WebLinkAboutCAG2020-418 - Change Order - #12 - T. Bailey, Inc. - West Hill Reservoir Construct New 5.0 Million Gallon - 04/10/2023 Agreement Routing Form • For Approvals,Signatures and Records Management KENT This form combines&replaces the Request for Mayor's Signature and Contract Cover Sheet forms. W A S H I N O T O N (Print on pink or cherry colored paper) Originator: Department: S.Anderson PW Engineering Date Sent: Date Required: > 4/24/2023 N/A 0 C. Authorized to Sign: Date of Council Approval: C' 0 Director or Designee ❑Mayor 12/8/2020 Q i Budget Account Number: Grant? ❑Yes 0 No W20054.64110.330 Budget? I]Yes ❑No Type: N/A Vendor Name: Category:T. Bailey, Inc. Contract Vendor Number: Sub-Category: C 294554 Change Order#12 0 'M Project Name: West Hill Reservoir E L C Project Details:Form and place additional concrete mowing curb and sidewalk work. in accordance with T. Bailey's lump sum quote dated 3-20-23, COP #12-R4. C Agreement Amount: $21,216.16 Basis for Selection of Contractor: E Bid aU Start Date: 12/23/2020 Termination Date: 412 Working Days Cn Q Local Business? ❑Yes 0 No* *Ifineets requirements per KCC3.10.100,please complete"Vendor Purchase-Local Exceptions"form on Cityspace. Notice required prior to disclosure? Contract Number: ❑Yes El No CAG2020-418 Date Received by City Attorney: Comments: p1 C a+ 3 0 a, •� i N � Cn Date Routed to the Mayor's Office: Vf Date Routed to the City Clerk's Office: aa«W22373 , 20 Visit Documents.KentWA.gov to obtain copies of all agreements �•� KEN T WA9 HIXOTON CHANGE ORDER NO. 12 NAME OF CONTRACTOR: T. Bailey, Inc. ("Contractor") CONTRACT NAME & PROJECT NUMBER: West Hill Reservoir ORIGINAL CONTRACT DATE: December 23, 2020 This Change Order amends the above-referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: 1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: Form and place additional concrete mowing curb and sidewalk work. In accordance with T. Bailey's lump sum quote dated 3-20-23, COP #12- R4. 2. The contract amount and time for performance provisions of Section II "Time of Completion," and Section III, "Compensation," are hereby modified as follows: Original Contract Sum, $8,493,470.72 (including applicable alternates and WSST) Net Change by Previous Change Orders $391,520.11 (incl. applicable WSST) Current Contract Amount $8,884,990.83 (incl. Previous Change Orders) Current Change Order $19,269.90 Applicable WSST Tax on this Change $1,946.26 Order Revised Contract Sum $8,906,206.99 CHANGE ORDER - 1 OF 3 Original Time for Completion 350 working days (insert date) Revised Time for Completion under working days prior Change Orders �'l (insert date) Days Required (f) for this Change Order 3 working days Revised Time for Completion working days (insert date) I Y. In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the Contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby, ratified and affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written below. CONTRACT R: CITY OF KENT: Chad Bieren i Chad Bleren 2023.04.10 17:14:03-07'00' By: By: slgnature) (signature) Print Name' W- Print Name: Chad Bieren, P.E. Its �r� Its Public Works Director (tile) (title) DATE: DATE: EC KP CHANGE ORDER - 2 OF 3 ATTEST: APPROVED AS TO FORM: (appficable if Mayor's signature required) Kent City Clerk Kent Law Department [In this field,you may enter the electronic nlepath where the contract has been saved] CHANGE ORDER - 3 OF 3 File No. 200.2 KENT CHANGE ORDER WORKSHEET NO. 12 Construction Engineering Division - Public Works Project: West Hill Reservoir Project No: 19-3027.1 Project Engineer: RH2 / Drew Holcomb Fed-Aid No: N/A Capital Projects Phil McConnell Contractor: T Bailey Inc. M n r: Date: Various I. Proposed Change Form and place additional concrete mowing curb and sidewalk work. In accordance with T. Bailey's lump sum quote dated 3-20-2023, COP# 12-R4. II. Reason and Background for Change Contract plans called for mowing curb placement on a portion of the west side property fence only. In discussions with the Water Department, they wanted it included around the entire site perimeter. The addition of mowing curb improves site security making it more difficult to tresspass under the fence and it also improves site maintenance, preventing grass and weeds from growing into fence fabric. There was additonal sidewalk work at the 42nd Av PRV and changes at the reservoir site due to elevations changes. III. Method of Payment NEW PAY ITEMS ❑ Not applicable Sch. Unit Unit Price Total Est. Total Estimated Cost of No Item Description t Item 1 Form and place additional concrete 1 LS $19,269.90 $ 19 269.90 mowing curb $ - New Pay Items Total: $ 19,269.90 DELETE EXISTING PAY ITEMS) per 1-09.5 ❑✓ Not applicable Sch Bid Item No. 7 Item Description Qty Unit Unit Price Cost of Item No. Page 1 Delete Existing Pay Items Total: $ INCREASE/DECREASE TO EXISTING PAY ITEM(S) ❑� Not applicable Soh Bid Item No. Item Description Qty Unit Unit Price Cost of Item No. $ Increase / Decrease to Existing Pay Items Total: $ - *TOTAL ESTIMATED COST OF CHANGE ORDER: $19,269.90 * Total of the Cost of Item Columns IV. WORKING DAYS Original Contract: 350 Due This Change Order: 3 Previous Total: 407 Explanation/Justification for Additional Working Days: The additional work impacted and extended the critical path *TOTAL WORKING DAYS: 410 * This Change Order + Previous Total Capital Projects Manager: t Date: 7j Phi McConnell Construction Engineering Date: Supervisor: wc, J n Barry Construction Manager: r'//� Date: Eric C E onnor Page 2 0 0 0 O O O O O O O O Q) O tf) O LO V CA N J 0 0 LO V N f0 00 f- - N N O) r N toO M f0 EA V)GO EA fA fR CL O) Ck z O O LO Lq O W 0 U to !) O a rn D O LLJ U o 0 o v v 0 rn m (D cNo LO 00 (M O M Z LO m 00 O U 00 U > U Z W - U Q w U) o O. m m o g Q a o L U 0 c L Z _n O J J O } O O O ? � N (� Y f0 U = fA H O U o � O n x K EO O U Q. 1 CL O m 3 O N CD O U O C r O X U 20 (6 CL Y O @ F O E Y O O O -O O O O -O O O L6 L6 m Q W �' N N ER fA (6 0 N D b4 n H Y w 3 U) 0) a) r a Z N O O : c c O 3 U. E v CU Ocn O lO o 0 0 0 0 o Z a O W O N O N O p N N N .- � O) _ — C wa U F- F- 0 0 O rn a •- Z (n O V p v ~O LLI a cn M UJ O O J LU C O Q n ."' W 'O 0) r J a U W U) o QQH 0 ` x U U U F Z ca ZU) o 3 04 a G = O m m w = L C m E 0 0 0 F- r 13 � a r N 2J W Un (n Un 0 0 McConnell, Phil From: Barry, Jason Sent: Thursday, March 16, 2023 7:13 AM To: McConnell, Phil Subject: Internal Approval Mowing Curb Change Order FYI... From: Peterson, Kelly<KPeterson@kentwa.gov> Sent:Wednesday, March 15, 2023 4:50 PM To: Connor, Eric<EConnor@kentwa.gov> Cc: Bieren, Chad <CBieren@kentwa.gov>; Barry,Jason <JBarry@kentwa.gov> Subject: RE: WH Res- Mowing Curb Change Order This is consistent with what we have discussed. Please proceed. Thank you, Kelly Kelly Peterson, AICP, Deputy Director-Engineering Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5547 - Cell 2S3-740-8066 Kpeterson_@ Ke ntW A.gov CITE'OF KENT, WASHINGTON KentWA.ciov Facebook '4`ouTube ,.3.: ONSI kERTHE ENt°:LrtiS ;TENT BEFORE PRINTING TH45 E-PYPIL From: Connor, Eric<EConnor@]<entwa.gov> Sent: Wednesday, March 15, 2023 3:15 PM To: Peterson, Kelly<KPeterson@kentwa.gov> Cc: Bieren, Chad<CBieren kentwa.gov>; Barry,Jason <JBarry@kentwa.gov> Subject: FW:WH Res- Mowing Curb Change Order Good Afternoon Kelly, We had previously discussed the need to add a concrete mow strip to the entire length of perimeter fence around the West Hill Reservoir site. The bid plans call out for approximately 100' of mow strip, but an additional 400' (approximately) will be needed to complete the perimeter. i The subcontractor that will be performing the concrete flat work on the project is working on a LS proposal to add this mow strip, plus some additional sidewalk revisions/repairs. We are estimating a rough order of magnitude cost of $22,000 for the concrete work and another $6,000 for associated prep work that needs to be performed by the site work subcontractor. We are not yet in receipt of final pricing, but have received numbers for the concrete work that we are negotiating. Are you okay with proceeding with this work in an effort to not hold up site work that cannot be completed until the completion of the perimeter fence with the added mow strip? Please let me know if you have questions or need any additional information. Thank you, Eric Eric Connor, construction Engineering Manager Phone 253-856-5533 1 Cell 253-797-0693 CITY OF KENT, WASHINGTON BF 'PRINTIN 15 E-MAIL From: McConnell, Phil <PMcConnell@kentwa.gov> Sent: Friday, March 10, 2023 9:49 AM To: Connor, Eric<EConnor kentwa.gov>; Barry,Jason <JBarry kentwa.gov> Subject: RE:WH Res- Mowing Curb Change Order Here they are. T Bailey still need to incorporate the additional equipment needed to place the concrete. Phil McConnell, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5542 1 Cell 253-261-5685 pmcconnell@KentWA.Qov CITY OF KENT,WASHINGTON KentWA.gov Faceboo€€ YouTube From: Connor, Eric<EConnor@kentwa.gov> Sent: Friday, March 10, 2023 8:03 AM To: McConnell, Phil <PMcConnell@l<entwa. ov>; Barry,Jason <JBarry@kentwa.gov> Subject: RE: WH Res- Mowing Curb Change Order I didn't get an attachment with this. 2 From: McConnell, Phil <PMcConnell kentwa.gov> Sent:Thursday, March 9, 2023 5:36 PM To: Barry,Jason<JBarry kentwa.gov> Cc: Connor, Eric<EConnor@kentwa.gov> Subject:WH Res- Mowing Curb Change Order Jason, Here is the price per foot for the mowing curb. This is ijust Tyee's pricing I'm sure there is additional equipment needed. Mark up too. Phil McConnell, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5542 1 Cell 253-261-5685 pmcconnell@KentWA.gov CITY OF KENT,WASHINGTON KentWA.gov Fab cecaolc YouTube R THE E;, _ ._.. IIS E-MAIL 3 h w '* C cn Lrl N Ul F+ FA N w V �I V 01 rn %0 V v 01 U1 Cr7 r O � 0 cr Q o rt o `�° m c F- un Lrl w 00 00 N 0c1 f.a V V F' O 0 al G1 V O v N N N C n 3 m N F+ t0 �0 N N O