HomeMy WebLinkAboutCity Council Committees - Public Facilities District Board - 09/25/2008 t
1 T
KENI
WASHINGTON
Public Facilities District
September 25, 2008
3:30 p.m.
Board Members Present: Chair Mike Miller, Vice-Chair Greg Haffner,
Secretary Lew Sellers, Randall Smith and Cass Prindle.
Others Present: Economic Development Director Ben Wolters, Finance
Director Bob Nachlinger, Tim Higgins, General Manager of the Events Center,
Brad Tong of Shiels Obletz Johnsen, Director of Sales and Marketing for the
Events Center Beth Sylves, and Administrative Assistant Julie Pulliam.
I. Call to Order
a. Introductions. Miller called the meeting to order at 3:30 p.m.
and introductions were made.
b. Approval of Minutes. Sellers moved to approve the minutes of
July 31, 2008. Haffner seconded and the motion carried.
II. Project Overview and Update
a. Overview of Project Budget. Tong noted that 73% of the project
budget has been spent, that 76% of the construction budget has been
spent, and that the mitigation and financing budget and the
construction contingencies budgets have either been spent or are
committed to be spent. He noted that project life to date expenditures
are at 73%.
b. Overview of Project Schedule. Wolters noted that things are
going well, and though there are challenges ahead, he expects the
Center to open as planned on January 2nd. He stated that he will be
testifying before a state legislative task force which is looking at public
facilities districts and funding for them next week.
Tong pointed out that the general contractor has committed to a
January 2nd completion date, and that although they are currently
seven days behind the early completion commitment, everyone is
working to maintain the schedule.
C. Current Status of Construction. Tong noted that the ice slab
was cast effectively, and that critical path activities include the Club
Lounge, James Street Plaza, and interior millwork. He outlined other
construction and contractor activities which are taking place. Tong
and Wolters then answered questions relating to construction.
d. Status of Design. Tong noted that design is essentially
completed and that procurement is in progress.
III. Operator Update
Tim Higgins noted that Savor has been selected as the food and
beverage provider, said that he is in the process of hiring, and
commented that there has been a lot of interest in putting together
sports teams. He added that contracts have gone out for
housekeeping and security. He said that bookings for the first quarter
are light due to the economy, but that the Harlem Globetrotters are
scheduled for February.
IV. Sales and Marketing Update
a. Thunderbirds. Colin Campbell was not in attendance, so no
update was given.
b. SMG. Beth Sylves explained the work she has been doing with
radio stations in the area promoting the events at the Center. She
said they are working on branding of the Events Center and on
development of a website, and that she expects to see the first draft in
mid-October. She noted that she's also working on advertising for the
grand opening.
V. Finance Report
a. Financial Update. Nachlinger distributed copies of the revenues
and expenses report as of August 31, 2008, and explained the figures.
b. Review of State Sales Tax Revenues. Nachlinger stated that
downturns in the economy result in people seeking entertainment
closer to home. He said he has noticed attendance at the AMC movie
theater in Kent has recently increased, and that he feels confident
about attendance at the Events Center.
VI. Other Business
a. Kiosk. Miller mentioned that downtown merchants have
asked about a kiosk in the Events Center which would contain
information on local restaurants and so forth. Wolters asked Miller to
work with Tim to find good locations for a kiosk. Miller also mentioned
that merchants would like a shuttle bus service.
b. Next Meeting Date. Miller questioned whether this group should
meet monthly from now on, and it was so agreed. It was also noted
that as soon as possible, this group's meeting will be held at the
Events Center. Wolters agreed to have Julie poll the Board as to
whether they can meet on October 23rd, and if not on the 23rd, then on
October 301". The meeting will be at the same time and same place.
VII. Adjournment
At 4:45 p.m., Haffner moved to adjourn. Sellers seconded and the
motion carried.
Mary Simmons
Deputy City Clerk
KENT
EVENTS CENTER
Facility Facts
OPENING JANUARY 2009
Building Attributes
Cost $84.5 million
Funding City of Kent Public Facilities District
Sustainability Built to Silver "LEED" Standard
Management SMG, contracted by City of Kent
Project Developers Mortenson Construction, LMN Architects
in association with PBK Architects
Intimate Seating — One Bowl Height from floor to highest
row only 28'
Scoreboard— Center hung Eight-sided, four 6'6"x14' video screens &
four LED displays
Seating Configurations Capacity(subject to slight changes)
Hockey & Ice Shows 6,125
Concerts Up to 7,800
Basketball 5,852
Arena Football 6,012
Indoor Soccer 5,992
Rodeo & Motorsports 4,213
Boxing/MMA/Pro Wrestling 7,812
Guest Amenities
FREE Parking 1 ,900 stalls
Luxury Suites 20
Club Seats w/Club Lounge Approximately 500
Seat Style Cushioned, 19"-22" width,
Restroom Fixtures — Women 51
Restroom Fixtures — Men 48
Restrooms — Family 2
Food & Beverage Service 28 permanent points of sale, plus
portables & Club Lounge
Private Management for Public Facilities
KENT EVENTS CENTER
PUBLIC FACILITIES DISTRICT
Thursday, September 25, 2008, 3:30 p.m.
Project Overview and Update— Brad Tong /SOJ
Overview of Project Budget
$78.6 M initial approved Project Budget, as of July 2007.
• $84.5 M adjusted Project Budget, approved by City Council as of July 2008.
• Of$84.5 M adjusted Project Budget, 73% ($57.4 M) is spent.
• Of$66.8 M adjusted Construction Budget, approximately 76%($49.8 M) is spent.
• Of$5.2 M adjusted Mitigation & Financing Budget, 100% is spent or committed to be spent.
• Construction contingencies within the original budget is spent or anticipated to be spent—
toward design &construction coordination, bid buyout results and unanticipated conditions in
the field or fabrication, to maintain the aggressive schedule and make-up for construction
schedule challenges.
Overview of Project Schedule
• Construction commenced onsite in August 2007.
13 months of construction completed of the 16-month construction schedule.
Contractual completion date(Beneficial Use) is January 11, 2009.
• Contractor committed to an EARLY COMPLETION date of Jan. 2, 2009, based on their
progress and projections. A community Opening Event is planned for Jan. 2, 2009. A change
order to reflect early completion will be drafted for execution.
• As of today, Contractor is 7 days behind its Jan. 2, 2009 early completion commitment.
• All team members(Owner, Proj. Mgr., Contractor, Design Team)continue to work nonstop to
maintain schedule, deploying schedule recovery plans every week to meet this commitment.
Current Status of Construction
100% of trade contractor buyout is complete.
Ice slab was cast effectively and achieved design strength earlier that anticipated.
Critical path activities include: Club Lounge and James St. Plaza, interior millwork
• Other major construction activities include: exterior metal panels, bi-fold door, all interior
finishes, HVAC testing and balancing, seating installation, landscaping, storefront and metal
panel soffit.
Owner's separate contractor activities include: scoreboard installation (late Oct), Owner's
fixture, furnishings and equipment procurement(delivery late Nov), all food service equipment
procurement in progress.
PFD - Kent Events Center - September 25, 2008
Board Members Present:
/
I. /J Call to Order
2. Project Overview and Update
.� ,!.-u2r1�i✓ ' �G{� c/`Gc,Ccf�'1itIIti.. � °�-YtZ/(C6 7!/'+. ���r� �
/ & o C °
3. Operator Update - Tim Higgins
Jn/1e — Su D/ z�Sirs cis,� " ,,
4. Sales and Marking Update
5. Finance Report - Bob Nachlinger
e
vas°
6. Other Business
pC7"CQ-
/��/+�^/�,.u'7)- CF2u%f"j/}�iZlt[�+�/ ✓� �:CUA t fjJLjy�l�° /fq .Pip•�.' G�tco..��,¢.e.o Lu-�-�.��-G'ON.-(''�°
Adjourn��, T ���
�.tti P•i-_
1�
Y
• III I�[1111��ID!I�;�� � � ��! i�111 .I ��� .•t�
P'Illit����
In
�t
Kent
Opening January 2009
Bellingham
$84.5 million multi-use facility, a 6,150-seat arena
with concert configurations ranging up to 7,800 ��:kJL
and the new home of the Western Hockey League's
Seattle Thunderbirds.
Everett
Seattle/Kent/Tacoma is the country's 14th largest
tle
metropolitan area (US Census 2007) with over 4.1 a lse
❑Beellevue
million residents.
KENT EVENTS _ .. .. .
Kent Events Center is centrally located only 15 _
minutes from Seattle, Tacoma and Bellevue.
Conveniently positioned near Interstate 5, just south _
of Interstate 405 and directly adjacent to State
Route 167.
Situated next to Kent Station, an urban village with
new retail and restaurants, Kent Events Center will
be the crown jewel in a well-designed gathering
place for the residents of the Puget Sound region!
w w w k e n t e v e n t S '
KENT SPECIAL EVENTS CENTER
PUBLIC FACILITIES DISTRICT FUND (PFD)
as of August 31, 2008
2008 YTD
REVENUES
Sales & Use Tax 43 ,129
1
Interest - Sales Tax , 9
Interest - Investments 459,735
Proprietary Gains 1,182,127
Proceeds-Sales Tax Bonds 53,150,000
Proceeds-Revenue Bonds 10,130,000
TOTAL REVENUES 65,361,470
EXPENDITURES
Debt & Financial Services 78,250
Legal Services 100,000
Other Insurance 1,148,620
Intergovernmental Services-Transfer from PFD to City 48,343,412
Printshop Charges 3,316
Debt Issuance Costs 272,104
TOTAL EXPENDITURES 49,945,702
CHANGE IN FUND 15,415,768
EVENTS CENTER CAPITAL PROJECT
as of August 31, 2008
2008 YTD
REVENUES
Intergovernmental Services-Transfer from PFD to City 48,343,412
Interest - Investments 131
Transfers In 50,000
TOTAL REVENUES 48,393,543
EXPENDITURES
Supplies 4,117
Services 48,316,740
Capital Outlay 72,686
TOTAL EXPENDITURES 48,393,543
CHANGE IN FUND
Kent Special Events Center Public Facilities District (PFD)
Sales Tax Revenues
As of August 31, 2008
Month Sales Tax Revenue
March 68,928.08
April 64,340.03
May 77,107.07
June 72,061.77
July 73,138.12
August 82,904.41
438,479.48
City of Kent Monthly Budget Report
KEr1T KENT EVENTS CENTER
Life to Date Costs
as ofSepternber lQ 2008(1-eeonciled.w/COKacctg J.P.tbrttRevised Budget
CommittedRemaining
Budget tLife to Date
7/1 5,108 t
=Archite7cture/Enrgineering(LMN) $ 4,072,229.00 $ 4,503,719.00 $ 4,456,401A0 $ 4,089,861.55 $ 366,539.45
WC TC $ $ 28,510.00 $ 27,470.00 $ 8 509.20 $ 18 960.80
Sub-TOTALI$ 4,072,229.00 $ 4 532 29.00 $ 4 483 871.00 $ 4 098 70.75 $ 385 500.25
2.Pro cl Management Services
Je
Project Management(SOJ) $ 975,975.00 $ 1,035,975.00 $ 1,035,975.00 $ 878,123.47 $ 157,851.53
Testing/Inspecdons(Shannon&Wilson) $ 214,025.00 $ 150,000.00 $ 141,005.90 $ 127,716.57 $ 13,289.33
Testing/lnspecdons(Mayes) $ - $ 172,025.00 $ 165,202.00 $ 156,180.73 $ 9,021.27
Testing/Inspections-Roofing Wetherholt $ - $ 36 000.00 $ 23 000.00 $ 18,063.13 $ 4,936.87
Sub-TOTALI 1 190 000.00 $ 1,394,000.00 $ 1,365,182.90 $ 1,180,083.90 $ 185 099.00
GC/CM Pre-Construction(met.WSST) $ 217,800.00 $ 272,250.00 $ 272,250.00 $ 272,250.00 $
GC/CM Construction incl.WSST $ 63 558 533.00 $ 66 577,827.00 $ 65 605 568.62 $ 49,527 284.21 $ 16,078 284.41
Sub-TOTAL $ 63 776 33.00 $ 66 850 077.00 $ 65 877 818.62 $ 49 799 534.21 $7 16,078,284.41
Operations Consultant $ 100,000.00 $ 100,184.00 $ 100,183.93 $ 100,183.93 $
Feasibility(B&D,Baldwin) $ 85,000.00 $ 85,000.00 $ 85,000.00 $ 84,805.04 $ 194.96
Outside Legal(Foster Pepper) $ 250,000.00 $ 250,000.00 $ 250,000.00 $ 246,262.67 $ 3,737.33
PR/Community Outreach $ 120,000.00 $ 120,000.00 $ 120,000.00 $ 110,197.96 $ 9,802.04
EIS&Transp(Blumen/Heffron) $ 160,000.00 $ 246,250.00 $ 246,250.62 $ 246,250.62 $
Lobbyist/External Fundraising $ 85,000.00 $ 85,000.00 $ 85,000.00 $ 45,000.00 $ 40,000.00
Survey(Baseline) $ 10,000.00 $ 10,000.00 $ 10,000.00 $ 1,718.82 $ 8,281.18
Geotechnical/Soils(S&W Piles) $ 75,000.00 $ 185,000.00 $ 185,000.00 $ 183,244.22 $ 1,755.78
Wetlands Delineation(Legal&Scientist) $ 30,000.00 $ 30,000.00 $ 30 000.00 $ 26,646.71 $ 3,353.29
TraveVMisc/Reimburseables $ 30,000.00 $ 85,000.00 $ 92,664.60 $ 92,664.60 $ -
Builders Risk Insurance $ 125,000.00 $ 211,000.00 $ 210,980.60 $ 210,980.60 $
Owner's Permits/Entitlements $ 200,000.00 $ 395,000.00 $ 390,874.14 $ 390,874.14 $ -
Site Utility Connections/Fees(met PSE/Potelco) $ 100,000.00 $ 100,000.00 $ ]OQ 000.00 $ 23,266.74 $ 76,733.26
Commissioning(EH) $ 100,000.00 $ 100,000.00 $ 96,424.00 $ 47,832.84 $ 48,591.16
FF&E(incl WSST) $ 3,000,000.00 $ 4,400,000.00 $ 4,400,000.00 $ 25,000.00 $ 4,375,000.00
Naming Rights $ $ 13,822.00 $ 13,821.48 $ 13,821.48 $
Owner's LEED Costs $ $ 153,000.00 $ 153,000.00 $ 96,936.91 $ 56,063.09
40,000.00 $ 40,000.00 $ 20,000.00 $ 20,000.00
Owner's Separate Cost Estimating $ $
Special Services(LMN) $ 261,372.00 $ 288,372.00 $ 266,896.78 $ 266,896.78 $
Reimbursables LMN $ 100 000.00 $ 125 000.00 $ 118 000.00 $ 115,339.68 $ 2 660.32
Sub-TOTALI$ 4 831 72.00 $ 7 022 628.00 $ 6,994,096.15 $ 2,347.923.74 $ 4,646,172.41
Mitigation Costs $ 2,112,000.00 $ 2,112,000.00 ',11_',!1!IO.DU $ $ 2,112,000.00
Financing Costs $ 2,600,000.00 $ 2,600,000.00
2 600000.00
! !! I llll
Additional Mitigation $ $ $
Sub-TOTAL $ 4 712 000.00 $ 4 712 000.00 $ 4,712,000.00 $ $ 4,712,000.00
Allocated for Anticipated Contracts $ $ " .'i $ $ 1,077,965.33
Contingency $ $ 8 $
Sub-TOTAL $ $ $ 1 077 965.33 $ $ 1,077,96
PROJECT TOTAL COSTS $ 78 581 934.00 $ 84 510 934.00 $ 84 510 934.00 $ 57 425 912.60 $ 27 O85 021.40
73%