CHANGE ORDER NO. #5
NAME OF CONTRACTOR:
CONTRACT NAME & PROJECT NUMBER:
ORIGINAL CONTRACT DATE:
Lakeside I ~adustries, Inc. ("Contractor")
2022 Asphalt Overlays
May 17, 2022
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Schedule I: Changing the channelization material from paint to plastic
on 124th Ave SE, 148th Ave SE, 144th Ave SE, SE 263 rd St and 148th Ave
SE corridor along Lake Meridian. Schedule II: Change the channelization
material from pairfto plastic on SE 256th St.
Description Unit Price Quantity Units Amount
Plastic Wide Line (Sch 11) 7.00 74S4.00 LF $52,178 .00
Profiled Plastic Double Yellow Centerline (Sch II) 9.00 5580.00 LF $50,220.00
Delete Bid Item 2590 Painted Wide Line (Sch II) 1.30 -250 .00 LF $(325.00)
Delete Bid Item 2595 TWL 1L Paint Line (Sch Il) 1.10 -2550 .00 LF $(2,805.00)
Delete Bid Item 2600 Double Yellow Centerline Paint Stripe (Sch II) 0.55 -700.00 LF $(385.00)
Delete Bid Item 2640 Painted Bike Lane Line (Sch II) 1.10 -4050.00 LF $(4,455.00)
Increase Bid Item 167S Profile Plastic Double Yellow Centerline (Sch I) 9.00 9662.00 LF $86,958.00
Increase Bid Item 1680 Single Solid Plastic Edge Line (Sch I) 5.00 6957.00 LF $34,785.00
Decrease Bid Item 1585 White Edge Line Paint Stripe (Sch I) 0.35 -10799.00 LF $(3, 779.65)
Decrease Bid Item 1595 Double Yellow Centerline Paint Stripe (Sch I) 0.55 -4948.00 LF $(2,721.40)
Delete Bid Item 1670 Plastic Double Yellow Centerline (Sch I) 7.00 -4500.00 LF $(31,500.00)
CHANGE ORDER - 1 OF 3
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $3,851,364.00
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $619,813.50
(incl. applicable WSST)
Current Contract Amount $4,471,177.50
(incl. Previous Change Orders)
Current Change Order _ f $178,169.95
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum i $4,649,347.45
Original Time for Completion
(insert date)
Revised Time for Completion
prior Change Orders
(insert date)
130 working days
under 130 working days
Days Required (f) for this Change Order 100 calendar days
Revised Time for Completion
(insert date)
160 working days
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above -referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
CHANGE ORDER - 2 OF 3
01/10/2023
ATTEST:
IMA
- et;t Kent City Clerk
C[In this field, you may enter the electronic filepath where the contract has been saved]
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
CHANGE ORDER - 4 OF 3
File No. 2OO.2
KENT
CHANGE ORDER WORKSHEET NO. 5
Construction Engineering Division - Public Works
Project: 2022 Overlay
Project Engineer: Drew Holcomb
Capital Projects
Manaaer:Brian Shields
Project No:
Fed-Aid No:
Contractor:
22-300r.L
Lakeside Industries, Inc
Date: t0/L7/2022
I. Pro d Chan e
is change makes the following revisions to the Contract Documents and provides compensation for
added work:
Schedule I: Changing the channelizatin material from paint to plastic on 124th Ave SE, 148th Ave SE,
and the t44th Ave SE, SE 263rd St, and 148th Ave SE corridoralong Lake Meridian. Schedule II: Change
the channelization material from paint to plastic on SE 256th St.
II. Reason and Ba round for Cha e
IIL Method of Payment
NEW PAY ITEMS f ruotapplicable
Change Order 1 accounted for adding asphalt overlay/inlay work and removing chip seal work, this
change order is to change the channelization material from paint to plastic at 256th (schedule ll), I24th
(schedule I), 148th (schedule I), and the L44th/263rd stretch (schedule I). This was not accounted for in
change order 1.
Sch
No Item Description Total Est.
Otv Unit Unit Price Total Estimated Cost of
Item
II Plastic Wide Line 7454 LF $7.00 $52,L7B.OO
II Profiled Plastic Double Yellow Centerline 5580 LF $s.00 $50,220.00
New Pay Items Total: $ 1O2,398.OO
DELETE EXISTING PAY ITEM(S) per 1-O9.5 !ruotappricabre
Sch
No.Bid Item No.Item Description Qtv Unit Unit Price Cost of Item
II 2590 Painted Wide Line -250 LF $1.30 $(32s.00)
II 2595 TWLTL Paint Line -2550 LF $1,10 $(2,805.00)
Page 1"
II 2600 Double Yellow Centerline
Paint Strioe -700 LF $0.ss $(3Bs.o0)
II 2640 Painted Bike Lane Line -4050 LF $1.10 $(4,455.00)
Delete Existing Pay Items Total: $(7,97O.OO)
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ! Notappricabre
Sch
No.Bid ltem No.Item Description Qtv Unit Unit Price Cost of Item
I L675 Profile Plastic Double Yellow
Centerline 9,662 LF $e.00 $86,958.00
I 1680 Single Solid Plastic Edge
Line 6,957 LF $s.00 $34,785.00
I 1585 White Edge Line Paint
Stripe -L0,799 LF $0.3s $(3,779.65)
I 1595 Double Yellow Centerline
Paint Stripe -4,948 LF $0.ss $(2,72L.40)
I L670 Plastic Double Yellow
Centerline -4500 LF $7.00 $(31,500.00)
Increase / Decrease to Existing Pay Items Total: $83174L.95
*TOTAL ESTIMATED COST OF CHANGE ORDER:$178,169.95
x Total of the Cost of Item Columns
IV. WORKING DAYS
Oriqinal Contract:130 Due This Chanqe Order:Previous Total:160
Explanation/Justification for Additional Working Days:
XTOTAL WORKING DAYS:160
x This Change Order + Previous Total
Date: lL -77 2e,22-Capital Projects Manager:
uonstrucuon En9rneenn9
Srrnerwicor:
Brian Shields
son Barry
--4/
Date:/2-/z?-1"-
Construction Manager:
@,<
Eric Connor
Page 2
Date:rek
Shields, Brian
From:
Sent:
To:
Cc:
Subiect:
Shields, Brian
Thursday, September 8,2022 2:50 PM
Holcomb, Drew
Hawkes, Derek; Adams, Brunye; Hallock, Toby; Barry, Jason;Araucto, Joseph
FW:2022 Overlay - Chip seal to Overlay striping change
FYI.
We got approval to lay down profiled plastic in lieu of the paint that was shown for the below-
referenced locations.
I'll be working with Lakeside to develop a change order request and make this happen.
Let me know if you have any questions. Thanks!
Brian Shields, Capitat Projects Manager
Construction Management I Public Works Department
220 4th Avenue South, Kent, WA 98032
Main/Cell 253-293-4973 | Desk 2s3-8s6-6s1o
bshields@KentWA.oov
CITY OF KENT, WASHINGTON
KentwA.oov Facebook -{.1:/itsg{ YouTube
From: Connor, Eric <EConnor@kentwa.gov>
Sent: Thursday, September 8,2022 2:40 PM
To: Shields, Brian <BShields@kentwa.gov>
Cc: Barry, Jason <JBarry@kentwa.gov>
Subject: FW:2O22 Overlay - Chip sealto Overlay striping change
Eric Connor, Construction Engineering Manager
Phone 253-856-5533 | Cell 253-797-0693
CITY OF KENT, WASHINGTON
PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL
From: Bieren, Chad <CBieren@kentwa.sov>
Sent: Thursday, September 8,20222:37 PM
To: Connor, Eric <EConnor(Okentwa.gov>
Subject: RE:2022 Overlay - Chip sealto Overlay striping change
Hi Eric,
Thanks for following up and providing the spreadsheet - please proceed with a change order to
place profiled plastic in lieu of paint.
Thanks,
Chad
1
Chad Bieren, P.E. pubtic works Director
Engineering Administration I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5534 | Cell 253-740-9139
cbieren@KentWA.qov
CITY OF KENT, WASHINGTON
KentWA.oov Facebook iuit!-i:i-l:l_r_ YouTube Instaoram
From: Connor, Eric <EConnor@kentwa.gov>
Sent: Tuesday, September 6,2O22 3:47 PM
To: Bieren, Chad <CBieren@kentwa.eov>
Subject: FW:-2022 Overlay - Chip seal to Overlay striping change
Eric Connor, Construction Engineering Manager
Phone 253-856-5533 | Cell 253-797-0693
CITY OF KENT, WASHINGTON
PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL
From: Connor, Eric
Sent: Thursday, August 25,2022 8:51AM
To: Peterson, Kelly <KPeterson@kentwa.gov>; Maloney, Carla <CMalonev@kentwa.gov>; Rob Brown
<RBrown@kentwa.gov>
Cc: Barry, Jason <J Barry@ kentwa.gov>
Subject: FW: 2022 Overlay - Chip seal to Overlay striping change
Good Morning,
Below are the numbers prepared by Drew for the potential change to the project as discussed in
Check-in. Please let me know if you would like to discuss further or if you have any specific
questions.
Thank you,
Eric
Eric Connor, Construction Engineering Manager
Phone 253-856-5533 | Cell 253-797-0693
CITY OF KENT, WASHINGTON
PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL
From: Holcomb, Drew <DHolcomb@kentwa.gov>
Sent: Wednesday, August 24,2022 5:16 PM
To: Shields, Brian <BShields@kentwa.sov>
Cc: Preston, Erik <EPreston@kentwa.gov>; Araucto, Joseph <JAraucto@kentwa.gov>; Hawkes, Derek
<DHawkes@kentwa.gov>; Barry, Jason <JBarry@kentwa.gov>; Connor, Eric <EConnor@kentwa.gov>
Subject: RE:2022 Overlay - Chip seal to Overlay striping change
2
Hi Brian,
Sorry for the delay. Here are my estimated striping cost changes. Saved in the striping change
tab here.
5tri ping
llerh Ave 5E
sE 256th 5r
t24th Ave 5E
l44th Ave SE/take Meridian
Russell Road
plaltic, add prafilel to centerline
p.rint to plastic plus added lants
paint to plartrc plus 300'to intersettion
pa int to plastic plus full road
Bid
5 4 0,140.00
$ 4,3s9.89
s 5,568.69
$ srt.gz
5 616.13
ChanBe
5
s
s
J
5
sr.vitch to plastic
5 44,801.60
$ 46,604.50
$ 88.6/1,69
$ qq,egl. oo
5 s.65s.00
To tal $ s 1,616.68 $ 2]4,634,79 S
Drew Holcomb, P.E. Design Engineer III
Design Engineering I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Main 253-856-5561 | Cell 253-561-1587
dholcomb@kentwa.gov
CITY OF KENT, WASHINGTON
KentWA.oov Facebook .1":tvj1,lq.l YouTube Instaoram
From: Holcomb, Drew
Sent: Tuesday, August 1.6,2022 3:29 PM
To: Shields, Brian <BShields@kentwa.gov>
Cc: Preston, Erik <EPreston@kentwa.gov>; Araucto, Joseph (JAraucto@kentwa.gov) <JAraucto@kentwa.gov>; Hawkes,
Derek <DHawkes@ ke ntwa.gov>; Barry, Jaso n <J Ba rrv@ kentwa.gov>
Subject: 2022 Overlay - Chip seal to Overlay striping change
Hi Brian,
A few changes to the striping. Since we are no longer doing a chip seal we would like to change
the striping on those roads from paint to plastic.
Joe requested that since we are changing L24th to plastic, can replace the existing paint chan on
this 265'segment to the intersection of 208th with plastic centerline and non-profiled edge
striping (this pavement is in decent shape and was not overlayed)? (This will also require bid
item 1600 plastic wide lane at the turn lane at the intersection of 208th.) I believe this makes
sense and think we should add this.
Also, speaking with Joe and Erik, we want to change all 1670 Plastic Double Yellow Centerline to
t675 Profiled Plastic Double Yellow Centerline. All double yellow plastic centerline shall be
profiled.
Foryour reference (and mine), this is what we bid and changes in red:
94th Ave - paint
248th St - plastic, profiled double yellow centerline
112th - Plastic, nen-profiled double yellow centerline
256th - Schedule 2 (all bid items begin with 2XXX)- eaint Plastic
196th - paint
L24rh - ea+n+Gnie-seat) Plastic and plastic all the way to 2o8th intersection
148th - paint
3
La ke Meri dian/ L44th - pain+plastic
268th - plastic, pr.ofiled double yellow centerline
Russell Rd - schedule 3 (all bid items begin with 3XXX) - pa+n+Plastic
L44th road raising - paint
Thank you,
Drew Hofcomb, P.E. oesign Engineer III
Design Engineering I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Main 253-856-5561 | Cell 253-561-15A7
dholcomb@kentwa.oov