HomeMy WebLinkAboutCAG2022-216 - Change Order - #5 - Lakeside Industries, Inc. - 2022 Asphalt Overlays - 05/17/20221/5/2023 Okay to sign. L. Todd 1/6/2023 1/10/2023 ....... ~ ........ KENT WASHINGTON CHANGE ORDER NO. #5 NAME OF CONTRACTOR: CONTRACT NAME & PROJECT NUMBER: ORIGINAL CONTRACT DATE: Lakeside I ~adustries, Inc. ("Contractor") 2022 Asphalt Overlays May 17, 2022 This Change Order amends the above-referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: 1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: Schedule I: Changing the channelization material from paint to plastic on 124th Ave SE, 148th Ave SE, 144th Ave SE, SE 263 rd St and 148th Ave SE corridor along Lake Meridian. Schedule II: Change the channelization material from pairfto plastic on SE 256th St. Description Unit Price Quantity Units Amount Plastic Wide Line (Sch 11) 7.00 74S4.00 LF $52,178 .00 Profiled Plastic Double Yellow Centerline (Sch II) 9.00 5580.00 LF $50,220.00 Delete Bid Item 2590 Painted Wide Line (Sch II) 1.30 -250 .00 LF $(325.00) Delete Bid Item 2595 TWL 1L Paint Line (Sch Il) 1.10 -2550 .00 LF $(2,805.00) Delete Bid Item 2600 Double Yellow Centerline Paint Stripe (Sch II) 0.55 -700.00 LF $(385.00) Delete Bid Item 2640 Painted Bike Lane Line (Sch II) 1.10 -4050.00 LF $(4,455.00) Increase Bid Item 167S Profile Plastic Double Yellow Centerline (Sch I) 9.00 9662.00 LF $86,958.00 Increase Bid Item 1680 Single Solid Plastic Edge Line (Sch I) 5.00 6957.00 LF $34,785.00 Decrease Bid Item 1585 White Edge Line Paint Stripe (Sch I) 0.35 -10799.00 LF $(3, 779.65) Decrease Bid Item 1595 Double Yellow Centerline Paint Stripe (Sch I) 0.55 -4948.00 LF $(2,721.40) Delete Bid Item 1670 Plastic Double Yellow Centerline (Sch I) 7.00 -4500.00 LF $(31,500.00) CHANGE ORDER - 1 OF 3 2. The contract amount and time for performance provisions of Section II "Time of Completion," and Section III, "Compensation," are hereby modified as follows: Original Contract Sum, $3,851,364.00 (including applicable alternates and WSST) Net Change by Previous Change Orders $619,813.50 (incl. applicable WSST) Current Contract Amount $4,471,177.50 (incl. Previous Change Orders) Current Change Order _ f $178,169.95 Applicable WSST Tax on this Change $0.00 Order Revised Contract Sum i $4,649,347.45 Original Time for Completion (insert date) Revised Time for Completion prior Change Orders (insert date) 130 working days under 130 working days Days Required (f) for this Change Order 100 calendar days Revised Time for Completion (insert date) 160 working days In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below. Also, pursuant to the above -referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the Contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby ratified and affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. CHANGE ORDER - 2 OF 3 01/10/2023 ATTEST: IMA - et;t Kent City Clerk C[In this field, you may enter the electronic filepath where the contract has been saved] APPROVED AS TO FORM: (applicable if Mayor's signature required) Kent Law Department CHANGE ORDER - 4 OF 3 File No. 2OO.2 KENT CHANGE ORDER WORKSHEET NO. 5 Construction Engineering Division - Public Works Project: 2022 Overlay Project Engineer: Drew Holcomb Capital Projects Manaaer:Brian Shields Project No: Fed-Aid No: Contractor: 22-300r.L Lakeside Industries, Inc Date: t0/L7/2022 I. Pro d Chan e is change makes the following revisions to the Contract Documents and provides compensation for added work: Schedule I: Changing the channelizatin material from paint to plastic on 124th Ave SE, 148th Ave SE, and the t44th Ave SE, SE 263rd St, and 148th Ave SE corridoralong Lake Meridian. Schedule II: Change the channelization material from paint to plastic on SE 256th St. II. Reason and Ba round for Cha e IIL Method of Payment NEW PAY ITEMS f ruotapplicable Change Order 1 accounted for adding asphalt overlay/inlay work and removing chip seal work, this change order is to change the channelization material from paint to plastic at 256th (schedule ll), I24th (schedule I), 148th (schedule I), and the L44th/263rd stretch (schedule I). This was not accounted for in change order 1. Sch No Item Description Total Est. Otv Unit Unit Price Total Estimated Cost of Item II Plastic Wide Line 7454 LF $7.00 $52,L7B.OO II Profiled Plastic Double Yellow Centerline 5580 LF $s.00 $50,220.00 New Pay Items Total: $ 1O2,398.OO DELETE EXISTING PAY ITEM(S) per 1-O9.5 !ruotappricabre Sch No.Bid Item No.Item Description Qtv Unit Unit Price Cost of Item II 2590 Painted Wide Line -250 LF $1.30 $(32s.00) II 2595 TWLTL Paint Line -2550 LF $1,10 $(2,805.00) Page 1" II 2600 Double Yellow Centerline Paint Strioe -700 LF $0.ss $(3Bs.o0) II 2640 Painted Bike Lane Line -4050 LF $1.10 $(4,455.00) Delete Existing Pay Items Total: $(7,97O.OO) INCREASE/DECREASE TO EXISTING PAY ITEM(S) ! Notappricabre Sch No.Bid ltem No.Item Description Qtv Unit Unit Price Cost of Item I L675 Profile Plastic Double Yellow Centerline 9,662 LF $e.00 $86,958.00 I 1680 Single Solid Plastic Edge Line 6,957 LF $s.00 $34,785.00 I 1585 White Edge Line Paint Stripe -L0,799 LF $0.3s $(3,779.65) I 1595 Double Yellow Centerline Paint Stripe -4,948 LF $0.ss $(2,72L.40) I L670 Plastic Double Yellow Centerline -4500 LF $7.00 $(31,500.00) Increase / Decrease to Existing Pay Items Total: $83174L.95 *TOTAL ESTIMATED COST OF CHANGE ORDER:$178,169.95 x Total of the Cost of Item Columns IV. WORKING DAYS Oriqinal Contract:130 Due This Chanqe Order:Previous Total:160 Explanation/Justification for Additional Working Days: XTOTAL WORKING DAYS:160 x This Change Order + Previous Total Date: lL -77 2e,22-Capital Projects Manager: uonstrucuon En9rneenn9 Srrnerwicor: Brian Shields son Barry --4/ Date:/2-/z?-1"- Construction Manager: @,< Eric Connor Page 2 Date:rek Shields, Brian From: Sent: To: Cc: Subiect: Shields, Brian Thursday, September 8,2022 2:50 PM Holcomb, Drew Hawkes, Derek; Adams, Brunye; Hallock, Toby; Barry, Jason;Araucto, Joseph FW:2022 Overlay - Chip seal to Overlay striping change FYI. We got approval to lay down profiled plastic in lieu of the paint that was shown for the below- referenced locations. I'll be working with Lakeside to develop a change order request and make this happen. Let me know if you have any questions. Thanks! Brian Shields, Capitat Projects Manager Construction Management I Public Works Department 220 4th Avenue South, Kent, WA 98032 Main/Cell 253-293-4973 | Desk 2s3-8s6-6s1o bshields@KentWA.oov CITY OF KENT, WASHINGTON KentwA.oov Facebook -{.1:/itsg{ YouTube From: Connor, Eric <EConnor@kentwa.gov> Sent: Thursday, September 8,2022 2:40 PM To: Shields, Brian <BShields@kentwa.gov> Cc: Barry, Jason <JBarry@kentwa.gov> Subject: FW:2O22 Overlay - Chip sealto Overlay striping change Eric Connor, Construction Engineering Manager Phone 253-856-5533 | Cell 253-797-0693 CITY OF KENT, WASHINGTON PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Bieren, Chad <CBieren@kentwa.sov> Sent: Thursday, September 8,20222:37 PM To: Connor, Eric <EConnor(Okentwa.gov> Subject: RE:2022 Overlay - Chip sealto Overlay striping change Hi Eric, Thanks for following up and providing the spreadsheet - please proceed with a change order to place profiled plastic in lieu of paint. Thanks, Chad 1 Chad Bieren, P.E. pubtic works Director Engineering Administration I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5534 | Cell 253-740-9139 cbieren@KentWA.qov CITY OF KENT, WASHINGTON KentWA.oov Facebook iuit!-i:i-l:l_r_ YouTube Instaoram From: Connor, Eric <EConnor@kentwa.gov> Sent: Tuesday, September 6,2O22 3:47 PM To: Bieren, Chad <CBieren@kentwa.eov> Subject: FW:-2022 Overlay - Chip seal to Overlay striping change Eric Connor, Construction Engineering Manager Phone 253-856-5533 | Cell 253-797-0693 CITY OF KENT, WASHINGTON PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Connor, Eric Sent: Thursday, August 25,2022 8:51AM To: Peterson, Kelly <KPeterson@kentwa.gov>; Maloney, Carla <CMalonev@kentwa.gov>; Rob Brown <RBrown@kentwa.gov> Cc: Barry, Jason <J Barry@ kentwa.gov> Subject: FW: 2022 Overlay - Chip seal to Overlay striping change Good Morning, Below are the numbers prepared by Drew for the potential change to the project as discussed in Check-in. Please let me know if you would like to discuss further or if you have any specific questions. Thank you, Eric Eric Connor, Construction Engineering Manager Phone 253-856-5533 | Cell 253-797-0693 CITY OF KENT, WASHINGTON PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Holcomb, Drew <DHolcomb@kentwa.gov> Sent: Wednesday, August 24,2022 5:16 PM To: Shields, Brian <BShields@kentwa.sov> Cc: Preston, Erik <EPreston@kentwa.gov>; Araucto, Joseph <JAraucto@kentwa.gov>; Hawkes, Derek <DHawkes@kentwa.gov>; Barry, Jason <JBarry@kentwa.gov>; Connor, Eric <EConnor@kentwa.gov> Subject: RE:2022 Overlay - Chip seal to Overlay striping change 2 Hi Brian, Sorry for the delay. Here are my estimated striping cost changes. Saved in the striping change tab here. 5tri ping llerh Ave 5E sE 256th 5r t24th Ave 5E l44th Ave SE/take Meridian Russell Road plaltic, add prafilel to centerline p.rint to plastic plus added lants paint to plartrc plus 300'to intersettion pa int to plastic plus full road Bid 5 4 0,140.00 $ 4,3s9.89 s 5,568.69 $ srt.gz 5 616.13 ChanBe 5 s s J 5 sr.vitch to plastic 5 44,801.60 $ 46,604.50 $ 88.6/1,69 $ qq,egl. oo 5 s.65s.00 To tal $ s 1,616.68 $ 2]4,634,79 S Drew Holcomb, P.E. Design Engineer III Design Engineering I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Main 253-856-5561 | Cell 253-561-1587 dholcomb@kentwa.gov CITY OF KENT, WASHINGTON KentWA.oov Facebook .1":tvj1,lq.l YouTube Instaoram From: Holcomb, Drew Sent: Tuesday, August 1.6,2022 3:29 PM To: Shields, Brian <BShields@kentwa.gov> Cc: Preston, Erik <EPreston@kentwa.gov>; Araucto, Joseph (JAraucto@kentwa.gov) <JAraucto@kentwa.gov>; Hawkes, Derek <DHawkes@ ke ntwa.gov>; Barry, Jaso n <J Ba rrv@ kentwa.gov> Subject: 2022 Overlay - Chip seal to Overlay striping change Hi Brian, A few changes to the striping. Since we are no longer doing a chip seal we would like to change the striping on those roads from paint to plastic. Joe requested that since we are changing L24th to plastic, can replace the existing paint chan on this 265'segment to the intersection of 208th with plastic centerline and non-profiled edge striping (this pavement is in decent shape and was not overlayed)? (This will also require bid item 1600 plastic wide lane at the turn lane at the intersection of 208th.) I believe this makes sense and think we should add this. Also, speaking with Joe and Erik, we want to change all 1670 Plastic Double Yellow Centerline to t675 Profiled Plastic Double Yellow Centerline. All double yellow plastic centerline shall be profiled. Foryour reference (and mine), this is what we bid and changes in red: 94th Ave - paint 248th St - plastic, profiled double yellow centerline 112th - Plastic, nen-profiled double yellow centerline 256th - Schedule 2 (all bid items begin with 2XXX)- eaint Plastic 196th - paint L24rh - ea+n+Gnie-seat) Plastic and plastic all the way to 2o8th intersection 148th - paint 3 La ke Meri dian/ L44th - pain+plastic 268th - plastic, pr.ofiled double yellow centerline Russell Rd - schedule 3 (all bid items begin with 3XXX) - pa+n+Plastic L44th road raising - paint Thank you, Drew Hofcomb, P.E. oesign Engineer III Design Engineering I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Main 253-856-5561 | Cell 253-561-15A7 dholcomb@kentwa.oov CITY OF KENT, WASHINGTON KentWA.oov Facebook Twltt-gl YouTube Instaoram 4