Loading...
HomeMy WebLinkAboutCAG2022-146 - Change Order - #6 - Olson Brothers Excavating, Inc. - Downey Side Channel Restoration Final Phase - 12/21/2022is O L a a Z. G1 C O T% aticcW22373_1_20 Agreement Routing Form • For Approvals, Signatures and Records Management KENT This form combines & replaces the Request for Mayor's Signature and Contract Cover Sheet forms. WASHINGTON (Print on pink or cherry colored paper) Originator: Department: Stephanie Anderson PW Engineering Date Sent: Date Required: 12/20/2022 N/A Authorized to Sign: Date of Council Approval: 0 Director or Designee ❑ Mayor 4/5/2022 Budget Account Number: Grant? 0 Yes ❑ No D20074.64110.330 Type: N/A Vendor Name: Category: Olson Brothers Excavating, Inc. Contract Vendor Number: Sub -Category: Change Order 6 Project Name: Downey Side Channel Restoration Final Phase Project Details: Compensation for force account work require to repair settlement on Frager Road. Work was tracked on FA sheets RR1-RR7. Agreement Amount: $47,474.24 Basis for Selection of Contractor: Bid Start Date: 4/15/2022 Termination Date: 114 working days Local Business? ❑ Yes ❑ No* *If meets requirements per KCC3.70.100, please complete "Vendor Purchase -Local Exceptions" form on Cityspoce. Notice required prior to disclosure? ❑ Yes ❑ No Date Received by City Attorney: Date Routed to the Mayor's Office: Contract Number: CAG2022-146 Comments: Date Routed to the City Clerk's Office: t Visit Documents.KentWA.gov to obtain copies of all agreements 400,0000� • N11-7KENT WASHINGTON CHANGE ORDER NO. #6 NAME OF CONTRACTOR: CONTRACT NAME & PROJECT NUMBER ORIGINAL CONTRACT DATE: Olson Brothers Excavatina, Inc ("Contractor") Downev Side Channel Restoration Final Phase Aoril 15, 2022 This Change Order amends the above -referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: 1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: Compensation for force account work required to repair settlement on Frager Road. Work was tracked on FA sheets RR1-RR7. 2. The contract amount and time for performance provisions of Section II "Time of Completion," and Section III, "Compensation," are hereby modified as follows: Original Contract Sum, $3,129,996.84 (including applicable alternates and WSST) Net Change by Previous Change Orders $164,975.67 (incl. applicable WSST) Current Contract Amount $3,294,972.51 (incl. Previous Change Orders) Current Change Order $43,119.20 Applicable WSST Tax on this Change $4,355.04 Order Revised Contract Sum $3,342,446.75 CHANGE ORDER - 1 OF 3 Original Time for Completion 1100 working days (insert date) Revised Time for Completion under 110 working days prior Change Orders (insert date) Days Required (f) for this Change Order i 4 calendar days Revised Time for Completion i 114 working days (insert date) In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below. Also, pursuant to the above -referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the Contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby ratified and affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written below. CONTRACTOR: Digitally signed by Bryce Sturrock W C=US, E=bryces@alsonbrolhars net, &Olson BrothersEcavaling, Inc", CN=Bryce Bryce Sturrock Sturrock Reason' I am approving this document By: Data: 2022.12. 1606.33.03-08'DO' (signature) Print Name: Brvice Sturrock Its Estimator / PM (title) DATE: 12/16/2022 CHANGE ORDER - 2 OF 3 CITY OF KENT: Digitally signed by Chad Bieren Chad B i e re n K.DN C=US, E=cbiWbrks, CN=C gd 3—ni y of DN C=US, E-I ,em, , -Chad , 0=0 By: Dats: 2022. 12211E M0-08'00' (signature) Print Name: Chad Bieren, P.E. Its Public Works Director (title) DATE: EC ATTEST: vW V Kent City Clerk C[In this Field, you may enter the electronic flepath where the contract has been saved] APPROVED AS TO FORM: ' (applicable if Mayor's signature required) Kent Law Department CHANGE ORDER - 3 OF 3 File No. 200.2 KENT CHANGE ORDER WORKSHEET NO. 06 Construction Engineering Division - Public Works Project: Downey Side Channel Restoration Final project No: 18-3007.1 Phase Project Engineer: Melissa Dahl Fed -Aid No: N/A Capital Projects Jason Bryant Contractor: Olson Brothers Manaaer: Date: 12/2/2022 I. Proposed Change This change order compensates Olson Brother's for force account worked required to repair settlement on Frager Road. Work was tracked on FA sheets RR1-RR7. II. Reason and Background for Change Contract plans identified a pavement settlement area within Frager Rd that had sunk over the course of previous phases of the project. Unfortunately original bid quanities did not account for this body of work. Had the HMA bid item been used, asphalt alone would have totaled $76,800 plus the estimated $10,000 in overexcavation/backfill work. With this in mind, Olson Brothers agreed to perform work under Force Account, tracked on FA sheets RR1-RR7. III. Method of Payment NEW PAY ITEMS ❑ Not applicable Sch No . Item Description No x Roadway Repairs Total Est. Unit Unit Price Qty 1 FA $43,119.20 Total Estimated Cost of Item $43,119.20 $ $ New Pay Items Total: $ DELETE EXISTING PAY ITEM(S) per 1-09[3 Not applicable 43,119.20 Page 1 Sch No. Bid Item No. Item Description Qty I Unit I Unit Price $ I 1 1$ Delete Existing Pay Items Total: $ Cost of Item INCREASE/DECREASE TO EXISTING PAY ITEM (E)Nct applicable Sch Bid Item No. Item Description ption Qty Unit I Unit Price Cost of Item $ - - $ Increase / Decrease to Existing Pay Items Total: $ - *TOTAL ESTIMATED COST OF CHANGE ORDER: ! $43,119.20 * Total of the Cost of Item Columns IV. WORKING DAYS �naiiye Original Contract: 100 uue i n�5 Cidiiy 4 I Previous Total: 100 Capital Projects Manager: Capital Projects Supervisor: Construction Manager: *TOTAL WORKING DAYS: 104 * This Change Order + Previous Total J. Zon Bryant J on Barry Eric Connor Date: �s2 Date: +2) 7 Z Z r � Date: Page 2 Connor, Eric From: Bieren, Chad Sent: Tuesday, December 13, 2022 8:53 AM To: Connor, Eric; Peterson, Kelly Cc: Barry, Jason Subject: RE: Downey- COWS-6 Road Repairs Hi Eric, Thank you for the update, we agreed to this change order verbally back before work started - please proceed with processing the paper work. Chad Chad Bieren, P.E. Public Works Director Engineering Administration I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5534 1 Cell 253-740-9139 cbieren(@KentWA.aov CITY OF KENT, WASHINGTON KentWA.gov Facebook YouTube Instagram From: Connor, Eric <EConnor@kentwa.gov> Sent: Tuesday, December 13, 2022 7:44 AM To: Peterson, Kelly <KPeterson@kentwa.gov>; Bieren, Chad <CBieren@kentwa.gov> Cc: Barry, Jason <JBarry@kentwa.gov> Subject: RE: Downey- COWS-6 Road Repairs Good Morning Kelly and Chad, As you may recall, we had communication regarding the road repairs needed on Frager Road on the Downey project as a result of organic debris that was buried beneath the roadway. The repair was completed under our direction and the final cost is $43,119.20. We had expected that it would be in the range of $50k to $60k. Are you okay with Construction proceeding with a change order in the amount of $43,119.20 so we can compensate the contractor on their next pay estimate? Please let me know if you have any questions or need any additional information. Thank you, Eric Eric Connor, Construction Engineering Manager Phone 253-856-5533 1 Cell 253-797-0693 CITY OF KENT, WASHINGTON PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Connor, Eric Sent: Wednesday, December 7, 2022 10:09 AM To: Peterson, Kelly <KPeterson@kentwa.gov>; Bieren, Chad <CBieren@kentwa.9ov> Subject: FW: Downey- CO-6 Road Repairs Hi Kelly / Chad, I wanted to share the final cost ($43,119.20) for the subsidence repair on Frager Road at Downey. Eric Connor, Construction Engineering Manager Phone 253-856-5533 1 Cell 253-797-0693 CITY OF KENT, WASHINGTON PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL From: Barry, Jason <JBarrv@kentwa.Rov> Sent: Tuesday, December 6, 2022 2:57 PM To: Bryant, Jason <JBrvant@kentwa.Rov> Cc: Connor, Eric <EConnor@kentwa.Rov>; Harris, Josh <JHarris@kentwa.gov> Subject: RE: Downey- CO-6 Road Repairs Here's my stab at it Jason. Thanks, Jason Jason Barry, Capital Projects Supervisor Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 s� `'� Phone 253-856-5546 1 Cell 253-797-8462 ` KENT ibarrvCd)KentwA.aov W,b—.6=6. www.KentWA.aov PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E- MAIL From: Bryant, Jason <JBrvant@kentwa.eov> Sent: Tuesday, December 6, 2022 8:51 AM To: Barry, Jason <JBarrv@kentwa.Rov> Cc: Connor, Eric <EConnor(@kentwa.Rov>; Harris, Josh <JHarris@kentwa.1zov> Subject: Downey- CO-6 Road Repairs Jason, Attached is change order worksheet # 6 for your review/edit. I put a copy in the P Drive: P:\Public\PROJECTS\_In Construction\18-3007.1 Downey Final phase\200 Measurement & Payment\200.2 Change Orders With Engineer's Estimates\CO-006 Road Repairs Thank you, Jason Bryant, Capital Projects Manager 2 MOOOOOOO u u u u u u u u u u u u u OOOOOOOz m 0 .-•I • +-� N N M It Ln TH .-1 w N Cn lfl M M O N O Cn %.6 Ln Lr1 N O N CTl to .-a O O .+ Ln .-z CO r, Cn M O F- d' if)- JA- 4d:'r 4j)- 4- J- ift -6+ M ro u O -O L7 C co � � 3 � L u t' m rn -v c c EL c (1) - 0 a U ra o c��a ru > 3 47 ro Q = c G }, � x rn E ° o w >, >. o -0 ru +� 3 D -0 -0 — L.0 .0 0 a 0 E r0 o E 5 mu u _� v u =lu r> ww-j aci O +� N M d' Ln lD I-, a' fy w CL LY Cr LY Q LL FA Sheet No.: RR1 DAILY REPORT OF ' FORCE ACCOUNT WORKED - E _ T Project Name: Downey Side Channel Project No: 18-3007.1 Item No.: Change Order # 6 Date: 10/10/2022 Description of Work: Remove asphalt from trail and roadway and haul away Work by Subcontractor?: NO Prime Contractor: Olson Brothers Sub -Contractor: LABOR STRAIGHT TIME OVERTIME DOLLAR NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT J. Pierson Foreman 8 88.94 $ 711.52 D Stockmeyer Laborer 8 63.12 $ 504.96 IG. Sorenson Foreman 8.5 83.21 $ 707.29 $ $ SUBTOTAL -LABOR: $ 1,923.77 LABOR OVERHEAD & PROFIT @ 31% $ 596.37 LABOR TOTAL $ 2,520.14 EQUIPMENT EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR Equipment # Equipment Descriotion Hrs Hourly Rate Hrs Standby Rate AMOUNT 27 KW-F550 8 51.75 $ 414.00 131 Cat-308 excavator 8 91.97 $ 735.76 45 KW Dump Truck 8.5 114.36 $ 972.06 $ SUBTOTAL - EQUIPMENT $ 2,121.82 EQUIPMENT OVERHEAD & PROFIT @ 21% $ 445.58 EQUIPMENT TOTAL $ 2,567.40 MATERIALS/SERVICES/RENTALS MATERIALS / SERVICES Quantity I Units Unit Price DOLLAR AMOUNT Miles Inv# 338564 62.94 tons $ 7.00 $ 440.58 $ $ $ SUBTOTAL $ 440.58 OVERHEAD & PROFIT @ 21% $ 92.52 TOTAL $ 533.10 Verification of Hours Worked: TOTAL: $ 5,620.64 12% MARKUP (for prime when subcontract work) $ - Bryce Sturrock SHEET TOTAL: $ 5,620.64 contractor's Representative Owners Representative �/ ] apil E r�//� ad Data 12/2/2022 Pay Estimate Entered: Date: By: Job Name DowneY Date: 1011012022 Force Account No 1040-9010-1 Olson Brothers Excavating, Inc. OBE Job No, 1301, FORCE ACCOUNT Description of Extra Remove asphalt from walk and street. Load out and haui to miles. work: Name Trade REG IOT UOM Re Rate 01 Rate 1.5 Total I 1.PIERSON FM 8 I I HR l .94 711.51 I O.STOCKMYCR LA83 8 I I HR 63.12 504.98 I TD 8.5 HR fl3.21 707,30 I NR 0 I 0.00 1 HR 0 0.00 1 HR 0 0.00 HR 0 0.00 I LABOR TOTAL $2,923,791 Equip lO Equipment Uescription I HRS Rate I Total I I 21 1W-1550 8 51.75 I I 414.D0 I 131 CAT,308 I 8 91.97 I 735.76 I 45 KW -DUMP TRUCK I 8.5 114.36 972.06 I I 0 0.00 I 1 0 0.00 I - I 0 1 0.Do I I 1 0 I I 0•O I I I I 0 I I 0.0o I ECIUIPMENTTOTALI $2,121.821 Vendor I38564 Uescripton I UUM Unlls I Price I Tola! IMILCS INV. 31N 62.94 7100 M0.58 I 0.00 I 0.00 I i 0.00 I i ° 00 1 1 0.00 I I I 0.00 I I I I I 0.00 I I I I I 0.00 I MATERIALTOTALI $440.581 SPb-1111Clgr Uescription I Units I P'l. Total I 0.00 I I o.o0 1 0.00 1 0.00 I 0.00 I 1 SUBCONTRACTOR TOTAL $o.001 Labor Subtotal 1,923J9 Material Subtotal 440.58 31% 596.37 21.00% 92.52 _Labor Total 2,520.16 Materiallotai 533.10 Equipment Subtotal 2,121.92 Subcnntractor 5ubto1 6.00 Eq21.00% 445.58 12.00% 0.00 muipent Total 2,567,40 Subcontractor Totai 0.00 ADDITIONAL WORK DAYS 1 , TOTAL FORCE ACCOUNT $5,610.66 FA01040-90M1 OLSON BROTHERS EXCAVATING, INC. N U 102 916 6622 1121h St. E., Puyallup, WA 98373 (253)770.3844 Fax (253) 770-3845 DATE O G 47 NAME_� f ADDRESS _ 1 .. ---.r lZe l / I3C Job LOCOY StartTimm 7: -- Timch Slop e 7'-3 G Lun2 Load Load Load) Load No. Material _ 7km Quantity No. Material_ Time Quanft 1 ,w z.� 16ITu 1isne,-,-; I 2 7—171 Z& le, -e aI 1 I 191 51 I I 201 61 I I I21I 71 I 1 1221 1 I B I I I 1231 /OY41 9o14 ' I g s C, 91 I I I24I I I 101 I I I251 I I 111 I I I26I I 1 121 I I 1271 I I 131 I I 128 I 14I I I I29 I 151 I I 1301 I Truck No.: Ltl�' ITruck Charges: Truck Type: S� I Driver Charge: Truck Rate: I Sub Total: Truck Hours: *Add Charges: Driver Hours: I Total Charges: Signature: *Terms Net loth, 1.5% billing charge on all accounts past due FA Sheet No.: RR2 DAILY REPORT OF FORCE ACCOUNT WORKED Project Name: Downey Side Channel Project No: 18-3007.1 Item No.: Change Order # 6 Date: 10/11/2022 Description of Work: Haul out asphalt. Work by Subcontractor?: NO Prime Contractor: Olson Brothers Sub -Contractor: LABOR STRAIGHT TIME OVERTIME DOLLAR NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT J. Pierson Foreman 4 88.94 $ 355.76 D Stockmeyer Laborer 4 63.12 $ 252.48 IG. Sorenson Foreman 1.75 83.21 $ 145.62 I $ SUBTOTAL -LABOR: $ 753.86 LABOR OVERHEAD & PROFIT @ 31 % $ 233.70 LABOR TOTAL $ 987.56 EQUIPMENT EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR Equipment # Equipment Description Hrs Hourly Rate Hrs Standb,.r Rate AMOUNT 27 KW-F550 4 51.75 $ 207.00 131 Cat-308 excavator 4 91.97 $ 367.88 45 KW Dump Truck 1.75 114.36 $ 200.13 $ I $ SUBTOTAL -EQUIPMENT $ 775.01 EQUIPMENT OVERHEAD & PROFIT @ 21% $ 162.75 EQUIPMENT TOTAL $ 937.76 MATERIALS/SERVICES/RENTALS MATERIALS / SERVICES Quantity I Units Unit Price DOLLAR AMOUNT Miles Inv# 338564 8.74 tons $ 7.00 $ 61.18 $ $ SUBTOTAL $ 61.18 OVERHEAD & PROFIT @ 21% $ 12.85 TOTAL $ 74.03 Verification of Hours Worked: TOTAL: $ 1,999.35 12% MARKUP (for prime when subcontract work) $ - Bryce Sturrock�:� SHEET TOTAL: $ 1,999.35 Contractor's Representative e �7asoh 51-yad Date 12/2/2022 Owners Representative Pay Estimate Entered: Date: By: Job Name Downey Date: 10/11/2022 Olson Brothers Excavating, Inc. OBE Job No. 1304 Force Account No 01040-9010-2 FORCE ACCOUNT Description of Extra Haul out asphalt. Prep for concrete bike Warning strip Work: Name Tratle AEG OT UOM Reg Rate _ OT Rate 1.5 total 'pIEeSON R 88.94 355.75 1I IT.WAL7ER LAB- 4 HR 63.12 252.49 1 ID 1.75 I HR 83,21 145.62 I HR 0 0.00 I HR 0 0.00 I HR 0 0.00 i HR 0 0.00 I LABOR TOTAL S753.86I Equip ID Lnuipnlent DMtription HRS Rate otal I 27 KW-F550 4 51.75 207.00 I _ 131 CAT-308 4 91.97 367.88 -j 46 KW -DUMP TRUCK 1.75 114.36 2ODA3 0 I 000 I D I 0,00 I D I--- 0.00 0 I 0.00 0 I 0.00 1 EQUIPMENT TOTALI $775.O1I I vendor Descripbon UOM I Units p rice Total I NtilES INV. 338564 TON 8.74 7.00 61,18 j I 0.00 I I 0 00 I r 0.00 I I 0100 I I 0.00 I 0.00 I 0,00 j I 0.00 I MATERIAL IOTALI $61,101 Subcontractor Description _toi�l ._.... Labor Subtotal 753.86 3176 233.70 Labor Total 987.56 Equipment Sublulal- 21.00ffi 16Z 775 16L7S Equipment Total 937.76 ADDITIONAL WORK DAYS 1 j PA01040.9010-2 Units p!;- I !qwl 0.00 I I o.00 I o I I I o0.0m I I I 0.0o I SUBCONTRACTOR TOTAL $0.001 Material Subtotal 61.178 ._._ _..__.......- 12,81 L Mdleria!23.0Tplal 04; 74.03 Subcontractor Subtoal 0.00 12,00`k O.Ob Subcontractor Total 0.00 TOTAL PORCE ACCOUNT $1,999.35 OLSON BROTHERS TRUCKING N2 6410 6822 112th St. S., Puyallup, WA 98373 (253) 770.35" Fax (253) 7703845 -• DATE -1' o NAME �Bn7 ADDRESS .( L A sr' Job Location start Time I4SZ tuna, Stop Time-5Loa�.]Z NO. Material I Tkm IOuentlN No. Materiel I Tkne IOuentlry — 0 1 16 2 17 I I 3 18 1 1 4 I 1 19 1 1 51 1 120 1 1 sl 1 1 121 I 1 71 1 I 122 1 101 I 1 1251 1 111 1 1261 1 1 121 I 1 1271 1 1 13 1 I 1281 l 15 I 0 I I Truck No.: L�/ 1 Truck Charges: Truck Type: Driver Charge: Truck Rate: Sub Total: Truck Hours: 3/,y / *Add Charges: Driver Hours: Total Charges: Signature: *Terms Net 10th, 1.5% bflfing charge on all accounts past due. Iul MILES RESOURCES From: Miles Resources, LLC 400 Valley Avenue NE Puyallup WA 98372 Sold To: OLSON BROTHERS EXCAVATING Delivered To: 6622 112TH ST E PUYALLUP. WA 98373 INVOICE Invoice #: 338564 Date: 10/17/22 Customer No: 50525 Job #: 22.1304 1304 PO #: NEY FARMSTEAD RES Tax Sale Date Ticket Units UM Unit Price Mail Total Haul Total Code Tax Total Sato Data: 10110/22 Location: 200 • Lakeview • Processing MATERIAL: WASTE CLEAN BROKEN ASPHALT 10110122 799880 20.900 TON 7.0000 E 10/10122 799970 23.870 TON 7.0000E 10/1012, 000032 18.OBO TON 7.0000E Total: WASTE CLEAN BROKEN ASPHAI 62.84 TON Total: 10110/2022 Sale Date: 10/11122 Location: 200 • Lakeview • Processing MATERIAL: WASTE CLEAN BROKEN ASPHALT 10111122 000182 8.740 TON 7.0000E Total: WASTE CLEAN BROKEN ASPHAL 8.74 TON Total: 1011112022 Total Invoice: 146.93 0.00 WASR% 0.00 148.93 187.09 0.00 WASR% 0.00 167.09 126.56 0.00 WASRb 0.00 126.56 440.58 0.00 0.00 440.58 440.58 0.00 0.00 440.58 61.18 0.00 WASH O.00 61.18 61.18 0.00 0.00 61.18 61.18 0.00 0.00 61.18 501.76 0.00 0.00 S01.76 0t()'-t0-q0o gl.w Payment Type: On Account ,,,,,,,,,""" 1t� 130 Pay Terms NET 30 DAYS yy �• - 1� l Il%jZ Total: 501.76 FA Sheet No.: RR3 DAILY REPORT OF FORCE ACCOUNT WORKED-�!NT Project Name: Downey Side Channel Project No: 18-3007.1 Item No.: Change Order # 6 Date: 10/19/2022 Description of Work: Excavate roadway to explore sub grade Work by Subcontractor?: NO Prime Contractor: Olson Brothers Sub -Contractor: LABOR STRAIGHT TIME OVERTIME DOLLAR NAME CODE OCCUPATION Hrs Hourly Rate Hrs I OT Rate AMOUNT 1J. Pierson Foreman 4I 88.94 $ 355.76 1 D Stockmeyer Laborer 63.12 $ IG. Sorenson Foreman 83.21 $ $ $ $ SUBTOTAL - LABOR: $ 355.76 LABOR OVERHEAD & PROFIT @ 31 % $ 110.29 LABOR TOTAL $ 466.05 EQUIPMENT EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR Equipment # Equipment Description Hrs I Hourl,r Rate Hrs Standby Rate AMOUNT 27 KW-F550 51.75 4 11.39 $ 45.56 131 Cat-308 excavator 4 91.97 $ 367.88 45 KW Dump Truck 114.36 $ - SUBTOTAL - EQUIPMENT $ 413.44 EQUIPMENT OVERHEAD & PROFIT @ 21% $ 86.82 EQUIPMENT TOTAL $ 500.26 MATERIALS/SERVICES/RENTALS MATERIALS / SERVICES Quantity I Units Unit Price DOLLAR AMOUNT $ $ $ SUBTOTAL $ OVERHEAD & PROFIT @ 21% $ TOTAL $ - Verification of Hours Worked: TOTAL: $ 966.31 12% MARKUP (for prime when subcontract work) $ - ameh Byneluma N..Gyp.gq.oromtlwn.rct a'ann py, Irw.', CN•Bryu 9unai Bryce Sturrock " �"I�"YYaY SHEET TOTAL: $ 966.31 Contractor's Representative ate:,:o w" Ev,aVe Jhf oar Date 12/2/2022 Owner's Representative Pay Estimate Entered: Date: By: Job Name Downey Date 10/1912022 Force Account No 01040-9010-3 Olson Brothers Excavating, Inc. OBE Job No. 1304 FORCE ACCOUNT Description of Extra Excavated down found wood and garbage debris under road at 3' Work: Name I Trade I REG I OT I UOM I Reg Rate OT Rate 1.5 Total 1.PIERSON FM A MR I 88.44 3SS-75 I I I MR I o 0.00 _ I 0.00 j I I MR 0 I 0.00 I I I I MR I 0 1 I 0.0 I I I I 1 Mn ( 0 I ( 0.01) LABOR TOTAL1 $355.75� Equlp iD I F.qulpment 0e"Mplion MRS I Rate I Total 49.5 FORO-F550-STANORY i 4 i 1139 + 45.% I 1311CAT•308 4 I 91.97 367.88 I 1 1 I I 0 I 0.00 j I 0 0.00 I I 0 0.00 I I 0 D.00 1 I I D 0,00 1 0 I 0.00 EQUIPMENT TOTALI $413.441 I Vendor _ Description UOM I Units 1'nce I !owl I 1 I I 0.00 I 0-00 0.00 I 0.00 I 0,00 I I 0.00 I 0.0o _ I 0.00 I I MATERIAL TOTALI $0.001 Submnlraclor Description UnRs Total I 1 � � I 0.00 I I I o.00 I 1 0.00 1 I l I 0.00 t I I 0.00 I SUBCONTRACTOR TOTAL so.OoJ Labor Sub[oWi 355J5 Material Subtotal 31R 110.28 21.00% D00 Labor Tulal 466.04I ... Material Total -.. 0.00 Equrprnent Sautotal 413.44; .. Subcontractor Subtotal . __... _..._-._-_,._ 0.00 21.00% 86.821 12.00%I 0.00 Equipment Total l 500.26 Subcontractor Tell o,00l ADDITIONAL WORK DAYS 2 70TAt FORCE ACCOUNT $966.30 FA01040.9030.3 FA Sheet No.: RR4 DAILY REPORT OF FORCE ACCOUNT WORKED Project Name: Downey Side Channel Project No: 18-3007.1 Item No.: Change Order # 6 Date: 10/26/2022 Description of Work: Excavate roadway install fabric and crushed rock Compact crushed rock Work by Subcontractor?: NO Prime Contractor: Olson Brothers Sub -Contractor: LABOR STRAIGHT TIME OVERTIME DOLLAR NAME CODE OCCUPATION Hrs Hourly Rate Hrs I OT Rate AMOUNT J. Pierson Foreman 2 88.94 $ 177.88 J. Fordham Operator 8 86.65 $ 693.20 K. Pentin operator 8 86.651 $ 693.20 Truck Driver 8 83.211 $ 665.68 Truck Driver 7 83.211 $ 582.47 $ SUBTOTAL -LABOR: $ 2,812.43 LABOR OVERHEAD & PROFIT @ 31 % $ 871.85 LABOR TOTAL $ 3,684.28 EQUIPMENT EQUIPMENT OR ATTACHMENTS OPERATED I STANDBY DOLLAR Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT 27 KW-F550 2 51.751 I $ 103.50 131 Cat 308 excavator 6 91.97 $ 551.82 45 KW Dump Truck 7 114.36 $ 800.52 47 Super Solo 8 114.36 $ 914.88 407 Cat 420D 2 61.17 $ 122.34 SUBTOTAL -EQUIPMENT $ 2,493.06 EQUIPMENT OVERHEAD & PROFIT @ 21% $ 523.54 EQUIPMENT TOTAL $ 3,016.60 MATERIALS/SERVICES/RENTALS MATERIALS / SERVICES Quantity Units Unit Price DOLLAR AMOUNT Washington Rock Inv # 68256 1 LS $ 1,416.64 $ 1,416.64 SUBTOTAL $ 1,416.64 OVERHEAD & PROFIT @ 21% $ 297.49 TOTAL $ 1,714.13 Verification of Hours Worked: TOTAL: $ 8,415.01 12% MARKUP (for prime when subcontract work) $ - �WY� b%w eemr. t t r R t , Bryce Sturrock oEz=�~�� SHEET TOTAL: $ 8,415.01 Con rac o s epresen a ive Owner's Representative " aSo4 BYYant Date12/2/2022 Pay Estimate Entered: Date: By: ki Job Name Downey Date: 10/2612022 Force Account No 01040-9010.4 Olson Brothers Excavating, Inc. OBE Job No. 1304 FORCEACCOUNT Description of Extra Over ezaavaled. Place and compact. Prep for asphalt Work: Name lratle REG. OT UDM Res Rate TO__' Rate 1.5 Total I__ 1.PILRSDN FM �...m..-._.__.�.-.�-._. 2 HR 88.94 177,98 I 11.FORDHAM OPGR2 8 PR I SEA 693.23 I �K.PENTIN OPGR2 8 HR 86.65 693.23 I TD 8 NR 83.21 665.69 I TO 7 HR 83.21 582.48 HR 0 0.00 NR 0 0.00 1 LABOR TOTAL $2,812.511 Equip lb Equipment Deuription HR5 Rate I total 49 FORU-F550 2 51.75 I 103.50 131 CA F.308 6 91.97 I 55Fall 407 CAT-420p 2 61.17 122.34 1 47ISUPER SOLO 8 114.36 I 914.88 I 45 KW -DUMP TRUCK 7 114.36 800.52 t 0 0.00 l 0 0.00 I 0 I 0.00 I EQUIPMENT TOTAL $2,493.061 I Vendor Uescrip[ion I UOM Units Price Tolat jWASNINGTONROCK INV.6825ti I LS i 1; 116.64 t,416.64 t 1 I I Sotxnntractor I D-spoon Labor Subtotall 2,812.51; 31% 871.88i Lab., total 3,684.38; Equipment Sutholall 2,493.06 21.00% 523.54 Equ phh, rotas, 3,016.60 ADDITIONAL WORN DAYS I FA03040-9010.4 0.00 0.00 0.00 I 0.00 0.00 I 0.00 I I 000 I MATERIAL TOTAL $1,416.64! UMts Price 7ptal 0.00 1 0.00 0.00 1 1 0.00 I o.oD I SUBCONTRACTOR IOTALI $0.00! Material Subtotal 1.416.64 21.00% 297..191 Material Total 1,714,13 -- Subcontract�rSubtotal 0,001 12.00Y< 000 I Subcontractor Total _ 0.D0'; TOTAL FORCE ACCOUNT $8.415.12 OLSON BROTHERS EXCAVATING, INC. Na 102928 6622 112th St. E., Puyallup, WA 98373 (253) 770-3844 Fax (253) 770-3a45 DATE 10 �7 NAME ADDRESS I /7 II 3 0 Y Job Locations Start Tune V' G Lunch 9 _ Stop Time '3 v -d� Load tea] No. Material Time Quantity No. Material Ouanttty V 1 1 S 21 %ri Zaj, 16 1 Zti Z'Q7; 17 31 II'.ZPII 16 I 1 41 I y 1-5413� 19 1 5 1 I 1 20 1 6 1 121 71 I I 1221 ro yo 61 I 1 1231 I 91 1 1241 I 101 I 1 1251 I 11 1 I 1 1261 121 1 1 1271 I 131 1 1 1281 1 141 1 1291 151 I 1 Truck No.: 4 S 1301 Truck Charges: Truck Type: Sn 1 Drver Charge: Truck Rate: 1 Sub Total: Truck Hours: 1-Add Charges: Driver Hours: 1 Total Charges: Signature: •Terms Net 10th, 1.5% billing charge on all accounts past due. OLSON BROTHERS EXCAVATING, INC, Na 17U636 6622112th St. E., Puyallup, WA 98373 (253) 770-3844 Fax (253) 770.3645 DATE r/ ✓ NAME ���/// ADDRESS ��'��L 7 I �r'✓ ^'`� Job LooMlon G V ( t C-0 Start Tima ' Cl-) Lunch Stop Time-Z-, Load toad No. Material Time ouantky Load toad No. Matedal Tyne ouanft 1 16 2 �� 17 3 18 4 19 II 5 ii ifl 20 6 21 7 22 9 24 10 25 11 26 12 27 13 26 14 29 15 30 Truck No.: y 7 Truck Charges: Truck Type: SN �� Driver Charge: Truck Rate: Sub Total: Truck Hours: *Add Charges: Driver 1J..7711_ Total Charges: Signature: "Terns Net 10th, 1.5% billing charge on all accounts pest due. ERRIEEwir- ENTIT-MING'T�N Washington Rock Quarries Po Box 250 OnIng WA 98360 2S3262.1661 OLSON BROS EXCAVATING 6622 112TH 5T E PUYALLUP, WA 98373 .I• Customer ID Pavment Terms 397 NET 30 DAYS INVOICE p INVOICE DATE BATCH # 68256 10/31/2022 103122 PURCHASE ORDER: ORDER DELIVERED 70: ORDER DESCRIPTION: 522 - P/U PRICING - OLSON BROS EXCAVATING 560372 OB45 ICV26/2022 4"-8"QUARRY SPALLS 29A4 Ton $15.25 $0.00 $471.04 560401 OB45 10/26/2022 4%8"QUARRY SPALLS 28.73 Ton $15.25 $0.00 $459.68 $60438 OB45 10/26/2022 4%8"QUARRY SPALL5 30,37 Ton $15.25 $0.00 $485.92 4"•8"QUARRYSYAI S/Kopowsin Quarry/Kapowsin Quarry: 88.S4 Ton 1WLA �bLO-6AOD N.OFTICKETS TOTALNETQUANT(TY MATERIALAMOUNT PREIGHTAMOUNT SURC ARGEAMOUNT 3 88.54 $1,350.23 $0.00 $66.41 ijyou have any questions about billing please SUBTOTAL $1,416.641 contact us. We appreciate your businessl TAX $0.00 TOTAL $1,416.641 FA Sheet No.: RR5 DAILY REPORT OF �_T FORCE ACCOUNT WORKED `../ Project Name: Downey Side Channel Project No: 18-3007.1 Item No.: Change Order # 6 Date: 10/27/2022 Description of Work: Load out spoils from excavation Spread out spoils on site Work by Subcontractor?: NO Prime Contractor: Olson Brothers Sub -Contractor: LABOR STRAIGHT TIME OVERTIME DOLLAR NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT J. Pierson Foreman 1 88.94 $ 88.94 J. Fordham Operator 86.65 $ - K. Pentin Operator 8 86.65 $ 693.20 Truck Driver 5.5 83.21 $ 457.66 Truck Driver 83.21 $ _ $ SUBTOTAL -LABOR: $ 1,239.80 LABOR OVERHEAD & PROFIT @ 31% $ 384.34 LABOR TOTAL $ 1,624.14 EQUIPMENT EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR Equipment # Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT 27 KW-F550 1 51.75 $ 51.75 131 Cat-308 excavator 2 91.97 $ 183.94 45 KW Dump Truck 5.5 114.361 $ 628.98 47 Super Solo 114.361 $ - 308 Cat 930K 6 87.451 $ 524.70 SUBTOTAL - EQUIPMENT $ 1,389.37 EQUIPMENT OVERHEAD & PROFIT @ 21% $ 291.77 EQUIPMENT TOTAL $ 1,681.14 MATE RIALS/S ERVICES/RENTA LS MATERIALS / SERVICES Quantity Units Unit Price DOLLAR AMOUNT $ $ $ $ $ SUBTOTAL $ OVERHEAD & PROFIT @ 21% $ TOTAL $ - Verification of Hours Worked: TOTAL: $ 3,305.28 12% MARKUP (for prime when subcontract work) $ - B ce Stock ry urrSHEET TOTAL: $ 3,305.28 Contractor's Representative ° pzpo,w �� /y� Owners Representative �/1 an" Data 12/2/2022 Pay Estimate Entered: Date: By: Job Name Downey Date- 1012712022 Olson Brothers Excavating, Inc. OBE Job No- 1304 Forte Account No 01040-9010.5 FORCEACCOUNT Urscription of Extra Load out material from excawitfon. Spread remaining material onsue. Site cleanup Work: ame R8G Reg 0T Rate 1.5 Total I �._U,1 K.PENI13ry O GH2 8665e 693.2I ITU I 5.5 HR 83,11 457,67 I I HR 1 0 0.00 I HR 0 0.00 I HR O 0.00 I I HR 0 0.00 I LABOR TOTAL $1,239.831 Equip ID Equipment Description I HRS I Rate Total 1 I 49 F0RD•E550 I I I 51.75 53.75 I 131 CAT308 2 I 91.97 183.94 1 308 CAT-930K 6 1 87.41 524.70 I 45 KW -DUMP TRUCK 5.5 1 114.16 628.98 I 0 0.00 0 0.00 0 I 0.00 I 0 I 0.00 1 EQUIPMENT TOTAL $1,38937,1 Vendor Description DOM unit. Price 'Total i 0.00 0.00 I 0.00 1 0.00 0.00 I 0.00 I I 0 00 0.00 I 0.00 I 1,konvaclor Description I I Lah4r Subtotal 1,239.83' 31% 384.35 Labor Total 1,624.10 Equipment Subtotal 1,389.37 21.00% 291.77 Equipment total 1,681.14 ADDITIONAL WORK DAYS I FA01040-9010-5 MATERIAL TOTALI Units Price Total j I O.Oo o.DO I O.DO I 0.00 o.00 I SUBC0NTNALT0R T0TAL $O.00I Material Subtotal u011 21.00% 0.00 Matenal Total 0.00 Subcontractor Subtotal 0A0 12.00% 0.00 5ubcoul-tor Total 0.00 TOTAL FORCE ACCOUNT 53 OLSON BROr1ERS EXCAVATING, INC. No 102932 6622 112th St. E., Puyallup, WA 98373 (253) 770-3844 Fax (253) 770-3845 DATE NAME v I3 i� ADDRESS I &Lu I—LAa Job Location I / 6 (' start Time 7 c u Lunch k, stop Time 17.'' 5G . Load Load Load Load No. Meter' Time DuaneN No. Material Time Duantlly 1 � z 6 � � 2 17 3 18 4 19 5 20 6 21 7 / 22 JOYD - %P/(7 & rF4. 8 23 9 24 10 25 11 26 12 27 13 28 14 29 15 30 Truck No.: �j Truck Charges: Truck Type r% Driver Charge: Truck Rate: Sub Total: Truck Hours: S. S 'Add Charges: Driver Hours: Total Charges: Signature: *Terms Net 10th, 1.5% billing charge on all accounts past due. DAILY REPORT OF FORCE ACCOUNT WORKED Project Name: Downey Side Channel Item No.: Change Order# 6 Description of Work: Paving Frager Rd /FA Sheet No.: RR6 KENT Project No: 18-3007.1 Date: 10/31 /2022 Work by Subcontractor?: NO Prime Contractor: Olson Brothers Sub -Contractor: LABOR STRAIGHT TIME OVERTIME DOLLAR NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT J. Pierson Foreman 8 88.94 $ 711.52 J. Fordham Operator 86.65 $ _ K. Pentin Operator 8 86.65 $ 693.20 Truck Driver 83.211 1 $ _ Truck Driver 83.211 1 Is I I Is - SUBTOTAL -LABOR: $ 1,404.72 LABOR OVERHEAD & PROFIT @ 31 % $ 435.46 LABOR TOTAL $ 1,840.18 EQUIPMENT EQUIPMENT OR ATTACHMENTS I OPERATED STANDBY DOLLAR Equipment # Equipment Description li Hrs Hourly Rate Hrs Standby Rate AMOUNT 27 KW-F550 8 51.75 $ 414.00 131 Cat-308 excavator 91.97 $ _ 45 KW Dump Truck 114.361 $ 47 Super Solo 1 114.361 Is _ 1 308 Cat 930K 1 87.451 1 Is SUBTOTAL - EQUIPMENT $ 414.00 EQUIPMENT OVERHEAD & PROFIT @ 21% $ 86.94 EQUIPMENT TOTAL $ 600.94 MATERIALS/SERVICES/RENTALS MATERIALS / SERVICES I Quantity Units Unit Price DOLLAR AMOUNT Asphalt Patch Inv # 52798 1 LS $ 14,100.00 $ 14,100.00 $ j Is - I Is SUBTOTAL $ 14,100.00 OVERHEAD & PROFIT @ 21% $ 2,961.00 TOTAL $ 17,061.00 Verification of Hours Worked: TOTAL: $ 19,402.12 12% MARKUP (for prime when subcontract work) $ - Bryce Sturrock a,._,_..,._'"°`�" Contractor's Representative o: SHEET TOTAL: $ 19,402.12 Owner's Representative (]7ZM &- ad Date 12/2/2022 Pay Estimate Entered: Date: By: Job Name Downey Date. 10131i2022 Force Accounl No 01040.9010-6 Olson Brothers Excavating, Inc. 013E Job No 1304 FORCEACCOUNT Description of Extra Onsite paving road and trail Work Name Trade REG OT UOM Reg Rate OT Rate 1.5 �Totat I.PIERSON FM 8 HR 88.94 711.51 IK.PENTIN OPGRZ 8 HR 86,65 I 693.23 I j HR 0 0.00 I HR 0 000 I j HR 0 0.00 HR 0 0.00 I I I HR o I 0.00 I LABOR TOTAL $1,404.731 Equip ID I Equipment Desalpt— I HRS Rate Total I I 491FORD-FS50 A 51.75 414.00 1 I 0 I 0.00 0,00 I I 1 0 1 0.0o I j 0 0.00 0 0.00 o 0.o0 j 1 1 1 j 0 I 0.00 I I EOUIPMENt TOTAL $414.001 Vendor bclariplon I UOM I Units Pncc f Total IASPHALT PATCH IINV. 5279R ( LS I 1 I 18,800.W II 18,am 000100 0j I I I I 0.00 I I 000 I 0.00 a 00 I 0.00 I I I I o.00 I MATERIALTOTA4 s18,8tt0.001 Subcontractor Description I Units I Price I total I { I 0.00 I 1y 0.00 o 00 I I I o.00 I I 0,00 I SUBCONTRACTOR fOTA0 $0.001 Labor Subtotal 1.404,73; Material Subtotal 1.00 31% 43S.47'- 21.00, 3.9483.948.W Labor Total 1,$40.20. Material Total 22,748.00 Equipment Subtotal Subtotal 0.00 2 1.00% 8G.9a 12.00% 000 Equipment Total 500.94 Subconvactor Total 0.00 ADDITIONAL WORK DAYS 1 , TOTA`l FORCE ACCOUNT $25,089.34 FA01040.9010.6 ASPHALT PATCH SYSTEMS INC 8012 CANYON ROAD EAST PUYALLUP, WA 98371 253 536.2690 Bill to: OLSON BROTHERS EXCAVATING, INC 6622 112TH STREET E PUYALLUP, WA 98373 Invoice 52798 Job: Invoice x: 52798 Date: 10/31/22 Customer P.O. r: FRAGER AVE ........................................................ ........ FRAG ... _.. _.___.... .... ., r Payment Tenns: NET 30 DAYS Salesperson: BILL SETZER Customer Code: OLSBRO Remarks: CONCRETE PAVING 2'X90Y@6" 4,700.00 ASPHALT PAVING 2,725 SF 14,100.00 1.5% monthly finance charge assessed on past due invoices. Total: 18,800.00 Current Due: 18,800.00 16ia�o-AID Fs, OL�o P" Ds1.: 10/31122 Pea.. 1 FA Sheet No.: RR7 DAILY REPORT OF FORCE ACCOUNT WORKED Project Name: Downey Side Channel Project No: 18-3007.1 Item No.: Change Order # 6 Date: 10/31/2022 Description of Work: Placing 1/4 minus along new paving Work by Subcontractor?: NO Prime Contractor: Olson Brothers Sub -Contractor: LABOR STRAIGHT TIME OVERTIME DOLLAR NAME CODE OCCUPATION Hrs I Hourly Rate Hrs OT Rate AMOUNT J. Pierson Foreman 6 88.94 $ 533.64 J. Fordham Operator 86.65 $ - K. Pentin Operator 6 86.65 $ 519.90 Truck Driver 3 83.21 $ 249.63 Truck Driver 83.21 $ - $ SUBTOTAL -LABOR: $ 1,303.17 LABOR OVERHEAD & PROFIT @ 31% $ 403.98 LABOR TOTAL $ 1,707.15 EQUIPMENT EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR Equipment # Equipment Description Hrs I Hourly Rate Hrs Standby Rate AMOUNT 27 KW-F550 6 51.75 $ 310.50 131 Cat-308 excavator 91.97 $ - 31 KW Dump Truck 3 114.36 $ 343.08 47 Super Solo 114.36 $ - 308 Cat 930K 6 87.45 $ 524.70 SUBTOTAL -EQUIPMENT $ 1,178.28 EQUIPMENT OVERHEAD & PROFIT @ 21% $ 247.44 EQUIPMENT TOTAL $ 1,426.72 MATERIALS/SERVICES/RENTALS MATERIALS / SERVICES Quantihr Units Unit Price DOLLAR AMOUNT MSA Invoice 14.34 LS $ 16.00 $ 229.44 I` $ $ $ SUBTOTAL $ 229.44 OVERHEAD & PROFIT @ 21 % $ 48.18 TOTAL $ 277.62 Verification of Hours Worked: TOTAL: $ 3,410.49 12% MARKUP (for prime when subcontract work) $ - �aw.wem �mEdeer. . C=uS E=Mcee@aiuMmNen reel, O=YMean Bryce u rrocStk a wew SHEET TOTAL: $ 3,41 U.49 Contractor's Representative o..:�z�� Jasm yan� 12/2/2022 Owner's Representative ( Date Pay Estimate Entered: Date: By: Job Name OowneY Date. 11/2/2022 Olson Brothers Excavating, Inc. OBE Job No, 1304 Fofce Account No 010400010.7 FORCE ACCOUNT ---- OescripU.. of Extra Place 1f4" minus along new paving. 8acklill along paving edges Work: -- I Trade I PEG OT UOM I Reg Rate OT Rate 1.5 I Total I1.PIERSCNName FM I 6 HR I 88.94 533.63 I IK.PCNTIN OPGR2 I 6 HR + 86.65 + 51%92 I I TO I 3 HR I 83.21 I 249.64 I HR 0 0.00 I HR 0 000 I FIR I 0 0.00 i HR 0 0.00. t IABORTO'TAL $1,303,191 I Equip ID Equipmenl Description HRS Rate I 1o1a1 I 49 EORO-ESso I 6 51.75 1 310.50 1 l 308 CAI-910K 6 87.45 I 124.70 I I 31 KW -DUMP TRUCK 3 114.36 I 343.08 I 0 I 0. DO 0 I 0.00 l 0 I I O:00 I 0 .00 I 0 0.000 Oj_ $1,178.281 Vendor I 0¢SCfipli0n I UDM is Pri[¢ TUlal I IMSA 193507 I TON 14.34Um16.00 229.44 I IINV 0 DO I 0.00 I 0.0 I � D.000 1 0.00 1 0.00 1 BOO l 0.00 MATERIALTOTAL $229.44! I Subcontractor D,scriplion 1 Units Price Total I I I 0.00 I 0.00 i I I 0.00 1 I I I 0.00 I I DOB I l SUBCONTRACTOR TOTAL $0.00! 1,303,19 Mata,W Subtotal 229.44! Labor Subtotal 31% 40399 11.ERT%. 48.18i Labor fotal� 1,707.17 Material Total 277.62I Equipmenl Subtotal 1,278.28 Subs-1011a1 Subtotal DOD 21.00% 247.44 12 GO% 0.001 -, Equipment Total --_ 1,425.72 Suocontfactor iq[al 0.00 ADDITIONAL WORK DAYS 1 TOTAL FJ-ORCE ACCOUNT $3,410.51 FA03040-9010.1 OLSON BROTHERS EXCAVATING, INC. N ! 102063 6622 112th St. E., Puyallup, INA 98373 (253)770-3844 Fax(253) TW-U45. DATE I I NAME ADDRESS KGrn Job Locatlon Start Time G a /T Lunch Stop Time p 30 Load Load Load I Load r No. Material Time Juan Na. Matedat TWM I Quan 2 17 3 18 4 19 1 5 20 1 6 21 I 1 7 22 8 23 L 9 24 10 25 11 26 1 12 27 13 28 14 29 15 30 1 Truck No.: Truck Charges: Truck Type: S,)La Driver Charge: Truck Rate: Sub Total: Truck Hours: o, 1 S 1 •Add Charges: Driver Hours: Total Charges: Signature: `Terms Not 10th, 1.5% billing charge on all accounts past due. Invoice Mountain Stone Aggregate, LLC �'` 30211 State Route 507 S. MSARoy, WA 98580 F Date Invoice 4 I t/I/2022 193507 Bill To Pit Location Olson Brothers Excavating, Inc. C&V PIT 6622 1121h St. E. ROY, WA Puyallup, WA 98373 - P.O. Number F.O.B. FRoy Date Term O 1304 Downy Farmslead I I H/p/2022 I Net 30 I I2/1/ 022 Quantity U/M Description Price Each Ticket Number Amount 14.34 TN 114" MINUS 16.00 190466778 229.44 136`� 1/60� 7l/l `►�W O�y'"` ► 1115IZ2 l/ Phonek 360.972-0845 I Total $229.44 All past due amounts will accrue a late charge at the annual percentage rate (18%) (1.5% per month). Bryant, Jason From: Bryant, Jason Sent: Thursday, October 20, 2022 7:59 AM To: Bryce Sturrock Cc: Joni Dombrowski; Harris, Josh Subject: RE: Downey- Road Repair Bryce, The HMA is 4" thick. You can also use only CSBC if John prefers. Thank you, Jason Bryant, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5541 1 Cell 253-261-5663 JBrvantCcbKentWA.gov CITY OF KENT, WASHINGTON KentWA.gov Facebook z YouTube From: Bryce Sturrock <bryces@olsonbrothers.net> Sent: Wednesday, October 19, 2022 3:25 PM To: Bryant, Jason <JBryant@kentwa.gov> Cc: Joni Dombrowski <jonid@olsonbrothers.net>; Harris, Josh <JHarris@kentwa.gov> Subject: RE: Downey- Road Repair Afiffikww No questions at this time, I believe they have been answered. - Quarry rock — WA Rock 4 x 8 - Fabric — soil separating geotextile (woven) like what we would use in construction entrance. - CSBC and or CSTC for the top layer (asphalt base) Was the asphalt thickness established? Assuming HMA CL. %" Thank you, 6622 sit^ St. F., Puyallup, WA. 08373 Office: f253j 774-3844 r= (253M 770•3845 -Dr4ce Stt4rrock 1 Cell; (253)-3�i-3-4a50 �tmgil; I,r�'_Icesa�vlsov�l�rv-i�bters.�ie--r From: Bryant, Jason <JBrvant@kentwa.gov> Sent: Wednesday, October 19, 2022 3:14 PM To: Bryce Sturrock <brvices@olsonbrothers. net,> Cc: Joni Dombrowski <ionid@olsonbrothers.net>; Harris, Josh <JHarris@kentwa.gov> Subject: Downey- Road Repair Bryce, Today we potholed the sag in the roadway. We discovered organic material @ 6' deep. We had our Geotech stop by and have decided to excavate and remove the large organics. The area is 24' by 24' x 6' deep. We will place fabric and spalls in the lower 2'-3' then backfill with crushed rock and another layer of fabric. John is going to set up the trucking and get another machine with a hoe pack. We will track this work as force account including today. If you have any questions feel free to give me a call. Thank you, Jason Bryant, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5541 1 Cell 253-261-5663 JBrvant@KentWA.aov CITY OF KENT, WASHINGTON KentWA.gov Facebook YouTube PLEASE CONS?ER THE 04VIRON *FONT BEFORE PRINTING THIS E-MAIL Bryant, Jason From: Dahl, Melissa Sent: Friday, October 7, 2022 10:42 AM To: Connor, Eric; Bryant, Jason Cc: Maloney, Carla; Mactutis, Michael; Barry, Jason; Murillo, Alex Subject: Downey HMA Hello Eric, After internal discussions on the matter, it's our recommendation that we move ahead with Olson completing the road work with the updated quantities. Let me know if you need any support from me on this moving forward. Thanks, Melissa Dahl EIT, Environmental Engineerll Design Engineering I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-6511 1 Cell Phone 206-482-4461 MDahl(a)KentWA.aov CITY OF KENT, WASHINGTON KentWA.gov Facebook You'rube Instagra 1