HomeMy WebLinkAboutCAG2022-199 - Original - Washington State Dept Of Transportation (WSDOT) - Green River Bridge Deck Repair - 06/01/2022Stephen Lincoln Public Works
05/10/2022 05/17/22
08/17/2021
R20152
Federal
WSDOT Highways and Local Programs Grant: Non-Real Property
Original
Green River Bridge Deck Repair
Repair of the Bridge Deck on the Meeker Street Bridge over the
Green River
1,246,000 Other
Per directions from Highways and Local Programs, the Local Agency
Agreement and Prospectus are to be signed in blue ink.
5/11/22
CAG2022-199
5/13/22
Page 1
Revised /20
Local Agency Agreement
Agency
Address
CFDA No. 20.205
(Catalog Federal Domestic Assistance)
Project No.
Agreement No.
For WSDOT Use Only
The Local Agency having complied, or hereby agreeing to comply, with the terms and conditions set forth in (1) Title 23, U.S. Code
Highways, (2) the regulations issued pursuant thereto, (3) 2 CFR Part 200, (4) 2 CFR Part 180 – certifying that the local agency is not
excluded from receiving Federal funds by a Federal suspension or debarment, (5) the policies and procedures promulgated by the
Washington State Department of Transportation, and (6) the federal aid project agreement entered into between the State and Federal
Government, relative to the above project, the Washington State Department of Transportation will authorize the Local Agency to
shown herein on line r, column 3, without written authority by the State, subject to the approval of the Federal Highway Administration.
All project costs not reimbursed by the Federal Government shall be the responsibility of the Local Agency.
Project Description
Name Length
Termini
Description of Work
Project Agreement End Date Claiming Indirect Cost Rate
Yes NoProposed Advertisement Date
Type of Work
Estimate of Funding
(1)
Estimated Total
Project Funds
(2)
Estimated Agency
Funds
(3)
Estimated Federal
Funds
PE
%a. Agency
b. OtherFederal Aid
Participation
Ratio for PE
c. Other
d. State
e. Total PE Cost Estimate (a+b+c+d)Right of Way
%f. Agency
g. OtherFederal Aid
Participation
Ratio for RW
h. Other
i. State
j. Total R/W Cost Estimate (f+g+h+i)Construction
%k. Contract
l. Other
m. OtherFederal Aid
Participation
Ratio for CN
n. Other
o. Agency
p. State
q. Total CN Cost Estimate (k+l+m+n+o+p)
r. Total Project Cost Estimate (e+j+q)
DOT Form 140-039
Kent
220 Fourth Avenue South
Kent, WA 98032-5838
Green River Bridge Deck Repair 0.05 Miles
State Route 516, Russell Road
The project consists of providing surface repairs to the Meeker Street Bridge deck.
12/31/2025
105,000.00 105,000.00
100 Consultants 25,000.00 25,000.00
10,000.00 10,000.00
Consultants100
Local Agency Federal Aid
Project Prospectus
Route ( )
Federal Aid
Project Number
Local Agency
Project Number WSDOT Use Only
Date
DUNS Number
Federal Employer
Agency CA Agency
Yes No
Federal Program Title
20.205 Other
Project Title Start Latitude N
End Latitude N
Start Longitude W
End Longitude W
Project Termini From-To Nearest City Name Project Zip Code (+4)
Begin Mile Post End Mile Post Length of Project Award Type
Local Local Forces State Railroad
Begin Mile Point End Mile Point City Number County Number County Name
WSDOT Region Legislative District(s) Congressional District(s) Urban Area Number
Phase
Total
Estimated Cost
(Nearest Hundred Dollar)
Local Agency
Funding
(Nearest Hundred Dollar)
Federal Funds
(Nearest Hundred Dollar)
Phase Start
Date
Month Year
P.E.
R/W
Const.
Total
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width Number of Lanes
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
Local Agency Contact Person Title Phone
Mailing Address City State Zip Code
Project Prospectus
By
Approving Authority
Title Date
DOT Form 140-101
Revised 0 /20 Previous Editions Obsolete
( )
Page 1
Agency Project Title Date
Type of Proposed Work
Project Type (Check all that Apply)
New Construction
Reconstruction
Railroad
Bridge
Path / Trail
Pedestrian / Facilities
Parking
3-R
2-R
Other
Roadway Width Number of Lanes
Geometric Design Data
Description
Federal
Functional
Terrain
Posted Speed
Design Speed
Existing ADT
Design Year ADT
Design Year
Design Hourly Volume (DHV)
Through Route
Urban
Rural
NHS
Principal Arterial
Minor Arterial
Collector
Major Collector
Minor Collector
Local Access
Flat Roll Mountain
Crossroad
Urban
Rural
NHS
Principal Arterial
Minor Arterial
Collector
Major Collector
Minor Collector
Local Access
Flat Roll Mountain
Performance of Work
Preliminary Engineering Will Be Performed By Others
%
Agency
%
Construction Will Be Performed By Contract
%
Agency
%
Class I - Environmental Impact Statement (EIS)
Project Involves NEPA/SEPA Section 404
Interagency Agreement
Class III - Environmental Assessment (EA)
Project Involves NEPA/SEPA Section 404
Interagency Agreements
Class II - Categorically Excluded (CE)
Projects Requiring Documentation
(Documented CE)
Environmental Considerations
DOT Form 140-101
Revised 0 /20 Previous Editions Obsolete
Page 2
Agency Project Title Date
Right of Way
No Right of Way Needed
* All construction required by the
contract can be accomplished
within the exi ting right of way.
Right of Way Needed
No Relocation Relocation Required
Utilities
No utility work required
All utility work will be completed prior to the start
of the construction contract
All utility work will be completed in coordination
with the construction contract
Railroad
No railroad work required
All railroad work will be completed prior to the start of
the construction contract
All the railroad work will be completed in coordination
with the construction contract
Is any airport located within 3.2 kilometers (2 miles) of the proposed project? Yes No
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it’s
designee, and is not inconsistent with the agency’s comprehensive plan for community development.
Agency
ByDate Mayor/Chairperson
DOT Form 140-101
Revised 0 /20 Previous Editions Obsolete Page 3
King
Meeker Street Bridge Vicinity Map
Date: 12/16/2021 Notes:
The information included on this map has been compiled by King County staff from a variety of sources and is subject to change
without notice. King County makes no representations or warranties, express or implied, as to accuracy, completeness, timeliness,
or rights to the use of such information. This document is not intended for use as a survey product. King County shall not be liable
for any general, special, indirect, incidental, or consequential damages including, but not limited to, lost revenues or lost profits
resulting from the use or misuse of the information contained on this map. Any sale of this map or information on this map is
prohibited except by written permission of King County.±
Agency: City of Kent
Green River Bridge Deck Repair Cost
Item
QTY
Units
Unit Cost
Total Cost
Mobilization (10%)
1
LS
$ 70,000.00
$ 70,000.00
Grinding/surface prep/spot repairs
900
SY
$ 190.00
$171,000.00
Polyester Concrete Overlay
1
LS
$ 350,000.00
$ 350,000.00
Demo Cement Conc. Sidewalk
180
SY
$ 50.00
$ 9,000.00
Cement Concrete Sidewalk
180
SY
$ 80.00
$ 14,400.00
Inlet Grates
8
Each
$ 2,000.00
$ 16,000.00
Abutment Plates
2
Each
$ 5,000.00
$ 10,000.00
Traffic Control
1
LS
$ 30,000.00
$ 30,000.00
TESC
1
LS
$ 30,000.00
$ 30,000.00
Totall
$700,400.00
Total rounded to nearest $1k
$ 700,000.00
Base Construction Cost $700,000.00
20% of Base Construction for PE $140,000.00
18% 15% 10.0% Approx 5%Annual
I I Cost ICN Ene IContineencv IMobilization Ilnflation ITotal I
Total Construction Contract Cost $ 700,000.00 1 $126,000.00 1 $105,000.00 $ 70,000.00 $ 105,000.00 $1,106,000.00
Preliminary Engineering Cost Breakdown
Agency Staff Time $105,000.00 Remainder after Environmental Docuemnts and State Time
Environmental Document Preparation (Consultants) $ 25,000.00 Based on Prior Environmental Document Contracts.
State Staff Time $ 10,000.00 Order of Magnitude Estimate
Local Programs Authorization Package Checklist
Agency: city of Kent
Project Title: Green River Bridge Deck Repair
Fed Aid/State Project #:
By Phase (check all that apply)
Funding Request PL* PE** RW CN
New Phase Authorization El `�
Phase Modification I El El
Non -Funding Request
*PL - Planning. Used for stand-alone planning and study projects.
**PE - Preliminary Engineering. This is the full design phase of a construction project. Once PE is authorized,
Region HQ
the construction phase must be completed, or all federal expenditures must be repaid.
Agency Check Check
cellaneous Ite III
In addition to this checklist, all Region submittals must utilize the standard Region IDC, memo, or cover letter,
The agency's DUNS # is active and agency has not been suspended/debarred at SAM.gov?
If authorizing a subsequent phase on an existing project, has at least one bill for the prior phase been fully
processed in SPORT (Posted date is present)? If not, supplement can't be processed.
Has the scope changed (description of work, limits, staging, RW needs, etc.) since previous submittal? (Yes or No)
IVO
Project Prospectus (DOT Form 140-101) - LAG Chapter 21 _
Are all three pages of the current form included?
./
Does information (title, termini, description, RW needs, cost, etc.) agree with STIP/LAA/NEPA-CE?
Is the project description written such that the project scope is clear to an average person?
Are pages 1 and 3 signed?
Is page 1 signed by a CA Agency? If not, indicate below which Agency will serve as CA.
CA Agency: Backup documentation included?
Are the Latitude and Longitudes (in decimal format) included and correct?
Are Congressional and Legislative Districts included and correct?
Project Zip Code includes the +4?
Are estimated costs included for all phases of the project?
Are the Functional Classification and Urban/Rural designation correct?
Are the Right of Way, Utilities, and Railroad sections filled out? i
Sections & Vicinity Map - LAG Chapter 21
When necessary, are the Vicinity Map(s) and Roadway Section(s) included?
Can someone unfamiliar with the project's location easily tell where it's located using the vicinity map.,
Are the project limits clearly marked on the map?
Does the section include all elements, with dimensions, of the roadway prism?
Are section changes, if applicable, throughout the project limits noted/displayed?
STIP/Funding Documentation - LAG Chapter 12
Is the currently approved STIP page included? V
Does STIP information (termini, description, etc.) match the LAA and Prospectus? V
Is the phase being authorized (or a later phase) programmed in the STIP?
Is funding from all requested programs shown in the STIP?
Are the requested funds supported by the STIP? T
If funded through a HQ managed program (ex. Bridge, HSIP), is the award letter and project summary included
when these funds are first obligated?
If funded through a HQ managed program, does the submitted scope match the project summary scope?
Local Agency Agreement (DOT Forms 140-039 & 140-041) - LAG Chapter 22
Is at least one LAA or LAA supplement, with an original signature, included? I/
Current form used? (check revision date at bottom left) V
All pages of Agreement included?
Are the Agency information, Project #, LAA #, Supplement #, and date of original agreement execution correct?
Does project information (title, termini, length, description, etc.) agree with STIP/Prospectus/NEPA-CE? V
Local Agency Agree nt (DOT Forms 140-039 & 140-041) - LAG Chapter 22 [CONTI
Authorization Package Checklist (May 2019) WSDOT/Local Programs 1 of 2
Local Programs Authorization Package Checklist
Is the reason for supplement accurate and up to date?
Is the Project Agreement End Date (month, day, and year) included? Does it follow LAG guidance?
When not authorizing a new phase, is the end date the same as shown on the previous agreement?
If not, is adequate justification (see LAG 22.3) included to support changing the end date?
Is the Advertisement Date (month, day, and year) included? Is it within 6 weeks of estimated CN authorization?
If the ICR box is checked 'Yes', is the agency's current approved/self-certifed rate documentation provided? It
must clearly shown the rate used, timeframe it covers, and the actual signature of approval/self-certification
If corrections made, are they initialed? If made by WSDOT is permission from Agency provided?
Are all federal aid participation ratios being used listed?
Are amounts calculated correctly and shown in the correct columns?
Documented Cost Estimate - LAG 22.4 and Appendix 22.56
Is a Documented Cost Estimate included for each phase requesting/changing funds?
Are total dollars on the LAA supported by the phase estimates?
Does the estimate sufficiently demonstrate how the costs were determined?
If historical percentages are used for PE/CE estimates, are the percentages reasonable and supported?
Right of Way - LAG Chapter 25
If authorizing RW, is a project funding estimate/true cost estimate summary sheet included?
Does the PFE/TCE summary sheet support RW amounts shown on the LAA?
If authorizing RW and Relocation is required, is the signature page of the approved Relocation Plan included?
If authorizing CN, is the HQ approved RW Certification included?
RW acquired under the Government Acquisitions Provisions? Documentation included or noted in SPORT?
Environmental Documentation/Approval (NEPA) - LAG Chapter 24
Is an approved NEPA package (at least signature page) included?
Does the description of work match the Prospectus/LAA/STIP?
Is the footprint of the project within the limits of the NEPA approval?
Do the NEPA-CE Part 3 RW responses agree with the STIP and Prospectus?
Is the approval date within the last 3 years?
If approval is older than 3 years, has the approval been re-evaluated by the Environmental group?
Contracting - DBE Goals (LAG Chapter 26) - Tied Bid (LAG Chapter 44) - Local Forces (LAG Chapter 61)
If authorizing construction, is the DBE goal letter/e-mail included, or are the goals in SPORT?
If construction includes a tied bid project, is the approved PIF included or noted in SPORT?
If construction by Local Forces, is the approved PIF included or noted in SPORT?
PROJECT NOTES (Provide additional information or explanation as necessary)
This check -list would be for the Preliminary Engineering phase of work,
As no full -depth replacement or section changes are included in the scope of this project, typical section
drawings are not applicable.
This check -list is not for a supplement and there is no prior agreement.
This project is not claiming the Indirect Cost Rate.
This project proposes no right-of-way acquisition.
A NEPA Package has not yet been prepared for this project and will be provided with future LAA
agreement package for authorization of Construction Funds.
DBE Documentation will be provided with future LAA agreement package for authorization of Construction
Funds.
Authorization Package Checklist (May 2019) WSDOT/Local Programs 2 of 2
July 15, 2021
Mr. Chad Bieren
Public Works Director
City of Kent
220 Fourth Avenue South
Kent, WA 98032-5838
Green River Bridge
FFY 2021 Local Bridge Program Selections
Federal Funding
Dear Mr. Bieren:
WSDOT is pleased to advise you that the above-mentioned bridge project was recently
selected to receive funding through the Local Bridge Program. The federal funding is
limited to the amount shown below:
Green River Bridge $1,484,320
Scope: Deck Repair
NOTE: This project requires a 13.5% local match during the preliminary engineering/design
and right of way phases. Projects that authorize construction by December 2024, are eligible
for 100% federal funding for eligible costs. If construction is authorized after December 2024,
13.5% local match is required. Preventative maintenance projects are limited to a maximum
$3 million.
In order to meet state and federal requirements, the following are required:
Project expenditures incurred before receiving notice from Local Programs of federal
fund authorization are not eligible for reimbursement.
Please refer to the Local Programs webpage for detailed information, including:
(http://www.wsdot.wa.gov/localprograms/)
Local Agency Guidelines (LAG) manual for the requirements regarding
programming, authorization, reimbursement, etc.;
Projects utilizing federal funds must be included in your current
Transportation Improvement Program (TIP) as a complete programmed
project. Once your TIP amendment is approved, WSDOT will amend the
Statewide Transportation Improvement Program (STIP);
Funding and billing forms;
Quarterly Project Reporting is required to be completed by the end of March,
June, September, and December each year. To access the database you will
need an account name and password. Your account name is Kent and your
password is Kent291. The password is case sensitive.
If the project is not actively pursued, or becomes inactive (23 CFR 630), the project
is at risk of being cancelled, funds repaid and reprogrammed.
Chad Bieren
Public Works Director
City of Kent
Green River Bridge – Deck Repair
July 15, 2021
FHWA requires that all projects are ADA compliant upon completion or the federal
funds must be repaid.
As a reminder, Local Programs requires all agencies to submit monthly progress billings to
ensure timely reimbursement of eligible federal expenditures. Also, it is critical that your
agency adhere to the project schedule previously provided, to ensure the delivery of the local
federal program.
For assistance please contact Mehrdad Moini, your Region Local Programs Engineer, at
206.440.4734.
Sincerely,
Stephanie Tax
Interim Director
Local Programs
SJT:sas
cc: Kelly McGourty, Transportation Director, PSRC
Mehrdad Moini, Northwest Region Local Programs Engineer, MS NB82-121
1 of 3
Puget Sound Regional Council
Transportation Improvement Program
Application
New Project Request
Green River Bridge Deck Repair
Submitted December 17th, 2021 9:19 AM
Wsdot Pin N/A
Sponsoring Agency
Sponsoring Agency Kent
Ca Sponsor N/A
Project Contact Person
Contact Name Stephen Lincoln
Email Address SLincoln@kentwa.gov
Phone Number 12538565552
Project Description
Project Title Green River Bridge Deck Repair
Project Description The project consists of providing surface repairs to the Meeker
Street Bridge deck.
Regional Transportation Plan Status Approved
Regional Transportation Plan ID N/A
Location
Location Meeker Street
County King
City Kent
Crossroad/landmark nearest to the beginning of the project State Route 516
Crossroad/landmark nearest to the end of the project Russell Road
Map File Name Mee ker_Street Bridge_Map.pdf
Improvement Type
Primary Improvement Type
Bridge Rehabilitation
Secondary Improvement Types
N/A
Functional Classification
Functional Class Name
16 Urban Minor Arterial
Programming
2 of 3
Planning:
None
Preliminary Engineering
Category
Funding Source
federal
NHPP
local
Local
Right of Way: None
Construction
Category Funding Source
federal NHPP
local Local
Other: None
Estimated Obligation Date Amount
February 1st, 2022 $123,348.00
February 1st, 2022 $16,652.00
$140,000.00
Estimated Obligation Date Amount
February 1st, 2024 $974,449.00
February 1st, 2024 $131,551.00
$1,106,000.00
Grand Total: $1,246,000.00
Secured Funding File Name Kent Green_River_Bridge_Deck Repair_vlp.pdf
Secured Funding Explanation Award letter for the Local Bridge Program Grant.
Programming Instructions N/A
Budget
Planning: None
Preliminary Engineering expected completion date: 2022
Funding Source Secured Status Amount
NHPP Secured $123,348.00
Local Secured $16,652.00
$140,000.00
Right of Way: None
Construction expected completion date: 2024
Funding Source Secured Status Amount
NHPP Secured $974,449.00
Local Secured $131,551.00
$1,106,000.00
Other: None
Total Project Cost: $1,246,000.00
Year of Expenditure 2024
Please confirm the date this project will be fully implemented October 1st, 2024
3 of 3
Project Details and Scope
Environmental Documentation
Type of documentation EA
Actual or expected completion date December 1st, 2022
Project Length
Total project length (in miles): 0.05
Turn pocket lanes
Number of new turn pocket lanes (right -turn, left -turn) to be added by the project: 0
Turn lane
Does the project include a continuous two-way left turn lane? No
Shared Use
Does the project include bicycle and/or pedestrian features and/or paved shoulders? No
Shared Use Explanation This is not a new construction or reconstruction project.
Intelligent Transportation System (ITS) Information
Does the project include Intelligent Transportation Systems (ITS), which are defined as advanced
information processing, communications, sensing, or control technologies? No
Consistency with Local Plans
Is the project specifically identified in a local comprehensive plan? Yes
Local Plan Explanation The bridge deck repair is covered under the City of Kent's
Transportation Master Plan. The project is referenced on page 95, listed as project P-
29.
If "No", describe how the project is consistent with the applicable local comprehensive plan(s). N/A
Compliance Certification
Compliance Certification Yes
Compliance Certification Date December 9th, 2020
Federal Compliance Yes