Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
CAG2022-130 - Original - Olson Brothers Excavating, Inc. - E Tacoma St - Kensington Ave Drainage Improvements - 04/05/2022
Nancy Y for Drew Holcomb Public Works 03/31/2022 04/07/2022 03/15/2022 D20118 N/A Olson Brothers Excavating, Inc.Contract Other E Tacoma St. - Kensington Ave. Drainage Improvements The project will construct a trapezoidal open channel drainage ditch with large rock in a wooded ravine to provide energy dissipation to minimize stormwater blowouts downstream which have been a constant maintenance issue for City staff. $407,406 Bid 3/31/22 ORIGINAL CAG2022-130 4/7/22 DATE: March 15, 2022 TO: Kent City Council SUBJECT: East Tacoma Street - Kensington Avenue Drainage Improvements Project Bid - Award MOTION: I move to award the East Tacoma Street - Kensington Avenue Drainage Improvements Project to Olson Brothers Excavating, Inc. in the amount of $407,406, and authorize the Mayor to sign all necessary documents, subject to final terms and conditions acceptable to the City Attorney and Public Works Director. SUMMARY: The project will construct an open channel drainage swale with large rock in a wooded ravine to provide energy dissipation and minimize downstream maintenance for city staff. The bid opening for the East Tacoma Street - Kensington Avenue Drainage Improvements Project was held on March 1, 2022 with five bids received. The lowest responsible and responsive bid was submitted by Olson Brothers Excavating, Inc. in the amount of $407,406.00. Bid Tab Summary 01. Olson Brothers Excavating, Inc. $407,406.00 02. Northwest Cascade, Inc. $408,815.61 03. R.W. Scott Construction Co. $513,435.66 04. Rodarte Construction, Inc. $514,189.02 05. Active Construction Inc. $541,541.00 Engineer's Estimate $410,067.45 BUDGET IMPACT: The project will be funded by the Drainage Utility. SUPPORTS STRATEGIC PLAN GOAL: Evolving Infrastructure - Connecting people and places through strategic investments in physical and technological infrastructure. ATTACHMENTS: 1. Kensington Ravine Bid Tab (PDF) CITY OF KENT KING COUNTY, WASHINGTON KENT SPECIAL PROVISIONS FOR E Tacoma St. – Kensington Ave. Drainage Improvements Project Number: 18-3019 BIDS ACCEPTED UNTIL March 1, 2022 11:00 A.M. BID OPENING IMMEDIATELY FOLLOWING DELIVER TO CITY OF KENT, CITY HALL 220 4th Avenue S., Kent, WA 98032-5895 CHAD BIEREN, P.E. PUBLIC WORKS DIRECTOR INDEX Section 1 Bidder’s Package Section 2 Payment and Performance Bond and Contract Section 3 Table of Contents Section 4 Kent Special Provisions Section 5 Kent Standard Plans Section 6 WSDOT Standard Plans Section 7 Geotechnical Report Section 8 Kensington Non-Critical Area Determination Section 9 Construction Stormwater Pollution Prevention Plan Section 10 Project Sign Section 11 Prevailing Wage Rates CITY OF KENT KING COUNTY, WASHINGTON KENT SPECIAL PROVISIONS FOR E Tacoma St. -Kensington Ave. Drainage Improvements Project Number: 18-3019 BIDS ACCEPTED UNTIL March 1, 2022 11:00 A.M. BID OPENING IMMEDIATELY FOLLOWING DELIVER TO CITY OF KENT, CITY HALL 220 4th Avenue S., Kent, WA 98032-5895 CHAD BIEREN, P.E. PUBLIC WORKS DIRECTOR KENT WAS H I NGTON 211 1 /LY BIDDER'S NAME Olson Brothers Excavating, Inc. CITY OF KENT KING COUNTY, WASHINGTON KENT SPECIAL PROVISIONS FOR E Tacoma St. -Kensington Ave. Drainage Improvements Project Number: 18-3019 BIDS ACCEPTED UNTIL March 1, 2022 11:00 A.M. BID OPENING IMMEDIATELY FOLLOWING DELIVER TO CITY OF KENT, CITY HALL 220 4th Avenue S., Kent, WA 98032-5895 CHAD BIEREN, P.E. PUBLIC WORKS DIRECTOR KENT W A S H I N G T 0 N ORDER OF CONTENTS Invitation to Bid Contractor Compliance Statement Declaration City of Kent Equal Employment Opportunity Policy Administrative Policy 1.2 Minority and Women Contractors City of Kent Equal Employment Opportunity Compliance Statement Proposal Subcontractor List (over $1 million) HVAC, Plumbing, and Electrical Subcontractor List (over $1 million) Structural Steel Installation and Rebar Installation Contractors Qualification Statement Statement that Bidder Has Not Been Disqualified Certification of Compliance with Wage Payment Statutes Proposal Signature Page Bid Bond Form Combined Declaration Form Non-Collusion, Minimum Wage Change Order Bidders Checklist Payment and Performance Bond Contract Table of Contents Kent Special Provisions Kent Standard Plans WSDOT Standard Plans Geotechnical Report Kensington Non-Critical Area Determination Construction Stormwater Pollution Prevention Plan Project Sign Prevailing Wage Rates INVITATION TO BID Notice is hereby given that the City of Kent, Washington, will receive sealed bids at the City Clerk's office through March 1, 2022 up to 11:00 a.m. as shown on the clock on the east wall of the City Clerk's Office on the first floor of City Hall, 220 4th Avenue South, Kent, Washington. All bids must be properly marked and sealed in accordance with this "Invitation to Bid." Bids must be delivered and received at the City Clerk's office by the above -stated time, regardless of delivery method, including U.S. Mail. All bids will be opened and read publicly aloud immediately following 11:00 a.m. for the City of Kent project named as follows: E Tacoma St. — Kensington Ave. Drainage Improvements Project Number: 18-3019 The City Clerk will read the bids out loud from the Clerk's office. Individuals can stand in the lobby outside the Clerk's office during the bid opening to hear the bid results. A mandatory pre -bid site visit is scheduled for Thursday February 24, 2022 at 9:00 a.m. at Mill Creek Canyon Earthworks Park (located to the east of the intersection of E Titus Street and Reiten Rd.). If you are unable to make this date but still wish to bid on this project, please contact Drew Holcomb at 253-856-5561. The purpose of this site visit is for interested contractors to get a sense of the project's location and its overall setting, which otherwise is not easily determined using Google Earth and is partially located on private property accessed through easements. City staff will be present only to provide access to the ditch; not to answer questions or provide information. If a follow-up question after the site visit requires further clarification, this information will be provided through an addendum. A sign -in sheet will be provided. Contractors must sign -in to confirm that they have visited the project site. Bids from the contractor will only be considered if they attend this mandatory pre - bid site visit. This project is not anticipated to begin construction until the dry season as this project consists of clearing and using rip rap to construct a trapezoidal drainage ditch in a forested ravine which is located on easements through private property and City right of way. Steep banks in the ravine will require the construction of gabion baskets walls and two gabion basket check dams. The existing ditch outlet will be filled and a new type 2 manhole will be set and storm pipe will connect to the existing manhole which will be raise to finished grade and filled in. Two quarry spall lined drainage swales will be constructed to drain Tacoma St. to the ditch inlet headwall. Should a contract be executed, it is the contractor's responsibility to comply with all COVID-19 workplace health and safety measures established by the state Department of Labor & Industries or otherwise imposed by the Governor, the state Department of Health, or the Local Health Officer of Seattle -King County Public Health, or subsequent modifications to such health and safety measures as those authorities may issue, including providing all needed personal protective equipment. The Engineer's estimated range for this project is approximately $375,000-$425,000. Bid documents may be obtained by contacting City of Kent Engineering Department, Nancy Yoshitake at 253-856-5508. For technical questions, please call Drew Holcomb at 253-856-5561. Bids must be clearly marked "Bid" with the name of the project on the outside of the envelope, addressed to the City Clerk, 220 4th Avenue South, Kent, WA 98032-5895. Only sealed bids will be accepted. No facsimiles or electronic submittals will be considered. Each bid shall be in accordance with the plans and specifications and other contract documents now on file in the office of the City Engineer, City of Kent, Washington. Plans and specifications can also be downloaded at no charge at littps:!/www.kent►rva.govlpav- and-apilvlbicis-procurement-rfps. Copies of the WSDOT Standard Specifications are available for perusal only. Apprentice Utilization Requirements are mandatory for all public works estimated to cost one million dollars or more, in which case no less than 15% of the labor hours must be performed by apprentices. KCC 6.01.030, A cashier's check, cash or surety bond in the amount of 5% of the bid must be included with the bid. The City of Kent reserves the right to reject any and all bids on any or all schedules or alternates or to waive any informalities in the bidding and shall determine which bid or bidders is the most responsive, satisfactory and responsible bidder and shall be the sole judge thereof. Note: The award of the contract will not occur until the City of Kent has reviewed all bids for responsiveness and responsibility determinations and the Kent City Council has formally awarded the contract. No plea of mistake in the bid shall be available to the bidder for the recovery of his/her deposit or as a defense to any action based upon the neglect or refusal to execute a contract. Bidders must submit with their initial bid a signed statement as to whether they have previously performed work subject to the President's Executive Order No. 11246. No bidder may withdraw his/her bid for a period of sixty (60) days after the day of bid opening. Dated this 14th day of February, 2022. / �j BY: '}L l Kimberley A.( Fnoto, City Cler Published: Daily Journal of Commerce on February 15 and 22, 2022 Washington State Office of Minority and Women's Business Enterprise on February 15, 2022 CONTRACTOR COMPLIANCE STATEMENT (President's Executive Order #11246) Date March 1, 2022 This statement relates to a proposed contract with the City of Kent named E Tacoma St. - Kensington Ave. Drainage Improvements Project Number: 18-3019 I am the undersigned bidder or prospective contractor. I represent that - 1. I X have, have not, participated in a previous contract or subcontract subject to the President's Executive Order #11246 (regarding equal employment opportunity) or a preceding similar Executive Order. Olson Brothers Excavating, Inc. NAME OF BIDDER BY: SIGNATURE/TITLE Steve Olson, Vice President 6622 112th St. E. Puyallup, WA 98373 ADDRESS (Note to Bidders: The information required in this Compliance Statement is informational only) Kensington Drainage Improvements/Holcomb 1 February 14, 2022 Project Number: 18-3019 DECLARATION CITY OF KENT EQUAL EMPLOYMENT OPPORTUNITY POLICY The City of Kent is committed to conform to Federal and State laws regarding equal opportunity. As such, all contractors, subcontractors and suppliers who perform work with relation to this contract shall comply with the regulations of the City's equal employment opportunity policies. The following questions specifically identify the requirements the City deems necessary for any contractor, subcontractor or supplier on this specific contract to adhere to. An affirmative response is required on all of the following questions for this contract to be valid and binding. If any contractor, subcontractor or supplier willfully misrepresents themselves with regard to the directives outlined, it will be considered a breach of contract and it will be at the City's sole determination regarding suspension or termination for all or part of the contract; The questions are as follows: 1. I have read the attached City of Kent administrative policy number 1.2. 2. During the time of this contract, I will not discriminate in employment on the basis of sex, race, color, national origin, age, or the presence of all sensory, mental or physical disability. 3. During the time of this contract, the prime contractor will provide a written statement to all new employees and subcontractors indicating commitment as an equal opportunity employer. 4. During the time of the contract I, the prime contractor, will actively consider hiring and promotion of women and minorities. 5. Before acceptance of this contract, an adherence statement will be signed by me, the Prime Contractor, that the Prime Contractor complied with the requirements as set forth above. By signing below, I agree to fulfill the fiv quirements referenced above, By: For: Olson Brothers Excavating, Inc. Title: Steve Olson, Vice President Date: March 1, 2022 Kensington Drainage Improvements/Holcomb 2 February 14, 2022 Project Number: 18-3019 CITY OF KENT ADMINISTRATIVE POLICY NUMBER: 1.2 EFFECTIVE DATE: January 1, 1998 SUBJECT: MINORITY AND WOMEN SUPERSEDES: April 1, 1996 CONTRACTORS APPROVED BY Jim White, Mayor POLICY: Equal employment opportunity requirements for the City of Kent will conform to federal and state laws. All contractors, subcontractors, consultants and suppliers of the City must guarantee equal employment opportunity within their organization and, if holding contracts with the City amounting to $10,000 or more within any given year, must take the following affirmative steps: 1. Provide a written statement to all new employees and subcontractors indicating commitment as an equal opportunity employer. 2. Actively consider for promotion and advancement available minorities and women. Any contractor, subcontractor, consultant or supplier who willfully disregards the City's nondiscrimination and equal opportunity requirements shall be considered in breach of contract and subject to suspension or termination for all or part of the contract. Contract Compliance Officers will be appointed by the Directors of Planning, Parks, and Public Works Departments to assume the following duties for their respective departments. 1. Ensuring that contractors, subcontractors, consultants, and suppliers subject to these regulations are familiar with the regulations and the City's equal employment opportunity policy. 2. Monitoring to assure adherence to federal, state and local laws, policies and guidelines. Kensington Drainage Improvements/Holcomb 3 February 14, 2022 Project Number: 18-3019 CITY OF KENT EQUAL EMPLOYMENT OPPORTUNITY COMPLIANCE STATEMENT This form shall be filled out AFTER COMPLETION of this project by the Contractor awarded the contract. I, the undersigned, a duly represented agent of Company, hereby acknowledge and declare that the before - mentioned company was the prime contractor for the contract known as E Tacoma St. — Kensington Ave. Drainage Improvements/Project Number: 18-3019 that was entered into on the (Date) , between the firm I represent and the City of Kent. I declare that I complied fully with all of the requirements and obligations as outlined in the City of Kent Administrative Policy 1.2 and the Declaration City of Kent Equal Employment Opportunity Policy that was part of the before -mentioned contract. By ; For: Title: Date: Kensington Drainage Improvements/Holcomb 4 February 14, 2022 Project Number; 18-3019 PROPOSAL To the City Clerk City Han Kent, Washington 98032 The undersigned hereby certifies that Olson Brothers Excavating, Inc. has examined the job site and construction details of the work as outlined on the plans and described in the specifications for the project named E Tacoma St. — Kensington Ave. Drainage Improvements/Project Number: 18-3019 for the City of Kent, Washington, and has read and thoroughly understands the plans and specifications and contract governing the work embraced in this improvement and the method by which payment will be made for that work and hereby proposes to undertake and complete the work embraced in this improvement in accordance with the bid and contract, and at the following schedule of rates and prices: NOTE TO BIDDERS: 1) All bid items are described in the Kent Special Provisions (KSP) or the Standard Specifications (WSDOT). Reference the Section No. listed in this proposal, where the bid item is described. 2) Proposal items are numbered in sequence but are non -continuous. 3) Unit prices for all items, all extensions, and total amount of bid must be shown. 4) Should bid items with identically worded bid item descriptions, marked with asterisk (*), appear in more than one schedule of the proposal, the bidder must bid the same unit price on corresponding items for each schedule. If the Contractor enters different unit prices on these items, the City will unilaterally revise the bid amounts to the lowest unit price on each corresponding item and recalculate the Contractor's total bid amount. The corrected total bid amount will be used by the City for award purposes and fix the amount of the contract bond. EXAMPLE SCHEDULE I - STREET ITEM SECTION APPROX. ITEM UNIT TOTAL NO. NO. QUANTITY PRICE AMOUNT 1006 2-03.5 100 WSDOT CU YDS Roadway Excavation, $14.00 $1,400.00 Including Haul Per CY Any bids not filled out properly may be considered non -responsive. Kensington Drainage Improvements/Holcomb 5 February 14, 2022 Project Number; 18-3019 SCHEDULE I - STREET ITEM SECTION APPROX. ITEM UNIT TOTAL NO. NO. QUANTITY PRICE AMOUNT 1000 1-09.7 1 Mobilization $ Y3i57VO$ ��,,6-79 70 WSDOT LUMP SUM Per LS 1005 2-01.5 1 Clearing and Grubbing $52.1A-S.oa WSDOT LUMP SUM Per LS 1015 8-33.5 6 KSP EACH 1020 2-02.5 220 KSP SQ YDS 1025 2-02.5 1 KSP LUMP SUM Remove Existing Trees Remove Existing Asphalt Concrete Pavement Remove and Dispose of Existing Wood Crossing $ J'2��-l�j 5 b $ Per EA $ -�i.sd $ zo-)o.00 Per SY $Ps'o9.5b$ t�Io£s.50 Per LS 1030 2-02.5 1 Remove and Dispose of $1A10 $ KSP LUMP SUM Grouted Rock Wall Per LS 1035 2-02.5 1 Remove and Dispose of PVC $ Ztrj.O6$ ),Le--)s 0 KSP LUMP SUM Pipe Per LS 1040 2-02.5 1 Remove and Connect $1,000* $1,000 KSP FORCE Unknown Drainage Pipes to Per FA ACCOUNT Ditch _ *Common price to all bidders 1060 2-03.5 330 Ditch Excavation Incl. Haul $ S1 50 $ 9-1.j1g�jCj,00 WSDOT CU YDS Per CY 1065 2-03.5 60 Unsuitable Foundation $ 1 Zlbo $ DO WSDOT CU YDS Excavation Incl. Haul Per CY Kensington Drainage Improvements/Holcomb 6 February 14, 2022 Project Number: 18-3019 SCHEDULE I - STREET ITEM SECTION APPROX. ITEM UNIT TOTAL NO. NO. QUANTITY PRICE AMOUNT 1070 2-12.5 660 Non -woven Geotextile Fabric $rs. 50 $ 3(930.00 KSP SQ YDS for Soil Stabilization Per SY 1075 4-03.5 190 Gravel Borrow, Including $��1•Sb $ Je jrS25. bD KSP TONS Haul and Compaction Per TON 2.50 Min 1080 4-04.5 100 Crushed Surfacing Top $ -Ib• Ob $ "� (� Ob• O KSP TONS Course, 5/8 Inch Minus Per TON 1085 8-24.5 100 Rock for Gabion Basket KSP TONS Backfill 1095 5-04.5 60 HMA Class 1/2", PG 58H-22 KSP TONS 1100 8-15.5 520 Rock for Erosion and Scour KSP TONS Protection Class B 1105 8-15.5 50 Quarry Spalls WSDOT TONS 1120 7-17.5 10 Concrete Pipe Anchor KSP CU YDS $X5g'.'C5p $S&tD-O.aO Per TON ($6.00 Min) $Y19i.O6) $ DO Per Per TON $ ' l Sb $r5ki-l"o.00 Per TON $1LoU-DO $�" 6o-c)D Per TON Per CY 1290 8-03.5 1 Existing Irrigation Systems $2,000* $2,000 KSP FORCE Removal, Repair and/or Per FA ACCOUNT Modifications *Common price to all bidders 1300 8-24.5 65 Gabion Cribbing $ l��j�]. d (� $ `�>,S't?'Jj ,C)D WSDOT CU YDS Per CY Kensington Drainage Improvements/Holcomb 7 Project Number: 18-3019 February 14, 2022 SCHEDULE I - STREET ITEM SECTION APPROX. ITEM UNIT TOTAL NO. NO. QUANTITY PRICE AMOUNT 1310 8-12.5 230 Temporary 6' High Chain Link $ OD KSP LN FT Fence Per LF 1315 8-21.5 1 Type III Fixed (Permanent) •5 C$ KSP EACH Barricade Per EA 1320 8-30.5 1 Project Sign $ I 2;?6. 5b$ 1 &16.50 KSP EACH Per EA 1325 8-22.5 1 Permanent Channelization $14(0N5(�,O KSP LUMP SUM Per LS 1350 7-17.5 36 Ductile Iron Sewer Pipe, 6 $ `�j�l .DO $p0 KSP LN FT Inch Diameter Class 52 Epoxy Per LF Coated 1360 7-19.5 1 6 Inch Two Way Sewer $ �$ KSP EACH Cleanout Per EA 1402 7-05.5 1 Raise Existing Custom 0Z-150$g2'I.6C> KSP EACH Manhole to Finished Grade Per EA 1405 7-05.5 1 Catch Basin, Type 2 $�&- cu KSP EACH 54 Inch Diameter Per EA 1407 7-04.5 10 Ductile Iron Storm Sewer $ 26b.06 $ KSP LN FT Pipe, 12 Inch Diameter Per LF 1410 7-04.5 20 Storm Sewer Pipe, $ f.' 1.00 $1'102-0 00 KSP LN FT 24 Inch Diameter Per LF Kensington Drainage Improvements/Holcomb 8 February 14, 2022 Project Number: 18-3019 SCHEDULE I - STREET ITEM SECTION APPROX. ITEM UNIT TOTAL NO. NO. QUANTITY PRICE AMOUNT 1415 7-05.5 2 Circular Frame (Ring) and $%"s -W $ KSP EACH Cover, Type 2 Per EA 1425 7-05.5 1 54 Inch Debris Cage $ G[. & tC) $ TLPtp4`. C)C) KSP EACH Per EA 1430 7-04.5 1 Trash Screen 12" Diameter $521.54 627I.50 KSP EACH Per EA 1450 7-05.5 2 Adjust Existing Catch Basin $Lp�Q`1 -,15cs 1��c=j 6b KSP EACH Grate or Curb Inlet Grate to Per EA . Finished Grade 1455 7-05.5 1 Adjust Existing Manhole Cover $000t,60$ [0(01'so KSP EACH to Finished Grade Per EA 1505 1-10.5 50 Traffic Control Labor $'�2.ov $ 2,Dio.Ob KSP HOURS Per HR 1510 1-10.5 25 Traffic Control Supervisor $ 251 .1175-(j KSP HOURS Per HR t 1520 1-10.5 1 KSP LUMP SUM 1530 1-10.5 30 KSP DAYS Temporary Traffic Control $ $�•$2;-:2p Devices Per LS Portable Changeable Message $ S2.00 $ 1�j(oC�.00 Sign (PCMS) Per DAY 1540 1-10.5(2) 50 Construction Signs Class A WSDOT SQ FT Kensington Drainage Improvements/Holcomb 9 Project Number: 18-3019 $ \'5. Sz $ -I-tS. CO Per SF February 14, 2022 SCHEDULE I - STREET ITEM SECTION APPROX. ITEM UNIT TOTAL NO. NO. QUANTITY PRICE AMOUNT 1700 8-01.5(2) 50 Seeding, Fertilizing, and $ 5- -C'(�) $ Y Oo-C)o KSP SQ YDS Mulching Per SY 1705 8-02.5 50 Topsoil Type A sPN'5. 15�t $ KSP CU YDS Per CY 1710 8-01.5(2) 4 Inlet Protection $ 1M -JC' $ J-A-1S_A,C)C) KSP EACH Per EA 1715 8-01.5(2) 150 Straw Mulch $ NO -'so $ KSP SQ YDS Per SY 1720 8-01.5(2) 600 Clear Plastic Covering $ 2A .00R $ pQ KSP SQ YDS Per SY 1725 8-01.5(2) 50 ESC Lead $ 1(0.60 $ �>2�60.00 KSP HOURS Per HR 1730 8-01.5(2) 800 Wattle $ & . fl 0 $ A W0.80 KSP LN FT Per LF 1732 8-01.5(2) 100 Filter Fabric Fence $ ( .Q(D $ low. OCR KSP LN FT Per LF 1735 8-01.5(2) 600 Erosion Control Blanket 0 •'aO $ a KSP SQ YDS Per SY 1740 1-07.15(1) 1 SPCC Plan $24-0 WSDOT LUMP SUM Per LS Kensington Drainage Improvements/Holcomb 10 February 14, 2022 Project Number: 18-3019 SCHEDULE I - STREET ITEM SECTION APPROX. ITEM UNIT TOTAL NO. NO. QUANTITY PRICE AMOUNT 1745 8-01.5(2) 1 Erosion/Water Pollution $10,000* $10,000 WSDOT FORCE Control Per FA ACCOUNT *Common rice to all bidders 1900 1-04.4(1) 1 Minor Changes WSDOT CALC *Common price to all bidders $10,000* $10,000 Per CALC Sub Total $ r1 D 10.1% Sales Tax $ Schedule I Total $ J—i d-1 . 60 Kensington Drainage Improvements/Holcomb 11 February 14, 2022 Project Number: 18-3019 SUBCONTRACTOR LIST (Contracts over 1 million dollars) HVAC, PLUMBING AND ELECTRICAL Name of Bidder: Olson Brothers Excavating, Inc. Project Name: E Tacoma St. — Kensington Ave. Drain Improve-ments Project Number: 18-3019 Pursuant to RCW 39.30.060, Bidder shall list the names of the subcontractors with whom the Bidder, if awarded the contract, will subcontract for performance of the work of heating, ventilation, and air conditioning; plumbing; and electrical, or name itself for the work. Failure of the Bidder to submit, within one hour after the published bid submittal time, the names of such subcontractors or to name itself to perform such work or the naming of two or more subcontractors to perform the same work shall render the Bidder's Bid non -responsive and, therefore, void. Heating, Ventilation, and Air Conditioning Subcontractor Name: Plumbing Subcontractor Name: Electrical Subcontractor Name: Signature of Bidder March 1, 2022 Date Kensington Drainage Improvements/Holcomb 12 February 14, 2022 Project Number: 18-3019 SUBCONTRACTOR LIST (Contracts over 1 million dollars) STRUCTURAL STEEL INSTALLATION AND REBAR INSTALLATION Name of Bidder: Olson Brothers Excavating, Inc. Project Name: E Tacoma St. - Kensington Ave. Drainage Improvements Project Number: Pursuant to RCW 39.30.060, Bidder shall list the names of the subcontractors with whom the Bidder, if awarded the contract, will subcontract for performance of the work of structural steel installation and rebar installation. Failure of the Bidder to submit, within 48 hours after the published bid submittal time, the names of such subcontractors or to name itself to perform such work or the naming of two or more subcontractors to perform the same work shall render the Bidder's Bid non -responsive and, therefore, void. Structural Steel Installation Subcontractor Name: Rebar Installation Subcontractor Name: Signature of Bidder March 1, 2022 Date Kensington Drainage Improvements/Holcomb 13 February 14, 2022 Project Number: 18-3019 CONTRACTOR'S QUALIFICATION STATEMENT (RCW 39.04.350) THE CITY WILL REVIEW THE CONTRACTOR'S RESPONSES TO THIS FORM TO DETERMINE WHETHER THE BIDDING CONTRACTOR IS RESPONSIBLE TO PERFORM THE CONTRACT WORK. THIS FORM INCLUDES CRITERIA ESTABLISHED BY STATE LAW THAT MUST BE MET TO BE CONSIDERED A RESPONSIBLE BIDDER AND QUALIFIED TO BE AWARDED THIS PUBLIC WORKS PROJECT AS WELL AS SUPPLEMENTAL CRITERIA ESTABLISHED BY THE CITY THAT ARE APPLICABLE TO THIS PUBLIC WORKS PROJECT. THE BIDDER SHOULD READ AND RESPOND TO THIS FORM CAREFULLY. Indicia of contractor's responsibility inherently involve subjective determinations as to the contractor's ability to perform and complete the contract work responsibly and to the owner city's satisfaction. The city has an obligation and a duty to its citizens and its taxpayers to administer its budgets and complete its projects in a businesslike manner. Accordingly, it has a duty to exercise the type of inquiry and discretion a business would conduct when selecting a contractor who will be responsible to perform the contract work. The city's supplemental criteria are based, in large part, on the qualification statement form used by the American Institute of Architects. The city provides these criteria so as to provide the most objective framework possible within which the city will make its decision regarding the bidder's ability to be responsible to perform the contract work. These criteria, taken together, will form the basis for the city's decision that a bidder is or is not responsible to perform the contract work. Any bidder may make a formal written request to the city to modify the criteria set forth in this qualification statement, but that request may only be made within 48 hours of the date and time that the bidder first obtains the bid documents or three (3) business days prior to the scheduled bid opening date, whichever occurs first. If the city receives a modification request, it will consider any information submitted in the request and will respond before the bid submittal deadline. If the city's evaluation results in changed criteria, the city will issue an addendum establishing the new or modified criteria. If the city determines that, based on the criteria established in this statement, a bidder is not responsible to perform the contract work, the city will provide written notice of its determination that will include the city's reason for its decision. The bidder has 24 hours from the time the city delivers written notice to the bidder that the bidder is not responsible to perform the contract work to appeal the city's determination. No appeals will be received after the expiration of this 24 hour appeal period. The city may deliver this notice by hand delivery, email, facsimile, or regular mail. In the event the city uses regular mail, the delivery will be deemed complete three days after being placed in the U.S. Mail. The bidder's right to appeal is limited to the single remedy of providing the city with additional information to be considered before the city issues a final determination. Bidder acknowledges and understands that, as provided by RCW 39.04.350, no other appeal is allowed and no other remedy of any kind or nature is available to the bidding contractor if the City determines that the bidder is not responsible to perform the contract work. Kensington Drainage Improvements/Holcomb 14 February 14, 2022 Project Number: 18-3019 If the bidder fails to request a modification within the time allowed, or fails to appeal a determination that the bidder is not responsible within the time allowed, the city will make its determination of bidder responsibility based on the information submitted. COMPLETE AND SIGN THIS FORM AS PART OF YOUR BID. FAILURE TO PROPERLY COMPLETE THIS FORM MAY ALSO RESULT IN A DETERMINATION THAT YOUR BID IS NON -RESPONSIVE AND THEREFORE VOID. THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES: CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION. The undersigned certifies under oath that the information provided herein is true and sufficiently complete so as not to be misleading. SUBMITTED BY: Olson Brothers Excavating, Inc. NAME: Steve Olson ADDRESS: 6622 112th St. E. Puyallup, WA 98373 PRINCIPAL OFFICE: Olson Brothers Excavating, Inc. ADDRESS: 6622 112th St. E. Puyallup, WA 98373 PHONE: 253-770-3844 FAX: 253-770-3845 STATUTORY REQUIREMENTS — Per state law a bidder must meet the following responsibility criteria 1. Required Responsibility Criteria 1.1 Provide a copy of your Department of Labor and Industries certificate of registration in compliance with chapter 18.27 RCW. 1.2 Provide your current state unified business identifier number. 1.3 Provide proof of applicable industrial insurance coverage for your employees working in Washington as required in Title 51 RCW, together with an employment security department number as required in Title 50 RCW, and a state excise tax registration number as required in Title 82 RCW. Providing a copy of a state of Washington "Master License Service Registration and Licenses" form is typically sufficient evidence of the requirements of this subsection. 1.4 Provide a statement, signed by a person with authority to act and speak for your company, that your company, including any subsidiary companies or affiliated companies under majority ownership or under Kensington Drainage Improvements/Holcomb 15 February 14, 2022 Project Number! 18-3019 control by the owners of the bidder's company, are not and have not been in the past three (3) years, disqualified from bidding on any public works contract under RCW 39,06.010 or 39.12.065 (3). 1.5 Provide a signed statement, signed under penalty of perjury by a person with authority to act and speak for your company, that within the three- year period immediately preceding the bid solicitation date, your company is not a "willful" violator as defined in RCW 49.48.082, of any provisions of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and notice of assessment issued by the Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction. 1.6 Provide proof that a designated person or persons with your company has either received training from the department of labor and industries or an approved training provider on the requirements related to public works and prevailing wages under chapter 39.04 RCW and 39.12 RCW or provide proof that your company has completed three or more public works projects and have had a valid business license in Washington for three or more years and are exempt from this training requirement. SUPPLEMENTAL CRITERIA — Established by the City to determine bidder responsibility 2. ORGANIZATION 2.1 How many years has your organization been in business as a Contractor? 2.2 How many years has your organization been in business under its present business name? 2.2.1 Under what other or former names has your organization operated? 2.3 If your organization is a corporation, answer the following: 2.3.1 Date of incorporation: 2.3.2 State of incorporation: 2.3.3 President's name: 2.3.4 Vice-president's name(s): 2.3.5 Secretary's name: 2.3.6 Treasurer's name: 2.4 If your organization is a partnership, answer the following: 2.4.1 Date of organization: 2.4.2 Type of partnership (if applicable): 2.4.3 Name(s) of general partner(s): 2.5 If your organization is individually owned, answer the following: 2.5.1 Date of organization: 2.5.2 Name of owner: Kensington Drainage Improvements/Holcomb 16 February 14, 2022 Project Number: 18-3019 2.6 If the form of your organization is other than those listed above, describe it and name the principals: 3. LICENSING 3.1 List jurisdictions and trade categories in which your organization is legally qualified to do business, and indicate license numbers, if applicable. 3.2 List jurisdictions in which your organization's partnership or trade name is filed. 4. EXPERIENCE 4.1 List the categories of work that your organization normally performs with its own forces. 4.2 Claims and Suits. (If the answer to any of the questions below is yes, please attach details.) 4.2.1 Has your organization ever failed to complete any work awarded to it? 4.2.2 Are there any judgments, claims, arbitration proceedings or suits pending or outstanding against your organization or its officers? 4.2.3 Has your organization filed any law suits or requested arbitration with regard to construction contracts within the last five years? 4.3 Within the last five years, has any officer or principal of your organization ever been an officer or principal of another organization when it failed to complete a construction contract? (If the answer is yes, please attach details.) 4.4 On a separate sheet, list major construction projects your organization has in progress, giving the name of project, owner, architect or design engineer, contract amount, percent complete and scheduled completion date. 4.4.1 State total worth of work in progress and under contract: 4.5 On a separate sheet, list the major projects your organization has completed in the past five years, giving the name of project, owner, architect or design engineer, contract amount, date of completion and percentage of the cost of the work performed with your own forces. 4.5.1 State average annual amount of construction work performed during the past five years: 4.6 On a separate sheet, list the construction experience and present commitments of the key individuals of your organization. 4.7 On a separate sheet, list your major equipment. Kensington Drainage Improvements/Holcomb 17 February 14, 2022 Project Number: 18-3019 S. REFERENCES 5.1 Trade References: 5.2 Bank References: 5.3 Surety: 5.3.1 Name of bonding company: 5.3.2 Name and address of agent: 6. FINANCING 6.1 Financial Statement. After bid opening, the City may require the following financial information from any of the three apparent low bidders. If so required, the selected bidder(s) must respond with this financial information within 24 hours of the City's request for that information. The City's request for this information shall not be construed as an award or as an intent to award the contract. A bidder's failure or refusal to provide this information may result in rejection of that bidder's bid. 6.1.1 Attach a financial statement, preferably audited, including your organization's latest balance sheet and income statement showing the following items: Current Assets (e.g., cash, joint venture accounts, accounts receivable, notes receivable, accrued income, deposits, materials inventory and prepaid expenses); Net Fixed Assets; Other Assets; Current Liabilities (e.g., accounts payable, notes payable, accrued expenses, provision for income taxes, advances, accrued salaries and accrued payroll taxes); Other Liabilities (e.g., capital, capital stock, authorized and outstanding shares par values, earned surplus and retained earnings). 6.1.2 Name and address of firm preparing attached financial statement, and date thereof: 6.1.3 Is the attached financial statement for the identical organization named on page one? 6.1.4 If not, explain the relationship and financial responsibility of the organization whose financial statement is provided (e.g., parent - subsidiary). 6.2 Will the organization whose financial statement is attached act as guarantor of the contract for construction? Kensington Drainage Improvements/Holcomb 18 February 14, 2022 Project Number: 18-3019 7. SIGNATURE 7.1 Dated at this 1 day of March 2022. Name of Organization: Olson Brothers Excavating, Inc. By: C Title: Steve Olson, Vice President 7.2 Steve Olson , being duly sworn, deposes and says that the information provided herein is true and sufficiently complete so as not to be misleading. Subscribed ands orn before m is 1 day of March , 2022. Notary Public: �"tyrirrnwr,,�, My Commission xpires: 12/15/202 ..�`'" KARCE�''.., 410 S. ° 9 41 •��ti• a.' == '?ssss ....... .,y,. '1NGTO, APO ",A Ai li 41 Kensington Drainage Improvements/Holcomb 19 February 14, 2022 Project Number: 18-3019 BROS. EXCAVATING INC. 6622 - 112th St. E • PUYALLUP,, WA 98373 • (253) 770-3844 FAX (253) 770-3845 City of Kent E Tacoma St. — Kensington Ave. Drainage Project No: 18-3019 Statutory Requirements: 1.1 See attached 1.2 601-161-685 1.3 ES Ref No: 674087007, Please see attached 1.4 See attached 1.5 See attached 1.6 See attached list of references 2.1 32 Years 2.2 32 Years 2.2.1 N/A 2.3 2.3.1 1/1/89 2.3.2 Washington 2.3.3 Mike Olson 2.3.4 Steve Olson 2.3.5 Mike Olson 2.3.6 Steve Olson 2.4 N/A 2.5 N/A 2/6 N/A 3.1 State of Washington — OLSONBE113N3 / 601-161-685 City of Sammamish City of Gig Harbor City of Tumwater City of Sumner City of Ruston City of Fircrest City of Port Orchard City of Olympia City of Lacey City of Puyallup 00990231 City of Tacoma S00005551 City of Snoqualmie 113485 City of Renton BL.034836 City of Seattle 520813 City of Bellevue 125373 EXCAVATING DEMOLITION LAND DEVELOPING CONTRACTOR'S LICENSE NO • OLSON B E 113N3 3.2 State of Washington — OLSONBE1131\13 / 601-161-685 City of Sammamish City of Gig Harbor City of Tumwater City of Sumner City of Ruston City of Fircrest City of Port Orchard City of Olympia City of Lacey City of Puyallup 00990231 City of Tacoma 500005551 City of Snoqualmie 113485 City of Renton BL.034836 City of Seattle 520813 City of Bellevue 125373 4.1 Sitework and underground utility installation; Sewer, Water, Storm 4.2.1 No 4.2.2 No 4.2.3 No 4.3 No 4.4 See attached 4.4.1 $ 4,000,000.00 4.5 See attached 4.5.1 $ 12,000,000.00 4.6 See attached 4.7 See attached 5.1 See attached 5.2 Heritage Bank Chuck Folsom (253) 770-7686 5.3.1 Travelers Casualty & Surety Company 5.3.2 Agent — Propel Insurance, P.O. Box 2940, Tacoma, WA. 98401 6.1 Financial Statement available upon request Department of Labor and Industries PO Box 44450 Olympia, WA 98504-4450 ' fi91 OLSON BROTHERS EXCAVATING INC 6622 112TH ST E PUYALLUP WA 98373 OLSON BROTHERS EXCAVATING INC Reg: CC OLSONBE 113N3 UBI: 601-161-685 Registered as.provided by Law as: Construction Contractor (CCO I) - GENERAL .Effective Date: '812311989 Expiration Date: 10/31/2023 CERTIFICATE OF COVERAGE EMPLOYER: This is your official certificate -of .industrial insurance ;8 e coverage. It remains active until your account is closed. You are required by law to post both this certificate and copies of the posters listed below. Ypu will soon bereceiving1 copy of each. If you require additional copies, call Labor aiid 'Indtistries 'if 36T902-4817. Insurance Services Division Employer Services . Job Safety and Health Protection (available in Spanish) • Your Rights as a Worker/Family Care Department of Labor &industries ■ Notice to Employees PO. Box 44144 Olympia WA 98504-4144 WORKER: The employer named below is an insured policyholder with the Washington. -State. Industrial.Insurance Trust Fund. UBI*: .., ? .c 13 Policy E€[ectiye date Location - '.;�'--�_:i t,-`+'w-i�l� . rti:.i',.' � _ .. BSc :-��ia - i{r %fie .•7:.„k....�.a ;.! :.y .. :.}.} c--� #,;ki {i'�{i _y�y1 f.:L:�'clk?' "3fR�iir !L. ti':}3.,i:e+ 1:1 [•�f.+-! i Y't i 6 r ...j if-: f Iia��'A iy . NNW,: - - *Your Unified Business Identifier is the only number you need to discuss your business account with the Washington state departments of Revenue, Licensing: Employment Security, Labor and Industries and the Offiee of the Secretary of State. Other state licenses•or registrations may be required for proper licensing of .your business. BROS. EXCAVATING INC. 6622 - 112th St. E • PUYALLUP, WA 98373 • (253) 770-3844 FAX (253) 770-3845 March 1, 2022 E Tacoma St. — Kensington Ave. Drainage Project No: 18-3019 EXCAVATING DEMOLITION LAND DEVELOPING Olson Brothers Excavating, Inc., including any subsidiary companies or affiliated companies under majority ownership or under control by the owners of the bidder's company, are not and have not been in the past three (3) years, disqualified from bidding on any public works contract under RCW 39.06-010 or 39.12.065(3). Sincerely, Olson Brothers Excavating, Inc. .r- Steve Olson Vice President CONTRACTOR'S LICENSE NO • OLSON B E 113N3 r% A BROS. EXCAVATING INC. 6622 - 112th St. E • PUYALLUP, WA 98373 • (253) 770-3844 FAX (253) 770-3845 March 1, 2022 E Tacoma St. — Kensington Ave. Drainage Project No: 18-3019 EXCAVATING DEMOLITION LAND DEVELOPING Olson Brothers Excavating, Inc., including any subsidiary companies or affiliated companies under majority ownership or under control by the owners of the bidder's company, affirms that within the three year period immediately preceding the bid solicitation date, our company is not a "willful" violator as defined in RCW 49.48.082, of any provisions of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and notice of assessment issued by the Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction. Signed under penalty of perjury by a person with authority to act and speak for Olson Brothers Excavating, Inc. Sincerely, Olson Brothers Excavating, Inc. t Steve Olson Vice President CONTRACTOR'S LICENSE NO • OLSON B E 113N3 2PJM 3M0AVA=Z3Ca I= References and Work Completed Project Name Perrigo Park Phase 2A Year 2015 Owner City of Redmond Size 1.2M Contact Joe O'Leary (425) 691-7793 Project Name 10 & Concord CSS Improvements Year 2016 Owner City of Seattle Size/Description 2.4M Contact Bobby Jones (206) 276-1762 Project Name Lower Coal Creek Flood Hazard Reduction Year 2017 Owner City of Bellevue Size/Description 1M Contact Debbie Harris (425) 452-4367 Project Name Blue Ridge Conduit Installation Phase 1 Year 2016 — In progress Owner Seattle City Light Size/Description 5 Million Contact Stan Eng. (206) 684-0841 Project Name Parker Court Year 2018 Owner City of Sumner Size/Description 400K Contact Michael Kosa (253) 299-5709 Project Name 39t" Street Widening Project Year 2016-2017 Owner City of Puyallup Size/Description 2.8M Contact Ted Hill (253) 841-5463 Project Name 30TI Ave Sidewalks & Natural Drainage Year 2018-2019 Owner Seattle Department of Transportation Size/Description 1.9M Contact Elsa Tibbits (206) 445-8597 6622 1121h St. East Puyallup, WA 98375 Office: 253.770.3844 Fax: 253.770.3845 N L� ZRW. ZXCAVATnfO UM Project Name Green River Shoreline Soil Preparation Year 2018 Owner City of Kent Size/Description 326K Contact Paul Kuehne (253) 856-5543 Project Name Mackey Creek Restoration Year 2018 Owner City of Redmond Size/Description 591K Contact Bassam AI -Ali (425)556-2712 Project Name 2019 Spot Sewer Repairs Year 2019 Owner Seattle Public Utilities Size/Description 1.7M Contact Stefanie Hegland (206)423-2605 Project Name Downey Farmstead Year 2019 Owner City of Kent Size/Description 400K Contact Paul Kuehne (253)856-5543 Project Name Puget Way Culvert Year 2019-2020 Owner Seattle Public Utilities Size/Description 1M Contact Steve Colony (206)423-2605 Project Name Foothills — Battersby Trail Year 2020 Owner City of Enumclaw Size/Description 820K Contact Scott Woodbury (360)615-5728 6622 112th St. East Puyallup, WA 98375 Office: 253.770.3844 Fax: 253.770.3845 Jason Duke EDUCATION Central Washington University; Bachelor of Science Construction Management, March2002. EXPERIENCE Olson Brothers Excavating, Inc. Construction Manager, Heavy Civil March 2015 — Present Projects for the City of Renton, City of Puyallup, CH2M Hill and Point Ruston LLC; project value ranging from $20k to $2M. Responsibilities include the overall management of construction operations including but not limited to the management of projects from identification to closeout; develop, maintain and forecast project budgets; negotiate and write subcontracts; develop and maintain CPM schedules; develop and review construction methods; maintain safety standards; estimating and change order pricing; contract administration; supervise project engineers and fieldpersonnel. PELLCO Construction, Inc. October 2012 — March 2015 Project Manager, Heavy Civil Projects for Seattle City Light and the University of Washington; project value ranging from $2m to $5m. Responsibilities include management of project from identification to closeout; develop, maintain and forecast project budgets; negotiate and write subcontracts; develop and maintain CPM schedules; develop and review construction methods; maintain safety standards; estimating and change order pricing; contract administration; supervise project engineers and fieldpersonnel. Northwest Construction, Bellevue, WA July 2010 — October 2012 Project Manager, Heavy Civil Projects for WSDOT, Sound Transit and SCORE; project value ranging from $50m to$I00m; subcontracts ranging $2m to $1 Im. Responsibilities include management of project from identification to closeout; develop, maintain and forecast project budgets; negotiate and write subcontracts; develop and maintain CPM schedules; develop and review construction methods; maintain safety standards; estimating and change order pricing; contract administration; supervise project engineer and field personnel. Volker Wessels-MidMountain Contractors, Kirkland, WA August 2005-February 2010 Project Manager, Heavy Civil Projects for WSDOT, City of Seattle, City of Tacoma, and the City of Kenmore; contracts ranging from $2m to $33m. Responsibilities include management of project from identification, to closeout; develop, maintain and forecast project budgets; negotiating and writing subcontracts; develop and maintain CPM schedules; develop and review construction methods; maintain safety standards; estimating and change order pricing; contract administration; supervise project engineer and field personnel. Kiewit Pacific Company, Renton, WA December 2003-August 2005 Engineer, Heavy Civil Light Rail projects C700 and C810 for Sound Transit -contract amount $100m. Responsibilities included general engineering tasks; develop and maintain budgets; quality control; maintain safety standards; develop and review formwork design and shoring methods; scheduling; estimating; quantity tracking; document control; contract administration. Gary Merlino Construction Co., Inc., Seattle, WA April 2002-December 2003 Engineer, Heavy Civil Projects for the City of Seattle, King County Metro, City of Redmond, City of Bellevue, Portof Seattle and various private firms; contracts ranging from $500k to $15m. Responsibilities included estimating; scheduling; submittals; RFI's; cost tracking; billing; contract negotiations; payroll; subcontract coordination and various contract administrative duties. Rich Pentin Project Superintendent 2002 - 2018 Olson Brothers Excavating, Inc. City of Renton j Maplewood Creek Stormwater Outfall Improvements October 2015 - Present Responsibilities: Supervise the installation of approximately 110OLF of storm pipe which outfalls to Maplewood Creek. Installing 10 Type I catch basins and 4 Type II —48" catch basins. Installing 54-inch diameter HDPE energy dissipator outfall structure including placement of 20 tons of rip :rap and 150 square yards geotextile fabric. Removal and replacement of asphalt concrete pavement; asphalt overlay, concrete curbs and gutters. Landscape and property restoration. Northwest Construction, Project Superintendent Turner / Sound Transit U240 Capitol Hill Station February 2012— December 2014 Responsibilities: Supervise open -cut retained excavation and grading. Installation of underground utilities including concrete incased ductbanks and power and communication vaults. Gary Merlino Construction, Project Superintendent Absher / Seattle Housing Authority Highpoint Redevelopment Project January 2003 December 2004 Responsibilities: Supervise excavation, site grading and utility installations including approximately 2 miles of concrete incased ductbanks and 100ea power and communication vaults. Gary Merlino Construction, Utility Foreman Sound Transit C910 Tacoma Link Light Rail January 2001 — August 2002 Responsibilities: Supervise utility installations including concrete incased ductbanks and vaults for the light rail system. Professional Project References Tommy Edwards, Seattle City Light, U240 Capital Hill Station, 206-386-1642 Dennis Smith, Senior Superintendent Absher Construction, Highpoint Redevelopment Project, 253-845-9544 Andrew Douherty, Seattle Housing Authority, Highpoint Redevelopment Project, 206-615-3524 Benny Reynolds, Now with NW Construction was the Superintendent for Merlino on the Sound Transit C910 Project, 206-793-7611 DBE Equipment List as of 111122 Excavators 08E Location Out on Equip # Model Serial # Attachments Service Hours Rent 'Woodinville 1225 113 Cat 315C C5C4493 1-36", 1-60", Clean up, Thumb, 'Woodinville 1225 114 Komatsu PC-128 7792 24" 1-33" 60" Clean 1,Thumb, Rubber Tr Pallis 1240 117 Hitachi ZX85-5 17358 4" ' Yelm 1260 118 Hitachi-245-5LO 4001 24",42",64"MUCK Fox yard 119 Kobelco SK-210-LC-8 9V3345 36"HOEPAC THUMB Fox yard 120 Hitachi ZX225 209529 48",60"MUCK, THUMB Meridian 1259 122 Cat 320C-LV PAC00955 24",36",47,46",60" MUCK, THUMB Yelm 1260 124 Cat 328 RMX00421 20".36".54" Meridian 1259 125 Cat 305.5 FKY00796 12" 24" 48"MUC BLADE,THUMB,RUBBER Pro Vac dump 126 Cat 311C CKE01763 36",DIG,BLADE,THUMB shop 127 CAT 314c PAC01310 60" CLEAN UP Woodinville 1 1225 JD MINI 60 12" 36" 48"CLEAN UP 52", Yelm 1260 1 130 303.5 JWY00542 116" 48"MU KTHUMB BLADE RUBBER TRACK Yelm 1 1260 1 131 30B FJX04916 24",r,8"MUCKjNUMB,RUSBER TRACK 1260. OBE Location Out on Rant Equip # Model rlal # Attachments Service Hours Meridian 1259 201 JD 850 C -So 939863 shop 205 JD 450H 93287<3 Brushrake Yelm 1260 207 JD 556H 910642 Disc Loaders OBE Location Out on Rent E ui # Model Serial # Attachments Service Hours P.R.S. xxx JD 624 Loader Bucket ox ar J D 544 LOADER 620702 FORKS, BUCKET Fox yard 30B CAT 930 K RHN01000 FORKS, BUCKET Yelm 1260 309 CAT950H K5K03006 FORKS, BUCKET Woodinville 1225 Wacker 80 Forks, Bucket BE Latatlarl Out on E u3 # Model Serial # Attachments Service Hours Rent Pallis 1240 406 Cat 420 D FDP 19562 FORKS,HOEPAC Shop 407 Cat 420 D I DP23003 Ext. Hoe. FORKS, HOEPAC Meridian 1259 409 Cat 420 D F1311302372 Hoepar, Forks. 4wa , Ext Hoa,24'BUCKET Yelm 1260 410 Cat 420 F FDP19591 FORKS, M4SC OBE Location Out on # Model Serial # Attachments Service Hours Rent ECONO VAC ___Equig 601 MO-45 Gen Set GENERAT RROR 3PH CAPABLE 602 MO-40 Gen Set OUT OF SERVICE FOX YARD 603 IR185 Comp AIR COMPRESSOR ro Vac dumpsite 604 Broce Rc-300 Sweeper 86767 BROOM FOX YARD 605 MO-10 Gen Set GENERATOR 1PH ONLY Shop 606 1 Cat 257-B Skid SLK05266 SKID STEER BLADE ATTACHMENT TRK Yard 607 Interstate Tilt Deck EMO13419 3 AXLE FOX YARD 608 LOADTRAIL 34333 DUMP TRAILER FOX YARD XXX 609 TRAIL KING M062481 CAR TRAILER STEVE O XXX 610 TRAILKING M067256 CAR TRAILER Fox Yard 611 SULLAIR Sows AIR COMPRESSOR FUX HARD I AAA b12 WYLIE 89 'WA T tR TRAILER SDU UAL shop bi3 CAI 272DSKED SITYG0251 SKIDSTEER, GRINDER. FORKS FOX YARD Felco Conveyor FOX YARD Rooster Ripper FOX YARD Hard Pan Bucket WOODINVILLE 1225 614 Multiquip Genset 8104115 Genset 11400 WOODINVILLE 1225 615 Terex light tower a1411909 light tower 6217 WOODINVILLE 1225 616 Terex AL411999 light tower 6978 WOODINVILLE 1225 617 Terexalight tower AL4111000 light tower 5186 Pro Vac I Orting 618 Multiquip Genset G1500123 Genset Yelm 1260 700 Sakai SV-510D OPEN 30163 Pape 705 Sakai 9V-510T CAB Fox Yard 706 CB 224 Double Drum 2X400228 Yelm 1260 808 MH-400 Haul Truck HM-400.2 1237 Truck Number Modal Year Serial Number ITraltiLue T RK YRD 1 33 1 KW T800W 2018 Lowbo A en SHOP XXX 15 KW W-300 1999 828213 ILube / Fuel Truck Yelm 1260 7 STERLING WATER TR 2004 4AN26484 'Water Truck on road TRK YRD 42 K. W. T880 2017 173056 3 AXLE PUP 163352 TRK YRD 43 K.W. T880 2017 173054 3 AXLE PUP 173054 TRK YRD 44 K.W. T880 2017 173055 3 AXLE PUP 153346 TRK YARD 1 D558449 Side Dump TRK YARD 22 IHC 9200 2001 IN001398 OSW SIDE DUMP TRK YARD 30 T800 2015 429459 P TRK YARD 31 T800 2015 429460 PUP TRK YARD 32 T800 2015 429461 PUP TRK YARD 'Woodinville 1225 35 GMC 5 YARD DUMP 2005 505039 Sumner 1255 37 CHEVY C-7500 2000 514030 shop 40 FREIGHTFL80 2003 HK74658 WATER TRUCK Truck Yard UZTucls LI ht lfrucks Model Year License Number I Last 4 of Vin Assl ned to: 25 Ford F-450 2000 B63349C / 9663 STEVE HOLT 26 Ford F-450 2000 B63056C / 7643 27 Ford F-550 2005 A07600X /7950 Gus 34 Ford F-450 1999 A36258Z / 2583 49 Ford F-550 2008 844567E / 5234 Jared 50 Ford F- 2003 !A29312T / 2510 sho 99 zu elico150 IsuHter 1998 k36257Z / 1245 TONY P Fox Yard Asphalt ZIPPer BIDDER RESPONSIBILITY CRITERIA Statement that Bidder Has Not Been Disqualified This statement is required by state law (RCW 39.04.350(1)(d)) to be submitted to the City before the contract can be awarded. The bidder hereby certifies that, within the three-year period immediately preceding the bid solicitation date (March 1, 2022), the bidder has not been disqualified from bidding on any public works contract under RCW 39.06.010 or 39.12.065(3). Olson Brothers Excavating, Inc. Bidder's Busine s Name Signature of Authorized Official* Steve Olson Printed Name Vice President Title 3/1 /2022 Puyallup WA Date City State * If a corporation, proposal must be executed in the corporate name by the president or vice-president (or any other corporate officer accompanied by evidence of authority to sign). If a co -partnership, proposal must be executed by a partner. Kensington Drainage Improvements/Holcomb 20 February 14, 2022 Project Number: 18-3019 BIDDER RESPONSIBILITY CRITERIA Certification of Compliance with Wage Payment Statutes This certification is required by state law (RCW 39.04.350(2)) to be submitted to the City before the contract can be awarded. The bidder hereby certifies that, within the three-year period immediately preceding the bid solicitation date (March 1, 2022), the bidder is not a "willful" violator, as defined in RCW 49.48.082, of any provision of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and notice of assessment issued by the Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction. I certify under penalty of perjury under the laws of the State of Washington that the foregoing is true and correct. Olson Brothers Excavating, Inc. _ Bidder'sLBusiine Name Signature of Authorized Official* Steve Olson Printed Name Vice President Title 3/1 /2022 Date Puyallup City WA State * If a corporation, proposal must be executed in the corporate name by the president or vice-president (or any other corporate officer accompanied by evidence of authority to sign). If a co -partnership, proposal must be executed by a partner. Kensington Drainage Improvements/Holcomb 21 February 14, 2022 Project Number: 18-3019 PROPOSAL SIGNATURE PAGE The undersigned bidder hereby proposes and agrees to start construction work on the Contract, if awarded to him/her, on or before ten (10) calendar days from the date of the Notice to Proceed, and agrees to complete the Contract within 30 working days after issuance of the City's Notice to Proceed. The undersigned bidder hereby agrees to submit all insurance documents, performance bonds and signed contracts within ten (10) calendar days after City awards the Contract. The City anticipates issuance of the Notice to Proceed on the day of the preconstruction meeting. No bidder may withdraw his/her bid for a period of sixty (60) calendar days after the day of bid opening. The required bid security consisting of a bid bond, cashier's check or cash in an amount equal to 5% of the total amount is hereto attached. Notice of acceptance of this bid or request for additional information shall be addressed to the undersigned at the address stated below. Receipt of Addendum No.'s to the plans and/or specifications is hereby acknowledged. Failure to acknowledge receipt of the addenda may be considered an irregularity in this proposal. By signing this Proposal Signature Page, the undersigned bidder agrees to accept all contract forms and documents included within the bid packet and to be bound by all terms, requirements and representations listed in the bid documents whether set forth by the City or by the Bidder. DATE: 3/1 /2022 Olson Brothers Excavating. NAME OF BI R Signature of Authorized Representative Steve Olson, Vice President (Print Name and Title) 6622 112th St. E. Address Puyallup, WA 98373 Kensington Drainage Improvements/Holcomb 22 February 14, 2022 Project Number: 18-3019 BID BOND FORM KNOW ALL MEN BY THESE PRESENTS: That we, Olson Brothers Excavating, Inc. , as Principal, and Travelers Casualty and Surety Company of America , as Surety, are held and firmly bound unto the CITY OF KENT, as Obligee, in the penal sum of Five Percei,t (5%) of Bid Amount Dollars, for the payment of which the Principal and the Surety bond themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, by these presents. The condition of this obligation is such that if the Obligee shall make any award to the Principal for E Tacoma St. - Kensington Ave. Drainage Improvements/Project Plumber: 18-3019 According to the terms of the proposal or bid made by the Principal thereof, and the Principal shall duly make and enter into a contract with the Obligee in accordance with the terms of said proposal or bid and award and shall give bond for the faithful performance thereof, with Surety or Sureties approved by the Obligee; or if the Principal shall, in case of failure so to do, pay and forfeit to the Obligee the penal amount of the deposit specified in the invitation to bid, then this obligation shall be null and void; otherwise it shall be and remain in full force and effect and the Surety shall forthwith pay and forfeit to the Obligee, as penalty and liquidated damaged, the amount of this bond. SIGNED, SEALED AND DATED THIS 1st DAY OF March 2022 Olson Brothe Excavati C. ,•`"` FIND"i NCIPAL Steve Olson, Vice President AN ..SU. �. i r Casu a d Surety Company of America v, : _ LU . OON 5. Y ;; :,_ N -in-Fact " z Holli Albers, Attorney 20 Received return of deposit in the sum of Kensington Drainage Improvements/Holcomb 23 February 14, 2022 Project Number: 18-3019 TRAVELERS Travelers Casualty and Surety Company of America Travelers Casualty and Surety Company St. Paul Fire and Marine Insurance Company POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company are corporations [filly organized under the laws of the State of Connecticut (herein collectively tailed the "Companies"). and that the Companies do hereby make, constitute and appoint HOLLi ALBERS of KNOXVILLE . Tennessee . their true and lawful Attorneys) -in -Fact to sign, execute. seal and acknowledge any and all bonds, recognizances, conditional undertakings and other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law. IN WITNESS WHEREOF, the Companies have caused this instrument to be signed, and their corporate seals to be hereto affixed, this 21st day of April, 2021. � Fyp Svl�Ilp �F�ir xyG �� 1070M. c HARTRW, {rcmdNR ?y CSk►Y. e CONN, SIX r State of Connecticut By: City of Hartford ss, Hobert L. Rane , enior Vice President On this the 21st day of April, 2021, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior Vice President of each of the Companies, and that he, as such, being authorized so to do, executed the foregoing instrument for the purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer. .�Nu,, •i�� IN WITNESS WHEREOF, I hereunto set my hand and official seal.'° � My Commission expires the 30th day of June, 2026 l� Anna P. Nowik, Notary Public ((t4Do�TAF11y F' This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of the Companies, which resolutions are now in full force and effect, reading as follows: RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attomeys-in-Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her; and it is FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such delegation is in writing and a copy thereof is filed in the office of the Secretary; and it is FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President. any Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary; or (b) duly executed (under seal, if required) by one or more Attorneys -in -Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of Attomey or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attomeys-in- Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory to the nature thereof, and any such rower of Attorney or certificate bearing such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached. I, Kevin E. Hughes, the undersigned, Assistant Secretary of ea c ,M.,;hp,,Companies, do hereby certify that the above and foregoing is a true and correct copy of the Power of Attorney executed by said Cerr�}0t� of r '"ains in full force and effect. Dated this 1st day of March 2022 �, * 3 i Cps R❑ �rs,�srrauri, � "V iUatcorra. � Ee cairo� : �s :• �1, r AcaNx coxN fiat 's `'•,�� ' ��'��` Kevin E. Hughes, Assl t� and Secretary To verify 66e aufhent k ty of this Pbwer oi'+Nt&?A4, please call us at 1-8a0-4?r-388a Please reter to the above -named Attorneys) -in -Fact and the dreWils of the bond to which this PbwierofAftorney is atbn*ed; CITY OF KENT COMBINED DECLARATION FORM: NON -COLLUSION, MINIMUM WAGE NON -COLLUSION DECLARATION I, by signing the proposal, hereby declare, under penalty of perjury under the laws of the United States that the following statements are true and correct: AND 1. That the undersigned person(s), firm, association or corporation has (have) not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with the project for which this proposal is submitted. 2. That by signing the signature page of this proposal, I am deemed to have signed and to have agreed to the provisions of this declaration. MINIMUM WAGE AFFIDAVIT FORM I, the undersigned, having duly sworn, deposed, say and certify that in connection with the performance of the work of this project, I will pay each classification of laborer, workman, or mechanic employed in the performance of such work not less than the prevailing rate of wage or not less than the minimum rate of wage as specified in the principal contract; that I have read the above and foregoing statement and certificate, know the contents thereof and the substance as set forth therein is true to my knowledge and belief. E Tacoma St. — Kensington Ave. Drainage Improvements Project Number: 18-3019 NAME OF PROJECT Olson Brothers Excavating, Inc. NAME OF BIDDER'S FIRM Steve Olson, Vice President SIGNATURE OF AUTHORIZED REPRESENTATIVE OF BIDDER Kensington Drainage Improvements/Holcomb 24 February 14, 2022 Project Number: 18-3019 This change order form is for exam le purposes only. By submittin a bid the bidder a rees tv be bound b the terms of this chan a order form for an change orders. CHANGE ORDER NO. [Enter # 1, 2, 3, etc.] NAME OF CONTRACTOR: Insert Com an Name ("Contractor") CONTRACT NAME & PROJECT NUMBER: Insert Name of Ori inai Contract &Pro ect # if a iicable ORIGINAL CONTRACT DATE: Insert Date Original Contract was Signed This Change Order amends the above -referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: 1. Section 1 of the Contract is hereby modified to revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: [Insert detailed description of additional materials, services, etc., that are needed which necessitate this change order - Be as detailed as possible. You may also refer to an attached exhibit, but clearly identify the exhibit by title and date] 2. The contract amount and time for performance provisions of Section 1 of the Contract are also modified as follows: Original Contract Sum, $ (including applicable alternates and WSST) Net Change by Previous Change Orders $ (incl. applicable WSST) Current Contract Amount $ (incl. Previous Change Orders) Current Change Order $ I Applicable WSST Tax on this Change $ Order Revised Contract Sum $ Kensington Drainage Improvements/Holcomb 25 February 14, 2022 Project Number: 18-3019 Original Time for Completion (insert date) Revised Time for Completion under prior Change Orders (insert date) Days Required (f) for this Change working days Order Revised Time for Completion (insert date) In accordance with Sections 1-04.4 and 1-04.5 of the Kent Special Provisions and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below. Also, pursuant to the above -referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the Contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby ratified and affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written below. CONTRACTOR: CITY OF KENT: By: BY: (signature) (signature) Print Name: Print Name: Chad Bieren P.E. Its Its PublicW o r _ks Director (title) (title) DATE: DATE: APPROVED AS TO FORM: (applicable if Mayor's signature required) Kent Law Department Kensington Drainage Improvements/Holcomb 26 February 14, 2022 Project Number: 18-3019 BIDDER'S CHECKLIST The following checklist is a guideline to help the Contractor make sure all forms are complete. The bidder's attention is especially called to the following forms. Failure to execute these forms as required may result in rejection of any bid. Bidder's Package should include the following: Bid Document Cover Sheet filled out with Bidder's Name ....................❑ Orderof Contents................................................................................. ❑ Invitationto Bid...................................................................................❑ ContractorCompliance Statement........................................................ ❑ Date............................................................................................ ❑ Have/have not participated acknowledgment .............................❑ Signatureand address................................................................ ❑ Declaration - City of Kent Equal Employment Opportunity Policy ........ ❑ Dateand signature..................................................................... ❑ AdministrativePolicy........................................................................... ❑ Proposal............................................................................................... ❑ First line of proposal - filled in ................................................... ❑ Unit prices are correct................................................................ ❑ Minimum bid prices are correct ...................................................❑ Subcontractor List (contracts over $1M — HVAC, Plumbing, & Electrical) ............ ❑ Subcontractors listed properly .................................................... ❑ Signature.................................................................................... ❑ Subcontractor List (contracts over $1M — Structural Steel & Rebar Installation) — ❑ Subcontractorslisted properly ....................................................❑ Dateand signature..................................................................... ❑ Contractor's Qualification Statement ................................................... ❑ Complete and notarized.............................................................. ❑ Statement that Bidder Has Not Been Disqualified ................................ ❑ Certification of Compliance with Wage Payment Statutes ....................❑ ProposalSignature Page...................................................................... ❑ AllAddenda acknowledged......................................................... ❑ Date, signature and address....................................................... ❑ BidBond Form..................................................................................... ❑ Signature, sealed and dated ....................................................... ❑ Powerof Attorney....................................................................... ❑ (Amount of bid bond shall equal 50/o of the total bid amount) Combined Declaration Form................................................................. ❑ Signature.................................................................................... ❑ ChangeOrder Form (Example).............................................................❑ Bidder's Checklist................................................................................ ❑ The following forms are to be executed after the Contract is awarded: A) CONTRACT This agreement is to be executed by the successful bidder. B) PAYMENT AND PERFORMANCE BOND To be executed by the successful bidder and its surety company. The following form is to be executed after the Contract is completed: A) CITY 0F KENT EQUAL EMPLOYMENT OPPORTUNITY COMPLIANCE STATEMENT To be executed by the successful bidder AFTER COMPLETION of this contract. Kensington Drainage Improvements/Holcomb 27 February 14, 2022 Project Number: 18-3019 0T WA2f11YGTOM PAYMENT AND PERFORMANCE BOND TO C I TY OF KENT KNOW ALL MEN BY THESE PRESENTS: Bond No. 107570222 That we, the undersigned, Olson Brothers Excavating, Inc. as Principal, and Travelers Casualty and Surety Company of America Connecticut_ a Corporation organized and existing under the laws of the State of Vh6iNkxpom as a Surety Corporation, and qualified under the laws of the State of Washington to become Surety upon bonds of Contractors with Municipal Corporations, as Surety, are jointly and severally held and firmly bound to the CITY OF KENT in the penal sum of $407,406,00 * , together with any adjustments, up or down, in the total contract price because of changes in the contract work, for the payment of which sum on demand we bind ourselves and our successors, heirs, administrators or personal representatives, as the case may be. * Four Hundred Seven Thousand, Four Hundred Six and No/100 Dollars This obligation is entered into in pursuance of the statutes of the State of Washington, and the Codes and Ordinances of the CITY OF KENT, Nevertheless, the conditions of the above obligation are such that: WHEREAS, under and pursuant to a motion, duly made, seconded and passed by the City Council of the City of Kent, King County, Washington, the Mayor of the City of Kent has let or is about to let to the above bounden Principal, a certain contract, the said contract providing for construction of E Tacoma St. — Kensington Ave. Drainage I mprovements/Project Number: 18-3018 (which contract is referred to herein and is made a part hereof as though attached hereto), and WHEREAS, the Principal has accepted, or is about to accept, the contract, and undertake to perform the work therein provided for in the manner and within the time set forth: NOW, THEREFORE, for non-FHWA projects only, if the Principal shall faithfully perform all the provisions of said contract in the manner and within the time herein set forth, or within such extensions of time as may be granted under the said contract, and shall pay all laborers, mechanics, subcontractors and material men, and all persons who shall supply the Principal or subcontractors with provisions and supplies for the carrying on of said work and shall indemnify and hold the CITY OF KENT harmless from any damage or expense by reason of failure of performance as specified in said contract or from defects appearing or developing in the material or workmanship provided or performed under said contract, then and in that event this obligation shall be void; but otherwise it shall be and remain in full force and effect. IN WITNESS WHEREOF, the above bounden parties have executed this instrument under their separate seals. The name and corporate seal (if required by law) of each corporate party is hereto affixed and duly signed by its undersigned representatives pursuant to authority of its governing body. Kensington Drainage Improvements/Holcomb 28 February 14, 2022 PrQJect Number; 18.3019 DATE: 3/21 2022 Kasev Samons Bryce Sturrock PRINT NAME DATE: 3/21 /2022 C%I:1go] ' 'ttai� HARTFORD ; CONN : o Olson Brothers Excavatin Inc. PR INC I PAL (enter grin ' I's name e BY: TITLE: Steve Olson, vice President DATE: 3/21 /2022 CORPORATE SEAL: Travelers Casualty and Surety Company of America SURETY -r BY: DATE: March 18, 2022 TITLE: Holli Albers, Attorney -in -Fact ADDRESS: 1501 Fourth Ave., Suite 1000 Seattle WA 98101 CERTIFICATE AS TO CORPORATE SEAL I hereby certify that I am the (Assistant) Secretary of the Corporation named as Principal in the within Bond; that Steve Olson Who signed the said bond on behalf of the Principal ,olson Brothers Excavating, Inc. of the said Corporation; that I know his/her signature thereto is genuine, and that said Bond was duly signed, sealed, and attested for and in behalf of said Corporation by authority of its governing body. --,I SECRETARY OR ASSISTANT SECRETARY Mike Olson, Secretary Kensington Drainage Improvements/Holcomb 29 February 14, 2022 Project Number; 18-3019 Travelers Casualty and Surety Company of America Travelers Casualty and Surety Company TRAVELERS. St. Paul Fire and Marine Insurance Company POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein collectively called the "Companies"). and that the Companies do hereby make, constitute and appoint Holli Albers of TACOMA . Washington , their true and lawful Alto rney(s)-in-Fact to sign, execute, seal and acknowledge any and all bonds, recognizances, conditional undertakings and other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law. IN WITNESS WHEREOF, the Companies have caused this instrument to be signed, and their corporate seals to be hereto affixed, this 21st day of April, 2021. s r A,ya a y NC. �y, y 4114rr8�7, IIANTFOf�, l CONN SIX i State of Connecticut By:. City of Hartford ss. Robert L Raney,lteriior Vice President On this the 21st day of April, 2021, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior Vice President of each of the Companies, and that he, as such, being authorized so to do, executed the foregoing instrument for the purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer. IN WITNESS WHEREOF, I hereunto set my hand and official seal. My Commission expires the 30th day of June, 2026 ff moo`^ r10T7ARP _ 1 ^� .NY yt � F0�`�c Anna P. Nowik, Notary Public ti .....t� This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of the Companies, which resolutions are now in full force and effect, reading as follows: RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attomeys-in-Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her; and it is FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such delegation is in writing and a copy thereof is fled in the office of the Secretary; and it is FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary; or (b) duly executed (under seal, if required) by one or more Attorneys -in -Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of Attorney or to any certificate relating thereto appointing Resident Vice presidents, Resident Assistant Secretaries or Attorneys -in - Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of Attorney or certificate bearing such facsimile signature or facsimile seal stall be valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached. I, Kevin E. Hughes, the undersigned, Assistant Secretary of earh,&tli%VL lomj)anies, do hereby certify that the above and foregoing is a true and correct copy of the Power of Attorney executed by said Coi�npVt�6idR__'6% in full force and effect. . C •. 0 Dated this 18th day of March 2022 , : ` %COW; SIX ;�ro ON 1E r li.�y ........ ^j . y.J� •�� Kevin E. Hughes, Assiittant Secretary f�'�f! �7f 1117 `414ti«k'�y` To verify the authenticity of this Power of Attorney, please caU us at 1 -800-421 -3880. Please refer to the above -named Attomey(s)-In-Pact and the detalls of the bond to which this PowerofAttonW is attached. CONTRACT THIS AGREEMENT, is entered into between the CITY OF KENT, a Washington municipal corporation ("City"), and Olson Brothers Excavating, Inc. organized under the laws of the State of Washington located and doing business at 6622 112th St. E., Puyallup, WA 98373 ("Contractor"). WITNESS: In consideration of the terms and conditions contained in this Agreement and in the project documents, plans, and specifications all of which are a part of this Agreement, the parties agree as follows: 1. The Contractor shall do all work and furnish all tools, materials, and equipment for: E Tacoma St. — Kensington Ave. Drainage Improvements/Project Number: 18-3019 in accordance with and as described in the Contract and shall perform any alterations in or additions to the work provided under the Contract and every part thereof. The Contract shall include all project specifications, provisions, and plans; the City's general and special conditions; the 2022 Standard Specifications for Road, Bridge, and Municipal Construction, as prepared by the Washington State Department of Transportation and the Washington State Chapter of the American Public Works Association, including all published amendments issued by those organizations, if applicable ("Standard Specifications"); the City's bid documents; and the Contractor's response to the City's bid. The Contractor is responsible to obtain copies of the 2022 WSDOT Standard Specifications including the latest amendments issued by WSDOT as of the date of bid opening. Unless otherwise directed by the City, work shall start within ten (10) days after the City issues its Notice to Proceed and work shall be physically completed within 30 working days. The term of this Contract shall continue until all work has been completed, Final Acceptance has occurred, and all Contractor obligations have been fulfilled. The Contractor shall provide and bear all expense of all equipment, work, and labor of any sort whatsoever that may be required for the transfer of materials and for constructing and completing all the work provided for in the Contract, except where the specifications allocate that responsibility to the City. The total contract amount for all Work performed under this Contract, including Washington State Sales Tax, is $407,406. 2. The City hereby promises and agrees with the Contractor to employ, and does employ, the Contractor to provide the materials and to do and cause to be done the above described work and to complete and finish the same according to the Contract and the terms and conditions herein contained and hereby contracts to pay for the same according to the Contract and the schedule of unit or itemized prices provided by Contractor in its response to the City's bid, at the time and in the manner and upon the conditions provided for in the Contract. 3. The Contractor for itself, and for its heirs, executors, administrators, successors, and assigns, does hereby agree to the full performance of all covenants herein contained upon the part of the Contractor. Kensington Drainage Improvements/Holcomb 30 March 2, 2022 Project Number: 18-3019 4. It is further provided that no liability shall attach to the City by reason of entering into this contract, except as expressly provided herein. 5. Contractor shall defend, indemnify, and hold the City, its officers, officials, employees, agents, volunteers and assigns harmless from any and all claims, injuries, damages, losses or suits, including all legal costs and attorney fees, arising out of or in connection with the performance of this contract, except for injuries and damages caused by the sole negligence of the City. The City's inspection or acceptance of any of Contractor's work when completed shall not be grounds to avoid any of these covenants of indemnification. Should a court of competent jurisdiction determine that this contract is subject to RCW 4.24.115, then, in the event of liability for damages arising out of bodily injury to persons or damages to property caused by or resulting from the concurrent negligence of the Contractor and the City, its officers, officials, employees, agents and volunteers, the Contractor's liability hereunder shall be only to the extent of the Contractor's negligence. IT IS FURTHER SPECIFICALLY AND EXPRESSLY UNDERSTOOD THAT THE INDEMNIFICATION PROVIDED HEREIN CONSTITUTES THE CONTRACTOR'S WAIVER OF IMMUNITY UNDER INDUSTRIAL INSURANCE, TITLE 51 RCW, SOLELY FOR THE PURPOSES OF THIS INDEMNIFICATION. THE PARTIES FURTHER ACKNOWLEDGE THAT THEY HAVE MUTUALLY NEGOTIATED THIS WAIVER. The provisions of this section shall survive the expiration or termination of this contract. 6. Contractor agrees, upon the City's written demand, to make all books and records available to the City for inspection, review, photocopying, and audit in the event of a contract related dispute, claim, modification, or other contract related action at reasonable times (not to exceed three (3) business days) and at places designated by the City. 7, The Contractor shall procure and maintain, during the term of construction and throughout the specified term of maintenance, insurance of the types and in the amounts described in Exhibit A attached and incorporated by this reference. 8. Contractor is responsible for locating any underground utilities affected by the work and is deemed to be an excavator for purposes of RCW Ch. 19.122, as amended. Contractor shall be responsible for compliance with RCW Ch. 19.122, including utilization of the "one call" locator service before commencing any excavation activities. Kensington Drainage Improvements/Holcomb 31 February 14, 2022 Project Number: 18-3019 CITY OF KENT DANA RALPH, MA OR DATE: 04/05/2022 ATTEST: KIMBERLEOPI. KOMOTO, CITY CLERK APPROVED AS TO FORM: KENT LAW DEPARTMENT CONTRACTOR Olson Brothers cavating, Inc. BY: PRINT NAME: Steve Olson TITLE: Vice President DATE: 3/21 /2022 Kensington Drainage Improvements/Holcomb 32 February 14, 2022 Project Number: 18-3019 EXHIBIT INSURANCE REQU I REMENTS FOR CONSTRUCTION PROJECTS Insurance The Contractor shall procure and maintain for the duration of the Agreement, insurance against claims for injuries to persons or damage to property which may arise from or in connection with the performance of the work hereunder by the Contractor, their agents, representatives, employees or subcontractors. A. Minimum Scope of Insurance Contractor shall obtain insurance of the types described below; Commercial General Liability insurance shall be written on ISO occurrence form CG 00 01 or its equivalent, with minimum limits of $3,000,000 per occurrence and in the aggregate for each 1 year policy period. This coverage may be any combination of primary, umbrella or excess liability coverage affording total liability limits of not less than $3,000,000 per occurrence and in the aggregate. Products and Completed Operations coverage shall be provided for a period of 3 years following Substantial Completion of the work. The Commercial General Liability insurance shall be endorsed to provide the Aggregate per Project Endorsement ISO form CG 25 03 11 85. The City shall be named as an Additional Insured under the Contactor's Commercial General Liability insurance policy with respect to the work performed for the City. All endorsements adding Additional Insureds shall be issued on form CG 20 10 11 85 or a form deemed equivalent, providing the Additional Insureds with all policies and endorsements set forth in this section. 2. Automobile Liability insurance covering all owned, non -owned, hired and leased vehicles. Coverage shall be written on Insurance Services Office (ISO) form CA 00 01 or a substitute form providing equivalent liability coverage. If necessary, the policy shall be endorsed to provide contractual liability coverage. 3. Workers' Compensation coverage as required by the Industrial Insurance laws of the State of Washington. B. Minimum Amounts of Insurance Contractor shall maintain the following insurance limits: Commercial General Liability insurance shall be written with minimum limits of $3,000,000 per occurrence and in the aggregate for each 1 year policy period. This coverage may be any combination of primary, umbrella or excess liability coverage affording total liability limits of not less than $3,000,000 per occurrence and in the aggregate. Products and Completed Operations coverage shall be provided for a period of 3 years following Substantial Completion of the work. Kensington Drainage Improvements/Holcomb 33 February 14, 2022 Project Number: 18-3019 EXH I BIT A (Continued) 2. Automobile Liability insurance with a minimum combined single limit for bodily injury and property damage of $1,000,000 per accident. C. Other Insurance Provisions The insurance policies are to contain, or be endorsed to contain, the following provisions for Automobile Liability and Commercial General Liability: 1. The Contractor's insurance coverage shall be primary insurance as respect the City. Any insurance, self-insurance, or insurance pool coverage maintained by the City shall be excess of the Contractor's insurance and shall not contribute with it. 2. The Contractor's insurance shall be endorsed to state that coverage shall not be cancelled by either party, except after thirty (30) days prior written notice by certified mail, return receipt requested, has been given to the City. 3. The City of Kent shall be named as an additional insured on all policies (except Professional Liability) as respects work performed by or on behalf of the contractor and a copy of the endorsement naming the City as additional insured shall be attached to the Certificate of Insurance. The City reserves the right to receive a certified copy of all required insurance policies. The Contractor's Commercial General Liability insurance shall also contain a clause stating that coverage shall apply separately to each insured against whom claim is made or suit is brought, except with respects to the limits of the insurer's liability. D. Contractor's Insurance for Other Losses The Contractor shall assume full responsibility for all loss or damage from any cause whatsoever to any tools, Contractor's employee owned tools, machinery, equipment, or motor vehicles owned or rented by the Contractor, or the Contractor's agents, suppliers or contractors as well as to any temporary structures, scaffolding and protective fences. E. Waiver of Subrogation The Contractor and the City waive all rights against each other any of their Subcontractors, Sub -subcontractors, agents and employees, each of the other, for damages caused by fire or other perils to the extend covered by Builders Risk insurance or other property insurance obtained pursuant to the Insurance Requirements Section of this Contract or other property insurance applicable to the work. The policies shall provide such waivers by endorsement or otherwise. Kensington Drainage Improvements/Holcomb 34 February 14, 2022 Project Number: 18-3019 EXH I B I T A (Continued) F. Acceptability of Insurers Insurance is to be placed with insurers with a current A.M. Best rating of not less than A:VII. G. Verification of Coverage Contractor shall furnish the City with original certificates and a copy of the amendatory endorsements, including but not necessarily limited to the additional insured endorsement, evidencing the Automobile Liability and Commercial General Liability insurance of the Contractor before commencement of the work. H. Subcontractors Contractor shall include all subcontractors as insureds under its policies or shall furnish separate certificates and endorsements for each subcontractor. All coverages for subcontractors shall be subject to all of the same insurance requirements as stated herein for the Contractor. Kensington Drainage Improvements/Holcomb 35 February 14, 2022 Project Number: 18-3019 Client#: 12996 OLSOBROS ACORDTM CERTIFICATE OF LIABILITY INSURANCE DATE (MM/DD/YYYY) 1 3/17/2022 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer any rights to the certificate holder in lieu of such endorsement(s). PRODUCER CONTACT Casey Jackson INAME:Propel Insurance PHONE 253 310-4142 FAX 866 577-1326 A/C No Ext : A/C, No Tacoma Commercial Insurance E-MAIL ADDRESS: casey-json�p p ackr0 elinsurance.com 1201 Pacific Ave, Suite 1000 INSURER(S)AFFORDING COVERAGE NAIC# Tacoma, WA 98402 INSURER A: Bitco National Insuance Company 20109 INSURED INSURER B : Olson Brothers Excavating Inc. 6622 112th Street East INSURER C Puyallup, WA 98373 INSURER D : INSURER E INSURER F : COVERAGES CERTIFICATE NUMBER: REVISION NUMBER: THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACTOR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. LT R LTR TYPE OF INSURANCE ADDL INSR SUBR WVD POLICY NUMBER POLICY EFF MM/DD POLICY EXP MM/DD LIMITS A X COMMERCIAL GENERAL LIABILITY CLAIMS -MADE � OCCUR PD Ded: $2,000 CLP3712058 11/30/2021 11/30/2022 EACH OCCURRENCE $1 OOO OOO PREMISES ERENTED nce $300000 X MED EXP (Any one person) $1 O 000 PERSONAL & ADV INJURY $1,000,000 GENT AGGREGATE LIMIT APPLIES PER: POLICY X1 JECOT LOC OTHER: GENERAL AGGREGATE $ 2,000,000 PRODUCTS - COMP/OP AGG $ 2,000,000 $ A AUTOMOBILE LIABILITY ANY AUTO OWNED SCHEDULED AUTOS ONLY AUTOS HIRED NON -OWNED AUTOS ONLY X AUTOS ONLY CAP3712059 11/30/2021 11/30/202 Ea aINED acid.",) SINGLE LIMIT $1,000,000 X BODILY INJURY (Per person) $ X BODILY INJURY (Per accident) $ PROPERTY DAMAGE Per accident $ A X UMBRELLA LIAB EXCESS LIAB X OCCUR CLAIMS -MADE CUP2821462 11/30/2021 11/30/2022 EACH OCCURRENCE s5,000,000 AGGREGATE s5,000,000 DED I X RETENTION $$1 O 000 $ A WORKERS COMPENSATION AND EMPLOYERS' LIABILITY N ANY PROPRIETOR/PARTNER/EXECUTIVE -- OFFICER/MEMBER EXCLUDED? (Mandatory in NH) If yes, describe under DESCRIPTION OF OPERATIONS below N / A CLP3712058 WA Stop Gap ONLY 11/30/2021 11/30/2022 PER OTH- TAT TE ER E.L. EACH ACCIDENT $1,000,000 E.L. DISEASE - EA EMPLOYEE $1,000,000 E.L. DISEASE- POLICY LIMIT $1,000,000 DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, maybe attached if more space is required) RE: E Tacoma ST - Kensington AVE Drainage Improvements / Project #18-3019 Additional Insured Status applies per attached form(s). Waiver of Subrogation applies per attached form(s). IL" a Gi In a Pf_\ I a• i LVJ A.J aC AL\C Nf AAAGU Lai City of Kent 400 West Gowe Kent, WA 98032 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS. AUTHORIZED REPRESENTATIVE ACORD 25 (2016/03) 1 of 1 #S5055035/M5054756 © 1988-2015 ACORD CORPORATION. All rights reserved. The ACORD name and logo are registered marks of ACORD LMA00 This page has been left blank intentionally. SCHEDULE OF FORMS AND ENDORSEMENTS NAMED INSURED OLSON BROTHERS EXCAVATING. INC. POLICY NUMBER CLP 3 712 058 GU-3076 (04/16) PRIVACY STATEMENT GU-4320 (05/04) ADVISORY NOTICE TO POLICYHOLDERS GU-4871 (09/20) POLICYHOLDER DISCLOSURE - NOTICE OF TERRORISM INSURANCE COVERAGE GU-5066 (08/16) POLICYHOLDER NOTICE GU-2368 (12/18) AUDIT INFORMATION GU-5032 (11/15) ADVISORY NOTICE TO POLICYHOLDERS GU-5200 (04/19) ADVISORY NOTICE TO POLICYHOLDERS GU 2510 (06/96) QUICK REFERENCE - COMMERCIAL GENERAL LIABILITY COVERAGE PART GU-2990 (05/00) FLOOD INSURANCE NOTICE GOX 2278 (12/92) SCHEDULE OF NAMED INSUREDS GOX 2281 (12/92) SCHEDULE OF PREMISES LOCATIONS GOX 2279 (12/92) SCHEDULE OF FORMS AND ENDORSEMENTS CLP-2584 (04/16) COMMERCIAL LINES POLICY DECLARATIONS IL 01 23 (11/13) WASHINGTON CHANGES - DEFENSE COSTS IL O1 46 (08/10) WASHINGTON COMMON POLICY CONDITIONS IL O1 57 (07102) WASHINGTON CHANGES - ACTUAL CASH VALUE IL O1 98 (09/08) NUCLEAR ENERGY LIABILITY EXCLUSION ENDORSEMENT IL 09 35 (07102) EXCLUSION OF CERTAIN COMPUTER RELATED LOSSES IL 09 53 (01/15) EXCLUSION OF CERTIFIED ACTS OF TERRORISM IL 09 83 (01/08) WASHINGTON - AMENDMENT OF TERRORISM EXCLUSIONS GL-2438-PKG (04/16) COMMERCIAL GENERAL LIABILITY DECLARATIONS GOX-2446 (07/95) COMMERCIAL GENERAL LIABILITY SCHEDULE GOX-2446 (07/95) COMMERCIAL GENERAL LIABILITY SCHEDULE GOX-2446 (07/95) COMMERCIAL GENERAL LIABILITY SCHEDULE CG 00 01 (04/13) COMMERCIAL GENERAL LIABILITY COVERAGE FORM GL 687c (01/86) EXCLUSION (DISMANTLING, DEMOLITION, WRECKING OR SALVAGE OPERATIONS) GL-2784 (09/11) EXTENDED LIABILITY COVERAGE GL-3088 (10/19) LAND IMPROVEMENT CONTRACTORS EXTENDED LIABILITY COVERAGE GL-5216 (01121) BREACH RESPONSE COVERAGE SUPPLEMENTAL DECLARATIONS L 1751b (09/14) EXCLUSION (ASBESTOS) L2399B (10/01) LIMITED POLLUTION COVERAGE - "WORK SITES" L 2474a (02/99) EXCLUSION - LEAD CG 03 00 (01/96) DEDUCTIBLE LIABILITY INSURANCE CG 04 35 (12107) EMPLOYEE BENEFITS LIABILITY COVERAGE CG 20 12 (04/13) ADDITIONAL INSURED - STATE OR GOVERNMENTAL AGENCY OR SUBDIVISION OR POLITICAL SUBDIVISION - PERMITS OR AUTHORIZATIONS CG O1 97 (12107) WASHINGTON CHANGES - EMPLOYMENT -RELATED PRACTICES EXCLUSION CG 04 50 (05/08) WASHINGTON CHANGES - WHO IS AN INSURED CG 20 01 (12/19) PRIMARY AND NONCONTRIBUTORY - OTHER INSURANCE CONDITION CG 21 06 (05/14) EXCLUSION - ACCESS OR DISCLOSURE OF CONFIDENTIAL OR PERSONAL INFORMATION AND DATA -RELATED LIABILITY - WITH LIMITED BODILY INJURY EXCEPTION CG 21 09 (06/15) EXCLUSION - UNMANNED AIRCRAFT CG 21 41 (12/19) EXCLUSION - INTERCOMPANY PRODUCTS SUITS CG 21 49 (09/99) TOTAL POLLUTION EXCLUSION ENDORSEMENT CG 21 73 (01/15) EXCLUSION OF CERTIFIED ACTS OF TERRORISM CG 21 86 (12/04) EXCLUSION - EXTERIOR INSULATION AND FINISH SYSTEMS CG 22 34 (04/13) EXCLUSION - CONSTRUCTION MANAGEMENT ERRORS AND OMISSIONS CG 22 79 (04/13) EXCLUSION - CONTRACTORS - PROFESSIONAL LIABILITY CG 26 77 (12104) WASHINGTON - FUNGI OR BACTERIA EXCLUSION GL-4105 (06/02) LIMITATION OF COVERAGE FOR INSUREDS WHO ARE INDIVIDUALS, TRUSTS OR ESTATES GOX-2279 (12/92) SCHEDULE OF FORMS AND ENDORSEMENTS NAMEDINSURED POLICY NUMBER OLSON BROTHERS EXCAVATING, INC. ICLP 3 712 058 GL-4302 (09/14) SILICA EXCLUSION GL-4473 (08/06) BLANKET EXCLUSION - DESIGNATED OPERATIONS COVERED BY A CONSOLIDATED INSURANCE PROGRAM GL-4666 (01/11) EXCLUSION - ENGINEERS, ARCHITECTS OR SURVEYORS PROFESSIONAL LIABILITY GL-4697 (02112) WASHINGTON CHANGES GL-5057 (10/16) ADDITIONAL INSURED - OWNERS, LESSEES OR CONTRACTORS - COMPLETED OPERATIONS GL-5058 (10/16) ADDITIONAL INSURED - OWNERS, LESSEES OR CONTRACTORS - ONGOING OPERATIONS GOX-2545A (04/11) COMMERCIAL PROPERTY SCHEDULE GOX-2545A (04/11) COMMERCIAL PROPERTY SCHEDULE GOX-2545A (04/11) COMMERCIAL PROPERTY SCHEDULE GOX-2545A (04/11) COMMERCIAL PROPERTY SCHEDULE GOX-2545A (04/11) COMMERCIAL PROPERTY SCHEDULE CP 00 10 (10112) BUILDING AND PERSONAL PROPERTY COVERAGE FORM CP 00 30 (10112) BUSINESS INCOME (AND EXTRA EXPENSE) COVERAGE FORM CP 00 90 (07/88) COMMERCIAL PROPERTY CONDITIONS CP 10 30 (09/17) CAUSES OF LOSS - SPECIAL FORM CP 01 40 (07/06) EXCLUSION OF LOSS DUE TO VIRUS OR BACTERIA CP 04 05 (09/17) ORDINANCE OR LAW COVERAGE CP 04 05 (09/17) ORDINANCE OR LAW COVERAGE CP 04 05 (09/17) ORDINANCE OR LAW COVERAGE CP-2230 (05/17) EXTENDED PROPERTY COVERAGE CP 01 26 (10112) WASHINGTON CHANGES CP 01 60 (03/21) WASHINGTON CHANGES - DOMESTIC ABUSE CP 01 79 (10112) WASHINGTON CHANGES - EXCLUDED CAUSES OF LOSS CP 10 75 (12120) CYBER INCIDENT EXCLUSION CP-4753 (01/13) NEWLY ACQUIRED PROPERTY AT DESCRIBED PREMISES IM-1785 (11/85) GENERAL PURPOSE INLAND MARINE DECLARATIONS IM-5122 (01/19) DECLARATION OF COVERAGES - BUILDERS RISK AND INSTALLATION FLOATER FORM CM 01 07 (06/19) WASHINGTON CHANGES IM-1302 (01/19) EQUIPMENT SCHEDULE IM-1302 (01/19) EQUIPMENT SCHEDULE IM-1302 (01/19) EQUIPMENT SCHEDULE IM-1302 (01/19) EQUIPMENT SCHEDULE IM-1302 (01/19) EQUIPMENT SCHEDULE IM-1615 (05/17) CONTRACTORS EQUIPMENT LEASED, BORROWED OR RENTED FROM OTHERS IM-5008 (05/17) SCHEDULE OF COVERAGES - CONTRACTORS' EQUIPMENT IM-5015 (05/17) SMALL TOOLS ENDORSEMENT IM-2097 (02117) AMENDATORY ENDORSEMENT - WASHINGTON IM-5054 (05117) BLANKET LOSS PAYEES IM-5070 (05/17) WAIVER OF THEFT DEDUCTIBLE IM-5074 (05/17) CONTRACTORS' EQUIPMENT COVERAGE SCHEDULED EQUIPMENT FORM IM-5121 (01/19) BUILDERS RISK COVERAGE GOX-2279 (12/92) SCHEDULE OF FORMS AND ENDORSEMENTS NAMED INSURED OLSON BROTHERS EXCAVATING, INC. POLICY NUMBER CAP 3 712 059 GU-4497 (09/16) FLEET RISK MANAGEMENT INFORMATION GU-3076 (04/16) PRIVACY STATEMENT GU-4320 (05/04) ADVISORY NOTICE TO POLICYHOLDERS AF-0005 (11120) 2020 COMMERCIAL AUTO ADVISORY NOTICE TO POLICYHOLDERS AF-9901 (09/05) STATED AMOUNT PHYSICAL DAMAGE COVERAGE GOX 2278 (12/92) SCHEDULE OF NAMED INSUREDS GOX 2279 (12/92) SCHEDULE OF FORMS AND ENDORSEMENTS AP-0003-1 (10121) BUSINESS AUTO COVERAGE FORM DECLARATIONS AP-0003-2 (10121) BUSINESS AUTO COVERAGE FORM DECLARATIONS PART 2 AP-0003-3 (10121) BUSINESS AUTO COVERAGE FORM DECLARATIONS PART 3 AP-0003-4 (10121) BUSINESS AUTO COVERAGE FORM DECLARATIONS PART 4 AP-0004 (10121) BUSINESS AUTO COVERAGE FORM DECLARATIONS SUPPLEMENT HIRED OR BORROWED MOBILE EQUIPMENT OR FARM EQUIPMENT AA-2709 (10121) AUTO SCHEDULE AA-2709 (10121) AUTO SCHEDULE AA-2709 (10121) AUTO SCHEDULE AA-2709 (10121) AUTO SCHEDULE AA-2709 (10121) AUTO SCHEDULE AA-2709 (10121) AUTO SCHEDULE AA-2709 (10121) AUTO SCHEDULE AA-2709 (10121) AUTO SCHEDULE IL O1 23 (11/13) WASHINGTON CHANGES - DEFENSE COSTS IL O1 46 (08/10) WASHINGTON COMMON POLICY CONDITIONS IL 01 98 (09/08) NUCLEAR ENERGY LIABILITY EXCLUSION ENDORSEMENT CA 00 01 (11120) BUSINESS AUTO COVERAGE FORM CA 99 03 (10/13) AUTO MEDICAL PAYMENTS COVERAGE A-2931 (11/99) ADDITIONAL INSURED - SPECIFIC ENTITIES CA 04 44 (10/13) WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US (WAIVER OF SUBROGATION) AA-3015 (09/00) NAMED DRIVER LIABILITY COVERAGE LIMITATION AND PHYSICAL DAMAGE EXCLUSION ENDORSEMENT AA-3015 (09/00) NAMED DRIVER LIABILITY COVERAGE LIMITATION AND PHYSICAL DAMAGE EXCLUSION ENDORSEMENT CA 03 02 (10/13) DEDUCTIBLE LIABILITY COVERAGE CA 21 34 (10/13) WASHINGTON UNDERINSURED MOTORISTS COVERAGE CA 99 10 (10/13) DRIVE OTHER CAR COVERAGE - BROADENED COVERAGE FOR NAMED INDIVIDUALS CA 99 10 (10/13) DRIVE OTHER CAR COVERAGE - BROADENED COVERAGE FOR NAMED INDIVIDUALS CA 99 28 (11120) STATED AMOUNT INSURANCE AP-0401 (10/17) BROADENED COVERAGE - AUTOMOBILES CA O1 35 (02121) WASHINGTON CHANGES CA 23 45 (11120) PUBLIC OR LIVERY PASSENGER CONVEYANCE AND ON -DEMAND DELIVERY SERVICES EXCLUSION CA 23 92 (10/13) WASHINGTON EXCLUSION OF TERRORISM CA 23 94 (10/13) SILICA OR SILICA -RELATED DUST EXCLUSION FOR COVERED AUTOS EXPOSURE A 200c (01/82) CERTIFICATE OF AUTOMOBILE INSURANCE AND LOSS PAYABLE CLAUSE ENDORSEMENT A 200c (01/82) CERTIFICATE OF AUTOMOBILE INSURANCE AND LOSS PAYABLE CLAUSE ENDORSEMENT A 200c (01/82) CERTIFICATE OF AUTOMOBILE INSURANCE AND LOSS PAYABLE CLAUSE ENDORSEMENT GOX-2279 (12/92) SCHEDULE OF FORMS AND ENDORSEMENTS NAMED INSURED OLSON BROTHERS EXCAVATING, INC. POLICY NUMBER CAP 3 712 059 A 200c (01/82) CERTIFICATE OF AUTOMOBILE INSURANCE AND LOSS PAYABLE CLAUSE ENDORSEMENT A 200c (01/82) CERTIFICATE OF AUTOMOBILE INSURANCE AND LOSS PAYABLE CLAUSE ENDORSEMENT CA 20 01 (10/13) LESSOR - ADDITIONAL INSURED AND LOSS PAYEE CA 99 89 (05/01) WASHINGTON LOSS PAYABLE FORM REG-335 CA 99 89 (05/01) WASHINGTON LOSS PAYABLE FORM REG-335 CA 99 89 (05/01) WASHINGTON LOSS PAYABLE FORM REG-335 GOX-2279 (12/92) THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. ADDITIONAL INSURED - OWNERS, LESSEES OR CONTRACTORS - COMPLETED OPERATIONS This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART Section II — Who is An Insured is amended to include as an additional insured any person or organization who is required by written contract to be an additional insured on your policy for completed operations, but only with respect to liability for "bodily injury" or "property damage" caused, in whole or in part, by "your work" at the project designated in the contract, performed for an additional insured and included in the "products -completed operations hazard". If the written contract or an additional insured endorsement required by the written contract requires that the additional insured be provided with coverage for "bodily injury" or "property damage" caused solely by their own negligence, then Section II — Who is An Insured cited immediately above does not apply and is replaced by: Section II — Who is An Insured is amended to include as an additional insured any person or organization required by the written contract to be an additional insured on your policy for completed operations, but only with respect to liability for "bodily injury" or "property damage" arising out of "your work" at the project designated in the contract, performed for an additional insured and included in the "products -completed operations hazard". Regardless of which of the aforementioned Section II — Who is An Insured amendments is applicable to the additional insured, the insurance afforded to the additional insured: 1. will only apply if the written contract requiring additional insured coverage was signed into effect by you and an additional insured prior to any "bodily injury" or "property damage" occurring for which this coverage is sought; and 2. will only apply to the extent not prohibited by the law governing the written contract; and 3. will not apply to "property damage" in connection with a project where "your work" on the project was completed and where the duration of the additional insured coverage requirement in the written contract governing "your work" on that project had expired by the time that "property damage" first occurred; and 4. will not apply to "property damage" in connection with a project where "your work" on the project was completed and where the "property damage" occurred after the minimum time required for completed operations coverage in the written contract, if any, has expired. The Limits of Insurance applicable to the additional insured under this endorsement are the minimum limits specified in the written contract requiring this coverage, or as stated in Section III — Limits of Insurance of the Commercial General Liability Coverage Form, whichever is less. These Limits of Insurance are inclusive of and not in addition to the Limits of Insurance described in Section III of that form. This insurance is excess of all other insurance available to the additional insured, whether excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designates the additional insured as a Named Insured and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance which the additional insured qualifies as an insured or additional insured, this insurance will be excess. Includes copyrighted material of Insurance Services Office, Inc. with its permission GL-5057 (10/16) This page has been left blank intentionally. THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. ADDITIONAL INSURED — OWNERS, LESSEES OR CONTRACTORS — ONGOING OPERATIONS This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART Section II — Who is An Insured is amended to include as an additional insured any person or organization who is required by written contract to be an additional insured on your policy, but only with respect to liability for "bodily injury" or "property damage" caused, in whole or in part, by "your work" at the project designated in the contract, performed for an additional insured and which occurred during your ongoing operations for that additional insured. If the written contract or an additional insured endorsement required by the written contract requires that the additional insured be provided with coverage for "bodily injury" or "property damage" caused solely by their own negligence, then Section II — Who is An Insured cited immediately above does not apply and is replaced by: Section II — Who is An Insured is amended to include as an additional insured any person or organization required by the written contract to be an additional insured on your policy, but only with respect to liability for "bodily injury" or "property damage" arising out of "your work" at the project designated in the contract, performed for an additional insured and which occurred during your ongoing operations for that additional insured. Regardless of which of the aforementioned Section II — Who is An Insured amendments is applicable to the additional insured, the insurance afforded to the additional insured: 1. will only apply if the written contract requiring additional insured coverage was signed into effect by you and an additional insured prior to any "bodily injury" or "property damage" occurring for which this coverage is sought; and 2. will only apply to the extent not prohibited by the law governing the written contract; and 3. will not apply to "bodily injury" or "property damage" occurring after: a. All work, including materials, parts or equipment furnished in connection with such work, on the project (other than service, maintenance or repairs) to be performed by or on behalf of the additional insured(s) at the location of the covered operations has been completed; or b. That portion of "your work" out of which the "bodily injury" or "property damage" arises has been put to its intended use by any person or organization other than another contractor or subcontractor engaged in performing operations for a principal as a part of the same project. The Limits of Insurance applicable to the additional insured under this endorsement are the minimum limits specified in the written contract requiring this coverage, or as stated in Section III — Limits of Insurance of the Commercial General Liability Coverage Form, whichever is less. These Limits of Insurance are inclusive of and not in addition to the Limits of Insurance described in Section III of that form. This insurance is excess of all other insurance available to the additional insured, whether excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designates the additional insured as a Named Insured and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance which the additional insured qualifies as an insured or additional insured, this insurance will be excess. Includes copyrighted material of Insurance Services Office, Inc. with its permission GL-5058 (10/16) This page has been left blank intentionally. THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. EXTENDED LIABILITY COVERAGE This endorsement modifies insurance provided under the following: It is agreed that the provisions listed below apply only upon the entry of an U in the box next to the caption of such provision. A U Broad Form Named Insured B. j X i Bodily Injury Extension F. U Chartered Ai rcraft G. j X j Coverage Territory Broadened C. U Employee As Insureds - Health Care Services H. U Medical Payments - Increased Limits D. n Non-Ojvned Watercraft Liability I. n Expanded Expected or Intended Exception E. U Liberalization J. U Property Perils Legal Liability K U Broadened Supplementary Payments A BROAD FORM NAKED INSURED SECTION II - WHO IS AN INSURED , Paragraph 3 is deleted and replaced by the following: 3. Any organization you newly acquire or form, except for a partnership, joint venture or limited liability company, and over which you maintain majority ownership or interest (51%or more) or for which you have assumed the active management, will qualify as a Named Insured if there is no other similar insurance available to that organization. However: a. Coverage under this provision is afforded only until the end of the policy period or the 12- month anniversary of the policy inception date, whichever is earlier; b. Coverage A does not apply to "bodily injury" or "property damage" that occurred before you acquired or formed the organization; C. Coverage B does not apply to "personal and advertising injury" arising out of an offense committed before you acquired or formed the organization. SECTION V- DEFINITIONS , Paragraph 3, is deleted and replaced by the following: 3. "Bodily injury" means bodily injury, sickness or disease sustained by a person, including mental anguish or death resulting from any of these, at any time. Mental anguish means any type of mental or emotional illness or disease. C. EMPLOYEES AS INSUREDS - HEALTH CARE SERVICES SECTION II - WHO IS AN INSURED , Item 2.a(1)(d) is deleted. GL-2784 (09/11) -1- D. NON -OWNED WATERCRAFT LIABILITY SECTION I - COVERAGES, COVERAGE A, 2. EXCLUSIONS , Item g.(2) is replaced with: (2) A watercraft you do not own that is: (a) Less than 51 feet long; and (b) Not being used to carry persons or property for a charge. E. LIBERALIZATION SECTION IV- CONDITIONS , is amended to include: 10. Liberalization If we adopt a change in our forms or rules which would broaden the coverage of this policy without an additional premium charge, the broader coverage will apply. This extension is effective upon the approval of such broader coverage in your state of domicile. SECTION I - COVERAGES , Coverage A, Exclusions, Item 2.g.(6) is added: (6) An aircraft in which you have no ownership interest and that you have chartered with crew. SECTION V- DEFINITIONS , Item 4.a is replaced with: a The United States of America (including its territories and possessions), Canada, Bermuda, the Bahamas, the Cayman Islands, British Virgin Islands and Puerto Rico. H. MEDICAL PAYMENTS - INCREASED LIMITS Unless COVERAGE C. - MEDICAL PAYMENTS is excluded from this policy: SECTION I - COVERAGES , Coverage C , Insuring Agreement , Item c. is added: C. The medical expense limit provided by this policy shall be the greater of: (1) $10,000; or (2) The amount shown in the declarations. I. EXPANDED EXPECTED or INTENDED EXCEPTION SECTION I - COVERAGES , 2. Exclusions Item a is amended as follows: a Expected or Intended Injury - "bodily injury' or "property damage" expected or intended from the standpoint of the insured. This exclusion does not apply to "bodily injury' or "property damage" resulting from the use of reasonable force to protect persons or property. GL-2784 (09/11) -2- J. PROPERTY PERILS LEGAL LIABILITY A SECTION I - COVERAGES, COVERAGE A, 2. Exclusions, the last paragraph following exclusion q. is replaced with: Exclusion c. through n., do not apply to damage by fire, explosion, smoke, water damage, sprinkler leakage, or lightning to premises while rented to you or temporarily occupied by you with the permission of the owner. A separate limit of insurance applies to this coverage as described in SECTION III - LIMITS OF INSURANCE . R SECTION III - LIMITS OF INSURANCE , Item 6. is replaced with: 6. Subject to 5. above, the Damage to Premises Rented to You Limit is the most we will pay under Coverage A for damages because of "property damage" to any one premises while rented to you, or in the case of damages by fire, explosion, smoke, water damage, sprinkler leakage or lightning, while rented to you or temporarily occupied by you with the permission of the owner, arising out of any one fire, explosion, smoke, water damage, sprinkler leakage or lightning incident. The Damage to Premises Rented to You Limit provided by this policy shall be the greater of: $300,000 or 2. The amount shown in the declarations. C. SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS, Item 4.b.(1)(a)(ii) is replaced with: (ii) That is fire, explosion, smoke, water damage, sprinkler leakage or lightning insurance for premises while rented to you or temporarily occupied by you with the permission of the owner. D. SECTION V- DERNITIONS , Item 9.a. is replaced with: a. A contract for a lease of premises. However, that portion of the contract for a lease of premises that indemnifies any person or organization for damage by fire, explosion, smoke, water damage, sprinkler leakage or lightning to premises while rented to you or temporarily occupied by you with the permission of the owner is not an "insured contract." SECTION I - COVERAGES, SUPPLEMENTARY PAYMENTS - Coverages A and 13, Item 1.b. and 1.d. are replaced with: 1.b. The cost of bail bonds required because of accidents or traffic law violations arising out of the use of any vehicle to which the Bodily Injury Liability Coverage applies. We do not have to furnish these bonds. 1.d. All reasonable expenses incurred by the insured at our request to assist us in the investigation or defense of the claim or "suit," including actual loss of earnings up to $500 a day because of time off from work. GL-2784 (09/11) -3- This page has been left blank intentionally. THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. "•111 = Q Z i 19:4 9 11ifiTmgo: 'I �: •• `D This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE FORM It is agreed that the provisions listed below apply only upon the entry of an OX in the box next to the caption of such provision. A U Partnership and Joint Venture Extension M. U Construction Project General Aggregate Limits B. ❑X Contractors Automatic Additional Insured Coverage — Ongoing Operations C. X Automatic Waiver of Subrogation D. X Extended Notice of Cancellation, Nonrenewal E. U Unintentional Failure to Disclose Hazards F. L X Broadened Mobile Equipment G. F7X Personal and Advertising Injury - Contractual Coverage H. j X Nonemployment Discrimination I. U Liquor Liability J. U Broadened Conditions K U Automatic Additional Insureds —Equipment Leases L. 0 Insured Contract Extension - Railroad Property and Construction Contracts A PARTNERSHIP AND JOINT VENTURE EXTENSION N. F7X Fellow Employee Coverage O. FX Property Damage to the Named Insured's Work P. FX_ Care, Custody or Control Q XJ Electronic Data Liability Coverage R. U Consolidated Insurance Program Residual Liability Coverage S. ❑X Automatic Additional Insureds — Managers or Lessors of Premises T. j X Automatic Additional Insureds —State or Governmental Agency or Political Subdivisions — Permits or Authorizations U. LX Contractors Automatic Additional Insured Coverage — Completed Operations V. F7X Additional Insured — Engineers, Architects or Surveyors The following provision is added to SECTION II - WHO IS AN INSURED : The last full paragraph which reads as follows: No person or organization is an insured with respect to the conduct of any current or past partnership, joint venture or limited liability company that is not shown as a Named Insured in the Declarations is deleted and replaced with the following: With respect to the conduct of any past or present joint venture or partnership not shown as a Named Insured in the Declarations and of which you are or were a partner or member, you are an insured, but only with respect to liability arising out of "your work" on behalf of any partnership or joint venture not shown as a Named Insured in the Declarations, provided no other similar liability insurance is available to you for "your work" in connection with your interest in such partnership or joint venture. GL-3088 (09/11) -1- B. CONTRACTORS AUTOMATIC ADDITIONAL INSURED COVERAGE— ONGOING OPERATIONS SECTION II — WHO IS AN INSURED is amended to include as an additional insured any person or organization who is required by written contract to be an additional insured on your policy, but only with respect to liability for "bodily injury", "property damage" or "personal and advertising injury" caused, in Mole or in part, by: Your acts or omissions; or 2. The acts or omissions of those acting on your behalf; in the performance of your ongoing operations for the additional insured(s) at the project(s) designated in the written contract. With respect to the insurance afforded to these additional insureds, the following additional exclusions apply: This insurance does not apply to "bodily injury" or "property damage" occurring after: All work, including materials, parts or equipment furnished in connection with such work, on the project (other than service, maintenance or repairs) to be performed by or on behalf of the additional insured(s) at the location of the covered operations has been completed; or 2. That portion of "your work" out of which the injury or damage arises has been put to its intended use by any person or organization other than another contractor or subcontractor engaged in performing operations for a principal as a part of the same project. This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. C. AUTOMATIC WAIVER OF SUBROGATION Item 8. of SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS, is deleted and replaced with the following: 8. Transfer of Fights of Recovery Against Others to Us and Automatic Waiver of Subrogation. a If the insured has rights to recover all or part of any payment we have made under this Coverage Form, those rights are transferred to us. The insured must do nothing after loss to impair those rights. At our request, the insured will bring "suit" or transfer those rights to us and help us enforce them. b. If required by a written contract executed prior to loss, we waive any right of recovery we may have against any person or organization because of payments we make for injury or damage arising out of "your work" for that person or organization. D. EXTENDED NOTICE OF CANCELLATION, NONRENEWAL Item A2.b. of the COMMON POLICY CONDITIONS , is deleted and replaced with the following: A.2.b. 60 days before the effective date of the cancellation if we cancel for any other reason. Item 9. of SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS , is deleted and replaced with the following: 9. WHEN WE DO NOT RENEW GL-3088 (09/11) -2- a If we choose to nonrenew this policy, we will mail or deliver to the first Named Insured shown in the Declarations written notice of the nonrenewal not less than 60 days before the expiration date. b. If we do not give notice of our intent to nonrenew as prescribed in a above, it is agreed that you may extend the period of this policy for a maximum additional sixty(60) days from its scheduled expiration date. Where not otherwise prohibited by law, the existing terms, conditions and rates will remain in effect during that extension period. It is further agreed that so long as it is not otherwise prohibited by law, this one time sixty day extension is the sole remedy and liquidated damages available to the insured as a result of our failure to give the notice as prescribed in 9. a above. E UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS Although we relied on your representations as to existing and past hazards, if unintentionally you should fail to disclose all such hazards at the inception date of your policy, we will not deny coverage under this Coverage Form because of such failure. F. BROADENED MOBILE EQUIPMENT Item 12.b. of SECTION V - DEFINITIONS , is deleted and replaced with the following: 12.b. Vehicles maintained for use solely on or next to premises, sites or locations you own, rent or occupy. G. PERSONAL AND ADVERTISING INJURY -CONTRACTUAL COVERAGE Exclusion 2.e. of SECTION I, COVERAGE B is deleted. H. NONEMPLOYMENT DISCRIMINATION Unless "personal and advertising injury" is excluded from this policy: Item 14. of SECTION V - DEFlNTIONS , is amended to include: "Personal and advertising injury" also means embarrassment or humiliation, mental or emotional distress, physical illness, physical impairment, loss of earning capacity or monetary loss, which is caused by "discrimination." SECTION V- DEFlNTIONS , is amended to include: "Discrimination" means the unlawful treatment of individuals based on race, color, ethnic origin, age, gender or religion. Item 2. Exclusions of SECTION I, COVERAGE B , is amended to include: "Personal and advertising injury' arising out of "discrimination" directly or indirectly related to the past employment, employment or prospective employment of any person or class of persons by any insured; "Personal and advertising injury" arising out of "discrimination" by or at your, your agents or your "employees" direction or with your, your agents or your "employees" knowledge or consent; "Personal and advertising injury" arising out of "discrimination" directly or indirectly related to the sale, rental, lease or sub -lease or prospective sale, rental, lease or sub -lease of any dwelling, permanent lodging or premises by or at the direction of any insured; or Fines, penalties, specific performance or injunctions levied or imposed by a governmental entity, or governmental code, law, or statute because of "discrimination." GL-3088 (09/11) -3- I. LIQUOR LIABILITY Exclusion 2.c. of SECTION I, COVERAGE A , is deleted. Items 2.a. and 2.b. of SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS, are deleted and replaced with the following: 2. Duties In The Event Of Occurrence, Offense, Claim Or Suit: a. You must see to it that we are notified of an 'occurrence" or an offense which may result in a claim as soon as practicable after the 'occurrence" has been reported to you, one of your officers or an "employee" designated to give notice to us. Notice should include: (1) How, when and where the 'occurrence" or offense took place; (2) The names and addresses of any injured persons and witnesses; and (3) The nature and location of any injury or damage arising out of the "occurrence" or offense. b. If a claim is made or "suit" is brought against any insured, you must: (1) Record the specifics of the claim or "suit" and the date received as soon as you, one of your officers, or an "employee" designated to record such information is notified of it; and (2) Notify us in writing as soon as practicable after you, one of your officers, your legal department or an "employee" you designate to give us such notice learns of the claims or "suit." Item 2.e. is added to SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS 2.e. If you report an 'occurrence" to your workers compensation insurer which develops into a liability claim for which coverage is provided by the Coverage Form, failure to report such 'occurrence" to us at the time of 'occurrence" shall not be deemed in violation of paragraphs 2.a., 2.b., and 2.c. However, you shall give written notice of this 'occurrence" to us as soon as you are made aware of the fact that this 'occurrence" may be a liability claim rather than a workers compensation claim. K AUTOMIAMC ADDITIONAL INSUREDS - EQUIPMENT LEASES SECTION II - WHO IS AN INSURED is amended to include any person or organization with whom you agree in a written equipment lease or rental agreement to name as an additional insured with respect to liability for "bodily injury", "property damage" or "personal and advertising injury" caused, at least in part, by your maintenance, operation, or use by you of the equipment leased to you by such person or organization, subject to the following additional exclusions. The insurance provided to the additional insured does not apply to: "Bodily injury" or "property damage" occurring after you cease leasing the equipment. 2. 'Bodily injury" or "property damage" arising out of the sole negligence of the additional insured. 3. 'Property damage" to: a. Property owned, used or occupied by or rented to the additional insured; or b. Property in the care, custody or control of the additional insured or over which the additional insured is for any purpose exercising physical control. GL-3088 (09/11) -4- This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. Item 9. of SECTION V- DEFINTIONS , is deleted and replaced with the following. 9. "Insured Contract" means: a A contract for a lease of premises. However, that portion of the contract for a lease of premses that indemnifies any person or organization for damage by fire to premises while rented to you or temporarily occupied by you with perrnission of the owner is not an "insured contract' b. A sidetrack agreement; c. Any easement or license agreement; d. An obligation, as required by ordinance, to indemnify a municipality, except in connection with work for a municipality; a An elevator maintenance agreement; f. That part of any other contract or agreement pertaining to your business (including an indemnification of a municipality in connection with work performed for a municipality) under which you assume the tort liability of another party to pay for "bodily injury' or "property damage" to a third person or organization. Tort liability means a liability that would be imposed by law in the absence of any contract or agreement. Paragraph f. does not include that part of any contract or agreement: (1) That indemnifies an architect, engineer or surveyor for injury or damage arising out of: (a) Preparing, approving, or failing to prepare or approve, maps, shop drawings, opinions, reports, surveys, field orders, change orders or drawings and specifications; or (b) Giving directions or instructions, or failing to give them, if that is the primary cause of the injury or damage; or (2) Under which the insured, if an architect, engineer or surveyor, assumes liability for an injury or damage arising out of the insured's rendering or failure to render professional services, including those listed in (1) above and supervisory, inspection, architectural or engineering activities. NL CONSTRUCTION PROJECT GENERAL AGGREGATE UPATS This modifies SECTION III - LIMTS OF INSURANCE A For all sums which can be attributed only to ongoing operations at a single construction project for which the insured becomes legally obligated to pay as damages caused by an "occurrence" under SECTION I - COVERAGE A, and for all medical expenses caused by accidents under SECTION I - COVERAGE C : GL-3088 (09/11) -5- 1. A separate Construction Project General Aggregate Limit applies to each construction project, and that limit is equal to the amount of the General Aggregate Limit shown in the Declarations. 2. The Construction Project General Aggregate Limit is the most we will pay for the sum of all damages under COVERAGE A, except damages because of "bodily injury' or "property damage" included in the "products -completed operations hazard," and for medical expenses under COVERAGE C regardless of the number of: a Insureds; b. Claims made or "suits" brought; or c. Persons or organizations making claims or bringing "suits." 3. Any payments made under COVERAGE A for damages or under COVERAGE C for medical expenses shall reduce the Construction Project General Aggregate Limit for that construction project. Such payments shall not reduce the General Aggregate Limit shown in the Declarations nor shall they reduce any other Construction Project General Aggregate Limit for any other construction project. 4. The limits shown in the Declarations for Each Occurrence, Fire Damage and Medical Expense continue to apply. However, instead of being subject to the General Aggregate Lirnit shown in the Declarations, such limits will be subject to the applicable Construction Project General Aggregate Limit. R For all sums which cannot be attributed only to ongoing operations at a single construction project for which the insured becomes legally obligated to pay as damages caused by an "occurrence" under SECTION I - COVERAGE A, and for all medical expenses caused by accidents under SECTION I - COVERAGE C : 1. Any payments made under COVERAGE A for damages or under COVERAGE C for medical expenses shall reduce the amount available under the General Aggregate Limit or the Products - Completed Operations Aggregate Limit, whichever is applicable; and 2. Such payments shall not reduce any Construction Project General Aggregate Limit. C. Payments for damages because of "bodily injury" or "property damage" included in the "products - completed operations hazard" will reduce the Products -Completed Operations Aggregate Limit, and not reduce the General Aggregate Limit nor the Construction Project General Aggregate Limit. D. If a construction project has been abandoned, delayed, or abandoned and then restarted, or if the authorized contracting parties deviate from plans, blueprints, designs, specifications or timetables, the project will still be deemed to be the same construction project. E The provisions of SECTION III - UNITS OF INSURANCE not otherwise modified by this endorsement shall continue to be applicable. N. FELLOW EMPLOYEE COVERAGE Exdusion 2.e. Employers Liability of SECTION I, COVERAGE A, is deleted and replaced with the following: 2.e. 'Bodily injury" to (1) An "employee" of the insured arising out of and in the course of: (a) Employment by the insured; or (b) Performing duties related to the conduct of the insured's business; or GL-3088 (09/11) -6- (2) The spouse, child, parent, brother or sister of that "employee" as a consequence of paragraph (1) above. This exclusion applies: (1) Whether the insured may be liable as an employer or in any other capacity; and (2) To any obligation to share damages with or repay someone else who must pay damages because of the injury. This exclusion does not apply to: (1) Liability assumed by the insured under an "insured contract"; or (2) Liability arising from any action or omission of a co2employee" while that co -"employee" is either in the course of his or her employment or performing duties related to the conduct of your business. Item 2.a (1)(a) of SECTION II - WHO IS AN INSURED , is deleted and replaced with the following: 2.a (1xa) To you, to your partners or members (if you are a partnership or joint venture) or to your members (if you are a limited liability company), or to your "volunteer workers" while performing duties related to the conduct of your business. O. PROPERTY DAMAGE TO THE NAKED INSUREDS WORK Exclusion I of SECTION I, COVERAGE A is deleted and replaced with the following: "Property damage" to "your work" arising out of it or any part of it and included in the "products completed operation hazard." This exclusion applies only to that portion of any loss in excess of $50,000 per occurrence if the damaged work and the work out of which the damage arises was performed by you. This exclusion does not apply if the damaged work or the work out of which the damage arises was performed on your behalf by a subcontractor. P. CARE, CUSTODY OR CONTROL Exclusion 2.j.4 of SECTION I, COVERAGE A is deleted and replaced with the following: 2.j.4 Personal property in the care, custody or control of the insured. However, for personal property in the care, custody or control of you or your "employees," this exclusion applies only to that portion of any loss in excess of $25,000 per occurrence, subject to the following terms and conditions: (a) The most that we will pay under this provision as an annual aggregate is $100,000, regardless of the number of occurrences. (b) This provision does not apply to "employee" owned property or any property that is missing where there is not physical evidence to show what happened to the property. (c) The aggregate limit for this coverage provision is part of the General Aggregate Limit and SECTION III - UM1TS OF INSURANCE is changed accordingly. (d) In the event of damage to or destruction of property covered by this exception, you shall, if requested by us, replace the property or furnish the labor and materials necessary for repairs thereto, at actual cost to you, exclusive of prospective profit or overhead charges of any nature. GL-3088 (09/11) -7- (e) $2,500 shall be deducted from the total amount of all sums you became obligated to pay as damages on account of damage to or destruction of all property of each person or organization, including the loss of use of that property, as a result of each "occurrence." Our limit of liability under the endorsement as being applicable to each "occurrence" shall be reduced by the amount of the deductible indicated above; however, our aggregate limit of liability under this provision shall not be reduced by the amount of such deductible. The conditions of the policy, including those with respect to duties in the event of "occurrence," claims or "suit" apply irrespective of the application of the deductible amount. We may pay any part or all of the deductible amount to effect settlement of any claim or "suit" and, upon notification of the action taken, you shall promptly reimburse us for such part of the deductible amount as has been paid by us. Q. ELECTRONIC DATA LIABILITY COVERAGE Exclusion 2.p. Electronic Data of SECTION I, COVERAGE A, is deleted and replaced with the following: 2.p. Damages arising out of the loss of, loss of use of, damage to, corruption of, inability to access, or inability to manipulate "electronic data" that does not result from physical injury to tangible property. 2. The following definition is added to SECTION V — DERNITIONS: "Electronic data" means information, facts or programs stored as or on, created or used on, or transmitted to or from computer software (including systems and applications software), hard or floppy disks, CD-ROMS, tapes, drives, cells, data processing devices or any other media which are used with electronically controlled equipment. 3. For the purposes of this coverage, the definition of "property damage" in SECTION V — DERNITIONS is replaced by the following: "Property damage" means: a Physical injury to tangible property, including all resulting loss of use of that property. Al such loss of use shall be deemed to occur at the time of the physical injury that caused it; b. Loss of use of tangible property that is not physically injured. Al such loss of use shall be deemed to occur at the time of the "occurrence" that caused it; or C. Loss of, loss of use of, damage to, corruption of, inability to access, or inability to properly manipulate "electronic data", resulting from physical injury to tangible property. All such loss of "electronic data" shall be deemed to occur at the time of the "occurrence" that caused it. For the purposes of this insurance, "electronic data" is not tangible property. R. CONSOLIDATED INSURANCE PROGRAM RESIDUAL LIABILITY COVERAGE With respect to "bodily injury', "property damage", or `personal and advertising injury' arising out of your ongoing operations; or operations included within the "products -completed operations hazard", the policy to Mich this coverage is attached shall apply as excess insurance over coverage available to `you" under a Consolidated Insurance Program (such as an Owner Controlled Insurance Program or Contractors Controlled Insurance Program). Coverage afforded bythis endorsement does not applyto any Consolidated Insurance Program involving a "residential project" or any deductible or insured retention, specified in the Consolidated Insurance Program. The following is added to Section V— Definitions GL-3088 (09/11) -8- "Residential project" means any project where 30% or more of the total square foot area of the structures on the project is used or is intended to be used for human residency. This includes but is not limited to single or multifamily housing, apartments, condominiums, townhouses, co-operatives or planned unit developments and appurtenant structures (including pools, hot tubs, detached garages, guest houses or any similar structures). A "residential project' does not include military owned housing, college/university owned housing or dormitories, long term care facilities, hotels, motels, hospitals or prisons. All other terms, provisions, exclusions and limitations of this policy apply. S. AUTOMATIC ADDITIONAL INSUREDS - MANAGERS OR LESSORS OR PREMSES SECTION II — WHO IS AN INSURED is amended to include: Any person or organization with whom you agree in a written contract or written agreement to name as an additional insured but only with respect to liability arising out of the ownership, maintenance or use of that part of the premises, designated in the written contract or written agreement, that is leased to you and subject to the following additional exclusions: This insurance does not apply to: Any `occurrence" which takes place after you cease to be a tenant in that premises. 2. Structural alterations, new construction or demolition operations performed by or on behalf of the additional insured listed in the written contract or written agreement. This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. T. AUTOMATIC ADDITIONAL INSUREDS — STATE OR GOVERNMENTAL AGENCY OR POUTICAL SUBDIVISIONS — PERMTS OR AUTHORIZATIONS SECTION II — WHO IS AN INSURED is amended to include any state or governmental agency or subdivision or political subdivision with whom you are required by written contract, ordinance, law or building code to name as an additional insured subject to the following provisions: This insurance applies only with respect to operations performed by you or on your behalf for which the state or governmental agency or subdivision or political subdivision has issued a permit or authorization. This insurance does not apply to: 1. "Bodily injury', "property damage" or "personal and advertising injury' arising out of operations performed for the federal government, state or municipality; or 2. "Bodily injury' or "property damage" included within the "products -completed operations hazard' This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. U. CONTRACTORS AUTOMATIC ADDITIONAL INSURED COVERAGE— COWLEfED OPERATIONS GL-3088 (09/11) -9- SECTION II — WHO IS AN INSURED is amended to include as an additional insured any person or organization who is required by written contract to be an additional insured on your policy for completed operations, but only with respect to liability for "bodily injury" or "property damage" caused, in whole or in part, by "your work" at the project designated in the contract, performed for that additional insured and included in the "products -completed operations hazard". This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. V. ADDITIONAL INSURED— ENGINEERS, ARCHITECTS OR SURVEYORS SECTION II — WHO IS AN INSURED is amended to include as an additional insured any architect, engineer or surveyor who is required by written contract to be an additional insured on your policy, but only with respect to liability for "bodily injury", "property damage" or "personal and advertising injury" caused, in Mole or in part, by: Your acts or omissions; or 2. The acts or omissions of those acting on your behalf; in the performance of your ongoing operations performed by you or on your behalf. This includes such architect, engineer or surveyor, who may not be engaged by you, but is contractually required to be added as an additional insured to your policy. With respect to the insurance afforded to these additional insureds, the following additional exclusion applies: This insurance does not apply to "bodily injury", "property damage" or "personal and advertising injury" arising out of the rendering of or the failure to render any professional services, including: 1. The preparing, approving, or failing to prepare or approve maps, drawings, opinions, reports, surveys, change orders, designs or specifications; or 2. Supervisory, inspection or engineering services. This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. GL-3088 (09/11) -10- COMMERCIAL GENERAL LIABILITY CG 20 01 04 13 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. PRIMARY AND NONCONTRIBUTORY - OTHER INSURANCE CONDITION This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE PART PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART The following is added to the Other Insurance Condition and supersedes any provision to the contrary: Primary And Noncontributory Insurance This insurance is primary to and will not seek contribution from any other insurance available to an additional insured under your policy provided that: (1) The additional insured is a Named Insured under such other insurance; and (2) You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to the additional insured. CG 20 01 04 13 © Insurance Services Office, Inc., 2012 Page 1 of 1 This page has been left blank intentionally. Policy Number: COMMERCIAL AUTO THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. ADDITIONAL INSURED - SPECIFIC ENTITIES This endorsement modifies insurance provided under the following: BUSINESS AUTO COVERAGE FORM WHO IS AN INSURED is changed to include as an "insured" the person or organization named in this endorsement. However, the additional insured is an "insured" only for "bodily injury" or "property damage" arising out of work or operations performed by you or on your behalf for the additional insured and resulting from the ownership, maintenance or use of a "covered auto," by: You, or 2. Any of your employees or agents; or 3. Anyone other than the additional insured or any employee or agent of the additional insured, while using with your permission a covered "auto" you own, hire or borrow. ADDITIONAL INSURED: Any person or organization for whom the named insured has agreed by written "insured contract" to designate as an additional insured subject to all the provisions and limitations of this policy. A-2931 (11/99) This page has been left blank intentionally. POLICY NUMBER: COMMERCIAL AUTO CA04441013 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US (WAIVER OF SUBROGAMOI) This endorsement modifies insurance provided under the following: AUTO DEALERS COVERAGE FORM BUSINESS AUTO COVERAGE FORM MOTOR CARRIER COVERAGE FORM With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement. This endorsement changes the policy effective on the inception date of the policy unless another date is indicated below. Named Insured: Endorsement Effective Date: Name(s) Of Person(s) Or Organization(s): "Any person or organization for whom the named insured is operating under written contract when such contract requires a waiver of subrogation." Information required to complete this Schedule, if not shown above, will be shown in the Declarations. 1 The Transfer Of Rights Of Recovery Against Others To Us condition does not apply to the person(s) or organization(s) shown in the Schedule, but only to the extent that subrogation is waived prior to the "accident" or the 'loss" under a contract with that person or organization. CA04441013 ©Insurance Services Office, Inc., 2011 Page 1 of 1 This page has been left blank intentionally. BITCO GENERAL INSURANCE CORPORATION BITCO NATIONAL INSURANCE COMPANY THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. BROADENED COVERAGE - AUTOMOBILES The following modifies insurance provided under: BUSINESS AUTO COVERAGE FORM With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by this endorsement. 1 - Broad Form Named Insured 2 - Automatic Waiver of Subrogation 3 - Automatic Additional Insured 4 - Primary and Noncontributory - Other Insurance Condition 5 - Unintentional Failure to Disclose Hazards 6 - Extended Notice of Cancellation, Non -Renewal 7 - When We Do Not Renew 8 - Notice of Knowledge of Accident or Loss 9 - Employees as Insured 10 - Employee Hired Autos 1. BROAD FORM NAKED INSURED 11 - Bodily Injury Extension 12 - Hired Auto Physical Damage 13 - Enhanced Supplementary Payments 14 - Fellow Employee Coverage for Designated Positions 15 - Physical Damage —Transportation Expenses 16 - Rental Reimbursement Coverage 17 - Loan/Lease Gap Coverage 18 - Accidental Air Bag Discharge Coverage 19 - Glass Repair — Waiver of Deductible SECTION II. A 1. -WHO IS AN INSURED - Paragraph d. is added: d. Any organization you newly acquire or form, except for a partnership, joint venture or limited liability company, and over which you maintain majority ownership or interest (51%or more) orfor Mich you have assumed the active management, will qualify as a Named Insured if there is no other similar insurance available to that organization. However, coverage under this provision is only afforded until the end of the policy period or the 12-month anniversary of the policy inception date, whichever is earlier. 2. AUTOMATIC WAIVER OF SUBROGATION Section IV — Business Auto Conditions, Paragraph A5., Transfer of Rights of Recovery Against Others to Lis, is deleted and replaced with the following: a If the insured has rights to recover all or part of any payment we have made under this Coverage Form, those rights are transferred to us. The insured must do nothing after loss to impair those rights. At our request, the insured will bring "suit" or transfer those rights to us and help us enforce them. b. If required by a written contract executed prior to loss, we waive any right of recovery we may have against any person or organization because of payments we make for damages under this coverage form. AP-0401 (10/17) -1- 3. AUTOMATIC ADDITIONAL INSURED SECTION II - WHO IS AN INSURED, Paragraph Al, is amended to include as an "insured" any person or organization who is required by written contract or agreement to be an additional insured on your policy, but only with respect to liability arising out of operations performed by you or on your behalf for the additional insured. 4. PRIMARY AND NONCONTRIBUTORY- OTHER INSURANCE CONDITION The following is added to the Other Insurance Condition in the Business Auto Coverage Form and the Other Insurance - Primary And Excess Insurance Provisions in the Motor Carrier Coverage Form and supersedes any provision to the contrary: This Coverage Form's Covered Autos Liability Coverage is primary to and will not seek contribution from any other insurance available to an "insured" under your policy provided that: 1. Such "insured" is a Named Insured under such other insurance; and 2. You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to such "insured". 5. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS Although we relied on your representations as to existing and past hazards, if unintentionally you should fail to disclose all such hazards at the inception date of your policy, we will not deny coverage under this Coverage Form because of such failure. 6. EXTENDED NOTICE OF CANCELLATION, NON -RENEWAL The CONNION POLICY CONDITIONS , Item A2.b. is deleted and replaced with the following: A2.b. 60 days before the effective date of the cancellation if we cancel for any other reason. 7. WHEN WE DO NOT RENEW SECTION IV- BUSINESS AUTO CONDITIONS , is amended to add Item B.9.: a If we choose to nonrenew this policy, we will mail or deliver to the first Named Insured shown in the Declarations written notice of the nonrenewal not less than 60 days before the expiration date. b. If we do not give notice of our intent to nonrenew as prescribed in a above, it is agreed that you may extend the period of this policy for a maximum additional sixty (60) days from its scheduled expiration date. Where not otherwise prohibited by law, the existing terms, conditions and rates will remain in effect during that extension period. It is further agreed that so long as it is not otherwise prohibited by law, this one-time sixty-day extension is the sole remedy and liquidated damages available to the insured as a result of our failure to give the notice as prescribed in 9. a above. 011010-i*0, .1016ATA I Z pi g-, a �0 9, a Kau., SECTION IV - BUSINESS AUTO CONDITIONS , Item A2.a is deleted and replaced with the following: 2. Duties in the Event of Accident, Claim Suit or Loss: a You must see to it that we are notified of an "accident", "claim", "suit" or "loss" which may result in a claim as soon as practicable after the "occurrence" has been reported to you, a partner, a member, an officer, or an employee designated to give notice to us. Notice should include: (1) How, when and where the "accident" or "loss" occurred; AP-0401 (10/17) -2- (2) The "insureds" name and address; and (3) To the extent possible, the names and addresses of any injured persons and witnesses. 9. EMPLOYEES AS INSURED The following is added to the Section II - Covered Autos Liability Coverage, Paragraph Ai. Who Is An Insured provision: Any "employee" of yours is an "insured" while using a covered "auto" you don't own, hire or borrow in your business or your personal affairs. 10. EMPLOYEE HIRED AUTOS A Changes In Covered Autos Liability Coverage The following is added to the Who Is An Insured Provision: An "employee" of yours is an "insured" while operating an "auto" hired or rented under a contract or agreement in an "employee's" name, with your permission, while performing duties related to the conduct of your business. B. Changes In General Conditions Paragraph 5.b. of the Other Insurance Condition in the Business Auto Coverage Form and Paragraph 5.f. of the Other Insurance - Primary And Excess Insurance Provisions Condition in the Motor Carrier Coverage Form are replaced by the following: For Hired Auto Physical Damage Coverage, the following are deemed to be covered "autos" you own: 1. Any covered "auto" you lease, hire, rent or borrow, and 2. Any covered "auto" hired or rented by your "employee" under a contract in an "employee's" name, with your permission, while performing duties related to the conduct of your business. However, any "auto" that is leased, hired, rented or borrowed with a driver is not a covered "auto" 11. BODILY INJURY EXTENSION SECTION V - DER"' IONS , Paragraph C. is deleted and replaced by the following: C. "Bodily injury" means bodily injury, sidmess or disease sustained by a person, including mental anguish or death resulting from any of these, at any time. Mental anguish means any type of mental or emotional illness or disease. 12. HIRED AUTO PHYSICAL DAMAGE SECTION III.A4. - Coverage Extensions - Paragraph c. is added: C. Hired Auto Physical Damage If Comprehensive, Specified Causes of Loss or Collision coverage is provided under this policy, then Hired Auto Physical Damage is provided for that coverage part subject to the following: (1) The most we will pay for any one "accident" or "loss" under this Hired Auto Physical Damage Coverage is the lesser of: (a) The any one "Accident" or "Loss" amount of $100,000; (b) The actual cash value; or AP-0401 (10/17) -3- (c) Cost of repair. Our obligation to pay for a loss in c.(1) above will be reduced by a deductible. The deductible will be equal to the largest deductible applicable to any owned "auto" for that coverage. The deductible will be waived for "loss" caused by fire or lightning. (2) Subject to paragraph c.(1). above, we will provide coverage equal to the broadest physical damage coverage applicable to any covered "auto" shown in the declarations. (3) When you are required by written contract to indemnify a lessor for actual financial loss because of loss of use of a hired "auto" resulting from a covered "accident" or "loss", we will cover that financial loss subject to the limit specified in paragraph c.(1). 13. ENHANCED SUPPLEMENTARY PAYMENTS SECTION II.A.2.a. COVERAGE EXTENSIONS, Supplementary Payments (2) and (4) are replaced by the following: (2) Up to $2,500 for the cost of bail bonds (including bonds for related traffic laws violations) required because of an "accident" we cover. We do not have to furnish these bonds. (4) All reasonable expenses incurred by the "insured" at our request, including actual loss of earnings up to $350 a day because of time off from work. 14. FELLOW EMPLOYEE COVERAGE FOR DESIGNATED POSITIONS The Fellow Employee Exclusion contained in Section 11.115. does not apply to the following positions or job titles: foreman, supervisor, manager, officer, partner or other senior level "employee". Coverage is excess over all other collectible insurance. 15. PHYSICAL DAMAGE - TRANSPORTATION EXPENSES SECTION III.A.4.a Transportation Expenses is replaced by the following: a Transportation Expenses We will pay up to $50 per day to a maximum of $1,500 for temporary transportation expense incurred by you because of the total theft of a covered "auto". We will pay only for those covered "autos" for which you carry either Comprehensive or Specified Cause of Loss Coverage. We will pay for temporary transportation expenses incurred during the period beginning 48 hours after the theft and ending, regardless of the policy's expirations, when the covered "auto" is returned to use or we pay for its "loss". For autos provided with temporary transportation expense, the following physical damage coverage will apply: (1) The most we will pay for any one "accident" or "loss" under the temporary transportation expense physical damage coverage is the lessor of: (a) The any one "Accident" or "Loss" amount of $100,000; (b) The actual cash value; or (c) Cost of repair. Our obligation to pay for a loss in a.(1) above will be reduced by a deductible. The deductible will be equal to the largest deductible applicable to any owned "auto" for that coverage. The deductible will be waived for "loss" caused by fire or lightning. AP-0401 (10/17) -4- (2) Subject to paragraph a.(1). above, we will provide coverage equal to the broadest physical damage coverage applicable to any covered "auto" shown in the declarations. (3) When you are required by written contract to indemnify a lessor for actual financial loss because of loss of use of a hired "auto" resulting from a covered "accident" or "loss", we will cover that financial loss subject to the lirrit specified in paragraph a.(1). 16. RENTAL REINBURSENENT COVERAGE SECTION III.A.4. - Coverage Extensions - Paragraph d. is added. d. If you carry Comprehensive, Specified Causes of Loss or Collision coverage for the damaged covered 'auto" as provided under this policy, then Rental Reimbursement Coverage is provided for that coverage part subject to the following: 1. We will pay for rental reimbursement expenses incurred by you for the rental of an "auto" because of "loss" other than theft, to a covered "auto". Payment applies in addition to the otherwise applicable amount of each coverage you have on a covered "auto". No deductibles apply to this coverage. 2. We will only pay for those expenses incurred during the policy period beginning 24 hours after the "loss" and ending, regardless of the policys expiration, with the lesser of the following number of days: (a) The number of days reasonably required to repair or replace the covered "auto"; or, (b) 30 days. (c) Our payment is limited to the lesser of the following amounts: (1) Necessary and actual expenses incurred; or (2) $50 per day. 17. LOAIWLEASE GAP COVERAGE Physical Damage Coverage is amended by the addition of the following: In the event of a total "loss" to a covered "auto", we will pay your additional legal obligation for any difference between the actual cash value of the "auto" at the time of the loss and the "outstanding balance" of the loan/lease, not to exceed $2,500 for any one vehicle or $25,000 annually in aggregate. For the purposes of this endorsement, "outstanding balance" means the amount you owe on the loan/lease at the time of loss less any amounts representing taxes, overdue payments, penalties, interest or charges resulting from overdue payments, additional mileage charges, excess wear and tear charges or lease termination fees, costs for extended warranties, credit Life Insurance; Health, Accident or Disability Insurance purchased with the loan or lease; and carry-over balances from previous loans or leases. 18. ACCIDENTAL AIR BAG DISCHARGE COVERAGE SECTION III.B.3.a - Exclusions . This exclusion does not apply to the accidental discharge of an air bag. 19. GLASS REPAIR- WAIVER OF DEDUCTIBLE SECTION III.D- Deductible is replaced with the following: For each covered "auto", our obligation to pay for, repair, return or replace damaged or stolen property will be reduced by the applicable deductible shown in the Declarations. Any Comprehensive Coverage deductible shown in the Declarations does not apply to "loss" caused by fire or lightning. The deductible does not apply to glass damage if the glass is repaired rather than replaced. AP-0401 (10/17) -5- This page has been left blank intentionally. THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. BLANKET WAIVER OF TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US The Transfer of Rights of Recovery Against Others to Us Condition 16. of SECTION V is amended by the addition of the following: If required by a written contract executed prior to loss, we waive any right of recovery we may have against any person or organization because of payments we make for injury or damage arising out of "your work" for that person or organization. CUP 03 13 01 07 This page has been left blank intentionally. Kensington Drainage Improvements/Holcomb February 14, 2022 Project Number: 18-3019 KENT SPECIAL PROVISIONS TABLE OF CONTENTS PAGE DIVISION 1 GENERAL REQUIREMENTS ..................................... 1-1 1-01 Definitions and Terms ...................................................... 1-1 1-02 Bid Procedures and Conditions .......................................... 1-2 1-03 Award and Execution of Contract....................................... 1-5 1-04 Scope of the Work .......................................................... 1-5 1-05 Control of Work .............................................................. 1-8 1-06 Control of Material .......................................................... 1-14 1-07 Legal Relations and Responsibilities to the Public ................. 1-17 1-08 Prosecution and Progress ................................................. 1-24 1-09 Measurement and Payment .............................................. 1-29 1-10 Temporary Traffic Control ................................................ 1-30 DIVISION 2 EARTHWORK .......................................................... 2-1 2-02 Removal of Structures and Obstructions ............................. 2-1 2-06 Subgrade Preparation ...................................................... 2-3 2-07 Watering ....................................................................... 2-4 2-12 Construction Geosynthetic ................................................ 2-4 DIVISION 4 BASES .................................................................... 4-1 4-03 Gravel Borrow ................................................................ 4-1 4-04 Ballast and Crushed Surfacing .......................................... 4-1 DIVISION 5 SURFACE TREATMENTS AND PAVEMENTS .............. 5-1 5-02 Bituminous Surface Treatment .......................................... 5-1 5-04 Hot Mix Asphalt .............................................................. 5-1 DIVISION 7 DRAINAGE STRUCTURES, STORM SEWERS, SANITARY SEWERS, WATER MAINS, AND CONDUITS .............. 7-1 7-01 Drains ........................................................................... 7-1 7-04 Storm Sewers ................................................................ 7-1 7-05 Manholes, Inlets, Catch Basins, and Drywells ...................... 7-3 7-08 General Pipe Installation Requirements .............................. 7-8 7-17 Sanitary Sewers ............................................................. 7-12 7-19 Sewer Cleanouts ............................................................. 7-18 DIVISION 8 MISCELLANEOUS CONSTRUCTION ......................... 8-1 8-01 Erosion Control and Water Pollution Control ........................ 8-1 8-02 Roadside Restoration ....................................................... 8-5 8-03 Irrigation Systems .......................................................... 8-12 8-12 Chain Link Fence and Wire Fence ...................................... 8-13 8-15 Riprap ........................................................................... 8-13 8-21 Permanent Signing .......................................................... 8-14 8-22 Pavement Marking .......................................................... 8-14 8-24 Rock and Gravity Block Wall and Gabion Cribbing ................ 8-16 Kensington Drainage Improvements/Holcomb February 14, 2022 Project Number: 18-3019 KENT SPECIAL PROVISIONS TABLE OF CONTENTS PAGE DIVISION 8 MISCELLANEOUS CONSTRUCTION 8-30 Project Signs .................................................................. 8-16 8-33 Tree Removal for Construction Improvements ..................... 8-17 DIVISION 9 MATERIALS ............................................................ 9-1 9-03 Aggregates .................................................................... 9-1 9-13 Riprap, Quarry Spalls, Slope Protection, and Rock for Erosion and Scour Protection and Rock Walls ...................... 9-3 9-14 Erosion Control and Roadside Planting ............................... 9-3 9-16 Fence and Guardrail ........................................................ 9-8 9-28 Signing Materials and Fabrication ...................................... 9-8 KENT STANDARD PLANS ................................................................. A-1 WSDOT STANDARD PLANS .............................................................. A-2 GEOTECHNICAL REPORT ................................................................. A-3 KENSINGTON NON-CRITICAL AREA DETERMINATION .................... A-4 CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN .... A-5 PROJECT SIGN ................................................................................ A-6 PREVAILING WAGE RATES .............................................................. A-7 Kensington Drainage Improvements/Holcomb 1 - 1 February 14, 2022 Project Number: 18-3019 KENT SPECIAL PROVISIONS The Kent Special Provisions (Kent Special Provisions or KSP) modify and supersede any conflicting provisions of the 2022 Standard Specifications for Road, Bridge, and Municipal Construction, as prepared by the Washington State Department of Transportation and the Washington State Chapter of the American Public Works Association, including all published amendments issued by those organizations (WSDOT Standard Specifications). Otherwise all provisions of the WSDOT Standard Specifications shall apply. All references in the WSDOT Standard Specifications to the State of Washington, its various departments or directors, or to the contracting agency, shall be revised to include the City and/or City Engineer, except for references to State statutes or regulations. Finally, all of these documents are a part of this contract. DIVISION 1 – GENERAL REQUIREMENTS 1-01 DEFINITIONS AND TERMS SECTION 1-01.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 1-01.1 General When these Kent Special Provisions make reference to a Section, for example, in accordance with Section 1-01, the reference is to the WSDOT Standard Specifications as modified by these Kent Special Provisions. SECTION 1-01.2(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 1-01.2(2) Items of Work and Units of Measurement EA Each Eq. Adj. Equitable Adjustment FA Force Account HR Hour M GAL Thousand gallons NIC Not In Contract SF Square Feet SECTION 1-01.3, “CONTRACT” DEFINITION, IS DELETED AND REPLACED WITH THE FOLLOWING: 1-01.3 Definitions Contract The written agreement between the Contracting Agency and the Contractor. It describes, among other things: 1. What work will be done, and by when; 2. Who provides labor and materials; and Kensington Drainage Improvements/Holcomb 1 - 2 February 14, 2022 Project Number: 18-3019 3. How Contractors will be paid. The Contract includes the Contract (agreement) Form, Bidders completed Proposal Form, Kent Special Provisions, Contract Provisions, Contract Plans, WSDOT Standard Specifications (also including amendments to the Standard Specifications issued by WSDOT as of the later date of bid advertisement or any subsequent addenda), Kent Standard Plans, Addenda, various certifications and affidavits, supplemental agreements, change orders, and subsurface boring logs (if any). Also incorporated in the Contract by reference are: 1. Standard Plans (M21-01) for Road, Bridge and Municipal Construction as prepared by the Washington State Department of Transportation and the American Public Works Association, current edition; 2. Manual on Uniform Traffic Control Devices for Streets and Highways, current edition, and; 3. American Water Works Association Standards, current edition; 4. The current edition of the National Electrical Code. Responsibility for obtaining these publications rests with the Contractor. SECTION 1-01.3, “DEFINITIONS” IS SUPPLEMENTED BY ADDING THE FOLLOWING DEFINITION: Incidental Work The terms incidental to the project, incidental to the involved bid item(s), etc., as used in the Contract shall mean that the Contractor is required to complete the specified work and the cost of such work shall be included in the unit contract prices of other bid items as specified in Section 1-04.1 (Intent of the Contract). No additional payment will be made. 1-02 BID PROCEDURES AND CONDITIONS SECTION 1-02.1 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-02.1 Qualification of Bidders Bidders shall be qualified by ability, experience, financing, equipment, and organization to do the work called for in the Contract. The City reserves the right to take any action it deems necessary to ascertain the ability of the Bidder to perform the work satisfactorily. This action includes the Citys review of the qualification information in the bid documents. The City will use this qualification data in its decision to determine whether the lowest responsive bidder is also responsible and able to perform the contract work. If the City determines that the lowest bidder is not the lowest responsive and responsible bidder, the City reserves its unqualified right to reject that bid and award the Kensington Drainage Improvements/Holcomb 1 - 3 February 14, 2022 Project Number: 18-3019 contract to the next lowest bidder that the City, in its sole judgment, determines is also responsible and able to perform the contract work (the lowest responsive and responsible bidder). SECTION 1-02.2 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-02.2 Plans and Specifications Upon awarding the Contract, the City shall supply to the Contractor, for its own use, up to ten (10) copies of the plans and specifications. If the Contractor requests more than ten (10) copies, the City may require the Contractor to purchase the additional sets. SECTION 1-02.5 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-02.5 Proposal Forms Prospective bidders may obtain Bid Documents including a Bid Proposal for the advertised project by downloading at no charge at KentWA.gov/doing-business/bids-procurement; however, a prospective bidder remains responsible to obtain Bid Documents, even if unable to download all or any part of the documents, whether or not inability to access is caused by the bidders or the Citys technology. SECTION 1-02.6 IS REVISED BY DELETING THE THIRD PARAGRAPH AND REPLACING WITH THE FOLLOWING: 1-02.6 Preparation of Proposal It is the Bidders sole responsibility to obtain and incorporate all issued addenda into the bid. In the space provided on the Proposal Signature Page, the Bidder shall confirm that all Addenda have been received. All blanks in the proposal forms must be appropriately filled in. SECTION 1-02.6 IS SUPPLEMENTED BY ADDING THE FOLLOWING TO THE LAST PARAGRAPH: Proposals must contain original signature pages. FACSIMILES OR OTHER FORMS OF ELECTRONIC DELIVERY ARE NOT ACCEPTABLE AND ARE CONSIDERED NON-RESPONSIVE SUBMITTALS. SECTION 1-02.7 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-02.7 Bid Deposit A deposit of at least 5 percent of the total Bid shall accompany each Bid. This deposit may be cash, cashiers check, or a proposal bond (Surety bond). Any proposal bond shall be on the Citys bond form and shall be signed by the Bidder and the Surety. A proposal bond shall not be conditioned in any way to modify the minimum 5-percent required. The Surety shall: (1) be registered with the Washington State Insurance Commissioner, and (2) appear on the current Authorized Kensington Drainage Improvements/Holcomb 1 - 4 February 14, 2022 Project Number: 18-3019 Insurance List in the State of Washington published by the Office of the Insurance Commissioner. The failure to furnish a Bid deposit of a minimum of 5 percent with the Bid shall make the Bid nonresponsive and shall cause the Bid to be rejected by the Contracting Agency. SECTION 1-02.9 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-02.9 Delivery of Proposal All bids must be sealed and delivered in accordance with the Invitation to Bid. Bids must be received at the City Clerks office by the stated time, regardless of delivery method, including U.S. Mail. SECTION 1-02.10 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-02.10 Withdrawing, Revising, or Supplementing Proposal After submitting a Bid Proposal to the Contracting Agency, the Bidder may withdraw or revise it if: 1. The Bidder submits a written request signed by an authorized person, and 2. The Contracting Agency receives the request before the time for opening Bids. The original Bid Proposal may be revised and resubmitted as the official Bid Proposal if the Contracting Agency receives it before the time for opening Bids. SECTION 1-02.11 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-02.11 Combination and Multiple Proposals No person, firm or corporation shall be allowed to make, file, or be interested in more than one bid for the same work unless alternate bids are specifically called for; however, a person, firm, or corporation that has submitted a subproposal to a bidder, or that has quoted prices of materials to a bidder is not disqualified from submitting a subproposal or quoting prices to other bidders or from making a prime proposal. SECTION 1-02.13 IS REVISED BY DELETING ITEM 1(a) AND REPLACING ITEM 1(a) WITH THE FOLLOWING: 1-02.13 Irregular Proposals a. The bidder is not prequalified when so required. SECTION 1-02.14 IS REVISED BY DELETING ITEM 3 AND REPLACING WITH THE FOLLOWING: Kensington Drainage Improvements/Holcomb 1 - 5 February 14, 2022 Project Number: 18-3019 1-02.14 Disqualification of Bidders 3. The bidder is not qualified for the work or to the full extent of the bid. 1-03 AWARD AND EXECUTION OF CONTRACT SECTION 1-03.1 IS REVISED BY INSERTING THE FOLLOWING PARAGRAPH AFTER THE SECOND PARAGRAPH IN THAT SECTION: 1-03.1 Consideration of Bids The City also reserves the right to include or omit any or all schedules or alternates of the Proposal and will award the Contract to the lowest responsive, responsible bidder based on the total bid amount, including schedules or alternates selected by the City. SECTION 1-03.2 IS REVISED BY REPLACING “45 CALENDAR DAYS” WITH “60 CALENDAR DAYS” RELATING TO CONTRACT AWARD OR BID REJECTION. 1-03.2 Award of Contract SECTION 1-03.3 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-03.3 Execution of Contract No claim for delay shall be granted to the Contractor due to its failure to submit the required documents to the City in accordance with the schedule provided in these Kent Special Provisions. SECTION 1-03.7 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-03.7 Judicial Review Any decision made by the City regarding the award and execution of the contract or bid rejection shall be conclusive subject to the scope of judicial review permitted under Washington State Law. Such review, if any, shall be timely filed in the King County Superior Court, located in Kent, Washington. 1-04 SCOPE OF THE WORK 1-04.1 Intent of the Contract SECTION 1-04.1(2) IS DELETED AND REPLACED WITH THE FOLLOWING: 1-04.1(2) Bid Items Not Included in the Proposal The Contractor shall include all costs of doing the work within the bid item prices. If the contract plans, contract provisions, addenda, or any other part of the contract require work that has no bid item price in the proposal form, the entire cost of labor and materials required to Kensington Drainage Improvements/Holcomb 1 - 6 February 14, 2022 Project Number: 18-3019 perform that work shall be incidental and included with the bid item prices in the contract. SECTION 1-04.2 IS SUPPLEMENTED BY ADDING THE WORDS, “KENT SPECIAL PROVISIONS, KENT STANDARD PLANS” FOLLOWING THE WORDS, “CONTRACT PROVISIONS” IN THE FIRST SENTENCE OF THE FIRST PARAGRAPH. SECTION 1-04.2 IS REVISED BY DELETING ITEMS 1 THROUGH 7 IN THE SECOND PARAGRAPH AND REPLACING WITH THE FOLLOWING 8 ITEMS: 1-04.2 Coordination of Contract Documents, Plans, Special Provisions, Specifications, and Addenda 1. Approved Change Orders 2. The Contract Agreement 3. Kent Special Provisions 4. Contract Plans 5. Amendments to WSDOT Standard Specifications 6. WSDOT Standard Specifications 7. Kent Standard Plans 8. WSDOT Standard Plans SECTION 1-04.4 IS REVISED BY DELETING THE THIRD PARAGRAPH (INCLUDING SUBPARAGRAPHS A AND B). 1-04.4 Changes SECTION 1-04.4 IS REVISED BY DELETING THE FIFTH PARAGRAPH AND REPLACING IT WITH THE FOLLOWING: For Item 2, increases or decreases in quantity for any bid item shall be paid at the appropriate bid item contract price, including any bid item increase or decrease by more than 25 percent from the original planned quantity. SECTION 1-04.4 IS REVISED BY DELETING THE EIGHTH PARAGRAPH (NEXT TO THE LAST PARAGRAPH) AND REPLACING WITH THE FOLLOWING: Within 14 calendar days of delivery of the change order the Contractor shall endorse and return the change order, request an extension of time for endorsement or respond in accordance with Section 1-04.5. The Contracting Agency may unilaterally process the change order if the Contractor fails to comply with these requirements. Changes normally noted on field stakes or variations from estimated quantities, will not require a written change order. These changes shall be made at the unit prices that apply. The Contractor shall respond immediately to changes shown on field stakes without waiting for further notice. SECTION 1-04.6 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-04.6 Variation in Estimated Quantities Kensington Drainage Improvements/Holcomb 1 - 7 February 14, 2022 Project Number: 18-3019 Payment to the Contractor will be made only for the actual quantities of Work performed and accepted in conformance with the Contract. SECTION 1-04.9 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-04.9 Use of Private Properties Staging and storage locations needed for the Project must be properly permitted for that use. Contractor may not stage or store equipment within easements outside of working hours. Limits of construction are indicated or defined on the plans. The Contractor shall confine all construction activities within these limits. If a staging and storage area is shown on the plans, the City will obtain all permits and approvals necessary for the Contractors use. Whether the City does or does not provide a staging area, if the Contractor selects its own staging and storage area(s), it is the Contractors sole responsibility to obtain all necessary permits/approvals to use the private property, specifically including, without limitation, all permits or approvals subject to State Environmental Policy Act, Shoreline Management Act, and critical areas regulations. Before using any other property as a staging or storage area (or for any other use), the Contractor shall thoroughly investigate the property for the presence of critical areas, buffers of critical areas, or other regulatory restrictions as defined in Kent City Code, county, state or federal regulations, and the Contractor shall provide the City written documentation that the property is not subject to other regulatory requirements or that the Contractor has obtained all necessary rights of entry, permits and approvals needed to use the property as the Contractor intends. Upon vacating the private property, the Contractor shall provide the City written verification that it has obtained all releases and/or performed all mitigation work as required by the conditions of the permit/approval and/or agreement with the property owner. The Contractor shall not be entitled to additional compensation or an extension of the time of completion of the Contractor for any work associated with the permitting, mitigation or use of private property. SECTION 1-04.11 ITEM 2 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-04.11 Final Cleanup 2. Remove from the project all unapproved and/or unneeded material left from grading, surfacing, paving, or temporary erosion control measures. Kensington Drainage Improvements/Holcomb 1 - 8 February 14, 2022 Project Number: 18-3019 1-05 CONTROL OF WORK SECTION 1-05.4 IS REVISED BY DELETING THE LAST FOUR PARAGRAPHS. 1-05.4 Conformity With and Deviations From Plans and Stakes SECTION 1-05.4 IS REVISED BY ADDING THE FOLLOWING PARAGRAPH AFTER PARAGRAPH 7: To the extent a conflict exists between the requirements of WSDOT Section 1-05.4 and Kent Special Provision Section 1-05.8, the requirements of KSP Section 1-05.8 will prevail. SECTION 1-05.7 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 1-05.7 Removal of Defective and Unauthorized Work If the Contractor fails to remedy defective or unauthorized work within the time specified by the Engineer, or fails to perform any part of the work required by the contract, the Engineer may provide the Contractor written notice establishing a date after which the City will correct and remedy that work by any means that the Engineer may deem necessary, including the use of City forces or other contractors. If the Engineer determines that the Contractors failure to promptly correct any defective or any unauthorized work creates a situation that could be potentially unsafe or might cause serious risk of loss or damage to the public, the Engineer may have the defective and unauthorized work corrected immediately, have the rejected work removed and replaced, or have the work the Contractor refuses to perform completed by using City or other forces. Direct and indirect costs incurred by the City attributable to correcting and remedying defective or unauthorized work, or work the Contractor failed or refused to perform, shall be paid by the Contractor. Payment may be deducted by the Engineer from monies due, or to become due, the Contractor. Direct and indirect costs shall include, without limitation, compensation for additional professional services required, compensation and engineering and inspection services required, and costs for repair and replacement of work of others destroyed or damaged by correction, removal, or replacement of the Contractors unauthorized work. No increase in contract time or compensation will be allowed because of the delay in the performance of the work attributable to the exercise of the Citys rights provided by this se ction nor shall the exercise of this right diminish the Citys right to pursue any other remedy available under law with respect to the Contractors failure to perform the work as required. DIVISION 1 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTIONS: Kensington Drainage Improvements/Holcomb 1 - 9 February 14, 2022 Project Number: 18-3019 1-05.8 City Provided Construction Staking 1-05.8(1) General As used in this Section 1-05.8, the words, stake, mark, marker, or monument will be deemed to include any kind of survey marking, whether or not set by the City. The City will supply construction stakes and marks establishing lines and points as set forth in Sections 1-05.8(2) and 1-05.8(3) of the Kent Special Provisions. The Contractor shall assume full responsibility for detailed dimensions, elevations, and measurements from these City furnished stakes and marks. The Contractor shall provide a work site clear of equipment, stockpiles and obstructions which has been prepared and maintained to permit construction staking to proceed in a safe and orderly manner. The Contractor shall provide staking requests for a reasonable amount of work to the Engineer at least 3 working days in advance to allow the survey crew adequate time for setting stakes. If the work site is obstructed so that survey work cannot be done, a new request for work shall be submitted by the Contractor so that the survey can be rescheduled once the site is properly prepared. Up to an additional 3 working days may be required depending on work load for the city survey crew to complete the rescheduled work. Note: A surveyor working day is a consecutive eight hour period between 7:00 AM and 4:00 PM, Monday through Friday, except holidays as listed in Section 1- 08.5. It is illegal under Revised Code of Washington 58.09.130 and Washington State Administrative Code 332-120 to willfully destroy survey markers. Stakes, marks, and other reference points set by City forces, and existing City, State or Federal monumentation, shall be carefully preserved by the Contractor. The Contractor shall notify the Engineer immediately if it becomes apparent that a survey marker will be disturbed due to construction. The Contractor will allow ample time for City Survey Department personnel to acquire adequate information so that the monument may be replaced in its original position after construction. If the City is not notified, and a stake, marker or monument is disturbed or destroyed the Contractor will be charged at a rate of $300/hour for a city survey crew to replace the stake, marker or monument that was not to be disturbed or damaged by the Contractors operations. This charge will be deducted from monies due or to become due to the Contractor. Any claim by the Contractor for extra compensation by reason of alterations or reconstruction work allegedly due to error in the Surveyors line and grade will not be allowed unless the original control points set by the Surveyor still exist, or unless the Contractor can provide other satisfactory substantiating evidence to prove the error was caused by incorrect city-furnished survey data. Three consecutive points set on line or grade shall be the minimum points used to determine any variation from a straight line or grade. Any such Kensington Drainage Improvements/Holcomb 1 - 10 February 14, 2022 Project Number: 18-3019 variation shall, upon discovery, be reported to the Engineer. In the absence of such report, the Contractor shall be liable for any error in alignment or grade. 1-05.8(3) Control Stakes Stakes that constitute reference points for all construction work will be conspicuously marked with an appropriate color of flagging tape. It will be the responsibility of the Contractor to inform its employees and subcontractors of the importance and necessity to preserve the stakes. The Contractor shall determine appropriate construction stake offset distances to prevent damage to stakes by its construction equipment. Should it become necessary, for any reason, to replace these control stakes, the Contractor will be charged at the rate of $300/hour for a city survey crew to replace the stakes. The Contractor may not charge the City for any standby or down time as a result of any replacement of control stakes. If the removal of a control stake or monument is required by the construction operations of the Contractor or its subcontractors, and advance notice of at least three (3) full working days is given to the City, the City will reference, remove, and later replace the stakes or monument at no cost to the Contractor. 1-05.8(4) Control Stakes Stakes that constitute reference points for all construction work will be conspicuously marked with an appropriate color of flagging tape. It will be the responsibility of the Contractor to inform its employees and subcontractors of the importance and necessity to preserve the stakes. The Contractor shall determine appropriate construction stake offset distances to prevent damage to stakes by its construction equipment. Should it become necessary, for any reason, to replace these control stakes, the Contractor will be charged at the rate of $300/hour for a city survey crew to replace the stakes. The Contractor may not charge the City for any standby or down time as a result of any replacement of control stakes. If the removal of a control stake or monument is required by the construction operations of the Contractor or its subcontractors, and advance notice of at least three (3) full working days is given to the City, the City will reference, remove, and later replace the stakes or monument at no cost to the Contractor. 1-05.8(5) Staking Services Work requests must be made at least 3 working days in advance of the required staking. The City will furnish the following stakes and reference marks: 1. Clearing Limits - One set of clearing limit stakes will be set at approximately 25-foot stations where needed. Kensington Drainage Improvements/Holcomb 1 - 11 February 14, 2022 Project Number: 18-3019 2. Rough Grading - One set of rough grade stakes will be set along the construction centerline of streets at 50-foot stations as required. (If superelevations require intermediate stakes along vertical curves, the City will provide staking at closer intervals.) One set of primary cut and fill stakes will be set for site work. One set of secondary final grade cut and fill stakes will be set where deemed applicable as determined by the Engineer. 3. Storm Sewers - Two cut or fill stakes for each inlet, catch basin or manhole will be set at appropriate offsets to the center of the structure. After installation and backfill, inverts will be checked for correctness. 4. Sanitary Sewers - Two cut or fill stakes for each manhole or cleanout location will be set at appropriate offsets to the center of the structure. After installation and backfill, inverts will be checked for correctness. 5. Water Main - One set of line stakes will be furnished for water mains at 50-foot stations. Additionally, two reference stakes for each valve, hydrant, tee and angle point location will be set concurrently with these line stakes. 6. Staking for Embankments - Catch points and one line stake will be set in those cases where the vertical difference in elevation from the construction centerline to the toe or top of a cut or fill slope exceeds 3 feet. In all other areas, stakes shall be set at an appropriate offset to the street centerline to allow for the preservation of said offsets through the rough grading phase. In both cases the stakes shall be clearly marked with appropriate information necessary to complete the rough grading phase. 7. Curb and Gutters - One set of curb and gutter stakes shall be set at an appropriate offset at 25-foot intervals, beginning and end points of curves and curb returns, wheelchair ramps, driveways, and sufficient mid-curve points to establish proper alignment. 8. Base and Top Course - One set of final construction centerline grade hubs will be set for each course, at not less than 50-foot stations. No intermediate stakes shall be provided unless superelevations require them. In those circumstances, one grade hub left and right of construction centerline at the transition stations will be set at an appropriate offset to centerline not less than 25-foot stations. 9. Adjacent or Adjoining Wetlands - One set of stakes delineating adjacent wetland perimeters will be set at 25 to 50-foot stations as required. 10. Illumination and Traffic Signals System - One set of stakes for luminaires and traffic signal pole foundations will be set as required. One set of stakes for vaults, junction boxes, and conduits will be set, only if curb and gutter is not in place at the time of the survey request. If curb and gutter is in place, staking for vaults, junction boxes, and conduits will be provided at an additional expense to the Contractor. When deemed appropriate by the Engineer, cut sheets will be supplied for curb, storm, sanitary sewer and water lines. Cuts or fills may be Kensington Drainage Improvements/Holcomb 1 - 12 February 14, 2022 Project Number: 18-3019 marked on the surveyed points but should not be relied on as accurate until a completed cut sheet is supplied. The Contractor, at its own expense, shall stake all other items not listed above to construct the project per the Plans and Specifications. Staking for channelization, traffic loops, and all other items not listed above shall be the sole responsibility and expense of the Contractor. The City may, at its sole discretion, provide additional staking at the request of the Contractor at the rate of $300/hour. 1-05.8(6) Survey Requests It shall be the Contractors responsibility to properly schedule survey crews and coordinate staking requests with construction activities. A survey crew may be reasonably expected to stake any one of the following items, in the quantity shown, in a single day: Roadway grading +/-1500 lineal feet of centerline Storm or sanitary sewer Approximately 8-10 structures Water main +/-1500 lineal feet of pipe Curb and gutter +/-1300 lineal feet (one side only) Base and top course +/-1000 lineal feet of centerline Slope staking +/-800-1200 lineal feet (top and toe) Illumination/signalization Approximately 15-20 structures Actual quantities may vary based on the complexity of the project, line of sight considerations, traffic interference, properly prepared work site, and other items that could affect production. The Contractor shall be aware that length does not always translate directly into stationing. For example, a survey request for storm sewer pipe from Station 3+00 to 8+00 is 500 lineal feet in length. There may be 1000 lineal feet, or more, of storm sewer pipe, if the pipe is placed on both sides of the roadway and interconnected. SECTION 1-05.9 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SUBSECTION: 1-05.9 Equipment 1-05.9(1) Operational Testing It is the intent of the City to have at the Physical Completion Date a complete and operable system. Therefore when the work involves the installation of machinery or other mechanical equipment, street lighting, electrical distribution of signal systems, building or other similar work, it may be desirable for the Engineer to have the Contractor operate and test the work for a period of time after final inspection but prior to the Physical Completion Date. Whenever items of work are listed in the contract provisions for operational testing they shall be fully tested under operating conditions for the time period specified to ensure their acceptability prior to the Kensington Drainage Improvements/Holcomb 1 - 13 February 14, 2022 Project Number: 18-3019 Physical Completion Date. In the event the contract does not specify testing time periods, the default testing time period shall be twenty-one (21) calendar days. During and following the test period, the Contractor shall correct any items of workmanship, materials, or equipment that prove faulty or that are not in first class operating condition. Equipment, electrical controls, meters, or other devices and equipment to be tested during this period shall be tested under the observation of the Engineer, so that the Engineer may determine their suitability for the purpose for which they were installed. The Physical Completion Date cannot be established until testing and corrections have been completed to the satisfaction of the Engineer. The costs for power, gas, labor, material, supplies, and everything else needed to successfully complete operational testing shall be included in the various contract bid item prices unless specifically set forth otherwise in the contract. Operational and test periods, when required by the Engineer, shall not affect a manufacturers guaranties or warranties furnished under the terms of the Contract. SECTION 1-05.10 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-05.10 Guarantees In addition to any other warranty or guarantee provided for at law or in the parties contract, the Contractor shall furnish to the Contracting Agency any guarantee or warranty furnished as a customary trade practice in connection with the purchase of any equipment, materials, or items incorporated into the project. Upon receipt of written notice of any required corrective work, the Contractor shall pursue vigorously, diligently, and without disrupting city facilities, the work necessary to correct the items listed in the notice. Approximately sixty (60) calendar days prior to the one year anniversary of final acceptance, the Contractor shall be available to tour the project, with the Engineer, in support of the Engineers effort to establish a list of corrective work then known and discovered. SECTION 1-05.13 IS REVISED BY INSERTING THE FOLLOWING PARAGRAPH AFTER THE FIRST PARAGRAPH: 1-05.13 Superintendents, Labor, and Equipment of Contractor Within ten (10) days of contract award, the Contractor shall designate the Contractor's project manager and superintendent for the contract work. Kensington Drainage Improvements/Holcomb 1 - 14 February 14, 2022 Project Number: 18-3019 SECTION 1-05.13 IS REVISED BY INSERTING THE FOLLOWING PARAGRAPH AFTER THE THIRD PARAGRAPH (AS PRINTED IN THE 2022 WSDOT STANDARD SPECIFICATIONS): If at any time during the contract work, the Contractor elects to replace the contract manager or superintendent, the Contractor shall only do so after obtaining the Engineer's prior written approval. THE LAST PARAGRAPH OF 1-05.13 IS DELETED AND REPLACED WITH THE FOLLOWING: Whenever the City evaluates the Contractors qualifications or prequalifications pursuant to Section 1-02.1 or RCW 47.28.070, the City may take these or other Contractor performance reports into account. SECTION 1-05.14 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 1-05.14 Cooperation With Other Contractors Details of known projects are as follows: N/A SECTION 1-05 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTIONS: 1-05.16 Water and Power The Contractor shall make necessary arrangements, and shall bear the costs for power and water necessary for the performance of the work, unless the Contract includes power or water as bid items, or unless otherwise provided for in other bid items. 1-05.17 Oral Agreements No oral agreement or conversation with any officer, agent, or employee of the City, either before or after execution of the contract, shall affect or modify the terms or obligations contained in any of the documents comprising the contract. Such oral agreement or conversation shall be considered unofficial information and in no way binding upon the City, unless subsequently recorded and/or put in writing and signed by an authorized agent of the City. 1-06 CONTROL OF MATERIAL 1-06.2 Acceptance of Materials SECTION 1-06.2(2) IS DELETED IN ITS ENTIRETY. 1-06.2(2) Statistical Evaluation of Materials for Acceptance SECTION 1-06 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTIONS: Kensington Drainage Improvements/Holcomb 1 - 15 February 14, 2022 Project Number: 18-3019 1-06.7 Submittals 1-06.7(1) Submittal Procedures All information submitted by the Contractor shall be clear, sharp, high contrast copies. Contractor shall accompany each submittal with a letter of transmittal containing the following information: 1.Contractors name and the name of Subcontractor or supplier who prepared the submittal. 2. The project name and identifying number. 3. Each new submittal shall be sequentially numbered (1, 2, 3, etc.). Each resubmittal shall include the original number with a sequential alpha letter added (1A, 1B, 1C, etc.). 4. Description of the submittal and reference to the Contract requirement or technical specification section and paragraph number being addressed. 5. Bid item(s) where product will be used. 1-06.7(2) Schedule of Submittals The Contractor shall create and submit three (3) copies of a schedule of submittals showing the date by which each submittal required for product review or product information will be made. The schedule can be modified, deducted, or added to by the City. The schedule shall be available at the preconstruction conference (see 1-08.0 of the Kent Special Provisions). The schedule of submittals must be accepted prior to the City making the first progress payment. The schedule shall identify the items that will be included in each submittal by listing the item or group of items and the Specification Section and paragraph number and bid item under which they are specified. The schedule shall indicate whether the submittal is required for product review of proposed equivalents, shop drawings, product data or samples or required for product information only. The Contractor shall allow a minimum of 21 days for the Engineers review of each submittal or resubmittal. All submittals shall be in accordance with the approved schedule of submittals. Submittals shall be made early enough to allow adequate time for manufacturing, delivery, labor issues, additional review due to inadequate or incomplete submittals, and any other reasonably foreseeable delay. 1-06.7(3) Shop Drawings, Product Data, and Samples The Contractor shall submit the following for the Engineers review: 1. Shop Drawings: Submit an electronic copy or three paper copies. Submittals will be marked, stamped and returned to the Contractor. The Contractor shall make and distribute any required copies for its superintendent, subcontractors and suppliers. 2. Product Data: Submit an electronic copy or three paper copies. Submittals will be marked, stamped and returned to the Kensington Drainage Improvements/Holcomb 1 - 16 February 14, 2022 Project Number: 18-3019 Contractor. The Contractor shall make and distribute any required copies for its superintendent, subcontractors and suppliers. 3. Samples: Submit three labeled samples or three sets of samples of manufacturers full range of colors and finishes unless otherwise directed. One approved sample will be returned to the Contractor. Content of submittals: 1. Each submittal shall include all of the items required for a complete assembly or system. 2. Submittals shall contain all of the physical, technical and performance data required to demonstrate conclusively that the items comply with the requirements of the Contract. 3. Each submittal shall verify that the physical characteristics of items submitted, including size, configurations, clearances, mounting points, utility connection points and service access points, are suitable for the space provided and are compatible with other interrelated items. 4. The Contractor shall label each Product Data submittal, Shop Drawing or Sample with the bid item number and, if a lump sum bid item, provide a reference to the applicable KSP paragraph. The Contractor shall highlight or mark every page of every copy of all Product Data submittals to show the specific items being submitted and all options included or choices offered. The City encourages a creative approach to complete a timely, economical, and quality project. Submittals that contain deviations from the requirements of the Contract shall be accompanied by a separate letter explaining the deviations. The Contractors letter shall: 1. Cite the specific Contract requirement including the Specification Section bid item number and paragraph number for which approval of a deviation is sought. 2. Describe the proposed alternate material, item or construction, explain its advantages, and explain how the proposed alternate meets or exceeds the Contract requirements. 3. State the reduction in Contract Price, if any, which is offered to the City. The Engineer retains the exclusive right, at his or her sole discretion, to accept or reject any proposed deviation with or without cause. The Engineer will stamp and mark each submittal prior to returning it to the Contractor. The stamps will indicate one of the following: 1.APPROVED AS SUBMITTED Accepted subject to its compatibility with the work not covered in this submission. This response does not constitute approval or deletion of specified or required items not shown in the partial submission. 2.APPROVED AS NOTED Accepted subject to minor corrections that shall be made by the Contractor and subject to its compatibility with the work not covered in this submission. This Kensington Drainage Improvements/Holcomb 1 - 17 February 14, 2022 Project Number: 18-3019 response does not constitute approval or deletion of specified or required items not shown in the partial submission. No resubmission is required. 3.AMEND AND RESUBMIT Rejected because of major inconsistencies, errors or insufficient information that shall be resolved or corrected by the Contractor prior to subsequent re- submittal. An amended resubmission is required. Re-submittals that contain changes that were not requested by the Engineer on the previous submittal shall note all changes and be accompanied by a letter explaining the changes. 1-06.7(4) Proposed Equivalents The Engineer retains the exclusive right, at his or her sole discretion, to accept or reject any proposed equivalent with or without cause. 1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC 1-07.2 State Taxes SECTION 1-07.2(1) IS REVISED BY DELETING THE SECOND PARAGRAPH AND REPLACING WITH THE FOLLOWING: 1-07.2(1) State Sales Tax: WAC 458-20-171—Use Tax Without waiving the Contractors obligation to understand and apply these tax rules correctly, the City has indicated those parts of the project that are subject to use tax under Section 1-07.2(1) in the proposal bid items. SECTION 1-07.2(2) IS REVISED BY DELETING THE SECOND PARAGRAPH AND REPLACING WITH THE FOLLOWING: 1-07.2(2) State Sales Tax: WAC 458-20-170—Retail Sales Tax Without waiving the Contractors obligation to understand and apply these tax rules correctly, the City has indicated those parts of the project that are subject to retail sales tax under Section 1-07.2(2) in the proposal bid items. SECTION 1-07.4(2) IS DELETED AND REPLACED WITH THE FOLLOWING: 1-07.4(2) COVID-19 Job Site Requirements The Contractor shall comply with all COVID-19 workplace health and safety measures established by the state Department of Labor & Industries or otherwise imposed by the Governor, the state Department of Health, or the Local Health Officer of Seattle-King County Public Health, or subsequent modifications to such health and safety measures as those authorities may issue, including providing all needed personal protective equipment. Kensington Drainage Improvements/Holcomb 1 - 18 February 14, 2022 Project Number: 18-3019 SECTION 1-07.6 IS SUPPLEMENTED BY INSERTING THE FOLLOWING PARAGRAPH BEFORE THE FIRST PARAGRAPH: 1-07.6 Permits and Licenses SEPA DNS dated September 10, 2021 SECTION 1-07.6 IS SUPPLEMENTED BY INSERTING THE FOLLOWING PARAGRAPHS AFTER THE LAST PARAGRAPH: A copy of each permit and/or license obtained by the Contractor shall be furnished to the City. Approved permits shall be furnished to the City upon completion of the project and prior to final acceptance. The Contractor shall promptly notify the City in writing of any variance in the contract work arising from the issuance of any permit. 1-07.9 Wages SECTION 1-07.9(1) IS SUPPLEMENTED BY INSERTING THE FOLLOWING PARAGRAPH AFTER THE SIXTH PARAGRAPH: 1-07.9(1) General To the extent allowed by law, the wage rates that will be in effect during the entire contract work period are those in effect on the day of bid opening, unless the City does not award the Contract within six months of the bid opening. SECTION 1-07.9(3) IS DELETED AND REPLACED WITH THE FOLLOWING: FOLLOWING: 1-07.9(3) Apprentices All contracts with an estimated construction cost greater than $1,000,000 (one million dollars) shall require that no less than 15 percent of the labor hours performed by workers subject to prevailing wages employed by the contractor or its subcontractors be performed by apprentices enrolled in a state-approved apprenticeship program. Definitions For the purposes of this specification, the following definitions apply: 1. Apprentice Utilization Requirement is expressed as a percentage of the project Labor Hours performed by Apprentices. 2. Labor Hours are the total hours performed by all workers receiving an hourly wage who are directly employed on the project site including hours performed by workers employed by the prime Contractor and all Subcontractors. Labor Hours do not include hours performed by foremen, superintendents, owners, and workers who are not subject to prevailing wage requirements. Kensington Drainage Improvements/Holcomb 1 - 19 February 14, 2022 Project Number: 18-3019 3. Apprentice is a person enrolled in a State-approved Apprenticeship Training Program. 4. State-approved Apprenticeship Training Program is an apprenticeship training program approved by the Washington State Apprenticeship Council. 5. Good Faith Effort is a demonstration that the Contractor has strived to meet the Apprenticeship Utilization Requirement including but not necessarily limited to the specific steps as described elsewhere in this specification. Plan The Contractor shall submit an Apprentice Utilization Plan within 30 calendar days of Notice of Award, demonstrating how they intend to achieve the Apprentice Utilization Requirement. The plan shall be updated and resubmitted as appropriate as the Work progresses. The intent is to provide the City with enough information to track progress in meeting the utilization requirements. Reporting The Contractor shall submit a Monthly Apprentice Reporting Form on a monthly basis. The report shall be submitted to the City by the last working day of the subsequent month, until the Physical Completion Date. The date reported shall be cumulative to date and consolidated to include the Contractor and all Subcontractors. At the Contractors request, the Engineer may suspend this reporting requirement during periods of minimal or no applicable work activities on the project. The Contractor shall submit documentation of their Good Faith Effort if: (1) they are unable to provide a plan demonstrating how they intend to meet the Apprentice Utilization Requirement; or (2) the project has been completed without meeting the Apprentice Utilization Requirement. Contacts The Contractor may obtain information on State-approved Apprenticeship Training Programs by contacting the Department of Labor and Industries at: Specialty Compliance Services Division, Apprenticeship Section, P.O. Box 44530, Olympia, WA 98504-4530 or by phone at (360) 902-5320. Compliance In the event that the Contractor is unable to accomplish the Apprentice Utilization Requirement, the Contractor shall demonstrate that a Good Faith Effort has been made as described within this specification. Failure to comply with the requirements as specified is subject to penalties for noncompliance as set forth in KCC 6.01.030(E). Good Faith Efforts In fulfilling the Good Faith Effort, the Contractor shall perform and, when appropriate, require its Subcontractors to perform the following steps: Kensington Drainage Improvements/Holcomb 1 - 20 February 14, 2022 Project Number: 18-3019 1. Solicit Apprentice(s) from State-approved Apprenticeship Training Program(s). 2. Document the solicitation and, in the event Apprentice(s) are not available, obtain supporting documentation from the solicited program(s). 3. Demonstrate that the plan was updated as required within this specification. 4. Provide documentation demonstrating what efforts the Contractor has taken to require Subcontractors to solicit and employ Apprentice(s). In the event that the preceding steps have been followed, the Contractor may also supplement the Good Faith Efforts documentation with the following documentation: 5. Submit documentation demonstrating successful Apprentice utilization on previous contracts. 6. Submit documentation indicating company-wide Apprentice utilization efforts and percentages of attainment. Payment Compensation for all costs involved with complying with the conditions of this specification is included in payment for the associated Contract items of work. 1-07.13 Contractor’s Responsibility for Work SECTION 1-07.13(4) IS REVISED BY DELETING THE SECOND SENTENCE OF THE FIRST PARAGRAPH AND DELETING THE LAST PARAGRAPH. 1-07.13(4) Repair of Damage SECTION 1-07.14 IS REVISED BY ADDING THE FOLLOWING TO THE BEGINNING OF THAT SECTION: 1-07.14 Responsibility for Damage To the extent a conflict exists between the terms of this Section 1-07.14 and Section 5 of the Contract, the terms of the Contract will control. Any reference to the State, Governor, Commission, Secretary, or all officers and employees of the State also will include the City, its officers and employees. 1-07.15 Temporary Water Pollution Prevention SECTION 1-07.15(1) IS REVISED BY ADDING THE FOLLOWING PARAGRAPH AFTER THE LAST PARAGRAPH: 1-07.15(1) Spill Prevention, Control, and Countermeasures Plan When the proposal form includes multiple bid schedules and the SPCC Plan bid item is present in only one bid schedule, the lump sum Kensington Drainage Improvements/Holcomb 1 - 21 February 14, 2022 Project Number: 18-3019 payment item for the SPCC Plan in that one schedule will apply to all bid schedules for all costs associated with creating and updating the accepted SPCC Plan, and all costs associated with the setup of prevention measures and for implementing the current SPCC Plan as required by this Specifications. SECTION 1-07.17 IS REVISED BY ADDING THE FOLLOWING SENTENCE TO THE END OF THE SECOND PARAGRAPH: 1-07.17 Utilities and Similar Facilities If a utility is known to have or suspected of having underground facilities within the area of the proposed excavation and that utility is not a subscriber to the utilities underground location center, the Contractor shall give individual notice to that utility within the same time frame prescribed in RCW 19.122.030 for subscriber utilities. SECTION 1-07.17 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTIONS: 1-07.17(3) Utility Markings Once underground utilities are marked by the utility owner or its agent, and/or once new underground facilities have been installed by the Contractor, the Contractor/excavator is responsible to determine the precise location of underground facilities that may conflict with other underground construction. The Contractor shall maintain the marks or a record of the location of buried facilities for the duration of time needed to avoid future damage until installation of all planned improvements at that location is complete. 1-07.17(4) Payment All costs to comply with subsection 1-07.17(3) and for the protection and repair of all identified or suspected underground utilities specified in RCW 19.122 are incidental to the contract and are the responsibility of the Contractor/excavator. The Contractor shall include all related costs in the unit bid prices of the contract. No additional time or monetary compensation shall be made for delays caused by utility re- marking or repair of damaged utilities due to the Contractors failure to maintain marks or to locate utilities in accordance with this section. 1-07.17(5) Notification of Excavation Within ten business days but not less than two business days prior to the commencement of excavation, the Contractor shall provide written notice (or other form of notice acceptable to the Engineer) to all owners of underground facilities, whether public or private, that excavation will occur, and when excavation will occur. 1-07.17(6) Site Inspection Kensington Drainage Improvements/Holcomb 1 - 22 February 14, 2022 Project Number: 18-3019 Contractor warrants and represents that it has personally, or through its employees, agents and/or subcontractors, examined all property affected by this project and that it is knowledgeable of specific locations for water, gas, telephone, electric power and combined sewerage utilities within those areas. The following list of contacts is provided only as a convenience to the Contractor. It may not be accurate and may not constitute a complete list of all affected utilities. Lumen/CenturyLink Jesse Patjens (425) 429-5722 Jesse.Patjens@lumen.com Comcast Danny Cooley (253) 686-7592 (cell) Danny_Cooley@comcast.com Puget Sound Energy Gas Glenn Helton 253-395-6926 425-559-4647 (cell) Glenn.Helton@pse.com Puget Sound Energy Power Hong Nguyen 425-449-6609 (cell) Hong.Nguyen@pse.com Verizon Scott Christenson 425-636-6046 425-471-1079 (cell) SECTION 1-07.18 IS REVISED BY ADDING THE FOLLOWING PARAGRAPH BEFORE THE FIRST PARAGRAPH: 1-07.18 Public Liability and Property Damage Insurance To the extent a conflict exists between the terms of this Section 1-07.18 and the insurance requirements in Section 7 of the Contract, the terms of the Contract will control. Any reference to the State, Governor, Commission, Secretary, or all officers and employees of the State also will include the City, its officers and employees. SECTION 1-07.23(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 1-07.23(1) Construction Under Traffic Driveways and private apartment parking and access shall remain open to traffic at all times. Contractor shall coordinate their work schedule with the property occupants to determine the best time to fully or partially close driveway/access to perform the work. The contractor is permitted to take two (2) parking stalls located in City Right of Way on Kensington Ave. for construction staging. These must be restored upon completion of the project including repaving and re- channelized. The contractor may post No Parking notice signs 72 hours in advance of closing the parking stalls. Kensington Drainage Improvements/Holcomb 1 - 23 February 14, 2022 Project Number: 18-3019 The Contractor shall request permission, in writing, a minimum of 2 weeks prior to any lane closures. The contractor shall place two PCMS message boards one week prior to start of the first lane closure and these shall remain in place no more than one week after the first lane closure. PCMS boards shall be field located with the approval of the Engineer, one being to the east of the project location and one to the west. There shall be no delay to medical, fire, police, or other emergency vehicles with flashing lights or sirens. The contractor shall alert all flaggers and personnel of this requirement. SECTION 1-07.24 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-07.24 Rights of Way Street right of way lines, limits of easements and limits of construction are indicated or defined on the plans. The Contractor's construction activities shall be confined within these limits, unless arrangements for use of private property are made. It is anticipated that the City will have obtained all right of way, easements or right of entry agreements prior to the start of construction. Locations where these rights have not been obtained will be brought to the Contractor's attention prior to start of construction. The Contractor shall not proceed with any portion of the work in areas where right of way, easements or rights of entry have not been acquired until the Engineer certifies to the Contractor that the right of way or easement is available or that the right of entry has been received. The ditch is located within right of way and easements which are shown on the plans. The contractor shall notify all three private property owners containing the ditch at least one week prior to the start of construction. Unless the contractor acquires permission from property owners via private agreements, the site must be accessed through the easement on Kensington Ave. S. or via public right of way on the east and west sides of E. Tacoma St. Any disturbed private property or right of way used to access the ditch shall be restored per the plans or as directed by the engineer. SECTION 1-07.26 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-07.26 Personal Liability of Public Officers Neither the City, the Engineer, nor any other official, officer or employee of the City shall be personally liable for any acts or failure to act in connection with the contract, it being understood that, in these matters, they are acting solely as agents of the City. Kensington Drainage Improvements/Holcomb 1 - 24 February 14, 2022 Project Number: 18-3019 1-08 PROSECUTION AND PROGRESS SECTION 1-08 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 1-08.0 Preconstruction and Preconstruction Conference The Engineer will furnish the Contractor with up to ten (10) copies of the plans and specifications. Additional documents may be purchased from the City at the price specified by the City or in the Invitation to Bid. Prior to undertaking each part of the work, the Contractor shall carefully study and compare the Contract and check and verify all pertinent figures shown and all applicable field measurements. The Contractor shall promptly report in writing to the Engineer any conflict, error or discrepancy that the Contractor discovers. After the Contract has been executed, but prior to the Contractor beginning the work, a preconstruction conference will be held with the Contractor, the Engineer and any other interested parties that the City determines to invite. The purpose of the preconstruction conference will be: 1. To review the initial progress schedule. 2. To establish a working understanding among the various parties associated or affected by the work. 3. To establish and review procedures for progress payment, notifications, approvals, submittals, etc. 4. To verify normal working hours for the work. 5. To review safety standards and traffic control. 6. To discuss any other related items that may be pertinent to the work. The Contractor shall prepare and submit for approval, at or prior to the preconstruction conference the following: 1. A price breakdown of all lump sum items. 2. A preliminary construction schedule. 3. A list of material sources for approval, if applicable. 4. Schedule of submittals. (See 1-06.6(2)) 5. Temporary Erosion/Sedimentation Control Plan (TESCP) for approval. 6. Traffic Control Plan (TCP) for approval. 7. Request to sublet, for approval by the Engineer, of all subcontractors. SECTION 1-08.4 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-08.4 Notice to Proceed, Prosecution and Hours of Work Notice to Proceed will be given after the contract has been executed and the contract bond and evidence of required insurance have been approved by and filed with the City. Unless otherwise approved in Kensington Drainage Improvements/Holcomb 1 - 25 February 14, 2022 Project Number: 18-3019 writing by the Engineer, the Contractor shall not commence the work until the Notice to Proceed has been given by the Engineer. The Contractor shall commence construction activities on the Project Site within ten working days of the Notice to Proceed Date. The Work thereafter shall be prosecuted diligently, vigorously, and without unauthorized interruption until physical completion of the work. Voluntary shutdown or slowing of operations by the Contractor shall not relieve the Contractor of the responsibility to complete the work within the time(s) specified in the Contract. Notice to proceed shall not be issued until July 11th, 2022. Except in the case of emergency or unless otherwise approved by the Engineer, the normal straight time working hours for the Contractor shall be any consecutive 8 hour period between 7:00 a.m. and 6:00 p.m. Monday through Friday, unless otherwise specified in the Kent Special Provisions, with a 5-day work week, plus allowing a maximum one-hour lunch break in each working day. The normal straight time 8-hour working period for the contract shall be established at the preconstruction conference or prior to the Contractor commencing work. If a Contractor desires to perform work on holidays, Saturdays, Sundays, or before 7:00 a.m. or after 6:00 p.m. on any day, the Contractor shall apply in writing to the Engineer for permission to work those times. The Contractor shall notify the Engineer at least 48 hours in advance (72 hours in advance for weekend work) so that the Inspector's time may be scheduled. Permission to work longer than an 8-hour period between 7:00 a.m. and 6:00 p.m. is not required. For any work outside of normal straight time working hours that requires city surveyors, all reasonable efforts shall be made by the Contractor to allow time for surveying to be completed during normal straight time hours. If city surveyors are required to work other than normal straight time hours at the convenience of the Contractor, all such work shall be reimbursed by the Contractor. Permission to work between the hours of 10:00 p.m. and 7:00 a.m. during weekdays and between the hours of 10:00 p.m. and 9:00 a.m. on weekends or holidays may also be subject to noise control requirements. Approval to continue work during these hours may be revoked at any time the Contractor exceeds the Citys noise control regulations or the city receives complaints from the public or adjoining property owners regarding noise from the Contractors operations. The Contractor shall have no claim for damages or delays should this permission be revoked for these reasons. The Engineer may grant permission to work Saturdays, Sundays, holidays or other than the agreed upon normal straight time working hours, but may be subject to other conditions established by the City or Engineer. These conditions may include, but are not limited to the following: hours worked by City employees; impacts to the construction Kensington Drainage Improvements/Holcomb 1 - 26 February 14, 2022 Project Number: 18-3019 schedule; or accommodations to adjoining properties affected by the contract work. 1-08.4(A) Reimbursement for Overtime Work of City Employees Following is a non-exclusive list of work that may require Contractor reimbursement for overtime of City employees. The City will bill the Contractor at the OVERTIME RATE in order for locate crews to complete other work. If the locate request is for nights, weekend, holidays or at other times when locate crews are not normally working, all locate work and expenses, including travel, minimum call out times, and/or Holiday premiums will be borne by the Contractor. 1. Locate work required to re-establish marks for City-owned underground facilities that were not maintained or recorded by the Contractor in accordance with RCW 19.122.030. 2. Work required by city survey crew(s) as the result of reestablishing survey stakes or markings that were not maintained or recorded by the Contractor or other work deemed to be for the convenience of the Contractor and not required of the City by the contract. 3. Work required by City personnel or independent testing laboratories to re-test project materials, utility pressure or vacuum tests, camera surveys or water purity tests as the result of initial test failure on the part of the Contractor. 1-08.4(B) General The City allocates its resources to a contract based on the total time allowed in the contract. The City will accept a progress schedule indicating an early physical completion date but cannot guarantee the City resources will be available to meet the accelerated schedule. No additional compensation will be allowed if the Contractor is not able to meet its accelerated schedule due to the unavailability of City resources or for other reasons beyond the City's control. Unless previously approved by the Engineer, the original and all supplemental progress schedules shall not conflict with any time and order-of-work requirements in the contract. If the Engineer deems that the original or any necessary supplemental progress schedule does not provide adequate information, the City may withhold progress payments until a schedule containing needed information has been submitted by the Contractor and approved by the Engineer. The Engineer's acceptance of any schedule shall not transfer any of the Contractor's responsibilities to the City. The Contractor alone shall remain responsible for adjusting forces, equipment, and work schedules to ensure completion of the work within the times specified in the contract. Kensington Drainage Improvements/Holcomb 1 - 27 February 14, 2022 Project Number: 18-3019 SECTION 1-08.5 IS REVISED BY DELETING THE THIRD PARAGRAPH AND REPLACING WITH THE FOLLOWING: 1-08.5 Time for Completion Contract time shall begin on the day of the Notice to Proceed. The Contract Provisions may specify another starting date for Contract time, in which case, time will begin on the starting date specified. SECTION 1-08.6 IS REVISED BY DELETING THE FIFTH, SIXTH, AND SEVENTH PARAGRAPHS AND REPLACING WITH THE FOLLOWING: 1-08.6 Suspension of Work If the performance of all or any part of the Work is suspended for an unreasonable period of time by an act of the Contracting Agency in the administration of the Contract, or by failure to act within the time specified in the Contract (or if no time is specified, within a reasonable time), the Engineer will make an adjustment for any increase in the cost or time for the performance of the Contract (excluding profit) necessarily caused by the suspension. However, no adjustment will be made for any suspension if (1) the performance would have been suspended by any other cause, including the fault or negligence of the Contractor, or (2) an equitable adjustment is provided for or excluded under any other provision of the Contract. If the Contactor believes that the performance of the Work is suspended for an unreasonable period of time and such suspension is the responsibility of the Contracting Agency, the Contractor shall immediately submit a written notice of protest to the Engineer as provided in Section 1-04.5. No adjustment shall be allowed for any costs incurred more than 10 calendar days before the date the Engineer receives the Contractors written notice to protest. In any event, no protest will be allowed later than the date of the Contractors signature on the Final Pay Estimate. The Contractor shall keep full and complete records of the costs and additional time of such suspension, and shall permit the Engineer to have access to those records and any other records as may be deemed necessary by the Engineer to assist in evaluating the protest. The Engineer will determine if an equitable adjustment in cost or time is due as provided in this Section. The equitable adjustment for increase in costs, if due, shall be subject to the limitations provided in Section 1-09.4, provided that no profit of any kind will be allowed on any increase in cost necessarily caused by the suspension. SECTION 1-08.7 MAINTENANCE DURING SUSPENSION IS REVISED BY DELETING THE FOURTH AND SIXTH PARAGRAPHS. SECTION 1-08.9 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-08.9 Notice to Proceed, Prosecution and Hours of Work Kensington Drainage Improvements/Holcomb 1 - 28 February 14, 2022 Project Number: 18-3019 Time is of the essence of the Contract. Delays inconvenience the traveling public, obstruct traffic, interfere with and delay commerce, and increase risk to Highway users. Delays also cost tax payers undue sums of money, adding time needed for administration, engineering, inspection, and supervision. Because the Contracting Agency finds it impractical to calculate the actual cost of delays, it has adopted the following formula to calculate liquidated damages for failure to complete the physical Work of a Contract on time. Accordingly, the Contractor agrees: 1. To pay (according to the following formula) liquidated damages for each working day beyond the number of working days established for Physical Completion, and 2. To authorize the Engineer to deduct these liquidated damages from any money due or coming due to the Contractor. Liquidated Damages Formula LD = 0.15*C / T Where: LD = liquidated damages per working day (rounded to the nearest dollar) C = original Contract amount T = original time for Physical Completion When the Contract Work has progressed to the extent that the Contracting Agency has full use and benefit of the facilities, both from the operational and safety standpoint, all the initial plantings are completed and only minor incidental Work, replacement of temporary substitute facilities, plant establishment periods, or correction or repair remains to physically complete the total Contract, the Engineer may determine the Contract Work is substantially complete. The Engineer will notify the Contractor in writing of the Substantial Completion Date. For overruns in Contract time occurring after the date so established, the formula for liquidated damages shown above will not apply. For overruns in Contract time occurring after the Substantial Completion Date, liquidated damages shall be assessed on the basis of direct engineering and related costs assignable to the project until the actual Physical Completion Date of all the Contract Work. The Contractor shall complete the remaining Work as promptly as possible. Upon request by the Engineer, the Contractor shall furnish a written schedule for completing the physical Work on the Contract. Liquidated damages will not be assessed for any days for which an extension of time is granted. No deduction or payment of liquidated damages will, in any degree, release the Contractor from further obligations and liabilities to complete the entire Contract. Kensington Drainage Improvements/Holcomb 1 - 29 February 14, 2022 Project Number: 18-3019 1-09 MEASUREMENT AND PAYMENT 1-09.9 Payments SECTION 1-09.9 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 1-09.9(2) City’s Right to Withhold Certain Amounts In addition to the amount that the City may otherwise retain under the Contract, the City may withhold a sufficient amount of any payments otherwise due to the Contractor, including nullifying the whole or part of any previous payment, because of subsequently discovered evidence or subsequent inspections that, in the City's judgment, may be necessary to cover the following: 1. The cost of defective work not remedied. 2. Fees incurred for material inspection, and overtime engineering and inspection for which the Contractor is obligated under this Contract. 3. Fees and charges of public authorities or municipalities. 4. Liquidated damages. 5. Engineering and inspection fees beyond Completion Date. 6. Cost of City personnel to re-establish locate marks for City-owned facilities that were not maintained by the Contractor in accordance with RCW 19.122.030 (3). 7. Additional inspection, testing and lab fees for re-doing failed, water, other utility tests. 1-09.11 Disputes and Claims SECTION 1-09.11(3) IS DELETED AND REPLACED WITH THE FOLLOWING: 1-09.11(3) Time Limitations and Jurisdiction This contract shall be construed and interpreted in accordance with the laws of the State of Washington. The venue of any claims or causes of action arising from this contract shall be exclusively in the Superior Court of King County, located in Kent, Washington. For convenience of the parties to this contract, it is mutually agreed that any claims or causes of action which the Contractor has against the City arising from this contract shall be brought within 180 days from the date of Final Acceptance of the contract by the City. The parties understand and agree that the Contractors failure to bring suit within the time period provided shall be a complete bar to any such claims or causes of action. It is further mutually agreed by the parties that when any claims or causes of action that a Contractor asserts against the City arising from this contract are filed with the City or initiated in court, the Contractor Kensington Drainage Improvements/Holcomb 1 - 30 February 14, 2022 Project Number: 18-3019 shall permit the City to have timely access to any records deemed necessary by the City to assist in evaluating the claims or actions. SECTION 1-09.13 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-09.13 Final Decision and Appeal All disputes arising under this contract shall proceed pursuant to Section 1-04.5 and 1-09.11 of the WSDOT Standard Specifications and any Kent Special Provisions provided for in the contract for claims and resolution of disputes. The provisions of these sections and the Kent Special Provisions must be complied with as a condition precedent to the Contractors right to seek an appeal of the Citys decision. The Citys decision under Section 1-09.11 will be final and conclusive. Thereafter, the exclusive means of Contractors right to appeal shall only be by filing suit exclusively under the venue, rules and jurisdiction of the Superior Court of King County, located in Kent, Washington, unless the parties agree in writing to an alternative dispute resolution process. 1-10 TEMPORARY TRAFFIC CONTROL 1-10.2 Traffic Control Management SECTION 1-10.2(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 1-10.2(1) General The TCS shall be certified as a work site traffic control supervisor by one of the following: Evergreen Safety Council 401 Pontius Avenue North Seattle, WA 98109 1-800-521-0778 or 206-382-4090 The Northwest Laborers-Employers Training Trust 27055 Ohio Avenue Kingston, WA 98346 360-297-3035 The American Traffic Safety Services Association 15 Riverside Parkway, Suite 100 Fredericksburg, VA 22406-1022 Training Dept. Toll Free (877) 642-4637 or (540) 368-1701 1-10.3 Traffic Control Labor, Procedures, and Devices 1-10.3(3) Traffic Control Devices SECTION 1-10.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 1-10.3(3)L Temporary Traffic Control Devices Kensington Drainage Improvements/Holcomb 1 - 31 February 14, 2022 Project Number: 18-3019 When the bid proposal includes an item for Temporary Traffic Control Devices, the work required for this item shall be furnishing barricades, flashers, cones, traffic safety drums, and other temporary traffic control devices, unless the contract provides for furnishing a specific temporary traffic control device under another item. The item Temporary Traffic Control Devices includes: 1. Initial delivery to the project site (or temporary storage) in good repair and in clean usable condition, 2. Repair or replacement when they are damaged and they are still needed on the project, and 3. Removal from the project site when they are no longer on the project. SECTION 1-10.5 IS DELETED AND REPLACED WITH THE FOLLOWING: 1-10.5 Payment Payment will be made in accordance with Section 1-04.1, for the following bid items when they are included in the Proposal: The unit contract price for Traffic Control Labor per hour shall be full pay for all costs for the labor provided for performing those construction operations described in Section 1-10.2(1)B, and Section 1-10.3(1) of the WSDOT Standard Specifications, and as authorized by the Engineer. The hours eligible for Traffic Control Labor shall be limited to the hours the worker is actually performing the work as documented by traffic control forms provided by the Contractors TCM, and verified by the City Inspectors records, and the Contractors Certified Payroll Records submitted to the City Inspector on a weekly basis. The unit contract price for Traffic Control Supervisor per hour shall be full pay for each hour a person performs the Traffic Control Supervisor duties described in Section 1-10.2(1)B of the WSDOT Standard Specifications. Payment for traffic control labor performed by the Traffic Control Supervisor will be paid under the item for Traffic Control Labor. The lump sum contract price for Temporary Traffic Control Devices shall be full pay for providing the work described in Section 1-10.3(3)L of the Kent Special Provisions. Progress payment for the lump sum item Temporary Traffic Control Devices will be made as follows: 1. When the initial temporary traffic control devices are set up, 50 percent of the amount bid for the item will be paid. 2. Payment for the remaining 50 percent of the amount bid for the item will be paid on a prorated basis in accordance with the total job progress as determined by progress payments. Kensington Drainage Improvements/Holcomb 1 - 32 February 14, 2022 Project Number: 18-3019 The unit contract price for Portable Changeable Message Sign (PCMS) per day shall be full pay for all costs for furnishing, transporting, initial installation within the project limits, maintaining and removing the PCMS, and associated work described in Section 1-10.3(3)C of the WSDOT Standard Specifications. Relocation of the PCMS within the project limits will be paid under the item Traffic Control Labor. Kensington Drainage Improvements/Holcomb 2 - 1 February 14, 2022 Project Number: 18-3019 DIVISION 2 – EARTHWORK 2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS SECTION 2-02.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 2-02.1 Description This work also includes the repair of adjacent improvements that were not designated for removal, but that were damaged by the Contractors operations. SECTION 2-02.3 IS REVISED BY REPLACING THE LAST THREE PARAGRAPHS WITH THE FOLLOWING: 2-02.3 Construction Requirements The City has identified the following materials that are marked for removal, but that will be salvaged as part of this project: 1. 2. The salvaged materials listed above shall be removed, hauled and stored at the following site(s): 1. 2. All improvements that are not designated for removal, but that are damaged by the Contractors operations shall be replaced, restored, or repaired at the Contractors sole expense. The Engineers determination regarding what replacement, restoration, or repair must be made by the Contractor to repair damage caused by the Contractors removal operations is final. SECTION 2-02.3(3) IS DELETED AND REPLACED WITH THE FOLLOWING: 2-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters In removing structures, pavement, sidewalks, and curbs the Contractor shall: 1. Haul broken-up pieces of concrete and asphalt pavement to some off-project site, unless otherwise directed by the Engineer, or permitted by the Kent Special Provisions. 2. Make a vertical saw cut between any existing pavement, sidewalk, or curb that is to remain and the portion to be removed. When asphalt pavements are being widened, the vertical saw cut shall be made at least 1-foot from the edge of the existing pavement, and at least 2-feet from the closest edge of any cement concrete curb that will remain or be replaced, unless otherwise directed by the Engineer. Kensington Drainage Improvements/Holcomb 2 - 2 February 14, 2022 Project Number: 18-3019 3. Replace at no expense to the City any existing pavement designated to remain that is damaged during the removal of other pavement, sidewalks, or curbs. 4. When cement concrete sidewalk, cement concrete pavement, or cement concrete curb is being removed, and the removal would result in a remaining strip of cement concrete less than 5 feet long, or where in the opinion of the Engineer the remaining portion of the sidewalk, pavement or curb would be damaged by the cutting required for the removal, then the entire sidewalk, pavement or curb shall be removed to the next expansion joint. SECTION 2-02.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 2-02.5 Payment Payment will be made in accordance with Section 1-04.1, for the following bid items when they are included in the Proposal: Remove and Dispose of Existing Wood Crossing Remove and Dispose of PVC Pipe Remove and Dispose of Grouted Rock Wall The lump sum unit contract price for the above items constitutes complete compensation for furnishing all labor, materials, tools, supplies, and equipment necessary for the removal, hauling offsite to an approved site of all wood crossings, PVC pipes, and grouted rock wall encountered during clearing and specified to be removed from the ditch on the plans. The force account unit contract price for Remove and Connect Unknown Drainage Pipes to Ditch items constitutes complete compensation for furnishing all labor, materials, tools, supplies, and equipment necessary to cut and tie in drainage pipes encountered during construction into the ditch as directed by the engineer. The unit contract price per square yard for Remove Existing Asphalt Concrete Pavement constitutes complete compensation for all labor, materials, tools, supplies and equipment required to remove existing asphalt from sidewalk for a depth of 3 inches, and from roads for a depth of 6 inches. Included in this price is the cost of hauling and disposal of the asphalt pavement. Should the Contractor encounter pavement to be removed which is thicker than 6 inches it shall be paid according to the following formula: actual depth in inches (square yards) x 6 inches = quantity For example, if the Contractor encounters pavement to be removed which is 8 inches thick and 100 square yards then the quantity would be: 8 100 SY x 6 = 133 S.Y. No other compensation shall be allowed. Kensington Drainage Improvements/Holcomb 2 - 3 February 14, 2022 Project Number: 18-3019 2-06 SUBGRADE PREPARATION SECTION 2-06.1 IS DELETED AND REPLACED WITH THE FOLLOWING: 2-06.1 Description This work consists of preparing the subgrade for the non-woven geotextile and placement of rock fill. SECTION 2-06.3(1) IS DELETED AND REPLACED WITH THE FOLLOWING: 2-06.3(1) Subgrade for Surfacing In preparing the subgrade for the rock fill the contractor shall review the geotechnical report attached in the appendix and shall: 1. Clear and strip all vegetation and organics from the improvement area identified on the plans. This is anticipated to require removal of 4 to 6 inches, however, greater stripping depths could be required to remove localized zones of loose or organic-rich soil. 2. Remove trees identified on the plans. During clearing and stripping, stumps and primary root systems of shrubs and trees should be completely removed from fill areas. a. Voids caused by removal of stumps and/or root systems shall be backfilled with structural fill (gravel borrow). b. If trees are removed from steep slopes for access purposes and approved by the Engineer, the root system can be left intact to allow for slope and erosion protection as new vegetation is being established. 3. Dispose of all debris as the Engineer directs. 4. Shape the entire Subgrade to a uniform surface running reasonably true to the line, grade, and cross-section as staked. The eroded channel shall be filled in to create a flat bottomed subgrade for the ditch. Fill shall be placed in maximum 12-inch- thick lifts and compacted to at least 95 percent of the theoretical maximum dry density (MDD) per ASTM International (ASTM) D 1557. a. The eroded channel shall be filled with gravel borrow as shown on the plans or native soil may be used when approved by the Engineer, provided it does not contain organics and can be adequately compacted. The on-site soils are extremely moisture sensitive and may not be used when wet or when placed over wet subgrade. All fill shall be proof-compacted to a firm and unyielding condition. b. The eroded channel shall be widened as needed to accommodate the size of compaction equipment prior to fill placement. 5. After the subgrade is established, a non-woven geotextile fabric for Soil Stabilization conforming to WSDOT 9-33 Table 3 shall be installed per the specifications in Section 2-12. Kensington Drainage Improvements/Holcomb 2 - 4 February 14, 2022 Project Number: 18-3019 SECTION 2-06.5 IS DELETED AND REPLACED WITH THE FOLLOWING: 2-06.5 Measurement and Payment Subgrade preparation is considered part of the construction Work. In this case, measurement and payment will conform to Section 2-03 and Section 8-15. 2-07 WATERING SECTION 2-07.4 IS DELETED AND REPLACED WITH THE FOLLOWING: 2-07.4 Measurement The Contractor shall obtain a hydrant meter and permit from the City Maintenance Shop located at 5821 South 240th Street 253-856-5600 to measure the quantities of water used. Hydrant wrenches are also available at the City Maintenance Shops at the Contractors option. No additional deposit is required for the hydrant wrench. The City shall provide all water that comes from the City water system. Prior to issuance of the hydrant meter (and wrench if applicable) and permit, the Contractor shall make a hydrant meter deposit to the City Customer Service Division located on the first floor of the Centennial Center at 400 West Gowe Street 253-856-5200. The said deposit is refundable provided the Contractor returns the hydrant meter (and wrench if applicable) to the City Maintenance Shops undamaged. The Contractor shall provide their own gate valve on the hose side of the hydrant meter with which to control water flow. The hydrant meter permit duration is two (2) months. At the end of the permit duration, the Contractor shall deliver the hydrant meter (and wrench if applicable) to the City Maintenance Shops for reading. If the Contractor requires another hydrant meter and permit at the time a meter is returned to the City Maintenance Shops, he shall request a meter and one shall be provided. An additional meter deposit will not be required. The Contractors initial hydrant meter deposit shall be transferred to the new meter issued. 2-12 CONSTRUCTION GEOSYNTHETIC SECTION 2-12.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 2-12.1 Description This work shall consist of furnishing and installing non-woven geotextile fabric at the locations shown on the plans and described in the specifications. SECTION 2-12.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 2-12.2 Materials Kensington Drainage Improvements/Holcomb 2 - 5 February 14, 2022 Project Number: 18-3019 Non-woven geotextile fabric for Soil Stabilization shall meet the material requirements of Section 9-33, Table 3 of the WSDOT Standard Specifications. SECTION 2-12.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 2-12.3 Construction Requirements The Contractor shall take all necessary precautions to not tear or damage the fabric during installation. The fabric shall be installed as described in 2-12.3(4) for Ditch Lining. This includes, but is not limited to, overlapping a minimum of 2 feet at all longitude and transverse joints or sewing joints SECTION 2-12.3(4) IS DELETED AND REPLACED WITH THE FOLLOWING: 2-12.3(4) Permanent Erosion Control and Ditch Lining Unless otherwise shown in the Plans, the geotextile shall either be overlapped a minimum of 2 feet at all longitudinal and transverse joints, or the geotextile joints shall be sewn together. If overlapped, the geotextile shall be placed so that the upstream strip of geotextile will overlap the next downstream strip. When placed on slopes, each strip shall overlap the next downhill strip. Placement of rock or other cover material on the geotextile shall start at the toe of the slope and proceed upwards. The geotextile shall be keyed at the top slope when indicated on the Plans. The geotextile shall be secured to the slope, but shall be secured loosely enough so that the geotextile will not tear when the riprap or other cover material is placed on the geotextile. The geotextile shall not be keyed where slope exceeds 3:1 until the riprap or other cover material is in place to the top of the slope. When geotextile ties into an existing slope steeper then 3:1, it shall not be keyed/anchored with the trench detail. All voids in the riprap or other cover material that allow the geotextile to be visible shall be backfilled with quarry spalls or other small stones, as designated by the Engineer, so that the geotextile is completely covered. When an aggregate cushion between the geotextile and the riprap or other cover material is required, it shall have a minimum thickness of 12 inches. Grading of slopes after placement of the riprap or other cover material will not be allowed if grading results in stone movement directly on the geotextile. Under no circumstances shall stones with a weight of more than 100 pounds be allowed to roll down slope. Stones shall not be dropped from a height greater than 3 feet above the geotextile surface if an aggregate cushion is present, or 1 foot if a cushion is not present. Lower drop heights may be required if geotextile damage from the stones is evident, as determined by the Engineer. If the geotextile is placed on slopes steeper than 2:1, the stones shall be placed on the Kensington Drainage Improvements/Holcomb 2 - 6 February 14, 2022 Project Number: 18-3019 slope without free-fall for moderate survivability, high survivability, and ditch lining geotextiles. SECTION 2-12.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 2-12.4 Measurement Non-woven geotextile fabric shall be measured per square yard of materials placed. SECTION 2-12.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 2-12.5 Payment The unit contract price per square yard for Non-woven Geotextile Fabric for Soil Stabilization constitutes complete compensation for all labor, materials, tools, supplies, and equipment necessary to furnish, install, and anchor the fabric at the locations shown on the plans and described in the specifications. Kensington Drainage Improvements/Holcomb 4 - 1 February 14, 2022 Project Number: 18-3019 DIVISION 4 – BASES DIVISION 4 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 4-03 GRAVEL BORROW 4-03.1 Description This work shall consist of constructing one or more layers of gravel borrow upon a prepared subgrade in accordance with these specifications and in conformity with the lines, grades, depths, and typical cross-section shown in the plans or as established by the Engineer. 4-03.2 Materials Materials shall meet the minimum requirements of the following section in the Kent Special Provisions: Gravel Borrow .......................... 9-03.14(1) 4-03.3 Construction Requirements Gravel borrow shall be uniformly spread upon the prepared subgrade to the depth, width, and cross-sections shown in the plans. Construction methods used shall meet the appropriate requirements of Section 4-04.3. 4-03.4 Measurement Gravel borrow will be measured in the same manner prescribed for the measurement of crushed surfacing materials as set forth in Section 4-04.4. 4-03.5 Payment Payment will be made in accordance with Section 1-04.1, for the following bid item when they are included in the Proposal: The unit contract price per ton for Gravel Borrow, Including Haul and Compaction constitutes complete compensation for furnishing all labor, materials, tools, supplies, and equipment necessary to haul, place, finish grade, and compact the gravel borrow as shown on the plans and described in the specifications. This item shall be used for roadway subbase, backfill for water, storm sewer, electrical conduit trenches, and other excavation backfill and compaction unless otherwise noted. 4-04 BALLAST AND CRUSHED SURFACING 4-04.3 Construction Requirements Kensington Drainage Improvements/Holcomb 4 - 2 February 14, 2022 Project Number: 18-3019 SECTION 4-04.3(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 4-04.3(2) Subgrade The Contractor is responsible for any delays or costs incurred as a result of placing ballast or surface materials before approval is received from the Engineer. SECTION 4-04.3(5) IS DELETED AND REPLACED WITH THE FOLLOWING: 4-04.3(5) Shaping and Compaction Surfacing shall be compacted in depths not to exceed 6 inches except top course shall not exceed 2 inches unless otherwise directed. Density shall be at least 95 percent of maximum density per ASTM D-1557 using a nuclear gauge. Compaction of each layer must be approved by the Engineer before the next succeeding layer of surfacing or pavement is placed thereon. SECTION 4-04.3(7) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 4-04.3(7) Miscellaneous Requirements The Contractor is solely responsible for any delays or additional costs incurred as a result of placing ballast or succeeding courses of surfacing materials before approval to proceed is received from the Engineer. SECTION 4-04.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 4-04.5 Payment The unit contract price per ton for Crushed Surfacing Top Course, 5/8 Inch Minus constitutes complete compensation for furnishing all labor, materials, tools, supplies, and equipment necessary to haul, place, finish grade, and compact the material as shown on the plans and described in the specifications. These items shall also be used for roadway or driveway remedial work or patching as requested by the Engineer. Quantities used for pipe zone bedding shall be measured and paid for under this bid item. Kensington Drainage Improvements/Holcomb 5 - 1 February 14, 2022 Project Number: 18-3019 DIVISION 5 – SURFACE TREATMENTS AND PAVEMENTS NOTE: If the contract also includes underground utility construction, permanent surface treatments and pavements shall not be placed until an as-built survey and testing of the new underground utilities have been completed. Verification that utility construction conforms to the line and grade requirements of Section 7-08.3(2)B of the WSDOT Standard Specifications shall be made by the Engineer prior to authorizing paving to begin. Also, each new utility must pass all appropriate tests specified herein for the type of utility prior to paving. 5-02 BITUMINOUS SURFACE TREATMENT SECTION 5-02.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 5-02.5 Payment Anti-stripping additive shall be included in the price of asphalt (grade) per ton. The quantity of asphalt material shall not be reduced by the quantity of anti-stripping additive. 5-04 HOT MIX ASPHALT SECTION 5-04 IS DELETED AND REPLACED IN ITS ENTIRETY WITH THE FOLLOWING: 5-04.1 Description This Work shall consist of providing and placing one or more layers of plant-mixed hot mix asphalt (HMA) on a prepared foundation or base in accordance with these Specifications and the lines, grades, thicknesses, and typical cross-sections shown inthePlans. The manufacture of HMA may include warm mix asphalt (WMA) processes in accordance with these Specifications. WMA processes include organic additives, chemical additives, and foaming. HMA shall be composed of asphalt binder and mineral materials as may berequired, mixed in the proportions specified to provide a homogeneous, stable, andworkablemixture. 5-04.2 Materials Materials shall meet the requirements of the following sections: Portland Cement 9-01 Asphalt Binder 9-02.1(4) Cationic Emulsified Asphalt 9-02.1(6) Anti-Stripping Additive 9-02.4 HMA Additive 9-02.5 Sand 9-03.1(2) (As noted in 5-04.3(5)C for crack sealing) Aggregates 9-03.8 Recycled Asphalt Pavement 9-03.8(3)B Kensington Drainage Improvements/Holcomb 5 - 2 February 14, 2022 Project Number: 18-3019 Mineral Filler 9-03.8(5) Recycled Material 9-03.21 Joint Sealant 9-04.2 Foam Backer Rod 9-04.2(3)A The Contract documents may establish that the various mineral materials required for the manufacture of HMA will be furnished in whole or in part by the Contracting Agency. If the documents do not establish the furnishing of any of these mineral materials by the Contracting Agency, the Contractor shall be required to furnish such materials in the amounts required for the designated mix. Mineral materials include coarse and fine aggregates, and mineral filler. The Contractor may choose to utilize recycled asphalt pavement (RAP) in the production of HMA. The RAP may be from pavements removed under the Contract, if any, or pavement material from an existing stockpile. The Contractor may use up to 20 percent RAP by total weight of HMA with no additional sampling or testing of the RAP. The RAP shall be sampled and tested at a frequency of one sample for every 1,000 tons produced and not less than ten samples per project. The asphalt content and gradation test data shall be reported to the Contracting Agency when submitting the mix design for approval on the QPL. The Contractor shall include the RAP as part of the mix design as defined in these Specifications. The grade of asphalt binder shall be as required by the Contract. Blending of asphalt binder from different sources is not permitted. The Contractor may only use warm mix asphalt (WMA) processes in the production of HMA with 20 percent or less RAP by total weight of HMA. The Contractor shall submit to the Engineer for approval the process that is proposed and how it will be used in the manufacture of HMA. Production of aggregates shall comply with the requirements of Section 3-01. Preparation of stockpile site, the stockpiling of aggregates, and the removal of aggregates from stockpiles shall comply with the requirements of Section 3-02. ESAL's The minimum number of ESAL's for the design and acceptance of the HMA in the contract shall be 11 million. 5-04.2(1) How to Get an HMA Mix Design on the QPL If the contractor wishes to submit a mix design for inclusion in the Qualified Products List (QPL), comply with each of the following: Develop the mix design in accordance with WSDOT SOP 732. Kensington Drainage Improvements/Holcomb 5 - 3 February 14, 2022 Project Number: 18-3019 Develop a mix design that complies with Sections 9-03.8(2) and 9- 03.8(6). Develop a mix design no more than 6 months prior to submitting it for QPL evaluation. Submit mix designs to the WSDOT State Materials Laboratory in Tumwater, including WSDOT Form 350-042. Include representative samples of the materials that are to be used in the HMA production as part of the mix design submittal. Identify the brand, type, and percentage of anti-stripping additive in the mix design submittal. Include with the mix design submittal a certification from the asphalt binder supplier that the anti-stripping additive is compatible with the crude source and the formulation of asphalt binder proposed for use in the mix design. Do not include warm mix asphalt (WMA) additives when developing a mix design or submitting a mix design for QPL evaluation. The use of warm mix asphalt (WMA) additives is not part of the process for obtaining approval for listing a mix design on the QPL. Refer to Section 5-04.2(2)B. The Contracting Agencys basis for approving, testing, and evaluating HMA mix designs for approval on the QPL is dependent on the contractual basis for acceptance of the HMA mixture, as shown in Table 1. Table 1 Basis for Contracting Agency Evaluation of HMA Mix Designs for Approval on the QPL Contractual Basis for Acceptance of HMA Mixture [see Section 5-04.3(9)] Basis for Contracting Agency Approval of Mix Design for Placement on QPL Contracting Agency Materials Testing for Evaluation of the Mix Design Statistical Evaluation WSDOT Standard Practice QC-8 The Contracting Agency will test the mix design materials for compliance with Sections 9-03.8(2) and 9-03.8(6). Visual Evaluation Review of Form 350-042 for compliance with Sections 9-03.8(2) and 9-03.8(6) The Contracting Agency may elect to test the mix design materials, or evaluate in accordance with WSDOT Standard Practice QC-8, at its sole discretion. If the Contracting Agency approves the mix design, it will be listed on the QPL for 12 consecutive months. The Contracting Agency may extend the 12 month listing provided the Contractor submits a certification letter to the Qualified Products Engineer verifying that the aggregate source and job mix formula (JMF) gradation, and asphalt binder crude source and formulation have not changed. The Contractor may submit the certification no sooner than three months prior to expiration of the initial 12 month mix design approval. Within 7 calendar days of receipt of the Contractors certification, the Kensington Drainage Improvements/Holcomb 5 - 4 February 14, 2022 Project Number: 18-3019 Contracting Agency will update the QPL. The maximum duration for approval of a mix design and listing on the QPL will be 24 months from the date of initial approval or as approved by the Engineer. 5-04.2(1)A Vacant 5-04.2(2) Mix Design – Obtaining Project Approval No paving shall begin prior to the approval of the mix design by the Engineer. Nonstatistical evaluation will be used for all HMA not designated as Commercial HMA in the contract documents. Commercial evaluation will be used for Commercial HMA and for other classes of HMA in the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, gores, prelevel, and pavement repair. Other nonstructural applications of HMA accepted by commercial evaluation shall be as approved by the Project Engineer. Sampling and testing of HMA accepted by commercial evaluation will be at the option of the Project Engineer. The Proposal quantity of HMA that is accepted by commercial evaluation will be excluded from the quantities used in the determination of nonstatistical evaluation. Nonstatistical Mix Design. Fifteen days prior to the first day of paving the contractor shall provide one of the following mix design verification certifications for Contracting Agency review; The WSDOT Mix Design Evaluation Report from the current WSDOT QPL, or one of the mix design verification certifications listed below. The proposed HMA mix design on WSDOT Form 350-042 with the seal and certification (stamp and signature) of a valid licensed Washington State Professional Engineer. The Mix Design Report for the proposed HMA mix design developed by a qualified City or County laboratory that is within one year of the approval date. The mix design shall be performed by a lab accredited by a national authority such as Laboratory Accreditation Bureau, L-A-B for Construction Materials Testing, The Construction Materials Engineering Council (CMECs) ISO 17025 or AASHTO Accreditation Program (AAP) and shall supply evidence of participation in the AASHTO: resource proficiency sample program. Mix designs for HMA accepted by Nonstatistical evaluation shall; Have the aggregate structure and asphalt binder content determined in accordance with WSDOT Standard Operating Procedure 732 and meet the requirements of Sections 9-03.8(2), except that Hamburg testing for ruts and stripping are at the discretion of the Engineer, and 9-03.8(6). Kensington Drainage Improvements/Holcomb 5 - 5 February 14, 2022 Project Number: 18-3019 Have anti-strip requirements, if any, for the proposed mix design determined in accordance with AASHTO T 283 or T 324, or based on historic anti-strip and aggregate source compatibility from previous WSDOT lab testing. At the discretion of the Engineer, agencies may accept verified mix designs older than 12 months from the original verification date with a certification from the Contractor that the materials and sources are the same as those shown on the original mix design. Commercial Evaluation Approval of a mix design for Commercial Evaluation will be based on a review of the Contractors submittal of WSDOT Form 350-042 (For commercial mixes, AASHTO T 324 evaluation is not required) or a Mix Design from the current WSDOT QPL or from one of the processes allowed by this section. Testing of the HMA by the Contracting Agency for mix design approval is not required. For the Bid Item Commercial HMA, the Contractor shall select a class of HMA and design level of Equivalent Single Axle Loads (ESALs) specified herein. 5-04.2(2)B Using Warm Mix Asphalt Processes The Contractor may elect to use additives that reduce the optimum mixing temperature or serve as a compaction aid for producing HMA. Additives include organic additives, chemical additives and foaming processes. The use of Additives is subject to the following: Do not use additives that reduce the mixing temperature more than allowed in Section 5-04.3(6) in the production of mixtures. Before using additives, obtain the Engineers approval using WSDOT Form 350-076 to describe the proposed additive and process. 5-04.3 Construction Requirements 5-04.3(1) Weather Limitations Do not place HMA for wearing course on any Traveled Way beginning October 1st through March 31st of the following year without written concurrence from the Engineer. Do not place HMA on any wet surface, or when the average surface temperatures are less than those specified below, or when weather conditions otherwise prevent the proper handling or finishing of the HMA. Minimum Surface Temperature for Paving Compacted Thickness (Feet) Wearing Course Other Courses Less than 0.10 55 F 45 F 0.10 to 0.20 45 F 35 F More than 0.20 35 F 35 F Kensington Drainage Improvements/Holcomb 5 - 6 February 14, 2022 Project Number: 18-3019 5-04.3(2) Paving Under Traffic When the Roadway being paved is open to traffic, the requirements of this Section shallapply. The Contractor shall keep intersections open to traffic at all times except when paving the intersection or paving across the intersection. During such time, and provided that there has been an advance warning to the public, the intersection may be closed for the minimum time required to place and compact the mixture. In hot weather, the Engineer may require the application of water to the pavement to accelerate the finish rolling of the pavement and to shorten the time required before reopening to traffic. Before closing an intersection, advance warning signs shall be placed and signs shall also be placed marking the detour or alternate route. During paving operations, temporary pavement markings shall be maintained throughout the project. Temporary pavement markings shall be installed on the Roadway prior to opening to traffic. Temporary pavement markings shall be in accordance with Section 8-23. All costs in connection with performing the Work in accordance with these requirements, except the cost of temporary pavement markings, shall be included in the unit Contract prices for the various Bid items involved in the Contract. 5-04.3(3) Equipment 5-04.3(3)A Mixing Plant Plants used for the preparation of HMA shall conform to the following requirements: 1. Equipment for Preparation of Asphalt Binder Tanks for the storage of asphalt binder shall be equipped to heat and hold the material at the required temperatures. The heating shall be accomplished by steam coils, electricity, or other approved means so that no flame shall be in contact with the storage tank. The circulating system for the asphalt binder shall be designed to ensure proper and continuous circulation during the operating period. A valve for the purpose of sampling the asphalt binder shall be placed in either the storage tank or in the supply line to the mixer. 2. Thermometric Equipment An armored thermometer, capable of detecting temperature ranges expected in the HMA mix, shall be fixed in the asphalt binder feed line at a location near the charging valve at the mixer unit. The thermometer location shall be convenient and safe for access by Inspectors. The plant shall also be equipped with an approved dial-scale thermometer, a mercury actuated thermometer, an electric pyrometer, or another approved thermometric instrument placed at the discharge chute of the drier Kensington Drainage Improvements/Holcomb 5 - 7 February 14, 2022 Project Number: 18-3019 to automatically register or indicate the temperature of the heated aggregates. Thisdevice shall be in full view of the plant operator. 3. Heating of Asphalt Binder The temperature of the asphalt binder shall not exceed the maximum recommended by the asphalt binder manufacturer nor shall it be below the minimum temperature required to maintain the asphalt binder in a homogeneous state. The asphalt binder shall be heated in a manner that will avoid local variations in heating. The heating method shall provide a continuous supply of asphalt binder to the mixer at a uniform average temperature with no individual variations exceeding 25°F. Also, when a WMA additive is included in the asphalt binder, the temperature of the asphalt binder shall not exceed the maximum recommended by the manufacturer of the WMA additive. 4. Sampling and Testing of Mineral Materials The HMA plant shall be equipped with a mechanical sampler for the sampling of the mineral materials. The mechanical sampler shall meet the requirements of Section 1-05.6 for the crushing and screening operation. The Contractor shall provide for the setup and operation of the field testing facilities of the Contracting Agency as provided for in Section 3-01.2(2). 5. Sampling HMA The HMA plant shall provide for sampling HMA by one of the following methods: a. A mechanical sampling device attached to the HMA plant. b. Platforms or devices to enable sampling from the hauling vehicle without entering the hauling vehicle. 5-04.3(3)B Hauling Equipment Trucks used for hauling HMA shall have tight, clean, smooth metal beds and shall have a cover of canvas or other suitable material of sufficient size to protect the mixture from adverse weather. Whenever the weather conditions during the work shift include, or are forecast to include, precipitation or an air temperature less than 45°F or when time from loading to unloading exceeds 30 minutes, the cover shall be securely attached to protect the HMA. The Contractor shall provide an environmentally benign means to prevent the HMA mixture from adhering to the hauling equipment. Excess release agent shall be drained prior to filling hauling equipment with HMA. Petroleum derivatives or other coating material that contaminate or alter the characteristics of the HMA shall not be used. For live bed trucks, the conveyer shall be in operation during the process of applying the release agent. 5-04.3(3)C Pavers HMA pavers shall be self-contained, power-propelled units, provided with aninternally heated vibratory screed and shall be capable of spreading and finishing courses of HMA plant mix material in lane widths required by the paving section shown inthePlans. Kensington Drainage Improvements/Holcomb 5 - 8 February 14, 2022 Project Number: 18-3019 The HMA paver shall be in good condition and shall have the most current equipment available from the manufacturer for the prevention of segregation of the HMA mixture installed, in good condition, and in working order. The equipment certification shall list the make, model, and year of the paver and any equipment that has been retrofitted. The screed shall be operated in accordance with the manufacturers recommendations and shall effectively produce a finished surface of the required evenness and texture without tearing, shoving, segregating, or gouging the mixture. A copy of the manufacturers recommendations shall be provided upon request by the Contracting Agency. Extensions will be allowed provided they produce the same results, including ride, density, and surface texture as obtained by the primary screed. Extensions without augers and an internally heated vibratory screed shall not be used in the TraveledWay. When specified in the Contract, reference lines for vertical control will be required. Lines shall be placed on both outer edges of the Traveled Way of each Roadway. Horizontal control utilizing the reference line will be permitted. The grade and slope for intermediate lanes shall be controlled automatically from reference lines or by means of a mat referencing device and a slope control device. When the finish of the grade prepared for paving is superior to the established tolerances and when, in the opinion of the Engineer, further improvement to the line, grade, cross-section, and smoothness can best be achieved without the use of the reference line, a mat referencing device may be substituted for the reference line. Substitution of the device will be subject to the continued approval of the Engineer. A joint matcher may be used subject to the approval of the Engineer. The reference line may be removed after the completion of the first course of HMA when approved by the Engineer. Whenever the Engineer determines that any of these methods are failing to provide the necessary vertical control, the reference lines will be reinstalled by the Contractor. The Contractor shall furnish and install all pins, brackets, tensioning devices, wire, and accessories necessary for satisfactory operation of the automatic control equipment. If the paving machine in use is not providing the required finish, the Engineer may suspend Work as allowed by Section 1-08.6. Any cleaning or solvent type liquids spilled on the pavement shall be thoroughly removed before paving proceeds. 5-04.3(3)D Material Transfer Device or Material Transfer Vehicle The use of a material transfer device or material transfer vehicle (MTD/V) is not required on this project. The MTD/V may mix the HMA after delivery by the hauling equipment and prior to laydown by the paving machine. Mixing of the HMA shall be sufficient to obtain a uniform temperature throughout the mixture. If a windrow elevator is used, the length of the windrow may be limited in urban areas or through intersections, at the discretion of the Engineer. Kensington Drainage Improvements/Holcomb 5 - 9 February 14, 2022 Project Number: 18-3019 To be approved for use, an MTV: 1. Shall be self-propelled vehicle, separate from the hauling vehicle or paver. 2. Shall not be connected to the hauling vehicle or paver. 3. May accept HMA directly from the haul vehicle or pick up HMA from a windrow. 4. Shall mix the HMA after delivery by the hauling equipment and prior to placement into the paving machine. 5. Shall mix the HMA sufficiently to obtain a uniform temperature throughout the mixture. To be approved for use, an MTD: 1. Shall be positively connected to the paver. 2. May accept HMA directly from the haul vehicle or pick up HMA from a windrow. 3. Shall mix the HMA after delivery by the hauling equipment and prior to placement into the paving machine. 4. Shall mix the HMA sufficiently to obtain a uniform temperature throughout the mixture. 5-04.3(3)E Rollers Rollers shall be of the steel wheel, vibratory, oscillatory, or pneumatic tire type, in good condition and capable of reversing without backlash. Operation of the roller shall be in accordance with the manufacturers recommendations. When ordered by the Engineer for any roller planned for use on the project, the Contractor shall provide a copy of the manufacturers recommendation for the use of that roller for compaction of HMA. The number and weight of rollers shall be sufficient to compact the mixture in compliance with the requirements of Section 5-04.3(10). The use of equipment that results in crushing of the aggregate will not be permitted. Rollers producing pickup, washboard, uneven compaction of the surface, displacement of the mixture or other undesirable results shall not be used. 5-04.3(4) Preparation of Existing Paved Surfaces When the surface of the existing pavement or old base is irregular, the Contractor shall bring it to a uniform grade and cross-section as shown on the Plans or approved by the Engineer. Preleveling of uneven or broken surfaces over which HMA is to be placed may be accomplished by using an asphalt paver, a motor patrol grader, or by hand raking, as approved by the Engineer. Compaction of preleveling HMA shall be to the satisfaction of the Engineer and may require the use of small steel wheel rollers, plate compactors, or pneumatic rollers to avoid bridging across preleveled areas by the compaction equipment. Equipment used for the compaction of preleveling HMA shall be approved by the Engineer. Kensington Drainage Improvements/Holcomb 5 - 10 February 14, 2022 Project Number: 18-3019 Before construction of HMA on an existing paved surface, the entire surface of the pavement shall be clean. All fatty asphalt patches, grease drippings, and other objectionable matter shall be entirely removed from the existing pavement. All pavements or bituminous surfaces shall be thoroughly cleaned of dust, soil, pavement grindings, and other foreign matter. All holes and small depressions shall be filled with an appropriate class of HMA. The surface of the patched area shall be leveled and compacted thoroughly. Prior to the application of tack coat, or paving, the condition of the surface shall be approved by the Engineer. A tack coat of asphalt shall be applied to all paved surfaces on which any course of HMA is to be placed or abutted; except that tack coat may be omitted from clean, newly paved surfaces at the discretion of the Engineer. Tack coat shall be uniformly applied to cover the existing pavement with a thin film of residual asphalt free of streaks and bare spots at a rate between 0.02 and 0.10 gallons per square yard of retained asphalt. The rate of application shall be approved by the Engineer. A heavy application of tack coat shall be applied to all joints. For Roadways open to traffic, the application of tack coat shall be limited to surfaces that will be paved during the same working shift. The spreading equipment shall be equipped with a thermometer to indicate the temperature of the tack coat material. Equipment shall not operate on tacked surfaces until the tack has broken and cured. If the Contractors operation damages the tack coat it shall be repaired prior to placement of the HMA. The tack coat shall be CSS-1, or CSS-1h emulsified asphalt. The CSS-1 and CSS-1h emulsified asphalt may be diluted once with water at a rate not to exceed one part water to one part emulsified asphalt. The tack coat shall have sufficient temperature such that it may be applied uniformly at the specified rate of application and shall not exceed the maximum temperature recommended by the emulsified asphalt manufacturer. 5-04.3(4)A Crack Sealing 5-04.3(4)A1 General When the Proposal includes a pay item for crack sealing, seal all cracks ¼ inch in width and greater. Cleaning: Ensure that cracks are thoroughly clean, dry and free of all loose and foreign material when filling with crack sealant material. Use a hot compressed air lance to dry and warm the pavement surfaces within the crack immediately prior to filling a crack with the sealant material. Do not overheat pavement. Do not use direct flame dryers. Routing cracks is not required. Sand Slurry: For cracks that are to be filled with sand slurry, thoroughly mix the components and pour the mixture into the cracks until full. Add additional CSS-1 cationic emulsified asphalt to the sand Kensington Drainage Improvements/Holcomb 5 - 11 February 14, 2022 Project Number: 18-3019 slurry as needed for workability to ensure the mixture will completely fill the cracks. Strike off the sand slurry flush with the existing pavement surface and allow the mixture to cure. Top off cracks that were not completely filled with additional sand slurry. Do not place the HMA overlay until the slurry has fully cured. The sand slurry shall consist of approximately 20 percent CSS-1 emulsified asphalt, approximately 2 percent portland cement, water (if required), and the remainder clean Class 1 or 2 fine aggregate per Section 9-03.1(2). The components shall be thoroughly mixed and then poured into the cracks and joints until full. The following day, any cracks or joints that are not completely filled shall be topped off with additional sand slurry. After the sand slurry is placed, the filler shall be struck off flush with the existing pavement surface and allowed to cure. The HMA overlay shall not be placed until the slurry has fully cured. The requirements of Section 1-06 will not apply to the portland cement and sand used in the sand slurry. In areas where HMA will be placed, use sand slurry to fill the cracks. In areas where HMA will not be placed, fill the cracks as follows: 1. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant. 2.Cracks greater than 1 inch in width fill with sand slurry. Hot Poured Sealant: For cracks that are to be filled with hot poured sealant, apply the material in accordance with these requirements and the manufacturers recommendations. Furnish a Type 1 Working Drawing of the manufacturers product information and recommendations to the Engineer prior to the start of work, including the manufacturers recommended heating time and temperatures, allowable storage time and temperatures after initial heating, allowable reheating criteria, and application temperature range. Confine hot poured sealant material within the crack. Clean any overflow of sealant from the pavement surface. If, in the opinion of the Engineer, the Contractors method of sealing the cracks with hot poured sealant results in an excessive amount of material on the pavement surface, stop and correct the operation to eliminate the excess material. 5-04.3(4)A2 Crack Sealing Areas Prior to Paving In areas where HMA will be placed, use sand slurry to fill the cracks. 5-04.3(4)A3 Crack Sealing Areas Not to be Paved In areas where HMA will not be placed, fill the cracks as follows: a. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant. b. Cracks greater than 1 inch in width fill with sand slurry. 5-04.3(4)B Vacant 5-04.3(4)C Pavement Repair Kensington Drainage Improvements/Holcomb 5 - 12 February 14, 2022 Project Number: 18-3019 The Contractor shall excavate pavement repair areas and shall backfill these with HMA in accordance with the details shown in the Plans and as marked in the field. The Contractor shall conduct the excavation operations in a manner that will protect the pavement that is to remain. Pavement not designated to be removed that is damaged as a result of the Contractors operations shall be repaired by the Contractor to the satisfaction of the Engineer at no cost to the Contracting Agency. The Contractor shall excavate only within one lane at a time unless approved otherwise by the Engineer. The Contractor shall not excavate more area than can be completely finished during the same shift, unless approved by the Engineer. Unless otherwise shown in the Plans or determined by the Engineer, excavate to a depth of 1.0 feet. The Engineer will make the final determination of the excavation depth required. The minimum width of any pavement repair area shall be 40 inches unless shown otherwise in the Plans. Before any excavation, the existing pavement shall be sawcut or shall be removed by a pavement grinder. Excavated materials will become the property of the Contractor and shall be disposed of in a Contractor-provided site off the Right of Way or used in accordance with Sections 2-02.3(3) or 9-03.21. Asphalt for tack coat shall be required as specified in Section 5-04.3(4). A heavy application of tack coat shall be applied to all surfaces of existing pavement in the pavement repair area. Placement of the HMA backfill shall be accomplished in lifts not to exceed 0.35-foot compacted depth. Lifts that exceed 0.35-foot of compacted depth may be accomplished with the approval of the Engineer. Each lift shall be thoroughly compacted by a mechanical tamper or a roller. 5-04.3(5) Producing/Stockpiling Aggregates and RAP Aggregates and RAP shall be stockpiled according to the requirements of Section 3-02. Sufficient storage space shall be provided for each size of aggregate and RAP. Materials shall be removed from stockpile(s) in a manner to ensure minimal segregation when being moved to the HMA plant for processing into the final mixture. Different aggregate sizes shall be kept separated until they have been delivered to the HMA plant. 5-04.3(5)A Vacant 5-04.3(6) Mixing After the required amount of mineral materials, asphalt binder, recycling agent and anti-stripping additives have been introduced into the mixer the HMA shall be mixed until complete and uniform coating of the particles and thorough distribution of the asphalt binder throughout the mineral materials is ensured. Kensington Drainage Improvements/Holcomb 5 - 13 February 14, 2022 Project Number: 18-3019 When discharged, the temperature of the HMA shall not exceed the optimum mixing temperature by more than 25°F as shown on the reference mix design report or as approved by the Engineer. Also, when a WMA additive is included in the manufacture of HMA, the discharge temperature of the HMA shall not exceed the maximum recommended by the manufacturer of the WMA additive. A maximum water content of 2 percent in the mix, at discharge, will be allowed providing the water causes no problems with handling, stripping, or flushing. If the water in the HMA causes any of these problems, the moisture content shall be reduced as directed by the Engineer. Storing or holding of the HMA in approved storage facilities will be permitted with approval of the Engineer, but in no event shall the HMA be held for more than 24 hours. HMA held for more than 24 hours after mixing shall be rejected. Rejected HMA shall be disposed of by the Contractor at no expense to the Contracting Agency. The storage facility shall have an accessible device located at the top of the cone or about the third point. The device shall indicate the amount of material in storage. No HMA shall be accepted from the storage facility when the HMA in storage is below the top of the cone of the storage facility, except as the storage facility is being emptied at the end of the workingshift. Recycled asphalt pavement (RAP) utilized in the production of HMA shall be sized prior to entering the mixer so that a uniform and thoroughly mixed HMA is produced. If there is evidence of the recycled asphalt pavement not breaking down during the heating and mixing of the HMA, the Contractor shall immediately suspend the use of the RAP until changes have been approved by the Engineer. After the required amount of mineral materials, RAP, new asphalt binder and asphalt rejuvenator have been introduced into the mixer the HMA shall be mixed until complete and uniform coating of the particles and thorough distribution of the asphalt binder throughout the mineral materials, and RAP is ensured. 5-04.3(7) Spreading and Finishing The mixture shall be laid upon an approved surface, spread, and struck off to the grade and elevation established. HMA pavers complying with Section 5-04.3(3) shall be used to distribute the mixture. Unless otherwise directed by the Engineer, the nominal compacted depth of any layer of any course shall not exceed the following: HMA Class 1 wearing course/final lift 0.17 feet other courses 0.35 feet HMA Class ¾ and HMA Class ½ wearing course/final lift 0.17 feet other courses 0.25 feet HMA Class 0.17 feet Kensington Drainage Improvements/Holcomb 5 - 14 February 14, 2022 Project Number: 18-3019 On areas where irregularities or unavoidable obstacles make the use of mechanical spreading and finishing equipment impractical, the paving may be done with other equipment or by hand. When more than one JMF is being utilized to produce HMA, the material produced for each JMF shall be placed by separate spreading and compacting equipment. The intermingling of HMA produced from more than one JMF is prohibited. Each strip of HMA placed during a work shift shall conform to a single JMF established for the class of HMA specified unless there is a need to make an adjustment in the JMF. Reference Section 8-20.3(14)C of the Kent Special Provisions for the placement of traffic signal detection loops. 5-04.3(8) Aggregate Acceptance Prior to Incorporation in HMA For HMA accepted by nonstatistical evaluation the aggregate properties of sand equivalent, uncompacted void content and fracture will be evaluated in accordance with Section 3-04. Sampling and testing of aggregates for HMA accepted by commercial evaluation will be at the option of the Engineer. 5-04.3(9) HMA Mixture Acceptance Acceptance of HMA shall be as provided under nonstatistical, or commercial evaluation. Nonstatistical evaluation will be used for the acceptance of HMA unless Commercial Evaluation is specified. Commercial evaluation will be used for Commercial HMA and for other classes of HMA in the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, gores, prelevel, temporary pavement, and pavement repair. Other nonstructural applications of HMA accepted by commercial evaluation shall be as approved by the Engineer. Sampling and testing of HMA accepted by commercial evaluation will be at the option of the Engineer. The mix design will be the initial JMF for the class of HMA. The Contractor may request a change in the JMF. Any adjustments to the JMF will require the approval of the Engineer and may be made in accordance with this section. HMA Tolerances and Adjustments 1. Job Mix Formula Tolerances The constituents of the mixture at the time of acceptance shall be within tolerance. The tolerance limits will be established as follows: For Asphalt Binder and Air Voids (Va), the acceptance limits are determined by adding the tolerances below to the approved JMF values. These values will also be the Upper Specification Limit (USL) and Lower Specification Limit (LSL) required in Section 1-06.2(2)D2 Kensington Drainage Improvements/Holcomb 5 - 15 February 14, 2022 Project Number: 18-3019 Property Non-Statistical Evaluation Commercial Evaluation Asphalt Binder +/- 0.5% +/- 0.7% Air Voids, Va 2.5% min. and 5.5% max N/A For Aggregates in the mixture: a. First, determine preliminary upper and lower acceptance limits by applying the following tolerances to the approved JMF. Aggregate Percent Passing Non-Statistical Evaluation Commercial Evaluation 1, ¾, ½, and 3/8 sieves +/- 6% +/- 8% No. 4 sieve +/-6% +/- 8% No. 8 Sieve +/- 6% +/-8% No. 200 sieve +/- 2.0% +/- 3.0% b. Second, adjust the preliminary upper and lower acceptance limits determined from step (a) the minimum amount necessary so that none of the aggregate properties are outside the control points in Section 9-03.8(6). The resulting values will be the upper and lower acceptance limits for aggregates, as well as the USL and LSL required in Section 1-06.2(2)D2. 2. Job Mix Formula Adjustments An adjustment to the aggregate gradation or asphalt binder content of the JMF requires approval of the Engineer. Adjustments to the JMF will only be considered if the change produces material of equal or better quality and may require the development of a new mix design if the adjustment exceeds the amounts listed below. a. Aggregates 2 percent for the aggregate passing the 1½, 1 , ¾, ½, , and the No. 4 sieves, 1 percent for aggregate passing the No. 8 sieve, and 0.5 percent for the aggregate passing the No. 200 sieve. The adjusted JMF shall be within the range of the control points in Section 9-03.8(6). b. Asphalt Binder Content The Engineer may order or approve changes to asphalt binder content. The maximum adjustment from the approved mix design for the asphalt binder content shall be 0.3 percent 5-04.3(9)A Vacant 5-04.3(9)B Vacant 5-04.3(9)C Mixture Acceptance – Nonstatistical Evaluation HMA mixture which is accepted by Nonstatistical Evaluation will be evaluated by the Contracting Agency by dividing the HMA tonnage into lots. Kensington Drainage Improvements/Holcomb 5 - 16 February 14, 2022 Project Number: 18-3019 5-04.3(9)C1 Mixture Nonstatistical Evaluation – Lots and Sublots A lot is represented by randomly selected samples of the same mix design that will be tested for acceptance. A lot is defined as the total quantity of material or work produced for each Job Mix Formula placed. Only one lot per JMF is expected. A sublot shall be equal to one days production or 800 tons, whichever is less except that the final sublot will be a minimum of 400 tons and may be increased to 1200 tons. All of the test results obtained from the acceptance samples from a given lot shall be evaluated collectively. If the Contractor requests a change to the JMF that is approved, the material produced after the change will be evaluated on the basis of the new JMF for the remaining sublots in the current lot and for acceptance of subsequent lots. For a lot in progress with a CPF less than 0.75, a new lot will begin at the Contractors request after the Engineer is satisfied that material conforming to the Specifications can be produced. Sampling and testing for evaluation shall be performed on the frequency of one sample per sublot. 5-04.3(9)C2 Mixture Nonstatistical Evaluation Sampling Samples for acceptance testing shall be obtained by the Contractor when ordered by the Engineer. The Contractor shall sample the HMA mixture in the presence of the Engineer and in accordance with AASHTO T 168. A minimum of three samples should be taken for each class of HMA placed on a project. If used in a structural application, at least one of the three samples shall to be tested. Sampling and testing HMA in a Structural application where quantities are less than 400 tons is at the discretion of the Engineer. For HMA used in a structural application and with a total project quantity less than 800 tons but more than 400 tons, a minimum of one acceptance test shall be performed. In all cases, a minimum of 3 samples will be obtained at the point of acceptance, a minimum of one of the three samples will be tested for conformance to the JMF: If the test results are found to be within specification requirements, additional testing will be at the Engineers discretion. If test results are found not to be within specification requirements, additional testing of the remaining samples to determine a Composite Pay Factor (CPF) shall be performed. 5-04.3(9)C3 Mixture Nonstatistical Evaluation – Acceptance Testing Testing of HMA for compliance of Va will be at the option of the Contracting Agency. If tested, compliance of Va will use WSDOT SOP 731. Kensington Drainage Improvements/Holcomb 5 - 17 February 14, 2022 Project Number: 18-3019 Testing for compliance of asphalt binder content will be by WSDOT FOP for AASHTO T 308. Testing for compliance of gradation will be by FOP for WAQTC T 27/T 11. 5-04.3(9)C4 Mixture Nonstatistical Evaluation – Pay Factors For each lot of material falling outside the tolerance limits in 5-04.3(9), the Contracting Agency will determine a Composite Pay Factor (CPF) using the following price adjustment factors: Table of Price Adjustment Factors Constituent Factor “f” All aggregate passing: 1½, 1 , ¾, ½, and No.4 sieves 2 All aggregate passing No. 8 sieve 15 All aggregate passing No. 200 sieve 20 Asphalt binder 40 Air Voids (Va) (where applicable) 20 Each lot of HMA produced under Nonstatistical Evaluation and having all constituents falling within the tolerance limits of the job mix formula shall be accepted at the unit Contract price with no further evaluation. When one or more constituents fall outside the nonstatistical tolerance limits in the Job Mix Formula shown in Table of Price Adjustment Factors, the lot shall be evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The nonstatistical tolerance limits will be used in the calculation of the CPF and the maximum CPF shall be 1.00. When less than three sublots exist, backup samples of the existing sublots or samples from the Roadway shall be tested to provide a minimum of three sets of results for evaluation. 5-04.3(9)C5 Vacant 5-04.3(9)C6 Mixture Nonstatistical Evaluation – Price Adjustments For each lot of HMA mix produced under Nonstatistical Evaluation when the calculated CPF is less than 1.00, a Nonconforming Mix Factor (NCMF) will be determined. The NCMF equals the algebraic difference of CPF minus 1.00 multiplied by 60 percent. The total job mix compliance price adjustment will be calculated as the product of the NCMF, the quantity of HMA in the lot in tons, and the unit Contract price per ton of mix. If a constituent is not measured in accordance with these Specifications, itsindividual pay factor will be considered 1.00 in calculating the Composite PayFactor(CPF). Kensington Drainage Improvements/Holcomb 5 - 18 February 14, 2022 Project Number: 18-3019 5-04.3(9)C7 Mixture Nonstatistical Evaluation - Retests The Contractor may request a sublot be retested. To request a retest, the Contractor shall submit a written request within 7 calendar days after the specific test results have been received. A split of the original acceptance sample will be retested. The split of the sample will not be tested with the same tester that ran the original acceptance test. The sample will be tested for a complete gradation analysis, asphalt binder content, and, at the option of the agency, Va. The results of the retest will be used for the acceptance of the HMA in place of the original sublot sample test results. The cost of testing will be deducted from any monies due or that may come due the Contractor under the Contract at the rate of $500 per sample. 5-04.3 (9)D Mixture Acceptance – Commercial Evaluation If sampled and tested, HMA produced under Commercial Evaluation and having all constituents falling within the tolerance limits of the job mix formula shall be accepted at the unit Contract price with no further evaluation. When one or more constituents fall outside the commercial tolerance limits in the Job Mix Formula shown in 5-04.3(9), the lot shall be evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The commercial tolerance limits will be used in the calculation of the CPF and the maximum CPF shall be 1.00. When less than three sublots exist, backup samples of the existing sublots or samples from the street shall be tested to provide a minimum of three sets of results for evaluation. For each lot of HMA mix produced and tested under Commercial Evaluation when the calculated CPF is less than 1.00, a Nonconforming Mix Factor (NCMF) will be determined. The NCMF equals the algebraic difference of CPF minus 1.00 multiplied by 60 percent. The Job Mix Compliance Price Adjustment will be calculated as the product of the NCMF, the quantity of HMA in the lot in tons, and the unit Contract price per ton of mix. If a constituent is not measured in accordance with these Specifications, itsindividual pay factor will be considered 1.00 in calculating the Composite PayFactor(CPF). 5-04.3(10) HMA Compaction Acceptance HMA mixture accepted by nonstatistical evaluation that is used in traffic lanes, including lanes for intersections, ramps, truck climbing, weaving, and speed change, and having a specified compacted course thickness greater than 0.10-foot, shall be compacted to a specified level of relative density. The specified level of relative density shall be a Composite Pay Factor (CPF) of not less than 0.75 when evaluated in accordance with Section 1-06.2, using a LSL of 92.0 (minimum of 92 percent of the maximum density). The maximum density shall be determined by WSDOT FOP for AASHTO T 729. The specified level of density attained will be determined by the evaluation of the density of the pavement. The density of the pavement shall be determined in Kensington Drainage Improvements/Holcomb 5 - 19 February 14, 2022 Project Number: 18-3019 accordance with WSDOT FOP for WAQTC TM 8, except that gauge correlation will be at the discretion of the Engineer, when using the nuclear density gauge and WSDOT SOP 736 when using cores to determine density. Tests for the determination of the pavement density will be taken in accordance with the required procedures for measurement by a nuclear density gauge or roadway cores after completion of the finish rolling. If the Contracting Agency uses a nuclear density gauge to determine density the test procedures FOP for WAQTC TM 8 and WSDOT SOP T 729 will be used on the day the mix is placed and prior to opening to traffic. Roadway cores for density may be obtained by either the Contracting Agency or the Contractor in accordance with WSDOT SOP 734. The core diameter shall be 4-inches minimum, unless otherwise approved by the Engineer. Roadway cores will be tested by the Contracting Agency in accordance with WSDOT FOP for AASHTO T 166. If the Contract includes the Bid item Roadway Core the cores shall be obtained by the Contractor in the presence of the Engineer on the same day the mix is placed and at locations designated by the Engineer. If the Contract does not include the Bid item Roadway Core the Contracting Agency may obtain the cores. For a lot in progress with a CPF less than 0.75, a new lot will begin at the Contractors request after the Engineer is satisfied that material conforming to the Specifications can be produced. HMA mixture accepted by commercial evaluation and HMA constructed under conditions other than those listed above shall be compacted on the basis of a test point evaluation of the compaction train. The test point evaluation shall be performed in accordance with instructions from the Engineer. The number of passes with an approved compaction train, required to attain the maximum test point density, shall be used on all subsequent paving. HMA for preleveling shall be thoroughly compacted. HMA that is used for preleveling wheel rutting shall be compacted with a pneumatic tire roller unless otherwise approved by the Engineer. Test Results For a sublot that has been tested with a nuclear density gauge that did not meet the minimum of 92 percent of the reference maximum density in a compaction lot with a CPF below 1.00 and thus subject to a price reduction or rejection, the Contractor may request that a core be used for determination of the relative density of the sublot. The relative density of the core will replace the relative density determined by the nuclear density gauge for the sublot and will be used for calculation of the CPF and acceptance of HMA compaction lot. Kensington Drainage Improvements/Holcomb 5 - 20 February 14, 2022 Project Number: 18-3019 When cores are taken by the Contracting Agency at the request of the Contractor, they shall be requested by noon of the next workday after the test results for the sublot have been provided or made available to the Contractor. Core locations shall be outside of wheel paths and as determined by the Engineer. Traffic control shall be provided by the Contractor as requested by the Engineer. Failure by the Contractor to provide the requested traffic control will result in forfeiture of the request for cores. When the CPF for the lot based on the results of the HMA cores is less than 1.00, the cost for the coring will be deducted from any monies due or that may become due the Contractor under the Contract at the rate of $200 per core and the Contractor shall pay for the cost of the traffic control. 5-04.3(10)A HMA Compaction – General Compaction Requirements Compaction shall take place when the mixture is in the proper condition so that no undue displacement, cracking, or shoving occurs. Areas inaccessible to large compaction equipment shall be compacted by other mechanical means. Any HMA that becomes loose, broken, contaminated, shows an excess or deficiency of asphalt, or is in any way defective, shall be removed and replaced with new hot mix that shall be immediately compacted to conform to the surrounding area. The type of rollers to be used and their relative position in the compaction sequence shall generally be the Contractors option, provided the specified densities are attained. Unless the Engineer has approved otherwise, rollers shall only be operated in the static mode when the internal temperature of the mix is less than 175°F. Regardless of mix temperature, a roller shall not be operated in a mode that results in checking or cracking of the mat. Rollers shall only be operated in static mode on bridge decks. 5-04.3(10)B HMA Compaction – Cyclic Density Low cyclic density areas are defined as spots or streaks in the pavement that are less than 90 percent of the theoretical maximum density. At the Engineers discretion, the Engineer may evaluate the HMA pavement for low cyclic density, and when doing so will follow WSDOT SOP 733. A $500 Cyclic Density Price Adjustment will be assessed for any 500-foot section with two or more density readings below 90 percent of the theoretical maximum density. 5-04.3(10)C Vacant 5-04.3(10)D HMA Nonstatistical Compaction 5-04.3(10)D1 HMA Nonstatistical Compaction – Lots and Sublots HMA compaction which is accepted by nonstatistical evaluation will be based on acceptance testing performed by the Contracting Agency dividing the project into compaction lots. Kensington Drainage Improvements/Holcomb 5 - 21 February 14, 2022 Project Number: 18-3019 A lot is represented by randomly selected samples of the same mix design that will be tested for acceptance. A lot is defined as the total quantity of material or work produced for each Job Mix Formula placed. Only one lot per JMF is expected. A sublot shall be equal to one days production or 400 tons, whichever is less except that the final sublot will be a minimum of 200 tons and may be increased to 800 tons. Testing for compaction will be at the rate of 5 tests per sublot per WSDOT T 738. The sublot locations within each density lot will be determined by the Engineer. For a lot in progress with a CPF less than 0.75, a new lot will begin at the Contractors request after the Engineer is satisfied that material conforming to the Specifications can be produced. HMA mixture accepted by commercial evaluation and HMA constructed under conditions other than those listed above shall be compacted on the basis of a test point evaluation of the compaction train. The test point evaluation shall be performed in accordance with instructions from the Engineer. The number of passes with an approved compaction train, required to attain the maximum test point density, shall be used on all subsequent paving. HMA for preleveling shall be thoroughly compacted. HMA that is used to prelevel wheel ruts shall be compacted with a pneumatic tire roller unless otherwise approved by the Engineer. 5-04.3(10)D2 HMA Compaction Nonstatistical Evaluation – Acceptance Testing The location of the HMA compaction acceptance tests will be randomly selected by the Engineer from within each sublot, with one test per sublot. 5-04.3(10)D3 HMA Nonstatistical Compaction – Price Adjustments For each compaction lot with one or two sublots, having all sublots attain a relative density that is 92 percent of the reference maximum density the HMA shall be accepted at the unit Contract price with no further evaluation. When a sublot does not attain a relative density that is 92 percent of the reference maximum density, the lot shall be evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The maximum CPF shall be 1.00, however, lots with a calculated CPF in excess of 1.00 will be used to offset lots with CPF values below 1.00 but greater than 0.90. Lots with CPF lower than 0.90 will be evaluated for compliance per 5-04.3(11). Additional testing by either a nuclear moisture-density gauge or cores will be completed as required to provide a minimum of three tests for evaluation. For compaction below the required 92% a Non-Conforming Compaction Factor (NCCF) will be determined. The NCCF equals the algebraic difference of CPF minus 1.00 multiplied by 40 percent. The Compaction Price Adjustment will be calculated as the product of CPF, the quantity Kensington Drainage Improvements/Holcomb 5 - 22 February 14, 2022 Project Number: 18-3019 of HMA in the compaction control lot intons, and the unit Contract price per ton of mix. 5-04.3(11) Reject Work 5-04.3(11)A Reject Work General Work that is defective or does not conform to Contract requirements shall be rejected. The Contractor may propose, in writing, alternatives to removal and replacement of rejected material. Acceptability of such alternative proposals will be determined at the sole discretion of the Engineer. HMA that has been rejected is subject to the requirements in Section 1-06.2(2) and this specification, and the Contractor shall submit a corrective action proposal to the Engineer for approval. 5-04.3(11)B Rejection by Contractor The Contractor may, prior to sampling, elect to remove any defective material and replace it with new material. Any such new material will be sampled, tested, and evaluated for acceptance. 5-04.3(11)C Rejection Without Testing (Mixture or Compaction) The Engineer may, without sampling, reject any batch, load, or section of Roadway that appears defective. Material rejected before placement shall not be incorporated into the pavement. Any rejected section of Roadway shall be removed. No payment will be made for the rejected materials or the removal of the materials unless the Contractor requests that the rejected material be tested. If the Contractor elects to have the rejected material tested, a minimum of three representative samples will be obtained and tested. Acceptance of rejected material will be based on conformance with the nonstatistical acceptance Specification. If the CPF for the rejected material is less than 0.75, no payment will be made for the rejected material; in addition, the cost of sampling and testing shall be borne by the Contractor. If the CPF is greater than or equal to 0.75, the cost of sampling and testing will be borne by the Contracting Agency. If the material is rejected before placement and the CPF is greater than or equal to 0.75, compensation for the rejected material will be at a CPF of 0.75. If rejection occurs after placement and the CPF is greater than or equal to 0.75, compensation for the rejected material will be at the calculated CPF with an addition of 25 percent of the unit Contract price added for the cost of removal and disposal. 5-04.3(11)D Rejection - A Partial Sublot In addition to the random acceptance sampling and testing, the Engineer may also isolate from a normal sublot any material that is suspected of being defective in relative density, gradation or asphalt binder content. Such isolated material will not include an original sample location. A minimum of three random samples of the suspect material will be obtained and tested. The material will then be Kensington Drainage Improvements/Holcomb 5 - 23 February 14, 2022 Project Number: 18-3019 statistically evaluated as an independent lot in accordance with Section 1-06.2(2). 5-04.3(11)E Rejection - An Entire Sublot An entire sublot that is suspected of being defective may be rejected. When a sublot is rejected a minimum of two additional random samples from this sublot will be obtained. These additional samples and the original sublot will be evaluated as an independent lot in accordance with Section 1-06.2(2). 5-04.3(11)F Rejection - A Lot in Progress The Contractor shall shut down operations and shall not resume HMA placement until such time as the Engineer is satisfied that material conforming to the Specifications can be produced: 1. When the Composite Pay Factor (CPF) of a lot in progress drops below 1.00 and the Contractor is taking no corrective action, or 2. When the Pay Factor (PF) for any constituent of a lot in progress drops below 0.95 and the Contractor is taking no corrective action, or 3. When either the PFi for any constituent or the CPF of a lot in progress is less than 0.75. 5-04.3(11)G Rejection - An Entire Lot (Mixture or Compaction) An entire lot with a CPF of less than 0.75 will be rejected. 5-04.3(12) Joints 5-04.3(12)A HMA Joints 5-04.3(12)A1 Transverse Joints The Contractor shall conduct operations such that the placing of the top or wearing course is a continuous operation or as close to continuous as possible. Unscheduled transverse joints will be allowed and the roller may pass over the unprotected end of the freshly laid mixture only when the placement of the course must be discontinued for such a length of time that the mixture will cool below compaction temperature. When the Work is resumed, the previously compacted mixture shall be cut back to produce a slightly beveled edge for the full thickness of the course. A temporary wedge of HMA constructed on a 20H:1V shall be constructed where a transverse joint as a result of paving or planing is open to traffic. The HMA in the temporary wedge shall be separated from the permanent HMA by strips of heavy wrapping paper or other methods approved by the Engineer. The wrapping paper shall be removed and the joint trimmed to a slightly beveled edge for the full thickness of the course prior to resumption of paving. Kensington Drainage Improvements/Holcomb 5 - 24 February 14, 2022 Project Number: 18-3019 The material that is cut away shall be wasted and new mix shall be laid against the cut. Rollers or tamping irons shall be used to seal the joint. 5-04.3(12)A2 Longitudinal Joints The longitudinal joint in any one course shall be offset from the course immediately below by not more than 6 inches nor less than 2 inches. All longitudinal joints constructed in the wearing course shall be located at a lane line or an edge line of the Traveled Way. A notched wedge joint shall be constructed along all longitudinal joints in the wearing surface of new HMA unless otherwise approved by the Engineer. The notched wedge joint shall have a vertical edge of not less than the maximum aggregate size or more than ½ of the compacted lift thickness and then taper down on a slope not steeper than 4H:1V. The sloped portion of the HMA notched wedge joint shall be uniformly compacted. 5-04.3(12)B Bridge Paving Joint Seals 5-04.3(12)B1 HMA Sawcut and Seal Prior to placing HMA on the bridge deck, establish sawcut alignment points at both ends of the bridge paving joint seals to be placed at the bridge ends, and at interior joints within the bridge deck when and where shown in the Plans. Establish the sawcut alignment points in a manner that they remain functional for use in aligning the sawcut after placing the overlay. Submit a Type 1 Working Drawing consisting of the sealant manufacturers application procedure. Construct the bridge paving joint seal as specified on the Plans and in accordance with the detail shown in the Standard Plans. Construct the sawcut in accordance with the detail shown in the Standard Plan. Construct the sawcut in accordance with Section 5-05.3(8)B and the manufacturers application procedure. 5-04.3(12)B2 Paved Panel Joint Seal Construct the paved panel joint seal in accordance with the requirements specified in Section 5-04.3(12)B1 and the following requirement: Clean and seal the existing joint between concrete panels in accordance with Section 5-01.3(8) and the details shown in the Standard Plans. 5-04.3(13) Surface Smoothness The completed surface of all courses shall be of uniform texture, smooth, uniform as to crown and grade, and free from defects of all kinds. The completed surface of the wearing course shall not vary more than inch from the lower edge of a 10-foot straightedge placed on the surface parallel to the centerline. The transverse slope of the Kensington Drainage Improvements/Holcomb 5 - 25 February 14, 2022 Project Number: 18-3019 completed surface of the wearing course shall vary not more than ¼ inch in 10 feet from the rate of transverse slope shown in the Plans. When deviations in excess of the above tolerances are found that result from ahigh place in the HMA, the pavement surface shall be corrected by one of the followingmethods: 1. Removal of material from high places by grinding with an approved grinding machine, or 2. Removal and replacement of the wearing course of HMA, or 3. By other method approved by the Engineer. Correction of defects shall be carried out until there are no deviations anywhere greater than the allowable tolerances. Deviations in excess of the above tolerances that result from a low place in the HMA and deviations resulting from a high place where corrective action, in the opinion of the Engineer, will not produce satisfactory results will be accepted with a price adjustment. The Engineer shall deduct from monies due or that may become dueto the Contractor the sum of $500.00 for each and every section of single traffic lane100 feet in length in which any excessive deviations described above are found. When utility appurtenances such as manhole covers and valve boxes are located in the traveled way, the utility appurtenances shall be adjusted to the finished grade prior to paving. This requirement may be waived when requested by the Contractor, at the discretion of the Engineer or when the adjustment details provided in the project plan or specifications call for utility appurtenance adjustments after the completion of paving. Utility appurtenance adjustment discussions will be included in the Pre- Paving planning (5-04.3(14)B3). Submit a written request to waive this requirement to the Engineer prior to the start of paving. 5-04.3(14) Planing (Milling) Bituminous Pavement The planing plan must be approved by the Engineer and a pre planing meeting must be held prior to the start of any planing. See Section 5-04.3(14)B2 for information on planing submittals. Planing operations shall be performed no more than 7 calendar days ahead of the time the planed area is to be paved, unless otherwise allowed by the Engineer in writing. Locations of existing surfacing to be planed are as shown in the Drawings. Where planing an existing pavement is specified in the Contract, the Contractor must remove existing surfacing material and to reshape the surface to remove irregularities. The finished product must be a prepared surface acceptable for receiving an HMA overlay. Kensington Drainage Improvements/Holcomb 5 - 26 February 14, 2022 Project Number: 18-3019 Use the cold milling method for planing unless otherwise specified in the Contract. Do not use the planer on the final wearing course of new HMA. Conduct planing operations in a manner that does not tear, break, burn, or otherwise damage the surface which is to remain. The finished planed surface must be slightly grooved or roughened and must be free from gouges, deep grooves, ridges, or other imperfections. The Contractor must repair any damage to the surface by the Contractors planing equipment, using an Engineer approved method. Repair or replace any metal castings and other surface improvements damaged by planing, as determined by the Engineer. A tapered wedge cut must be planed longitudinally along curb lines sufficient to provide a minimum of 4 inches of curb reveal after placement and compaction of the final wearing course. The dimensions of the wedge must be as shown on the Drawings or as specified by the Engineer. A tapered wedge cut must also be made at transitions to adjoining pavement surfaces (meet lines) where butt joints are shown on the Drawings. Cut butt joints in a straight line with vertical faces 2 inches or more in height, producing a smooth transition to the existing adjoining pavement. After planing is complete, planed surfaces must be swept, cleaned, and if required by the Contract, patched and preleveled. The Engineer may direct additional depth planing. Before performing this additional depth planing, the Contractor must conduct a hidden metal in pavement detection survey as specified in Section 5-04.3(14)A. 5-04.3(14)A Pre-Planing Metal Detection Check Before starting planing of pavements, and before any additional depth planing required by the Engineer, the Contractor must conduct a physical survey of existing pavement to be planed with equipment that can identify hidden metal objects. Should such metal be identified, promptly notify the Engineer. See Section 1-07.16(1) regarding the protection of survey monumentation that may be hidden in pavement. The Contractor is solely responsible for any damage to equipment resulting from the Contractors failure to conduct a pre-planing metal detection survey, or from the Contractors failure to notify the Engineer of any hidden metal that is detected. 5-04.3(14)B Paving and Planing Under Traffic Kensington Drainage Improvements/Holcomb 5 - 27 February 14, 2022 Project Number: 18-3019 5-04.3(14)B1 General In addition the requirements of Section 1-07.23 and the traffic controls required in Section 1-10, and unless the Contract specifies otherwise or the Engineer approves, the Contractor must comply with the following: 1. Intersections: a. Keep intersections open to traffic at all times, except when paving or planing operations through an intersection requires closure. Such closure must be kept to the minimum time required to place and compact the HMA mixture, or plane as appropriate. For paving, schedule such closure to individual lanes or portions thereof that allows the traffic volumes and schedule of traffic volumes required in the approved traffic control plan. Schedule work so that adjacent intersections are not impacted at the same time and comply with the traffic control restrictions required by the Traffic Engineer. Each individual intersection closure or partial closure, must be addressed in the traffic control plan, which must be submitted to and accepted by the Engineer, see Section 1-10.2(2). b. When planing or paving and related construction must occur in an intersection, consider scheduling and sequencing such work into quarters of the intersection, or half or more of an intersection with side street detours. Be prepared to sequence the work to individual lanes or portions thereof. c. Should closure of the intersection in its entirety be necessary, and no trolley service is impacted, keep such closure to the minimum time required to place and compact the HMA mixture, plane, remove asphalt, tack coat, and as needed. d. Any work in an intersection requires advance warning in both signage and a number of Working Days advance notice as determined by the Engineer, to alert traffic and emergency services of the intersection closure or partial closure. e. Allow new compacted HMA asphalt to cool to ambient temperature before any traffic is allowed on it. Traffic is not allowed on newly placed asphalt until approval has been obtained from the Engineer. 2. Temporary centerline marking, post-paving temporary marking, temporary stop bars, and maintaining temporary pavement marking must comply with Section 8-23. 3. Permanent pavement marking must comply with Section 8-22. 5-04.3(14)B2 Submittals – Planing Plan and HMA Paving Plan The Contractor must submit a separate planing plan and a separate paving plan to the Engineer at least 5 Working Days in advance of each operations activity start date. These plans must show how the moving operation and traffic control are coordinated, as they will be discussed at the pre-planing briefing and pre-paving briefing. When requested by the Engineer, the Contractor must provide each operations traffic control plan on 24 x 36 inch or larger size Shop Drawings with a scale showing both the area of operation and sufficient detail of traffic Kensington Drainage Improvements/Holcomb 5 - 28 February 14, 2022 Project Number: 18-3019 beyond the area of operation where detour traffic may be required. The scale on the Shop Drawings is 1 inch = 20 feet, which may be changed if the Engineer agrees sufficient detail is shown. The planing operation and the paving operation include, but are not limited to, metal detection, removal of asphalt and temporary asphalt of any kind, tack coat and drying, staging of supply trucks, paving trains, rolling, scheduling, and as may be discussed at the briefing. When intersections will be partially or totally blocked, provide adequately sized and noticeable signage alerting traffic of closures to come, a minimum 2 Working Days in advance. The traffic control plan must show where police officers will be stationed when signalization is or may be, countermanded, and show areas where flaggers are proposed. At a minimum, the planing and the paving plan must include: 1. A copy of the accepted traffic control plan, see Section 1-10.2(2), detailing each days traffic control as it relates to the specific requirements of that days planing and paving. Briefly describe the sequencing of traffic control consistent with the proposed planing and paving sequence, and scheduling of placement of temporary pavement markings and channelizing devices after each days planing, and paving. 2. A copy of each intersections traffic control plan. 3. Haul routes from Supplier facilities, and locations of temporary parking and staging areas, including return routes. Describe the complete round trip as it relates to the sequencing of paving operations. 4. Names and locations of HMA Supplier facilities to be used. 5. List of all equipment to be used for paving. 6. List of personnel and associated job classification assigned to each piece of paving equipment. 7. Description (geometric or narrative) of the scheduled sequence of planing and of paving, and intended area of planing and of paving for each days work, must include the directions of proposed planing and of proposed paving, sequence of adjacent lane paving, sequence of skipped lane paving, intersection planing and paving scheduling and sequencing, and proposed notifications and coordination to be timely made. The plan must show HMA joints relative to the final pavement marking lane lines. 8. Names, job titles, and contact information for field, office, and plant supervisory personnel. 9. A copy of the approved Mix Designs. 10. Tonnage of HMA to be placed each day. 11. Approximate times and days for starting and ending daily operations. 5-04.3(14)B3 Pre-Paving and Pre-Planing Briefing At least 2 Working Days before the first paving operation and the first planing operation, or as scheduled by the Engineer for future paving Kensington Drainage Improvements/Holcomb 5 - 29 February 14, 2022 Project Number: 18-3019 and planing operations to ensure the Contractor has adequately prepared for notifying and coordinating as required in the Contract, the Contractor must be prepared to discuss that days operations as they relate to other entities and to public safety and convenience, including driveway and business access, garbage truck operations, Metro transit operations and working around energized overhead wires, school and nursing home and hospital and other accesses, other contractors who may be operating in the area, pedestrian and bicycle traffic, and emergency services. The Contractor, and Subcontractors that may be part of that days operations, must meet with the Engineer and discuss the proposed operation as it relates to the submitted planing plan and paving plan, approved traffic control plan, and public convenience and safety. Such discussion includes, but is not limited to: 1. General for both Paving Plan and for Planing Plan: a. The actual times of starting and ending daily operations. b. In intersections, how to break up the intersection, and address traffic control and signalization for that operation, including use of peace officers. c. The sequencing and scheduling of paving operations and of planing operations, as applicable, as it relates to traffic control, to public convenience and safety, and to other contractors who may operate in the Project Site. d. Notifications required of Contractor activities, and coordinating with other entities and the public as necessary. e. Description of the sequencing of installation and types of temporary pavement markings as it relates to planing and to paving. f. Description of the sequencing of installation of, and the removal of, temporary pavement patch material around exposed castings and as may be needed. g. Description of procedures and equipment to identify hidden metal in the pavement, such as survey monumentation, monitoring wells, street car rail, and castings, before planing, see Section 5-04.3(14)B2. h. Description of how flaggers will be coordinated with the planing, paving, and related operations. i. Description of sequencing of traffic controls for the process of rigid pavement base repairs. j. Other items the Engineer deems necessary to address. 2.Paving additional topics: a. When to start applying tack and coordinating with paving. b. Types of equipment and numbers of each type of equipment to be used. If more pieces of equipment than personnel are proposed, describe the sequencing of the personnel operating the types of equipment. Discuss the continuance of operator personnel for each type of equipment as it relates to meeting Specification requirements. c. Number of JMFs to be placed, and if more than one JMF how the Contractor will ensure different JMFs are distinguished, how pavers and MTVs are distinguished if more than one JMF is being placed at the time, and how pavers and MTVs are Kensington Drainage Improvements/Holcomb 5 - 30 February 14, 2022 Project Number: 18-3019 cleaned so that one JMF does not adversely influence the other JMF. d. Description of contingency plans for that days operations such as equipment breakdown, rain out, and Supplier shutdown of operations. e. Number of sublots to be placed, sequencing of density testing, and other sampling and testing. 5-04.3(15) Sealing Pavement Surfaces Apply a fog seal where shown in the plans. Construct the fog seal in accordance with Section 5-02.3. Unless otherwise approved by the Engineer, apply the fog seal prior to opening to traffic. 5-04.3(16) HMA Road Approaches HMA approaches shall be constructed at the locations shown in the Plans or where staked by the Engineer. The Work shall be performed in accordance withSection5-04. 5-04.3(17) Pavement Reinforcement The Contractor shall install the asphalt interlay fabric at the locations and to the dimensions shown on the Plans and as directed by the Engineer. The interlay fabric shall be placed on existing asphalt or concrete pavement to be overlaid with HMA mix specified in the contract. CONSTRUCTION REQUIREMENTS All equipment, tools, and machines used in the performance of the work shall be subject to the approval of the Engineer and shall be maintained in satisfactory working condition at all times. Equipment for surface cleaning shall be capable of effectively removing oil, grease, dust, dirt or other objectionable materials from the pavement. Application equipment shall consist of suitable brooms, distributor, and laydown machine as required. The distributor shall have a capacity of not less than 1,000 gallons and shall be so designed, equipped, maintained and operated that asphalt material of an even heat shall be uniformly applied at the required rate. It shall be insulated and equipped with an adequate heating device. It shall be equipped with a 10-foot spray bar with extensions, pressure pump and gauge, with a volume gauge so located as to be observed easily by the inspector from the ground, a tachometer to control accurately the speed and spread of asphalt, and two thermometers, one to be installed permanently in the tank to indicate temperature of the asphalt at all times. The power for operating the pressure pump shall be supplied by an independent power unit which will develop a minimum of 25 pounds per square inch pressure at the spray bar. Kensington Drainage Improvements/Holcomb 5 - 31 February 14, 2022 Project Number: 18-3019 The laydown machine shall consist of a small tractor with attachment for the fabric installation. Bucket loaders or backhoes are not permitted for installation. The Contractor shall not begin application of the interlay fabric until he/her has demonstrated, to the satisfaction of the Engineer, that all labor, equipment, and materials necessary to apply the interlay fabric are either on hand or readily available. MATERIALS The approved products are: 1. TenCate Mirafi MPM30 (PGM-30) 2. Tensar GlasPave 25 3. Roadmat RM35 The material properties of the asphalt interlay fabric shall conform to all design and nominal performance standards of TenCate Mirafi MPM30 (PGM-30), Tensar GlasPave 25, Roadmat RM35 or the properties listed below in Table 2.01. Submittals shall include independent confirmation of the material properties. Table 2.01 Physical Properties of the asphalt interlay fabric Property ASTM Test Method Units Min. Avg. Roll Value Tensile Strength @ 0º Tensile Strength @ 90º D5035 lbs/in 200 200 Tensile Elongation % < 5.0 Melting Point (glass) D276 °F (°C ) 450º (232º) Asphalt Retention D6140 gal/yd² 0.10 Mass per Unit Area D5261 oz/yd² 4.0 STORAGE The paving interlayer rolls shall be labeled, with a durable label indicating manufacturer, product name or style number, roll and lot number, and roll dimensions shall be attached to each roll. The paving interlayer rolls shall be delivered and handled in a manner to prevent damage and shall be inspected for defects and damage prior to use. The paving interlayer shall be stored in a dry covered condition, free from dust, dirt, off the ground, flat to prevent bowing, protected from precipitation, ultraviolet radiation, strong chemicals, sparks and flames, temperatures in excess 71 °C (160 °F) and other environmental condition that could cause damage. WEATHER AND MOISTURE LIMITATIONS Work shall not be done during wet weather conditions nor when the pavement and ambient air temperatures are below 50°F. The pavement shall be surface-dry at the time of the application of the asphalt. Kensington Drainage Improvements/Holcomb 5 - 32 February 14, 2022 Project Number: 18-3019 SURFACE PREPARATION All areas of base failure shall be removed and replaced to acceptable industry standards for the specific traffic loads and condition of the project. Pre-Leveling, if necessary, shall be done prior to placing paving interlayer. The pavement surface shall be free of all foreign materials such as dirt, grease, etc. Prior to applying the asphalt, all dust and loose material shall be removed from the pavement surface with compressed air. Existing cracks shall be filled as specified elsewhere under Crack Sealing. In an overlay or milled surface application, repair all failed pavement areas prior to installation of the paving interlayer. Fill all cracks ¼ or greater with approved material. Immediately prior to placement of paving interlayer, the pavement surface shall be dry, cleaned of anything that would interfere with adhesion, for e.g., vegetation, moss, dirt, gravel or water. A leveling or "scratch" course is recommended when road surface is not acceptable and shall be of proper gradation and sufficient thickness to achieve a smooth, level surface with no gaps greater than ¼ depth and width or be acceptable to the project engineer. A finish grind may be used as an alternative to an asphalt leveling course being placed, when you can achieve the final surface texture has no cracks, gaps or vertical angles greater the ¼ depth and width or be acceptable to the project engineer. In all cases the surface must be clean and dry and the application rate of the Hot PG grade asphalt binder shall be increased to insure complete interlayer saturation and bonding. INSTALLATION A. Apply the asphalt interlay fabric in a hot PG graded asphalt binder. Asphalt Emulsion is NOT acceptable for placing paving interlayer due to time delay for it to break and the difficulty in insuring quality as installed. B. Asphalt Binder 1. A hot asphalt binder shall be applied to saturate the paving interlayer (min. to be the asphalt retention rate) plus amount needed to bond to existing surface and the new overlay. The asphalt binder to be used shall be PG58H 22 (PG64 -22) or higher. Sustained ambient temperatures (above 90º) may require a stiffer binder gradation like PG58V 22 (PG70 -22) or higher to improve set time and reduce risk of fabric pick-up under construction traffic. 2. The hot asphalt binder shall be applied per the paving interlayer manufacturer or as directed by the Engineer. For TenCate Mirafi MPM30 the hot asphalt binder shall be applied at a rate of 0.10 Gal/SY on a new HMA leveling surface. On an Kensington Drainage Improvements/Holcomb 5 - 33 February 14, 2022 Project Number: 18-3019 old smooth surface or a clean fine milled surface apply hot asphalt binder shall be applied at a rate of 0.12 Gal/SY. For Tensar GlasPave 25 the hot asphalt binder shall be applied at a rate of 0.15 Gal/SY on a new pavement surface, 0.17 Gal/SY on an aged oxidized surface, and a rate of 0.2 Gal/SY on a milled surface. 3. Spray application shall extend four (4) inches wider than width of paving interlayer on lap side. Hot asphalt binder application shall be wide enough to cover the entire width of engineered paving mat material overlaps. The hot asphalt binder shall be applied only as far in advance of the engineered paving mat material installation as is appropriate to ensure a tacky surface at the time of the engineered paving mat material placement. Traffic shall not be allowed on the hot asphalt binder. 4. The hot asphalt binder shall be applied by a distributor truck in a smooth uniform manner at as low a temperature as is possible to achieve the right application rate, depending on ambient and road surface temperatures and type of PG asphalt binder used. Temperature of the hot asphalt binder shall be sufficiently high enough to permit uniform spray pattern and shall be between 350º F and 400º F. The air temperature shall be 50º F and rising for placement of the hot asphalt binder coat. C. The paving interlayer shall be installed with equipment in good working order that is capable of installing the fabric without wrinkles or manually as needed and recommended by manufacturer. 1. Initial alignment of the interlay fabric is very important, since the fabric direction cannot be changed appreciably without causing wrinkles. If the alignment of the interlay fabric must be changed, the fabric shall be cut and realigned, overlapping the previous material and proceeding as before. 2. If manual lay-down methods are used, the paving fabric shall be unrolled, aligned, and placed in increments of approximately thirty (30) feet or as project engineer suggest. 3. The material shall be placed flat and wrinkle-free. The paving interlayer installation may require hand brooming as necessary to eliminate ripples that may occur during installation. 4. Brooming or squeegee of paving interlayer is required to insure adequate adhesion into the hot asphalt binder before the hot asphalt binder has cooled and lost tackiness. If the interlayer wrinkles more than 1 height during installation, the wrinkle shall be cut and lapped in the direction of paving. In these repaired areas, additional hot asphalt binder shall be Kensington Drainage Improvements/Holcomb 5 - 34 February 14, 2022 Project Number: 18-3019 applied as needed to achieve a sound bond to the substrate. Damaged engineered paving mat shall be removed and replaced, per the manufacturer's recommendations, at the contractor's expense with the same type of material. 5. To ease installations around curves, the paving fabric can be placed in shortened lengths by mechanical equipment or by hand. 6. Paving interlayer shall be lapped two (2) to four (4) inches longitudinally and two (2) to four (4) inches transversely. Transverse laps shall be in the direction of the asphalt concrete overlay placement insuring hot asphalt binder is placed under the overlap. The interlay fabric shall be neatly cut and contoured at all joints. 7. Excess hot asphalt binder that bleeds through the engineered paving mat under normal construction traffic shall be countered by broadcasting clean sand or hot mix to create a bond break between the excess hot asphalt binder and the construction equipment tires. Excess blotting sand shall be removed from the interlayer prior to placing the HMA overlay. No other material, such as asphalt release agents or diesel, shall be used for this purpose. 8. No traffic, except necessary construction traffic or emergency vehicles, shall be driven on the engineered paving mat, unless approved by the engineer. If traffic on the interlayer is approved by the engineer, clean sand shall be lightly broadcasted over the engineered paving mat interlayer, and any loose sand shall be removed prior to paving. 9. Turning of construction equipment and other vehicles shall be gradual and kept to a minimum to avoid damage to the paving interlayer. Caution: Parking on the installed paving fabric prior to final overlay for extended periods could cause damage to the interlayer. 10. Placement of the first lift of the HMA overlay shall closely follow placement of the engineered paving mat. All areas in which the engineered paving mat has been placed shall be paved during the same day, unless approved otherwise by the engineer. In the event of rainfall on the engineered paving mat prior to the placement of the first HMA overlay lift, the engineered paving mat shall be allowed to dry before the HMA is placed. The compacted thickness of the first lift of the HMA overlay on the engineered paving mat shall not be less than 1.5 inches, and the temperature of the mix at placement shall not exceed the engineered paving mat melting point temperature. Where the total HMA overlay thickness is less than 1.5 inches, engineered paving mat shall not be placed. NOTE: Minimum lift thickness should be at least 3 times the nominal maximum aggregate size to ensure aggregate can Kensington Drainage Improvements/Holcomb 5 - 35 February 14, 2022 Project Number: 18-3019 align themselves during compaction to achieve required density and also to ensure mix is impermeable. 11. Paving interlayer should never be installed when it or the pavement surface is wet. 12. The Contractor shall not place more interlay fabric on the roadway than can be overlaid the same day with Hot Mix Asphalt. No fabric, except that which is required for normal lapped joints, shall be exposed to traffic. 13. In the event of breakdown of the paving operation, the interlay fabric which has not been overlaid shall be dusted with sand to break the tackiness of the sealant so traffic does not pick up the fabric. The application rate shall uniformly dust the roadway as approved by the Engineer. More than one application of sand may be required. Before placing the asphalt concrete, the fabric surface shall be broomed to remove the excess sand as directed by the Engineer. The sand shall meet the graduation requirements of the Section 9-03.1(2)B of the WSDOT Standard Specifications. WORKMANSHIP AND QUALITY CONTROL A Technical Representative for the manufacturer of the paving interlayer shall be on the project to work with the Contractors personnel and to provide the necessary technical assistance to ensure the satisfactory placement of the interlay fabric and HMA overlay. The representative shall not leave the project until the Engineer is satisfied that the Contractor has a full understanding of what is required to place the interlay fabric satisfactorily. The installing contractor shall give sufficient notice of planned work schedule such that proper inspection of workmanship is accomplished. 1. Daily, the Contractor shall certify that interlayer was installed per plans and specifications and confirm, by weight tickets and measuring asphalt used, that the hot asphalt binder usage equates to the specified amount for proper interlayer saturation and bonding. 2. Hot asphalt binder application rate shall not be reduced without the Engineers approval. 3. Certification of compliance from the binder supplier shall be provided for each load of hot asphalt binder delivered to the jobsite, showing the type and quality of material delivered. 4. The Contractor shall provide satisfactory confirmation to the Engineer, for each Street Section, showing the total quantity of asphalt binder installed, at the proper application rate as published by the manufacturer. Kensington Drainage Improvements/Holcomb 5 - 36 February 14, 2022 Project Number: 18-3019 5-04.4 Measurement HMA Cl. ½ PG 58H-22, will be measured by the ton in accordance with Section 1-09.2, with no deduction being made for the weight of asphalt binder, mineral filler, or any other component ofthe mixture. If the Contractor elects to remove and replace mix as allowed by Section 5-04.3(11), the material removed will not be measured. No measurement will be made for the installation, maintenance, and removal of temporary pavement markings. 5-04.5 Payment Payment will be made for each of the following Bid items that are included in the Proposal: The unit contract price per ton for HMA Class ½ PG 58H-22 shall be full compensation for all costs incurred to carry out the requirements of Section 5-04 except for those costs included in other items which are included in the Subsection and which are included in the Proposal. This work shall include the cost to install an asphalt thickened edge and/or the pre-leveling work in the areas identified on the plans. The cost for anti-stripping additive and water shall be included in this bid item. No payment will be made for temporary pavement markings. Temporary pavement markings shall be incidental to the project and cost shall be included in the various items of the Contract. Kensington Drainage Improvements/Holcomb 7 - 1 February 14, 2022 Project Number: 18-3019 DIVISION 7 – DRAINAGE STRUCTURES, STORM SEWERS, SANITARY SEWERS, WATER MAINS, AND CONDUITS 7-01 DRAINS SECTION 7-01.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-01.2 Materials Materials for this project shall meet the requirements of the following sections: Geotextile Fabric .................................................... 2-12.2 Gravel Backfill for Drains ......................................... 9-03.12(4) Perforated Polyvinyl Chloride (PVC) Underdrain Pipe .... 9-05.2(6) SECTION 7-01.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-01.4 Measurement The linear foot measurement will include the length of the cleanouts. 7-04 STORM SEWERS THE FIRST PARAGRAPH OF SECTION 7-04.2 IS DELETED AND REPLACED WITH THE FOLLOWING: 7-04.2 Materials Storm sewer pipe 24 inch in diameter shall be lined with cement concrete. The following pipe types are acceptable: Reinforced Concrete Pipe (RCP) Class IV ........ 9-05.7(2) Ductile Iron Pipe Class 50 ............................. 9-05.13 For all Ductile Iron Storm Sewer Pipe __ Diameter, refer to Section 9- 05.13. 7-04.3 Construction Requirements 7-04.3(1) Cleaning and Testing SECTION 7-04.3(1)A IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-04.3(1)A General All storm drain pipe including the downstream system shall be thoroughly cleaned to remove any solids or construction debris that may have entered the pipe system during construction. The Contractor shall be responsible to insure that materials flushed from the storm drain is trapped, removed, and does not enter the downstream drainage system. Kensington Drainage Improvements/Holcomb 7 - 2 February 14, 2022 Project Number: 18-3019 SECTION 7-04.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 7-04.3(1)G Television Inspection All new City storm drain extensions, 24-inch diameter and smaller shall be TV camera inspected by the City Utility Department and accepted prior to placing final crushed rock surfacing and pavement. All construction except final casting adjustments must be completed and approved by the Inspector prior to the TV inspection. The manholes and catch basins must be set to grade, channeled, and grade rings set in place prior to TV inspection. Castings must be removed for paving, and fully grouted in place after paving. SECTION 7-04.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-04.5 Payment The unit contract price per lineal foot for Storm Sewer Pipe, 24 Inch Diameter shall be complete compensation for all labor, materials, tools, supplies and equipment necessary to furnish and install the cement lined pipe at the locations shown on the plans and described in the specifications. The bid item price includes but is not limited to: trench excavation; unsuitable material excavation, hauling, dewatering; backfill and compaction (when native material is to be used), surface restoration, and cleanup. The bid price shall also include fittings, tees, couplings, gaskets, connection to new or existing storm pipes, catch basins, or ditches, testing, coordination for TV inspection, and additional costs for overtime work when working on weekends. The unit contract price per lineal foot for Ductile Iron Storm Sewer Pipe, 12 Inch Diameter shall be complete compensation for all labor, materials, tools, supplies and equipment necessary to furnish and install the pipe with a beveled end as shown in Standard Plan 5-19 at the locations shown on the plans and described in the specifications. This length of pipe specified on the plan is smaller than a single stick of pipe so the contractor shall cut the pipe to the length specified on the plans and provide the remaining pipe to City Operations staff. The bid item price includes but is not limited to: trench excavation; unsuitable material excavation, hauling, dewatering; backfill and compaction (when native material is to be used), surface restoration, and cleanup. The bid price shall also include fittings, tees, couplings, gaskets, connection to new or existing storm pipes, catch basins, or ditches, testing, coordination for TV inspection, and additional costs for overtime work when working on weekends. The unit contract price per each for Trash Screen 12" Diameter constitutes complete compensation for all labor, materials, tools, supplies and equipment necessary to furnish and install the hot dipped galvanized trash screen as shown in standard plan 5-20 and described in the specifications. Kensington Drainage Improvements/Holcomb 7 - 3 February 14, 2022 Project Number: 18-3019 7-05 MANHOLES, INLETS, CATCH BASINS, AND DRYWELLS SECTION 7-05.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-05.3 Construction Requirements All manholes and catch basins shall be precast concrete units and shall conform to Kent Standard Plans 4-1, 4-2, 5-1 and 5-2 unless specified otherwise. Minimum height for Type 1-48 inch, 54 inch, and 60 inch manholes shall be 5 feet. Manholes under 5 feet in height shall conform to Kent Standard Plan 4-2. All manholes and Type II and III CB structures shall be equipped with the drop rung type manhole steps and ladders in accordance with Kent Standard Plan 4-5. The ladder shall be secured from top to bottom, inside the structure wall. No 4 foot hanging ladder sections are allowed. The sanitary sewer manholes shall be fully channeled to conform to the inside diameter of the sewer line from invert to spring line, then the channel shall be vertical to the top of the pipe. The top edge of the channel shall have a radius of 1/2 to 3/4 inch. The shelves shall slope at 2 percent to the top of the channel. All manhole section joints and pick holes shall be filled with grout and smooth finished outside and inside after installation. All manhole penetrations, lifting holes, barrel joints (interior or exterior), risers, frames, and any other location determined by the Engineer, shall be sealed to prevent infiltration. The Contractor shall submit proposed sealing product literature to the Engineer for acceptance, prior to use. Manhole frame and covers shall be cast gray or ductile iron and shall comply with the following Kent Standard Plans as applicable: 4-3 Standard Manhole Frame and Locking Cover Catch basin grates and solid covers shall be ductile iron and of the locking type unless indicated otherwise on the plans and shall be in accordance with Kent Standard Plans 5-4 through 5-16 as applicable. Miscellaneous catch basin details shall be in accordance with Kent Standard Plan 5-3. Care must be taken to insure that pressures exerted on the soils beneath the manholes and the adjacent mains are approximately uniform. Unequal soil pressures may result in excessive settlement at manholes. A spread foundation or other measures may be required to reduce the unit load imposed by the manhole. PVC pipe adaptors shall be KOR-IN-SEAL type flex joints or sand collars or other materials as approved by the Engineer to permit slight Kensington Drainage Improvements/Holcomb 7 - 4 February 14, 2022 Project Number: 18-3019 differential movement. All pipe materials other than the above shall be mudded directly into the manholes and catch basins using a smooth forty five (45) degree bevel from the pipe to the structure meeting ASTM D-303-H-78 SDR35. The allowable protrusion is two (2) inches inside the structure unless approved otherwise by the Engineer. Block lettering is required on the top surfaces of storm drain castings, and shall read as follows: “OUTFALL TO STREAM, DUMP NO POLLUTANTS” SECTION 7-05.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-05.3(1) Adjusting Manholes and Catch Basins to Grade All construction in performing adjustments of existing or new utilities shall conform to the WSDOT Standard Specifications, Standard Plans, Kent Standard Plans and the Kent Special Provisions. Locating all new and existing utilities to be adjusted following the paving shall be the responsibility of the Contractor. The Contractor shall mark or reference all affected utilities including traffic loops prior to paving. Should it be determined by City personnel upon inspection or by notification from other utility companies that the Contractor has failed to adjust existing utilities, the Contractor shall be responsible for completing the adjustments, at no additional cost to the utility company or the City, even if the Contractor has vacated the project site. If the Contractor neglects to reference utilities prior to paving, and for example causes conflicts with or damage to traffic loops, the Contractor shall be responsible to relocate or replace the traffic loops at no additional cost to the City. No less than 4 inches or greater than 16 inches shall be provided between the top of the cone and the underside of the manhole frame for adjustment to street grade or ground surface. Final elevation and slope of the frame and cover shall conform to the final street surface. All joints in the brick or ring adjustment shall be filled with grout, and the castings shall be sealed in grout placed on the ring or brick. A 3/8 inch mortar lining shall be installed inside and out of the adjustment section to form a smooth watertight finish. NOTE: The use or presence of wood, asphalt, expansion joint material or other non-approved product for catch basin or manhole adjustment shall be cause for immediate rejection. On asphalt concrete paving and/or asphalt resurfacing projects, manholes, catch basins and similar structures shall not be adjusted until the pavement is completed, at which time the center of each structure shall be relocated from references previously established by the Contractor. The pavement shall be cut in a restricted area and base material removed to permit removal of the cover. Kensington Drainage Improvements/Holcomb 7 - 5 February 14, 2022 Project Number: 18-3019 The asphalt concrete pavement shall be cut and removed to a neat circle, the diameter of which shall be equal to the outside diameter of the frame plus two feet. The frame shall be placed on concrete blocks and fully mortared to the desired grade. The base materials and crushed rock shall be removed and Cement Concrete Class 3000 shall be placed so that the entire volume of the excavation and up to within, but not to exceed 1-1/2 inches of the finished pavement surface. Note: casting adjustments shall be made with cementatious materials only. Wood, plastic, iron, aluminum, bituminous or similar materials are prohibited. On the following day, the concrete, the edges of the asphalt concrete pavement, and the outer edge of the casting shall be painted with hot asphalt cement. Asphalt concrete shall then be placed and compacted with hand tampers and a patching roller. The completed patch shall match the existing paved surface for texture, density, and uniformity of grade. The joint between the patch and the existing pavement shall then be painted with hot asphalt cement or asphalt emulsion and shall be immediately covered with dry paving sand before the asphalt cement solidifies. SECTION 7-05.3(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-05.3(2) Abandon Existing Manholes Manholes being abandoned shall have the top four feet removed and the remainder of the structure filled with bankrun gravel for trench backfill or gravel borrow as included in the proposal and shall otherwise be in accordance with Section 7-05.3(2) of the WSDOT Standard Specifications. SECTION 7-05.3(3) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-05.3(3) Connections to Existing Manholes It shall be the Contractors sole responsibility to protect the existing sewer system from any damage and/or debris resulting from the construction. Should any damage and/or debris occur, the Contractor shall, at no cost to the City, repair and/or clean said system to the satisfaction of the Engineer. NOTE: Cleaning shall include those existing lines downstream of the project in which debris has been deposited. SECTION 7-05.3(4) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-05.3(4) Drop Manhole Connection Drop manhole connections shall be in accordance with Kent Standard Plan 4-6. Inside drop connections are not allowed. Kensington Drainage Improvements/Holcomb 7 - 6 February 14, 2022 Project Number: 18-3019 SECTION 7-05.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTIONS: 7-05.3(5) Manhole Installation on Existing Sewer The manhole will be placed on and channeled for the existing lines in their existing location. It shall be the Contractors sole responsibility to protect the existing sewer from any damage and/or debris resulting from the construction. Should any damage and/or debris occur, the Contractor shall, at no cost to the City, repair and/or clean said system to the satisfaction of the Engineer. NOTE: Cleaning shall include those existing lines downstream of the project in which debris has been deposited. 7-05.3(6) Storm Drain Marking The pavement adjacent to all new catch basins shall be marked with the following standard pollution prevention button: The Contractor is responsible for installation of the buttons. Markers for publicly owned catch basins will be provided by the City. 7-05.3(7) Relocate Existing Catch Basin The existing catch basin assemblies indicated to be relocated shall be carefully removed to avoid damage. The Contractor will then install the catch basin at the location indicated on the plans so that the assembly will function as shown on the plans. 7-05.3(8) Raise Existing Custom Manhole to Finished Grade The existing Type 1L manhole trash screen shall be removed and disposed of off site. The contractor shall form a cast in place (CIP) cement concrete structure to raise the existing manhole to finished grade. The structure opening is 4x3. Drop rung manhole rungs shall be installed in new CIP walls and a prefabricated ladder shall be installed to the bottom of the catch basin per Std. Plan 4-5. The existing catch basin sump shall be filled in to create a flat cement concrete bottom to the catch basin. Kensington Drainage Improvements/Holcomb 7 - 7 February 14, 2022 Project Number: 18-3019 The existing rockery outfall around the Type 1L structure shall be removed so the pavement can be extended per the plans and described in the specification. SECTION 7-05.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-05.5 Payment The unit contract price per each for Catch Basin, Type 2 54 Inch Diameter constitutes complete compensation for furnishing all labor, materials, tools, supplies, and equipment necessary to install the specified structure to final finished grade as shown on the plans and described in the specifications. This work includes but shall not be limited to: excavating; dewatering; installing; connecting new or existing pipes, backfilling; compacting; surface restoration; referencing for future locates prior to final overlay; and storm drain stenciling. The unit contract price per each for Raise Existing Custom Manhole to Finished Grade constitutes complete compensation for furnishing all labor, materials, tools, supplies, and equipment necessary to adjust the specified structure to final finished grade as shown on the plans and described in the specifications. This work includes but shall not be limited to: disposal of existing cover and concrete grate, forms, cast in place concrete, ladder rungs, preformed ladder, excavating; dewatering; installing; connecting new or existing pipes, backfilling; compacting; surface restoration; referencing for future locates prior to final overlay; and installing City provided storm drain markers. Adjusting the grade by adding or removing risers, grade rings, or sections as required will be included in this bid item. Any adjustments made prior to the final finished elevation shall be considered incidental. The Circular Frame (Ring) and Cover, Type 2 is not included in this bid item and shall be paid for under the corresponding bid item. The unit contract price per each for Circular Frame (Ring) and Cover, Type 2 constitutes complete compensation for all labor, materials, tools, supplies and equipment necessary to furnish and install the new frame and cover or grate as shown on the plans and described in the specifications. This price shall also include adjusting the new frame and cover or grate to match final grades. Any adjustments made prior to the final finished elevation shall be considered incidental. Adjust Existing Manhole Cover to Finished Grade Adjust Existing Catch Basin Grate or Curb Inlet Grate to Finished Grade The unit contract price per each for the above items constitutes complete compensation for furnishing all labor, materials, tools, supplies, and equipment necessary to adjust the specified structure to final finished grade as shown on the plans and described in the specifications. This work includes but shall not be limited to: excavating; dewatering; installing; connecting new or existing pipes, backfilling; compacting; surface restoration; referencing for future locates prior to final overlay; and installing City provided storm drain Kensington Drainage Improvements/Holcomb 7 - 8 February 14, 2022 Project Number: 18-3019 markers. Adjusting the grade by adding or removing risers, grade rings, or sections as required will be included in this bid item. Any adjustments made prior to the final finished elevation shall be considered incidental. The unit contract price per each for 54 Inch Debris Cage constitutes complete compensation for all labor, materials, tools, supplies and equipment necessary to furnish and install the debris cage as shown in standard plan 5-15 and described in the specifications. This price shall also include adjusting the cage to match final grades. Any adjustments made prior to the final finished elevation shall be considered incidental. 7-08 GENERAL PIPE INSTALLATION REQUIREMENTS SECTION 7-08.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-08.2 Materials All pipe shall be of the type and material specified in the bid proposal, shown on the plans or specified herein. All materials used for construction of sanitary sewer and storm drainage systems and appurtenances shall be new and undamaged. All materials used shall be subject to inspection by the City prior to use. The Contractor shall provide the City with shop drawings, manufacturers specifications and certificates of materials as requested. The materials referred to herein, shall conform to the applicable provisions of the WSDOT Standard Specifications, the Kent Special Provisions and the manufacturers recommended installation procedures. See the following Sections of the WSDOT Standard Specifications and the Kent Special Provisions: Cement Concrete Pavement .............. 5-05.2 Culvert Pipe .................................... 7-02.2 Storm Sewers ................................. 7-04.2 Manholes, Inlets and Catch Basins...... 7-05.2 Sanitary Sewer ................................ 7-17.2 Side Sewers .................................... 7-18.2 Crushed Surfacing ........................... 9-03.9(3) Gravel Backfill for Pipe Zone Bedding .. 9-03.12(3) Gravel Borrow ................................. 9-03.14(1) Foundation Material Class I and II ...... 9-03.17 Bank Run Gravel for Trench Backfill .... 9-03.19 7-08.3 Construction Requirements SECTION 7-08.3(1)A IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-08.3(1)A Trenches Kensington Drainage Improvements/Holcomb 7 - 9 February 14, 2022 Project Number: 18-3019 If well points are used for dewatering pipe trenches, they shall be adequately spaced to provide the necessary dewatering and shall be sandpacked and/or other means used to prevent pumping of fine sands or silts from the sub-surface. A continual check by the Contractor shall be maintained to insure that the sub-surface soil is not being removed by the dewatering operation. Once commenced, the dewatering operation shall be continuous until construction and backfilling in the dewatered area is complete. Pump shutdown shall be accomplished in an approved gradual manner. The Contractor shall provide enough facilities and personnel to maintain continuous operation once commenced. Such continuous operation shall be the responsibility of the Contractor. In the event of damage to the trench foundation as determined by the Engineer, or to the ditch walls, or other operations resulting from the failure of the Contractor to maintain the dewatering operation, the complete cost of all repairs shall be borne by the Contractor. It shall be the sole responsibility of the Contractor to dispose of all waters resulting from its dewatering operation. This responsibility also includes choice of method, obtaining regulatory agency approvals, complying with state water quality standards and other agency requirements. Each individual project and dewatering operation shall be evaluated individually to determine exact requirements; however, in general the following conditions will apply. 1. Disposal into the existing storm drain facilities (pipes, channels, ditches, etc.) may be acceptable if the Contractor obtains the necessary permits and approvals. 2. Discharge to existing storm drain facilities shall not result in a violation of state water quality standards for surface water, Chapter 173-203 WAC. 3. The Contractor shall monitor discharge and receiving water(s) as required to verify that water quality standards are being met. 4. If necessary to meet standards and approval requirements, the Contractor shall treat the water prior to discharge. A settling pond may be an acceptable method of treatment. Any damage, as determined by the Engineer to properties or improvements resulting from an inadequate disposal (water) operation shall be the responsibility of the Contractor, including repairs, replacements and/or restoration. Where required or where directed by the Engineer, stabilization of the trench bottom shall be in accordance with Section 7-08.3(1)A of the WSDOT Standard Specifications. Excavation of the unsuitable material shall be considered as trench excavation. The unsuitable material shall be disposed of by the Contractor. Kensington Drainage Improvements/Holcomb 7 - 10 February 14, 2022 Project Number: 18-3019 Backfill unsuitable material excavations with Foundation Material Class I or II meeting the requirements of Section 9-03.17 of the Kent Special Provisions with the class called for in the bid proposal, on the plans or by the Engineer in the field. Trench excavation shall include the required pavement removal for construction of the trench. See Section 2-02.3(3) of the Kent Special Provisions. SECTION 7-08.3(1)C IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-08.3(1)C Bedding the Pipe Bedding shall be placed in accordance with Standard Plan B-55.20-00. Bedding material shall be in accordance with Section 9-03.12(3) of the Kent Special Provisions. Bedding material shall be tamped in layers under, around and above the pipe to adequately support and protect the pipe. The Contractor shall use compaction equipment approved by the Engineer to obtain adequate compaction of the bedding material. Unless otherwise approved by the Engineer, adequate compaction shall be construed to mean to at least 95 percent of the maximum density measured in accordance with ASTM D-1557. The pipe shall be protected from damage when compacting. At least two feet of cover is required over the pipe prior to using heavy compaction equipment. SECTION 7-08.3(2)B IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-08.3(2)B Pipe Laying - General At locations of pipe crossing between new or existing pipes the minimum vertical clearance shall be one and one-half foot unless otherwise approved by the Engineer. If this clearance cannot be obtained, the Contractor shall install a 2-inch thick 1-2 PSF styrofoam cushion between the pipes. The cushion shall be installed longitudinally with the lower pipe. The cushion width shall be equal to the lower pipe diameter and the length shall be one foot greater than the upper pipe diameter. It should be noted that field adjustment of specified slopes for storm and sanitary side sewers are permissible, if approved by the Design Engineer, to obtain the minimum clearances. External or internal grouting or repair by use of collars on the new sanitary or storm sewer line will not be an acceptable means of repair, should repair be necessary. Kensington Drainage Improvements/Holcomb 7 - 11 February 14, 2022 Project Number: 18-3019 All pipe, adaptors, tees, and other fittings shall be used for the purpose intended by the manufacturer and shall be installed according to manufacturers recommendations. SECTION 7-08.3(2)G IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-08.3(2)G Jointing of Dissimilar Pipe Connections of Ductile or Cast Iron Pipe to Concrete Pipe or PVC Pipe will be done by the use of Cast Transition or reducing couplings (Romac 501 or equivalent). SECTION 7-08.3(2)H IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-08.3(2)H Sewer Line Connections Where indicated on the plans or where directed by the Engineer, connections shall be made to the existing storm drain/sewer systems by the Contractor in accordance with applicable portions of the WSDOT Standard Specifications and Kent Special Provisions in a workmanlike manner satisfactory to the Engineer. SECTION 7-08.3(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 7-08.3(2)J Pipe Laying - PVC For PVC pipe, the Contractor shall maintain a cover over the pipe to prevent temperature deformation caused by the sun and shall remove such cover only for a sufficient time to allow the pipe to be installed. When making field cuts of PVC pipe, a new reference line shall be marked on the spigot end a distance of 4-5/8 inches from said end. Said end will provide a visual means of determining whether full insertion of the spigot into the bell has been made during installation. SECTION 7-08.3(4) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-08.3(4) Plugging Existing Pipe Existing pipes being plugged shall be plugged with concrete at both ends and shall otherwise be in accordance with Section 7-08.3(4) of the WSDOT Standard Specifications. SECTION 7-08.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 7-08.3(5) Street Restoration Unless otherwise shown on the plans, street restoration shall be in accordance with the following requirements: Kensington Drainage Improvements/Holcomb 7 - 12 February 14, 2022 Project Number: 18-3019 Where cuts have been made in either asphalt concrete pavement, or in oil mats, the Contractor shall reconstruct the trench areas with a 3 inch thick asphalt concrete patch placed on a 2 inch thickness of crushed surfacing top course over a 4 inch thickness of crushed surfacing base course or as directed by the Engineer in the field. However, where cuts have been made in an asphalt concrete pavement section to be overlayed, the Contractor shall reconstruct the trench with a 2 inch thick asphalt concrete patch with a 2 inch asphalt overlay for a total of 4 inches of asphalt concrete pavement over 6 inches of crushed surfacing top/base course. In all cases, the asphalt and crushed surfacing thickness for the patch shall meet or exceed the existing pavement section. Upon approval of the Engineer, Controlled Density Fill may be used to back fill the narrow trenches where it is difficult to compact crushed surfacing. In these cases the asphalt concrete layer shall increase to a minimum of 2 inches greater than the existing section. Where cuts have been made in cement concrete pavement, the Contractor shall reconstruct the trench area with a 6 inch thick cement concrete patch placed on a 6 inch thickness of crushed surfacing top course. In all cases, the cement concrete and crushed surfacing thickness for the patch shall meet or exceed the existing pavement section. Where there is an existing asphalt overlay over cement concrete pavement, the cement concrete shall be patched to original grade as above and then overlaid with an asphalt concrete patch to existing grade. All gravel shoulders shall be restored to their original condition and shape. The Contractor shall spread a 2 inch thick layer of crushed surfacing on the shoulder. The shoulder shall be finished with a grader after backfilling and compacting and before spreading the crushed surfacing. Permanent surface treatments and pavements shall not be placed until an as-built survey and testing of the new underground utilities have been completed. Verification that utility construction conforms to the line and grade requirements of Section 7-08.3(2)B of the WSDOT Standard Specifications shall be made by the Engineer prior to authorizing paving to begin. Also, each new utility must pass all appropriate tests specified herein for the type of utility prior to paving. 7-17 SANITARY SEWERS SECTION 7-17.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-17.2 Materials Kensington Drainage Improvements/Holcomb 7 - 13 February 14, 2022 Project Number: 18-3019 Materials shall meet the requirements of the following sections unless noted: All sewer pipe for this project shall ductile iron pipe, Class 52 conforming to Section 9-05.13 of the WSDOT Standard Specifications. Epoxy coating for epoxy coated ductile iron sewer pipe shall be Protecto 401 or approved equal. The fitting connecting the PVC pipe to the ductile iron pipe shall be Romac (or approved equal) rigid coupler with gasket. All sewer pipe fittings shall be of the same materials as the pipe. 7-17.3 Construction Requirements SECTION 7-17.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-17.3(1) Protection of Existing Sewerage Facilities The Contractor shall have the sole responsibility for providing and maintaining an adequate sewage bypass system through the project for the duration of the sanitary sewer construction. The adequacy of the bypass system shall be determined by the Engineer and corrected by the Contractor as directed by the Engineer. The existing side sewer that will be worked on is active. The upstream and downstream manholes are unknown. The contractor shall notify the property owner connected to the active sanitary sewer line prior to taking the line temporarily out of service. The sewer line may not be left out of service outside of working hours. The Contractor shall protect the existing 6 diameter PVC side sewer from any damage during construction. This may require placing of plywood or steel plates. To establish the existing condition of the side sewer, before any construction activity occurs in the area of the side sewer pipe the contractor shall install a bi-directional clean out and TV the existing line upstream and downstream of where construction activities will occur. Upon completion of the project, the contractor shall TV the new and existing pipe to confirm that it is undamaged. If the existing side sewer is damaged after construction, the contractor will be responsible for replacing the damaged side sewer at their own expense. 7-17.3(2) Cleaning and Testing SECTION 7-17.3(2)A IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-17.3(2)A General Kensington Drainage Improvements/Holcomb 7 - 14 February 14, 2022 Project Number: 18-3019 All sewer pipe shall be thoroughly cleaned to remove any solids or construction debris that may have entered the pipe during construction by jet cleaning or flush and pigging as approved by the City. The Contractor shall be responsible to insure that material flushed from sewers are trapped, and do not enter the downstream system. The City shall approve the Contractors method prior to cleaning sanitary sewer mains. The rate of flushing shall be such that the flow will not overload the downstream sewers. The flushing of a sewer main tributary to a lift station shall be coordinated with the Operations Division to insure that the lift station is not overloaded. City water used for cleaning sewer lines is not metered, but shall pass through an approved double check valve assembly. SECTION 7-17.3(2)F IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-17.3(2)F Low Pressure Air Test for Sanitary Sewers Constructed of Non Air Permeable Materials All testing shall be verified by the City Inspector. All sewer mains and appurtenances shall be air pressure tested for leakage in accordance with Section 7-17 of the WSDOT Standard Specifications as modified by the following: Procedure for Air Testing Sanitary Sewer Lines For PVC and Ductile Iron Pipe - The Contractor shall furnish all facilities and personnel for conducting the test under the observation of the Engineer. The equipment and personnel shall be subject to the approval of the Engineer. The Contractor may desire to make an air test prior to backfilling for its own purposes. However, the acceptance air test shall be made after backfilling has been completed and compacted. All wyes, tees, or ends of side sewer stubs shall be plugged with flexible-joint caps, or acceptable alternates, securely fastened to withstand the internal test pressures. Such plugs or caps shall be readily removable, and their removal shall provide a socket suitable for making a flexible-jointed lateral connection or extension. Immediately following pipe cleaning, the pipe installation shall be tested with low-pressure air. Air shall be slowly supplied to the plugged pipe installation until the internal air pressure reaches 4.0 pounds per square inch greater than the average back pressure of any ground water that may submerge the pipe. At least two minutes shall be allowed for temperature stabilization before proceeding further. Then, disconnect the air supply and wait until the pressure drops to 3.5 psig greater than the average back pressure of groundwater. The pressure shall be held to the time indicated on the attached tables. Kensington Drainage Improvements/Holcomb 7 - 15 February 14, 2022 Project Number: 18-3019 Groundwater Pressure p = 0.4332 (z) z = Distance between groundwater surface and centerline of pipe in feet. p = Average back pressure of groundwater above the centerline of the pipe in psi. If the pipe installation fails to meet these requirements, the Contractor shall determine at its own expense the source or sources of leakage, and he shall repair (if the extent and type of repairs proposed by the Contractor appear reasonable to the Engineer) or replace all defective materials or workmanship. The completed pipe installation shall meet the requirements of this test before being considered acceptable. Caution When air testing adequate bracing is required to hold plugs in place to prevent the sudden release of compressed air. A pressure of 4 psig against an 8-inch plug will cause a force of approximately 200 lbs.; against a 12-inch plug, 450 lbs. The compressed air acts as a spring. Proper precaution must be taken to prevent this force from propelling the plug from the pipe like a bullet. For systems where groundwater is negligible, at the inspectors discretion, pressure shall be maintained at 4.0 psig with no drop at the time indicated on the attached graphs. LENGTH OF 6 INCH PIPE (FEET) LENGTH OF 8 INCH PIPE (FEET) 0 50 100 150 200 250 300 350 400 0 0 40 80 118 158 198 238 278 316 50 70 110 150 190 228 268 308 348 356 100 140 180 220 260 300 338 374 372 368 150 212 250 290 330 370 390 386 382 378 200 282 322 360 400 404 398 394 390 386 250 352 392 428 418 410 404 400 396 392 300 422 440 430 422 416 410 404 400 396 350 454 442 434 426 420 414 410 404 402 400 454 444 436 428 422 418 412 408 404 Time in seconds required for decompression from 3.5 psig to 3.0 psig. LENGTH OF 6 INCH PIPE (FEET) LENGTH OF 10 INCH PIPE (FEET) 0 50 100 150 200 250 300 350 400 0 0 40 80 118 158 198 238 278 316 50 110 150 190 228 268 308 348 384 380 100 220 260 300 338 378 418 420 414 406 150 330 370 410 448 466 454 444 434 428 200 440 480 514 496 482 470 460 450 444 250 550 542 522 506 494 482 472 464 456 300 566 544 528 514 502 492 482 474 466 350 566 548 534 520 508 494 490 482 474 400 566 550 538 526 514 504 496 488 482 Time in seconds required for decompression from 3.5 psig to 3.0 psig. Kensington Drainage Improvements/Holcomb 7 - 16 February 14, 2022 Project Number: 18-3019 LENGTH OF 6 INCH PIPE (FEET) LENGTH OF 12 INCH PIPE (FEET) 0 50 100 150 200 250 300 350 400 0 0 40 80 118 158 198 238 278 316 50 158 198 238 278 316 356 396 416 408 100 316 356 396 436 476 492 476 464 454 150 476 514 554 566 544 526 510 496 486 200 634 642 612 584 566 550 534 522 510 250 680 650 624 602 582 566 552 540 528 300 680 654 632 612 596 580 566 554 544 350 680 658 638 620 604 590 578 566 556 400 680 660 642 626 612 600 588 576 566 Time in seconds required for decompression from 3.5 psig to 3.0 psig. LENGTH OF 6 INCH PIPE (FEET) LENGTH OF 15 INCH PIPE (FEET) 0 50 100 150 200 250 300 350 400 0 0 40 80 118 158 198 238 278 316 50 248 288 326 376 406 446 486 476 462 100 496 534 574 614 624 596 572 552 530 150 742 782 742 704 672 646 624 604 586 200 850 804 766 732 704 680 658 640 624 250 850 812 780 752 726 704 684 666 652 300 850 818 790 766 742 722 704 688 672 350 850 822 798 776 756 736 720 704 690 400 850 826 804 784 766 748 732 718 704 Time in seconds required for decompression from 3.5 psig to 3.0 psig. LENGTH OF 6 INCH PIPE (FEET) LENGTH OF 18 INCH PIPE (FEET) 0 50 100 150 200 250 300 350 400 0 0 40 80 118 158 198 238 278 316 50 356 396 436 476 314 554 566 544 526 100 712 752 792 794 748 710 680 654 632 150 1020 952 896 850 810 778 748 722 700 200 1020 968 922 884 850 820 794 770 748 250 1020 978 940 906 876 850 826 804 784 300 1020 984 952 922 896 872 850 830 810 350 1020 990 960 916 912 890 868 850 832 400 1020 992 968 944 922 902 884 866 850 Time in seconds required for decompression from 3.5 psig to 3.0 psig. Kensington Drainage Improvements/Holcomb 7 - 17 February 14, 2022 Project Number: 18-3019 LENGTH OF 6 INCH PIPE (FEET) LENGTH OF 24 INCH PIPE (FEET) 0 50 100 150 200 250 300 350 400 0 0 40 80 118 158 198 238 278 316 50 634 674 712 752 792 794 748 710 680 100 1268 1246 1156 1082 1020 968 922 884 850 150 1360 1282 1214 1156 1106 1060 1020 984 952 200 1360 1300 1246 1200 1156 1118 1082 1050 1020 250 1360 1312 1268 1228 1190 1156 1124 1096 1068 300 1360 1320 1282 1246 1214 1184 1156 1130 1106 350 1360 1324 1292 1262 1232 1206 1180 1156 1134 400 1360 1330 1300 1272 1246 1222 1200 1178 1156 Time in seconds required for decompression from 3.5 psig to 3.0 psig. SECTION 7-17.3(2)H IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-17.3(2)H Television Inspection All new sanitary sewer extensions shall be TV camera inspected by the City Operations Division prior to acceptance. All construction must be completed and approved by the inspector prior to the TV inspection. All manholes shall be channeled, and grade rings set in place prior to TV inspection by the City. The casting and top grade ring, do not have to be mudded in until after the final grade is established. SECTION 7-17.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 7-17.3(2)I Vacuum Testing of Sanitary Manholes All new sanitary sewer manholes shall be vacuum tested by the City Operations Division prior to acceptance to ensure it is air-tight and not susceptible to infiltration. On projects with more than one manhole, the Contractor shall have all of the manholes ready for testing prior to scheduling the air-testing with the project inspector. Manholes will not be considered ready for testing until all grouting has been performed and the frame and cover have been grouted in place. It is the responsibility of the Contractor to ensure all manholes are ready for testing prior to scheduling the testing through the inspector. Manholes not ready for testing shall receive a failing mark and a re-test shall be scheduled through the inspector once the manhole is ready. All retests after failure shall be at the Contractors expense. The Contractor shall bear all costs for correction of deficiencies found during the vacuum testing, including the actual or overtime costs of city crew for additional vacuum testing to verify the correction of deficiencies. SECTION 7-17.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-17.4 Measurement Kensington Drainage Improvements/Holcomb 7 - 18 February 14, 2022 Project Number: 18-3019 Concrete Pipe Anchor shall be measure per cubic yard of Concrete poured to install the anchor as shown on the plans. SECTION 7-17.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-17.5 Payment The unit contract price per lineal foot for Ductile Iron Sewer Pipe, 6 Inch Diameter Class 52 Epoxy Coated shall be complete compensation for all labor, materials, tools, supplies and equipment necessary to furnish and install the pipe at the location shown on the plans and described in the specifications. The bid item price includes but is not limited to: connection to the existing active PVC sanitary side sewer pipe, trench excavation; unsuitable material excavation, hauling, dewatering; backfill and compaction (when native material is to be used), surface restoration, and cleanup. The bid price shall also include, connections, fittings, wyes, tees, plugs, and joint materials; connection to new or existing manholes and pipes, air testing; TV inspection before and after installation; coordination for TV inspection with the City, additional costs for overtime work when working on other than normal working hours, and any sewage bypass systems used. The unit bid price per cubic yard for Concrete Pipe Anchor constitutes complete compensation for all labor, tools, supplies, materials and equipment required to provide and place cement concrete (concrete mix may be permitted) and maybe mixed on site and poured without forms as shown on the drawings and specifications or as directed by the Engineer. The unit bid price shall include but not be limited to: excavation, hauling, wrapping pipe in plastic bond breaker, rebar, formwork, backfill and compaction, and clean up. 7-19 SEWER CLEANOUTS SECTION 7-19.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 7-19.5 Payment 6 Inch Two Way Sewer Cleanout, per each. Kensington Drainage Improvements/Holcomb 8 - 1 February 14, 2022 Project Number: 18-3019 DIVISION 8 – MISCELLANEOUS CONSTRUCTION 8-01 EROSION CONTROL AND WATER POLLUTION CONTROL SECTION 8-01.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-01.1 Description This work consists of temporary erosion and sedimentation control procedures (TESCP) as shown on the construction plans, specified in these Kent Special Provisions, and ordered by the Engineer as work proceeds. The TESCP are intended to minimize erosion and sedimentation as well as protect waters of the state and the citys municipal separate storm sewer system (MS4) as required by law. SECTION 8-01.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-01.2 Materials Materials shall meet the requirements of the following sections of the Kent Special Provisions and the WSDOT Standard Specifications: Seed .................................... 9-14.3 Fertilizer ............................... 9-14.4 Mulch and Amendments .......... 9-14.5 Tackifier ............................... 9-14.5(7) 8-01.3 Construction Requirements SECTION 8-01.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-01.3(1) General Preventing and controlling pollution, erosion, runoff, and related damage requires the Contractor to install temporary stormwater best management practices (BMPs) as per the plans and as directed by the City. As site conditions dictate, additional BMPs may be required. The Contractor shall anticipate the need for additional best management practices and propose necessary changes to the City. Should the Contractor fail to install the required temporary erosion and sediment control (TESC) measures or to perform maintenance in a timely manner, or fail to take immediate action to install additional approved measures, all fines, cost of cleanup, costs for delays and down time shall be borne by the Contractor. All cost for this work shall be paid for under the unit contract bid prices. The upgrading of the TESCP facilities shall not constitute a basis for additional working days for this project. The Contractor shall provide the Engineer a minimum of two working days notice prior to clearing adjacent to any wetland, creek or other Kensington Drainage Improvements/Holcomb 8 - 2 February 14, 2022 Project Number: 18-3019 sensitive area. During the construction period, no disturbance beyond the flagged clearing limits shall be permitted. The flagging shall be maintained by the Contractor for the duration of construction. The TESC facilities shall be in accordance with and conform to the CSWPP, Geotechnical report included in the appendix, Kent Surface Water Design Manual, the WSDOT Standards Specifications, and the Ecology Construction Stormwater General Permit (if applicable), except as modified by the Kent Design and Construction Standards or these Kent Special Provisions. It shall be the responsibility of the Contractor to notify the City at once of any TESC deficiencies or changes in conditions such as rutting and or erosion that may occur during construction. The Contractor may recommend possible solutions to the Engineer in order to resolve any problems that are occurring. The requirements of this section shall apply to all areas of the site subject to construction activity as described in the WSDOT Standard Specifications, the Kent Special Provisions and contract plans, including Contractor construction support facilities, Contractor personnel parking areas, equipment and material storage/laydown areas, and other areas utilized by the Contractor for completion of the work. Nothing in this section shall relieve the Contractor from complying with other contract requirements. The erosion control blanket installed on 3:1 slopes shall be PemaTex/PermeaLok Coir 400, Northwest Linings and Geotextile Products, Inc. or Engineer approved equivalent. Blanket shall be installed with staples per WSDOT Std. Plan I-60.10. SECTION 8-01.3(1)A IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-01.3(1)A Submittals Prior to the start of any construction activities, the Contractor shall submit for the Engineers review and approval, the following, as necessitated by the work: 1. Dewatering Plan 2. Spill Prevention Control and Countermeasures Plan 3. Stream Bypass Plan for in-water work 4. Name and contact info for Contractors CESCL SECTION 8-01.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTIONS: 8-01.3(1)F Applicable Regulations and Criteria All construction activities are subject to applicable federal, state, and local permits. The Contractor shall comply with requirements of applicable state and local regulatory requirements, including, but not limited to the following: Kensington Drainage Improvements/Holcomb 8 - 3 February 14, 2022 Project Number: 18-3019 1. WAC 173-201A Water Quality Standards for Surface Waters of the State of Washington 2. RCW 90.48.080 Discharge of pollutants in waters prohibited 3. City of Kent 2017 Surface Water Design Manual 4. Construction Stormwater General Permit WA Department of Ecology 8-01.3(1)G Water Quality Monitoring Sampling of site stormwater discharges is only required if the project is covered under the WA Department of Ecology Construction Stormwater General Permit or if there is a suspected discharge that exceeds state water quality standards. If the project is covered under the Construction Stormwater General Permit, then the Contractor shall conduct sampling as per the conditions listed in the permit. Any results that are outside the appropriate range of compliance will require immediate implementation of adaptive management as outlined in applicable permits, stormwater pollution prevention plan, and as directed by the Engineer. All sampling records shall be submitted to the Engineer by the last day of the monitoring period. All necessary adaptive management requirements shall be the responsibility of the Contractor to implement and maintain. All costs for this work shall be included in the various unit contract bid prices. SECTION 8-01.3(2)E IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-01.3(2)E Tackifiers Unless specified otherwise, wood cellulose fiber mulch per Section 9-14(5)10 of the Standard Specifications shall have tackifier incorporated into the mulch fiber during manufacture. If additional tackifier is required, the tackifier shall be organic tackifier as specified in Section 9-14.5(7)A of the WSDOT Standard Specifications. When specified, tackifiers shall be applied in accordance with the manufacturer's recommendations. 8-01.3(9) Sediment Control Barriers SECTION 8-01.3(9)D IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-01.3(9)D Inlet Protection Cleaning and maintenance of inlet protection shall not flush sediment, or sediment-laden water into the downstream system. Kensington Drainage Improvements/Holcomb 8 - 4 February 14, 2022 Project Number: 18-3019 SECTION 8-01.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 8-01.3(17) Vehicle Maintenance and Storage Handling and storage of fuel, oil and chemicals shall not take place within 50 feet of waterways. Storage shall be in dike tanks and barrels with drip pans provided under the dispensing area. Shut-off and lock valves shall be provided on hoses. Fuel, oil, and chemicals shall be dispensed only during daylight hours unless approved by the engineer. Fencing shall be provided around storage area. Locks shall be provided on all valves, pumps, and tanks. Materials used to clean up fuel, oil, and chemical spills shall be disposed of as directed by the engineer. Water used for washing vehicles and equipment shall not be allowed to enter storm drains or other State waters. No processed waste water(s) of any kind shall be discharged onto the ground, to surface waters, or to stormwater conveyance systems. SECTION 8-01.5(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-01.5(2) Item Bids The unit contract price per square yard for Seeding, Fertilizing, and Mulching shall be full pay for all labor, materials tools and equipment necessary to complete the above said hydroseeding, seeding, fertilizing and mulching at the locations shown on the plans, including the following areas: 1. All planter areas or areas disturbed by the Contractor's operations behind the sidewalk, even where it is only a narrow strip. 2. All biofiltration swales. 3. Detention pond site. 4. Other areas as directed by the Engineer. Water, fertilizer and mulch shall be provided by the Contractor as necessary to maintain and establish the seeded areas and is considered incidental to this bid item. Topsoil Type B is considered incidental to this bid item unless a specific bid item is listed in the proposal. The cost of baffling or blocking over spray as required to prevent over spray onto the sidewalk, curbing and non-planter areas is incidental to the unit price. The unit bid price per lineal foot for Filter Fabric Fence constitutes complete compensation for all labor, tools, materials, supplies and equipment necessary to construct and install the fence as shown on the plans, including fabric, posts and gravel to anchor fabric. This bid item also includes: maintenance throughout the project; and removal and disposal of the fence and accumulated sediment as directed by the Engineer. Filter fabric fence is included in the payment items and shall only be used when directed by the engineer. Kensington Drainage Improvements/Holcomb 8 - 5 February 14, 2022 Project Number: 18-3019 The unit contract price per each for Inlet Protection shall be full pay for furnishing all labor, materials, tools and equipment necessary to construct, maintain, and remove when no longer required, this temporary erosion control measure. No other further compensation will be made. The unit bid price per square yard for Straw Mulch constitutes complete compensation for all materials, tools, labor and equipment required for applying straw mulch on exposed soils for erosion control as directed by the Engineer. Straw shall be in an air-dried condition, and free of noxious weeds and other materials detrimental to plant life. The unit contract price per square yard for Erosion Control Blanket shall be full compensation for all labor, materials, tools, staples and equipment necessary to install the blanket per the referenced plans and these specifications. The unit bid price per linear foot used for Wattle constitutes complete compensation for all materials, tools, labor and equipment required for supply, removal and disposal, placement and grading to install the straw wattles wherever specified, as shown on the plans or as directed by the Engineer. Straw shall be in an air dried condition free of noxious weeds and other materials detrimental to plant life. Straw wattles shall conform with requirements in WSDOT Standard Specifications 9- 14.5(5). The unit price per square yard for Clear Plastic Covering (6 mil polyethylene sheets) shall constitute complete compensation for furnishing, staking, maintaining and protecting, the material in place (including sand bags and stakes) on all exposed soils per the WSDOT Standard Specification and as directed by the Engineer. The unit contract price per hour for ESC Lead shall be full pay for all duties outlined in Section 8-01.3(1)B (Erosion and Sediment Control (ESC) Lead) in per hour increments. 8-02 ROADSIDE RESTORATION SECTION 8-02.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.1 Description Drawings and Specifications: Definitions: The word provide means furnish and install (for landscaping only). Dimensions and Measurements: Dimensions govern when shown. Scale is approximate. Contractor shall check all dimensions in the field and verify them with respect to adjacent or incorporated work. Any discrepancies in the drawings shall be brought to the immediate attention of the Engineer before work proceeds further. Kensington Drainage Improvements/Holcomb 8 - 6 February 14, 2022 Project Number: 18-3019 Number of Specified Items Required: Wherever in these Kent Special Provisions an article, device or piece of equipment is referred to in the singular number, such reference shall include as many such items as are shown on drawings or required to complete the installation. SECTION 8-02.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 8-02.1(1) Submittals The Contractor shall submit within 20 days after Notice to Proceed date a list of all plant material indicating source of supply, order invoice, size and quantity for such species or variety. All plant materials shall meet requirements of State and Federal laws with respect to inspection for plant diseases and infestations. Inspection certificates required by law shall accompany each shipment of plant material and submitted to the Engineer. SECTION 8-02.2 IS DELETED AND REPLACED WITH THE FOLLOWING: 8-02.2 Materials Materials shall meet the requirements of the following sections: Topsoil Type A, Type B, and Type C ............. 9-14.2(1), (2), (3) Seed ....................................................... 9-14.3 Fertilizer .................................................. 9-14.4 Mulch and Amendments ............................. 9-14.5 Wood Cellulose Fiber ................................. 9-14.5(10) Erosion Control Devices ............................. 9-14.6 Plant Materials .......................................... 9-14.7 Street Trees ............................................. 9-14.7(1)A Stakes, Guys and Wrapping ....................... 9-14.8 Tree Ties ................................................. 9-14.8(1) Water for Plants........................................ 9-25.2 Botanical identification and nomenclature of plant materials shall be based on descriptions by Bailey in Hortus Third or superseding editions and amendments. 8-02.3 Construction Requirements SECTION 8-02.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(1) Responsibility During Construction The Contractor shall at all times keep the planted areas free from accumulations of waste materials or rubbish. Upon completion of the planting work, the Contractor shall immediately remove all refuse and debris resulting from the planting activities. The project will not receive either preliminary or final approval if the cleanup does not meet with the approval of the Engineer. Kensington Drainage Improvements/Holcomb 8 - 7 February 14, 2022 Project Number: 18-3019 SECTION 8-02.3(3) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(3) Weed and Pest Control During the maintenance period, all weeds are to be removed by hand. SECTION 8-02.3(5)A IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(5)A Seeding Area Preparation The Contractor shall excavate planting pits to a depth of three feet below the top of adjacent sidewalks, or adjacent ground if trees are not being planted in sidewalk cutouts. Tree pits shall be about three feet in diameter, and shall be neat and uniform basins around each tree. The Contractor shall then place special planting mixture into the tree basins, bringing to grade about one and one-half foot below the top of the planter by compaction by repeated watering. Refer to Section 8-02.3(4) of the WSDOT Standard Specifications. SECTION 8-02.3(7) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(7) Layout of Planting, Lawn and Seeding Areas The location of plantings shall be according to the landscaping details, unless otherwise directed by the Engineer. The Contractor shall layout tree, shrub and herbaceous plant locations and receive the approval of the Engineer before planting begins. SECTION 8-02.3(8) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(8) Planting All plants shall be carefully placed in excavated holes to prevent damage to fibrous root systems during placement and backfilling operations, with burlap or container removed. Plants shall be set vertically in the center of the pits, backfilled with native soil, watered and settled so that the crown of the root ball will have the same relation to finished grade as it bore to the grade of the ground from which it was dug. All street trees shall be planted in general conformance to Kent Standard Plan 6-55. SECTION 8-02.3(8)C IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(8)C Pruning, Staking, Guying, and Wrapping Pruning shall be limited to the minimum amount necessary to remove injured twigs and branches. Only cut injured limbs to the nearest lateral bud. Do not apply tree wound paint or petroleum product to tree cuts. The Contractor shall use rootball bracing (triangle method) rather than staking or guying to support new trees. Kensington Drainage Improvements/Holcomb 8 - 8 February 14, 2022 Project Number: 18-3019 8-02.3(9) Seeding, Fertilizing and Mulching SECTION 8-02.3(9)A IS REVISED BY DELETING THE FIRST THREE PARAGRAPHS AND REPLACING WITH THE FOLLOWING: 8-02.3(9)A Dates for Application of Seed Unless otherwise approved by the Engineer, the final application of seeding, fertilizing, and mulching of slopes shall be performed during the following periods: West of the summit of the Cascade Range - March 1 to May 15 and August 15 to October 1. Where contract timing is appropriate, seeding, fertilizing, and mulching shall be accomplished during the spring period listed above. Written permission to seed after October 1 will only be given when physical completion of the project is imminent and the environmental conditions are conducive to satisfactory growth. SECTION 8-02.3(9)B IS DELETED AND REPLACED WITH THE FOLLOWING: 8-02.3(9)B Seeding and Fertilizing Topsoil and all other unpaved and unsodded areas within easements and right-of-way disturbed as part of this project shall be seeded. Hydroseeding shall be the method of seed application. Hydroseed shall consist of a slurry composed of water, seed, fertilizer, tackifier, and mulch and shall be evenly broadcast over areas to be seeded. All work shall conform in all respects to Section 8-01 of the WSDOT Standard Specifications, except as modified herein. The Contractor shall notify the Engineer not less than 48 hours in advance of any hydroseeding operation and shall not begin the work until areas prepared or designated for hydroseeding have been approved. Following the Engineer's approval, hydroseeding of the approved slopes shall begin immediately. Hydroseeding shall not be done during windy weather or when the ground is frozen, excessively wet, or otherwise untillable. Hydroseed mixture to be applied by an approved hydro seeder which utilizes water as the carrying agent, and maintains continuous agitation through paddle blades. It shall have an operating capacity sufficient to agitate, suspend, and mix into a homogeneous slurry the specified amount of seed and water or other material. Distribution and discharge lines shall be large enough to prevent stoppage and shall be equipped with a set of hydraulic discharge spray nozzles that will provide a uniform distribution of the slurry. The seed and fertilizer cannot be placed in the tank more than 30 minutes prior to application. The seed and fertilizer shall have a tracer added to visibly aid uniform application. This tracer shall not be harmful to plant and animal life. If wood cellulose fiber is used as a tracer, the application rate shall not exceed 25 pounds per acre. Kensington Drainage Improvements/Holcomb 8 - 9 February 14, 2022 Project Number: 18-3019 Areas where hydroseeding is not practical, must be seeded by approved hand methods as approved by the engineer. When seeding by hand, Contractor shall incorporate seed into the top 1/4 inch of soil. The hydroseed slurry shall consist of the following materials mixed thoroughly together and applied in the quantities indicated. 1. Grass Seed: Mixture shall be fresh, clean, new crop seed. Seed to be mixed mechanically on the site or may be mixed by the dealer. If seed is mixed on site, each variety shall be delivered in the original containers bearing the dealers guaranteed analysis. If seed is mixed by the dealer, the Contractor shall furnish to the Engineer the Dealers guaranteed statement of the composition of the mixture and the percentage of purity and germination of each variety. Grass seed shall be purchased from a recognized distributor and shall be composed of the varieties mixed in the proportions indicated in the WSDOT Standard Specifications and Kent Special Provisions. Seed shall meet the minimum percentages of purity and germination specified in Section 9-14.3 of the Kent Special Provisions. Seed shall be applied at the rate of 120 pounds per acre. The Contractor shall protect seed from hydration, contamination, and heating during delivery, storage, and handling. Seed shall be stored in a cool dry location away from contaminants. Mix A shall be used as the standard hydroseed mix unless otherwise specified herein or on approved project plans. Mix B shall be used exclusively for seeded areas adjacent to grass lawns, within seeded medians, and within seeded traffic islands. In addition, Mix B shall be used for all seeded areas not specifically showing Mix A on the plans, or where otherwise directed by the Engineer. 2. Water: The Contractor shall begin maintenance immediately after seeding for a minimum of ten (10) weeks or longer as needed. Water seeded areas before hydroseed slurry has completely dried out. Water slowly and thoroughly with fine spray nozzle. Water the hydroseeded areas at least twice daily (in the early morning and late afternoon) until the grass is well established as determined by the Engineer. Repeat watering operation as required by climatic conditions to keep areas moist for a minimum period of 2 weeks from the day of first watering and as necessary for healthy growth. 3. Mulch: As needed to meet requirements of Sections 8-01.3(11)A and 9-14.5. 4. Fertilizer: All areas which are seeded shall receive fertilizer of the following proportions and formulation applied at the rate of 400 Kensington Drainage Improvements/Holcomb 8 - 10 February 14, 2022 Project Number: 18-3019 pounds per acre. All areas which are seeded shall receive fertilizer meeting the requirements of Section 9-14.4 of the Kent Special Provisions. Fertilizer shall not be applied on any creek sideslopes in order to avoid contamination of these creeks. 5. Hand Seeding: Seeding shall be applied at the rate of 6 pounds per 1,000 square feet. The seed shall be applied by an approved hand held spreader. The seed shall be evenly distributed over the disturbed area. Apply seed mix after fertilizing and rake the seed into the surface soil to a depth of 1/4-inch. 6. If the slurry is used for temporary erosion control it shall be applied at the following rates: EROSION CONTROL: Seed 170 lbs/acre of Mix A unless otherwise directed by Engineer. Fertilizer 400 lbs/acre Wood Fiber 2,000 lbs/ acre Tackifier 80 lbs/acre SECTION 8-02.3(9)D IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(9)D Inspection Inspection of seeded areas shall be made upon completion of seeding operations, at the end of the maintenance period, and at any time during the maintenance period. The Contractor shall reseed, re-mulch or re-fertilize as required to establish a uniform, thick stand of grass. A uniform stand of grass shall be defined as any grass area with no spots greater than one square foot. Areas failing to show a uniform thick, healthy stand of grass after the maintenance period shall be reseeded consistent with the Kent Special Provisions at the Contractor's expense. Reseeded areas will be subject to inspection for acceptance. SECTION 8-02.3(9)E IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(9)E Protection and Care of Seeded Areas Protect adjacent property, public walks, curbs and pavement from damage. Do not place soil directly on paved surfaces. Locate all underground utilities prior to the commencement of work. Keep streets and area drains open and free flowing. Protect all seeding against wind, storm, and trespassing. Replace any plants that become damaged or injured. In seeded areas, treat and reseed damaged spots larger than one square foot. Kensington Drainage Improvements/Holcomb 8 - 11 February 14, 2022 Project Number: 18-3019 SECTION 8-02.3(11)A IS DELETED AND REPLACED WITH THE FOLLOWING: 8-02.3(11)A Mulch for Seeding Areas Wood cellulose fiber mulch conforming to Section 9-14.5(10) of the Standard Specifications shall be used where mulch is called for on this project. The application rate shall be 2,000 pounds to the acre in accordance with Section 8-01 of the WSDOT Standard Specifications. Mulch shall be incorporated into the slurry of seed and fertilizer. Mulch of the type specified in Section 9-14.5 shall be included in the hydroseeding process. Wood cellulose fiber used as a mulch shall be suitable for application with hydroseeders as specified in Section 8-01.3(9)B. The application of seed, fertilizer, and mulch shall be required in a single operation for all seed applications, unless otherwise directed. Mulch materials, shall be furnished, hauled, and evenly applied at the rates indicated, and shall be spread on seeded areas immediately after seeding unless otherwise specified. Distribution of straw mulch material shall be by means of an approved type mulch spreader, which utilizes forced air to blow mulch material on seeded areas. In spreading straw mulch, the spreader shall not cut or break the straw into short stalks. Straw mulch shall be applied at a rate to achieve a loose, overall thickness of three (3) inches. Areas not accessible by mulching equipment shall be mulched by approved hand methods and shall achieve similar results. Mulch sprayed on signs or sign structures shall be removed the same day. SECTION 8-02.3(11)B IS REVISED AS FOLLOWS: 8-02.3(11)B Bark or Woodchip Mulch Revise all references in this section from bark or wood chip mulch to wood chip mulch. Add A sample of the wood chip mulch shall be provided to the Engineer or project Ecologist in a 1-gallon re-closable bag at least seven (7) days prior to application. SECTION 8-02.3(13) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(13) Plant Establishment The Contractor is responsible for maintaining all trees and shrubs in a clean and thriving condition for a period of not less than two calendar years. The period of maintenance shall begin upon final installation and inspection of work, and subsequent written notification by the Engineer. Maintenance shall include all necessary cleaning, weeding, pruning, watering, and one supplemental feeding with approved fertilizer. Kensington Drainage Improvements/Holcomb 8 - 12 February 14, 2022 Project Number: 18-3019 The Contractor shall water all trees and shrubs a minimum of once per week during the months of June through September to establish the vegetation during the dry summer months. Maintenance of this watering schedule is critical to the survival of the trees and shrubs. SECTION 8-02.3(14) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.3(14) Plant Replacement The Contractor shall replace all trees and shrubs which, in the opinion of the City Nursery Supervisor, have failed to establish themselves during the maintenance period at its sole expense. All replacement planting shall be conducted in conformance to these specifications. SECTION 8-02.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 8-02.3(17) Plant and Site Protection During Entire Construction Period The Contractor shall: 1. Protect existing trees to remain and new plants against injury and damage, including but not limited to: cutting, breaking, or skinning of roots, trunk or branches, or smothering by stockpiling construction material, or compaction by equipment. 2. Keep all heavy equipment (e.g., backhoe) outside of the drip lines of all existing trees, so as not to damage the root systems. 3. Notify Engineer immediately if a conflict arises between construction activity and the protection of trees and shrubs; alter methods as necessary and as approved by the Engineer. SECTION 8-02.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-02.5 Payment The unit contract price per cubic yard for Topsoil Type A constitutes complete compensation for all labor, materials, tools and equipment necessary to supply and spread the topsoil in the areas shown on the plans, or where directed by the Engineer. This item includes but is not limited to the labor required for raking and compacting the topsoil, cleanup and complete preparation ready for seeding. 8-03 IRRIGATION SYSTEMS SECTION 8-03.5 IS DELETED AND REPLACED WITH THE FOLLOWING: 8-03.5 Payment The bid item Existing Irrigation Systems Removal, Repair and/or Modifications shall be paid by force account in accordance with Section 1-09.6 of the WSDOT Standard Specifications. This payment shall constitute complete compensation for all labor, tools, materials, and equipment necessary to repair any irrigation system disturbed Kensington Drainage Improvements/Holcomb 8 - 13 February 14, 2022 Project Number: 18-3019 during construction as approved by the Engineer. This item also includes all costs to submit plans and obtain approval from the City as required for the work to be completed. This bid item shall include all costs associated with relocating existing irrigation boxes and valves. For the purpose of providing a common proposal for all bidders, the City has entered an estimated amount for force account for this item in the proposal to become part of the total bid by the Contractor. 8-12 CHAIN LINK FENCE AND WIRE FENCE SECTION 8-12.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-12.4 Measurement Temporary fencing shall be measured by the linear foot of temporary fence, along the ground line exclusive of openings. Gates shall be included in the fence measurement. SECTION 8-12.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-12.5 Payment Temporary 6' High Chain Link Fence, per linear foot. 8-15 RIPRAP SECTION 8-15.3(4) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-15.3(4) Rock for Erosion and Scour Protection Rock for Erosion and Scour Protection shall conform to Class B riprap as described in Section 9-13.4(2) of the WSDOT Specifications. Rock shall be free of debris and organic contaminants. Rock fill should be placed and compacted in accordance with Section 8- 15.3(3) Hand Placed Riprap. Compaction may be performed via tamping with an excavator bucket or the use of vibratory compaction equipment. SECTION 8-15.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-15.5 Payment The unit contract price for Rock for Erosion and Scour Protection Class B per tons shall be full pay for furnishing all labor, tools, equipment and materials required to prepare the ditch subgrade and place and compact rock fill on the prepared subgrades as ditch lining material described in the specifications. Kensington Drainage Improvements/Holcomb 8 - 14 February 14, 2022 Project Number: 18-3019 8-21 PERMANENT SIGNING 8-21.3 Construction Requirements SECTION 8-21.3(4) IS REVISED BY DELETING THE 4TH SENTENCE AND BY ADDING THE FOLLOWING: 8-21.3(4) Sign Removal Wood signs, wood sign posts, wood structures, metal sign posts, windbeams, and other metal structural members shall become the property of the Contractor and shall be removed from the project. Aluminum signs shall remain the property of the City. The Contractor shall bundle and band the signs, and deliver the signs to the Sign Shop at the City Maintenance Facility located at 5821 South 240th Street (a.k.a. West James Street). All signs shall be delivered to the Sign Shop prior to physical completion of the project. The Contractor shall be charged $2.00 per square foot for any signs that are lost or are rendered unusable as signs by the Contractors operation. Also see Section 2-02.3 of the Kent Special Provisions. SECTION 8-21.3(5) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-21.3(5) Sign Relocation Relocated signs shall be installed on new wood posts unless otherwise specified on the plans, or by the Engineer. SECTION 8-21.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-21.5 Payment The unit contract price for Type III Fixed (Permanent) Barricade per each will be full pay for all labor, materials, supplies and equipment necessary to furnishing and install the barricade per Std. Plan 6-71a in the location shown on the plans. This bid item will also include all costs to furnish and install a 3M High Intensity Prismatic end of road symbol (OM-4) sign on the Type III barricade. 8-22 PAVEMENT MARKING SECTION 8.22.2 IS DELETED AND REPLACED WITH THE FOLLOWING: 8-22.2 Materials Material for pavement and curb markings shall be white or yellow paint as noted in the Proposal and Bid Item Descriptions. All paint, including the paint for the concrete curbs, shall be described in the Qualified Products List as Temporary Pavement Marking Paint Low VOC Solvent Based. Paint and sprayed material shall be applied with a top dressing of glass beads. Kensington Drainage Improvements/Holcomb 8 - 15 February 14, 2022 Project Number: 18-3019 All Paint shall comply with the specifications for no heat, instant dry pavement markings. Glass beads shall be AC-110 Highway Street Spheres, or pre-approved equal. Material for pavement markings shall be paint, plastic or Raised Pavement Markings (RPMs) as noted in the bid item. Paint and plastic shall be selected from materials listed in the Qualified Products list (QPL). Material for RPMs shall meet the requirements for Section 8-09.2. 8-22.3 Construction Requirements SECTION 8-22.3(1) IS DELETED AND REPLACED WITH THE FOLLOWING: 8-22.3(1) Preliminary Spotting The Contractor shall be responsible for matching the existing channelization in the roadway including preliminary spotting of the lines to be marked and verification that minimum lane widths will result from the application. Approval by the Engineer is required before the placement of permanent pavement marking. SECTION 8-22.3(3) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-22.3(3) Marking Application The Contractor is responsible for providing traffic control and traffic control devices as necessary to direct vehicular traffic away from freshly painted traffic stripes until such time as the marking paint has completely dried. Failure to ensure reasonable protection for the undried paint stripes will result in the Engineers decision to adjust the method of payment for damaged paint stripes. The Engineers decision regarding the means of payment adjustment for vehicle damaged paint stripes is final in this matter. SECTION 8-22.3(3)B IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-22.3(3)B Line Patterns Edge Line– Paint;A single solid white/yellow line 4 inches wide used for road edge and lane delineation, bike lane delineation, parking stall and ADA delineation, adjacent lanes traveling in the same direction or bus pull-outs. SECTION 8-22.3(6) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 8-22.3(6) Removal of Pavement Markings Kensington Drainage Improvements/Holcomb 8 - 16 February 14, 2022 Project Number: 18-3019 The City has not shown the existing pavement markings on the plans. The bidder shall visit the site to determine the extent, location and type of items to be removed. SECTION 8-22.5 IS DELETED AND REPLACED WITH THE FOLLOWING: 8-22.5 Payment Payment will be made in accordance with Section 1-04.1, for each of the following bid items that are included in the Proposal: The unit contract price per lump sum for Permanent Channelization constitutes complete compensation for all labor, materials, tools, supplies and equipment necessary to remove existing, reference existing, furnish and install permanent channelization matching the existing channelization as shown on the plans and described in the specifications. All costs to supply and install temporary pavement making shall be included in this payment item. 8-24 ROCK AND GRAVITY BLOCK WALL AND GABION CRIBBING SECTION 8-24.3(A) IS DELETED AND REPLACED WITH THE FOLLOWING: 8-24.3(A) Foundations Before placing any gabion cribbing, the Contractor shall excavate the foundation or bed to the specified grade in accordance with Section 2- 06.3(1). Foundation soils found to be unsuitable shall be removed and replaced in accordance with Section 2-09.3(1)C. Non-woven geotextile fabric shall be installed per Section 2-12 between the subgrade and the gabion cribbing. SECTION 8-24.4 IS SUPPLIMENTED WITH THE FOLLOWING: 8-24.4 Measurement Rock for Gabion Basket Backfill will be measured by the ton of rock actually placed in the gabion baskets. Gabion Basket cribbing does not include the rock backfill for the gabion basket. SECTION 8-24.5 IS SUPPLIMENTED WITH THE FOLLOWING: 8-24.5 Payment Rock for Gabion Basket Backfill, per ton. 8-30 PROJECT SIGNS 8-30.1 Description This work shall consist of fabrication of the project signs; furnishing and installing all posts, braces, and hardware and installation and maintenance of the project signs where shown in the plans or where Kensington Drainage Improvements/Holcomb 8 - 17 February 14, 2022 Project Number: 18-3019 directed by the Engineer. All project signs become the property of the City at the end of the project and shall be delivered by the Contractor to the City Maintenance Shop on West James Street. 8-30.2 Materials Sign posts shall be 4 inch x 6 inch Fir. 8-30.3 Construction Requirements 8-30.3(1) Erection of Posts All posts shall be set reasonably vertical, and deep enough to sustain sign and expected wind loads as determined by the Engineer. 8-30.3(2) Design A Three (3) vertical 4 inch x 4 inch Fir posts shall be attached to the sign board. Three horizontal 2 inch x 4 inch Fir braces shall be attached to the back of the sign board, one each on the top, the bottom, and in the middle. Attachment of posts and bracing shall meet with the approval of the Engineer. 8-30.3 Installation Fasten two (2) vertical 4 inch x 6 inch Fir posts evenly spaced at the back of the sign board. Posts shall be of break-away design with no more than 12.25 square inches of drilled shear area at a point 2 inches above the ground, or as directed by the Engineer. Attachment of posts and bracing shall meet with the approval of the Engineer. 8-30.4 Measurement Project signs will be measured by the installed and maintained unit. Failure of the Contractor to adequately maintain the project signs, as determined by the Engineer, shall be deemed noncompliance with this Specification. 8-30.5 Payment Payment will be made in accordance with Section 1-04.1, for the following bid item when included in the Proposal: The unit contract price per each for Project Sign constitutes complete compensation for furnishing all labor and materials for fabrication, installation and maintenance of project sign(s) for the life of the project and removal and delivery of sign(s) back to the City Shops upon project completion. Failure to adequately maintain and project signs to the City Maintenance Shop shall be deemed reasonable grounds for the Engineer to adjust the payment made under this bid item. 8-33 TREE REMOVAL FOR CONSTRUCTION IMPROVEMENTS SECTION 8-33 IS SUPPLEMENTED BY ADDING THE FOLLOWING: Kensington Drainage Improvements/Holcomb 8 - 18 February 14, 2022 Project Number: 18-3019 8-33.1 Description This work shall consist of cutting and removal of those trees and stumps shown on the plan sheets that may be encountered during construction. The contractor shall cut and transport trees to an approved off-site location. All stumps will be grubbed and disposed of by the Contractor off-site. Contractor shall avoid disturbing any overhead utilities encountered. 8-33.4 Measurement Remove Existing Trees shall be measured per each. Trees are defined as trees 12 or larger DBH (diameter breast height, defined as 4 -0 above ground). Smaller diameter tress requiring removal shall be considered incidental to the clearing and grubbing bid item. 8-33.5 Payment The Contractor shall include all cost associated with the above referenced in the unit contract price for the following bid items as required: The unit contract price for Remove Existing Trees per each shall be full pay for all labor, materials, tools and equipment necessary for but not limited to, cutting, excavation, stump removal, hauling from site, backfill and compaction, regrading existing ditch as required by the Engineer, and cleanup as shown on the plans and described in the specifications. Clearing and Grubbing shall be paid for under bid item 1005. Kensington Drainage Improvements/Holcomb 9 - 1 February 14, 2022 Project Number: 18-3019 DIVISION 9 – MATERIALS 9-03 AGGREGATES 9-03.12 Gravel Backfill SECTION 9-03.12(3) IS REVISED BY DELETING THE GRAVEL SPECIFICATION AND REPLACING IT WITH THE FOLLOWING: 9-03.12(3) Gravel Backfill for Pipe Zone Bedding Pipe bedding shall be 5/8 inch minus crushed rock. Pea gravel is not allowed. All material shall conform with the following gradation: Sieve Size Passing 3/4 Inch 100% 5/8 Inch 95 - 100% 1/4 Inch 45 - 65% US No. 40 6 - 18% US No. 200 7.5 max. % % Fracture 75 min. Sand Equivalent 40 min. L.A. wear 500 rev. 35 percent max., degradation 25 percent min. Free from wood waste, bark and other deleterious material. 9-03.14 Borrow SECTION 9-03.14(1) IS DELETED AND REPLACED WITH THE FOLLOWING: 9-03.14(1) Gravel Borrow Gravel Borrow material shall consist of pit-run granular material conforming to the following gradation: Sieve Size Percent Passing 3 Inch* 100 3/4 Inch 65 - 100 U.S. No. 4 25 - 70 U.S. No. 10 10 - 50 U.S. No. 40 0- 30 U.S. No. 200 0 - 5 Sand equivalent 50 min. The maximum passing the U.S. No. 200 sieve is limited to five percent (5%) based on the minus #4 inch fraction. Sieve analysis shall be used to verify that this requirement is met. Recycled materials such as broken concrete or asphalt, shall not be allowed unless specifically authorized in advance by the Engineer. Kensington Drainage Improvements/Holcomb 9 - 2 February 14, 2022 Project Number: 18-3019 Where additional materials are required to formulate the street sub- base to the cross section denoted in the plans, said additional material shall be Gravel Borrow. * The maximum size of stone for geosynthetic reinforced walls or slopes shall be 100 percent passing 1 1/4 inch square sieve and 90 to 100 percent passing 1 inch square sieve. All other sieve values continue to apply. SECTION 9-03.17 IS DELETED AND REPLACED WITH THE FOLLOWING: 9-03.17 Foundation Material Class I and Class II Foundation Material Class I and Class II shall be used to replace unsuitable material removed from unstable pipe trench bottoms. Foundation Material Class I and Class II shall conform to the following gradations: Percent Passing Sieve Size Class I Class II 6 square 100 --- 4 square --- 100 2 square 0 65-85 1 square --- 40-70 1/4 square --- 20 max All percentages are by weight. In addition, all rock shall be sound, angular ledge rock or recycled cement concrete pavement meeting the following specifications. Suppliers of recycled cement concrete products shall have a quality assurance program reviewed and approved by the City. Each rock or piece of recycled cement concrete pavement shall have at least two fractured faces. Adsorption 3% max (Corps of Engineers CRD-C-107) Accelerated Expansion (15) days 15% max Soundness 5% max loss Density (solid volume) 155 pcf min Specific Gravity 2.48 min 9-03.21 Recycled Material SECTION 9-03.21(1)D IS SUPPLEMENTED BY ADDING THE FOLLOWING: Kensington Drainage Improvements/Holcomb 9 - 3 February 14, 2022 Project Number: 18-3019 9-03.21(1)D Recycled Glass (glass cullet) Recycle glass (glass cullet) shall not be used for any purposes. 9-13 RIPRAP, QUARRY SPALLS, SLOPE PROTECTION, AND ROCK FOR EROSION AND SCOUR PROTECTION AND ROCK WALLS SECTION 9-13 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 9-13.8 Rock for Ditches Rocks for ditches shall meet the following requirements for grading: Sieve Size Percent Passing 12 95 to 100 6 40 to 60 3 10 to 20 3/4 0 to 5 9-14 EROSION CONTROL AND ROADSIDE PLANTING 9-14.2 Topsoil SECTION 9-14.2(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 9-14.2(1) Topsoil Type A Topsoil Type A (Compost Amended Planting Soil) shall consist of 50 67% sand and/or sandy loam and 33 50% composted organic material by volume. Total organic matter shall be at least 5% by dry weight for areas where turf will be installed, and at least 10% by dry weight for all other landscape areas. Organic matter shall be determined by Loss-on-Ignition test. Acceptable tests include the most current version of ASTM D2974 Test Methods for Moisture, Ash, and Organic Matter of Peat and Other Organic Soils, and TMECC 05.07A Loss-On-Ignition Organic Matter Method. Compost-Amended Planting soil shall not contain any viable seeds or roots capable of sprouting any State-listed noxious weed, or invasive root-propagating plants including but not limited to horsetail, ivy, clematis, knotweed, Scots broom, reed canary grass, Himalayan blackberry, etc. Soil found to contain these prohibited viable plant materials shall be removed and replaced at the Contractors expense. A. The soil shall meet the following requirements. 1. The mixed soil shall meet the following gradation: Kensington Drainage Improvements/Holcomb 9 - 4 February 14, 2022 Project Number: 18-3019 Screen Size * Percent Passing 2 inch 100 1 inch 99-100 5/8 90 100 1/4" 75-100 *Maximum particle length of 6 inches B. Shall have a pH range between 5.5 and 8.5. The pH shall be determined by soil test. C. Organic material shall consist of composted yard debris or organic waste material composted for a minimum of 3 months. Compost shall consist of 100% recycled content and meet all requirements for compost in Section 9-14.5(8) of the Standard Specifications. D. Submit a certified laboratory analysis from an accredited soils testing laboratory indicating the Material source and compliance with all planting soil and compost specifications to the Engineer or project Ecologist for approval no less than seven (7) days before delivery to the Project Site. The analysis shall be with a sample size of no less than 2 pounds. E. Site specific soil testing (after placement of material) may be required for projects requiring more than 50 cubic yards of compost-amended planting soil A Contractor provided accredited laboratory approved by the Engineer shall make recommendations for amendments required for optimum growth at no cost to the owner. The Contractor will be allowed five (5) Working Days to complete the testing from the time of written notice given by the Engineer. F. A sample of the compost amended planting soil shall be provided to the Engineer or project Ecologist in a 1-gallon re-closable bag at least seven (7) days prior to application. SECTION 9-14.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 9-14.2(4) Sandy Loam Sandy loam shall consist of soil having a maximum clay content of ten percent by weight. In addition, soil particles shall meet the following requirements for grading: Passing 1 inch sieve (square opening) ......... 100% Passing 1 mm sieve .................................. 80% minimum Passing 0.15 mm sieve .............................. 15% maximum SECTION 9-14.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 9-14.3 Seed Kensington Drainage Improvements/Holcomb 9 - 5 February 14, 2022 Project Number: 18-3019 Hydroseed: Seed shall be Blue Tag or certified quality. The Contractor shall deliver in unopened containers with mixture seed content and inert material content plainly marked on the outside of the container. Grasses used shall meet the following specifications: Mix A (Roadside and Erosion Control Grass): Weight Proportion Seed Mix A Ingredient Min. % Pure Seed Min. % Germination Max. % Weed Seed 40% Perennial Ryegrass 98% 90% 0.5% 40% Creeping Red Fescue 98% 85% 0.5% 10% Colonial Bentgrass 98% 90% 0.5% 10% White Dutch Clover (Pre-inoculated) 98% 90% 0.5% The Contractor shall submit to the Engineer the manufacturer's Certificate of Conformance for seed. A complete analysis of the seed shall be submitted to the City for approval including percent of pure seed, germination, other crop seed, inert and weed and the germination test date. The City reserves the right to reject any or all plant material at any time until final inspection or acceptance. The Contractor shall remove rejected plants immediately from site. The Contractor shall produce upon request sales receipt for all nursery stock and certificates of inspection. SECTION 9-14.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING: 9-14.4 Fertilizer Fertilizer for trees: Fertilizer shall consist of slow-release commercial fertilizer (6-10-8). Fertilizer for upland seeded areas: Lilly Miller or approved equal to provide the following nutrients: All areas which are seeded shall receive fertilizer of the following proportions and formulation: Total available Nitrogen ........... 16% of weight (of which 50% is derived from ureaform) Total available Phosphorous ..... 16% of weight Total available Potassium ......... 16% of weight Fertilizer for wetland seeded areas: All areas which are seeded in wetlands or in detention ponds shall receive fertilizer of the following proportions and formulation: Total available nitrogen ........... 21% (Analyzed as N) Available phosphorous ............. 0% Kensington Drainage Improvements/Holcomb 9 - 6 February 14, 2022 Project Number: 18-3019 (Analyzed as P205) Available potassium ................ 10% (Analyzed as K20) Above percentages are proportioned by weight. The Contractor shall deliver fertilizer to the site in original unopened containers bearing manufacturer's chemical analysis, name, trade name, trade mark, and indication of conformance to state and federal laws. Instead of containers, fertilizer may be furnished in bulk with certificate indicating the above information. 9-14.5 Mulch and Amendments SECTION 9-14.5(8) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 9-14.5(8) Compost Compost shall not contain any sawdust, straw, green or under- composed organic matter, under-sterilized manure or toxic or otherwise harmful materials. SECTION 9-14.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 9-14.5(10) Wood Cellulose Fiber Wood cellulose mulch shall be specially processed 100 percent virgin wood fiber containing no growth or germination-inhibiting ingredients. It shall be manufactured in such a manner that after addition and agitation in slurry tanks with water, the fibers in the material will become uniformly suspended to form a homogenous slurry. When hydraulically sprayed on the ground, the material shall allow the absorption and percolation of moisture. Wood cellulose fiber shall be Weyerhaeuser Silva-Fiber Plus w/Tackifier or approved equal. Organic matter content shall be at least 93 percent on an oven-dry basis as determined by ASTM D 586. The moisture content shall be no more than 15 percent as determined by oven dried weight. Each package of the cellulose fiber shall be marked by the manufacturer to show the dried weight content. 9-14.7 Plant Materials 9-14.7(1) Description SECTION 9-14.7(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 9-14.7(1)A Street Trees Kensington Drainage Improvements/Holcomb 9 - 7 February 14, 2022 Project Number: 18-3019 The following table provides both the list of approved street tree species, and some of the characteristics associated with each street tree species at maturity: Common Name Scientific Name Height (feet) Width (feet) Shape Min. Spacing (feet) Small Street Trees For planting under powerlines 30’ or less Trident Maple Acer buergeranum 20 20 Round, low spreading 30 Flame Maple Acer ginnala ‘Flame’ 20 20 Round w/ spreading low branches 30 Flamingo Box Elder Acer negundo ‘Flamingo’ 20 15 Oval to round 25 Apollo Maple Acer saccharum 25 10 Narrow to columnar 20 Tatarian Maple Acer tataricum 25 20 Oval to round, often low branched 30 Lavalle Hawthorn Crataegus x lavallei 28 20 Irregular vase shaped 30 Washington Hawthorn Crataegus phaenopyrum 25 20 Broadly oval to round 30 Golden Desert Ash Fraxinus excelsior ‘Aureafolia’ 20 18 Rounded, compact 30 Leprechaun Ash Fraxinus pennsylvanica ‘Johnson’ 18 16 Dense, compact, round 25 Amur Maackia Maackia amurensis 25 20 Vase shaped becoming round 30 Golden Raindrops Crabapple Malus transitoria ‘Schmidt cutleaf’ 20 15 Upright, vase shaped 25 Red Barron Crabapple Malus ‘Red Barron’ 18 8 Narrow, columnar 20 Red Jewel Crabapple Malus ‘Jewelcole’ 15 12 Upright, pyramidal 25 Tschonoskii Crabapple Malus tschonoskii 28 14 Upright, narrowly oval 25 Cascade Snow Cherry Prunus ‘Berry’ 25 14 Upright, spreading 25 Amanogawa Cherry Prunus serrulata ‘Amanogawa’ 20 6 Columnar, fastigiate branches 20 Red Cascade Mountain Ash Sorbus Americana ‘Dwarfcrown’ 18 8 Compact oval 20 Fragrant Snowbell Styrax obassia 25 15 Pyramidal to upright narrow oval 25 Ivory Silk Japanese Syringa reticulata ‘Ivory Silk’ 20 15 Upright spreading becoming round 25 Medium Street Trees Plant when powerlines are not present 30’ to 45’ trees Armstrong Maple Acer rubrum ‘Armstrong’ 45 15 Narrow, upright columnar 25 Queen Elizabeth Maple Acer campestre ‘Evelyn’ 35 30 Upright, becoming round 40 Sensation Box Elder Acer negundo ‘Sensation’ 30 25 Rounded 35 Pacific Sunset Maple Acer truncatum x Acer plantanoides ‘Warrenred’ 30 15 Upright spreading, rounded crown 25 Frans Fontaine Hornbeam Carpinus betulus ‘Frans Fontaine’ 30 15 Columnar 25 American Hornbeam Carpinus caroliniana 25 25 Oval 35 Tricolor Beech Fagus sylvatica ‘Roseo – Marginata’ 30 20 Pyramidal when young, rounding w/ age 30 Raywood Ash Fraxinus oxycarpa ‘Raywood’ 35 25 Oval, dense crown 35 Imperial Honeylocust Gleditsia triacanthos ‘Impcole’ 35 35 Rounded 45 Kensington Drainage Improvements/Holcomb 9 - 8 February 14, 2022 Project Number: 18-3019 Medium Street Trees Plant when powerlines are not present 30’ to 45’ trees Galaxy Magnolia Magnolia ‘Galaxy’ 30 15 Pyramidal to oval 25 Edith Bogue Southern Magnolia Magnolia grandiflora ‘Edith Bogue’ 30 15 Pyramidal tight 25 American Hophornbeam Ostrya Virginiana 40 25 Upright oval 35 Spire Cherry Prunus x hillieri ‘Spire’ 30 10 Upright columnar, narrowly vase shaped 20 Columnar Sargent Cherry Prunus sargentii ‘Columnaris’ 35 15 Upright columnar, narrowly vase shaped 25 Edgewood Pear Pyrus calleryana x betulaefolia ‘Edgewood’ 30 25 Rounded 35 Capital Pear Pyrus calleryana ‘Capital’ 35 12 Columnar 20 Chanticleer Pear Pyrus calleryana ‘Glen’s Form’ 40 15 Columnar, narrowly pyramidal 25 Crimson Spire Oak Quercus alba x Quercus robur ‘Crimschmidt’ 45 15 Columnar, tightly fastigiated 25 Skyrocket Oak Quercus robur ‘Fastigiata’ 45 15 Narrow, fastigiated 25 Musashino Zelkova serrata ‘Musashino’ 45 20 Very narrow, upright vase shaped 30 9-14.8 Stakes, Guys, and Wrapping SECTION 9-14.8 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION: 9-14.8(1) Tree Ties Tree ties shall be patent Tre-Ties sufficient in size and number to adequately support the trees as determined by Quentin Poil, Nursery Supervisor at 253-856-5127. 9-16 FENCE AND GUARDRAIL 9-16.1 Chain Link Fence and Gates SECTION 9-16.1(1)B IS DELETED AND REPLACED WITH THE FOLLOWING: 9-16.1(1)B Chain Link Fence Fabric Chain link fabric shall consist of 9 gage wire (0.148-inch diameter) for all fences unless specified otherwise. The fabric wire shall be: Galvanized steel wire conforming to ASTM A 392. Galvanizing shall be Class I performed by the hot dip process. The wire shall be woven into approximately 2-inch diamond mesh. The width and top and bottom finish of the fabric shall be as shown in the plans. 9-28 SIGNING MATERIALS AND FABRICATION SECTION 9-28.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING: Kensington Drainage Improvements/Holcomb 9 - 9 February 14, 2022 Project Number: 18-3019 9-28.1 General All signs shall be reflectorized except for City Project Signs. ALL PERMANENT SIGNS, EXCEPT NO PARKING ANYTIME SIGNS SHALL HAVE VIP SIGNS AND CLASS A TEMPORARY DIAMOND GRADE RETRO- REFLECTORIZED SHEETING, UNLESS NOTED OTHERWISE IN THE PLANS. NO PARKING ANYTIME signs shall have engineer grade retro- reflectorized sheeting. 9-28.14 Sign Support Structures SECTION 9-28.14(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING: 9-28.14(2) Steel Structures and Posts Truss chords, struts, and diagonals, end posts, and end post struts and diagonals for sign bridge structures and cantilever sign structures shall conform to either ASTM A 36 or ASTM A 53 Grade B Type E or S. The nominal pipe diameter and the pipe wall thickness shall be as specified in the plans or Standard Plans. All other structural steel for sign bridge structures and cantilever sign structures shall conform to ASTM A 36. Truss member connection hardware shall conform to Section 9-06.5(3). Pipe members for bridge mounted sign brackets shall conform to ASTM A 53 Grade B Type E or S, and shall be Schedule 40 unless otherwise specified. All other structural steel for bridge mounted sign brackets shall conform to ASTM A 36. U bolts, and associated nuts and washers, shall be stainless steel conforming to Section 9-28.11, and shall be fabricated hot. Anchor rods, nuts and washers for sign bridge structure foundations shall conform to Section 9-06.5(4). Anchor rods for cantilever sign structure foundations shall conform to ASTM F 1554 Grade 104, including the appropriate supplemental requirements for grade and manufacturers identification, and charpy impact testing (15 foot- pounds minimum at 40F). Nuts and washers for cantilever sign structure foundations shall conform to AASHTO M 291 Grade DH and AASHTO M 293, respectively. Anchor rods for sign bridge structures and cantilever sign structures shall be galvanized after fabrication a minimum of 1-0 at the exposed end in accordance with AASHTO M 232. Anchor rod templates shall conform to ASTM A 36, but need not be galvanized. Steel sign structures and posts shall be galvanized after fabrication in accordance with AASHTO M 111, unless noted otherwise in the plans. All bolts, nuts, and washers shall be galvanized after fabrication in accordance with AASHTO M 232. Unless otherwise specified in the plans or Kent Special Provisions, metal surfaces shall not be painted. Minor fabricating and modifications necessary for galvanizing will be allowed if not detrimental to the end product as determined by the Kensington Drainage Improvements/Holcomb 9 - 10 February 14, 2022 Project Number: 18-3019 Engineer. If such modifications are contemplated, the Contractor shall submit to the Engineer, for approval six copies of the proposed modifications, prior to fabrication. Kensington Drainage Improvements/Holcomb A - 1 February 14, 2022 Project Number: 18-301a KENT STANDARD PLANS The following Kent Standard Plans supplement all other plans, which have been prepared for this project and are considered to be a part of the project plans. SEWER 4-5 Manhole Grade Ring, Safety Steps & Ladder 4-13 Adjustment of New and Existing Utility Structures to Finish Grade STORM 5-2 Catch Basin Type II 5-3 Misc. Details for Drainage Structures 5-4 20x24 Catch Basin Frame 5-5 20x24 Vaned Grate 5-8 18x24 Solid Catch Basin Cover 5-9 20x24 Solid Catch Basin Cover 5-15 Debris Cage 5-19 Beveled End Pipe Section 5-20 Trash Screen 5-31 Filter Fabric Fence 5-37 Storm Drain Markers STREET 6-71a Roadway Barricades (sheet 1 of 2) 6-74 Typical Lane Markings 12" MIN. 12" MIN. 3" 6 1/2" 3 1/2" SEE NOTE 4-F:=:l MIN. DROP RUNG HANDHOLD MANHOLE STEP 12" MIN. 6" 9 1/2" SEE NOTE 4 MIN. MANHOLE STEP GALVANIZED DROP RUNG MANHOLE STEP 1" RADIUS 3" 12" 11 3/4" MIN. x a CENTER TO CENTER 6" SEE NOTE 4 a, SEE NOTE 5 GALVANIZED PREFABRICATED LADDER 12" 11 1/2" c0 Ca 12" SEE NOTE 4 11 3/4" MIN. CENTER TO CENTER 9 1/8" FOR STEP 6 1/8" FOR HANDHOLD 6" FOR STEP 3" FOR HANDHOLD SEE NOTE 5 POLYPROPYLENE DROP RUNG MANHOLE STEP POLYPROPYLENE PREFABRICATED LADDER NOTES: 1. MANHOLE STEPS CONFORMING TO SECTION R, ASTM C-478. AASHTO M-199 REQUIREMENTS AND REQUIREMENTS OF ASTM D-4101 FOR POLYPROPYLENE AND 5 ASTM A-615 FOR 1/2" GRADE 60 DEFORMED REINFORCING BAR FOR POLYPROPYLENE 24" 5" STEPS, AND ALL WISHA AND OSHA SPECIFICATIONS, ARE ACCEPTABLE PROVIDED THEY ARE PRE -APPROVED BY THE ENGINEER. _ v 2. PREFABRICATED LADDERS ARE TO BE #7 GALVANIZED SMOOTH STEEL. #4 BAR 1" CLEARANCE 3. MANHOLE PREFABRICATED LADDER STEPS SHALL BE PARALLEL OR APPROXIMATELY RADIAL AT THE OPTION OF THE MANUFACTURER, EXCEPT THAT ALL STEPS IN ANY MANHOLE SHALL BE THE SAME. GRADE RING 4. PENETRATION OF OUTER WALL BY A STEP LADDER OR LADDER LEG IS NOTE: THIS PLAN IS NOT A LEGAL ENGINEERING DOCUMENT PROHIBITED. USE FLANGED END FOR BUT AN ELECTRONIC DUPLICATE. THE ORIGINAL, SIGNED BY BOLTING TO WALL. THE ENGINEER AND APPROVED FOR PUBLICATION IS KEPT ON 5. EMBED FOOT OF GALVANIZED �V F REf FILE AT THE CITY OF KENT. A COPY MAY BE OBTAINED UPON PREFABRICATED LADDER IN CONCRETE �F WASh,I REQUEST. IN POURED OR CHANNELED FLOOR. CITY OF KENT ENGINEERING DEPARTMENT 6. MANHOLE STEPS OR LADDERS ARE NOT REQUIRED WHEN THE COVER TO KENT MANHOLE GRADE RING, BOTTOM OF MANHOLE IS LESS THAN 4'. 10 38296 �' W,,.„INGTON SAFETY STEPS & LADDER � � 0� IST- �S's10NAL DESIGNED COK SCALE NONE STANDARD PLAN DRAWN- COK CHECKED COK DATE 12/2019 5 4-5 ENGINEER APPROVED MANHOLE MAY INCLUDE OTHER UTILITY MANHOLE \8" MIN. HMA PER A KDCS 6.16, OR 8" MIN. DEPTH CONC. l SAWCUT LINE, 6' DIAMETER SEE NOTE 5 TYPICAL PLAN VIEW OF MANHOLE (OR CB) IN ASPHALT AREA 8" MIN. HMA PER KDCS 6.16, OR 8" MIN. DEPTH CONC. VALVE BOX AND LID ARE FLUSH WITH EXISTING SEE NOTE 5 GRADE 8" MIN. HMA PER KDCS SEE NOTE 3 6.16, OR 8" MIN. DEPTH CONC. OR THICKNESS OF ROADWAY, WHICHEVER 10 IS GREATER 14 SEE NOTE 5 d d VALVE BOX IN ASPHALT AREA 6' DIAMETER 6' DIAMETER OR 6'SQUARE SEE NOTE 3 1 EXISTING A.C. PAVEMENT EXISTING GRADE da d. MANHOLE OR CATCH BASIN IN UNIMPROVED AREA VALVE BOX, LID AND CONC. COLLAR SHALL BE FLUSH WITH EXISTIIN,G GRADE I I I i 8" MIN. HMA PER KDCS 6.16, OR 8" MIN DEPTH CONC. NOTES: 1. ADJUSTMENT OF UTILITY STRUCTURES SHALL BE PER KENT OR WSDOT SPECIAL PROVISION SECTION 7-05.3(1), AS DIRECTED BY CITY OF KENT. 2. ALL ADJUSTMENTS SHALL BE COMPLETED AFTER FINISHED PAVING. 3. SURFACE SEAL AT MATCHLINE SHALL BE AR-4000. 4. VALVE IN UNIMPROVED AREAS SHALL HAVE A MARKER. 5. FILL ANY VOIDS OR DISTURBED AREAS BELOW CASTING WITH QUICK SETTING CEMENT CONCRETE. NO CALCIUM ACCELERANT PERMITTED. CONCRETE SHALL EXTEND A MIN. OF 2" ABOVE jV F RE!t' CASTING FLANGE. pF WAgk1 38296 �4 FOG TITE VALVE POST MARKER, 60# NOTE 4 42" 3' I a 12" a a SEE NOTE 5 d VALVE BOX IN UNIMPROVED AREA AL CATCH BASIN FRAME AND GRATE. (SEE STANDARD PLANS 5-5, 5-6, 5-7a AND NOTES: 5-7b AND 5-8) FOR SOLID LOCKING CIRCULAR FRAME 1. CATCH BASINS TO BE CONSTRUCTED IN AND COVER SEE WSDOT ACCORDANCE W/ AASHTO M 199, (ASTM C 478, STANDARD PLAN B-30.70 AND ASTM C 890) UNLESS OTHERWISE SHOWN X HANDHOLD ON PLANS OR NOTED IN THE WSDOT STD. SPECS. < RECTANGULAR ADJUSTMENT - SECTION OR CIRCULAR 2. HANDHOLDS IN RISER OR ADJUSTMENT SECTION coADJUSTMENT SECTION SHALL HAVE 3" MIN. CLEARANCE. STEPS IN FLAT SLAB TOP CATCH BASIN SHALL HAVE 6" MIN. CLEARANCE. a GASKET PIPE SHALL NOT PROTRUDE NO STEPS ARE REQ'D WHEN 'B' IS 4' OR LESS. ,zL, BETWEEN 48", 54", 60", MORE THAN 2" INTO z RISERS (TYP.) 72", 84" OR 96" STRUCTURE 3. THE BOTTOM OF THE PRECAST CATCH BASIN MAY a BE SLOPED TO FACILITATE CLEANING. � MORTAR (TYP.) 0 4. KNOCKOUTS SHALL HAVE A WALL THICKNESS OF STEPS OR 2" MINIMUM TO 2.5" MAXIMUM. PROVIDE A 1.5" a LADDER INSTALL MANHOLE MINIMUM GAP BETWEEN THE KNOCKOUT WALL � (SEE STANDARD ADAPTER, 'SAND COLLAR' FOR PVC AND THE OUTSIDE OF THE PIPE. AFTER THE PIPE _ PLAN 4-5) — AND HDPE PIPES OR IS INSTALLED, FILL THE GAP WITH JOINT N a AS REQUIRED BY MORTAR IN ACCORDANCE WITH WSDOT m r OTHER PIPE TYPES STANDARD SPECIFICATION 9-04.3. 5. ALL BASE REINFORCING STEEL SHALL HAVE A z N x REINFORCING STEEL (TYP.) MIN. YIELD STRENGTH OF 60,000 PSI & BE PLACED IN THE UPPER HALF OF THE BASE WITH N r, CRUSHED SURFACING TOP COURSE PIPE 1" MIN. CLEARANCE. / ZONE BEDDING 61f 12" 6. PICK HOLES, CRACKS AND ANY OTHER JOINTS SHALL BE FINISHED GROUTED TO PROVIDE A WATERTIGHT STRUCTURE. ( CORRUGATED POLYETHYLENE STORM SEWER PIPE (WSDOT STD. SPEC. 9-05.20) (2) (WSDOT STD. SPEC. 9-05.12(1)) CATCH BASIN DIMENSIONS (3 (WSDOT STD. SPEC. 9-05.12(2)) BASE REINFORCING PIPE ALLOWANCES CATCH WALL BASE MAXIMUM MINIMUM DISTANCE STEEL inz/ft. IN EACH DIRECTION CATCH PIPE MATERIAL WITH MAXIMUM INSIDE DIAMETER BASIN THICKNESS THICKNESS KNOCKOUT SIZE BETWEEN BASIN ALL SOLID PROFILE DIA. KNOCKOUTS SEPARATE INTEGRAL DIAMETER CONCRETE METAL CPSSP WALL WALL BASE BASE (1) PVC (2) PVC 3� 48" 4" 6" 36" 81, 0.23 0.15 48" 24" 30" 24" 27 30" 54" 4.5" 811 42" 8" 0.19 0.19 54" 30" 36" 30" 271' 36" 60" 5" 811 48" 8" 0.25 0.25 60" 36" 42" 36" 36" 42" 72" 6" 811 60" 12" 0.35 0.24 721' 42" 54" 42" 36" 48" 84" 8" 12" 72" 12" 0.39 0.29 84" 54" 60" 5411 36" 48" 96" 8" 12" 84" 12" 0.39 0.29 96" 60" 72" 1 60" 3 ' 4811 NOTE: THIS PLAN IS NOT A LEGAL ENGINEERING DOCUMENT BUT AN DUPLICATE.ELECTRONIC SIGNED Y H ENGINEER AND APPROVED FOR PUBLICATION IS KEPT ON FILE TTHE CITY OF �� OF WA,q�l �� KENT. A COPY MAY BE OBTAINED UPON REQUEST. DQ CITY OF KENT ENGINEERING DEPARTMENT KENT WA•HINGTON CATCH BASIN TYPE II O�</ 38296 � IST DESIGNEDCOK SCALE NONE STANDARD PLAN DRAWN COK �gIOIVAL � DATE 9/2020 C — n J L CHECKED COK � ENGINEER APPROVED 20" x 24", OR 24" DIAM. 2" CLR TYP. 20" x 24", OR 24" DIAM. 2" CLR TYP. #6 BARS @ 7" CENTERS BOTTOM FACE WITH 1" MIN. COVER S 6" OR 12" D. D , 2" TYP N 96" TOP SLAB 1" MIN. 2 1/2" MAX. ONE #3 BAR HOOP FOR 6" TWO #3 BAR HOOPS FOR AS AN ACCEPTABLE ALTERNATIVE TO REBAR, WIRE MESH HAVING A MINIMUM AREA OF 0.12 SQUARE INCHES PER FOOT MAY BE USED FOR ADJUSTMENT SECTIONS. #5 BARS @ 6" CENTERS BOTTOM FACE WITH 1" MIN. COVER 2" TYP. 72" TOP SLAB 1" MIN. 2 1/2" MAX. #4 BARS @ 6" CENTERS BOTTOM FACE WITH 1" 2" CLR. MIN. COVER TYP. i 20" x 24", OR it 24" DIAM. 20" ~{ 2" TYP. 48" & 54" TOP SLAB 34" ONE #3- T BAR HOOP 4" S" CIRCULAR ADJUSTMENT SECTION NOTES: 1. SLAB OPENING SHALL BE 24" X 20" FOR RECTANGULAR AND 24" DIAMETER FOR ROUND. �� OF WAS 2. SEE STANDARD PLAN 4 5 FOR STEP, LADDER AND GRADE RING. U 3. ONLY ONE STYLE OF CATCH BASIN STEPS MAY BE USED IN A CATCH 38296 BASIN. DO NOT MIX STYLES. 0� ��I(,YI$T ��q4 �S�IO N AT i RECTANGULAR ADJUSTMENT SECTION �`� •LR 2g„ 46" CONVERSION RISER TYPICAL ORIENTATION FOR ACCESS AND STEPS 5/8"-11 NC A A 29 1/4" L 26" 24 1/4" 22 1/2" -41� TOP VIEW 1 5/8" TYP. � 20 1/4" �7/8" TYP. 1 1/4" 1 5/8" TYP. MIN. 3 3/41L[\ �Lj __L A 4 1/2" 11 2 1/2" I 18 1/2"� 3/4" 22" 25 1/4" SECTION A -A NOTES: 1. MATERIAL USED FOR THE FRAME SHALL BE CAST IRON ONLY. (PER ASTM A48 CL30 H-20 LOADING). 2. TOP OF FRAME SHALL BE ADJUSTED EVEN WITH ROADWAY SECTION. NOTE: THIS PLAN IS NOT A LEGAL ENGINEERING DOCUMENT BUT AN ELECTRONIC DUPLICATE. THE ORIGINAL, SIGNED BY THE ENGINEER AND APPROVED FOR PUBLICATION IS KEPT ON FILE AT �� OF WASh,I �� THE CITY OF KENT. A COPY MAY BE OBTAINED UPON REQUEST. CITY OF KENT ENGINEERING DEPARTMENT KENT 38296 20 x 24 W-HI.uru. CATCH BASIN FRAME � IST �'�± DESIGNED CO: SCALE NONE STANDARD PLAN DRAWN COK �S's10NAL CCHECKED COK DATE 12A2019 — APPROVED ENGINEER I -_I o To ILI TOP VIEW 24" 1 1/4" 1 5/8'.71 r _ DIRECTION OF FLOW \_ 3 1/2" R. 5/16" R. FRONT VIEW NOTES: 1. PROVIDE FRAME SHOWN IN STANDARD PLAN 5-4. 2. PROVIDE 2-5/8" DIAMETER STAINLESS STEEL ALLEN TYPE BOLTS COUNTER SUNK FLUSH WITH COVER. 3. GRATE SHALL BE STAMPED "DUMP NO POLLUTANTS", "OUTFALL TO STREAM". 4. ALL LETTERING SHOWN SHALL BE 1/2" AND SHALL BE RECESSED UNLESS OTHERWISE INDICATED. 5. DUCTILE IRON ASTM A-536 GRADE 80-55-06 H-20 RATED. 6. GRATE SHALL BE LOCKING. 7. BI-DIRECTIONAL VANED GRATES ARE REQUIRED WHEN LOCATED IN A LOW -SPOT. -1 5/8" 2 1/4" 1 5/8"' PARTING LINE VANE DETAIL �-1 5/8" TYP. 1 3/8" TYP. INSET SOCKET 15/16" �3/4" T 5/8"-11 NC-2A STAINLESS STEEL SECURING BOLT T2" �--1/2" --� 5/8 SLOT DETAIL SLOT FORMED AND RECESSED FOR 5/8" - 11 NC x 2" S.S. SOCKET HEAD (ALLEN HEAD) CAP SCREW. �FFRE)- �� of WA U � 38296 �I SmF]R�� �SSIONAL ���1 23 3/4" L PROVIDE 5/8" DIA. BOLTS & TAP FRAME FOR LOCK DOWN LID PLAN SECTION B-B 1/2" INSET HEX SOCKET 15/16" 5/8"-11 NC-2A STAINLESS STEEL SECURING BOLT 3 1/2" 3/ 4 3/4" 3/4 3/4" 4" 1 1/2" 5/8" _ 1/2" DIA. 3/4" DIA. HANDLE HOLE 5/8' SECTION C-C NOTES: 1. WHEN SPECIFIED ON THE APPROVED PLANS, THE SOLID METAL COVER FOR CATCH BASIN SHALL BE FURNISHED IN PLACE OF AN 18"x24" GRATE. 2. RAISED DESIGNS OTHER THAN THE DIAMOND DESIGN SHOWN HEREON MAY BE USED IF APPROVED BY THE ENGINEER. COVERS IN WALKWAYS SHALL BE NON -SLIP. 3. CAST IN THE LETTERS "DRAIN" IN 2" RAISED LETTERS, 1/8" HIGH. 4. PROVIDE 2-5/8" DIAMETER STAINLESS STEEL ALLEN TYPE BOLTS COUNTER SUNK FLUSH WITH COVER. oFWA Y 5. FRAME: CAST IRON ASTM A48 CL30, COVER: DUCTILE IRON ASTM A 536 GR 80-55-06 H-20 RATED. 38296 11/16' _ 1/4" 1-3/16" DIA. SLOT 00 L M N _ c 1 1/8" SECTION D-D 24" L PROVIDE 5/8" DIA. BOLTS & TAP FRAME FOR LOCK DOWN LID PLAN NOTES: 1. WHEN SPECIFIED ON THE APPROVED PLANS, THE SOLID METAL COVER FOR CATCH BASIN SHALL BE FURNISHED IN PLACE OF A 20"X24" GRATE. 2. RAISED DESIGNS OTHER THAN THE DIAMOND DESIGN SHOWN HEREON MAY BE USED IF APPROVED BY THE ENGINEER. COVERS IN WALKWAYS SHALL BE NON -SLIP. 3. CAST IN THE LETTERS "DRAIN" IN 2" RAISED LETTERS, 1/8" HIGH. 4. TO BE USED WITH FRAME SHOWN IN STANDARD PLAN 5-4. 5. PROVIDE 2-5/8" DIAMETER STAINLESS STEEL ALLEN TYPE BOLTS COUNTER SUNK FLUSH WITH COVER. (SEE STANDARD PLAN 5-4 FOR BOLT -DOWN �FFRE)- CATCH BASIN FRAME). �� pF WA 6. FRAME: CAST IRON ASTM A48 CL30, COVER: DUCTILE IRON ASTM A 536 = �' GR 80-55-06 H-20 RATED. 38296 1/2" INSET HEX SOCKET 15/16" 5/8"-11 NC-2A STAINLESS STEEL SECURING BOLT 1 1/4" SECTION B-B 3 1/2" 3/ 4" 1 1/2" � 5/8" 1/2 DIA. 3/4" DIA. HANDLE71 HOLE 11/16' _ co 1/4" 1-3/16" DIA. SLOT ao L M N _ c 1 1/8" SECTION D-D LOWER BAND 3/4" DIAM. SMOOTH ROUND BARS EQUALLY SPACED. BARS SHALL BE WELDED TO UPPER & LOWER BANDS. PLAN EQUALLY SPACED INNER DIAMETER SEE TABLE BELOW CB INNER DIAM. 48" 58" 54" 65" 60" 72" 72" 86" 96" 114" 3/4" DIAM. SMOOTH ROUND BARS EQUALLY SPACED (4" O.C. MAX.) *NOTE: BARS OMITTED ON DRAWING pF WASgl 38296 �' �0)" ���I SmF]R�� �SSIONAL u, M 3/4" BAR DRILL HOLES FOR LOCK v LOWER BAND UPPER BAND 1/2" >IAM. BAR 1/2" PLATE ENTRY GATE DETAIL NOTES: 1. ALL STEEL IN PLATES, BARS AND BANDS SHALL CONFORM TO THE REQUIREMENTS OF ASTM A36. 2. DEBRIS CAGE SHALL BE HOT -DIP GALVANIZED IN ACCORDANCE WITH AASHTO M111 (ASTM A123). 3. ENTRY GATE SHALL BE LOCKABLE WITH A CITY OF KENT PADLOCK. END SECTION 1' MIN. 3 Q 1 a (TYP.) PIPE JOINT 1 METAL PIPE NOTES: 1. SIDE SLOPE SHALL BE WARPED TO MATCH THE BEVELED PIPE END. WHEN CULVERT IS ON SKEW, BEVELED END SHALL BE ROTATED TO CONFORM TO SLOPE. IF SLOPE DIFFERS FROM 3: 1, PIPE SHALL BE BEVELED TO MATCH SLOPE. 2. BEVELED END PIPE SHALL BE PRECAST CONCRETE PIPE OR DUCTILE IRON ONLY. THE PIPE TYPE SHALL BE CONSISTENT THE ENTIRE LENGTH OF ANY REQUIRED CULVERT OR TO THE NEAREST STRUCTURE PRIOR TO THE BEVELED OUTFALL. TONGUE END ON INLET END GROOVE END ON OUTLET END ENDS TO FIT ADJACENT PIPE SECTIONS ROUND EDGES PLAN END SECTION 1' MIN. 3 X Q1 a — — (TYP.) v ELEVATION CONCRETE PIPE NOTE: THIS PLAN IS NOT A LEGAL ENGINEERING DOCUMENT BUT AN ELECTRONIC DUPLICATE. THE ORIGINAL, SIGNED BY THE ENGINEER AND APPROVED FOR PUBLICATION IS KEPT ON FILE AT OF WASNI ) THE CITY OF KENT. A COPY MAY BE OBTAINED UPON REQUEST. CITY OF KENT �$ ENGINEERING DEPARTMENT • KENT BEVELED END PIPE SECTION 38296 � �' 0� �ISm�'�� �'�� DESI NED COK SCOK CALE NONE STANDARD PLAN SSIONAL ��� CHECKED COK IDATE 12A2019 5-19 APPROVED ENGINEER 3/4" DIAMETER GALVANIZED STEEL BAR (4) 1/4"x2"X8" GALVANIZED STEEL STRIPS. BEND AND WELD (2) 1/4"x3" GALVANIZED STEEL STRIPS TO FRAME, SPACE UNIFORMLY VERIFY ANGLE OF BEVEL WITH RACK 7 SUPPLIER. 1:1 OR GREATER REQUIRED 5" 0 + - - - VARIES STORM DRAIN PIPE (12"QJ OR LARGER) 0 6" MAX. SPACING DRILL THROUGH PIPE MATERIAL & STEEL STRIPS. BOLT WITH 1/2" S. STEL. HEX BOLTS 3/4" DIAMETER GALVANIZED STEEL BARS. WELD ENDS TO FRAME NOTES: 1. WELD AT ALL JOINTS. 2. SHOP DRAWINGS REQUIRED. 3. ALL STEEL IN PLATES, BARS AND BANDS SHALL CONFORM TO THE REQUIREMENTS OF ASTM A36. 4. DEBRIS CAGE SHALL BE HOT -DIP GALVANIZED IN ACCORDANCE WITH AASHTO M111 (ASTM A123). 5. GALVANIZING SHALL BE PER WSDOT STD. SPECIFICATION 9-05.16. NOTE: THIS PLAN IS NOT A LEGAL ENGINEERING DOCUMENT BUT AN ELECTRONIC DUPLICATE. THE ORIGINAL, SIGNED BY THE ENGINEER AND APPROVED FOR PUBLICATION IS KEPT ON FILE AT �� OF WASNI ) THE CITY OF KENT. A COPY MAY BE OBTAINED UPON REQUEST. CITY OF KENT �$ ENGINEERING DEPARTMENT • KENT TRASH SCREEN 38296 � �' 0� �ISm�'�� �'�� DESI NED COK COK SCALE NONE STANDARD PLAN SsIONAL ��� CHECKED COK IDATE 12A2019 _ r�L O APPROVED ENGINEER WIRE FABRIC NEWLY GRADED OR DISTURBED SIDE SLOPE - 2 2 �\ FLOW 211 NATIVE BACKFILL MATERIAL OR 3/4"-1.5" WASHED GRAVEL 3" Ito MATERIAL z N 1 1/2" WASHED ROCK 6"x6" JOINTS IN FILTER FABRIC TRENCH SHALL BE SPLICED AT POSTS. USE STAPLES, WIRE RINGS, u OR EQUIVALENT TO ATTACH FABRIC TO POSTS. SECTION A -A 2"x2"x14 GAUGE WELDED WIRE FABRIC OR FILTER FABRIC MATERIAL WIRE RINGS EQUAL (IF 180# EXTRA STRENGTH FABRIC MIRAFI 100X OR QUIVALENT A �j (TYP) IF USED MAY ELIMINATE WIRE FABRIC) i I ICI III I STEEL OR 2x4 A J WOOD POSTS I J I J 6' O.C. INSTALLATION NOTES: ELEVATION 1. FILTER FABRIC FENCE SHALL BE REMOVED WHEN THEY HAVE SERVED THEIR USEFUL PURPOSE AFTER THE UPSLOPE AREA HAS BEEN PERMANENTLY STABILIZED. THE NEWLY DISTURBED AREAS RESULTING FROM FILTER FABRIC REMOVAL SHALL BE IMMEDIATELY SEEDED AND MULCHED OR STABILIZED AS APPROVED BY THE ENGINEER. 2. FILTER FABRIC FENCES SHALL BE INSPECTED NOTE: THIS PLAN IS NI IMMEDIATELY AFTER EACH RAINFALL AND AT RE� AN ELECTRONIC DUPLI LEAST DAILY DURING PROLONGED RAINFAL ENGINEER AND APPRO' ��oF h� � THE CITY OF KENT. A ANY REQUIRED REPAIRS SHALL BE MADE I� IMMEDIATELY. � 3. REMOVE SEDIMENT WHEN IT REACHES 1/3 FENCE HEIGHT. KENT 4. INSTALL THE SILT FENCE FIRST. AFTER w.�� .oro. �,� � 38296 � ,��' THE SILT FENCE HAS BEEN INSTALLED, O� �ISmF]g� �� DESIGNED cOK scnu CONSTRUCT BERM AND TRENCH. �SSIONAL CHECKED�DDRAWN COK COK DATE APPROVED DUMPIV6 - --------------------------- <•} • . - --- ---- --- --- PUBLIC CATCH BASIN MARKER a M 40 • s f PRIVATE CATCH BASIN MARKER NOTE: 1. CATCH BASIN MARKER SHALL BE AFFIXED WITH MANUFACTURER'S EPDXY IN DRY WEATHER, 40 DEGREES AND WARMER. IF CURB EXISTS, MARKER IS PLACED ON TOP OF CURB. IF RAISED EDGE PAVEMENT, MARKER PLACEMENT IS ON THE WEDGE. IF NEITHER EXIST, MARKER WILL BE PLACED ON SIDE LEAST EXPOSED TO TRAFFIC. NOTE: THIS PLAN IS NOT A LEGAL ENGINEERING DOCUMENT BUT AN ELECTRONIC DUPLICATE. THE ORIGINAL, SIGNED BY THE �� ��Y ENGINEER AND APPROVED FOR PUBLICATION IS KEPT ON FILE AT �� OF WAtighrl �� THE CITY OF KENT. A COPY MAY BE OBTAINED UPON REQUEST. CITY OF KENT ENGINEERING DEPARTMENT • KENT STORM DRAIN MARKERS 8296 WA�HINGTON 3� �' ol%DESIGN/ ��1 OOK STF]g� �'�� DRAWN ED COK SCALE NONE STANDARD PLAN SSIONAL �CHECKED COK JDATE 12A2019 G Z APPROVED ENGINEER J J 45° VARIES TYPE OF 6" SUPPORT VARIES M TWO SS BOLTS PER JOINT —� ALL HOLES PRE -PUNCHED 2" TELESPAR 14 GAUGE POST 3-1/2" STAINLESS STEEL 3/8" BOLT ASSEMBLY — 1' (TYP.) TYPE I BARRICADE SEE SIGN FOUNDATION DETAIL 6-82a 7 GAUGE GALVANIZED 30" 2 1/2"x2 1/2" BASE CTDTDC KlnTCC- - RED & WHITE - REFLECTORIZED SANDBAGS FOR ADDED STABILITY I■� MOVABLE (TEMPORARY) TYPE III BARRICADE BOARDS: 8"xl" - HIP PRIZ SHEETING RED ON WHITE ELECTRIC CUT SHEETING MATERIAL 0 N Z_ J° O - N p — VARIES 2' MIN. N CORNER BOLTS BASE TO POSTS FIXED (PERMANENT) TYPE III BARRICADE - SLANT DOWNWARD, RIGHT OR LEFT, IN DIRECTION TRAFFIC WILL PASS. SLANT BOTH DIRECTIONS FROM MIDDLE IF TRAFFIC PASSES BOTH ENDS. WIDTH 6" EXCEPT 4" IF RAILS ARE LESS THAN 3' LONG. - SLANT DOWNWARD TO MIDDLE AT END OF CLOSED ROAD. -SEE MUTCD SECTION 6F.63 r�FRE OF WAs�l c i TYPE II BARRICADE NOTE: SEE TABLE FOR DIMENSIONS NOT SHOWN. BARRICADE NOTES: TYPE I II III 8" MIN. 8" MIN. 8" MIN. WIDTH OF RAIL 12" MAX. 12" MAX. 12" MAX. LENGTH OF RAIL 2' MIN. 2' MIN. 4' MIN. HEIGHT 3' MIN. 3' MIN. 5' MIN. DEMOUNTABLE LIGHT "A" POST OR TYPE OF FRAME OR HEAVY "A" FRAME SKIDS FLEXIBILITY MOVABLE PORTABLE MOVABLE OR PERMANENT 1' 10 30' TRAFFIC DIRECTION 0 0 0 0 0 0 0 0 0 4,' GAP VARIES (300' MAX.) 5' 2.5' TWO WAY LEFT TURN LANE 0 0 0 0 0 0 0 0 0 TRAFFIC DIRECTION TWO WAY LEFT TURN LINES TRAFFIC DIRECTION TRAFFIC DIRECTION 20' 8" WHITE LINE 0 o TYPE 2W RPM TYPE 2YY RPM o 0 20' 4" GAP 4" GAP �� 4" YELLOW LINE TRAFFIC DIRECTION TRAFFIC DIRECTION DOUBLE YELLOW CENTER LINE WIDE LINE TRAFFIC DIRECTION TRAFFIC DIRECTION 11'1. IN 30' 11' 30' D �o TYPE 2W RPM 137 � TYoPE 2Y RPM 4" WHITE LINE TRAFFIC DIRECTION 4 YELLOW LINE TRAFFIC DIRECTION LANE LINE SKIP CENTER LINE 6' 8' 0 0 0 n a�TYPE 2W RPM 4" WHITE OR YELLOW LINE 4" GAP 8" WHITE LINE EDGE LINE DOTTED WIDE LINE TRAFFIC DIRECTION 3' 9' 21'(TYP.) 18" YELLOW BARRIER 1„ LINE �I TYPE 2W RPM�B� 90 $ � OR 8" WHITE LINE �j DROP LANE LINE 18"-TYPE 2Y RPM'S EQUALLY SPACED TRAFFIC DIRECTION NOTE: THIS PLAN IS NOT A LEGAL ENGINEERING DOCUMENT BUT AN BARRIER LINE �� ELECTRONIC DUPLICATE. THE ORIGINAL, SIGNED BY THE ENGINEER AND APPROVED FOR PUBLICATION IS KEPT ON FILE AT THE CITY OF �� �� OF WAShr1 KENT. A COPY MAY BE OBTAINED UPON REQUEST. NOTE: ���� 1. SEE SECTION 6.12.B FOR PLASTIC CITY OF KENT ENGINEERING DEPARTMENT MATERIAL SPECIFICATIONS. • KENT TYPICAL LANE MARKINGS 2. RAISED PAVEMENT MARKERS (RPM'S) d� 38296 �� WASHINGTON SHALL BE INSTALLED PER WSDOT I ymF7�� �� DESIGNED COK SCALE NONE STANDARD PLAN STANDARD SPECIFICATIONS 8-09, �SSIpNAL DRAWN COK � 9-02.1(8), 9 26.2 AND 9-21. CHECKED COK DATE s/zozo 6-74 crn ENGINEER APPROVED Kensington Drainage Improvements/Holcomb A - 2 February 14, 2022 Project Number: 18-3019 WSDOT STANDARD PLANS DRAINAGE, STRUCTURES AND HYDRAULICS B-30.70.04 Circular Frame (Ring) and Cover B-55.20-02 Pipe Zone Bedding and Backfill RETAINING, NOISE BARRIER, AND GEOSYNTHETIC WALLS D-6 Gabions SITE PRESERVATION AND EROSION CONTROL I-30.30-02 Wattle Installation on Slope I-40.20-00 Storm Drain Inlet Protection I-60.10-01 Biodegradable Erosion Control Blanket Placement for Slopes H 3 118" BLIND PICK NOTCH DETAIL "A" 1 7/16" WASHER m 15/i6" (SEE NOTES) DOVETAIL GROOVE WITH NEOPRENE GASKET (SEE NOTES) BOLT -DOWN / WATERTIGHT DETAIL"B- RING PLAN 27 518" 26 3/8" 1' /TJI� 24' 26 3/4' 34 118" RING SECTION Op SKID GROOVE PATTERN - SEE DETAIL SEE DETAIL "A' I TOP - - -- -- BOTTOM---- ----' I COVER PLAN SEE DETAIL "A" " 5/8" COVER SECTION OB (SEE NOTE 7) STANDARD TYPE 1 SEE DI RING PLAN 27 518" 26 318" I 24" 26 3/4" 3a 118-- RING SECTION OA SEE DETAIL "A' TOP••"". _ BOTTOM ----y- ----' I COVER PLAN SEE DETAIL'B" DETAIL "A' �A�SEE f 1I SIB" COVERSECTION OB (SEE NOTE 7) BOLT -DOWN I WATERTIGHT TYPE 2 NOTES 1. The gasket and groove may be in the seat (frame) or in the underside of the Cover. The gasket may be "T" shaped in section. The groove may be cast or machined. 2. Bolt -down Capability is required on all frames, grates, and Covers, unless specified otherwise in the Contract. Provide 3 holes in the frame that are vertically aligned with the grate or cover slots. The frame shall accept the 304 Stainless Steel (S.S) 6/8" - 11 NC x 2" (in) alien head Cap screw by being tapped, or other approved mechanism. Location of bolt down holes varies by manufacturer. 3. For bolt -down manhole ring and covers that are not designated "Watertight," the neoprene gasket, groove, and washer are not required. 4. Washer shall be neoprene (Detail "B"). 5. In lieu of blind pick notch for manhole covers, a single 1" (in) pick hole is acceptable. Hole location and number of holes may vary by manufacturer. 6. Alternative reinforcing designs are acceptable in lieu of the rib design. 7. For clarity, the vertical scale of the Cover Section has been exaggerated, it is 1.5 times the horizontal scale (1H:1.5V). ISOMETRIC VIEW �� Rr SKID GROOVE PATTERN DETAIL �45bo� oAR 80f 5T86$ ti} BBZONAL g�G CIRCULAR FRAME (RING) AND COVER STANDARD PLAN B-30.70-04 SHEET 1 OF 1 SHEET APPROVED FOR PUBLICATION _ eucw w.mmebn smn c.a=mm.m./Tmnw.nvilen 19};�\�1T• \�lTi GRAVEL BA"'LL PIPE ZONE BEDDING ,SEE NOTE • �� FOUNDATION LEVEL C�yl ��► lr��l/y� CONCRETE AND DUCTILE IRON PIPE TRENCH WITH (SEE NOTE 3) GRAVEL BACKFILL FOR PIPE ZONE BEDDING (SEE NOTE 2) EL O N O FOUNDATION LEVEL THERMOPLASTIC PIPE TRENCH WIDTH (SEE NOTE 3) PIPE ZONE BACKFILL (SEE NOTE 1) G 00 O GRAVEL BACKFILL FOR O N PIPE ZONE BEDDING o 0 (SEE NOTE 2) FOUNDATION LEVEL = PIPE ZONE BACKFILL (SEE NOTE 1) GRAVEL BACKFILL FOR PIPE ZONE BEDDING (SEE NOTE 2) FOUNDATION LEVEL -\ NOTES 1. See Standard Speclflcatlons Section 7-08.3(3) for Pipe Zone Backfll. 2. See Standard Speclflcatlons Section 9-0 .12(3) for Gravel Backfill for Pipe Zone Bedding. 3. See Standard Specifications Section 2-09A for Measurement of Trench Width. 4. For sanitary sewer installation, Concrete pipe shall be bedded to spring line. TRENCH WIDTH (SEE NOTE 3) PIPE ARCHES CLEARANCE BETWEEN PIPES FOR MULTIPLE INSTALLATIONS MINIMUM PIPE SIZE DISTANCE BETWEEN BARRELS CIRCULAR PIPE (DIAMETER) UP TO 48" 24" METAL DIAMETER/2 PIPE ARCH 48" AND OR 36" (SPAN) LARGER WHICHEVER IS LESS 15% RISE AeBBr015T gNbl} PIPE ZONE BEDDING AND BACKFILL STANDARD PLAN B-55.20-02 SHEET 1 OF 1 SHEET APPROVED FOR PUBLICATION METAL AND STEEL RIB REINFORCED POLYETHYLENE PIPE w.mmemn smn o.a=mm.m.l T....n.n.6.. w Unit A - 2 cell gabion = 6' Unit B - 3 cell ga' bion = 9 Unit C - 4 cell gabion = 12' TYPICAL GABION CROSS -CONNECTING WIRE PLACEMENT, END CELLS CROSS CONNECTING WIRE PLACMENT, INTERIOR CELLS OF FRONT GABIONS Double loop Single loop Double loop Single loop TAIL independent encompassed cal and ontal mpossed O M is 9 25339 �0.cl✓A,A`�QIST0 Opt, H iii g "'ONAL 4'N iiii EXPIRES JULY I, 1999 ����� GAB IDNS STANDARD PLAN D-6 APPROVED FOR PUBLICATION Gifford E. Mansfield W9M l— I. All ALLOWABLE ALTERNATIVE TIE -DOWN METHOD WATTLE TRENCH - SEE NOTE 1 113 DIAMETER OF WATTLE CONTOUR LINE (TYP.) INt ANGLE TERMINAL END UPHILL 24" (IN) TO 48" (IN) TO PREVENT FLOW AROUND WATTLE (TYP.) GAO MA 2" (IN) - 2" (IN)- 24' (IN) MIN. - UN -TREATED WOODEN STAKE (TVPJ WATTLE DETAIL PLAN VIEW 2" (IN) . 2" (IN) - 24" (IN) WOODEN STAKE (TYP.) AREAAVAILABLE FOR SEDIMENT TRAPPING (TYP.) NOTES 1. Wattles shall be in accordance with Standard Specification, Section 9-14.5(5). Install Wattles along contours. Installation shall be in accordance with Standard Specification, Section 8-01.3(10). 2. Securely knot each end of Wattle. Overlap adjacent Wattle ends 12" (in) behind one another and securely tie together. 3. Compact excavated soil and trenches to prevent undercutting. Additional staking may be necessary to prevent undercutting. 4. Install Wattle perpendicular to flow along contours. 5. Wattles shall be inspected regularly, and immediately after a rainfall produces runoff, to ensure they remain thoroughly entrenched and in contact with the soil. 0. Perform maintenance in accordance with Standard Specification, Section 8-01.3(15). 7. Refer to Standard Specification, Section 8.01.3(16) for removal. WATTLE SPACING TABLE TEMPORARY PERMANENT 8"-10" OR 10"-12"DIAM. 10"-12"DIAM. SLOPE MAX. SPACING SLOPE MAX. SPACING 1H:1V 5'-01, - - 2H:1V 10'-0" 3H:1V 3H:iV 15'-0" 3H:1V 10'-0" 4H:iV 20'-0" 4H:1V 15'-0" SPA21NIG VAELI�LS -.SEE WATTLE - III on SECTION ( WATTLE INSTALLATION ON SLOPES OF IN OBE N4,y, 1•ni he' � z • 2 N O tiry O P. sCAPE APO WATTLE (TYP.) - SEE DETAIL WATTLE INSTALLATION ON SLOPE STANDARD PLAN 1-30.30-02 SHEET 1 OF 1 SHEET APPROVED FOR PUBLICATION _ eucw w.mmemn smn c.a=mm.m.I Tmnw.nvilen 2 0 aU N DRAINAGE GRATE TRW GRATE FRAIME: SEDIMENT AND DEBRIS FILTER® MTER 0 0 0 SECTION VIEW NDTTO SCALE OVERFLOW BYPASS BELOWINLET GRATE DEVICE DRAINAGE GRATE - RECTANGULAR GRATE SHOWN NOTES 1. Size the Below Inlet Grate Device (BIGD) for the storm water structure R Will service. 2. The BIGD shall have a built-in high -flow relief system (overflow bypass). 3. The retrieval system must allow removal of the BIGD without spilling the collected material. 4. Perform maintenance in accordance with Standard Specification 841.3(15). RETRIEVAL SYSTEM (TYP.) STORM DRAIN INLET PROTECTION STANDARD PLAN 1-40.20-00 SHEET 1 OF 1 SHEET APPROVED FOR PUBLICATION Pasco BakoNch Ill 08-20-07 YralNrm 11prr MPseFir MTgigsrpr.n F� W MIN. END �OW \ OVERLAP EROSION CONTROL BLANKET STAPLES - 4' MART. STAGGERED, W O. C. SHINGLE SPLICE -SECTION OA 11 O INE NATIVE SOIL - FOLLOW INSTALLATION STEPS EROSION CONTROL BLANKET 2 ROWS OF STAPLE (TYP.) - 4" APART, STAGGERED, TO C. INITIAL ANCHOR - DETAIL OB NOTES EXTEND BLANKET FAR ENOUGH OVER 1. More than the minimum of one fastener per square CREST OF SLOPE TO EFFECTIVELY yard may be required due to Conditions such as PREVENT UNDERCUTTING AND TO blanket composition, soil type, surface uniformity, PROVIDE SECURE ANCHORING and slope steepness. ' 2. See Standard Specification B-01.3(3) and 9-14.5)2). 3. Use manufacturers requirements. When manufacturers FASTENER requirements are not provided, use installation requirements shown on Standard Plans. ` 4. Additional staples may be required on slopes 1s" MAX (TYP.) greater than 3H : 1V. Is- MAX. (TYP.) \ 38" MAX. , (TYPJ s8" MAX. . ' \ :✓ \ /,¢ DE OVERLAP END BLANKET 24' NO TO OPSLOPEORTOE GE ' OF VEGETATION -WHICHEVER IS CLOSER 2 ROWS OF STAPLES 4" APART, STAGGERED, S" O. C. PLACED WITHIN S" OF BLANKET EDGE. 04t J tlidt OW INSTALLATION STEPS: 1. Prepare smooth slope. 2. Amend soil and seed, as specified. 3. Dig anchor trench. Set aside native soil removed from trench. 4. Secure blanket in anchor trench, staking or stapling blanket as shown. 5. Replace native soil previously removed from trench. 6. Roll blanket down the slope in a controlled manner, taking care to remove excess slack, and taking care not to stretch blanket. 7. Stake or staple blanket as shown so there are no gaps between the blanket and the soil. Staple while unrolling blanket to minimize walking on blanket. ISOMETRIC VIEW �f7 (tN SCAPE ARCHITECT U TON REGISTERED UWDfifAPE ARCHITECT SANDRA L. SALISBURY SANDRA L. SALISBURY LICENSE NO. 860 DATE: SfiT13 BIODEGRADABLE EROSION CONTROLBLANKET PLACEMENT FOR SLOPES STANDARD PLAN 1-60.10-01 SHEET 1 OF 1 SHEET APPROVED FOR PUBLICATION Pasco Bakotich Ill 6110113 — ,>re oEsiox �oixE� o..,E wo.nl„rn� s.m. D.ponm.m el TA�.P=nal� Kensington Drainage Improvements/Holcomb A - 3 February 14, 2022 Project Number: 18-3019 GEOTECHNICAL REPORT Geotechnical Engineering Services Report Kensington Ravine Kent, Washington for City of Kent June 28, 2021 Geotechnical Engineering Services Report Kensington Ravine Kent, Washington for City of Kent June 28, 2021 1101 South Fawcett Avenue, Suite 200 Tacoma, Washington 98402 253.383.4940 Geotechnical Engineering Services Report Kensington Ravine Kent, Washington File No. 0410-217-00 June 28, 2021 Prepared for: City of Kent 220 Fourth Avenue South Kent, Washington 98032-5895 Attention: Drew Holcomb, PE Prepared by: GeoEngineers, Inc. 1101 South Fawcett Avenue, Suite 200 Tacoma, Washington 98402 253.383.4940 Clinton J. Lindgren Staff Geotechnical Engineer Lyle J. Stone, PE Associate Geotechnical Engineer 7/28/2021 CJL:LJS:tt Disclaimer: Any electronic form, facsimile or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record. June 28, 2021| Page i File No. 0410-217-00 Table of Contents 1.0 INTRODUCTION AND PROJECT UNDERSTANDING ........................................................................................ 1 2.0 PURPOSE AND SCOPE OF SERVICES ............................................................................................................ 1 3.0 SITE CONDITIONS ............................................................................................................................................ 1 3.1. Geologic Setting .......................................................................................................................................... 1 3.2. Slope Reconnaissance ............................................................................................................................... 1 4.0 CONCLUSIONS AND RECOMMENDATIONS ................................................................................................... 2 4.1. Slope Evaluation ......................................................................................................................................... 2 4.1.1. Slope Stability Modeling .................................................................................................................. 2 4.1.2. Conclusions...................................................................................................................................... 3 4.2. General Site Development and Earthwork Recommendations ............................................................... 3 4.2.1. Temporary Erosion and Sedimentation Control ............................................................................ 3 4.2.2. Temporary Excavations and Cut Slopes ......................................................................................... 4 4.2.3. Permanent Cut and Fill Slopes ....................................................................................................... 5 4.2.4. Temporary Groundwater Handling Considerations ....................................................................... 5 4.2.5. Subgrade Protection and Wet Weather Considerations ............................................................... 5 4.3. Drainage Ditch Improvements ................................................................................................................... 6 4.3.1. General ............................................................................................................................................. 6 4.3.2. Site Preparation ............................................................................................................................... 6 4.3.3. Rock Fill Placement, Materials, and Compaction .......................................................................... 7 4.3.4. Other Fill Placement, Materials and Compaction .......................................................................... 7 5.0 LIMITATIONS ................................................................................................................................................... 7 LIST OF FIGURES Figure 1. Vicinity Map Figures 2 and 3. Slope Stability Outputs APPENDIX Appendix A. Provided Project Documents Appendix B. Report Limitations and Guidelines for Use June 28, 2021 | Page 1 File No. 0410-217-00 1.0 INTRODUCTION AND PROJECT UNDERSTANDING This report presents the results of our geotechnical reconnaissance and geotechnical recommendations for the Kensington Ravine project. The project site is located about 500 feet south of the intersection of Kensington Avenue South and Reiten Road in Kent, Washington as shown on the Vicinity Map, Figure 1. We previously issued a technical memorandum for the project dated June 23, 2021 that provides hydraulic analysis and recommendations (Hydraulic Analysis Memorandum). We were provided two sheets from preliminary plans including a site plan and typical sections prepared by the City of Kent (the City) dated June 8, 2021. Stationing discussed herein references the stationing shown on the provided plan sheets, which are attached to this report as Appendix A. We understand that the City plans to construct a new drainage ditch with components to reduce flow velocities and prevent erosion. Based on review of the provided plans, the improvements will include two gabion basket check dams, reinforced slopes, and rock armoring. The new ditch will be trapezoidal and cut to grade in the same general location as the existing ditch. Water within the new ditch will be directed to a Type 2 catch basin structure near Kensington Avenue South. Due to steep slopes at the site, it is our understanding that the site is designated as a critical area. 2.0 PURPOSE AND SCOPE OF SERVICES The purpose of our services is to complete a geologic reconnaissance at the project site to provide our opinion on the current stability of the slope and evaluate potential impacts to slope stability due to the proposed improvements. We will also provide geotechnical design recommendations pertaining to the proposed improvements. Our services have been completed in accordance with our signed agreement for this project executed on May 18, 2021. A complete list of our authorized services is provided in the signed agreement. 3.0 SITE CONDITIONS 3.1. Geologic Setting We reviewed the Geologic Map of the Tacoma 1:100,000-scale Quadrangle, Washington (Schuster et al.). According to the map, soils in the near site vicinity include Vashon drift (Qgd) and Salmon Springs Drift (Qgps). Both units are glacially consolidated soils and described to consist of a mixture of clay, silt, sand, and gravel. The upper few feet of glacially consolidated deposits can be weathered and in a loose to medium dense condition. Undisturbed glacially consolidated soils are dense to very dense. 3.2. Slope Reconnaissance We performed a visual reconnaissance of the site on May 24, 2021. Per Chapter 11.06 Critical Areas of the Kent City Code, the project site is designated as a critical area for landslide hazard due to having slopes greater than 40 percent with vertical relief of more than 10 feet. Kensington Ravine is located about 500 feet south of the intersection of Kensington Avenue South and Reiten Road in Kent, Washington. The top of the ravine is located near the western terminus of East Tacoma Street and the bottom of the ravine June 28, 2021 | Page 2 File No. 0410-217-00 is located near Kensington Avenue South. The top of the ravine generally trends to the west and then turns northwest towards Kensington Avenue South. Total grade change along the ravine is on the order of 60 feet. The ravine is heavily vegetated with trees and underbrush. We observed surface water at the base of the ravine that, in some areas, appears to have eroded a narrow channel up to about 6 feet deep. Observed surface water, where present, was typically a few inches deep. In the north portion of the ravine (from approximate Station 10+00 to 11+50) steep banks form its sides. The banks are up to about 15 to 20 feet tall with near vertical slopes. We expect the steep banks were formed from localized surficial erosion at the site. The steep banks of the ravine and the sidewalls of eroded channels generally expose silty sand with variable gravel content, visually consistent with glacially consolidated soils mapped within the project area. We observed exposed soil to generally be in a dense condition. During our reconnaissance we did not observe significant signs of deep-seated slope failure such as pistol- butted trees near the top of the banks or groundwater seepage emitting from the faces of the banks. We did not observe signs of tension cracks forming or surface settlement at the crest of the slope nor the top of the steep banks; however, due to heavy vegetation and difficult access, some of these areas were unable to be observed directly. 4.0 CONCLUSIONS AND RECOMMENDATIONS 4.1. Slope Evaluation 4.1.1. Slope Stability Modeling In addition to our site reconnaissance, we evaluated the stability of the ravine bank at approximate Station 11+10 as shown on Sheet 4 of the provided plans (Appendix A). Based on review of the provided plans, it appears that the area near Station 11+10 represents a typical steep slope condition. We performed two slope stability analyses at this location, which are presented as Figures 2 and 3. Slope stability was evaluated using the GeoStudio commercial software Slope/W. The critical slip surface and corresponding factor of safety (FS) were determined using the Morgernstern-Price limit equilibrium method. The minimum slip surface depth used in our analyses was set to 5 feet in order to evaluate non- surficial slope failures. Since we did not perform subsurface explorations at the site, soil type and conditions are generally unconfirmed at depth. However, as previously discussed we did observe some exposed soils consistent with glacially consolidated soils. We estimated soil strength parameters in our slope stability analysis using our observations in the field and our understanding of local geologic conditions. Additionally, we calibrated soil strength parameters of the site soils (glacially consolidated soils) based on existing site topography and the presence of the steep banks that appear to be stable (i.e., FS equal to or greater than 1). Soil strength parameters for the rock fill (Class B riprap) were estimated using typical values presented in Chapter 5 of the Washington State Department of Transportation (WSDOT) Geotechnical Design Manual. Figure 2 presents our stability analysis of the ravine bank at Station 11+10 in its current state. Note that the stability analysis shown in Figure 2 was used to calibrate the soil strength parameters of the glacially June 28, 2021 | Page 3 File No. 0410-217-00 consolidated soils; soil strength parameters were increased in the model until a stable condition was achieved. Figure 3 presents the stability analysis at of the ravine bank at Station 11+10 after the proposed improvements, which include placement of rock fill as recommended in our Hydraulic Analysis Memorandum. Rock fill consists of Class B riprap that lines a 2.5-foot-wide channel, is embedded 2.5 feet and extends up the banks a height of 1.5 feet above the bottom of the channel. The global stability analysis results are summarized below in Table 1. TABLE 1. SUMMARY OF SLOPE STABILITY RESULTS Global Stability Case FS Static, Existing Conditions 1.0 Static, Post-Construction 1.8 4.1.2. Conclusions Based on our observations during our site reconnaissance it is our opinion that there is a low risk of deep- seated or global failures and instability of the slopes near the proposed improvements. Based on our analysis it is also our opinion that the proposed development will not significantly impact the stability of the adjacent slope and will result in a net increase in factor of safety of the banks. The proposed armoring will reduce the potential for further erosion and will provide a buttress effect at the toe of the banks. Existing slopes could still experience shallow surficial sloughing over the long term. Sloughing is typically due to natural weathering processes such as seepage, saturation of shallow soils during heavy rain events, decay of roots, or root removal of blown down trees. The magnitude and volume of material involved in shallow surficial sloughing depends on several factors including steepness of slope, time of year, rainfall, saturation of ground, and activity of burrowing animals. Sloughing is a natural process that occurs with or without development. The risk of sloughing will remain even after the project is completed. The purpose of the project and the overall effect of the project will be to reduce erosion and thereby increase slope stability. As such, it is our opinion, the remaining landslide hazards as defined should not be considered a limiting factor for the proposed development. 4.2. General Site Development and Earthwork Recommendations We anticipate site development and earthwork activities will include: clearing and stripping vegetated areas, site grading, establishing subgrades for project improvements; and placing and compacting fill material. We expect that site grading and earthwork can be accomplished primarily with conventional earthmoving equipment. Some specialized equipment could be required due to space constraints. 4.2.1. Temporary Erosion and Sedimentation Control Erosion and sedimentation rates and quantities can be influenced by construction methods, slope length and gradient, amount of soil exposed and/or disturbed, soil type, construction sequencing and weather. Implementing an Erosion and Sedimentation Control Plan will reduce the project impact on erosion-prone areas. The plan should be designed in accordance with applicable city, county, and state standards. The plan should incorporate basic planning principles, including: Scheduling grading and construction to reduce soil exposure; June 28, 2021 | Page 4 File No. 0410-217-00 Re-vegetating or mulching denuded areas; Directing runoff away from exposed soils; Reducing the length and steepness of slopes with exposed soils; Decreasing runoff velocities; Preparing drainage ways and outlets to handle concentrated or increased runoff; Confining sediment to the project site; Inspecting and maintaining control measures frequently. Some sloughing and raveling of exposed or disturbed soil on slopes should be expected. We recommend disturbed soil be restored promptly so that surface runoff does not become channeled. Temporary erosion protection should be used and maintained in areas with exposed or disturbed soils to help reduce erosion and reduce transport of sediment to adjacent areas and receiving waters. Permanent erosion protection should be provided by the proposed developments. Until the permanent erosion protection is established and the site is stabilized, site monitoring may be required by qualified personnel to evaluate the effectiveness of the erosion control measures and to repair and/or modify them as appropriate. Provisions for modifications to the erosion control system based on monitoring observations should be included in the Erosion and sedimentation Control Plan. 4.2.2. Temporary Excavations and Cut Slopes We anticipate that shallow excavations could experience minor caving. Excavations deeper than 4 feet should be shored or laid back at a stable slope if workers are required to enter. Shoring and temporary slope inclinations must conform to the provisions of Title 296 Washington Administrative Code (WAC), Part N, Excavation, Trenching and Shoring. Regardless of the soil type encountered in the excavation shoring, trench boxes or sloped sidewalls will be required under Washington Industrial Safety and Health Act (WISHA). We recommend the contract documents specify that the contractor is responsible for selecting excavation and dewatering methods, monitoring the excavations for safety and providing shoring, as required, to protect personnel and structures. Glacially consolidated soils can maintain near vertical cut slopes for a time. However, near vertical slopes in these soils can also slough quickly and without warning. In general, we recommend that for planning purposes all temporary cut slopes be inclined no steeper than about 1.5H:1V (horizontal:vertical) if workers are required to enter confined trenches. Temporary cut slopes in dense glacially consolidated soil can be cut to steeper inclinations provided that a collapse or slough of the slope will not endanger workers or adjacent property. This guideline assumes all surface loads are kept at a minimum distance of at least one- half the depth of the cut away from the top of the slope and that seepage is not present on the slope face. Flatter cut slopes will be necessary where seepage occurs or if surface surcharge loads are anticipated. Temporary covering with heavy plastic sheeting should be used to protect these slopes during periods of wet weather. June 28, 2021 | Page 5 File No. 0410-217-00 4.2.3. Permanent Cut and Fill Slopes We recommend permanent soil slopes be constructed at a maximum inclination of 2H:1V to manage erosion. Where 2H:1V permanent slopes are not feasible, protective facings and/or retaining structures should be considered. Rock fill placed as part of the ditch improvements will have inclinations exceeding 2H:1V; however, it is our opinion that provided the slope is rebuilt using rock fill as recommended in this report, steeper inclinations (on the order of 1H:1V) are acceptable. Exposed areas should be re-vegetated as soon as practical to reduce the surface erosion and sloughing. Temporary protection should be used until permanent protection is established. 4.2.4. Temporary Groundwater Handling Considerations We observed surface water in some areas at the base of the ravine during our slope reconnaissance, which we expect could be a combination of surface water runoff and perched groundwater seepage. We anticipate groundwater levels will vary throughout the year and will generally be highest during the wet season, typically October through May. We expect that perched groundwater and surface water could be encountered depending on the time of year of construction, likely near contacts where soil that is more permeable overlies soil that is less permeable (i.e., weathered glacially consolidated soils over glacially consolidated soils) or flowing at the base of the ravine. Groundwater handling needs will typically be lower during the late summer and early fall months. We anticipate shallow perched groundwater can typically be handled adequately with diversion ditches, and/or sumps and pumps, as necessary. If rock fills are constructed in the summer months it is expected that the seepage can be allowed to flow through the fill as it is placed and that it will not inhibit rock fill placement. Ultimately, we recommend the contractor performing the work be made responsible for controlling and collecting groundwater encountered. 4.2.5. Subgrade Protection and Wet Weather Considerations Site soils observed typically contain a significant amount of fines and will be susceptible to disturbance during periods of wet weather. Soil with high fines content is very sensitive to small changes in moisture and is susceptible to disturbance from construction traffic when wet or if earthwork is performed during wet weather. When the moisture content of the soil is more than a few percent above the optimum moisture content, this soil can become unstable and it will be challenging to meet the required compaction criteria. The wet weather season generally begins in October and continues through May in western Washington; however, periods of wet weather can occur during any month of the year. In our opinion, earthwork will be most efficient during the summer months or during periods of extended dry weather. If wet weather earthwork is unavoidable, we offer the following recommendations: The ground surface in and around the work area should be sloped so that surface water is directed away from the work area. The ground surface should be graded so that areas of ponded water do not develop. Measures should be taken by the contractor to prevent surface water from collecting in excavations and trenches. Measures should be implemented to remove surface water from the work area. Earthwork activities should not take place during periods of heavy precipitation. Slopes with exposed soils should be covered with plastic sheeting. June 28, 2021 | Page 6 File No. 0410-217-00 The contractor should take necessary measures to prevent on-site soils and other soils to be used as fill from becoming wet or unstable. These measures may include the use of plastic sheeting, sumps with pumps and grading. The site soils should not be left uncompacted and exposed to moisture. Sealing exposed soils by rolling with a smooth-drum roller prior to periods of precipitation will help reduce the extent to which these soils become wet or unstable. Construction traffic should be restricted to specific areas of the site, preferably areas that are surfaced with working pad materials not susceptible to wet weather disturbance. Construction activities should be scheduled so that the length of time that soils are left exposed to moisture is reduced to the extent practical. 4.3. Drainage Ditch Improvements 4.3.1. General We understand that currently proposed plans pertaining to geotechnical improvements include reinforced slopes and rock armoring in order to construct the new ditch alignment. 4.3.2. Site Preparation Prior to placement of fill, the improvement area should be cleared and stripped of all vegetation and organics. Based on conditions observed during our site reconnaissance, minimum stripping depths at the site will likely be on the order of 4 to 6 inches. However, greater stripping depths could be required to remove localized zones of loose or organic-rich soil. We anticipate that some trees will need to be removed prior to excavation. During clearing and stripping, stumps and primary root systems of shrubs and trees should be completely removed from fill areas. Voids caused by removal of stumps and/or root systems should be backfilled with rock fill, described below. If trees are removed from steep slopes for access purposes, the root system can be left intact to allow for slope and erosion protection as new vegetation is being established. We anticipate soils exposed after stripping will have a high fines content and will, therefore, be susceptible to disturbance when wet. Care should be taken to avoid allowing these soils to become saturated and disturbed. Based on review of the provided plans, it appears that most of the ditch improvements will consist of placement of fill with limited excavation. Fill subgrades should be free of organics and expose firm and unyielding soils. In areas of excavation, excavation should extend to expose firm and unyielding on-site soils. Based on our observations, we expect that excavated material will consist of medium dense to very dense silty sand with gravel. Provided excavations are relatively shallow, we anticipate these soils can be excavated with conventional excavation equipment such as midsize excavators. If smaller equipment such as mini excavators are required due to site space constraints, additional tools and attachments such as hydraulic breakers or chisels could be required for efficient excavation. Cobbles and/or boulders could be encountered, and the contractor should be prepared to deal with these during construction. After subgrades are established, we recommend installation of a geotextile fabric over the subgrade prior to placement of rock fill. Geotextile fabric should conform to WSDOT Standard Specification 9-33 Construction Geotextile for Soil Stabilization (Table 3). June 28, 2021 | Page 7 File No. 0410-217-00 4.3.3. Rock Fill Placement, Materials, and Compaction Place and compact rock fill on the prepared subgrades as ditch lining material. As discussed in our Hydraulic Analysis Memorandum, rock fill should consist of Class B riprap, extend to a height of at least 1.5 feet above the proposed channel bottom and have a thickness below proposed grade of at least 2.5 feet. For areas of rock fill extending up the sides of the ditch, we recommend that they be placed no steeper than 1H:1V. Rock fill should be free of debris and organic contaminants. We recommend rock fill consist of material similar to Class B riprap as described in Section 9-13.4(3) of the WSDOT Standard Specifications. Rock fill should be placed in lifts and compacted and locked in via mechanical means, such as tamping with an excavator bucket or use of vibratory compaction equipment. 4.3.4. Other Fill Placement, Materials and Compaction In addition to rock fill areas, other parts of the site may need to be filled. We expect that this could include placement of fill to attain rock fill subgrade elevation, such as filling the eroded narrow channels previously discussed. In our opinion, on-site soil could be used as fill in these areas provided it does not contain organics and can be adequately compacted. The on-site soils observed and anticipated at the site are extremely moisture sensitive and will be very difficult or impossible to properly compact when wet or when placed over wet subgrade. If earthwork occurs during the wet season, or if the soils and/or subgrades are persistently wet and cannot be dried back to near optimum due to prevailing wet weather and site conditions, we recommend the use of imported granular fill. Imported granular fill should consist of material similar to Select Borrow or Gravel Borrow as described in Section 9-03.14 of the WSDOT Standard Specifications. Fill should be placed in maximum 12-inch-thick lifts and compacted to at least 95 percent of the theoretical maximum dry density (MDD) per ASTM International (ASTM) D 1557. We expect that relatively small or narrow fill areas, such as the eroded channels, may need to be widened prior to filling in order to accommodate the size of compaction equipment. 5.0 LIMITATIONS We have prepared this report for City of Kent for the Kensington Ravine project in Kent, Washington. City of Kent may distribute copies of this report to their authorized agents and regulatory agencies as may be required for the project. Our services were provided to assist in the design of improvements located on and adjacent sloping property. Our recommendations are intended to improve the overall stability of the site and to reduce the potential for future damage related to earth movements, drainage or erosion. Qualified engineering and construction practices can help mitigate the risks inherent in construction on slopes, although those risks cannot be eliminated completely. Favorable performance of structures in the near term is useful information for anticipating future performance, but it cannot predict or imply a certainty of long-term performance, especially under conditions of adverse weather or seismic activity. June 28, 2021 | Page 8 File No. 0410-217-00 Within the limitations of scope, schedule and budget, our services have been executed in accordance with generally accepted practices for geotechnical engineering services in this area at the time this report was prepared. The conclusions, recommendations, and opinions presented in this report are based on our professional knowledge, judgment and experience. No warranty, express or implied, applies to the services or this report. Please refer to Appendix B titled Report Limitations and Guidelines for Use for additional information pertaining to use of this report. rluu nn Gull II I ICI II P z ❑ UK) I II� II Illu� J.arnesESt= W James St E-James St—Q 2;9_J� o - a uuo 0000o z i0° L411 IL�L�IIo TA o _ W=Srrii4h=St W`mith 8t' [�oouoi—U nr� SoEl 8 la SITE r1— o W-MeLU ID ot❑oo L_Qq]IG1oKent lu°o �ooloIru � p'CQOQ C� a uu-o �'i � m� °'_. ❑ �� der r> R rI 516 SS r�rn�n rJD ,°nl nI 04 ��i rS po -� �WrN� Inl r d� ,,� J4',�a 0 =47 L ��N ��� �0 0 �. Q -C Vr Horsehead �=�1 D��n��•�� Bend Natural (3 Area G �R—! �w _J 3 V i Jnt n 1 Tacoma' V y 7 s �I Notes: 0 1. The locations of all features shown are approximate. 2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document. GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master o file is stored by GeoEngineers, Inc. and will serve as the official record of this communication. m Data Source: ESRI Projection: NAD 1983 UTM Zone 10N J,-C 2,000 In 2,000 ia Vicinity Map Kensington Ravine Kent, Washington GEOENGINEERS Figure 1 1.0 Distance (feet) 0 10 20 30 40 50 60Elevation (feet)140 150 160 170 Color Name Model Unit Weight (pcf) Cohesion' (psf) Phi' (°) Glacially Consolidated Soils Mohr-Coulomb 130 0 38 Notes: Existing Conditions, Station 11+10 1. The locations of all features shown are approximate. 2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document. 3. GeoEngineers, Inc. cannot guarangtee the accuracy and context of electronic files. The master file is stored by GeoEngineers, Inc. and will serve as the official record of this communication. City of Kent - Kensington Ravine Kent, Washington Figure 2 1.8 Distance (feet) 0 10 20 30 40 50 60Elevation (feet)140 150 160 170 Color Name Model Unit Weight (pcf) Cohesion' (psf) Phi' (°) Class B Rip Rap Mohr-Coulomb 105 0 40 Glacially Consolidated Soils Mohr-Coulomb 130 0 38 2.5 ft Notes: 1. The locations of all features shown are approximate. 2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document. 3. GeoEngineers, Inc. cannot guarangtee the accuracy and context of electronic files. The master file is stored by GeoEngineers, Inc. and will serve as the official record of this communication. City of Kent - Kensington Ravine Kent, Washington Figure 3 Post Construction, Station 11+10 APPENDIX A Provided Project Plans NW 1/4 SEC. 19, T 22N, R 5E, W.M. \ / / sTE PARCEL #118370-OD50 N \ � \ PARCEL Ng9183r0-0050\STE PARCEL X918370-0015 h- — — _ _ _ 215 KEN-1&030NAAVE 5 W \ \ \ \ 218 K NESINGTON AVE MROILIA TA / \ \ 98030 S \� \\ T SCH EL M192205AKNA G 9o45 115 TACO Si / GRADING LIMITS, EXISnNG R/ iq� KAVE 5 \EIDSETI C11-1 E OA C,7 / STRAW WATTLE TO BE %Sn G F/W 98030 .ii �� PLA BEYOND ^/\ ~camITS (TYP) N M 1-1 R/w HEIKs .y \ 10, noLg18re m 7 80 TACOM �n NEW mE 2ESTRIJ \ \ / REMOVE AND DISPOSE OF BRIDGE 1 WITH SEEM v CRATE y \ REMOVE A� DISPOSE OF PIPE / 4 s ELo-no \ _ 1112211EIi � \ PARCEL z-o KA1RL HANLONIMARK orvc 8ACOM 118 R AVE 12oK SINc� 9Bo3o / \\ \\ . PLAN NOTES SCALE 1" = 20' 220 220 200 t.a i�'. .y.�. 200 7 . ... ....... 180 160 140 �- ___ }III 140 120 - .� ....>. v..... �... 120 r�rr��r.✓ ,_ .... �... ...s. 100 .....v........... >...v...... 100 9. B'X0H 60 9+80 10+00 10+20 10+40 10+60 10+80 11+00 11+20 11+40 11+60 11+80 12+00 12+20 12+40 12+60 12+80 13+00 13+20 13+40 13+60 13+80 14+00 PROFILE SCALE t = 20'(H, h PRELIMINARY _ CityofKCvt PubGCW ks Department PLAN AND PROFILE E STREET NGTON KENSIMENTS T _ _ NT Engineers Divi AVENTACOUE AVENUE DRAINAGE IMPROVEMENTS D I _ A. 11-9. ROM um��ovam�a a c/e�oa1 HITCH DITCH / / I NN \\\PEV GINDU VARIES; RC I CROBS SECTIONS AND T/FILL / �El III ON PLANSS (TFIL f� d z d a NON -WOVEN GEOTE%TILE ohm NON -WOMEN FABRIC GEOTE%TLE 0 FABRIC 10)0 0.5' C COMPACTED rc 1CJ5 GRAVEL BORROW SECTION A -A DRAINAGE SWALE SCALE 1"=1' SCALE 1"=1' STATIONS : 10+00.00 TO 13-96 RETER TO' PLAINS TO' 'OCATO' SILDPE DITCH TO HEADWALL PER PLAN DITCH EXTEND HEIGHT OF 1095�� ^ aoam \\\\ 6 N i --7z1 I —NET I EX ORWND voi'OOn CHECK DAM O(IYP.) KE eo 1 N, z ®`s \ PAN SIX ROCK HEADWALL DETAIL SEE SECTION A -A GABION BASKET CHECK DAM CHECK DAM DETAIL PRELIMINARY Cily of Kent E TACOMA STREET — KENSINGTON T A. Public W ks Department TYPICAL SECTIONS AVENUE DRAINAGE IMPROVEMENTS L3pff Engine ring Divi mMo..ls•Ve-core E Tacoma st-K.�.msm, AK -mog. PLAN ANDbPRanc si t APPENDIX B Report Limitations and Guidelines for Use June 28, 2021 | Page B-1 File No. 0410-217-00 APPENDIX B REPORT LIMITATIONS AND GUIDELINES FOR USE1 This appendix provides information to help you manage your risks with respect to the use of this report. Read These Provisions Closely It is important to recognize that the geoscience practices (geotechnical engineering, geology and environmental science) rely on professional judgment and opinion to a greater extent than other engineering and natural science disciplines, where more precise and/or readily observable data may exist. To help clients better understand how this difference pertains to our services, GeoEngineers includes the following explanatory limitations provisions in its reports. Please confer with GeoEngineers if you need to know more how these Report Limitations and Guidelines for Use apply to your project or site. Geotechnical Services are Performed for Specific Purposes, Persons and Projects This report has been prepared for City of Kent and for the Project specifically identified in the report. The information contained herein is not applicable to other sites or projects. GeoEngineers structures its services to meet the specific needs of its clients. No party other than the party to whom this report is addressed may rely on the product of our services unless we agree to such reliance in advance and in writing. Within the limitations of the agreed scope of services for the Project, and its schedule and budget, our services have been executed in accordance with our Agreement with City of Kent executed on May 18, 2021 and generally accepted geotechnical practices in this area at the time this report was prepared. We do not authorize, and will not be responsible for, the use of this report for any purposes or projects other than those identified in the report. A Geotechnical Engineering or Geologic Report is based on a Unique Set of Project-Specific Factors This report has been prepared for the Kensington Ravine project in Kent, Washington. GeoEngineers considered a number of unique, project-specific factors when establishing the scope of services for this project and report. Unless GeoEngineers specifically indicates otherwise, it is important not to rely on this report if it was: not prepared for you, not prepared for your project, not prepared for the specific site explored, or completed before important project changes were made. For example, changes that can affect the applicability of this report include those that affect: the function of the proposed structure; elevation, configuration, location, orientation or weight of the proposed structure; 1 Developed based on material provided by GBA, GeoProfessional Business Association; www.geoprofessional.org. June 28, 2021 | Page B-2 File No. 0410-217-00 composition of the design team; or project ownership. If changes occur after the date of this report, GeoEngineers cannot be responsible for any consequences of such changes in relation to this report unless we have been given the opportunity to review our interpretations and recommendations. Based on that review, we can provide written modifications or confirmation, as appropriate. Environmental Concerns are Not Covered Unless environmental services were specifically included in our scope of services, this report does not provide any environmental findings, conclusions, or recommendations, including but not limited to, the likelihood of encountering underground storage tanks or regulated contaminants. Subsurface Conditions Can Change This geotechnical or geologic report is based on conditions that existed at the time the study was performed. The findings and conclusions of this report may be affected by the passage of time, by man-made events such as construction on or adjacent to the site, new information or technology that becomes available subsequent to the report date, or by natural events such as floods, earthquakes, slope instability or groundwater fluctuations. If more than a few months have passed since issuance of our report or work product, or if any of the described events may have occurred, please contact GeoEngineers before applying this report for its intended purpose so that we may evaluate whether changed conditions affect the continued reliability or applicability of our conclusions and recommendations. Geotechnical and Geologic Findings are Professional Opinions Our interpretations of subsurface conditions are based on field observations from widely spaced sampling locations at the site. Site exploration identifies the specific subsurface conditions only at those points where subsurface tests are conducted or samples are taken. GeoEngineers reviewed field and laboratory data and then applied its professional judgment to render an informed opinion about subsurface conditions at other locations. Actual subsurface conditions may differ, sometimes significantly, from the opinions presented in this report. Our report, conclusions and interpretations are not a warranty of the actual subsurface conditions. Geotechnical Engineering Report Recommendations are Not Final We have developed the following recommendations based on data gathered from subsurface investigation(s). These investigations sample just a small percentage of a site to create a snapshot of the subsurface conditions elsewhere on the site. Such sampling on its own cannot provide a complete and accurate view of subsurface conditions for the entire site. Therefore, the recommendations included in this report are preliminary and should not be considered final. GeoEngineers recommendations can be finalized only by observing actual subsurface conditions revealed during construction. GeoEngineers cannot assume responsibility or liability for the recommendations in this report if we do not perform construction observation. We recommend that you allow sufficient monitoring, testing and consultation during construction by GeoEngineers to confirm that the conditions encountered are consistent with those indicated by the explorations, to provide recommendations for design changes if the conditions revealed during the work June 28, 2021 | Page B-3 File No. 0410-217-00 differ from those anticipated, and to evaluate whether earthwork activities are completed in accordance with our recommendations. Retaining GeoEngineers for construction observation for this project is the most effective means of managing the risks associated with unanticipated conditions. If another party performs field observation and confirms our expectations, the other party must take full responsibility for both the observations and recommendations. Please note, however, that another party would lack our project- specific knowledge and resources. A Geotechnical Engineering or Geologic Report Could Be Subject to Misinterpretation Misinterpretation of this report by members of the design team or by contractors can result in costly problems. GeoEngineers can help reduce the risks of misinterpretation by conferring with appropriate members of the design team after submitting the report, reviewing pertinent elements of the design teams plans and specifications, participating in pre-bid and preconstruction conferences, and providing construction observation. Do Not Redraw the Exploration Logs Geotechnical engineers and geologists prepare final boring and testing logs based upon their interpretation of field logs and laboratory data. The logs included in a geotechnical engineering or geologic report should never be redrawn for inclusion in architectural or other design drawings. Photographic or electronic reproduction is acceptable, but separating logs from the report can create a risk of misinterpretation. Give Contractors a Complete Report and Guidance To help reduce the risk of problems associated with unanticipated subsurface conditions, GeoEngineers recommends giving contractors the complete geotechnical engineering or geologic report, including these Report Limitations and Guidelines for Use. When providing the report, you should preface it with a clearly written letter of transmittal that: advises contractors that the report was not prepared for purposes of bid development and that its accuracy is limited; and encourages contractors to conduct additional study to obtain the specific types of information they need or prefer. Contractors are Responsible for Site Safety on Their Own Construction Projects Our geotechnical recommendations are not intended to direct the contractors procedures, methods, schedule or management of the work site. The contractor is solely responsible for job site safety and for managing construction operations to minimize risks to on-site personnel and adjacent properties. Biological Pollutants GeoEngineers Scope of Work specifically excludes the investigation, detection, prevention or assessment of the presence of Biological Pollutants. Accordingly, this report does not include any interpretations, recommendations, findings or conclusions regarding the detecting, assessing, preventing or abating of Biological Pollutants, and no conclusions or inferences should be drawn regarding Biological Pollutants as they may relate to this project. The term Biological Pollutants includes, but is not limited to, molds, fungi, spores, bacteria and viruses, and/or any of their byproducts. June 28, 2021 | Page B-4 File No. 0410-217-00 A Client that desires these specialized services is advised to obtain them from a consultant who offers services in this specialized field. Information Provided by Others GeoEngineers has relied upon certain data or information provided or compiled by others in the performance of our services. Although we use sources that we reasonably believe to be trustworthy, GeoEngineers cannot warrant or guarantee the accuracy or completeness of information provided or compiled by others. Kensington Drainage Improvements/Holcomb A - 4 February 14, 2022 Project Number: 18-3019 KENSINGTON NON-CRITICAL AREA DETERMINATION ECONOMIC & COMMUNITY DEVELOPMENT Kurt Hanson, Director 220 Fourth Avenue South Kent, WA 98032-5895 Fax: 253-856-6454 Phone: 253-856-5454 Mayor Dana Ralph City of Kent Economic & Community Development 7/1/2021 Drew Holcomb City of Kent Public Works 400 W Gowe St Kent, WA 98032 RE: Kensington Ravine, Delineation Review KIVA Number: RECR-2212093 Dear Drew Holcomb: The City of Kent has received and reviewed the Wateway Determination and Critical Area Report, prepared by ICF in June 2021. I am pleased to inform you that the City of Kent hereby grants approval of the report. The report is approved as of the date of this letter. The city agrees that the site does not contain conditions to be considered a wetland, as determined by ICF. Review of the ICF report and the residential areas adjacent to the ravine determined the channel is an ephemeral system meaning that water exists only because of storm precipitation. Fish do not use the ravine. The upstream and downstream areas are shallow roadside ditches and curbs on slopes that direct water off the roads and through the residential area. Per the applicants report Kensington Ravine is not regulated by the Kent City Code 11.06. The City of Kent concurs with the report finding that Kensington Ravine is not regulated by the Kent City Code 11.06. Should you have any questions regarding this letter, please contact me by phone at (253) 856-6449 or email at salcorn@KentWa.gov Sincerely, Sam Alcorn, Planner Enclosed: Kensington Wetland/Stream Review RECR 2211164 Kensington Drainage Improvements/Holcomb A - 5 February 14, 2022 Project Number: 18-3019 CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN PUBLIC WORKS DESIGN ENGINEERING Carla Maloney, P.E. Design Engineering Manager 400 West Gowe Kent, WA 98032 Fax: 253-856-6500 PHONE: 253-856-5500 City of Kent Public Works Department Chad Bieren, P.E., Public Works Director Date: June 22, 2021 To: File cc: Shawn Gilbertson, Environmental Supervisor Derek Hawkes, Engineering Supervisor Matt Coy, Environmental Compliance From: Drew Holcomb, P.E., Design Engineer, Regarding: Tacoma St Kensington Ave Drainage Improvement Project Construction Stormwater Pollution Prevention Plan (CSPPP) Project Summary. In the Scenic Hill neighborhood of the City of Kent, there is an existing drainage ditch known as Kensington Ravine that runs from the unopened right of way of Tacoma St. down through the woods to a catch basin on Kensington Ave. This ravine is approximately 350 LF long and drains approximately 23 acres through City right of way and easements on three properties, 807 Tacoma St.; 118 Kensington Ave. S.; and 120 Kensington Ave S. Slopes of the existing wooded ravine vary from approximately 15% to 45%. City outfalls onto one man rock that they have placed at the top of the ditch. This rock has mostly remaining in place since it was added a few years ago, however, it only lines the existing glacial till soil and deposited it downstream. After the placed rock, the ditch continues downhill with varying ditch width and depth. Most concerning is the section - which are being washed downstream and often plug the ravine outlet. The stream drains into a Type 1L catch basin with a trash rack located in an easement directly adjacent to is connected to the City storm system which drains through a pipe, then a swale and then is piped to the Mill Creek Earthworks Dam Park where the stormwater outfalls to Mill Creek. Site Conditions This continually eroding ravine often plugs the outlet grate and causes flooding on the downstream property as well as washouts onto the Kensington Ave. roadway and is a constant maintenance burden for City Drainage Staff especially during periods of intense rainfalls when crews are busy in other parts of the City. This project will maintain this drainage ditch by constructing an open flow channel with large rock to slow the high velocity flow and prevent wash outs. This project will add gabion baskets to prevent additional erosion on the side slopes of the ditch and create check dams to further reduce the water velocity and sediment migration downstream. A new catch basin and trash rack will be installed to reduce instances of the outlet being plugged. Soils The exposed soils on the site are comprised of dense glacial soils at depth. There are some areas of relatively loose/soft surficial material (i.e. forest duff/weathered soils) typical of vegetated slopes. Erosion Construction of this project will require clearing of vegetation and removal of one tree on steep side slopes to access the ditch and place the rock. The exposed soils have the potential to be washed downstream should it rain while they are exposed. In this case the contractor shall cover exposed soil with plastic to prevent it from washing downstream. Construction Schedule and Phasing This project shall be constructed during the dry season to minimize any potential TESC concerns. Phasing to minimize exposed soils on this site will be challenging because of existing steep slopes and lack of access. The contractor will likely access the site by clearing and working their way up the ditch and then placing the rock at the top and working their way down the ditch. Required Elements Element 1: Preserve Vegetation/Mark Clearing Limits Prior to land disturbing activities, including clearing and grading, clearly mark all clearing limits, sensitive areas and their buffers, and trees that are to be preserved within the construction area, both in the field and on the plans, to prevent damage and offsite impacts. Clearing limits shown on plans. Element 2: Establish Construction Access Construction Vehicles can damage or compact soils, create sediment pollution, or track sediment onto public roads. Construction access points are shown on the plans. Element 3: Control Flow Rates Stormwater on a cleared site can create significant flows that can damage downstream properties. This purpose of this project is to control the flow rate of the existing ditch and decrease scour and erosion because it is currently causing problems downstream. We will accomplish this by widening the channel, covering exposed soils with a non-woven geotextile fabric and placing large rock to in the channel to reduce flow velocity. Additionally, we plan to install gabion basket chec reduce velocity in the ditch. Unfortunately, during construction this site does not easily allow for a bypass of stormwater or similar due to it being a drainage ditch. However, exposed side slopes will be covered with plastic in the event of rain and the ditch soils will not be exposed anymore than existing conditions prior to placing the geotextile fabric. Element 4: Install Sediment Controls When land is devegetated, stormwater can pick up sediment, a pollutant. BMPs can prevent sediment from leaving the site. The plans call for the installation of straw wattles on the side slopes. If these are easily overwhelmed or as directed by the engineer, the contractor will install silt fencing or other appropriate BMPs. Element 5: Stabilize Soils Leaving soils devegetated or exposed needlessly creates erosion and sediment problems. No soils will be exposed for more than two days from October 1 to April 30 and no longer than seven days the rest of the year. Exposed side slopes will be covered with jute matting. When rain is forecasted, exposed soils will be covered and secured with plastic. Some sloughing and raveling of exposed or disturbed soil on slopes should be expected. Disturbed soils shall be restored promptly so that surface runoff does not become channeled. Temporary erosion protection shall be used and maintained in areas with exposed or disturbed soils to help reduce erosion and reduce transport of sediment to adjacent areas and receiving waters. Permanent erosion protection will be provided by the proposed project. Element 6: Protect Slopes Slopes can be especially vulnerable to erosion, but BMPs can mitigate sediment problems. No soils will be exposed for more than two days from October 1 to April 30 and no longer than seven days the rest of the year. Exposed side slopes will be covered with jute matting. When rain is forecasted, temporary covering with heavy plastic sheeting will be used to protect these slopes during periods of wet weather. Shallow excavations could experience minor caving. Excavations deeper than 4 feet should be shored or laid back at a stable slope if workers are required to enter. Glacially consolidated soils can maintain near vertical cut slopes for a time. However, near vertical slopes in these soils can also slough quickly and without warning. Element 7: Protect Drain Inlets Storm drains are designed to collect and transport clean stormwater, not water polluted with sediment. Storm drain inlets must be protected so that runoff does not enter the stormwater system without first being filtered or treated to remove sediment. Silt socks will be inserted in downstream catch basins. Element 8: Stabilize Channels and Outlets Stormwater channels and outlets can themselves erode unless stabilized with rock or other armoring. This purpose of this project is to stabilize the existing ditch and decrease scour and erosion. We will accomplish this by widening the channel, cover exposed soils with a non-woven geotextile fabric and place large rock to in the channel to reduce flow velocity. Element 9: Control Pollutants Waste materials, demolition debris, and other pollutants that occur onsite during construction can contaminate the stormwater system unless managed. Cement and related products can modify the pH of stormwater. The Contractor shall prepare a Type 2 Working Drawing consisting of a project-specific spill prevention, control, and countermeasures plan (SPCC Plan), and shall implement the plan for the duration of the project. No on-site construction activities may commence until the Contracting Agency accepts an SPCC Plan for the project. An SPCC Plan template and guidance information is available at www.wsdot.wa.gov/environment/technical/disciplines/hazardous-materials/spill- prevent-report. The SPCC Plan shall address all fuels, petroleum products, hazardous materials, and other materials defined in Chapter 447 of the WSDOT Environmental Manual M 31-11. Occupational safety and health requirements that may pertain to SPCC Plan implementation are contained in, but not limited to, WAC 296-824 and WAC 296-843. The SPCC Plan shall address conditions that may be required by Section 3406 of the current International Fire Code, or as approved by the local Fire Marshal. Element 10: Control De-Watering De-watering water extracted from foundations, vaults, or trenches, has similar characteristics to stormwater runoff at the site and can cause the same impacts unless properly managed. This element does not apply to this project because no dewatering of the site is anticipated. Element 11: Maintain BMPs Best Management Practices (BMPs) are activities, protective measures, and maintenance procedures that, when used singly or in combination, prevent or reduce the impacts of erosion and sediment transport. All temporary and permanent erosion and sediment control BMPs must be maintained and repaired as needed to assure continued performance of their intended function. Sediment control BMPs must be inspected weekly or after a runoff producing storm event during the dry season and daily during the wet season. Element 12: Manage the Project Phasing a project, especially when revegetation occurs as part of each phase, can help prevent the transport of sediment from the site. This Construction SWPPP will be fully implemented at all times and modified and approved as directed by the engineer or whenever there is a change in design, construction, operation, or maintenance at the construction site that has or could have a significant effect on the discharge of pollutants to waters of the state. Element 13: Protect Low-Impact Development BMPs Low-Impact Development techniques can be damaged if they are compacted or accumulate sediment during construction. This element does not apply to this project because there are no Low-Impact Development BMPs planned. SWPPS MEASURES Each of the following categories of Stormwater Pollution Prevention and Spill Control (SWPPS) Standards measures must be considered for application to the project site. The SWPPS standards are located in the King County Surface Water Design Manual, Construction Stormwater Pollution Prevention Standards adopted as Appendix D: Follow effective pollutant handling and disposal procedures. Provide cover and containment for materials, fuel and other pollutants. Manage the project site to maximize pollutant control and minimize pollutant sources. Protect from spills and drips of petroleum products and other pollutants. Avoid over application or untimely application of chemicals and fertilizers. Prevent or treat contamination of stormwater runoff by pH modifying sources. Kensington Drainage Improvements/Holcomb A - 6 February 14, 2022 Project Number: 18-3019 PROJECT SIGN Your Tax Dollars at Work 212th Street Peservation 72nd Ave. S. to 84th Ave. S. $xxx,xxx KentWA.govContractor – Kensington Drainage Improvements/Holcomb A - 7 February 14, 2022 Project Number: 18-3019 PREVAILING WAGE RATES State of Washington Department of Labor & Industries Prevailing Wage Section - Telephone 360-902-5335 PO Box 44540, Olympia, WA 98504-4540 Washington State Prevailing Wage The PREVAILING WAGES listed here include both the hourly wage rate and the hourly rate of fringe benefits. On public works projects, worker's wage and benefit rates must add to not less than this total. A brief description of overtime calculation requirements are provided on the Benefit Code Key. Journey Level Prevailing Wage Rates for the Effective Date: 03/01/2022 County Trade Job Classification Wage Holiday Overtime Note Asbestos Abatement Workers Journey Level $54.62 5D 1 H Boilermakers Journey Level $70.79 5N 1C Brick Mason Journey Level $63.32 7E 1 N Brick Mason Pointer -Caulker -Cleaner $63.32 7E 1N Building Service Employees Janitor $26.28 5S 2F Building Service Employees Traveling Waxer/Shampooer $26.63 5S 2F Building Service Employees Window Cleaner (Non -Scaffold) $29.98 5S 2F Building Service Employees Window Cleaner (Scaffold) $30.98 5S 2F Cabinet Makers In Shop), Journey Level $22.74 1 Carpenters Acoustical Worker $68.24 7A 4C Carpenters Bridge, Dock And Wharf Carpenters $68.19 7A 4C Carpenters Carpenter $68.19 7A 4C Carpenters Floor Finisher $68.19 7A 4C Carpenters Floor Layer $68.19 7A 4C Carpenters Scaffold Erector $68.19 7A 4C Cement Masons Application of all Composition Mastic $67.41 7A 4U Cement Masons Application of all Epoxy Material $66.91 7A 4U Cement Masons Application of all Plastic Material $67.41 7A 4U Cement Masons Application of Sealing Compound $66.91 7A 4U Cement Masons Application of Underlayment $67.41 7A 4U Cement Masons Building General $66.91 7A 4U Cement Masons Composition or Kalman Floors $67.41 7A 4U Cement Masons Concrete Paving $66.91 7A 4U Cement Masons Curb Et Gutter Machine $67.41 7A 4U Cement Masons Curb Et Gutter, Sidewalks $66.91 7A 4U Cement Masons Curing Concrete $66.91 7A 4U Cement Masons Finish Colored Concrete $67.41 7A 4U Cement Masons Floor Grinding $67.41 7A 4U Cement Masons Floor Grinding/Polisher $66.91 7A 4U Cement Masons Green Concrete Saw, self -powered $67.41 7A 4U Cement Masons Grouting of all Plates $66.91 7A 4U Cement Masons Grouting of all Tilt -up Panels $66.91 7A 4U Cement Masons Gunite Nozzleman $67.41 7A 4U Cement Masons Hand Powered Grinder $67.41 7A 4U Cement Masons Journey Level $66.91 7A 4U Cement Masons Patching Concrete $66.91 7A 4U Cement Masons Pneumatic Power Tools $67.41 7A 4U Cement Masons Power Chipping Et Brushing $67.41 7A 4U Cement Masons Sand Blasting Architectural Finish $67.41 7A 4U Cement Masons Screed Et Rodding Machine $67.41 7A 4U Cement Masons Spackling or Skim Coat Concrete $66.91 7A 4U Cement Masons Troweling Machine Operator $67.41 7A 4U *Risk Class View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View View King Cement Masons King Cement Masons King Divers Et Tenders King King King King King King King King King King King King King King King Divers Et Tenders Divers Et Tenders Divers Et Tenders Divers Et Tenders Divers 8 Tenders Divers Et Tenders Divers Et Tenders Divers Et Tenders Dredge Workers Dredge Workers Dredge Workers Dredge Workers Dredge Workers Dredge Workers Dredge Workers Drywall Applicator Drywall Tapers Electrical Fixture Maintenance Workers Electricians - Inside Electricians - Inside Electricians - Inside Electricians - Inside Electricians - Inside Electricians - Inside Electricians - Inside Electricians - Motor Shop Electricians - Powerline Construction Electricians - Powerline Construction Electricians - Powerline Construction Electricians - Powerline Construction Electricians - Powerline Construction Electricians - Powerline Construction Electricians - Powerline Construction Electricians - Powerline Construction Electricians - Powerline Construction Electronic Technicians Elevator Constructors Elevator Constructors Fabricated Precast Concrete Products Fence Erectors Fence Erectors Flaggers Glaziers Heat Et Frost Insulators And Asbestos Workers Heating Equipment Mechanics Hod Carriers Et Mason Tenders Industrial Power Vacuum Cleaner Inland Boatmen Inland Boatmen Inland Boatmen Inland Boatmen Inland Boatmen Troweling Machine Operator on Colored Slabs Tunnel Workers Bell/Vehicle or Submersible Operator (Not Under Pressure) Dive Supervisor/Master Diver Diver On Standby Diver Tender Manifold Operator Manifold Operator Mixed Gas Remote Operated Vehicle Operator/Technician Remote Operated Vehicle Tender Assistant Engineer Assistant Mate (Deckhand) Boatmen Engineer Welder Leverman, Hydraulic Mates Oiler Journey Level Journey Level Journey Level Cable Splicer Cable Splicer (tunnel) Certified Welder Certified Welder (tunnel) Construction Stock Person Journey Level Journey Level (tunnel) Journey Level Cable Splicer Certified Line Welder Groundperson Heavy Line Equipment Operator Journey Level Lineperson Line Equipment Operator Meter Installer Pole Sprayer Powderperson Journey Level Mechanic Mechanic In Charge All Classifications - In -Factory Work Only Fence Erector Fence Laborer Journey Level Journey Level Journey Level Journey Level Journey Level Journey Level Boat Operator Cook Deckhand Deckhand Engineer Launch Operator $67.41 7A 4U View $67.41 7A 4U View $122.49 7A 4C View $86.04 7A 4C View $122.49 7A 4C 8V View $81.04 7A 4C View $73.60 7A 4C View $73.60 7A 4C View $78.60 7A 4C View $73.60 7A 4C View $68.64 7A 4C View $73.62 5D 3F View $73.05 5D 3F View $73.62 5D 3F View $75.03 5D 3F View $76.53 5D 3F View $73.62 5D 3F View $73.05 5D 3F View $67.54 5D 1 H View $67.91 5P 1 E View $33.19 5L 1 E View $94.22 7C 4E View $101.27 7C 4E View $91.00 7C 4E View $97.74 7C 4E View $44.78 7C 4E View $87.80 7C 4E View $94.22 7C 4E View $47.53 5A 1 B View $82.39 5A 4D View $75.64 5A 4D View $49.17 5A 4D View $75.64 5A 4D View $75.64 5A 4D View $64.54 5A 4D View $49.17 5A 4D 8W View $75.64 5A 4D View $56.49 5A 4D View $57.07 7E 1 E View $100.51 7D 4A View $108.53 7D 4A View $18.25 5B 1 R View $46.29 7A 4V BY View $46.29 7A 4V 8Y View $46.29 7A 4V 8Y View $72.41 7L 1Y View $82.02 15H 11C View $91.83 7F 1 E View $57.31 7A 4V 8Y View $14.49 1 View $61.41 5B 1 K View $56.48 5B 1 K View $57.48 5B 1 K View $58.81 5B 1 K View $58.89 5B 1 K View King Inland Boatmen Mate $57.31 5B 1K View King Inspection/Cleaning/Sealing Of Sewer Et Cleaner Operator, Foamer Operator $31.49 1 View Water Systems By Remote Control King Inspection/Cleaning/Sealing Of Sewer 8 Grout Truck Operator $14.49 1 View Water Systems By Remote Control King Inspection/Cleaning/Sealing Of Sewer Et Head Operator $24.91 1 View Water Systems By Remote Control King Inspection/Cleaning/Sealing Of Sewer Et Technician $19.33 1 View Water Systems By Remote Control King Inspection/Cleaning/Sealing Of Sewer 8 Tv Truck Operator $20.45 1 View Water Systems By Remote Control King Insulation Applicators Journey Level $68.19 7A 4C View King Ironworkers Journeyman $78.53 7N 10 View King Laborers Air, Gas Or Electric Vibrating Screed $54.62 7A 4V 8Y View King Laborers Airtrac Drill Operator $56.31 7A 4V 8Y View King Laborers Ballast Regular Machine $54.62 7A 4V 8Y View King Laborers Batch Weighman $46.29 7A 4V 8Y View King Laborers Brick Pavers $54.62 7A 4V 8Y View King Laborers Brush Cutter $54.62 7A 4V 8Y View King Laborers Brush Hog Feeder $54.62 7A 4V 8Y View King Laborers Burner $54.62 7A 4V 8Y View King Laborers Caisson Worker $56.31 7A 4V 8Y View King Laborers Carpenter Tender $54.62 7A 4V 8Y View King Laborers Cement Dumper -paving $55.62 7A 4V 8Y View King Laborers Cement Finisher Tender $54.62 7A 4V 8Y View King Laborers Change House Or Dry Shack $54.62 7A 4V 8Y View King Laborers Chipping Gun (30 Lbs. And Over) $55.62 7A 4V 8Y View King Laborers Chipping Gun (Under 30 Lbs.) $54.62 7A 4V 8Y View King Laborers Choker Setter $54.62 7A 4V 8Y View King Laborers Chuck Tender $54.62 7A 4V 8Y View King Laborers Clary Power Spreader $55.62 7A 4V 8Y View King Laborers Clean-up Laborer $54.62 7A 4V 8Y View King Laborers Concrete Dumper/Chute Operator $55.62 7A 4V 8Y View King Laborers Concrete Form Stripper $54.62 7A 4V 8Y View King Laborers Concrete Placement Crew $55.62 7A 4V 8Y View King Laborers Concrete Saw Operator/Core Driller $55.62 7A 4V 8Y View King Laborers Crusher Feeder $46.29 7A 4V 8Y View King Laborers Curing Laborer $54.62 7A 4V 8Y View King Laborers Demolition: Wrecking 8 Moving (Incl. $54.62 7A 4V 8Y View Charred Material) King Laborers Ditch Digger $54.62 7A 4V 8Y View King Laborers Diver $56.31 7A 4V 8Y View King Laborers Drill Operator (Hydraulic, Diamond) $55.62 7A 4V 8Y View King Laborers Dry Stack Walls $54.62 7A 4V 8Y View King Laborers Dump Person $54.62 7A 4V 8Y View King Laborers Epoxy Technician $54.62 7A 4V 8Y View King Laborers Erosion Control Worker $54.62 7A 4V 8Y View King Laborers Faller Et Bucker Chain Saw $55.62 7A 4V 8Y View King Laborers Fine Graders $54.62 7A 4V 8Y View King Laborers Firewatch $46.29 7A 4V 8Y View King Laborers Form Setter $54.62 7A 4V 8Y View King Laborers Gabian Basket Builders $54.62 7A 4V 8Y View King Laborers General Laborer $54.62 7A 4V 8Y View King Laborers Grade Checker Et Transit Person $57.31 7A 4V 8Y View King Laborers Grinders $54.62 7A 4V 8Y View King Laborers Grout Machine Tender $54.62 7A 4V 8Y View King Laborers Groutmen (Pressure) Including Post $55.62 7A 4V 8Y View Tension Beams King Laborers Guardrail Erector $54.62 7A 4V 8Y View King Laborers Hazardous Waste Worker (Level A) $56.31 7A 4V 8Y View King Laborers Hazardous Waste Worker (Level B) $55.62 7A 4V 8Y View King Laborers Hazardous Waste Worker (Level C) $54.62 7A 4V 8Y View King Laborers High Scaler $56.31 7A 4V 8Y View King Laborers Jackhammer $55.62 7A 4V 8Y View King Laborers Laserbeam Operator $55.62 7A 4V 8Y View King Laborers Maintenance Person $54.62 7A 4V 8Y View King Laborers Manhole Builder-Mudman $55.62 7A 4V 8Y View King Laborers Material Yard Person $54.62 7A 4V 8Y View King Laborers Motorman -Dinky Locomotive $55.62 7A 4V 8Y View King Laborers nozzleman (concrete pump, green cutter $57.31 7A 4V 8Y View when using combination of high pressure air Et water on concrete Et rock, sandblast, gunite, shotcrete, water blaster, vacuum blaster) King Laborers Pavement Breaker $55.62 7A 4V 8Y View King Laborers Pilot Car $46.29 7A 4V 8Y View King Laborers Pipe Layer (Lead) $57.31 7A 4V 8Y View King Laborers Pipe Layer/Tailor $55.62 7A 4V 8Y View King Laborers Pipe Pot Tender $55.62 7A 4V 8Y View King Laborers Pipe Reliner $55.62 7A 4V 8Y View King Laborers Pipe Wrapper $55.62 7A 4V 8Y View King Laborers Pot Tender $54.62 7A 4V 8Y View King Laborers Powderman $56.31 7A 4V BY View King Laborers Powderman's Helper $54.62 7A 4V 8Y View King Laborers Power Jacks $55.62 7A 4V 8Y View King Laborers Railroad Spike Puller - Power $55.62 7A 4V 8Y View King Laborers Raker - Asphalt $57.31 7A 4V 8Y View King Laborers Re-timberman $56.31 7A 4V 8Y View King Laborers Remote Equipment Operator $55.62 7A 4V 8Y View King Laborers Rigger/Signal Person $55.62 7A 4V 8Y View King Laborers Rip Rap Person $54.62 7A 4V 8Y View King Laborers Rivet Buster $55.62 7A 4V 8Y View King Laborers Rodder $55.62 7A 4V 8Y View King Laborers Scaffold Erector $54.62 7A 4V 8Y View King Laborers Scale Person $54.62 7A 4V 8Y View King Laborers Sloper (Over 20") $55.62 7A 4V 8Y View King Laborers Sloper Sprayer $54.62 7A 4V 8Y View King Laborers Spreader (Concrete) $55.62 7A 4V 8Y View King Laborers Stake Hopper $54.62 7A 4V 8Y View King Laborers Stock Piler $54.62 7A 4V 8Y View King Laborers Swinging Stage/Boatswain Chair $46.29 7A 4V 8Y View King Laborers Tamper Et Similar Electric, Air Et Gas $55.62 7A 4V 8Y View Operated Tools King Laborers Tamper (Multiple Et Self-propelled) $55.62 7A 4V 8Y View King Laborers Timber Person - Sewer (Lagger, Shorer Et $55.62 7A 4V 8Y View Cribber) King Laborers Toolroom Person (at Jobsite) $54.62 7A 4V 8Y View King Laborers Topper $54.62 7A 4V 8Y View King Laborers Track Laborer $54.62 7A 4V 8Y View King Laborers Track Liner (Power) $55.62 7A 4V 8Y View King Laborers Traffic Control Laborer $49.50 7A 4V 9C View King Laborers Traffic Control Supervisor $52.45 7A 4V 9C View King Laborers Truck Spotter $54.62 7A 4V 8Y View King Laborers Tugger Operator $55.62 7A 4V 8Y View King Laborers Tunnel Work -Compressed Air Worker 0-30 $142.82 7A 4V 9B View psi King Laborers Tunnel Work -Compressed Air Worker $147.85 7A 4V 9B View 30.01-44.00 psi King Laborers Tunnel Work -Compressed Air Worker $151.53 7A 4V 9B View 44.01-54.00 psi King Laborers Tunnel Work -Compressed Air Worker $157.23 7A 4V 913 View 54.01-60.00 psi King Laborers Tunnel Work -Compressed Air Worker $159.35 7A 4V 9B View 60.01-64.00 psi King Laborers Tunnel Work -Compressed Air Worker $164.45 7A 4V 9B View 64.01-68.00 psi King Laborers Tunnel Work -Compressed Air Worker $166.35 7A 4V 9B View 68.01-70.00 psi King Laborers Tunnel Work -Compressed Air Worker $168.35 7A 4V 9B View 70.01-72.00 psi King Laborers Tunnel Work -Compressed Air Worker $170.35 7A 4V 96 View 72.01-74.00 psi King Laborers Tunnel Work-Guage and Lock Tender $57.41 7A 4V 8Y View King Laborers Tunnel Work -Miner $57.41 7A 4V 8Y View King Laborers Vibrator $55.62 7A 4V 8Y View King Laborers Vinyl Seamer $54.62 7A 4V 8Y View King Laborers Watchman $42.08 7A 4V 8Y View King Laborers Welder $55.62 7A 4V 8Y View King Laborers Well Point Laborer $55.62 7A 4V 8Y View King Laborers Window Washer/Cleaner $42.08 7A 4V 8Y View King Laborers - Underground Sewer Et Water General Laborer Et Topman $54.62 7A 4V 8Y View King Laborers - Underground Sewer Et Water Pipe Layer $55.62 7A 4V 8Y View King Landscape Construction Landscape Construction/Landscaping Or $42.08 7A 4V 8Y View Planting Laborers King Landscape Construction Landscape Operator $75.50 15J 11G 8X View King Landscape Maintenance Groundskeeper $17.87 1 View King Lathers Journey Level $67.54 5D 1 H View King Marble Setters Journey Level $63.32 7E 1 N View King Metal Fabrication In Shop) Fitter/Certified Welder $40.39 151 11E View King Metal Fabrication In Shop). General Laborer $28.86 151 11E View King Metal Fabrication In Shop) Mechanic $41.78 151 11E View King Metal Fabrication In Shop), Welder/Burner $37.64 151 11E View King Millwright Journey Level $69.64 7A 4C View King Modular Buildings Cabinet Assembly $14.49 1 View King Modular Buildings Electrician $14.49 1 View King Modular Buildings Equipment Maintenance $14.49 1 View King Modular Buildings Plumber $14.49 1 View King Modular Buildings Production Worker $14.49 1 View King Modular Buildings Tool Maintenance $14.49 1 View King Modular Buildings Utility Person $14.49 1 View King Modular Buildings Welder $14.49 1 View King Painters Journey Level $47.70 6Z 2B View h King Pile Driver Crew Tender $62.69 7A 4C View King Pile Driver Crew Tender/Technician $62.69 7A 4C View King Pile Driver Hyperbaric Worker - Compressed Air $85.00 7A 4C View Worker 0-30.00 PSI King Pile Driver Hyperbaric Worker - Compressed Air $90.00 7A 4C View Worker 30.01 - 44.00 PSI King Pile Driver Hyperbaric Worker - Compressed Air $94.00 7A 4C View Worker 44.01 - 54.00 PSI King Pile Driver Hyperbaric Worker - Compressed Air $99.00 7A 4C View Worker 54.01 - 60.00 PSI King Pile Driver Hyperbaric Worker - Compressed Air $101.50 7A 4C View Worker 60.01 - 64.00 PSI King Pile Driver Hyperbaric Worker - Compressed Air $106.50 7A 4C View Worker 64.01 - 68.00 PSI King Pile Driver Hyperbaric Worker - Compressed Air $108.50 7A 4C View Worker 68.01 - 70.00 PSI King Pile Driver Hyperbaric Worker - Compressed Air $110.50 7A 4C View Worker 70.01 - 72.00 PSI King Pile Driver Hyperbaric Worker - Compressed Air $112.50 7A 4C View Worker 72.01 - 74.00 PSI King Pile Driver Journey Level $68.64 7A 4C View King Plasterers Journey Level $64.14 M 1 R View King Plasterers Nozzleman $67.64 ZQ 1 R View King Playground Et Park Equipment Installers Journey Level $14.49 1 View King Plumbers Et Pipefitters Journey Level $93.69 6Z 1G View King Power Equipment Operators Asphalt Plant Operators $76.77 15J 11G 8X View King Power Equipment Operators Assistant Engineer $72.30 7A 11H 8X View King Power Equipment Operators Barrier Machine (zipper) $76.09 15J 11G 8X View King Power Equipment Operators Batch Plant Operator: concrete $76.09 15J 11G 8X View King Power Equipment Operators Boat Operator $76.87 7A 11H 8X View King Power Equipment Operators Bobcat $72.20 15J 11G 8X View King Power Equipment Operators _ Brokk - Remote Demolition Equipment $72.20 15J 11G 8X View King Power Equipment Operators Brooms _ $72.20 15J 11G 8X View King Power Equipment Operators Bump Cutter $76.09 15J 11G 8X View King Power Equipment Operators Cableways $76.77 15J 11G 8X View King Power Equipment Operators Chipper $76.09 15J 11G 8X View King Power Equipment Operators Compressor $72.20 15J 11G 8X View King Power Equipment Operators Concrete Finish Machine - Laser Screed $72.20 15J 11G 8X View King Power Equipment Operators Concrete Pump - Mounted Or Trailer High $75.50 15J 11G 8X View Pressure Line Pump, Pump High Pressure King Power Equipment Operators Concrete Pump: Truck Mount With Boom $76.77 15J 11G 8X View Attachment Over 42 M King Power Equipment Operators Concrete Pump: Truck Mount With Boom $76.09 15J 11G 8X View Attachment Up To 42m King Power Equipment Operators Conveyors $75.50 15J 11G 8X View King Power Equipment Operators Cranes Friction: 200 tons and over $79.20 7A 11H 8X View King Power Equipment Operators Cranes, A -frame: 10 tons and under $72.30 7A 11H 8X View King Power Equipment Operators Cranes: 100 tons through 199 tons, or $77.63 7A 11H 8X View 150' of boom (including jib with attachments) King Power Equipment Operators Cranes: 20 tons through 44 tons with $76.19 7A 11H 8X View attachments King Power Equipment Operators Cranes: 200 tons- 299 tons, or 250' of $78.44 7A 11H 8X View boom including jib with attachments King Power Equipment Operators Cranes: 300 tons and over or 300' of $79.20 7A 11H 8X View boom including jib with attachments King Power Equipment Operators Cranes: 45 tons through 99 tons, under $76.87 7A 11H 8X View 150' of boom(including jib with attachments) King Power Equipment Operators Cranes: Friction cranes through 199 tons $78.44 7A 11H 8X View King Power Equipment Operators Cranes: through 19 tons with $75.60 7A 11H 8X View attachments, a -frame over 10 tons King Power Equipment Operators Crusher $76.09 15J 11G 8X View King Power Equipment Operators Deck Engineer/Deck Winches (power) $76.09 15J 11G 8X View King Power Equipment Operators Derricks, On Building Work $76.77 15J 11G 8X View King Power Equipment Operators Dozers D-9 Et Under $75.50 15J 11G 8X View King Power Equipment Operators Drill Oilers: Auger Type, Truck Or Crane $75.50 15J 11G 8X View Mount King Power Equipment Operators Drilling Machine $77.53 15J 11G 8X View King Power Equipment Operators Elevator and man -lift: permanent and $72.30 7A 11H 8X View shaft type King Power Equipment Operators Finishing Machine, Bidwell And Gamaco $76.09 15J 11G 8X View 8 Similar Equipment King Power Equipment Operators Forklift: 3000 lbs and over with $75.60 7A 11H 8X View attachments King Power Equipment Operators Forklifts: under 3000 lbs. with $72.30 7A 11H 8X View attachments King Power Equipment Operators Grade Engineer: Using Blue Prints, Cut $76.09 15J 11G 8X View Sheets, Etc King Power Equipment Operators Gradechecker/Stakeman $72.20 15J 11G 8X View King Power Equipment Operators Guardrail Punch $76.09 15J 11G 8X View King Power Equipment Operators Hard Tail End Dump Articulating Off- $76.77 15J 11G 8X View Road Equipment 45 Yards. Et Over King Power Equipment Operators Hard Tail End Dump Articulating Off -road $76.09 15J 11G 8X View Equipment Under 45 Yards King Power Equipment Operators Horizontal/Directional Drill Locator $75.50 15J 11G 8X View King Power Equipment Operators Horizontal/Directional Drill Operator $76.09 15J 11G 8X View King Power Equipment Operators Hydralifts/Boom Trucks Over 10 Tons $75.60 7A 11H 8X View King Power Equipment Operators Hydralifts/boom trucks: 10 tons and $72.30 7A 11H 8X View under King Power Equipment Operators Leverman $78.44 7A 11H 8X View King Power Equipment Operators Loader, Overhead, 6 Yards. But Not $76.77 15J 11G 8X View Including 8 Yards King Power Equipment Operators Loaders, Overhead Under 6 Yards $76.09 15J 11G 8X View King Power Equipment Operators Loaders, Plant Feed $76.09 15J 11G 8X View King Power Equipment Operators Loaders: Elevating Type Belt $75.50 15J 11G 8X View King Power Equipment Operators Locomotives, All $76.09 15J 11G 8X View King Power Equipment Operators Material Transfer Device $76.09 15J 11G 8X View King Power Equipment Operators Mechanics: all (Leadmen - $0.50 per hour $77.63 7A 11H 8X View over mechanic) King Power Equipment Operators Motor Patrol Graders $76.77 15J 11G 8X View King Power Equipment Operators Mucking Machine, Mole, Tunnel Drill, $76.77 15J 11G 8X View Boring, Road Header And/or Shield King Power Equipment Operators Oil Distributors, Blower Distribution Et $72.20 15J 11G 8X View Mulch Seeding Operator King Power Equipment Operators Outside Hoists (elevators and manlifts), $75.60 7A 11H 8X View Air Tuggers, Strato King Power Equipment Operators Overhead, bridge type: 100 tons and $77.63 7A 11H 8X View over King Power Equipment Operators Overhead, bridge type: 45 tons through $76.87 7A 11H 8X View 99 tons King Power Equipment Operators Pavement Breaker $72.20 15J 11G 8X View King Power Equipment Operators Pile Driver (other Than Crane Mount) $76.09 15J 11G 8X View King Power Equipment Operators Plant Oiler - Asphalt, Crusher $75.50 15J 11G 8X View King Power Equipment Operators Posthole Digger, Mechanical $72.20 15J 11G 8X View King Power Equipment Operators Power Plant $72.20 15J 11G 8X View King Power Equipment Operators Pumps - Water $72.20 15J 11G 8X View King Power Equipment Operators Quad 9, Hd 41, D10 And Over $76.77 15J 11G 8X View King Power Equipment Operators Remote Control Operator On Rubber $76.77 15J 11G 8X View Tired Earth Moving Equipment King Power Equipment Operators Rigger and Bellman $72.30 7A 11H 8X View King Power Equipment Operators Rigger/Signal Person, Bellman(Certified) $75.60 7A 11H 8X View King Power Equipment Operators Rollagon $76.77 15J 11G 8X View King Power Equipment Operators Roller, Other Than Plant Mix $72.20 15J 11G 8X View King Power Equipment Operators Roller, Plant Mix Or Multi -lift Materials $75.50 15J 11G 8X View King Power Equipment Operators Roto-mill, Roto-grinder $76.09 15J 11G 8X View King Power Equipment Operators Saws - Concrete $75.50 15J 11G 8X View King Power Equipment Operators Scraper, Self Propelled Under 45 Yards $76.09 15J 11G 8X View King Power Equipment Operators Scrapers - Concrete 8t Carry All $75.50 15J 11G 8X View King Power Equipment Operators Scrapers, Self-propelled: 45 Yards And $76.77 15J 11G 8X View Over King Power Equipment Operators Service Engineers: equipment $75.60 7A 11H 8X View King Power Equipment Operators Shotcrete/Gunite Equipment $72.20 15J 11G 8X View King Power Equipment Operators Shovel, Excavator, Backhoe, Tractors $75.50 15J 11G 8X View Under 15 Metric Tons King Power Equipment Operators Shovel, Excavator, Backhoe: Over 30 $76.77 15J 11G 8X View Metric Tons To 50 Metric Tons King Power Equipment Operators Shovel, Excavator, Backhoes, Tractors: 15 $76.09 15J 11G 8X View To 30 Metric Tons King Power Equipment Operators Shovel, Excavator, Backhoes: Over 50 $77.53 15J 11G 8X View Metric Tons To 90 Metric Tons King Power Equipment Operators Shovel, Excavator, Backhoes: Over 90 $78.33 15J 11G 8X View Metric Tons King Power Equipment Operators Slipform Pavers $76.77 15J 11G 8X View King Power Equipment Operators Spreader, Topsider Et Screedman $76.77 15J 11G 8X View King Power Equipment Operators Subgrader Trimmer $76.09 15J 11G 8X View King Power Equipment Operators Tower Bucket Elevators $75.50 15J 11G 8X View King Power Equipment Operators Tower Crane: over 175' through 250' in $78.44 7A 11H 8X View height, base to boom King Power Equipment Operators Tower crane: up to 175' in height base to $77.63 7A 11H 8X View boom King Power Equipment Operators Tower Cranes: over 250' in height from $79.20 7A 11H 8X View base to boom King Power Equipment Operators Transporters, All Track Or Truck Type $76.77 15J 11G 8X View King Power Equipment Operators Trenching Machines $75.50 15J 11G 8X View King Power Equipment Operators Truck crane oiler/driver: under 100 tons $75.60 7A 11H 8X View King Power Equipment Operators Truck Mount Portable Conveyor $76.09 15J 11G 8X View King Power Equipment Operators Welder $76.87 7A 11H 8X View King Power Equipment Operators Wheel Tractors, Farmall Type $72.20 15J 11G 8X View King Power Equipment Operators Yo Yo Pay Dozer $76.09 15J 11G 8X View King Power Equipment Operators- Asphalt Plant Operators $76.77 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Assistant Engineer $72.30 7A 11H 8X View Underground Sewer 8 Water King Power Equipment Operators- Barrier Machine (zipper) $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Batch Plant Operator, Concrete $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Boat Operator $76.87 7A 11H 8X View Underground Sewer 8 Water King Power Equipment Operators- Bobcat $72.20 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Brokk - Remote Demolition Equipment $72.20 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Brooms $72.20 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Bump Cutter $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Cableways $76.77 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Chipper $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Compressor $72.20 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Concrete Finish Machine - Laser Screed $72.20 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Concrete Pump - Mounted Or Trailer High $75.50 15J 11G 8X View Underground Sewer Et Water Pressure Line Pump, Pump High Pressure King Power Equipment Operators- Concrete Pump: Truck Mount With Boom $76.77 15J 11G 8X View Underground Sewer Et Water Attachment Over 42 M King Power Equipment Operators- Concrete Pump: Truck Mount With Boom $76.09 15J 11G 8X View Underground Sewer Et Water Attachment Up To 42m King Power Equipment Operators- Conveyors $75.50 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Cranes Friction: 200 tons and over $79.20 7A 11H 8X View Underground Sewer 8 Water King Power Equipment Operators- Cranes, A -frame: 10 tons and under $72.30 7A 11H 8X View Underground Sewer Et Water King Power Equipment Operators- Cranes: 100 tons through 199 tons, or $77.63 7A 11H 8X View Underground Sewer 8 Water 150' of boom (including jib with attachments) King Power Equipment Operators- Cranes: 20 tons through 44 tons with $76.19 7A 11H 8X View Underground Sewer 8 Water attachments King Power Equipment Operators- Cranes: 20 tons through 44 tons with $76.19 7A 11H 8X View Underground Sewer Et Water attachments King Power Equipment Operators- Cranes: 200 tons- 299 tons, or 250' of $78.44 7A 11H 8X View Underground Sewer 8 Water boom including jib with attachments King Power Equipment Operators- Cranes: 300 tons and over or 300' of $79.20 7A 11H 8X View Underground Sewer Et Water boom including jib with attachments King Power Equipment Operators- Cranes: 45 tons through 99 tons, under $76.87 7A 11H 8X View Underground Sewer Et Water 150' of boom(including jib with attachments) King Power Equipment Operators- Cranes: Friction cranes through 199 tons $78.44 7A 11H 8X View Underground Sewer Et Water King Power Equipment Operators- Cranes: through 19 tons with $75.60 7A 11H 8X View Underground Sewer Et Water attachments, a -frame over 10 tons King Power Equipment Operators- Crusher $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Deck Engineer/Deck Winches (power) $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Derricks, On Building Work $76.77 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Dozers D-9 8 Under $75.50 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Drill Oilers: Auger Type, Truck Or Crane $75.50 15J 11G 8X View Underground Sewer Et Water Mount King Power Equipment Operators- Drilling Machine $77.53 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Elevator and man -lift: permanent and $72.30 7A 11H 8X View Underground Sewer 8 Water shaft type King Power Equipment Operators- Finishing Machine, Bidwell And Gamaco $76.09 15J 11G 8X View Underground Sewer Et Water Et Similar Equipment King Power Equipment Operators- Forklift: 3000 lbs and over with $75.60 7A 11H 8X View Underground Sewer Et Water attachments King Power Equipment Operators- Forklifts: under 3000 lbs. with $72.30 7A 11H 8X View Underground Sewer Et Water attachments King Power Equipment Operators- Grade Engineer: Using Blue Prints, Cut $76.09 15J 11G 8X View Underground Sewer Et Water Sheets, Etc King Power Equipment Operators- Gradechecker/Stakeman $72.20 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Guardrail Punch $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Hard Tail End Dump Articulating Off- $76.77 15J 11G 8X View Underground Sewer Et Water Road Equipment 45 Yards. Et Over King Power Equipment Operators- Hard Tail End Dump Articulating Off -road $76.09 15J 11G 8X View Underground Sewer Et Water Equipment Under 45 Yards King Power Equipment Operators- Horizontal/Directional Drill Locator $75.50 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Horizontal/Directional Drill Operator $76.09 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Hydralifts/boom trucks: 10 tons and $72.30 7A 11H 8X View Underground Sewer 8 Water under King Power Equipment Operators- Hydralifts/boom trucks: over 10 tons $75.60 7A 11H 8X View Underground Sewer Et Water King Power Equipment Operators- Leverman $78.44 7A 11H 8X View Underground Sewer Et Water King Power Equipment Operators- Loader, Overhead, 6 Yards. But Not $76.77 15J 11G 8X View Underground Sewer Et Water Including 8 Yards King Power Equipment Operators- Loaders, Overhead Under 6 Yards $76.09 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Loaders, Plant Feed $76.09 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Loaders: Elevating Type Belt $75.50 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Locomotives, All $76.09 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Material Transfer Device $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Mechanics: all (Leadmen - $0.50 per hour $77.63 7A 11H 8X View Underground Sewer Et Water over mechanic) King Power Equipment Operators- Motor Patrol Graders $76.77 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Mucking Machine, Mole, Tunnel Drill, $76.77 15J 11G 8X View Underground Sewer Et Water Boring, Road Header And/or Shield King Power Equipment Operators- Oil Distributors, Blower Distribution Et $72.20 15J 11G 8X View Underground Sewer 8 Water Mulch Seeding Operator King Power Equipment Operators- Outside Hoists (elevators and manlifts), $75.60 7A 11H 8X View Underground Sewer Et Water Air Tuggers, Strato King Power Equipment Operators- Overhead, bridge type: 100 tons and $77.63 7A 11H 8X View Underground Sewer 8 Water over King Power Equipment Operators- Overhead, bridge type: 45 tons through $76.87 7A 11H 8X View Underground Sewer Et Water 99 tons King Power Equipment Operators- Pavement Breaker $72.20 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Pile Driver (other Than Crane Mount) $76.09 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Plant Oiler - Asphalt, Crusher $75.50 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Posthole Digger, Mechanical $72.20 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Power Plant $72.20 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Pumps - Water $72.20 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Quad 9, Hd 41, D10 And Over $76.77 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Remote Control Operator On Rubber $76.77 15J 11G 8X View Underground Sewer Et Water Tired Earth Moving Equipment King Power Equipment Operators- Rigger and Bellman $72.30 7A 11H 8X View Underground Sewer Et Water King Power Equipment Operators- Rigger/Signal Person, Bellman(Certified) $75.60 7A 11H 8X View Underground Sewer Et Water King Power Equipment Operators- Rollagon $76.77 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Roller, Other Than Plant Mix $72.20 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Roller, Plant Mix Or Multi -lift Materials $75.50 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Roto-mill, Roto-grinder $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Saws - Concrete $75.50 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Scraper, Self Propelled Under 45 Yards $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Scrapers - Concrete Et Carry All $75.50 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Scrapers, Self-propelled: 45 Yards And $76.77 15J 11G 8X View Underground Sewer 8 Water Over King Power Equipment Operators- Service Engineers: equipment $75.60 7A 11H 8X View Underground Sewer Et Water King Power Equipment Operators- Shotcrete/Gunite Equipment $72.20 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Shovel, Excavator, Backhoe, Tractors $75.50 15J 11G 8X View Underground Sewer Et Water Under 15 Metric Tons King Power Equipment Operators- Shovel, Excavator, Backhoe: Over 30 $76.77 15J 11G 8X View Underground Sewer Et Water Metric Tons To 50 Metric Tons King Power Equipment Operators- Shovel, Excavator, Backhoes, Tractors: 15 $76.09 15J 11G 8X View Underground Sewer 8 Water To 30 Metric Tons King Power Equipment Operators- Shovel, Excavator, Backhoes: Over 50 $77.53 15J 11G 8X View Underground Sewer Et Water Metric Tons To 90 Metric Tons King Power Equipment Operators- Shovel, Excavator, Backhoes: Over 90 $78.33 15J 11G 8X View Underground Sewer 8 Water Metric Tons King Power Equipment Operators- Slipform Pavers $76.77 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Spreader, Topsider Et Screedman $76.77 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Subgrader Trimmer $76.09 15J 11G 8X View Underground Sewer 8 Water King Power Equipment Operators- Tower Bucket Elevators $75.50 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Tower Crane: over 175' through 250' in $78.44 7A 11H 8X View Underground Sewer 8 Water height, base to boom King Power Equipment Operators- Tower crane: up to 175' in height base to $77.63 7A 11H 8X View Underground Sewer Et Water boom King Power Equipment Operators- Tower Cranes: over 250' in height from $79.20 7A 11H 8X View Underground Sewer 8 Water base to boom King Power Equipment Operators- Transporters, All Track Or Truck Type $76.77 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Trenching Machines $75.50 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Truck Crane Oiler/Driver: 100 tons and $76.19 7A 11H 8X View Underground Sewer 8 Water over King Power Equipment Operators- Truck crane oiler/driver: under 100 tons $75.60 7A 11H 8X View Underground Sewer Et Water King Power Equipment Operators- Truck Mount Portable Conveyor $76.09 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Welder $76.87 7A 11H 8X View Underground Sewer Et Water King Power Equipment Operators- Wheel Tractors, Farmall Type $72.20 15J 11G 8X View Underground Sewer Et Water King Power Equipment Operators- Yo Yo Pay Dozer $76.09 15J 11G 8X View Underground Sewer 8 Water King Power Line Clearance Tree Trimmers Journey Level In Charge $55.03 5A 4A View King Power Line Clearance Tree Trimmers Spray Person $52.24 5A 4A View King Power Line Clearance Tree Trimmers Tree Equipment Operator $55.03 5A 4A View King Power Line Clearance Tree Trimmers Tree Trimmer $49.21 5A 4A View King Power Line Clearance Tree Trimmers Tree Trimmer Groundperson $37.47 5A 4A View King Refrigeration Et Air Conditioning Journey Level $88.51 6Z 1G View Mechanics King Residential Brick Mason Journey Level $63.32 7E 1 N View King Residential Carpenters Journey Level $36.44 1 View King Residential Cement Masons Journey Level $46.64 1 View King Residential Drywall Applicators Journey Level $68.19 7A 4C View King Residential Drywall Tapers Journey Level $36.36 1 View King Residential Electricians Journey Level $48.80 1 View King Residential Glaziers Journey Level $28.93 1 View King Residential Insulation Applicators Journey Level $28.18 1 View King Residential Laborers Journey Level $29.73 1 View King Residential Marble Setters Journey Level $27.38 1 View King Residential Painters Journey Level $23.47 1 View King Residential Plumbers 8 Pipefitters Journey Level $93.69 6Z 1G View King Residential Refrigeration Et Air Journey Level $88.51 6Z 1G View Conditioning Mechanics King Residential Sheet Metal Workers Journey Level $91.83 7F 1 E View King Residential Soft Floor Layers Journey Level $51.91 5A 3J View King Residential Sprinkler Fitters (Fire Journey Level $53.04 5C 211 View Protection), King Residential Stone Masons Journey Level $63.32 7E 1 N View King Residential Terrazzo Workers Journey Level $57.71 7E 1 N View King Residential Terrazzo/Tile Finishers Journey Level $24.39 1 View King Residential Tile Setters Journey Level $21.04 1 View King Roofers Journey Level $57.30 5A 3H View King Roofers Using Irritable Bituminous Materials $60.30 5A 3H View King Sheet Metal Workers Journey Level (Field or Shop) $91.83 7F 1 E View King Shipbuilding 8 Ship Repair New Construction Boilermaker $39.58 7V 1 View King Shipbuilding Et Ship Repair New Construction Carpenter $39.58 7V 1 View King Shipbuilding It Ship Repair New Construction Crane Operator $39.58 7V 1 View King Shipbuilding 8 Ship Repair New Construction Electrician $39.58 7V 1 View King Shipbuilding Et Ship Repair New Construction Heat Et Frost Insulator $82.02 15H 11C View King Shipbuilding 8 Ship Repair New Construction Laborer $39.58 7V 1 View King Shipbuilding Et Ship Repair New Construction Machinist $39.58 7V 1 View King Shipbuilding 8 Ship Repair New Construction Operating Engineer $39.58 7V 1 View King Shipbuilding 8 Ship Repair New Construction Painter $39.58 7V 1 View King Shipbuilding Et Ship Repair New Construction Pipefitter $39.58 7V 1 View King Shipbuilding 8 Ship Repair New Construction Rigger $39.58 7V 1 View King Shipbuilding Et Ship Repair New Construction Sheet Metal $39.58 7V 1 View King Shipbuilding 8 Ship Repair New Construction Shipfitter $39.58 7V 1 View King Shipbuilding Et Ship Repair New Construction Warehouse/Teamster $39.58 7V 1 View King Shipbuilding Et Ship Repair New Construction Welder / Burner $39.58 7V 1 View King Shipbuilding 8 Ship Repair Ship Repair Boilermaker $47.45 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Carpenter $47.35 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Crane Operator $45.06 7Y 4K View King Shipbuilding Et Ship Repair Ship Repair Electrician $47.42 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Heat Et Frost Insulator $82.02 15H 11C View King Shipbuilding Et Ship Repair Ship Repair Laborer $47.35 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Machinist $47.35 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Operating Engineer $45.06 7Y 4K View King Shipbuilding Et Ship Repair Ship Repair Painter $47.35 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Pipefitter $47.35 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Rigger $47.45 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Sheet Metal $47.35 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Shipwright $47.35 7X 4J View King Shipbuilding Et Ship Repair Ship Repair Warehouse / Teamster $45.06 7Y 4K View King Sign Makers Et Installers (Electrical) Journey Level $53.62 0 1 View King Sign Makers Et Installers (Non -Electrical), Journey Level $34.43 0 1 View King Soft Floor Layers Journey Level $51.91 5A 3J View King Solar Controls For Windows Journey Level $14.49 1 View King Sprinkler Fitters (Fire Protection) Journey Level $87.99 5C 1X View King Stage Rigging Mechanics (Non Structural). Journey Level $14.49 1 View King Stone Masons Journey Level $63.32 7E 1N View King Street And Parking Lot Sweeper Workers Journey Level $19.09 1 View King Surveyors Assistant Construction Site Surveyor $75.60 7A 11H 8X View King Surveyors Chainman $72.30 7A 11H 8X View King Surveyors Construction Site Surveyor $76.87 7A 11H 8X View King Surveyors Drone Operator (when used in $72.30 7A 11H 8X View conjunction with survey work only) King Telecommunication Technicians Journey Level $57.07 7E 1 E View King Telephone Line Construction - Outside Cable Splicer $38.27 5A 2B View King Telephone Line Construction - Outside Hole Digger/Ground Person $25.66 5A 2B View King Telephone Line Construction - Outside Telephone Equipment Operator (Light) $31.96 5A 2B View King Telephone Line Construction - Outside Telephone Lineperson $36.17 5A 2B View King Terrazzo Workers Journey Level $57.71 7E 1N View King Tile Setters Journey Level $57.71 7E 1N View King Tile, Marble Et Terrazzo Finishers Finisher $48.54 7E 1N View King Traffic Control Stripers Journey Level $50.51 7A 1 K View King Truck Drivers Asphalt Mix Over 16 Yards $69.95 15J ill 8L View King Truck Drivers Asphalt Mix To 16 Yards $69.11 15J ill 8L View King Truck Drivers Dump Truck $69.11 15J 111 8L View King Truck Drivers Dump Truck Et Trailer $69.95 15J 111 8L View King Truck Drivers Other Trucks $69.95 15J ill 8L View King Truck Drivers - Ready Mix Transit Mix $69.95 15J ill 8L View King Well Drillers Et Irrigation Pump Installers Irrigation Pump Installer $17.71 1 View King Well Drillers Et Irrigation Pump Installers Oiler $14.49 1 View King Well Drillers Et Irrigation Pump Installers Well Driller $18.00 1 View Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Overtime Codes Overtime calculations are based on the hourly rate actually paid to the worker. On public works projects, the hourly rate must be not less than the prevailing rate of wage minus the hourly rate of the cost of fringe benefits actually provided for the worker. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE. B. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. C. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. D. The first two (2) hours before or after a five -eight (8) hour workweek day or a four -ten (10) hour workweek day and the first eight (8) hours worked the next day after either workweek shall be paid at one and one-half times the hourly rate of wage. All additional hours worked and all worked on Sundays and holidays shall be paid at double the hourly rate of wage. E. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. F. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours worked, except Labor Day, shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage. G. The first ten (10) hours worked on Saturdays and the first ten (10) hours worked on a fifth calendar weekday in a four - ten hour schedule, shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten (10) hours per day Monday through Saturday and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. H. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions or equipment breakdown) shall be paid at one and one-half times the hourly rate of wage. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. I. All hours worked on Sundays and holidays shall also be paid at double the hourly rate of wage. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid atone and one-half times the hourly rate of wage. All hours worked over ten (10) hours Monday through Saturday, Sundays and holidays shall be paid at double the hourly rate of wage. K. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage. M. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. N. All hours worked on Saturdays (except makeup days) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. 1of15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Overtime Codes Continued O. The first ten (10) hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays, holidays and after twelve (12) hours, Monday through Friday and after ten (10) hours on Saturday shall be paid at double the hourly rate of wage. P. All hours worked on Saturdays (except makeup days if circumstances warrant) and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage. Q. The first two (2) hours after eight (8) regular hours Monday through Friday and up to ten (10) hours worked on Saturdays shall be paid atone and one-half times the hourly rate of wage. All hours worked in excess often (10) hours per day Monday through Saturday and all hours worked on Sundays and holidays (except Christmas day) shall be paid at double the hourly rate of wage. All hours worked on Christmas day shall be paid at two and one-half times the hourly rate of wage. R. All hours worked on Sundays and holidays shall be paid at two times the hourly rate of wage. U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays (except Labor Day) shall be paid at two times the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage. V. All hours worked on Sundays and holidays (except Thanksgiving Day and Christmas day) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Thanksgiving Day and Christmas day shall be paid at double the hourly rate of wage. W. All hours worked on Saturdays and Sundays (except make-up days due to conditions beyond the control of the employer)) shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage. X. The first four (4) hours after eight (8) regular hours Monday through Friday and the first twelve (12) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked over twelve (12) hours Monday through Saturday, Sundays and holidays shall be paid at double the hourly rate of wage. When holiday falls on Saturday or Sunday, the day before Saturday, Friday, and the day after Sunday, Monday, shall be considered the holiday and all work performed shall be paid at double the hourly rate of wage. Y. All hours worked outside the hours of 5:00 am and 5:00 pm (or such other hours as may be agreed upon by any employer and the employee) and all hours worked in excess of eight (8) hours per day (10 hours per day for a 4 x 10 workweek) and on Saturdays and holidays (except labor day) shall be paid at one and one-half times the hourly rate of wage. (except for employees who are absent from work without prior approval on a scheduled workday during the workweek shall be paid at the straight -rime rate until they have worked 8 hours in a day (10 in a 4 x 10 workweek) or 40 hours during that workweek.) All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and Labor Day shall be paid at double the hourly rate of wage. Z. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid the straight time rate of pay in addition to holiday pay. 2of15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Overtime Codes Continued 2. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE. B. All hours worked on holidays shall be paid at one and one-half times the hourly rate of wage. F. The first eight (8) hours worked on holidays shall be paid at the straight hourly rate of wage in addition to the holiday pay. All hours worked in excess of eight (8) hours on holidays shall be paid at double the hourly rate of wage. M. This code appears to be missing. All hours worked on Saturdays, Sundays and holidays shall be paid at double the hourly rate of wage. O. All hours worked on Sundays and holidays shall be paid at one and one-half times the hourly rate of wage. R. All hours worked on Sundays and holidays and all hours worked over sixty (60) in one week shall be paid at double the hourly rate of wage. U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked over 12 hours in a day or on Sundays and holidays shall be paid at double the hourly rate of wage. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE. F. All hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on paid holidays shall be paid at two and one-half times the hourly rate of wage including holiday pay. H. All work performed on Sundays between March 16th and October 14th and all Holidays shall be compensated for at two (2) times the regular rate of pay. Work performed on Sundays between October 15th and March 15th shall be compensated at one and one half (1-1/2) times the regular rate of pay. J. All hours worked between the hours of 10:00 pm and 5:00 am, Monday through Friday, and all hours worked on Saturdays shall be paid at a one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. K. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal 5 am to 6pm shift, and all work on Saturdays shall be paid at one and one-half times the hourly rate of wage. All work performed after 6:00 pm Saturday to 5:00 am Monday and Holidays, and all hours worked in excess of twelve (12) hours in a single shift shall be paid at double the hourly rate of wage. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more. When an employee returns to work without at least eight (8) hours time off since their previous shift, all such time shall be a continuation of shift and paid at the applicable overtime rate until he/she shall have the eight (8) hours rest period. 4. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE. A. All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at double the hourly rate of wage. All hours worked on Saturdays, Sundays and holidays shall be paid at double the hourly rate of wage. 3of15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Overtime Codes Continued 4. C. On Monday through Friday, the first four (4) hours of overtime after eight (8) hours of straight time work shall be paid at one and one half (1-1/2) times the straight time rate of pay, unless a four (4) day ten (10) hour workweek has been established. On a four (4) day ten (10) hour workweek scheduled Monday through Thursday, or Tuesday through Friday, the first two (2) hours of overtime after ten (10) hours of straight time work shall be paid at one and one half (1-1/2) times the straight time rate of pay. On Saturday, the first twelve (12) hours of work shall be paid at one and one half (1-1/2) times the straight time rate of pay, except that if the job is down on Monday through Friday due to weather conditions or other conditions outside the control of the employer, the first ten (10) hours on Saturday may be worked at the straight time rate of pay. All hours worked over twelve (12) hours in a day and all hours worked on Sunday and Holidays shall be paid at two (2) times the straight time rate of pay. D. All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at double the hourly rate of wage. All hours worked on Saturday, Sundays and holidays shall be paid at double the hourly rate of pay. Rates include all members of the assigned crew. EXCEPTION: On all multipole structures and steel transmission lines, switching stations, regulating, capacitor stations, generating plants, industrial plants, associated installations and substations, except those substations whose primary function is to feed a distribution system, will be paid overtime under the following rates: The first two (2) hours after eight (8) regular hours Monday through Friday of overtime on a regular workday, shall be paid at one and one-half times the hourly rate of wage. All hours in excess of ten (10) hours will be at two (2) times the hourly rate of wage. The first eight (8) hours worked on Saturday will be paid at one and one-half (1-1/2) times the hourly rate of wage. All hours worked in excess of eight (8) hours on Saturday, and all hours worked on Sundays and holidays will be at the double the hourly rate of wage. All overtime eligible hours performed on the above described work that is energized, shall be paid at the double the hourly rate of wage. E. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. On a four -day, ten-hour weekly schedule, either Monday thru Thursday or Tuesday thru Friday schedule, all hours worked after ten shall be paid at double the hourly rate of wage. The Monday or Friday not utilized in the normal four - day, ten hour work week, and Saturday shall be paid at one and one half (1%) times the regular shift rate for the first eight (8) hours. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. G. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. I. The First eight (8) hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of eight (8) per day on Saturdays shall be paid at double the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. 4of15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Overtime Codes Continued 4. J. The first eight (8) hours worked on a Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of eight (8) hours on a Saturday shall be paid at double the hourly rate of wage. All hours worked over twelve (12) in a day, and all hours worked on Sundays and Holidays shall be paid at double the hourly rate of wage. K. All hours worked on a Saturday shall be paid at one and one-half times the hourly rate of wage, so long as Saturday is the sixth consecutive day worked. All hours worked over twelve (12) in a day Monday through Saturday, and all hours worked on Sundays and Holidays shall be paid at double the hourly rate of wage. L. The first twelve (12) hours worked on a Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on a Saturday in excess of twelve (12) hours shall be paid at double the hourly rate of pay. All hours worked over twelve (12) in a day Monday through Friday, and all hours worked on Sundays shall be paid at double the hourly rate of wage. All hours worked on a holiday shall be paid at one and one-half times the hourly rate of wage, except that all hours worked on Labor Day shall be paid at double the hourly rate of pay. U. The first four (4) hours after eight (8) regular hours Monday through Friday and the first twelve (12) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. (Except on makeup days if work is lost due to inclement weather, then the first eight (8) hours on Saturday may be paid the regular rate.) All hours worked over twelve (12) hours Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. V. Work performed in excess of ten (10) hours of straight time per day when four ten (10) hour shifts are established or outside the normal shift (5 am to 6pm), and all work on Saturdays, except for make-up days shall be paid at time and one-half (1 %z) the straight time rate. In the event the job is down due to weather conditions, then Saturday may, be worked as a voluntary make-up day at the straight time rate. However, Saturday shall not be utilized as a make-up day when a holiday falls on Friday. All work performed on Sundays and holidays and work in excess of twelve (12) hours per day shall be paid at double (2x) the straight time rate of pay. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours. When an employee returns to work without a break of eight (8) hours since their previous shift, all such time shall be a continuation of shift and paid at the applicable overtime rate until such time as the employee has had a break of eight (8) hours. W. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. When an employee returns to work without at least eight (8) hours time off since their previous shift, all such time shall be a continuation of shift and paid at the applicable overtime rate until such time as the employee has had a break of eight (8) hours. 5of15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Overtime Codes Continued 4. X. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. Work performed outside the normal shift of 6 am to 6pm shall be paid at one and one-half the straight time rate, (except for special shifts or three shift operations). All work performed on Sundays and holidays shall be paid at double the hourly rate of wage. Shifts may be established when considered necessary by the Employer. The Employer may establish shifts consisting of eight (8) or ten (10) hours of work (subject to WAC 296-127-022), that shall constitute a normal forty (40) hour work week. The Employer can change from a 5-eight to a 4-ten hour schedule or back to the other. All hours of work on these shifts shall be paid for at the straight time hourly rate. Work performed in excess of eight hours (or ten hours per day (subject to WAC 296-127-022) shall be paid at one and one- half the straight time rate. When due to conditions beyond the control of the Employer, or when contract specifications require that work can only be performed outside the regular day shift, then by mutual agreement a special shift may be worked at the straight time rate, eight (8) hours work for eight (8) hours pay. The starting time shall be arranged to fit such conditions of work. When an employee returns to work without at a break of eight (8) hours since their previous shift, all such time shall be a continuation of shift and paid at the applicable overtime rate until such time as the employee has had a break of eight (8) hours. Y. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal shift, and all work on Saturdays shall be paid at time and one-half the straight time rate. All work performed after 6:00 pm Saturday to 6:00 am Monday and holidays shall be paid at double the straight time rate of pay. Any shift starting between the hours of 6:00 pm and midnight shall receive an additional one dollar ($1.00) per hour for all hours worked that shift. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more. Z. All hours worked between the hours of 6:00 pm and 6:00 am, Monday through Saturday, shall be paid at a premium rate of 20% over the hourly rate of wage. Work performed on Sundays may be paid at double time. All hours worked on holidays shall be paid at double the hourly rate of wage. 11. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE. B After an employee has worked eight (8) hours, all additional hours worked shall be paid at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more. C The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours worked, except Labor Day, and all hours on Sunday shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage. All non -overtime and non -holiday hours worked between 4:00 pm and 5:00 am, Monday through Friday, shall be paid at a premium rate of 15% over the hourly rate of wage. 6of15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Overtime Codes Continued 11. D. All hours worked on Saturdays and holidays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays shall be paid at double the hourly rate of wage. After an employee has worked eight (8) hours, all additional hours worked shall be paid at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more. E. The first two (2) hours after eight (8) regular hours Monday through Friday, the first ten (10) hours on Saturday, and the first ten (10) hours worked on Holidays shall be paid at one and one-half times the hourly rate of wage. All hours worked over ten (10) hours Monday through Saturday, and Sundays shall be paid at double the hourly rate of wage. After an employee has worked eight (8) hours, all additional hours worked shall be paid at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more. F. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. On a four -day, ten-hour weekly schedule, either Monday thru Thursday or Tuesday thru Friday schedule, all hours worked after ten shall be paid at double the hourly rate of wage. The Monday or Friday not utilized in the normal four - day, ten hour work week, and Saturday shall be paid at one-half times the hourly rate of wage for the first eight (8) hours. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. G. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal 5 am to 6pm shift, and all work on Saturdays shall be paid at one and one-half times the hourly rate of wage. All work performed after 6:00 pm Saturday to 5:00 am Monday and Holidays, and all hours worked in excess of twelve (12) hours in a single shift shall be paid at double the hourly rate of wage. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of nine (9) hours or more. When an employee returns to work without at least nine (9) hours time off since their previous shift, all such time shall be a continuation of shift and paid at the applicable overtime rate until he/she shall have the nine (9) hours rest period. H. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal 5 am to 6pm shift, and all work on Saturdays shall be paid at one and one-half times the hourly rate of wage. All work performed after 6:00 pm Saturday to 5:00 am Monday and Holidays, and all hours worked in excess of twelve (12) hours in a single shift shall be paid at double the hourly rate of wage. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of ten (10) hours or more. When an employee returns to work without at least ten (10) hours time off since their previous shift, all such time shall be a continuation of shift and paid at the applicable overtime rate until he/she shall have the ten (10) hours rest period. Overtime Codes Continued 7of15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) On Monday through Friday, the first four (4) hours of overtime after eight (8) hours of straight time work shall be paid at one and one half (1-1/2) times the straight time rate of pay, unless a four (4) day ten (10) hour workweek has been established. On a four (4) day ten (10) hour workweek scheduled Monday through Thursday, or Tuesday through Friday, the first two (2) hours of overtime after ten (10) hours of straight time work shall be paid at one and one half (1-1/2) times the straight time rate of pay. On Saturday, the first twelve (12) hours of work shall be paid at one and one half (1-1/2) times the straight time rate of pay. All work performed after 6:00 pm Saturday to 5:00 am Monday, all work performed over twelve (12) hours, and all work performed on holidays shall be paid at double the straight time rate of pay. Any shift starting between the hours of 6:00 pm and midnight shall receive an additional two dollar ($2.00) per hour for all hours worked that shift. Holiday Codes 5. A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, and Christmas Day (7). B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, the day before Christmas, and Christmas Day (8). C. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). D. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). H. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Day after Thanksgiving Day, And Christmas (6). I. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6). J. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Eve Day, And Christmas Day (7). K. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9). L. Holidays: New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (8). N. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, The Friday After Thanksgiving Day, And Christmas Day (9). P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday And Saturday After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9). If A Holiday Falls On Sunday, The Following Monday Shall Be Considered As A Holiday. Q. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6). 8of15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Holiday Codes Continued R. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Day After Thanksgiving Day, One -Half Day Before Christmas Day, And Christmas Day. (7 1/2). S. Paid Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day (7). Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). 6. G. Paid Holidays: New Year's Day, Martin Luther King Jr. Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and Christmas Eve Day (11). H. Paid Holidays: New Year's Day, New Year's Eve Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, Christmas Day, The Day After Christmas, And A Floating Holiday (10). T. Paid Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, The Last Working Day Before Christmas Day, And Christmas Day (9). Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (7). If a holiday falls on Saturday, the preceding Friday shall be considered as the holiday. If a holiday falls on Sunday, the following Monday shall be considered as the holiday. A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any Holiday Which Falls On A Sunday Shall Be Observed As A Holiday On The Following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day. B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. C. Holidays: New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. D. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). Unpaid Holidays: President's Day. Any paid holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any paid holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. E. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. 9of15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Holiday Codes Continued F. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the last working day before Christmas day and Christmas day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. G. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. H. Holidays: New Year's Day, Martin Luther King Jr. Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. I. Holidays: New Year's Day, President's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, The Day Before Christmas Day And Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. J. Holidays: New Year's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day and Christmas Day (6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. K. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. L. Holidays: New Year's Day, Memorial Day, Labor Day, Independence Day, Thanksgiving Day, the Last Work Day before Christmas Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. N. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. When Christmas falls on a Saturday, the preceding Friday shall be observed as a holiday. P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Q. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day. S. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Day, the Day after Christmas, and A Floating Holiday (9). If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. V. Holidays: New Year's Day, President's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, the day before or after Christmas, and the day before or after New Year's Day. If any of the above listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. 10 of 15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Holiday Codes Continued 7. W. Holidays: New Year's Day, Day After New Year's, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Eve Day, Christmas Day, the day after Christmas, the day before New Year's Day, and a Floating Holiday. X. Holidays: New Year's Day, Day before or after New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and the day before or after Christmas day. If a holiday falls on a Saturday or on a Friday that is the normal day off, then the holiday will be taken on the last normal workday. If the holiday falls on a Monday that is the normal day off or on a Sunday, then the holiday will be taken on the next normal workday. Y. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas Day. (8) If the holiday falls on a Sunday, then the day observed by the federal government shall be considered a holiday and compensated accordingly. G. New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, the last scheduled workday before Christmas, and Christmas Day (9). If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. H. Holidays: New Year's Day, Martin Luther King Jr. Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. I. Holidays: New Year's Day, President's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, The Day Before Christmas Day And Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. J. Holidays: New Year's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day and Christmas Day (6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. K. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. L. Holidays: New Year's Day, Memorial Day, Labor Day, Independence Day, Thanksgiving Day, the Last Work Day before Christmas Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. N. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. When Christmas falls on a Saturday, the preceding Friday shall be observed as a holiday. P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. 11 of 15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Holiday Codes Continued Q. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day. S. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Day, the Day after Christmas, and A Floating Holiday (9). If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. V. Holidays: New Year's Day, President's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, the day before or after Christmas, and the day before or after New Year's Day. If any of the above listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. W. Holidays: New Year's Day, Day After New Year's, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Eve Day, Christmas Day, the day after Christmas, the day before New Year's Day, and a Floating Holiday. X. Holidays: New Year's Day, Day before or after New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and the day before or after Christmas day. If a holiday falls on a Saturday or on a Friday that is the normal day off, then the holiday will be taken on the last normal workday. If the holiday falls on a Monday that is the normal day off or on a Sunday, then the holiday will be taken on the next normal workday. Y. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas Day. (8) If the holiday falls on a Sunday, then the day observed by the federal government shall be considered a holiday and compensated accordingly. 15. G. New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, the last scheduled workday before Christmas, and Christmas Day (9). If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. H. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Eve Day, and Christmas Day (8). When the following holidays fall on a Saturday (New Year's Day, Independence Day, and Christmas Day) the preceding Friday will be considered as the holiday; should they fall on a Sunday, the following Monday shall be considered as the holiday. I. Holidays: New Year's Day, President's Day, Memorial Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, the last regular workday before Christmas (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. J. Holidays: New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, and Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day. 12 of 15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Note Codes 8. D. Workers working with supplied air on hazmat projects receive an additional $1.00 per hour. L. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $0.75, Level B: $0.50, And Level C: $0.25. M. Workers on hazmat projects receive additional hourly premiums as follows: Levels A & B: $1.00, Levels C & D: $0.50. N. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $1.00, Level B: $0.75, Level C: $0.50, And Level D: $0.25. S. Effective August 31, 2012 — A Traffic Control Supervisor shall be present on the project whenever flagging or spotting or other traffic control labor is being utilized. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31, 2012. T. Effective August 31, 2012 — A Traffic Control Laborer performs the setup, maintenance and removal of all temporary traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian traffic during construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31, 2012. U. Workers on hazmat projects receive additional hourly premiums as follows — Class A Suit: $2.00, Class B Suit: $1.50, And Class C Suit: $1.00. Workers performing underground work receive an additional $0.40 per hour for any and all work performed underground, including operating, servicing and repairing of equipment. The premium for underground work shall be paid for the entire shift worked. Workers who work suspended by a rope or cable receive an additional $0.50 per hour. The premium for work suspended shall be paid for the entire shift worked. Workers who do "pioneer" work (break open a cut, build road, etc.) more than one hundred fifty (150) feet above grade elevation receive an additional $0.50 per hour. V. In addition to the hourly wage and fringe benefits, the following depth and enclosure premiums shall be paid. The premiums are to be calculated for the maximum depth and distance into an enclosure that a diver reaches in a day. The premiums are to be paid one time for the day and are not used in calculating overtime pay. Depth premiums apply to depths of fifty feet or more. Over 50' to 100' - $2.00 per foot for each foot over 50 feet. Over 10l' to 150' - $3.00 per foot for each foot over 101 feet. Over 15l' to 220' - $4.00 per foot for each foot over 220 feet. Over 221' - $5.00 per foot for each foot over 221 feet. Enclosure premiums apply when divers enter enclosures (such as pipes or tunnels) where there is no vertical ascent and is measured by the distance travelled from the entrance. 25' to 300' - $1.00 per foot from entrance. 300' to 600' - $1.50 per foot beginning at 300'. Over 600' - $2.00 per foot beginning at 600'. W. Meter Installers work on single phase 120/240V self-contained residential meters. The Lineman/Groundmen rates would apply to meters not fitting this description. 13 of 15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Note Codes Continued 8. X. Workers on hazmat projects receive additional hourly premiums as follows - Class A Suit: $2.00, Class B Suit: $1.50, Class C Suit: $1.00, and Class D Suit: $0.50. Special Shift Premium: Basic hourly rate plus $2.00 per hour. When due to conditions beyond the control of the Employer or when an owner (not acting as the contractor), a government agency or the contract specifications requires that work can only be performed outside the normal 5 am to 6pm shift, then the special shift premium will be applied to the basic hourly rate. When an employee works on a special shift, they shall be paid a special shift premium for each hour worked unless they are in OT or Double-time status. (For example, the special shift premium does not waive the overtime requirements for work performed on Saturday or Sunday.) Tide Work: When employees are called out between the hours of 6:00 p.m. and 6:00 a.m. to work on tide work (work located in the tide plane) all time worked shall be at one and one-half times the hourly rate of pay. Swinging Stage/Boatswains Chair: Employees working on a swinging state or boatswains chair or under conditions that require them to be tied off to allow their hands to be free shall receive seventy-five cents ($0.75) per hour above the classification rate. Z. Workers working with supplied air on hazmat projects receive an additional $1.00 per hour. Special Shift Premium: Basic hourly rate plus $2.00 per hour. When due to conditions beyond the control of the Employer or when an owner (not acting as a contractor), a government agency or the contract specifications require that more than (4) hours of a special shift can only be performed outside the normal 6 am to 6pm shift, then the special shift premium will be applied to the basic straight time for the entire shift. When an employee works on a special shift, they will be paid a special shift premium for each hour worked unless they are in overtime or double- time status. (For example, the special shift premium does not waive the overtime requirements for work performed on Saturday or Sunday.) A. Workers working with supplied air on hazmat projects receive an additional $1.00 per hour. Special Shift Premium: Basic hourly rate plus $2.00 per hour. When due to conditions beyond the control of the Employer or when an owner (not acting as the contractor), a government agency or the contract specifications require that more than four (4) hours of a special shift can only be performed outside the normal 6 am to 6pm shift, then the special shift premium will be applied to the basic straight time for the entire shift. When an employee works on a special shift, they shall be paid a special shift premium for each hour worked unless they are in overtime or double- time status. (For example, the special shift premium does not waive the overtime requirements for work performed on Saturday or Sunday.) Certified Crane Operator Premium: Crane operators requiring certifications shall be paid $0.50 per hour above their classification rate. Boom Pay Premium: All cranes including tower shall be paid as follows based on boom length: (A) — 130' to 199' — $0.50 per hour over their classification rate. (B) — 200' to 299' — $0.80 per hour over their classification rate. (C) — 300' and over — $1.00 per hour over their classification rate. 14 of 15 Benefit Code Key — Effective 9/1/2021 thru 3/2/2022 (Updated 12/14/2021) Note Codes Continued 9. B. The highest pressure registered on the gauge for an accumulated time of more than fifteen (15) minutes during the shift shall be used in determining the scale paid. Tide Work: When employees are called out between the hours of 6:00 p.m. and 6:00 a.m. to work on tide work (work located in the tide plane) all time worked shall be at one and one-half times the hourly rate of pay. Swinging Stage/Boatswains Chair: Employees working on a swinging stage or boatswains chair or under conditions that require them to be tied off to allow their hands to be free shall receive seventy-five cents ($0.75) per hour above the classification rate. C. Tide Work: When employees are called out between the hours of 6:00 p.m. and 6:00 a.m. to work on tide work (work located in the tide plane) all time worked shall be at one and one-half times the hourly rate of pay. Swinging Stage/Boatswains Chair: Employees working on a swinging stage or boatswains chair or under conditions that require them to be tied off to allow their hands to be free shall receive seventy-five cents ($0.75) per hour above the classification rate. Effective August 31, 2012 — A Traffic Control Supervisor shall be present on the project whenever flagging or spotting or other traffic control labor is being utilized. A Traffic Control Laborer performs the setup, maintenance and removal of all temporary traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian traffic during construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. These classifications are only effective on or after August 31, 2012. D. Industrial Painter wages are required for painting within industrial facilities such as treatment plants, pipelines, towers, dams, bridges, power generation facilities and manufacturing facilities such as chemical plants, etc., or anywhere abrasive blasting is necessary to prepare surfaces, or hazardous materials encapsulation is required. E. Heavy Construction includes construction, repair, alteration or additions to the production, fabrication or manufacturing portions of industrial or manufacturing plants, hydroelectric or nuclear power plants and atomic reactor construction. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $1.00, Level B: $0.75, Level C: $0.50, And Level D: $0.25. F. Industrial Painter wages are required for painting within industrial facilities such as treatment plants, pipelines, towers, dams, power generation facilities and manufacturing facilities such as chemical plants, etc., or anywhere abrasive blasting is necessary to prepare surfaces, or hazardous materials encapsulation is required. 15 of 15