HomeMy WebLinkAboutCAG2021-265 - Change Order - #2 - ICON Materials - 2021 Asphalt Overlays - 03/07/2022KENT
Agreement Routing Form
For Approvals, Signatures and Records Management
This form tombines & replaces the Request for Mayor's Signature and Contract Cover Sheet forms.
(Print on pink or cherry colored paper)WASHINGTON
E
oLeo.
Originator:
C. Frame
Department:
PW Engineering
Date Sent:
3t15t2022
Date Required
N/A
Authorized to Sign:
E Director or Designee E MaYor
Date of Council Approval
N/A
Budget Account Number:
R201 13.641 '10.330
Budget? EYes E No
Grant? EYes E No
Type: N/A
g
.9+,o
ELor-
E*.co
E
atoLgl
Vendor Name:
ICON Materials
Category:
Contract
Vendor Number:
34467
Sub-Category:
Change Order #2
Project Name: 2021 Asphalt Overlays
project Deraits:Emergency roadway repair on SE 248th St between 96th Ave S and 98th
Ave S due to harsh winter weather
Agreement Amount: $81 ,610.70
Start Date: N/A
Basis for Selection of Contractor: $id
Termtnation Date: 130 Working Days
Local Business? E Yes E No*
*lf meets requirements per KCC 3.70.100, ptease complete "Vendor Purchase-Local Exceptions" form on Cityspace'
Notice required prior to disclosure?
EYes E No
Contract Number:
cAG2021-265
Oltr
1H
J\o
.E -<agEiog
.9ut
Date Received by City Attorney:Comments:
Date Routed to the Mayor's Office:
Date Routed to the City Clerk's Office:$(tElLL
ad(W22i7l I 20 Visit Documents.KentWA.govto obtain copies of all agreements
AIevt<
KENT
W49HtNctoN
CHANGE ORDER NO. #2
NAME OF CONTMCTOR:ICON Materials ("Contractor")
CONTRACT NAME & PROJECT NUMBER:2021 Asphalt Overlavs
ORIGINAL CONTRACT DATE :June 03. 2021
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the pafties, the project contract is modified as follows:
1' Section I of the Agreement, entitled "Descrlption of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to :
Emergency roadway repair on SE 248th St between 96th Ave S and 98th
Ave S, due to harsh winter weather. Bid item includes roadway
excavation including haul, crushed surfacing base course and I/2" HMA.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract 5um,
(including applicable alternates and
wssT)
$s,064,977.00
Net Change by Previous Change Orders
(incl, applicable WSST)
$20,024.25
Current Contract Amount
(incl. Previous Change Orders)
$s,085,001.25
Current Change Order $81,610.70
Applicable WSST Tax on this Change
Order
$0.00
Revised Contract Sum $5,166,611.95
CHANGE ORDER - 1 OF 3
Original Time for Completion
(inseft date)
130 working days
Revised Time for Completion under
prior Change Orders
(insert date)
130 working days
Days Required (+) for this Change Order O calendar days
Revised Time for Completion
(insert date)
130 working days
In accordance with Sections L-O4.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those peftaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The pafties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
AF ec
K?
CONTRACTOR:
By:N^,r; r{l*,'a
IPrint Name:
(tiile)
DATE
CITY OF KENTI
By . Chad B
,: Olliqily sisned by chad Brer€n
i e re h l}ifiqT$ xff l#;;"r;-.:;3Y"
(signature)
Print Name: Chad Bieren. P.E.Its Public Works Directm
(tiile)
DATE
CHANGE ORDER. 2 OF 3
ATTEST:
c
U,{fu
Kent Clty Clerk
APPROVED AS TO FORMr
(applicable lf Mayols signature requlred)
Kent Law Department
[n thir ffeld, you may stE the electronic filepeth wisc th€ ontlrct has b€€n savcdl
CHANGE ORDER - 3 OF 3
File No. 2OO.2
KENT
CHANGE ORDER WORKSHEET NO. 2
Construction Engineering Division - Public Works
Project: 2021 AsPhalt OverlaYs
Project Engineer: Mark Madfai
Capital Projects
Manaoer:Brian Shields
Project No:
Fed-Aid No:
Contractor:
21-3001.1
N/A
Icon Materials
Date: 2/23/2022
I Pro d Cha e
66 CY at $80.00/CY; Crushed
33I.57 TON at $111.00/TON
o n ncl ha udRoaExcaatiVrerSon248tESTh QTYemforeroawaydwaddbiitemspargencyv
H AM255NL/634 TO24 atNrfaciunseBarseCou $00/ToSQw139g
If. Reason and Bac round for Chan e
III. Method of Payment
NEW PAY ITEMS flNotapplicable
Ave S. Unit pricing agreed upon via email, prior to work taking place.
96th Ave S and 98thEmergency roadway rePair, due to harsh winter weather, on SE 248th St between
Sch.
No Item Description Total Est.
Otv Unit Unit Price Total Estlmateo uost or
Item
I Roadway Excavation incl. haul 319.66 CY $80.00 $25,572.8O
I Crushed Surfacing Base Course 346.24 TON $5s.ss $t9,233.63
I t/2" HMA 33L.57 TON $ 111.00 $36,8O4.27
New Pay Items Total: $81,61O.70
DELETE EXISTING PAY ITEM(S) per 1-O9.5 pNotappricabre
Sch
No.Bid ltem No.Item Description Qtv Unit Unit Price Cost of Item
Page 1
$
$
Delete Existing PaY ltems Total: $
INCREASE/DECREASE TO EXISTING PAY ITEM(S) pl ruotappricabre
Sch
No.Bid Item No.Item DescriPtion Qtv Unit Unit Price Cost of ltem
$
Increase / Decrease to Existing Pay ltems Total: $
*TOTAL ESTIMATED COST OF CHANGE ORDER:81 1o.70
* Total of the Cost of ltem Columns
IV. WORKING DAYS
130Previous Total:oDue This Change Order:130Original Contract:
Explanation/Justification for Additional Working Days:
Capital Projects Manager:
Construction Engineeri ng
Supervisor:
*TOTAL WORKING DAYS:
ds
130
x This Change Order + Previous Total
Date: o*-zr - ?-o uL-
Date: z z
t n Barry
Construction Manager:--/r-*--1rkDate
a-
Eric Connor
PageT
A
lE0lt
Alilllll/'L\
ICON lt{aterials
1508 Valeutine Ave- SE
Pacifit WA 9804?
(206) 575-3s00 0 Far GOO 5?$tl3l9
terials.com
ASPHALT PAWNC PROPOSAL CONTRACT (APPIC)
ftmJdftoh
To:
Address:
City Of Kent
220 4th Ave S.
Kent, WA 98032-5895
Contact:
Phone:
Fax:
Brian Shields
(2s3) 8s6-ss08
Project Name:
Project Location:
S 248th Repair
City Of Kent
Bid Number:
Bid Date:11712022
Estimated Unit Total PriceUnit PriceItem #Item
820
821
822
823
Roadway Excavation
Geotextile
Crushed Surfacing Base Course
1/2'HMA
700.00 cY
2,100.00 sY
650.00 ToN
690.00 ToN
$80.00
$2.s0
$ss.00
$111.00
$56,000.00
$5,250,00
$35,750.00
$76,s90.00
Total Bid Price: $173,59O,O0
Notes:. This quotation is firm for 30 days. Without wriften notification of the G.C./ Owner's intent to subcontract within 30 days, ICON Materials retains the
option to withdraw or alter its quotation.
Payment Terms:
Terms of payment are net thirty (30) days, subject to approval or modification by ICON MATERIALS credit department according to Exhibit "B".
ACCEPTED:
The above prices, specifications and conditions are satisfactory and
are hereby accepted.
Buyer:
Signature:
Date of Acceptance:
CONFIRMED:
ICON Materials (dba Of CPM Development Gorp.)
Authorized Signature
Estimator: BillJohnson
253-26L -4852 bi I l.joh nson@ iconmaterials. com
11712022 L7129i44 AM
Page 1 of 1
Eric
From:
Sent:
To:
Cc:
Subject:
Bieren, Chad
Monday, February 28,2022 6:26 PM
Connor, Eric
Peterson, Kelly
RE: S 248th Repair - Contractor Pricing
Hi Eric,
I know that we discussed the work outlined in the attached emails later in the afternoon on
January 7th, and again on Monday January 10th after Bill Thomas and Brent Collins met with
Brian SlrietOs to discuss the extents of the repairs. Following those discussions, and based on
your initial analysis of the estimated contractor pricing along with the status of the 2021 Asphalt
bverlay project, I authorized the repairs on 248th Street. The repairs have been completed and
the roadway is open. Please process the associated change orders'
Thanks,
Chad
Chad Bieren, P'E. pubtic works Director
Engineering Administration I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5534 | Cell 253-7 4O-9139
cbieren@KentWA.qov
CITY OF KENT, WASHINGTON
KentwA.oov Facebook i.,llJ!l;l*-'L YouTube Instaqram
From: Con nor, Eric <EConnor@kentwa.gov>
Sent: Friday, January 7,20221:L2 PM
To: Peterson, Kelly <KPeterson@kentwa.gov>; Bieren, Chad <CBieren@kentwa.gov>; Thomas, Bill
<WBThomas@kentwa.gov>; Brock, David <DBrock@kentwa.gov>; Collins, Brent <BCollins@kentwa.gov>
Cc: Shields, Brian <BShields@kentwa.gov>
Subiect: FW: S 248th Repair - Contractor Pricing
Good Afternoon,
Attached is Icon's estimate for the road repair work on S 248th. We had intended to may
payment via Force Account. However, if I understand correctly they are willing to honor the
attached unit prices in addition to prices for traffic control. Please let us know if you have a
preference.
The work that is taking place today is not included in this pricing'
Overall, we will be looking a spending in excess of $200,000. Please let me know if we are okay
to keep moving forward ais planned. And of course, let me know if you have questions or need
additional information.
1
Thank you,
Eric
Eric Connor, Construction Engineering Manager
Phone 253-856-5533 | Cell 253-797-069?
CITY OF KENT, WASHINGTON
PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E'MAIL
From: Shields, Brian <BShields@kentwa.sov>
Sent: Friday, January 7, 2022 L1:51 AM
To: Connor, Eric <EConnor@ kentwa.gov>
Subject: FW: S 248th Repair
Brian Shields, Senior Construction Inspector
Construction Management I Public Works Department
220 Ath Avenue South, Kent, WA 98032
MainlCell 253-293-4973 | Desk 2s3-8s6-6s1o
bshields@KentWA.oov
CITY OF KENT, WASHINGTON
KentWA.oov Facebook -r vvlller YouTube
From: Johnson, Bill x (lcoN Materials) <bill.iohnson@iconmaterials.com>
Sent: Friday, January 7,20221"L:49 AM
To: Shields, Brian <BShields@kentwa.eov>
Subject: S 248th Repair
Brian,
Please see attached quote.
AEilrrrrrrrrr
A CRH COMPANY
Bill Johnson
Cell/253-26t-4852
Direct/206-574-3907
Email/ bill.iohnson@iconmaterials.com