Loading...
HomeMy WebLinkAboutCAG2019-084 - Change Order - #27 - Scarsella Brothers, Inc. - LID 363: S 224th Street Project - 01/10/2022KENT Agreement Routing Form For Approvals, Signatures and Records Management This form combines & replaces the Request for Mayor! Signature and Contract Cover Sheet forms (Print on pink or cheny colored paper)WasHtNoroN lE ot-cc Originator: Stephanie Anderson Department: PW Engineering Date Sent: 3t9t22 Date Required N/A Authorized to Sign: E Director or Designee E MaYor Date of Council APProval: 2t1912019 Budget Account Number: R90094.64110j20 Grant? E Yes El No Type: N/A co {J IE ELorts EvEo EooLgt Vendor Name: Scarsella Bros, lnc. Category: Contract Vendor Number: 34547 Sub-Category: Change Order 27 Project Name: LID 363: S 224th St Project project Detaits:Brush clearing and mowing to control vegetation in preparation_forfuture wetland' habitat mitigalion work. Tricked as force accounts on sheets 192 through 206. Agreement Amount: $36,966.77 Start Date: N/A Basis for Selection of Contractor: $id Terminarion Date: 225 working daYs Local Business? E Yes E No* *lf meets requirements per KCC 3.70.100, please complete "Vendor Purchase-Local Exceptions" form on Otyspace' Notice required prior to disclosure? EYes E No Contract Number: cAG2019-084 Comments RECEIVED [,|AR 9 2022 CITY OF KENT CITY CLERK Date Received by city Attorney: Date Routed to the Mayor's Office: Date Routed to the City Clerk's Office: E'le U)\olcK\utt'so7.L8,fiotr .9UI ad(W2217l_1,20 Visit Documents.KentWA.gov to obtain copies of all agreements KENT W*tireoroF CHANGE ORDER NO' #27 NAME OF CONTRACTOR: $carsella Bros' Inc' ("Contractor") CONTMCT NAME & PROIECT NUMBER: Lid 363: S 224tI Street Proiect Febluary 19, 2019 ORIGINAL CONTMCT DATE: This Change Order amends the above-referenced contract; all other provislons of the contract that are not inconsistent with this change order shall remain in effect, For valuable consideration and by mutual consent or ilt" parties, the project contract is modified as follows: 1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and.any prior Amendments, contractor shall provide all labor, materials, and equiPment necessarY to : Brush ctearing and mowing to control vegetation in preparation for future wetland habitat mitigation work. Tracked as force accounts on sheets 192 through 206' 2. The contract amount and time for performance provisionl. of Section II "Time of Completion ," and SectiOn III, "Compensation," are hereby modified as followS: Original Contract Sum, (including aPPlicable wssT) alternates and $8,423,307,67 Net Change bY Previous ( incl. applicable WSST) Change Orders $741,348.38 Current Contract Amount (inct. Previous Change Orders) $9,164,656.05 Current Change Order $36,966.17 Applicable WSST Tax on th is Change Order $0.00 Revised Contract Sum $9,201,622.82 CHANGE ORDER - 1 OF 3 In accordance with Sections l-o4.4 and 1-04.5 0f the Kent and wsDoT standard specifications, and section VII of the Rgreement, the contractor accepts all requirements of this Change Order OV signing below. Asol pursuuni to !lt: above-referenced contract, Contractor agrees to waive any protest it may huu. ,"g"rding this Change Order and acknowledges and accepts that this Change Order constitutes finat setttement of all claims of any kind or nature arising from or connectei with any work either covered or affected by this change order, including, without limitation, ctaims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Changu Ordur, ,ni"tt otherwise provided, does not relieve the contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date' All acts consistent with the authority of the Agreement, previous Change Orders (if ?nV), and this Change order, prior to the e*ective date of ttris Change Order, are hereby ratified and affirmed, and the terms of the ngreeme.tL previous Change Orders (if any), and this Change Order shall be deemed to have aPPlied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the pafties of this contract' 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above' IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written below' Original Time for ComPl etion (insert date) 130 working daYs Revised Time for ComPletion u nder prior Change Orders (insert date) 225 working daYs Days Req u I red (a )for t h I s Cha n ge Ord er 0 calendar daYs Revised Time for ComPletion (insert date) 225 working daYs KP ' l&sNrytud&d. Chad Bieren ,*ffiffiff"#F*"'-' Its Public Works Director - (title) CITY OF KENT: EC Print Name:Chad Bieren. P.E. By DATE (signature) CONTRACTOR: DATE By: Print N CHANGE ORDER. ZOF 3 (appltcabte if Mayork signature requlred) Kent Law DePaftment APPROVED AS TO FORM:ATTEST: Kent CiW Clerk [In thls ield, y@ dav .nter the eleEtanlcfileprth wheG the cont6d has b€s sv€d] CHANGE ORDER - 3 OF 3 File No. 2OO.2 KENTW^axr{drO{ CHANGE ORDER WORKSHEET NO.27 Construction Engineering Division - Public Works Project: LID 363 224th St Improvements Project Engineer: Stephen Lincoln Project No: Fed-Aid No: Contractor: 14-3010 ScarsellaCapital ProjectsManaoer: Jason Bryant Date: 7/7l2O2L I a Pro ed Chan e Brush clearing and mowing to control vegitation in prepararation work. Tracked as force account on sheets 192 through 206. for future wetland habitat mitigation II. Reason and Ba round for Chan e III. Method of Payment NEW PAY ITEMS [I Notapplicable 206 Th wiwork a ow thefutthewetlurenasitedtslaclBrothersreandamowecireScarseuestedtyq htnnheetss91thro2racketadforcesccoauoitimnoecttoedrsThwaworksu9atiroprojprocepsedgp Sch No Item Description Total Est. QW Unit Unit Price Total Estimated Cost of Item 1 Mow and Clear brush at Hytek 1 FA $36,966.77 $36,966.77 $ $ New Pay ltems Total: $36,966.77 DELETE EXISTING PAY ITEM(S) per 1-O9.5 E Notappricabre Sch No,Bid Item No.Item Description Qtv Unit Unit Price Cost of Item Page 1 $ $ Delete Existing Pay ltems Total: $ INCREASE/DECREASE TO EXISTING PAY ITEM(S) E Notappricabre Sch No.Bid ltem No.Item Description Qtv Unit Unit Price Cost of Item $ $ $ Increase / Decrease to Existing Pay ltems Total: *TOTAL ESTIMATED COST OF CHANGE ORDER: IV. WORKING DAYS $ 66.77 * Total of the Cost of Item Columns Original Contract:130 Due This Change Order:o Previous Total:L75 Explanation/Justification for Additional Working Days: Capital Projects Manager: _--,2,* *TOTAL WORKING DAYS:L75 * This Change Order + Previous Total Date: t2/l9/21 Construction Engineeri ng Supervisor: forJason Bryant ,4 forPaul Kuehne Construction Manager: 11,- *-4,,n- Date: nlrcl2l Eric Connor Page2 Date: nlrcl2l LID 363 224th St Impprovements (Ph 2) FA # Date Amount CO # 192 193 L94 195 196 197 198 199 200 20L 202 203 204 205 206 slt2/202L $ slL3/2021 $ slL4/202r $ 5/24/202t $ s/2s/202L $ s/26/202L $ s/27/2021 $ s/28/2021 $ 6/L/2O2r $ 6/2/202r $ 6/3/2021 $ 6/4/2021 $ 6ls/202r $ 617/202r $ 6le/202l $ 1,031. 10 353.03 L,O34.54 1,840.85 L,423.43 r,423.43 L,002.45 L,636.76 4,595.31 3,O83.74 3,083.74 3,038.94 657.03 LO,767.43 r,994.99 #27 #27 #27 #27 #27 #27 #27 #27 #27 #27 #27 #27 #27 #27 #27 i36,966.77 A Sheet N 192GFORCE ACCOUNT WORKED DAILY REPORT OF HrsOCCUPATION 1 CODE LaborerP 1 1 00.55 Project Name:LID 363 224th St Phase 2 L Prime Contractor:Scarsella $ $ $ Work by Subcontractor?: Hrs Hourly Rate Description of Work: Mow flelds NAME Item No 14-3010 Sub-Contractor: STRAIGHT TIME 65 OT Rale 01 DOLLAR AMOUNT Project No: Date: Foreman Laborer Rafael B Robert S Webster F 642.56 $ $ 79.35 100.55 59.96 60.69 56.04 OPERATED ForemanM $ $ $ LABOR OVERHEAD & PROFIT @ 2S% 5 SUBTOTAL. LABOR: LABOR TOTAL 1 86.34 828.90 EQUIPMENT OR ATTACHMENTS uipment DescriPtionEquipment # F1 sO-PU2-210 F2-291 Raie 12. '19.91 11 DOLLAR AMOUNT JD Tractor W Mower Ford2-203 13-12 16.26I 130,08 $ $ $ 130.08 157.r10 27.32 SUBTOTAL. EQUIPMENT EOUIPMENT OVERHEAD & PROFIT @ 21% PMENT TOTAL DOLLAR AMOUNTUnit PriceunitsOuantity MATERIALS / SERVICES 1 67570023lnvoice#Renlal72" bucket 37.03$dav $ 37.031 $ $ D $ 37.03 al.81 7.78 SUBTOTAL oVERHEAD&PROFIT@21% TOTAL of Hours Worked: Contractot's Jaou 121912021 Owne/s RePresentative Date 12% MARKUP (for Prime when subcontract work) 1.11 SHEET TOTAL:1 031.11 TOTAL; Pay Estimate Entered: Date: By: DAILY FORGE ACGOUNT ' EXTRAWORK REPORTSUBTOTAL LABOR:SUBCONTRACTORS$0.00$$$$u$SUBTOTAL SUBCONTRACTORSSCARSELLA BROS., INC. REPRESENTATIVEDATEMow fields at Hytek site.5112t2021Citv of KentS. 224th St ProiectSUBTOTAL EQUIPMENT:SUBTOTAL MATERIAL:P.O. Box 66697Seattle, WA 98168-0697Offce: (253) 872-7173Fax: (253) 395-1209GONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:Bid ltem#:DESCRIPTION OF WORK:Paid on PE#{ L;l:OWNER / CONTRACTOR REPRESENTATIVEE 1945SCARSELLAeR0 r rrtRS lNC.lvlatt Lovo SR.LABOR - Name, ClassificationofTREGo/TREGo/TREGo/TREGofiREGonREG6.0HOURS$80.32LOADEDHOURLY RATEs 642.56$s$$$$$$$$$$ 642.56EXTENDEDAMOUNTSEQUIP.NO.13-12EOUlPMENTJD Tractor with mowerOWN o.RENTAL?STDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPER6.0HOURS$0.00$16.26HOURLYRATE$0.00$0.00$0.00$0.00$$$130.08$EXTENDEDAMOUNTS$$$$$$$ 130.0E$$MATERIALQTYUNITCOST$$$$$$EXTENDEDAMOUNTSMARKUP EQUIPMENT:21VoSUBTOTAL EAUIPMENT:MARKUP LABOR:29o/oSUBTOTAL LABOR:12YO MARKUP SUBCONTRACTORS:SUBTOTAL SUBCONTRACTORS:TOTAL THIS REPORT:MARKUP MATERIAL:21%SUBTOTAL MATERIAL:27.32$$130.08$ 186-34I 642.56$0.00s905.30$$ FA Sheet No.193GFORCE ACCOUNT WORKED DAILY REPORT OF Project Name LtD 353 224th st Phase 2 Prime Contractor:Scarsella Project No: 14-3010 Description of Work: Mow fields Work by Subcontracto.?: Sub-Contractor: Item No.:Date: 511312021 STRAIGHT TIME DOLLAR AMOUNTOT RateHrsHrsRateCODEOCCUPATIONNAME107.7565.5 I42"1Laborer $100 LaborerB 85.99c 59.9656.04 200.80100.5580.322.5M LABOR OVERHEAD & PROFIT @ 29% LABOR TOTAL $200.80 2s9.03 SUBTOTAL. LABOR: STANDBYOPERATED DOLLAR AMOUNTRateEOUIPMENT OR ATTACHMENTS ment DesctiPlionEquipment # 12.79F15O-PU2-210 $19.S1F1 50.PU2-291 11.82Ford2-203 58.23Cat938 Loader15-74 40.65$16.262.5JD Tractor d Mower 1 z EOUIPMENT OVERHEAD & PROFIT @ 21% EQUIPMENT TOTAL $ 40.65 49.10 8.54 SUBTOTAL. EOUIPMENT DOLLAR AMOUNTUnit PriceUnitsQuantitY MATERIALS / SERVICES 37.03$37.03I 72" bucket Rental 231#700675lnvoice $ $ SUBTOTAL oVERHEAD&PROFlr@21% TOTAL $ 37.03 44.81 7 "78 n of Hours Worked Jason p61s 121912O21 12% MARKUP (for Prime when subconiract work) 353.03 353.03SHEET TOTAL: TOTAL: Pay Estimate Entered: Date: By: BBOiHtRS INC.SCARSELLADAILY FORCE ACCOUNT / EXTRA WORK REPORT.4 ')T>lvlow fields at Hvtek site.5113t2021Citv ot KentS. 224th St ProiecttIP.O. Box 68697Seattle, WA 98168-0697Office: (2s3) 872-7173Fax: (253) 395-1209CONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:Bid ltem#:DESCRIPTION OF WORK:Paid on PE#SUBTOTAL LABOR:SUBCONTRACTORS$0.00c$$$$$SUBTOTAL SUBCONTRACTORSSCARSELLA BROS., INC. REPRESENTATIVEDATESUBTOTAL EQUIPMENT:MATERIALOTYUNITcosTs$s$$$EXTENDEDAMOUNTSSUBTOTAL MATERIAL;TOTAL THIS REPORT:2'lo/oMARKUP MATERIAL:SUBTOTAL MATERIAL:210hMARKUP EQUIPMENT:SUBTOTAL EQUIPMENT:290hMARKUP LABOR:SUBTOTAL LABOR:12VO MARKUP SUBCONTMCTORS:SUBTOTAL SUBCONTMCTORS:$308.22$t$8.54$40.65$58.23$ 200"80$$0.00"t1 ,t l. f'l .,r't ,t /f( i z ,ffiREsENTATTvE,/.6nrel\ilatt Lovo sRLABOR - Name, Classificationo/TREGo/TREGo/TREGo/TREGo/TREGo/TREG2,5HOURS$80.32LOADEDHOURLY RATE$ 200.80$$$$$QC$$$ 200"80EXTENOEDAMOUNTS13-12EQUIPNO.JD Tractor with mowerEQUIPMENTOWN orRENTAL?STDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPER2.5HOURSs0.00$0.00$0.00$0.00$0.00$ 1 6.26HOTJRLYRATEs40.65$$Gs$$$$$$$$40.65EXTENDEDAMOUNTS FA Sheet No.94 FORCE ACCOUNT WORKED DAILY REPORT OF LID 363 224th St Phase 2 Prime Contractor:Scarsella Project No: 14-3010 Date:511412021 black berriersFinishand start raki Work bY Subconlractor?: Project Name: Item No.: Description of Work: TIME OOLLAR AMOUNTOT RateHrsHrsOCCUPATIONCODENAME 163.75$107.7565.52.5LaborerP 105.25100.5542,1LaborerL 151"73b60,6S B 79,85 Robert $56. F 281.12$100.5580,323 LABOR OVERHEAD & PROFIT @ 2goh s 70'1.85 905.39 203.54 SUBTOTAL. LABOR: LABOR TOTAL STANDBYOPERATED DOLLAR AMOUNTHrsHourly RateHrs 2-210 EQUIPMENT OR AfiACHMENTS Equipment Description FI5O.PU Equipment #12.79$ s 12.75 19.91 I 2-?91 $1 1.82Ford Ranger2-203 58.23 $ $EOUI PMENT TOTAL D Tractor w/ Mower Cat 938 Loader15-74 13-12 56.9,| 8ir.34 69.70 14.64 16.26 EOUIPMENT OVERHEAD & PROFIT @ 21% SUBTOTAL. EQUIPMENT DOLLAR AMOUNTUnit PriceUnitsOuantltY MATER IALS / SERVICES 37.03$37.03$day1 $ $ 72" bucket $ $ 37.03 41.81 7.78 SUBTOTAL oVERHEAD&PRoFlT@21% TOTAL of Hours Worked Date Jaton Dej@ 121912021 Representative 12% MARKUP (for Prime when subcontraci work) SHEET TOTAL:1 034.54TOTAL: Pay Estimate Entered: Date: By: 1945SCARSELLA8H0rHt8S [iC..LJlir'i !:liiDAILY FORCE ACCOUNT I EXTRAWORK REPORTP.O. Box 68697Seattle, WA 98168-0697Office: (2s3) 872-7173Fax: (253) 395-1209CONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:Bid ltem#:DESCRIPTION OF WORK:Paid on PE#Finish additional mowinq and start rakinq black-berry at Hytek site5t14t2021City of KentS. 224th St ProiectLABOR:SUBCONTRACTORS$0.00$$$ss$SUBTOTAL SUBCONTRACTORS:SCARSELIA BROS., INC" REPRESENTATIVEDATE5"I)?lr/SUBTOTAL EQUIPMENT:MATERIALOTYUNITcosT$$$G$$EXTENDEDAMOUNTSSUBTOTAL MATERIAL:TOTAL THIS REPORT:21"/oMARKUP MATERIAL:SUBTOTAL MATERIAL:21o/oMARKUP EQUIPMENT:SUBTOTAL EQUIPMENT:29o/"MARKUP TABOR:SUBTOTAL I-ABOR:12O/O MARKUP SUBCONTRACTORS:SUBTOTAL SUBCONTRACTORS:$969.72$i$14.64$69.70$ 203.54$ 701.8s$t0.00Siaosi PeleRafael BarajasAlejandro LunaMatt Lovo SRLABOR - Name, ClassificationotTREGorTREGo/TREGofTREGo/TREGol'fREG!l2.52.52"53.5HOURS$6s.50$60.69$42.10$E0.32LOADEDHOURLY RATE$ 701.E5$$$$!s 163.75$$ 151 .73$ 105.25@$ 281.12EXTENDEDAMOUNTS2-21013-12EOUIPNOFl50 PUJD TractorEQUIPMENToWN orRENTAL?STDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPER1,03.5HOURS$0.00$0.00$0.00$0.00$ 12.79$16.26HOURLYRATEt69.70$$$$$$$$$$12.79c!56.91EXTENDEDAMOUNTSOWNER / CONTMCTOR FA Sheet 1{x\--,r' KENTFORCE ACCOUNT WORKED DAILY REPORT OF Item No. e them Project Name LID 363 224th St Phase 2 Contractor:Scarsella Project No: 14-3010 Date 512412021 Description of Work:Remove blackberries and Work by Subcontractor?: Sub-Contractor: OVERTIMESTRAIGHT DOLLAR AMOUNTHrsOT RateRateHHrsOCCUPATIONCODENAME107 $100.5542.1Leborer 100.5560.69LaborerRafael $79_385.99SRo 183.73$EO73.49 642-56$180.32IAsu F SU B-TOTAL. LABOR: $826;?9 235.62 LABORTOTAL $ LABoR OVERHEAD & PROFIT @ 297q STANDBYOPERATED DOLLAR AMOUNTRateEOUIPMENT OR ATTAC Equipment DescriPtion HMENTS Equipment # 12F1 50-PU2-210 179.'137'l_652.5Mack 63.9525.582.5Trailer27-215 $ Cat 938 Loader15-74 $'t6-20 JD Tractor w/ Mower13-12 U $ SUBTOTAL -EQUIPMENT EQUIPMENT TOTAL 243.08 294.13 51.05 EQUIPMENT OVERHEAD & PROFIT @ 21% DOLLAR AMOUNTL-Jnit PriceUnitsOuanlitY MATERIALS / SERVICES 34.07$ 34.07I Rental lnvoice #72" bucket 363.29383.291 JD lnvoice # 231676800 $ SUBTOTAL oVERHEAD&PROFIT@21% TOTAL $ $ $ 397,36 480.81 83.45 on of Hours Worked: Jaon g'alg 121912021 12% MARKUP (for Prime when subcontract work) SHEET TOTAL .85 $ .85$1 TOTAL: Pay Estimate Entered: Date: By: l7tDAILY FORCE ACCOUNT / EXTRAWORK REPORTSUBTOTAL LABOR:SUBCONTRACTORS$0.00$$$$$!SUBTOTAL SUBCONTRACTORS:SCARSELLA BROS., INC. REPRESENTATIVEDATERemove and stack blackberrv at Hytek site.5t24t2021Citv of KentS. 224th St ProiectSUBTOTAL EQUIPMENT:SUBTOTAL MATERIAL:P"O. Box 68697Seattle, WA 98168-0697Ofnce: (253) 872-7173Fax: (253) 395-1209CONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:Bid ltem#:DESCRIPTION OF WORK:Paid on PE#8F0',l hE8S ll{C19AbSCARSELLAAaron WallaceAsu FuimaonoLABOR - Name, ClassificationofTREGo/TREGofiREGo/TREGo/TREGorTREG2.58.0HOURS$73.49$80.32LOADEDHOURLY RATEs E26.29$$$$$$$$$$ 183.73$s 642.56EXTENDEDAMOUNTS27-2158-035EQUIPNO.Lowboy TrailerMack Lowboy TruckEQUIPMENTOWN orRENTAL?STDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPER2.52"5HOURS$0.00$0.00$0.00$0.00$25.58$71.6sHOURLYRATE$243.08$$$$ss$$$$63.95s$179.13EXTENDEDAMOUNTSPape lnv # 231678900Pape lnv # 231676600MATERIAL11QTY"$ 2,152.46$ 4,359.s6UNITCOST$ 6.512.42$$$$ 2.1s2.46$ 4,359.96EXTENDEDAMOUNTSTOTAL THIS REPORT:MARKUP MATERIAL:210,/oSUBTOTAL MATERIAL:21o/oMARKUP EQUIPMENT:SUBTOTAL EQUIPMENT:29o/oMARKUP TABOR:SUBTOTAL LABOR:12O/O MARKUP SUBCONTRACTORS:SUBTOTAL SUBCONTRACTORS:t9,240.06$ 1.367.61$ 6,s12.42$51.05t 24il.0Ea239.62$ E26.29$$0.00OWNER / CONTRACTOR REPRESENTATIVEDATE P.O. Box 68697Seattle, WA 98168-0697Office: (253) 872_7173Fax: (2S3) 395-1209I,'AIL Y F{JRCE ACCOUNT / EXTRA WORK REPORTCONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:SUBTOTALLABOR:TESUBTOTALEQUIPMENT:SUBTOTAL MATERIAL:BROS,, INC.REPRESENTATIVEa-).t535EQUIPNO.-lt-i t",t.t'VLi-HL"rboy frc^cKKi.,t-RrnV-t\(\<-cr.;\\OWN orRENTAL?STDBYSTDBYSTDEYSTDBYSTDBYRSTDBYOPERSTDBVSTDBYSTDBYRHOURSHOURLYRATE$$$o/Tono/TorToiTO/To/ToiTo/TLAAORRALOADED$c$RSELER0THER$ lilcTOTAL THISMATERMARKUPIAL:MATERIAL:/oMARKUPEOUIPMENT:SUBTOTAI./oMARKUPLABOR:SUBTOTALLABOR:MARKUPSUMATERIALQTYUNITCOSTOWNER /TEz FAS No.:196GFORCE ACCOUNT WORKED DAILY REPORT OF Item No. them Project Name:LtD 363 224th St Phase 2 Description of Work:Remove blackbe rries and Prime Contractor:Scarsella Project No: 14-3010 by Subcontractor?: Date: 512512A21 ESTRAIGHT TIME DOLLAR AMOUNTOT Rat€HrsRateHrsCODEOCCUPATIONNAME 65.50$107.75651Laborer 142,1Laborerndro $160.69Laborer 85.99 S $59.9673 642.56t 00.5580I SU BTOTAL. LABOR: $ LABORTOTAL 9 LABOR OVERHEAD & PROFIT @ 29%205.34 913.40 STANDBYOPERATED DOLLAR AMOUNTRateEOUIPMENT OR ATTACHMENTS DescriEquipment # 12"F15O-PU2-210 $71Mack8-035 25.58Trailer27-215 21.19$21IFlatbed3-082 Traclor w/ Mower13-12 EOUTPMENT OVERHEAD & PROFIT @ 21% EQUIPMENT TOTAL $ $ 21.19 25.81 4.45 SUBTOTAL - EQUIPMENT DOLLAR AMOUNTt-Jnit PriceUnitsQuantitY MATERIALS / SERVICES 37.03$37.03I Rental lnvoice # 2372" bucket 363,29$ 363.29 JD 325G lnvoice # 231676800 $ $ SUBTOTAL oVERHEAD&PROFIT@21% TOTAL 400.32 484.39 $ $ $ Verification of Hours Worked: Jason Derr- 121912021 Ownels 12% MARKUP (for Prime when subcontract work) SHEET TOTAL: 3.43 1 3.43 TOTAL: Pay Estimate Entered Date: By: L4I{bDAILY FORCE ACCOUNT / EXTRA WORK REPORTP.O.Box68697seatfle, wA 98168-0697Office: (253) 872-7173Fax (253) 395-1209CONTRACT NAME, NO,:OWNER / CONTMCTOR:DATE:Bid ltem#:DESCRIPTION OF WORKPaid on PE#S. 224th St ProiectCity of Keni5125t2021Remove blackberry from Hvtek site.SCARSELLABBOIHTRS INC.1946RACEXTET{DEDAMOUNTS$21.19$$c$$$D$s$$$21.19I.IOURLYRATE$21.19$0.00$0.00$0.00$0.00$0.00HOURS1.0OPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN orRENTAL?EQUIPMENTFlatbed to fuel skidsteerEXTENDEDAMOUNTSEQUIPNO.642.563-08265.50$$$$$$$s 708.06LOADEDHOURLY RATE$80.32$65.50HOURS8.01.0LABOR - Name, ClassificationREGo/TREGo/TREGonREGo/TREGOTTREGo/TAsu FuimaonoSiaosi PeleSUBTOTAL LABOR:$$$e$$$0.00SUBCONTRACTORSSUBTOTALSCARSELLA 8ROS", INC, REPRESENTATIVEDATESUBTOTAL EQUIPMENT:SUBTOTALEXTENDEDAMOUNTS$a$$$sUNITcosTQTYMATERIAL$0.00$$ 708.06$205.34$21.19e4.4st$$939.04SUBTOTAL SUBCONTRACTORS:12YO MARKUP SUBCONTRACTORS:SUBTOTAL LqBOR:29o/oMARKUP LABOR:SUBTOTAL EQUIPMENT:21o/oMARKUP EQUIPMENT:SUBTOTAL MATERIAL:MARKUP MATERIAL:21o/oTOTAL THIS REPORT:OWNER / CONTRACTOR REPRESENTATIVEDATE RSELER(}THERE INE.DAILY FORCE ACCOUNT / EXTRA WORK REPORTCONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:P O. Box 68697seanle, wA 98168-0697Office; (253) 872-7173Fax: (253) 395-1209SUBTOTAL LABOR:cv$$$$$$SUBCONTRACTORSSUBCONTRACTORS:REPRESENTATIVEDATEEXTENDEDAMOUNTSs$$$$$$$$$$$c$$$$$$$bLOADEDHOURLY RATTHOURSAILABOR - Name, ClassificationREGO/TREGoiTREGo/TREGo/TREGoffREGo/TREGo1TREGo/TREGo/TREGo/Ttr 5n "-rna- F u -T N\ ono-F.f(w. be*w./EXTENDEDAMOUNTS$$$$$$$$$$$oq$$$$$$$$$HOURLYRATEHOURSf4IOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN orRENTAL?{t^.p(rJ\EOUIPMENTR.s.\-t Shi,! <k?f e,i\tr(abP r-K. ,Lrzil!^. c'z^ tDl -EQUIPNO.j-81SUBTOTAL EAUIPMENT:SUBTOTAL MATERIAL:EXTENDEDAMOUNTSb$o$oUNITcosTQTYMATERIALSUBTOTAL SUBCONTRACTORSTI$% MARKUP SUBCONTRACTORS: l$SUBTOTAL LABOR: l$-% MARKUP LABOR:I$SUBTOTAL EOUIPMENT:l$% MARKUP EOUIPMENT:l$SUBTOTAL MATERIAL:l$% MARKUP MATERIAL:l$TOTAL THIS REPORT:l$OWNER /BROSaNTATIVEL Sheet 1,A\-./ KENTFORCE ACCOUNT WORKED DAILY REPORT OF and o Project Name:LrD 363 224th St Phase 2 Prime Contractor:Scarsella Work by Description of Work:Remove bl them Item No. 14-30{0Prolect No: Date: OVERTIMESTRAIGHT TIME DOLIAR AMOUNTOT RateHrsHourly RaleHrsOCCUPATIONCODENAME $107.75R 1 10042.1 b160.69Laborer 79.3585.99Foreman $59.9673.49LaborerW 642.561 00.5580.32 F LABOR OVERHEAD & PROFIT @ 29Yo $ 708.06 913.40 205.34 SUBTOTAL. LABOR: LABOR TOTAL STANDBY DOLLAR AMOUNTHrs OP HouEQUIPMENT OR ATTACHMENTS EquipmentEquipment # F1 50-PU2-214 Mack0-035 Trailer 25.58 71.65 Rate 12.79 $ 27-215 13-12 3-082 16.26 21.191Flatbed JD Tractor d Mower 21.19$ $ $ EOUIPMENT TOTAL 21.19 25.64 4.45 SUBTOTAL. EOUIPMENT EQUIPMENT OVERHEAD & PROFIT @ 21% DOLTAR AMOUNTUnilsUnit PrlceQuantitY MATERIALS / SERVICES 37.03$37.031 72" bucket lnvolce #231675704 363.29$363.291 lnvoice * 23JD 325G $ $ $ $ s 400.32 484.39 84.07 SUBTOTAL oVERHEAD&PRoFlr@21% TOTAL of Hours Worked; Jwon DaE1A9l2O21 12% MARKUP (for Prime when subcontract work) SHEET TOTAL 43 1 TOTAL: Pay Estimate Entered: Date; By: 1tr.{it1DAILY FORCE ACCOUNT I EXTRAWORK REPORTSUBTOTAL LABORT$$$$q$s0.00SUBCONTRACTORSSUBTOTALSCARSELLA BROS., INC. REPRESENTATIVEDATES. 224ih St ProieciCity of Kent512612021Remove and pile blackberry at Hytek site.SUBTOTAL EQUIPMENTSUBTOTAL MATEP.O. Box 68697Seattle, WA 98168-0697Office: (2s3) 872-7173Fax: (253) 395-1209CONTRACT NAME, NO.:OWNER I CONTRACTOR:DATE:Bid ltem#:OESCRIPTION OF WORK:Paid on PE#1946SCARSELLA8RO IHLBS INC.EXTENDEDAMOUNTSs 642.56$$ 65.50$$$$$$$$$$ 708.06LOADEDHOURLY RATE$80"32$65.50HOURS6.01.0LABOR - Name, ClassificationREGorTREGo/TREGo/TREGo/TREGo/TREGorTAsu FuimaonoSiaosi PeleEXTENDEDAMOUNTS$21 .19${$$$$$$D!$c2't.19HOURLYRATE$21.19$0"00$0"00$0.00$0.00$0.00HOURS1.0OPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN o.RENTAL?EQUIPMENTFlatbed to fuel skidsteerEQUIPNO.3-082EXTENDEDAMOUNTSo$$$$UNITcosTQTYMATERIALt0.00$$70E.06$2A5.34s21.19$4.45I$$939.04SUBTOTAL SUBCONTRACTORS:12Oh MARKUP SUBCONTRACTORS:SUBTOTAL LABOR:29o/oMARKUP TABOR:SUBTOTAL EQUIPMENT:21%MARKUP EOUIPMENT:SUBTOTAL MATERIAL:MARKUP MATERIAL:210,/oTOTAL THIS REPORT:OWNER / CONTRACTOR REPRESENTATIVEDATE DAILY FORGE I\GCOUNT / EXTRA WORK REPORTP.O. Box 68697seattte, wA 98168-0697Office: t2S3)872_7175Fax; (253) 39s-1209CONTMCT NAME, NO.:OWNER / CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:DATESUBTOTALLABOR:SUBTOTALSUBTOTAL EQUIPMENTSUBTOTALMATERIAL:8ROS., INC. REPRESENTATIVEBROIHERS INC.RSELEXTENDEDAMOUNTS$s$$$$$LOADEDHOURLYREGREGOffREGo/To/TLurr Qrn"r.LABOR.lassiflcationco\"d^Ldf p7-ntar\-'lsi(tEXTENDEDAMOUNTS$UNITcosTQry.TERIALaEXTENDEDAMOUNTS$$$$$$HOURLYRATEHOURSSTDBYOPERSTDBYRBYOPERPERSTDBYOPERSTDBYYOPEROWN orRENTAL?(d-AIPMENTSK:d*StsLrki{.r\Rzr\--tSt-t{o.."-1,",,\l" p^",tEQUIPNO.sJ$ac$$!$$$b$$$$s$SUBTOTALNTRACTORS;SUBCOMARKUPo/OR:SUBTOTAL LABLABOR:MARKUPIOSUBTOTALUIPMENT:EQNT:EQUIPMEMARKUP%MATERIAL:UBTOTALSMATERIAL:MARKUPTOTAL THIS REOWNER/TIVEDA FA Sheet No.:198GFORCE ACCOUNT WORKED DAILY REPORT OF Scarsella them Prime LID 363 224th St Phase 2 Project No: 14-3010 Date:512712021 blackberries and Work bY Subcontractor?: Sub-Contractor: Project Name: Item No.: Description of Work: OVERTIMESTRAIGHT TIME DOLLAR AMOUNTOT RateHrsHourly RateHrsOCCUPATIONCODENAME s107.75 142.1LaborerL $10060.6S B 79.3585.99 Robert $ 401.60$1 00.55805ForemanuF $AL LABOR:SUBTOT LABOR OVERHEAD & PROFIT @ 29Yo $ 401 .60 518.06 t 16.46 LABOR TOTAL STANDBYOPERATED DOLLAR AMOUNTHrsHourly RateHTS EOUIPMENT OR Equipmeni #Equipment Descrlption Flaibed ENTS F1 50.PU Mack Trailer 2-210 27-215 8-035 $12.79 $71.65 25.58 $ $ 3-082 13-12 $16.26JD Tractor d Mower $ EQU IPMENT TOTAL SUBTOTAL - EOUIPMENT EQUIPMENT OVERHEAD & PROFIT @ 21% DOLLAR AMOUNTUnit PriceunltsQuantitY MATERIALS / SERVICES 37.03$37.03 72" bucket Rental lnvoice # 23 363.29363,291 JD 325G lnvoice # 231676800 $ $ s s E 400.32 484.39 84.07 SUBTOTAL OVERHEAD & PROFIT @ 21 o/o TOTAL of Hours Worked: Jaon oale 121912021 12% MARKUP (for Prime when subcontract work) 1,002.45 SHEET TOTAL:1 TOTAL Pay Estimate Entered: Date: By: itjf'DAILY FORCE ACCOUNT / EXTRA WORK REPORTCONTRACT NAME. NO.:OWNER / CONTMCTOR:DATE:P.O. Box 68697seatfle, wA 98168_0697Offce; (2Sg) 872-7173Fax: (259) 395-1209SUBTOTALBid ttem#:DESCRIPTION OF WORK:paid on pE#SCARSELTA BROS.,OWNER / COREPRESENTATIVElNc.DATEE 1945SCARSELLA8RC rhf tls tr.lcof Kent5127na21atrarn.toduestartlateAMOUNTS$ 401.60D$$$$401.60RATEHOURLYLOADEDREGo/TREGREGREGo/TREGFuimaono$401.60116.46i!SUBTOTALMARKUPSUBTOTALMARKUPEQUIPMENT:TOTALSUBEQUIPMENT:MARKUPMATERIAL:SUBTOTALTERIAL:MAPMARKUTOTAL THISAMOUNTS$sa$UNITcosTQTYMATERIALYRATEAMOUNTS$$$0.$$$HOURSOPEROPERSTDBYOPEROPEROPERSTDBYOPERSTDBYNO.IPMENTOWN orRENTAL?NTRACTORREPRESENTATIVEDATE EROTHERS IilC.ARSELDAILY FORCE ACCOUNT i EXTRA WORK REPORTCONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:P,O. Box 68697Sealue, WA 98168-0697Omce: (25qA72-7173Fax: (253) 395-1209cosT coDESCRIPTION OF WORK:SUBTOTAL LABOR:SUBTOTAL EQUIPMENT:SUBTOTAL MATERIAL:EXTENDEDAMOUNTS$$$$$$$b$$$$$$$s$$c$aLOADEDHOURLY RATEHOURSLABOR - Name, ClassificationRtrGo/TREGo/TREGo/TDEAo/TREGo/TREGo/TREGo/TREGo/TREGoffREGo/rA(r^ -rnr^ n^t -TN\oA,-rlWWltr'rrw,rxEXTENDEDAMOUNTS$$$a$$b$$$$$s$$$b$$$$HOURLYRATEHOURSOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN orRENTAL?P"*^EQUIPMENTSKasP"rc-i \-in r.'"YEQUIPNO.$SUBTOTAL SUBCONTRACTORS:l$l$$$SUBCONTRACTORSlsl$EXTENDEDAMOUNTS$o$$$UNITcosTQTYMATERIAL($$$$$$$$$SUBTOTAL SUBCONTMCTORS% MARKUP SUBCONTRACTORS:SUBTOTAL LABOR:% MARKUP LABOR:SUBTOTAL EQUIPMENT:% MARKUP EQUIPMENT:SUBTOTAL MATERIAL:% MARKUP MATERIAL:TOTAL THIS REPORT:OWNER /REPRESENTATIVE No.:199{x\/KENT DAILY REPORT OF FORCE ACCOUNT WORKED LtD 363 224th St Phase 2 ines Project No: 14-3010 Work bY Subcontractor?: Sub-Contractor: Project Name: Item No.: Description of Work: Date: 512812021 OVERTIMESTRAIGHT TIME $65.50 DOLLAR AMOUNT 100,55 OT Rate 107 HrsHourly Rate 42.1 HrsOCCUPATION Laborer CODENAME 79.35 59.96 '100.5580.32 9U.OJ 85.99 73.491 oForeman 73.49 642.56b $ Asu F TABOR OVERHEAD & PROFIT @ 290k $ 781.55 226"65 LABORTOTAL T SUETOTAL.IABOR: OPERATED 71.65 ST Rate 71 25.58 $ $ 1 I EOUIPMENT OR ATTACHMENTS Equipment # F15O-PU2-210 Mack8-035 DOLLAR AMOUNT 1 19,'l 5s ata EOUIPMENT s TOTAL $ 25.O2 144.17 EOUIPMENT OVERHEAD & PROFIT @ 21% SUBTOTAL. EQUIPMENT DOLLAR AMOUNTUnit PriceUnitsQuantiiY #23JD 325G 72" MATERIALS / SERVICES Rental lnvoice *2X1675700 37.03$$ 37.03dav1 363.29$363.29$day1 $ $ $ SUBTOTAL oVERHEAD&PROFIT@21% TOTAL 484.39 a a on of Hours Worked: 0nOwneis Date 121912021 1270 MARKUP (for Prime when subcontract work) SHEET TOTAL: 636. 761 TOTAL: Pay Estimate Entered: Date: By: DAILY FORCE ACCOUNT/ EXTRA WORK REPORT^lt/HlillrP.O. Box 6E697Sealtle, WA 98168_069?Office: (2Sa) 872-7173Fax (253) B9s-1209SUBTOTALCONTMCT NAME, NO.:OWNER/DATE:Bid ltem#:DESCRIPTION OF WORK:paid on pE#SUEQUIPMENTSCARSELTA 8ROS.,OWNER /CONTRACTORREPRESENTATIVEtNcDATE$781.55s$ 226.65$ 119.1s25.02$$SUBTOTALMARKUPTABOR:P LABOR:MARKUEQUIPMENT:SUBTOTALEQUIPMENT:MARKUPTERIAL:MASUBTOTALMATERIAL:MARKUPREPORT:THISALTOT$$s10.00DEXTENDEAMOUNTS$ 642.5673.49G$ 6s.s0$$$781.55HOURLY RATE$65.s08.011,0REGREGoiTREGFuimaonoWallaceSlaosi Pele224th sroi KentforfromRemovetomachineEXTENDEDAMOUNTS21.92I$71.65Go25.58$c$$$$$119.15RATE071$0.00HOURS11ROPERSTDBYOPER$IDBYoWN orRENTAL?EQUIPMENTwith fuelMack Lowboy TruckTrailerNO.EQUIP3-0825AMOUNTSa$6$$UNITCOSTQTYMATERIALREPRESENTATIVEDATE DAILY FORCE ACCOUNT / EXTRA WORK REPORTll:,,P.O, Box 68692Seattle, WA 98168-0697Omce: (2S3) 872_217sFax; (253) 395-.t209CONTRACT NAME, NO.:OWNER / CONTMCTOR:DATE:COST CODE:DESCRIPTION OF WORK:TESUBTOTALLABOR:EQUIPMENT:SUBTOTALSUBTOTALBROS., INC.REPRESENTA8R0TH[Rs B,/c.RSELEXTENDEDAMOUNTS$c$$$sLOADEDHOURLY RAHOo/To/To/TREGorfo/TWrLABOR.Classificationol*+.r(/"(,-\\64<-sw(/q\TI/lJ\r^\i05*EXTENDEDAMOUNTSUNITcosTQTYMATERIALEXTENDEDAMOUNTS$$$$sHOURLYRATEHOURSOPERSTDBYROPEROPERSTDBYOPERBYSTDBYSTDBYOWN orRENTAL?o-(\&-v{\MENTR.rrtr, SK;<F^4eV*U-r-.- c^r.\tfn4{-KLr./b.Y tn<-(Lov\rV f.r-^.t<--EQUIPNO.3-eL94591-)6t$$$s$$$$MARKUP%SUBTOTALLABOR:LABOR:MARKUPNTEQUIPMESUBTOTALPMENT:EQUPMARKUo//oMATERIAL:ALSUBTOTTERIAL:MAMARKUP/oREPORT:THISALTOTOWNER/TIVEE FA./x\-/KENTFORCE ACCOUNT WORKED DAILY REPORT OF Project Name LtD 363 224th St Phase 2 Prime Contractor: Project No:14-3010 Date 6t112021 Description of Work: Remove mob Work bY Subcontractor?: Sub-Contractor: Item No.: STRAIGHT TIME DOLLAR AMOUNTOT RateHrsRateHrsOCCUPATIONCODENAME10765LaborerP u100.551LaborerLAII60.69 B $85.99Robert 367.45o60 642.56$80IF SUBTOT AL - LqBOR: $ LABOR OVERHEAD & PROFIT @ 29% $ 1 ,010.01 292.90 TOTAL $ OPERATED DOLLAR AMOUNTRaleEQUIPMENT OR ATTACH MENTS DescrlplionEquipment # $12.7950-PU2-210 358,2571.65Mack8-035 127.90$25.58Trailer $21 3-082 $16JD Tractor w/ Mower13-12 $ $ $EQUIPM ENT TOTAL 486.1 5 588.24 102.09 SUBTOTAL - EQUIPMENT EOUIPMENT OVERHEAD & PROFIT @ 21% DOLLAR AMOUNTUnit Pricet-JnitsQuantitY MATERIALS / SERVICES $ 744"651tractor lnvoice #track kuck 37.03$37.03$1# 231675700Renlal 16$383.29 lnvoice # 231676800JD 325G $ SUBTOTAL oVERHEAD&PROFIT@21% TOTAL 2,704.16 $ $ $ Verification of Hours Worked Date Jatou DaIe 1219t2021 '12% MARKUP (for Prime when subcontract work) SHEET TOTAL: $ 4 595.31TOTAL: $ Pay Estimate Entered: Date: By: u-du)DAILY FORCE ACCOUNT / EXTRA WORK REPORTP.O" Box 6d697Seattle, WA 98168-0697Office: (253) A7Z-Zt7gFax: (2S3) 3SS-1209CONTRACT NAME, NO,:OWNER / CONTMCTOR:DATE:Bid ttem#DESCRIPTION OF WORK:paid on pE#AL LABOR:SUBTOTALSCARSELLA BROS., INC.REPRESENTATIVEOWNER iCONTRACTORDATE19458HC rHiRS tt{c.SCARSELLA$1292.90I$ 486.15'102.09$$ 625.50SUBTOTALMARKUPLABOR:SUBTOTALMARKUP LABOR:EQUIPMENT:SUBTOTALEQUIPMENT:MARKUPMATERIAL:SUBTOTALMATERIAL:MARKUPTOTAL THISAMOUNTS$$$UcosTQTY'|II/|ATERIALRenlal MarookaTractorlnv #1 9845s. 224th stof Kenl12021fromRemoven.backskidtersite/MOBAMOUNTS358.25s127.90$$s$$$QHOURLRATE$25.58HOURSOPERSTDBYOPEROWN orRENTAL?Lowboy TruckTrailerNOEQUIP8-035-215EXTENDEDAMOUNTS$ 642.56$$ 367.45$s$$$$$$1RATEHOURLYLOADED8.0o/TREGoffREGFuimaonoWallaceREPRESENTATIVEDATE UAILY FORCE ACCOUNT / EXTRA WORK REPORTP"O. Box 6e6S7Seattle, WA 98168_0697Oitice: (253)e72_7173Fax; (253) 395-1209CONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:SUBTOTALLABOR:SUBTOTALSSUBTOTALEQUIPMENTSUBTOTALMATERIAL:REPRESENTATIVEEXTENDEDAMOUNTS$$$$$$$LOADEDHOURLY RAREGo/TREGo/TREGo/TREGo/To/TClassificationLABOR.at{d.rrAr1r\A{EXTENDEOAMOUNTSUNITcosTQTYMATERIALEXTENDEDAMOUNTS$$4$0$HOURLYRATEHOURSSTDBYOPFROPERTDBYOPERSTDBYRSTDBYOPEROPERROPEROWN orRENTAL?Iteltqr^&;r!NTlv^l&4/LKSffura,Ka 11=<frR"At^iNO.EQUIP8-ss$$$$$$$$uALTOTBUSMARKUPOR:SUBTOTAL LABLABOR:MARKUP/oIPMENT:EOUALSUBTOTENT:PMEQUIPMARKUTERIAL:MAALBTOTSUTERIALTMAMARKUPOtTOT.AL THISOWNER /Z FA Sheet No.201{ADAILY REPORT OF FORCE ACCOUNT WORKED 2 to la Project Name LrD 363 224th st Prime Contractor: Project No: 14-3010 Work by Su bcontractor?: Description of Work:Haul blackberries Sub-Contractor: Item No.:Date: 61212021 OVERTIMESTRAIGHT TIME DOLLAR AMOUNTOT RateHrsRateHrsOCCUPATIONCODENAME 65.50$107.765.51Laborer 587.92 Matt $1 00.55 LaborerB $79.3585,99Foreman $73LaborerW 642.56D100,5580IF LABOR OVERHEAD & PROFIT @ 29% LABOR TOTAL s.83 .81 SUBTOTAL. LAEOR: STANDBYOPERATED DOLLAR AMOUNTRateEOUIPMENT OR ATTACHMENTS Equlpment DescriPtionEqulpment # 12.79F12-AA s71,65Mack8-035 u25.58Trailer27-215 21.92$211Flatbed3-082 $16JD Traclor w/ Mower13-12 EQUIPMENT OVERHEAD & PROFIT @ 21% EQUIPMENT TOTAL $ 21.92 26.52 4.60 SUBTOTAL - EQUIPMENT DOLLAR AMOUNTUnit PriceUnitsQuantitY MATE RIALS / SERVICES tractor lnvoice # 1 9845 Renlal lnvoios * 231675700 JD 325G lnvoice # 23't676800 Marooka track lruck 72" bucket $744.65$ 744.65DAY1 37.03$$ 37.03DAY1 363,29$$ 363.29DAY1 $ $ $ $ 144.57 240,44oVERHEAD&PROFlr@21% TOTAL SUBTOTAL $ cation of Hours Worked z* -" Ja^lou 12t9t2021 DateRepresenialive 12% MARKUP (for Prime when subcontraci work) 083.74 74SHEET TOTAL: $ TOTAL: $ Pay Estimate Entered: Date: By: 1945SCARSELLAEROIHTRS IN[.'7cDAILY FORCE ACCOUNT / EXTRAWORK REPORTP-O. Box 68697Seattle, WA 98168-0697Ofilce: (253) 872-7173Far (253) 395-1209CONTR,ACT NAME, NO.:OWNER / CONTMCTOR:DATE:Bid ltem#:DESCRIPTION OF WORK:Paid on PE#SUBTOTAL LABOR:SUBCONTRACTORS$aol$l$$0.00SUBTOTAL SUBCONTRACTORS:SUBTOTAL EQUIPMENT:EXTENDEDAMOUNTS$U$$UsUNITCOSTQTYMATERIALSUBTOTALSCARSELLA BROS., INC. REPRESENTATIVEDATE224th slCitv of Kent61212021blackberrv out to loadino sDot with track truck.HaulEXTENDEDAMOUNTS$ 642.56$$ 642.s6$$ 65.50$$$$$$$s 1,350.62LOADEDHOURLY RATE$40.32$80.32$65.50HOURS8.06.01.0LABOR - Name, classificationREGo/TREGo/TREGo/TREGo/TREGo/TREGo/TAsu FulmaonoMatt Lovo JRSiaosi PeleEXTENDEDAMOUNTSG21"92$$$$$Q$s$$$21.92HOURLYRATE$21.92$0.00$0.00$0,00$0.00$0"00HOURS1.0OPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN orRENTAL?EQUIPMENTFord Flatbed with Fuel TankEQUIPNO3-0E2$0.00c$ 1.350.62a391.68$21.924.60s$$1,768.82SUBTOTAL SUBCONTRACTORS:12j6 MARKUP SUBCONTMCTORS:SUBTOTAL LABOR:29%MARKUP LABOR;SUBTOTAL EQIJIPMENT:21YoMARKUP EQUIPMENT:SUBTOTAL MATERIAL:MARKUP MATERIAL:21o/oTOTAL THIS REPORT:OWNER / CONTRACTOR REPRESENTATIVEDATE BRoTH[ff8 t]lB"ARSELDAILY FORGE ACCOUNT / EXTRA WORK REPORTCONTRACT NAME, NOP.O. Box 68697Seatue, WA 98168-0697Office; (253) 872-7173Fax: (253) 395-1209OWNER / CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:SUBTOTAL LABORf :lz^ n{ [4-n{(b /9- / e-lutl).^t 8lo. ll-,,*- .-.-L l-r" LoJt$t- <aaL. utaYhllu-K In^{!\SUBTOTAL EQUIPMENT:SUBTOTAL MATERIAL:ATIVEzEXTENDEDAMOUNTS$b$$$$a$$$$$$$$$$$$$bLOADEDHOURLY RATEHOURSq?at.LABOR - Name, ClassificationREGorTREGO/TREGo/TREGo/TREGo/TREGoiTREGo/Tl)trno/TREGoffREGo/TAsu,"^n F r, i, r.oriDSf{,* o(avJ1(m^.* Lovo'fK-0?.'ph((';,,< i o,\,, /L.t ^.EXTENDEDAMOUNTS$$$$$$$$$$$$$$$$o$$$HOURLYRATEHOURSqOPERSTDBYOPERSTDBYOPFRSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN orRENTAL?ft*t[t"n"t-EQUIPMENTR^t-+ St'i'Lgk+cr,ulkw rz'ttVcos(-cfsr-<.ifr -trtrtA \ruwrz,Va-l(r r .N -F-c,rr- ?-cv{ lLfEQUIP.NO.3*t$b$$$$$SUBTOTAL SUBCONTRACTORSSUBCONTRACTORSEXTENDEDAMOUNTS$$$$oUNITcosTQTYMATERIA.L$$$$$$$SL]BTOTAL SUBCONTRACTORS% MARKUP SUBCONTRACTORS:SUBTOTAL LABOR:% MARKUP LABOR:SUBTOTAL EQUIPMENT"/O MARKUP EQUIPMENT:SUBTOTAL MATERIAL:O/O MARKUP MATERIAL:TOTAL THIS REPORT:OWNER/BROS.TATIVE FA No,242./>\-./KENTFORCE ACCOUNT WORKED DAILY REPORT OF Project Name:LtD 363 224th St Phase 2 Work bY Subcontraclor?: Prime Contractor:Scarsella Description of Work:Haul blackbe rries out to Item No.: 14-3010Project No: Date: OVERTIMESTRAIGHTTIME DOLLAR AMOUNTOT RateHrsRateHrsOCCUPATIONCODENAME 65.50107.75o1LaborerSa ^92100.55 L $60.69 7g85;99S s W 642-56$1 UF s t ,81 SUBTOTAL - LABOR LABOR ovERHEAD & PROFIT @ 29% TOTAL OPERATED DOLLAR AMOUNTRateEOUIPMENT OR ATTACHMENTS Equipment DescriptionEquipment # 12F12-21A $71Mack8-035 25.58Trailer27-215 21$21Flatbed3-082 1JD Tractor W Mowert3-12 EQUIPMENT OVERHEAD & PROFIT @ 21% EQUIPMENT TOTAL a 21.92 26.52 4.60 UBTOTAL. EQUIPMENT IATERIAL8ISEF DOLLAR AMOUNTUnit PriceUnitsQuantitY kaclor lnvoice f 231#lnvoiceRentalbucket72" MATERIALS / SERVICES Marooka ttack truck *23JD 744.65$$ 744.65day1 37.03$$ 37.03day1 $363.29$ 363.29daya $ $ SUBTOTAL oVERHEAD&PRoFlT@21% TOTAL $ $ 144.97 240"44 Verification of Hours Worked: Data Jaou ggi(e 1219t2o2'l 12% MARKUP (for Prime when subcontract work) 3.74 74SHEET TOTAL: 3TOTAL: Pay Estimate Entered: Date: By: 19A6SCARSELLAEF.iOTHTRS INC//' :L'1oLDAILY FORCE ACCOUNT I EXTRA WORK REPORTP.O. Box 68697Seattle, WA 9E168-0697Ofilce: (253) 872-7173Fax: (253) 395-1209CONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:Bid ltem#:DESCRIPTION OF WORK:Paid on PE#S. 224th St ProtectCity of Kent51312021Haul blackberry from stockpileR:$o$$$$$0.00SUBCONTRACTORSSUBTOTAL SUBCONTRACTORS:SUBTOTAL EQUIPMENTEXTENOEDAMOUNTScG$$$UNITcosTQTY,MATERIALSUBTOTAL MASCARSELLA BROS., INC. REPRESENTATIVEDATEEXTENDEDAMOUNTS$ 642.56$$ 642.56s$ 65.50$$$$!$$$ 1,350.62LOADEDHOURLY RATE$80.32$80"32$65.50HOURS8.08.01.0LABOR - Name, ClassificationREGo/TREGotfREGo/TREGonREGo/TREGo/TAsu FuimaonoMan Lovo JRSiaosi PeleEXTENDEDAMOUNTS$21.92$$$$$$s$$$s21.92HOURLYRATE$21"92$0.00$0.00$0.00$0,00$0.00HOURS1.0OPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN otRENTAL?EQUIPMENTFord Flatbed with Fuel TankEQUIPNO.3-082$0.00s 1,350.62$ 391.68I21.92$4.60I$$1,76E.82SUBTOTAL SUBCONTRACTORS:12O/O MARKUP SUBCONTRACTORS:SUBTOTAL I.ABOR:29%MARKUP LABOR:SUBTOTAL EOUIPMENT:21YoMARKUP EQUIPMENT:SUBTOTAL MATERIAL:MARKUP MATERIAL:210,/"TOTAL THIS REPORT:OWNER / CONTRACTOR REPRESENTATIVEDATE P O. Box 68697Seatlle, WA 98168-0697Office: (253)872_7173Fax; (253) 395..1209DAILY FORCE ACCOUNT / EXTRA WORK REPORTCONTMCT NAME, NOOWNER / CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:SUBTOTAL LABOR:SUBTOTALEQUIPMENTSUBTOTAL MATERIAL:REPRESENIATIVE$SUBTOTALMARKUP[-SUBTOTAL LABOLABOR:% MARKUPPMENT:EQUALUBTOTSENTUIPMEQUPMARKTERIAL:MAALTOTBUTERIAL:% MARKUP MATHISALTOTDEDEXTENAMOUNTS$UNITCOSTQTYTERIALRSELSROTHERS INC.EXTENDEDAIT4OUNTSo$$$GI$RAHOURLYLOADEDREGonREGotTofio/TREGolTlassificationName, CLABOR.I tndn,-w\(LJ CJ.FUnt*+ ouvo J(i'n^Il Llc-PToEXTENDEDAMOUNTSs$s$$$HOURLYRATEHOURSSTDBYSTDBYOPERSTDBYOPERBYOPERSTDBYSTDBYOPERPERSTDEYOPERBYOWN orRENTAL?Shi/-S l-,.+("a*lre,-.1\Fr-.Kmuo</ll- f LtG,€-^EQUIPNo.j-"Lo$$$e$ccBTOTAL SUSUOWNER /BROS.REPRESENTATIVEDAz/ SheetGFORCE ACCOUNT WORKED DAILY REPORT OF o lla Project Name:LID 363 224th St Phase 2 P rime Contractor: Project No: 14-3010 Work by Subcontractor? Description of Work:Haul blackberries out to Item No Sub-Contractor: Date. 61412 OVERTIMEHT TIME DOLLAR AMOUNTOT RaieHrsRateHrsCODEOCCUPATIONNAME $1A7.7s65.51Laborer 587.92$1o $100 B $85.99 73.49LaborerW 642.56$180.328ForemanF 375.83LABOR OVERHEAD & PROFIT @ zgok $ SUBTOTAL. LABOR: LABOR TOTAL STANDBYOPERATED DOLLAR AMOUNTHrsHourly Ratel..lr$EQUIPMENT OR ATTACHMENTS Equipment # F1 50.PU2-2'lo Mack Trailer27-215 $ $ 12.79 21"92 4.60$ 26.52 hI EOUIPMENT SUETOTAL. EQU IPIIENT $ TOTAL $ EOUIPMENT OVERHEAD & PROFIT @ 21% DOLLAR AMOUNTUnitsUnit PriceQuantity 98451#lnvoicetractor 23'.1 676800lnvoice325GJD MATERIALS / SERVICES Marooka track truck 744.65D$ 744.65day1 363.29o$ 363.29day1 $ $ 1.107 .94 232.67 SUBTOTAL oVERHEAD&PROFIT@21% TOTAL Verification of Hours Worked: Jaton Dale 121912021 Owne/5 12% MARKUP (for Prime when subcontract work) 38.94 SHEET TOTAL:3 TOTAL: Pay Estimate Entered: Date: By: 1945SCARSELLA8R01Ht8S lNC.DAILY FORCE ACCOUNT / EXTRA WORK REPORT,"-)L.C)2S. 224th St ProiectCity of Kent6t4t2021Remove and stack blackberry at Hytek Site.P.O. Box 68697Seattle, WA 98168-0697Omce: (2ss) 872-7173Fax: (253) 395-1209CONTRACT NAME, NO.:OWNER I CONTRACTOR:DATE:Bid ltem#:DESCRIPTION OF WORK:Paid on PE#EXTENDEDAMOUNTS$ 642,56$s 65.50$$ 642.56$$$!$$Ds 1.350,62LOADEDHOURLY RATE$80.32$65-50$80.32HOURS8.C1.0aLABOR - Name, ClassificationREGotTREGo/TREGo/TREGo/TREGo/TREGo/TAsu FuimaonoSiaosi PeleMatt Lovo JrEXTENDEDAMOUNTS$21.92$s$$$oe$D$$521.92HOURLYRATE$21.92$0.00$0.00$0.00$0.00s0.00HOURS1.0OPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN orRENTAL?EQUIPMENTFord Flatbed with Fuel TankEOUIPNO.3-082SUBTOTAL LABORi$$$$a$$0.00SUBCONTRACTORSAL SUBCONTRACTORS:SUBTOTAL EQUIPMENTEXTENDEDAMOUNTSo$c$$$UNtTCOSTQTYMATERIALSUATOTALSCARSELLA BROS.. INC. REPRESENTATIVEDATE$0.00$$ 1,3s0.62$391.68$21.92$4.60t$$1,768.82SUBTOTAL SUBCONTRACTORS:12O/" MARKUP SUBCONTRACTORS:SUBTOTAL LABOR:29o/oMARKUP LABOR:SUBTOTAL EQUIPMENT:21o/oMARKUP EQUIPMENT:SUBTOTAL MATERIAL:MARKUP MATERIAL:2'la/oTOTAL THIS REPORT:OWNER / CONTRACTOR REPRESENTATIVEDATE aR0THt&$ tNc.RSELDAILY FORCE ACCOUNT / EXTR,A WORK REPORTP.C Box 68697Seattle, WA 98168-0697Offlcer (253)872-7173Fax: i253) 3S5-120SCONTRACT NAME, NO.:OWNER/ CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:SUBTOTAL LABOR:SUBTOTAL SUBCONTMCTORS:i5l.^.KL*,.r* S<"rrt SLx,Kei\- |- 9o6*.t),*SUBTOTAL EQUIPMENTEXTENDEDAMOUNTS$$$a$UNITCOSTQTY.MATERIALSUBTOTAL MATERIAL:INC. REPRESENTATIVEEXTENDEDAMOUNTS$$$$$$$$o$$$$$$$$$$$$LOADEDHOIJRLY RATEHOURSIoLABOR - Name, GlassificationREGo/TREGoiTREGo/TREGofiREGo/TREGo/TREGo/TREGo/TREGo/TREGolTA5u-et", fi-r-",rnrrnfrr*^n o€r-Fui(: o5".\<./L"+r(fhz".l{ Lrc tREXTENDEDAMOUNTS$$o$o.p$o{$$$b$$$$cv$$$$$HOURLYRATEHOURSfrIOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN orRENTAL?("nk(^lEQUIPMENT5(;,.S l--tr cu,\'r'..ul- f^(.r, kan PAOF-frt-"K b*i\ G,nC-!rf-..{r-{r&-Fo**lt\Hn FLs(EOUIP.NO.J-BLb$$$o$qSUBCONTRACTORSa$$$$$$b$SUBTOTAL SUBCONTRACTORS:% MARKUP SUBCONTRACTORS:SUBTOTAL LABOR:% MARKUP LABOR:SUBTOTAL EQUIPMENT:% MARKUP EQUIPMENT:SUBTOTAL MATERIAL:% MARKUP MATERIAL:TOTAL THIS REPORT:OWNER / CONTRACTOR REPRESENTATIVEDATE FA Sheet/A\.'rrl i<ENTFORCE ACCOUNT WORKED DAILY REPORT OF th St Phase 2 Prime C ent Scarsella Project Name: LID 363 Project No: 14-3010 Date:61512021 Work by Subcontractor?: Sub-C Description of Work: Mob out Item No.: OVERTIMEME DOLLAR AMOUNTHrsoT RateHrsOCCUPATIONCODENAME 274.183.4465.51Laborer s100.5580.32Foreman 10060.69Labore(B $ Robert 59.96 ron W $100.5580, F 274.10 353.59 79.49 LABORTOTAL $ TABOR oVERHEAD & PROFIT @ 29% SUBTOTAL - LABOR: STANDBYOPERATED DOLLAR AMOUNTRateEquipment DescrlPtion EQUIPMENT OR ATTACHMENTS Equipment #b12.79F1 50-PU2-xa 250.7871.653.5Mack Trailer27-215 $21Flatbed3-082 $16JDTractorw/ Mower13-12 $SUBTOTAL EQUIPMENT EOUIPMENT TOTAL 250.78 303.44 52.66 EOUIPMENT OVERHEAO & PROFIT @ 21% DOLLAR AMOUNTLJnit PriceUnitsQuantitY MA TERIALS / SERVICES $ $ SUBTOTAL oVERHEAD&PROFIT@21% TOTAL $ u $ of Hours Worked: Jwon oate 1A912021 Repr€gonlaliva 12% MARKUP (for Prlme when subcontract work) 657.03 657.03 $ SHEET TOTAL: $ TOTALT Pay Estimate Entered; Date: By: 194bESCARSELLA8BU rHEftS tNC.2!t-?L.,tJ{DAILY FORCE AGCOUNT / EXTRA WORK REPORTP.O. Box 68697Seattle, WA 98168-0697Office: (253) 872-7173Fax: (253) 395-1209CONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:8id ltem#:DESCRIPTION OF WORK:Paid on PE#outs. 224th stof KentEXTENDEDAMOUNTS$ 65.50$ 208.60$ccU$a$$$$ 274.10LOADEDHOURLY RATE$65.50$63.44HOURS1.02.5LABOR - Name, ClassificationREGo/TREGo/TREGotrREGo/TREGorTREGo/TSiaosi PeleEXTENDEDAMOUNTS$250.7E$$s$$$$Ds$!$ 250.78HOURLYRATE$71.6s$0.00$0.00$0.00$0.00$0.00HOURSOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN orRENTAL?EQUIPMENTLowboy trailerEQUIPNO.8-036AL$$s$$$$0.00SUBCONTRACTORSSUBTOTAL SUBCONTRACTORS:SCARSELLA BROS". INC. REPRESENTATIVEDATEAL EQUIPMENT:SUBTOTAL MATERIALEXTENDEDAMOUNTS$$$$c5UNITcosTQTYMATERIAL$0.00$$274.10s79.49s 250.7E$f,zst$$657.03SUBTOTAL SUBCONTMCTORS:12O/O MARKUP SUECONTRAGTORS:SUBTOTAL LABOR:29%MARKUP TABOR:SUBTOTAL EQUIPMENT:21o/oMARKUP EOUIPMENT:SUBTOTAL MATERIAL:MARKUP MATERIAL:21o/oTOTAL THIS REPORT:OWNER I CONTRACTOR REPRESENTATIVEDATE FA Sheet No 205./>\-./ KENTFORCE ACCOUNT WORKED DAILY REPORT OF debris to ScarsellaPrime haulout LtD 363 224th St Phase 2 Project No: 14-3010 Date:6F12021 Work by Subcontraclor?: Su b-Contractor: Project Name Item No. Description of Work OVERTIMEGHT T DOLLAR AMOUNTOT RateHrsRateHrsCODEOCCUPATIONNAME $83.4465.5Laborer $18att L 293.96100.5573.494Truck OriverAndrew 404;20$7S.3573.495DriverH $ Drivervan C U10080.32uF 744.92SUBTOTAL- LABOR: $ 506,03 LABORTOTAL $ LABOR OVERHEAD & PROFIT @ 29% STANDBY DOLLAR AMOUNTHrs 4 EQUIPMENT OR ATTACHMENTS OPERATED DescriptionEquipment # Trailer8-036 Trailer 7'1.65 Rate 71 s $ 286.60 386.49 286.60 5.5 5.5 386.49$70,27 JD Tractor w/ Mower Solo Mack Truck Solo Mack Truck $ 13-12 o s SUBTOTAL. EOU IPMENT EQUIPMENT TOTAL 1 ,346.18 282.70 EOUIPMENT OVERHEAD & PROFIT @ 21% DOLLAR AMOUNTUnit PriceLJnitsQuantitY MATE RIALS / SERVICES 1$$11 JD 135G 67890023'.\lnvoice fRental $CY132 I lnvoics 1i48621 $ $ $ 1 ,195.37 6,887.60 oVERHEAD&PROFIT@21% TOTAL SUBTOTAL $ of Hours Worked: tDate Jwon oale 121912021 12% MARKUP (forPrimewhen subcontract work) 767.43SHEET TOTAL:1 TOTAL: $10 767.43 Pay Estimate Entered: Date: By: \1945SCARSELLA8l't0THtRS INC642.56$293"96$$404.20$404.20$$e$U$744.91IRATEHOURLY6.04.oofto/TREGonMatt Lovo Jr.HallHlvan Crumpton$$$$cosrQTYot KentsrMOBAMOUNTS286.60366.49386.49$286.60$YRATEHOHOURS4.05.54.OPEROPEROPEROWN orR€NTAL?trailerSoto Mack Dump$olo Mack DumptrailerNO.EQUIP.DAILY FORCE ACCOUNT / EXTRA WORK REPORTCONTRACT NAME, NO.:OWNER / CONTRACTOR.DATE:P"O. Box 68€97Seatfle, WA 98.168_0697Office: (2S3) A72_7173Fax; (253) 395-1209Bid ttem#.DESCRIPTION OF WORK:paid on pE#SUMABROS., INC.TIVEOWNER IDATE-* s0.00$1,74p,.9'li$ .sfr-s$sMARKUPLABOR:t-ABOR:MARKUPMARKUPTERIAL:MAMARKUPTOTALREPORT:THISDATE UAILY FORCE AGCOUNT / EXTRA WORK REPORTCONTMCT NAME, NO.:OWNER / CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:P.O. Box 6A697Seaftie, WA 9816S-0692Otrice: (253) 822-7173Fax; (253) 3SS_120SALLABOR$RSONTRACTOUBCSRKUPMAOJLABOR:LABOR:KUPMARPMENT:EQU% MARKUPMAIAL:RTEMAPMARKUYoAL THISTOTNDEDEXTEAMOUNTS$UNITcosTQTYMATERIAL$$$YLOADEDotTo/TREGo/TREGonREGGo/To/TGowlLAMOUNTS$$HOURLYRATEHOURSRSTDBYSTDBYOPERTDBYOFEROPERSTDBYSTDBYOWN orRENTAL?\\l\No.EQUIPu-35t-7-/8fi0lHt8S tilc.BSTLeEOUIMATERIAL:OWNER /TiVE2-1 HBuckley ltecycle Center lncoqporated Enumclaw, WA 98022 253-939-7422 qnai I - info@brcrecyclers.com Phone 253.939.7422 lnvoice RECElVEI} ? 8 2021 BROS, iNC Date lnvoice # 6/9t202t 4862t ,//? Toto.r' 11Of,.wt'/ FaEc€ Accar,rr -rs \0 Bill To Scarcella Brothers, Inc. PO Box 68697 Seaule, WA 98168-0697 SCARS Delivery Ticket No Terms 51957 51956 Due on rcceipt Description Qty Rate AmountDisposai cfsoti/dirt City of Kent t32 35.00 4,624.00 Please Remit fo above address Thank you for your business Subtotal $4,620.00 Sales Tax (10.0%l $0.00 Total $4,620.00 Payments/Credits $0.00 Balance Due s4,620.00 No 53"S5?No $1S56l=D IE A*-::-15x"S30lA- !i<A .- . t-.ut( wA e8321Frs&ryffi IHONE:(253)939-7422I}EtIIfERY,are,PO. Brt1zuozucKEYWA98321, PHONE (253) 9397422OELIVERYV4snrortr.rwllIara\LAt?.T?*t&lLOAOstzEt7Ttttuiro DEo,"7DATE:SOLOTIATTRIIL0Er.rYERf0 m_TFIUCK NO.LA7D;11D', f *o"{fDi,rfIiITERIAI-LOABEO FB(lflD} s' nD:' {TilAIENhTIIAULEOTIHELOAOEDREASON FOR DOWNTIME:L|MITATION OF LIABILITY: BRC'S liability to customer, however caused, whether in contract, tort or otherwise, includingwithout limitation. anv indemnificalion. tiabilities or damage lor property or personal loss, shall in no event exced the totalcompensation paid 8RC hereunder. This limitation of liability shall suryiw the completion or termination of this cont@ct.-56RENTAL CO.L(lAOl0tt.13qsK*r'o't'-/IYr"lriv 6{.-Tqtr,STIIIDBYFdL>LAT&Tt0A0SEEIAlel;\TltfUIILOADED-al,orr, 6SOLOLSareo1./ n'" rfiIATERIALlEllVER[0 T0*i:T"OffiDitln;/D", tfD', rff'AlEBlAtloaoao FR0tillTEnilt[/tuLE0ilttL0A0t0tlLLiMITATION OF LIABILITY: BBC'S liability to customer, however caused, whelher in contract, tort or oth€Mise,.including*ltnoi,i ii.iiaiion. inv indemnitication. liabilities or damag€ lor property or peFonal loss, shall in oo event exceed the totalcompensation paid BhC hereunder. This limitation of liabiliVshall survive the completion ot termimtion of this @ntractnolareaasDeliveryticketall workr-ril\untilPAYMENT TERMS: Fullunless otheruiseCustom€r toREASON FOR D-OWNTIME:^fLOAOi0*-43RehrrAL co. /6Driver XAccepted By:lime StartTime EndStandbyStandbyTime StartTime EndStandbyDriver XAccepted By:FORM - 1002IOTAL H(I'RSFORM - 1002TOIAL TIIX'RSStandby DAILY FORCE ACCOUNT / EXTRA WORK REPORTP.O.Box68697Seattle, WA 98168-0697Office: (253) 872-7173Fax: (253) 395-1209CONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:Bid ltem#:DESCRIPTION OF WORK:Paid on PE#90051of Kent224th stMOB outLenni BailesPeleLABOR.Classificationo/TREGoiTREGo/TREGoirREGo/TREGoiTREG'1.52q1.0HOURS105.48$83.44$bu bvLOADEDHOURLY RATE$ --344d$$$$$$$$60.699-036$$158.22EXTENDEDAMOUNTSEQUIP.NO.Lowboy TrailerEQUIPMENTOWN orRENTAL?STDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPER1.5HOURS$0.00$0.00$0.00$0.00$0.00$80.49HOURLYRATE$120.74b$$o$$$aba$$120.74EXTENDEDAMOUNTSSUBTOTAL LABOR:$o.ooal$l$l$lE$SUBCONTRACTORSSUBTOTAL SUBCONTRACTORSSCARSELLA BROS., INC. REPRESENTATIVEDATE(z+.SUBTOTAL EQUIPMENT:SUBTOTAL MATERIAL:MATERIALIQTYffilzssfUNITcosr$ 4,620.00$s$$-$ '<r:eaeeeEXTENDEDAMOUNTSSUBTOTAL MATERIAL:MARKUP EQUIPMENT:21%SUBTOTAL EQUIPMENT:MARKUP IABOR:290kSUBTOTAL LABOR:1O"/o MARKUP SUBCONTMCTORS:SUBTOTAL SUBCONTRACTORS:TOTAL THIS REPORT:210kMARKUP MATERIAL:$6,r{o.14s s7029$ 4,620.0025.35$$ 120.7499.78$$3M.O7$$0.00OWNER i CONTRACTOR REPRESENTATIVEDATE FA No.:206{ADAILY REPORT OF FORCE ACCOUNT WORKED Project Name LtD 363 St Phase 2 Prime Contractor: Scarsella Project No: 14-3010 Sub-Contractor: Work by Description of Work out Item No.:Date: 61912A21 OVERTIME DOLLAR AMOUNTOT RateHrsRateHrsOCCUPATIONCODENAME 269.29$83.44 1LaborerP $180.32ForemanMatt 158.22105.4I73.49Truck DriverLenni B $79.3573.49DriverH $59.96 Driverlvan 100.55 F SUBTOTAL - LABOR: $427.51 551.49 123.98 LABORTOTAL iLABOR OVERHEAD & PROFIT @ 29% STANDBYOPERATED DOLLAR AMOUNTRateEQUIPMENT OR ATTACHMENTS DescrlptionEquipmenl #120.74$80.491Trailer8-036 71.65 8-035 $70.27Solo Mack Truck $ Solo Mack Truck 't6 JD Tractor d Mower13-12 $ $ 74SUBTOTAL - EQU IPMENT EOUIPMEI.IT TOTAL 146.10 25.36EQUIPMENT OVERHEAD & PROFIT @ 210lO DOLLAR AMOUNTL,nlt PriceUnitsQuantitY MATERIALS / SERVICES 1$11 JD 135G 78900Rentallnvoice # 23 $ $ SUBTOTAL ovERHEAD&PROFlr@21% TOTAL $ $ $ .23 1,297.40 225.17 of Hours Worked: Jason 12t9t2021Dete OwnefE 12% MARKUP (for Pdme when subcontract work) SHEET TOTAL: $ I 994.99TOTAL: $ Pay Estimate Entered: Date: By: €45ESCARSELLAEROI HIBS iNC,-u/tuDAILY FORCE ACCOUNT / EXTRA WORK REPORTP.O. Box 68697Seattle, WA 98'168-0697Fax: (253) 395-1209CONTRACT NAME, NO.:OWNER I CONTRACTOR:DATE:Bid ltem#:DESCRIPTION OF WORK:Paid on PE#S. 224th St ProjectCity of Kent6t9t2021DisDosalSUBTOTAL EQUIPMENT:SUBTOTAL LABOR:$$$$$o.ooSUBCONTRACTORSSUBTOTAL SUBCONTRACTORSTSCARSELLA BROS-, INC, REPRESENTATIVEDATEEXTENDEDAMOUNTS$$$$$$$s$$s$LOADEDHOURLY RATEHOURSLABOR - Name, ClassificationREGorTREGonREGo/TREGotlREGo/TREGoiTEXTENDEDAMOUNTS$$$s$$$$s$DU$HOURLYRATEHOURSoWN orRENTAL?EQUIPMENTEQUIPNO.EXTENDEDAIIllOUNTS$ 4,620.00$s$$ 4620.00UNITcosT$ 4,620.00QTY1MATERIALBuckley Recyclinq lnv 48621$0.00G$$$$$ 4,620.00$ 970.20$s,590.20SUBTOTAL SUBCONTMCTORSI12o/o MARKUP SUBCONTRACTORS:SUBTOTAL IABOR:29%MARKUP LABOR:SUBTOTAL EQUIPMENT:21VoMARKUP EQUIPMENT:SUBTOTAL MATERIAL:MARKUP MATERIAL:21o/oTOTAL THIS REPORT:OWNER / CONTMCTOR REPRESENTATIVEDATE EHOTHERS INC.ARSELDAILY FORCE ACCOUNT / EXTRA WORK REPORTCONTMCT NAME, NO.:OWNER / CONTMCTOR:DATE:P.O. Box 68697Seattle, WA 98168-0697Office: (253) 872-7173Fax; (253) 395-1209COST CODESCRIPTION OF WORK:SUBTOTAL LABOR:SUBTOTAL SUBCONTRACTORS1-14/9tSUBTOTAL EQUIPMENT:EXTENDEDAMOUNTSb$$$$UNITcosrQTY.MATERIALSUBTOTAL MATERIAL:INC. REPRESENTATIVEEXTENDEDAMOUNTS$$$$$$$$$$$$$$$$o$$$$LOADEDHOURLY RATEHOURSLABOR - Name, ClassificationREGo/TDENo/TREGo/TREGo/TREGo/TREGO/TREGOITo/TREGonREGorTIlt$,r,kti.q /Tr^,t(l+ -EXTENDEDAMOUNTS$c$$$$$$$$$$$$$$$$$$$HOURLYRATEHOURSOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOWN orRENTAL?EQUIPMENT/...A^i ]<t;1,.rQ,'rr^ R.N\e-\e*,i\Yrl.^\ V (A(e-EQUIPNO.g.Yn$$$$$BCONTRACTORS$$$$$$SUBTOTAL SUBCONTRACTORS:% MARKUP SUBCONTRACTORS:SUBTOTAL LABOR:% MARKUP LABOR:SUBTOTAL EOUIPMENT% MARKUP EQUIPMENT:SUBTOTAL MATERIAL:% MARKUP MATERIAL:TOTAL THIS REPORT::R/(REPRESENTATIVE H[HllilERY Pte MmilHy, lnc., PO Box 1052/, Eug€re, OR 974,10 RUN DATE: O OPEN DATE: 0 SHIP DATE: O RENTAL INVOICE INVOICE NO:231678900 BILLING DATE: 6/30/2LBRANCH.. 23PAGE: 1 v0A 98032 6/ 3A / 202r 6/07 /202L 6/A'7 /202r CONTACT: PO NUMBER: SALESMAN:2301- DAVE Or CONNOR ** sHrP TO ** KENT YARD 19808 68TH AVE S ** cusToMER ** 2O2L63 SCARSELLA BROS INC PO BoX 5869'7 SEATTLE WA 98168 KENT SHIP VrA: w/C : ORDER #START END QTY RATE DISC EXTENDED : .rD l35G HF50005/01/21 06/09/21 l-.00 1,955.00 RENTAL INCLUDES 36'' DIG BUCKET PM127358 RENT BILLED ]S TOR 3 DAYS RffifiNlVEC JuL - $ ?'0?1 SCARSEL1''A' BROS, INC' REM]T TO: PAPT MACHINERY PO BOX 35144 #50't1 SEATTLE, WA 98L24-5T44 1, 955 . o0 f .l.-f 3 oro,ool qoas.@tl0E TOTAL AMOUNT : 1, 955. 00 STATE/LOCAL TAX: L97.46 TELEPHONE : 206'575-0140 INVOICE TOTAL: 2,I52.46 *** TERMS: PAYMENT DUE 0"1/LA/202I *** Payment should be by cash, check or ACH/wire transfer This renhl is sublect lo Pap6's Rental Tems and Condlllons elfectlve on lhe dale hefiot whlch ars lncoryo|,/ted in lull by lhls ntarence, The Renhl Tems and Condilions are avallabte al 1tr/ww;Ittgg&fd!lb@1, and wlll also be sont by matl or &,/nell lo lhe purchasu upon 'gqrosl' C?r* iIIGIIIITTRY PapeMrhinsy, |flc., PO Box 10527, Eu$m, oR 97440 RUN DATE: OPEN DATE: SHIP DATE: RENTAL INVOICE INVOICE NO:23167680O BILLING DATE: 6/20/2IBRANCH: 23PAGE: 1 06/ 05/ a5/ 20 / 2027 20 / 202L 20 /202L ** cusToMER ** ** SHIP TO ** 2O2L63 SCARSELI,A BROS INC KENT YARD ]-9BOB 6BTH AVE S PO BOX 68691SEATTLE WA 98158 KENT WA 98032 SHTP VIAT CUSTOMER TRUCK CONF]RM #: 594 =:*===-=:F=====E=AS-==AE===-sg=s::$=:=ff=:::==:=:::::::::::===:==:==::::=::::=::= ORDER # START END QTY RATE D]SC EXTENDED : :=:==:-=:5:A:==:===== ====***Hg=a=--=€dGE=:::::==::::::::::=====:=:==:::: 1.00 3, 060 - 00 3,060.00 JD 325G 900 .00 CONTACT: PO NUMBER: SALESMANz23OL DAVE Or CONNOR 1.00 900.00 KJ36771-6 05 / 20 / 21 06 / 09 / 2rSerial #- 1T0325GJ8KJ3611]-6 -00325 CTL Loooor43 05/20/2L 06/oe/2r Serial #- 1T0RR72XCLO000143 -00 MISC RAKE RENT BILLED IS FOR 3 WEEKS. JD RR72 'rfi 0a"ryt frsvt*tt REMIT TO: PAP6 MACHINERY PO BOX 35144 #5011 SEATTLE, WA 98L24_5L44 TELEPHONE : 206-57 5-01- 4 0 \'.IIL-, RECEIVED JUN ? \ 2l,2I SCARSELLA BROS, INC. t. O l*fS O tu.Oo I q Oos'odtpe TOTAL AMOUNT: 3,960.00 STATE/LOCAL TAX:399.96 INVOTCE TOTALz 4,359.96 *** TERMS: PAYMENT DUE 06/30/202L *** Payment should be by cash, check or ACHlwie transler This renlal Is sublect lo Pap6's Renlal Tems and Condttlons elleclive on lhe dale herwl, whlch arc incorporaled ln tull hy lhls refennco. The Renlal Tems end Condttlons are avaitebts at www.oaoe.eomlterms , and wlll also be sent by mall or *mall to lhe purchas* upon request,'[r 164 S. Michigan Street Seattle, WA 98108-3242 Phone (206) 264-8551 Fax (206) 264-6269 \'L lnvoice Date lnvoice # 6t1512021 1 9845 ECEI}CED Ship To Scarsella Bros., lnc. r BillTo Scarsella Bros., lnc' P.O. Box 68697 Seattle, WA 98168 SCAfi $El"'L.A l:jl-;O:r' tt'r Sales RepShip ViaOrdered BYP.O. No.Teflns TomCustomerJerryBobby's Mowing JobNet 30 AmountRateDescriptionQuanti$Item 2.660.007 41.657 0.007 1..) q l"ll\r r i.. r::,*,\ "' j,.l 0.00 665,00 5.95 o One Hour labor for Cleaning equipment ($'125'00/Hour) at No Charge Gallons Diesel Fuel 935200057Serial#T8PantherrinothCD01PRental: 06t0412to06l01t2PeriodRental ofRate .0 day$66satrentalDailytheDayst4) 4 1 7 co101 Clean NC Fuel $2,701.65Subtotal Sales Tax (10.25%l $276s2 $2,978.57Subtotal Payments/Credits $0.00 Balance Due $2,978.57 11 u)-dft TIACHIIUTRY Pap6 Mehlnery lnc., PO Bd |0527, Exgem, OR 97440 RUN DATE: OPEN DATE: SHIP DATE: RENTAL INVOICE INVOICE NO:231675 BILLING DATE: 6/06 BRANCH: PAGE: O UNASS]GNED *r( SHIP TO ** SCARSELLA BROS INC PO BOX 68697 WA 98168 700/2t 23 t- 06/ 05/0s/ 06/202r 0'1 /202L0-t/202r CONTACT: PO NUMBER: SALESMAN: : ORDER # START END QTY RATE DISC EXTENDED : PM83103 05Seria1 #* PMB31 250 "12" BKT 1. 00 370.00 370.00 ** cusToMER ** 202L63 SCARSELLA BROS ]NC PO BOX 68697 SEATTLE WA 98168 REMIT TO: PAPf MACHINERY PO BOX 351,44 #5077 SEATTLE, WA 98L24_5I44 TELEPHONE : 206*515-0140 SEATTLE SHIP VIA: WC KENT 06 PM /01 /2r 03-00 /03/2r 250 . T:1, ",n n; i -utf ll -' $t ;l';:'S'$tA BRCIS' INC' t. ot*lsolfr'oa I la JLlil t {i ?*?l TOTAL AMOUNT: 9oas.oo 370.00 407.31 STATE/LOCAL TAX:31 .37 ]NVOICE TOTAL *** TERMS: PAYMENT DUE 06/16/2021 *** Payment should be by cash, check or ACH/tvire transfer lhis rcnta! Is sublect lo pap6's Renla! Terms and Condittons ellectlve on the date hereol, whlch are lncorporated ln lull by this relerenca lhe Rental Tems and Conditions are avaitable al Id&,uI'$AINBM!1, and wll! alto bs sent by mall or *mall to the purchaser upon nquasL LQ l{\- B From: Sent: To: Cc: Subject: nt, Jason Heubach, Meara Thursday, May 13, 2021 9:45 AM Bryant, Jason Maloney, Carla Next work for Scarsella on Hytek site Hi Jason, Could you check in with Scarsella on a few things regarding their work at Hytek and let me know their plans? 1. Alex Klinger just shot some drone images of the site, and they show a good chunk of land in the southern section that hasn't been mowed yet but needs to be (shown in red on map). The entrance to this area is narrow and must have played an optical illusion on me because I didn't realize there was this much blackberry behind there that needed to get mowed, and I never indicated to Scarsella to mow there. could you ask Scarsella to mow this area and remove the cut canes and roots from there the next time they are on site to remove blackberry? I can also go to the site to point this area out' 1 2. Once the grasses on the southern area have regrown to at least 8" tall, the grasses need to be sprayed with an herbicide and surfactant approved for aquatic use (scarsella already knows this). But we have not yet received documentation showing that they have licensed staff that can do that. can you ask scarsella to send us the license(s) of the staff that will be spraying and also document which herbicide and surfactant they will be using? (I'd expect them to use Rodeo and Activator 90 but they could recommend other brands)' Thank you, Meara Heubach, MES Environmental Specialist Kent Public Works Engineering 1253-579-5764 2 Bryant, Jason From: Sent: To: Subject: Heubach, Meara Thursday, May 13, 2021 6:00 PM Bryant, Jason Another task for Scarsella at Hytek Jason, To keep our options open for how we deal with the weeds at the north Hytek site, we would like Scarsella to spray the reed canarygrass at the north Hytek site. The spraying should be done in May, and, like the spraying for the south, we'd need proof of license to apply herbicide in aquatic areas. The map below shows the approximate location of the reed canarygrass (it occupies about 4.5 acres-most of the site). I can meet Scarsella on site to go over the bounds of work and expectations. Could you share this additional work request with them and let me know when they could do it? Thanks, Meara Heubach, MES Fnvlronmental Specialist Kent Public Works Engineering 1253-579-5764 1 nt, JasonBrya From: Sent: To: Subject: Heubach, Meara Thursday, May 20, 2021 6:16 PM Bryant, Jason RE: Mechanical methods for removing blackberry rootballs Hi Jason, scarsella can start with blackberry removal immediately, I was out this morning and couldn't answer my phone. should I still give scarsella a ring first thing Friday morning to confirm and see if they have other questions? I'll out on flex tomorrow but will be working for about an hour in the morning. Meara Heubach, MES Environmental Specialist Kent Public Works Engineering 1253-579-5764 From: Bryant, Jason <J Bryant@kentwa.gov> Sent: Thursday, MaY 20,2O2'J" 9:14 AM To: Heubach, Meara <M Heubach@kentwa.gov> subject: RE: Mechanical methods for removing blackberry rootballs Meara, I just spoke with BobbY Scarsell He said he left You a voice mail. Thank you, Jason Bryant' Capital Proiects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5541 | Cell 253-261-5563 JBryant@ KentWA.qov crTY oF KENT, WASHTNGTON KentWA.gov Facebook !"\';ii!-t:r YouTube ;$Lrasf; e(}NsI$FiR Ttlf nf{vf.qsffMf l*Y B*F1}RS pRINTINS Y[{Csi F-MAI{ From: Heubach, Meara <MHeubach@kentwa'gov> Sent: Tuesday, MaY t8,TOZL t2:I7 PM To: Bryant, Jason <J Brvant@kentwa.gov> subject: RE: Mechanical methods for removing blackberry rootballs a and he mentioned he wanted to start the blackberry removal Can you let us know if theY can begin? 1 Jason, Sounds good, As long as Scarsella doesn't disturb the adjacent vegetation or remove much soil, they can go ahead with mechanical removal. can you let me know when they plan on doing the blackberry root removal at the S Hytek site? Thanks, Meara Heubach, MES Environmental Specialist Kent Public Works Engineering 1253-579-5764 From: Bryant, Jason <JBrvant@kentwa'gov> Sent: MondaY, MaY 17 ,2O2t 1:46 PM To: Heubach, Meara <M Heubach@kentwa'gov> Cc: Maloney, Carla <CMalonev@kentwa'gov> subject: RE: Mechanical methods for removing blackberry rootballs Meara, They will probably just use a backhoe or mini excavator if they can get it in there' Thank you, Jason Bryant' Capital Proiects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5541 I Cell 253-261-5663 lBryant@KentWA'gov CITY OF KENT, WASHINGTON KentwA,gov Facebook i'!'*till:r::r YouTube rLEASf COFI$I$Eft Yfif rs{VxROl{MtNY Sr$t}&t PR!NTII'*{S TF{fS F'MJIXL From: Heubach, Meara <MHeubach@kentwa'gov> Sent: MondaY, MaY t7,\AZL 1:05 PM To: Brya nt, Jason <J Brvant@kentwa.gov> Cc: Maloney, Carla <CMaloney@kentwa.sov> subject: Mechanical methods for removing blackberry rootballs Hi Jason, when I met with Hytek on site the other week to go over which areas needed to be mowed, scarsella wasn't sure about which mechanical method or equipment to use to uproot the blackberries on the s site. They mentioned a rototiller, but I think we want to pull the material 2 out instead of chop it up, I've asked our consultant for recommendations, but do you have any recommendations for which equipment scarsella should use to grub out the blackberry on site? Thanks, Meara Heubach, t'lES Environmental Specialist Kent Public Works Engineering 1253-579-5764 3