Department:
PW Engineering
Originator:
Stephanie Anderson
Date Required:
9129t21
Date Sent:
9129121
Date of Council APProval
1A120120
Authorized to Sign:
E Director or Designee E Mayor
Grant? trYes E No
Type:
Budget Account Number:
w20090.641 10.330
Category:Vendor Name:
Colvico, lnc.
Sub-Category:
Change Order #1
Vendor Number:
35124
project r.,rame: clark springs Generator and Electrical Upgrades
Project Details:Demolition and reconstruction of the' design of the slab being flat and as a
curb & gutter and the generator slab due to the
n outsidL work area poses a safety hazard'
Basis for Selection of Contractor: $i6l
Termination Date: 80 Worfing DaYs
Ag reement Amount: $22,O20.0O
Start Date: Mayor'S Signature
Local Business? EYes E No*
*lf meets requirements per KCC 3.20.100, ptease complete "Vendor Purchase-Local Exceptions" form on Cityspace'
Contract Number:
cAG202A-357
Notice required prior to disclosure?
EYes E No
C
.glP
IE
ELor|-c-tFc
IU
EooL
EI
adccvll2237l I 20 Visit Documents.KentwA.gov to obtain copies of all agreements
$/
KENT
WASHINGION
CHANGE ORDER NO. #L
NAME OF CONTRACTOR:
CONTRACT NAME & PROJECT NUMBER:
ORIGINAL CONTRACT DATE :
Colvico. Inc. ("Contractor")
Clark Springs Generator and Electrical Upgrades
Novemeber 5, 2020
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equiPment necessarY to :
Demolition and reconstruction of the curb & gutter and the generator
slab due to the design of the slab being flat and as an outside work area
poses a safetY hazard'
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum,
(inctuding applicable alternates and
WSST)
$t,009,421.02
Net Change by Previous Change Orders
(incl. applicable WSST)
$o.oo
Current Contract Amount
(incl. Previous Change Orders)
$t,009,421.02
Current Change Order $2o,ooo.o0
Applicable WSST Tax on this Change
Order
$2,020.00
Revised Contract Sum $1,031,441.02
CHANGE ORDER - 1 OF 3
Original Time for ComPletion
(insert date)
60 working days
Revised Time for ComPletion under
prior Change Orders
(insert date)
0
Days Required (+) for this Change Order 20 calendar days
Revised Time for ComPletion
(insert date)
80 working days
In accordance with Sections L-O4.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Ci1ange Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agreJs to waive any protest it may have regarding this Change Order and acknowledges and
aicepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connecte]d with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from sirict compliance witn the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have aPPlied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
Print Name: Chad Bieren, P'E.
CITY OF KENT:
(tiue)
a
Publi
DATE
Its Works Director
(signature)
CONTRACTOR:
,7af,to Araaoo
Its Vice President
By I i!*" orrg* ts"c ld2o2l t5:15 PDT)
DATE : September 24,2021
Print Name Jesse Dragoo
(signature)
(title)
CHANGE ORDER - 2 OF 3
ATTEST:
f
Kent City Clerk
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
[In thls field, you may enter the electrcnic filepath where the contract has been savedl
CHANGE ORDER - 3 OF 3
File No. 2OO.2
KENT
CHANGE ORDER WORKSHEET NO.' I
Construction Engineering Division - Public Works
clarKs 5pflngs Generator ano Electrical Project No: 19-3021Project:Upgrades
Project Engineert RH2/Joe Araucto Fed-Aid No: N/A
capital Projects phil Mcconnell contractor: colvico Inc.
tttanaoer:
Date: Various
I Pro osed Chan e
Demolition and reconstruction of the cu rb & gutter and generator slab
II. Reason and Bac round for Chan e
III. Method of Payment
NEW PAY ITEMS n ruotaPPlicable
hazard. Inconsistancies within the specifications on the sla
Workmanship on the contractors part. All were factors for the change. It was negotiated that the City
would contribute $20,000 to the removal and replacement of the concrete work performed to date'
n outside work area this would be a safety
b finish (smooth versus brushed).
portion of the concrete slab was designed to be flat. As a
Sch.
No Item Description Total Est.
Otv Unit Unit Price Total Estimated Cost of
Item
1
on an recon ng ecu
utter and slab oured to date 1 LS $20,000.00 $20,000.00
$
$
New Pay ltems Total: $20,OOO.OO
DELETE EXISTING PAY ITEM(S) per 1-O9.5 E ruotappricabre
Sch
No.Bid Item No.Item Description Qtv Unit Unit Price Cost of Item
$
Page L
Delete Existing PaY ltems Total: $
INCREASE/DECREASE TO EXISTING PAY ITEM(S) p Notappricabre
Sch
No.Bid Item No.Item DescriPtion Qtv Unit Unit Price cost of Item
$
Increase / Decrease to Existing Pay ltems Total:
*TOTAL ESTIMATED COST OF CHANGE ORDER:
IV. WORKING DAYS
$
000.oo
x Total of the Cost of ltem Columns
60Previous Total:2060Due This Ghange Order:Original Contract:
Explanation/Justification for Additional Working Days:
*TOTAL WORKING DAYS: eo .
* fni, CTingre-Order I Previous Total
Date:q L e0 LICapital Proiects Manager:
Construction Engi neeri ng
Supervisor:
Phil McConnell
ul ne
c Gonnor
'/6(
Date f /..
Date:fy'"/',Construction Manager:
Page 2
McConnell, Phil
From:
Sent:
To:
Cc:
Subject:
Peterson, Kelly
Tuesday, August 31,2021 6:16 PM
Connor, Eric
McConnell, Phil; Bieren, Chad
CO2 Concrete Rejection lnternal Approval
Eric-
I talked this over with Chad, please proceed'
Kelly
Kelfy Peterson, AICP, Deputy Director-Engineering
Public Works DePartment
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5547 - Cell 253'740-8066
Koeterson@KentWA.oov
CITY OF KENT, WASHINGTON
KentWA.qov Faeebook :#gi!"!q: YouTu be
PI.ffi'\SE COI$SYSER Til* f NVTR$NMTNT SEFON'H PR'INTTT{G Tf{NS N-MATL
From: Connor, Eric <EConnor@kentwa.gov>
Sent: Tuesday, August 3t,2O2I 3:51 PM
To: Peterson, Kelly <KPeterson@kentwa'gov>
Cc: McConnell, Phil <PMcConnell@kentwa'gov>
Subject: FW: CS Gen - Concrete Rejection
Good Afternoon KellY,
please take a look at phil,s description of the background and negotiations he has completed
regarding the concrete pad that was rejected on our clark springs project. Are you okay with
pr6ceediig with a change order in the negotiated amount of $20,000 as a shared cost for
removing and replacing this concrete work?
please let phil and/or me know if you have any questions or need any additional information'
Thank you,
Eric
Eric Connot, Construction Engineering Manager
Phone 253-856-5533 | Cell 253-797-0693
crTY oF KENT, WASHTNGTON
i}|.[AsEe(}N$iIsERTfi€frsl\'I${C}l{MHNYsbF(}l{Fp!{xl{TI.'*$TH3$'F-MAIL
From: McConnel l, Phil <PMcConnell @ kentwa.gov>
Sent: Tuesday, August 3L,202L 7:52 AM
To: Connor, Eric <EConnor@kentwa.gov>
1
Cc: Kuehne, Paul <PKuehne@kentwa'gov>
Subject: CS Gen - Concrete Rejection
Eric,
The generator slab has been rejected at clark Springs. Demolition h.9s been completed' There
were multiple reasons for the rejection. Ambiguity in tl.re contract with final finishes, back fall in
the concrete work, design issues: elevations not designated, outdoors concrete with no slope,
etc.
since there is fault on both the city's and contractor's sides, I requested a quote for the work'
originally it came in at +/- $55,00b, then the demo was removed and I was adjusted to +/-
$44,000.
I reached out to Jesse Dragoo with Colvico, on how they expected to split these costs. His
starting point was the total in the proposal would be the City's' I counter offered with $10,000
explaining the contract's bid item price forthis work is $108,000' This included all steel
structures and the concrete work. That the concrete work was a small portion of of the overall
bid item.
Jesse counter offered with the city picking up $20,000 of the concrete demolition and rebuild' I
believe this is a fair comPromise'
Phil McConnell, Capital Projects Manager
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5542 | Cell 253-261-5685
pmccon nell@ KentWA.qov
crTY OF KENT, WASHINGTON
KentWA.qov Facebook,H-!gi,i;gg.i- YouTu be
$}LMASfICONSIDII|RTI'!ffiilf'{i,TRq}NMNN*T'SfiF$RfrPITTNTlNGTI'!T$N'MATI"
2
McConnell, Phil
From:
Sent:
To:
Cc:
Subject:
Jesse Dragoo <jdragoo@colvicoinc.com>
Wednesday, SePtember 1,2021 12:51 PM
McConnell, Phil
Ethan Giles; Evan Tisler
Concrete Rejection - Colvico dollar accept
Phil,
That works for us, thanks
Jesse Dragoo
Vice President
Direct: (509)252-5817
Cell: (5 09) 342-1361.
@lll
P,O. Box 2682, SPokane, WA 99220
Office: (509) 536-1875 | Fax: (509) 534-3551
From: McConnell, Phil <PMcConnell @kentwa'gov>
Sent: Wednesday, September t,202'J' 12:51 PM
To: Jesse Dragoo <jdragoo@colvicoinc,com>
Cc: Ethan Giles <egiles@colvicoinc.com>; Evan Tisler <etisler@colvicoinc'com>
Subject: CS Gen - Concrete Rejection - Replacement
Jesse,
participation in these efforts.
Phil McConnell, Capital Projects Manager
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5542 | Cell 253-261-5685
pmccon nel I @ KentWA'qov
CITY OF KENT, WASHINGTON
KentWA.oov Faleboak .-i ri:,i:.i {.,:::!: YouTu b€
pr...fastr c(}l*$r$$iR Yl{fi iiH\rIR$NMfineT Ef;iiF$RS pRXNTIN{i Yl{}S #-MAII
The city will agree to participate in the demolition and reconstruction of the concrete slab,
curbing and associated work on the clark springs Generator Project. The city will change order
in g20,000 to the structural bid item #L020, This will be the city's sole and only financial
1
EXTERNAL EMAIL
trtrr
ItrO8112t202',1KentCOLVICO Change OrderSlab workMATERIALGurb RemovalBreakerRemoveHaulPad removalBreakerRemovehaulRemove rebar for gradingGrade slab (not sure on yards)New CurbForm curbLABOR UNITS TOTAL LABOR7.5 yds7.5 yds2load0.951.2520.951.2527.1259.375$$$$$$$$$$$$$$$40017 -118 yds18 yds4.5 load600 fr900 sqf22.50.0050.02903180001_56150 ft $ 3.65547.500.41
ConcreteFinishDowels#4 rebarNew Catch Basin Riser (wating on elevation)SlabForm 2x8Rebar purchaseRebar install & tieConcreteFinishSwellstopLABORLabor7.5 yds7.5 yds57 ea150 ft2ea4ea $1342ft $2150 ft18 yds $18 yds300 ft $140.001,050.00$$$$0.571.25800.0032.49187.501,600.0060.001,945.902,520.00ssz.oo0.6540"120.00510.020.651.250.0154.875306.840.7523$$$$$$$$$$$$$$$$$$$$$$$$$140.001.8415.001.4501204311.722.54.50000000000000$ 8,495.39 MATERIAL289.765 MAN HRS287.765 HRS $ 97.8328,152.05$$$$$$28J52.05 DIRECT LABOR
SUPERVISION 15% OF DIRECT LABOREQUIPMENTBackhoe with breakerDump truck15% $ 4,222.81$ 32,374.86 TOTAL LABOR24.225 HR,13 HR62.50 $3985 $$$1,514.06518.05$ 2,032.11 EQUIPMENTTOTAL MATERIAL $TOTALLABOR $SAFETY $SMALLTOOLS $EQUIPMENT $SUBTOTAL $OVERHEAD $SUBTOTAL $PROFIT $SUBTOTAL $LIABILITY INSURAI $BOND $TOTAL8,495.3932,374.86647.50 2%323.75 1%2,O32.1143,873.614,387.36 100/,OF LABOROF LABOR1ST $50,000BALANCE48,260.974,926.10 100/053,087.061,231.20 41.04 PER $1,000.002%{Y.:@ts;b; lt1$ 55,114.57PLEASE CALL JESSE DRAGOO WITH QUESTIONS, 509.252-5817A-+DC:*u1" 5^lc,Drc