CALYTERA PROJECT CHANGE REQUEST
Client City of Kent
Project Name City of Kent – Permitting System - Phase 2
Change requested by: City of Kent
Project Manager: Derek McConnery – Calytera Project Manager
Change Request # CO-14 (Phase 2)
Urgency: High Date March 9th, 2021
Change Request Identification
Change Title Bluebeam Changes
Change Request Details
Description The purpose of this Change Order is to increase the scope and budget of Milestone:
9b BlueBeam Interface Configuration and QA . The request is to automate the
exchange of documents between Amanda and Bluebeam. The additional scope
includes the following additions to the Bluebeam interface functionality:
Add step to Download files from Bluebeam and Upload to Amanda when the
Amanda processes = Permit Center Notification (Process 10385) OR Close Bluebeam
Session (Process 11175) are inserted on the folder
• FRD updates – update/review/approval
• Development – Automated process for downloading/uploading documents
from Bluebeam to Amanda
See workflow diagram in Appendix A.
Justification This change request is in response to the City of Kent’s request to enhance the
Amanda and BlueBeam Interface from the previously approved FRD .
Priority High
Evaluation
Cost This change includes a cost increase of $3,300.00. This amount will be added to the
value of Milestone 9B Bluebeam from the Phase 2 Statement of Work. The new
value of Milestone 9B Bluebeam is $15,800.00
Schedule There is no impact to the project schedule because of this change order specifically.
Risk n/a
Alternatives and
recommendation
n/a
Implementation Options
N/A
Decision
Approved
Denied
Place on Hold
Page 2 of 2
CALYTERA PROJECT CHANGE REQUEST
Rationale: (if denied or on hold)
Cl:
(by signing this form, the client authorizes Calytera to engage Vision33 to implement the changes
identified in this Change Order):
Section 1: To be completed by the Client
Name (Print):
Title:
Signature:
Date:
Appendix A: Bluebeam Workflow Diagram
Mike Carrington
IT Director
03/11/2021
City of Kent, WA