HomeMy WebLinkAboutCAG2021-332 - Original - Scarsella Bros., Inc. - Summit Landsburg Road and Rock Creek Culvert Replacement - 07/20/2021ApprovalOriginator:Department:
Date Sent:Date Required:
Mayor or Designee
Date of Council Approval:
Grant? Yes No
Type:Review/Signatures/RoutingDate Received: City Attorney:
Comments:
Date Routed: Mayor’s Office City Clerk’s OfficeAgreement InformationVendor Name:Category:
Vendor Number:Sub-Category:
Project Name:
Project Details:
Agreement Amount:
Start Date:
Local Business? Yes No*
Business License Verification:
If meets requirements per KCC 3.70.100, please complete “Vendor Purchase-Local Exceptions” form on Cityspace.
Yes In-Process Exempt (KCC 5.01.045)
Notice required prior to disclosure?
Yes No
Contract Number:
This form combines & replaces the Request for Mayor’s Signature and Contract Cover
Sheet forms. (Print on pink or cherry colored paper)
Visit Documents.KentWA.gov to obtain copies of all agreementsadccW22373_1_20
Budget Account Number:
Budget? Yes No
Dir Asst:
Sup/Mgr:
Dir/Dep:
rev. 20210513
FOR CITY OF KENT OFFICIAL USE ONLY
Agreement Routing Form
For Approvals, Signatures and Records Management
(Optional)
Basis for Selection of Contractor:
* Memo to Mayor must be attached
Termination Date:
Authorized to Sign:
CAG2021-332
7/20/21
Original
DATE: July 6, 2021
TO: Kent City Council
SUBJECT: Summit Landsburg Road and Rock Creek Culvert
Replacement Project Bid - Award
MOTION: I move to award the Summit Landsburg Road and Rock Creek
Culvert Replacement Project to Scarsella Bros., Inc. in the amount of
$2,288,875.34 and authorize the Mayor to sign all necessary documents,
subject to final terms and conditions acceptable to the City Attorney and
Public Works Director.
SUMMARY:
The project includes removal of three existing culverts in Rock Creek, and
construction of a new concrete bridge (measuring about 110-FT end-to-end) over
Rock Creek on SE Summit Landsburg Road. The project is located within the city of
Kent’s Clarks Springs Watershed, located east of Maple Valley. The new bridge will
be relocated partially in the city of Kent and in unincorporated King County. Work
related to this project includes restoration of the Rock Creek stream bed, placement
of woody debris habitat features, the relocation of a Covington Water District water
main, a Soos Creek Water and Sewer District sanitary sewer force main,
Lumen/Century Link telecommunications utilities, and other necessary items. The
project will improve salmon habitat in the Clark Springs Watershed, which is a
critical water supply resource for the city of Kent. This project is a requirement of
the Clark Springs Habitat Conservation Plan.
The bid opening for the Summit Landsburg Road and Rock Creek Culvert
Replacement Project was held on June 8, 2021 with six bids received. The lowest
responsible and responsive bid was submitted by Scarsella Bros., Inc. in the
amount of $2,288,875.34.
Bid Tab Summary
01. Scarsella Bros., Inc. $2,288,875.34
02. Johansen Construction Co. $2,473,617.84
03. Active Construction, Inc. $2,593,195.76
04. Olson Brothers Excavating, Inc. $2,630,446.65
05. Rodarte Construction, Inc. $2,645,821.26
06. Northwest Cascade, Inc. $2,982,876.55
Engineer's Estimate $2,300,400.19
BUDGET IMPACT: The project is fully budgeted through the Water Fund.
SUPPORTS STRATEGIC PLAN GOAL:
Evolving Infrastructure - Connecting people and places through strategic investments in physical
and technological infrastructure.
ATTACHMENTS:
1. Rock Creek Culvert Replacement Bid Tab (PDF)
CONFORMED TO ADDENDUM 1
CITY OF KENT
KING COUNTY, WASHINGTON
KENT SPECIAL PROVISIONS FOR
Summit Landsburg Road and Rock
Creek Culvert Replacement
Project Number: 13-3007.5
BIDS ACCEPTED UNTIL
June 8, 2021
1:00 P.M.
BID OPENING IMMEDIATELY FOLLOWING
DELIVER TO
CITY OF KENT, CITY HALL
220 4th Avenue S., Kent, WA 98032-5895
CHAD BIEREN, P.E.
PUBLIC WORKS DIRECTOR
INDEX
Section 1 Bidder’s Package
Section 2 Payment and Performance Bond
and Contract
Section 3 Table of Contents
Section 4 Kent Special Provisions
Appendix A – SCWSD Rock Creek Culvert
Crossing (02-2020S) Specification -
Supplemental Criteria
Appendix B – Washington State
Department of Fish and Wildlife HPA
Appendix C – United States Army Corps
of Engineers Nationwide Permit
Appendix D – Traffic Control Plan
Appendix E - Prevailing Wage Rates
Appendix F – Geotechnical Report
CITY OF KENT
KING COUNTY, WASHINGTON
KENT SPECIAL PROVISIONS FOR
REPLACEMENT
Project Number: 13-3007.5
BIDS ACCEPTED UNTIL
,dune S. 2021
1:00 P.M.
BID OPENING IMMEDIATELY FOLLOWING
DELIVER TO
CITY OF KENT, CITY HALL
220 4th Avenue S., Kent, WA 98032-5895
CHAD BIEREN, P.E.
PUBLIC=WORKS DIRECTOR
W A S H I N G T 0 N
r-- i
BIDDER'S NAM E Scarsella Bros Inc.
CITY OF KENT
KrNG COUNTY, WASHTNGTON
KENT SPECIAL PROVISIONS FOR
Summit Landsburg Road and Rock
Creek Culvert Replacement
Project Number: 13-3OO7 .5
BIDS ACCEPTED UNTIL
June 8, 2O2t
1:OO P.M.
BID OPENING IMMEDIATELY FOLLOWING
DELIVER TO
CITY OF KENT, CITY HALL
22O 4th Avenue S., Kent, WA 98032-5895
CHAD BIEREN, P.E.
PUBLIC WORKS DIRECTOR
KENT
WlsnrNcroN
ORDER OF CONTENTS
Invitation to Bid
Contractor Compliance Statement
Declaration – City of Kent Equal Employment Opportunity Policy
Administrative Policy 1.2 – Minority and Women Contractors
City of Kent Equal Employment Opportunity Compliance Statement
Proposal
Subcontractor List (over $1 million) – HVAC, Plumbing, and Electrical
Subcontractor List (over $1 million) – Structural Steel Installation and Rebar
Installation
Contractor’s Qualification Statement
Statement that Bidder Has Not Been Disqualified
Certification of Compliance with Wage Payment Statutes
Proposal Signature Page
Bid Bond Form
Combined Declaration Form
Non-Collusion, Minimum Wage
Change Order
Bidder’s Checklist
Payment and Performance Bond
Contract
Table of Contents
Kent Special Provisions
Appendix A – SCWSD Rock Creek Culvert Crossing (02-2020S) Specification –
Supplemental Criteria
Appendix B – Washington State Department of Fish and Wildlife HPA
Appendix C – United States Army Corps of Engineers Nationwide Permit
Appendix D – Traffic Control Plans
Appendix E - Prevailing Wage Rates
Appendix F – Geotechnical Report
INVITATION TO BID
Notice is hereby given that the City of Kent, Washington, will receive sealed bids at the City
Clerk,s office throlgh June a,zOiL up to 1:OO p.m, as shown on the clock on the east wall of
the City Clerk's OffLe on the first floorof City Hall,220 4th Avenue South, Kent, Washington. All
bids must be properly marked and sealed in accordance with this "Invitation to Bid." Bids must
be delivered and received at the City Clerk's office by the above-stated time, regardless of
delivery method, including U.S. Mail, All bids will be opened and read publicly aloud immediately
following 1:OO p.m. for the City of Kent project named as follows:
Summit Landsburg Road and Rock Creek Culvert Replacement
Project Number 13-3OO7.5
The City of Kent will conduct the bid opening at the time and date as scheduled,
howevir, due to the coronavirus disease 2o19 (coVID-l9) and its impacts the bid
opening process will take place as followsl
Bidders shal ca1 the City €terk at (253) 856-5725 to drop off bids. The City Clerk will
read the bids out loud from the Clerk's office. Individuals can stand in the lobby
outside the Clerk's office during the bid opening to hear the bid results, but must
stand 5 feet or more aPart.
The project consists of the removal of three (3) existing culverts in Rock Creek, and construction
of a new concrete bridge (measuring about 110-FT end-to-end from the approach slabs), over
Rock Creek on SE Summit Landsburg Road. The project is located within the City of Kent's
Clarks Springs Watershed, located east of Maple Valley. The new bridge will be relocated
partially in tfie City of Kent and in unincorporated King County. Work related to this project
includes restoration of the Rock Creek stream bed, placement of woody debris habitat features,
the relocation of a Covington Water District water main, a Soos Creek Water and Sewer District
sanitary sewer force main, Lumen/Century Link telecommunications utilities, and other items'
Construction of in-water work can only occur during the WA Dept of Fish and Wildlife HPA
permitted fish window, which is from June 15th to September 30th. As the roadway is a major
arterial, a detour route will be necessary during construction, All of the above work to open SE
Summit Landsburg Road must be completed by August 26, 2022, ahead of the 2022/2023
school year for ttre tahoma School District. As such, early procurement of the concrete bridge
girders and other long lead items will be critical for successful completion of the project' The
firoject will improue salmon habitat and reduce flood risk in the Clark Springs Watershed, which
is a critical water supply resource for the City of Kent'
The City of Kent has determined the project is essential pursuant to the Governor
Inslee ilssued Proclamation 2O-25. Should a contract be executed and this
proclamation or a similar proclamation be in place, specialized plans and protocols
must be established and implemented to meet the social distancing and sanitation
measures set forth by the United States Department of Labor or the Washington State
Department of Health. It is the contractor's responsibility to implement these
measures.
The Engineer's estimated range for this project is approximately $2,280,000 and $2,510,000 Bid
docum6nts may be obtained by contacting City of Kent Engineering Department, Nancy
yoshitake at 253-g56-550g. Fortechnical questions, please call stephen Lincoln, P.E' at 253-
856-5552.
Bids must be clearly marked *Bid' with the name of the project on the outside of the envelope,
addressed to the City Clerk,22O 4th Avenue South, Kent, WA 98032-5895. Only sealed bids will
be accepted. No facsimiles or electronic submittals will be considered.
Each bid shall be in accordance with the plans and specifications and other contract documents
now on file in the office of the City Engineer, City of Kent, Washington. Plans and
specifications can also be downloaded at no charge at KentWA.oov/doing-
business/bids-procurement, Copies of the WSDOT Standard Specifications are available for
perusal only.
Apprentice Utilization Requirements are mandatory for all public works estimated to cost one
million dollars or more, in which case no less than Lio/o of the labor hours must be performed by
apprentices. KCC 6.01.030.
A cashier's check, cash or surety bond in the amount of 5o/o of the bid must be included with the
bid.
The City of Kent reserves the right to reject any and all bids on any or all schedules or alternates
or to waive any informalities in the bidding and shall determine which bid or bidders is the most
responsive, satisfactory and responsible bidder and shall be the sole judge thereof. Note: The
award of the contract will not occur until the City of Kent has reviewed all bids for
responsiveness and responsibility determinations and the Kent City Council has formally
awarded the contract,
No plea of mistake in the bid shall be available to the bidder for the recovery of his/her deposit
or as a defense to any action based upon the neglect or refusal to execute a contract.
Bidders must submit with their initial bid a signed statement as to whether they have previously
performed work subject to the President's Executive Order No. 1L246.
No bidder may withdraw his/her bid for a period of sixty (60) days after the day of bid opening.
Dated this 24th day of May, 2O2L.
BY y'*l*l-tr,&rA
rim-erteyf I romoto]ity Clerk
Published in:
Daily Journal of Commerce on May 25 and June t,2O2L
Washington State Office of Minority and Women's Business Enterprise on May 25,2021
CONTRACTOR COM PLIANCE STATEM ENT
(President's Executive Order # LL246)
Date June 8,2021
This statement relates to a proposed contract with the City of Kent named
Summit Landsburg Road and Rock Creek Culvert Replacement
Project Number 13-3OO7.5
1.rX
I am the undersigned bidder or prospective contractor. I represent that -
have,have not, participated in a previous contract or
subcontract subject to the President's Executive Order #LL246 (regarding equal
employment opportunity) or a preceding similar Executive Order.
Scarsella Bros., Inc.
NAME OF BIDDER
BY
GNATU LE
Bob Scarsella, Vice President
P.O. Box 68697
Seattle, WA 98168
ADDRESS
(Note to Bidders: The information required in this Compliance Statement is
informational only)
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
1 May 24,2O2l
DECLARATION
CITY OF KENT EQUAL EMPLOYMENT OPPORTUNITY POLICY
The City of Kent is committed to conform to Federal and State laws regarding equal
opportunity. As such, all contractors, subcontractors and suppliers who perform work
with relation to this contract shall comply with the regulations of the City's equal
employment opportunity policies.
The following questions specifically identify the requirements the City deems
necessary for any contractor, subcontractor or supplier on this specific contract to
adhere to. An affirmative response is required on all of the following questions for this
contract to be valid and binding. If any contractor, subcontractor or supplier willfully
misrepresents themselves with regard to the directives outlined, it will be considered a
breach of contract and it will be at the City's sole determination regarding suspension
or termination for all or part of the contract;
The questions are as follows:
1. I have read the attached City of Kent administrative policy number 1'2.
2. During the time of this contract, I will not discriminate in employment on the basis
of sex, race, color, national origin, age, or the presence of all sensory, mental or
physical disabilitY,
3. During the time of this contract, the prime contractor will provide a written
statement to all new employees and subcontractors indicating commitment as an
equal opportunity emPloYer.
4. During the time of the contract I, the prime contractor, will actively consider hiring
and promotion of women and minorities.
5. Before acceptance of this contract, an adherence statement will be signed by me,
the Prime Contractor, that the Prime Contractor complied with the requirements as
set forth above.
By signing below, I agree fiil referenced above.
For:Bros., lnc.
Title Bob Scarsella, Vice President
Date:June 8,2021
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
By
2
ve req
May 24,2021
CITY OF KENT
ADMINISTRATIVE POLICY
NUMBER: L.2 EFFECTIVE DATE: JanuarY 1, 1998
SUBJECT:
POLICY:
Equal employment opportunity requirements for the City of Kent will conform to
federal and state laws. All contractors, subcontractors, consultants and suppliers of
the City must guarantee equal employment opportunity within their organization and,
if holding contracts with the City amounting to $10,000 or more within any given
year, must take the following affirmative steps:
1. Provide a written statementto all new employees and subcontractors indicating
commitment as an equal opportunity employer.
Z. Actively consider for promotion and advancement available minorities and women.
Any contractor, subcontractor, consultant or supplier who willfully disregards the City's
nondiscrimination and equal opportunity requirements shall be considered in breach of
contract and subject to suspension or termination for all or part of the contract.
Contract Compliance Officers will be appointed by the Directors of Planning, Parks,
and public Works Departments to assume the following duties for their respective
departments,
1. Ensuring that contractors, subcontractors, consultants, and suppliers subject to
these regulations are familiar with the regulations and the City's equal employment
opportunity policY.
2. Monitoring to assure adherence to federal, state and local laws, policies and
guidelines,
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
MINORITY AND WOMEN
CONTRACTORS
SUPERSEDES: April L, L996
APPROVED BY Jim White, MaYor
3 May 24,202I
CITY OF KENT
EQUAL EMPLOYM ENT OPPORTUNITY
COMPLIANCE STATEMENT
This form shall be filled out AFTER COMPLETION of this project by the Contractor
awarded the contract.
I, the undersigned, a duly represented agent of Scarsella Bros Inc.
Company, hereby acknowledge and declare that the before-
mentioned company was the prime contractor for the contract known as Summit
Landsburg Road and Rock Creek Culvert Replacement/Project Number 13-
3OO7.5 that was entered into on the
represent and the CitY of Kent.
June 2021 between the firm I
I declare that I complied fully with all of the requirements and obligations as outlined
in the City of Kent Administrative Policy t.2 and the Declaration City of Kent Equal
Employment Opportun of the before-mentioned contract'
By
For S Bros., lnc
Title: Bob Scarsella, Vice President
Date:June 8,2021
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
4 May 24,202L
PROPOSAL
To the City Clerk
City Hall
Kent, Washington 98032
The undersigned hereby certifies that Scarsella Bros., Inc
has examined the job site and constru ction details of the work as outlined on the
plans and described in the specificatio ns for the project named Summit Landsburg
Road and Rock Creek Culvert RePl acement/Project Number 13-3OO7.5 for the
City of Kent, Washington, and has rea d and thoroughly understands the plans and
specifications and contract governing the work embraced in this improvement and the
method by which paYment will be ma de for that work and hereby proposes to
undertake and complete the work embraced in this improvement in acc
the bid and contract, and at the following schedule of rates and prices:
ordance with
NOTE TO BIDDERS:
1) All bid items are described in the Kent Special Provisions (KSP) or the Standard
Specifications (WSDOT). Reference the Section No. listed in this proposal, where
the bid item is described.
2) Proposal items are numbered in sequence but are non-continuous.
3) Unit prices for all items, all extensions, and total amount of bid must be shown'
4) Should bid items with identically worded bid item descriptions, marked with
asterisk (*), appear in more than one schedule of the proposal, the bidder must
bid the same unit price on corresponding items for each schedule' If the Contractor
enters different unit prices on these items, the City will unilaterally revise the bid
amounts to the lowest unit price on each corresponding item and recalculate the
Contractor's total bid amount, The corrected total bid amount will be used by the
City for award purposes and fix the amount of the contract bond.
EXAMPLE
SCHEDULE I - STREET
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
QUANTITY
ITEM
1006 2-03,5
WSDOT
100
CU YDS
$ 14.00
Per CY
$ 1,400,00Roadway Excavation,
Including Haul
Any bids not filled out properly may be considered non-responsive.
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
5 May 24,2021
SCHEDULE I - STREET
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
OUANTITY
ITEM
1000 L-09.7
WSDOT
1
LUMP SUM
Mobilizationl $ aAqooo.oo $ Sao,rDo.oD
Per LS
1: Excludinq Schedules II & III
1005 2-01.5
WSDOT
1
LUMP SUM
Clearing and Grubbing g 9looo,oo $ 4(,ooo,oo
Per LS
1060 2-03.5
WSDOT
580
CU YDS
$ Lll,oo
Per CY
$ al tso,ooRoadway Excavation Incl
Haul
1065 2-03.5
WSDOT
70
CU YDS
$ 5o'oo
Per CY
$ 3, stto, ooUnsuitable Foundation
Excavation Incl. Haul
ro70 2-L2.5
KSP
L20
SQ YDS
Geotextile Fabric, Non-Woven $ 8,b
Per SY
$ Qbu,oo
to75 4-03.5
KSP
L,45O
TONS
$ ab,io
Per TON
($2.50 Min)
$ 31,Brlg,ooGravel Borrow, Including
Haul and Compaction
1080 4-O4.5
KSP
570
TONS
Crushed Surfacing ToP
Course, 5/8 Inch Minus
$ 4o,oo
Per TON
($6,00 Min)
$ aa,8m,oo
1085 4-O4.5
KSP
L40
TONS
$ 4o.oo
Per TON
($6.00 Min)
$ 516oo,obCrushed Surfacing Base
Course, L-L/4 Inch Minus
1086 2-03.5
WSDOT
360
CU YDS
$ {P.oo
Per CY
$ a, lbo, ooEmbankment Compaction
1 100 5-04.5
KSP
720
TONS
HMA Class L/2", PG 58H-22 $ l3o.os
Per TON
$ q3i(,oo.or>
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
6 May 24,202I
SCHEDULE I - STREET
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
OUANTITY
ITEM
1230 7-L2.5
KSP
2
EACH
$ tl5o,oo
Per EA
$ ?or,ooAdjust Existing Valve Box ToP
Section and Lid to Finished
Grade
L25t 2-O2.5
WSDOT
1
LUMP SUM
$[ ooo,oo
Per LS
$ /{ oat,odRemoval of Structure and
Obstruction
r296 6-06.s
WSDOT
220
LN FT
Bridge Railing Type S-BP-12 $ ?5oo
Per LF
$ 4o, ?oo, oo
1306 8- 10.5
WSDOT
38
EACH
Flexible Guardrail Reflectors $ 75.oo
Per EA
$ t,aso. oo
L307 8- 1 1.5
WSDOT
4
EACH
Beam Guardrail Transition
Type 24
$ 4aso,oo
Per EA
$ ?, coo.co
13 10 8- 11.5 2
WSDOT EACH
Beam Guardrail Anchor
Type 10
$ /16sD.oD $ 313oo, oo
Per EA
1311 8-11.5 2
WSDOT EACH
Beam Guardrail Type 31 Non- $ {/ssDao $ 8i"7ob.ob
Flared Terminal Per EA
1315 8-28.5
KSP
8
EACH
Utility Pothole $ 8bo,oo
Per EA
$ b,4oo,oo
13 18 8-20.5
KSP
1
EACH
Furnish 25-TA Vault $ {, zgo oo $ Ll,73o,,ru
Per EA
13 19 8-20.5
KSP
240
LIN FT
Furnish and Install 4-Inch
Diameter Schedule 40 Conduit
$ 8/, rf
Per LF
$ ll,ttt a.ob
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
7 May 24,2O2L
SCHEDULE I - STREET
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
OUANTITY
ITEM
1353 1-08
WSDOT
1
CALC
$3,ooo*
Per CALC
$3,0ooxType B Progress Schedule
xCommon price to all bidders
L354 8-31.5
KSP
1
LUMP SUM
Field Trailer $ lDroN.Db
Per LS
$ JNI Fboob
1355 1-04.4(1) 1
WSDOT CALC
Minor Changes $20,000x $20,000
Per CALC
xCommon p rice to all bidders
Schedule I Total $50/, DD
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
8 May 24,2O21
SCHEDULE II - WATER
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
QUANTITY
ITEM
2000 1-09
WSDOT
1
LUMP SUM
Mobilization2 g 3lrooo"u) g3l,Doo,ob
Per LS
2: For Schedu le II onlv
20L6 7-O9.5
KSP
2 Connection to Existing Water
Main 12 Inch Diameter
$ b,8s0,P $ ts,7oo.cs
Per EAEACH
2035 7-O9.5
KSP
203
LN FT
D.L Water Main - 12-inch
Diameter
$ lqo,uo
Per LF
$38,stD,r:o
2036 7-O9.5
KSP
60
LN FT
D.L Water Main - 12-inch
Diameter on Bridge
$ 8t-lu,')D
PeT LF
$ 5Q tou.oo
2037 7-A9.5
KSP
60
LN FT
Steel Casing, 2O-Inch
Diameter
$Sou.uo
Per LF
$ 3o,oob 'oo
2038 7-O9.5
KSP
1
LUMP SUM
Pipe Insulation $ -7, sDD, ')rl $
.1soo.oo
Per LS
20s6 7-I2.5
KSP
1 Gate Valve, 12 Inch $3, alo.oo
Per EA
$ 3,alo,Ds
EACH
2080 7-I4.5
KSP
1
EACH
Hydrant Assembly g 8,85o, oo $ 8, 850, oo
Per EA
2082 7-O9.5
KSP
75
LBS
Additional Ductile Iron Fittings $ J3.S0 $ l, ota,50
Per LB
2101 2-O2.5
KSP
1
EACH
Remove and Salvage Hydrant $ l,lol,oo $ l,0D0,oo
Assembly Per EA
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
9 May 24,2O2!
SCHEDULE II - WATER
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
OUANTITY
ITEM
2ro6 2-O2.5
KSP
1
EACH
$ 350, (D
Per EA
$35o,ooRemove and Salvage Water
Valve, 12-Inch
2LLT 2-O2.5
KSP
255
LN FT
$ /5oo
Per LF
$ 3,8as,s6Remove Ductile Iron Water
Main, 12-Inch
2tL2 2-O2.5
KSP
55
LN FT
Remove Steel Casing, 24-lnch $sD,cO
Per LF
$ d,7so. oo
2254 7-09.5
KSP
20
CU YDS
$ 30'oo
Per CY
$ /, 6Do,ooRemoval and Replacement of
Unsuitable Material
2255 2-09.5
WSDOT
800
sQ rr $ D,iJo
Per SF
$ 3ao,ooShoring or Extra Excavation
Class B
2295 5-04.5
KSP
6
TONS
$ 375,00
Per TON
$ l, eso.ooTemporary Pavement
23I6 8-28.5
KSP
2
EACH
Utility Pothole $ 8oo.oo
Per EA
$ i, d,oo, oo
23t7 8-30.5
KSP
$5,000x
Per FA
$5,0001
FORCE
ACCOUNT
Resolution of Utility Conflicts
xCommon price to all bidders
23LB 7-O9.5
KSP
$9,000x
Per EST
$9,0001
EST
Minor Change for Water
Improvements
xCommon price to all bidders
Sub Total
10.1olo WA State Sales Tax
Schedule II Total
10
$&l I ,437,50
Al,4o6,bet
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
$e?3 ,3
May 24,2O2I
SCHEDULE III - SEWER
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
OUANTITY
ITEM
3001 1-09
WSDOT
1
LUMP SUM
$ D'el
Per LS
$o,o/Mobilization3
3: For S chedule III onlv
3002 2-O2.5
KSP
153
SQ YDS
$ ?5,0u
Per SY
$ $9as,ooRemove Existing AsPhatt
Concrete Pavement
3003 2-O2.5
KSP
306
LN FT
$ 3"50
Per LF
$ li oT), ooSaw Cut Existing Asphalt
Concrete Pavement
3004 2-03.5
WSDOT
195
CU YDS
$ {/,oo
Per CY
$ Jf (s,bDRoadway Excavation Incl
Haul
3005 7-L7.5
KSP
1
LUMP SUM
Abandon Existing SanitarY
Sewer Force Main
$ a,DDo bD $ ?,, oou.oo
Per LS
3006 7-t7.5
KSP
346
LN FT
6-Inch Sewer Force Main,
c900
$ 6o"oo
Per LF
$ io,1bD,6
3007 7-L7.5
KSP
L4L
LN FT
16-Inch Steel Casing $ 3ts, oo
Per LF
$ 3o,3/5,oo
3008 7-L7.5
KSP
2
EACH
Connection to Existing Sewer
Force Main
$ i,5oo. oo $ "f ooo,oo
Per EA
31 16 2-09.5
WSDOT
10
CU YDS
Controlled Density Fill $ 4?5, oc $ 2t LSD,a)
Per CY
3LL7 306
LN FT
8-01. s(2)
KSP
Filter Fabric Fence g5ao g /,53a, cn
11
Per LF
May 24,2O2LRock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
SCHEDULE III - SEWER
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
OUANTITY
ITEM
3118
3119
8-01.5
WSDOT
306
LN FT
Wattle
Trench Shoring Systems in
Compliance with WISHA
$ 6'aD
Per LF
$ Jt83h oD
$5oD $ {53u,co
Per LF
7-L7.5
KSP
306
LN FT
3140 4-04.5
KSP
310
TONS
$ 4D,oD
Per TON
($6.00 Min)
$ la,ub, ooCrushed Surfacing Top
Course, 5/B Inch Minus
3150 4-03.5
KSP
25
TONS
$ "l
t", lo
Per TON
($2.50 Min)
$ b,a,,ioGravel Borrow, Including Haul
and Compaction
3155 5-04.5
KSP
15
TONS
Temporary Pavement $ 375,oo
Per TON
$5,6 2s,oo
3 160 5-04.5
KSP
60
TONS
HMA Class !/2", PG 58H-22 5 l3o'0o $ 7t8DO,oo
Per TON
3316 B-28.5
KSP
2
EACH
Utility Pothole $ 8Do,oD $ l, boo, oo
Per EA
3318 1-04.4(1)
KSP
1
CALC
Minor Changes $25,000* $25,000
Per CALC
xCommon orice to all bidders
Sub Total
10.1% WA State Sales Tax
Schedule III Total
$sl
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
t2
3 afr,l
May 24,2O21
SCHEDULE IV - BRIDGE CONSTRUCTION
ITEM
NO.
SECTION
NO.
APPROX.
OUANTITY
UNIT
PRICE
TOTAL
AMOUNT
ITEM
4r47 7-06.5
KSP
1
LUMP SUM
Temporary Stream Diversion I ilO,ooD,oo $4o, CoO,oo
Per LS
4L4B 2-03.5
WSDOT
L,2OO
CU YDS
Channel Excavation Incl. Haul $50,co
Per CY
$ 60, Doo, cn
4149 2-09.5
WSDOT
700
CU YDS
$50,ou
Per CY
$35 DoD.DDStructure Excavation Class A
Incl. Haul.
4r57 2-O9.5
WSDOT
1
LUMP SUM
Shoring or Extra Excavation
Class A
g l{gmo.oo $ ltiqcoo.ot'
Per LS
4t52 2-LL.5
WSDOT
1
LUMP SUM
Trimming and Cleanup $ 3,reo,oo $ 3,soo,oDPer LS
4t65 30
TONS
8- 1 5.5
WSDOT
Quarry Spalls $ 65,ou
Per TON
$ fgso,oD
($6.00 Min)
4L66 8- 19.5
KSP
900
TONS
Streambed Gravel $ 65oo
Per TON
$ 54soo, oo
4L67 8-15.5
KSP
180
TONS
$ 65,oo
Per TON
$ {zou,ooRock for Erosion and Scour
Protection Class B
42t6 6-02.5
WSDOT
L25
CU YDS
Conc. Class 4000 for Bridge $ /700o,oo $ llt DoD-oo
Per CY
4217 6-02.5
WSDOT
80
CU YDS
Conc, Class 4000D for Bridge $ l,e{0,w $ i OorDDo.cD
13
Per CY
May 24,2O21Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
SCHEDULE IV _ BRIDGE CONSTRUCTION
ITEM
NO.
SECTION
NO.
APPROX.
OUANTITY
UNIT
PRICE
TOTAL
AMOUNT
ITEM
42LB 6-02.5
WSDOT
36,800
LBS
St. Reinf. Bar for Bridge $ l' a-3 $ t{8r'lVt{, ob
Per LB
42L9 6-02.5
WSDOT
3,100
LBS
Epoxy Coated St. Reinf. Bar
for Bridge
$ ).LlD
Per LB
$ 7, ./.t o. oo
4220 6-02.5
WSDOT
345
LN FT
Prestressed Conc. Girder
W35DG
g 8U5. oo $ &ctl 1St_5, oD
Per LF
422t 6-02.5
KSP
195
SQ YDS
Bridge Approach Slab $ qts.ob $gDr(ts,oo
Per SY
4222 6- 10.5
WSDOT
220
LN FT
Single Slope Concrete Barrier g 3a5'oD $ '7lt 5oo.oo
Per LF
4223 6- 11.5
WSDOT
15
CU YDS
Conc, Class 4000 for
Retaining Wall
g l,rloD,ou $ ?lr ooo.aO
Per CY
4224 6- 1 1.5
WSDOT
2,20O
LBS
St. Reinf, Bar for Retaining
Wall
$1,3n $ losg,oD
Per LB
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
Schedule IV Total $OES D Db
L4 May 24,2O2L
SCHEDULE V - TRAFFIC CONTROL
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
QUANTITY
ITEM
5001 1- 10.5
WSDOT
1
LUMP SUM
Project Temporary Traffic
Control
g 4DrrDo,oo $ eO coo,oD
Per LS
5030 1- 10.5
KSP
640
DAYS
Portable Changeable Message
Sign (PCMS)
$ 60,DD
Per DAY
$ J8, {ouoo
5076 8-21.5
WSDOT
1
LUMP SUM
$ /,5oo,ou
Per LS
$ /, so> osPermanent Signing
51 16 8-22.5
WSDOT
86s
LN FT
Plastic Line $ 3,go
Per LF
$a, ssi/,so
5LL7 8-22.5
WSDOT
435
sQ Fr
$ 7su
Per SF
$3,aua,sDProfiled Plastic Line
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007,5
Schedule V Total + bb, b,7, Db
15 May 24,2O2L
SCHEDULE VI -EROSION AND SEDIMENTATION CONTROL
ITEM
NO.
SECTION
NO.
UNIT
PRICE
TOTAL
AMOUNT
APPROX.
QUANTITY
ITEM
6000 8-01. s(2)
KSP
0.1
ACRE
Seeding, Fertilizing, and
Mulching
g,{5,ooo.oo $ t,,soD, oo
Per AC
600 1 8-01.5
WSDOT
180
SQ YD
$ ao' rD
Per SY
$3, 6oo, coSta bil ized Construction
Entrance
6002 8-01.s(2)
KSP
580
LN FT
High Visibility Filter Fabric
Fence
$ 6,ur $3,180 ,m
Per LF
6003 8-01. s(2)
KSP
t70
LN FT
g 3,{s
Per LF
$ 554,soHigh Visibility Fence
6010 8-01.5
WSDOT
130
LN FT
Wattle $ lr,oo
Per LF
$ 78o'aa
601 1 B-01. s(2)
KSP
200
SQ YDS
Biodegradable Erosion Control $ 8,S
Blanket Per SY
$ l,7uo.uo
6030 8-01. s(2)
KSP
800
HOURS
ESC Lead g {oo,oo $ SorDf,D,DD
Per HR
6055 8-01. s(2)
WSDOT
1
FORCE
ACCOUNT
$5,000*
PeT FA
$5,000Erosion/Water Poll ution
Control
*Com mon orice to all bidders
6056 1-07.15
WSDOT
1
LUMP SUM
SPCC Plan $3,coo,Do $ 3,oou,oo
Per LS
Schedule VI Total ${OO, 1r1A,5D
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007,5
16 May 24,2021
SC HEDULE VII - ROADSIDE RESTORATION
ITEM
NO.
SECTION
NO.
APPROX.UNIT
PRICE
TOTAL
AMOUNT
ITEM
7005 8-02.5
KSP
L75
CU YDS
Topsoil Type A g 70,'n $ lir4sD.oD
Per CY
7014 8-02.5
WSDOT
25
CU YDS
$ 70, (b
Per CY
$ l,-7trb, ooWood Chip Mulch
7021 8-02.5
WSDOT
4
EACH
$ eob,'J\
Per EA
$ 8m,uoPSIPE Vine Maple, 6-8'Tall
7022 8-02.5
WSDOT
45
EACH
PSIPE Slough Sedge, plug $ 3r:.oo
Per EA
$ lr 3so,ob
7023 8-02.5
WSDOT
7 PSIPE Red Twig Dogwood, live
stake
g 3o.co
Per EA
$ a-ro,ob
EACH
7024 8-02.5
WSDOT
42
EACH
PSIPE Salal, 2-gallon $ 3o'ou
Per EA
$ l, a,uo'o
7025 8-02.5
WSDOT
55
EACH
PSIPE Tall Oregon GraPe, 2-
gallon
$ 3b.DD
Per EA
g l, bso,oo
7026 8-02.5
WSDOT
16
EACH
PSIPE Thimbleberry, l-gallon $ 3o.oo
Per EA
$ 98o,oo
7A27 8-02.5
WSDOT
23 PSIPE Salmonberry, l-gallon $ 3o'o>
Per EA
$ b9o, oo
EACH
7028 8-02.5
WSDOT
29
EACH
$ 3u,o'>
Per EA
$ 8;o. ooPSIPE Snowberry, 2-gallon
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
t7 May 24,2O2I
SCHEDU LE VII - ROADSIDE RESTORATION
ITEM
NO.
SECTION
NO.
APPROX.UNIT
PRICE
TOTAL
AMOUNT
ITEM
NTITY
7029 8-02.5
WSDOT
37
EACH
PSIPE Evergreen HuckleberrY,
2-gallon
$ 3D,DD
PeT EA
$ li llo, oo
7030 8-26.5
KSP
4 Anchored Log TYPe B $ L'lrosO.oO $ lt ,ouo'oo
PeT EAEACH
703L 8-26.5
KSP
1
EACH
Habitat Log Type A g Llv oco'tr>
Per EA
$ 4, ooo'DD
7032 8-26.5
KSP
5 Habitat Log TyPe B g A1Sob.rt $ \},1SDD,ob
Per EAEACH
7033 B-26.s
KSP
5
EACH
Habitat Log Type C g iL1 DDD'u) $ lDrooD, oD
Per EA
7034 8-26.5
KSP
6 Habitat Log Type D $ li5bb,OD $ 4, ooo. Db
Per EAEACH
Schedule VII Total $1 ob
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
18 May 24,2O2t
BID SUMMARY
sg{t sol , oDSchedule I
Schedule II
Schedule III
Schedule IV
Schedule V
Schedule VI
Schedule VII
TOTAL BID AMOUNT
Street
a33,3t)4,)q
Water
l44,Izq'vs
Sewer
o
Bridge Construction
lob, otJ, b b
Traffic Control
lDorbla,F0
Erosion and Sedimentation Control
73,4ao, uD
Roadside Restoration
'A,^88,815 ,31-l
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
19 May 24,202t
SUBCONTRACTOR LIST
(Contracts over 1 million dollars)
HVAC, PLUMBING AND ELECTRICAL
Name of Bidder Scarsella Tnc.
Project Name:Summit ndsburo Road and Rock Creek Culvert
Reolacem ent
Project Number:13-3007.
pursuant to RCW 39.30.060, Bidder shall list the names of the subcontractors with
whom the Bidder, if awarded the contract, will subcontract for performance of the
work of heating, ventilation, and air conditioning; plumbing; and electrical, or name
itself for the work.
Failure of the Bidder to submit, within one hour after the published bid submittal time,
the names of such subcontractors or to name itself to perform such work or the
naming of two or more subcontractors to perform the same work shall render the
Bidder's Bid non-responsive and, therefore, void.
Heating, Ventilation, and Air Conditioning S bcontractor Name:
Plumbing Subcontractor Name :
Electrical Subcontractor Name:
Si ature of B der
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
D
20 May 24,2O2I
SUBCONTRACTOR LIST
(Contracts over 1 million dollars)
STRUCTURAL STEEL INSTALLATION AND REBAR INSTALLATION
Name of Bidder Scarsella Bros Inc.
Project Name:Summ Landsburo d and Rock C ek Culvert
R.eola ment
Project Number:13-3(l(t7.
pursuant to RCW 39.30,060, Bidder shall list the names of the subcontractors with
whom the Bidder, if awarded the contract, will subcontract for performance of the
work of structural steel installation and rebar installation.
Failure of the Bidder to submit, within 48 hours after the published bid submittal time,
the names of such subcontractors or to name itself to perform such work or the
naming of two or more subcontractors to perform the same work shall render the
Bidder's Bid non-responsive and, therefore, void.
Structural Steel Installation Subcontractor Name: 8 &rWC*utl*rLVC-
Rebar Installation Subcontractor Name :(r t\)c
gnature Bidder
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
Date
27 May 24,2O21
CoNTRACTOR'S QUALTFTCATTON STATEM ENT
(RCW 39.O4.35O)
THE CITY WILL REVIEW THE CONTRACTOR'S RESPONSES TO THIS FORM TO
DETERMINE WHETHER THE BIDDING CONTRACTOR IS RESPONSIBLE TO
PERFORM THE CONTRACT WORK. THIS FORM INCLUDES CRITERIA
ESTABLISHED BY STATE LAW THAT MUST BE MET TO BE CONSIDERED A
RESPONSIB LE BIDDER AND QUALIFIED TO BE AWARDED THIS PUBLIC
WORKS PROJECT AS WELL AS ST'PPLEMENTAL CRITERIA ESTABLISHED BY
THE CITY THAT ARE APPLICABLE TO THIS PUBLIC WORKS PRO]ECT.
THE BIDDER SHOULD READ AND RESPOAID TO THIS FORM CAREFULLY'
Indicia of contractor's responsibility inherently involve subjective determinations as to
the contractor's ability to perform and complete the contract work responsibly and to
the owner city's satisfaction. The city has an obligation and a duty to its citizens and
its taxpayers to administer its budgets and complete its projects in a businesslike
manner. Accordingly, it has a duty to exercise the type of inquiry and discretion a
business would conduct when selecting a contractor who will be responsible to
perform the contract work.
The city's supplemental criteria are based, in large part, on the qualification statement
form used by the American Institute of Architects. The city provides these criteria so
as to provide the most objective framework possible within which the city will make its
decision regarding the bidder's ability to be responsible to perform the contract work.
These criteria, taken together, will form the basis for the city's decision that a bidder
is or is not responsible to perform the contract work.
Any bidder may make a formal written request to the city to modify the criteria set
forth in this qualification statement, but that request may only be made within 48
hours of the date and time that the bidder first obtains the bid documents or three (3)
business days prior to the scheduled bid opening date, whichever occurs first' If the
city receives a modification request, it will consider any information submitted in the
request and will respond before the bid submittal deadline. If the city's evaluation
results in changed criteria, the city will issue an addendum establishing the new or
modified criteria.
If the city determines that, based on the criteria established in this statement, a
bidder is not responsible to perform the contract work, the city will provide written
notice of its determination that will include the city's reason for its decision' The
bidder has 24 hours from the time the city delivers written notice to the bidder that
the bidder is not responsible to perform the contract work to appeal the city's
determination, No appeals will be received after the expiration of this 24 hour appeal
period. The city may deliver this notice by hand delivery, email, facsimile, or regular
mail. In the event the city uses regular mail, the delivery will be deemed complete
three days after being placed in the U.S. Mail. The bidder's right to appeal is limited to
the single remedy of providing the city with additional information to be considered
before the city issues a final determination. Bidder acknowledges and understands
that, as provided by RCW 39.04,350, no other appeal is allowed and no other remedy
of any kind or nature is available to the bidding contractor if the City determines that
the bidder is not responsible to perform the contract work.
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
22 May 24,2021
If the bidder fails to request a modification within the time allowed, or fails to appeal a
determination that the bidder is not responsible within the time allowed, the city will
make its determination of bidder responsibility based on the information submitted.
COMPLETE AND STGil THIS FORM AS PART OF YOUR BID. FAILURE TO
PROPERLY COMPLETE THIS FORM MAY ALSO RESI'LT IN A DETERMINATION
THAT YOUR BID IS A'OAI-RESPONSIVE AND THEREFORE VOID,
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES: CONSULTATION
WITH AN ATTORNEY TS ENCOURAGED WITH RESPECT TO ITS COMPLETION
OR MODIFICATION.
The undersigned certifies under oath that the information provided herein is true and
sufficiently complete so as not to be misleading.
SUBMITTED BY:Scarsella Bros., lnc.
NAME:Bob Scarsella
ADDRESS:P.O. Box 68697
Seattle, WA 98168
PRINCIPAL OFFICE:
ADDRESS:
P.O. Box 68697
Seattle,wA 98168
PHONE:
FAX:
253-872-7173
253-395-1209
STATUTORY REQUIREMENTS - Per state law a bidder must meet the
following responsibility criteria
1. Required Responsibility Criteria
1.1 provide a copy of your Department of Labor and Industries certificate of
registration in compliance with chapter 18.27 RCW'
L.2 provide your current state unified business identifier number. 578-035-242
1.3 Provide proof of applicable industrial insurance coverage for your
employees working in Washington as required in Title 51 RCW, together
with an employment security department number as required in Title 50
RCW, and a state excise tax registration number as required in Title 82
RCW. Providing a copy of a state of Washington "Master License Service
Registration and Licenses" form is typically sufficient evidence of the
requirements of this subsection'
L.4 provide a statement, signed by a person with authority to act and speak
for your company, that your company, including any subsidiary
companies or affiliated companies under majority ownership or under
Rock Creek Culvert Replacement/Lincoln 23 May 24' 202t
Project Number: 13-3007.5
control by the owners of the bidder's company, are not and have not
been in the past three (3) years, disqualified from bidding on any public
works contract under RCW 39.06'010 or 39'12.065 (3). SeeAttached
1.5 Provide a signed statement, signed under penalty of perjury by a person
with authority to act and speak for your company, that within the three-
year period immediately preceding the bid solicitation date, your
company is not a "willful" violator as defined in RCW 49.48.O82, of any
provisions of chapters 49.46, 49.48, or 49.52 RCW, as determined by a
final and binding citation and notice of assessment issued by the
Department of Labor and Industries or through a civil judgment entered
by a court of limited or general jurisdiction' See Attached.
1.6 Provide proof that a designated person or persons with your company
has either received training from the department of labor and industries
or an approved training provider on the requirements related to public
works and prevailing wages under chapter 39,O4 RCW and 39.t2 RCW or
provide proof that your company has completed three or more public
works projects and have had a valid business license in Washington for
three or more years and are exempt from this training requirement.
Exempt; See Attached business licenses and completed project lists.
SUppLEMENTAL CRITERIA - Established by the City to determine bidder
responsibility
2.ORGANIZATION
Z.L How many years has your organization been in business as a Contractor?
73 Years.
2.2 How many years has your organization been in business under its
oresent business name?' 61Years.
2.2.L Under what other or former names has your organization
oPerated? scarsella Bros.
2.3 If your organization is a corporation, answer the following:
3.1 Date of incorporation: June 10, 1958
3.2 State of incorporation: Washington
3.3 President's name: Not Used.g.4 ViCe-preSident'S na me(S) 1 A. Don Scarsella, Bob Scarsella, Gino Scarsella, Rick Scarsella
3.5 Secretary's name: A. Don Scarsella
3.6 Treasurer's name: Not Used.
2.4 If your organization is a partnership, answer the following:
2
2
2
2
2
2
2.4.1
2.4.2
2.4.3
Date of organization: N/A
Type of partnership (if applicable):
Name(s) of general partner(s):
2.5 If your organization is individually owned, answer the following:
2.5.1 Date of organizatien; N/A
2.5.2 Name of owner:
Rock Creek Culvert Replacement/Lincoln 24
Project Number: 13-3007.5
May 24,2021
2.6 If the form of your organization is other than those listed above, describe
it and name the Principals: N/R
3. LICENSING
3.1 List jurisdictions and trade categories in which your organization is legally
qualified to do business, and indicate license numbers, if applicable.
WA State: SCARSBl18388 City of Kent: BLC-8809640
3.2 List jurisdictions in which your organization's partnership or trade name
is filed. N/n
4. EXPERIENCE
4.L
4.2
4.6
4.7
4.2.L
4.2.2
4.2.3
List the categories of work that your organization normally performs with
its own forces.
Clearing/Grubbing, grading, drainage, sewer, water and bridge construction.
Claims and Suits. (If the answer to any of the questions below is yes,
please attach details, )
4,3 Within the last five years, has any officer or principal of your organization
ever been an officer or principal of another organization when it failed to
complete a construction contract? (If the answer is yes, please attach
details,) No.
4.4 On a separate sheet, list major construction projects your organization
has in progress/ giving the name of project, owner, architect or design
engineer, contract amount, percent complete and scheduled completion
date. See Attached.
4.4.L State total worth of work in progress and under contract:1s0,000,000
4.5 On a separate sheet, list the major projects your organization has
completed in the past five years, giving the name of projectf owner,
architect or design engineer, contract amount, date of completion and
percentage of the cost of the work performed with your own forces
Attached.
4.5.1 State average annual amount of construction work performed
during the past five yearsl S132,000,000
Has your organization ever failed to complete any work awarded
to it? No
Are there any judgments, claims, arbitration proceedings or suits
pending or outstanding against your organization or its officers?No
Has your organization filed any law suits or requested arbitration
with regard to construction contracts within the last five years? 5s
On a separate sheet, list the construction experience and present
commitments of the key individuals of your organization, seeAttached.
on a separate sheet' rist your major equipment'
seeAttached.
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
25 May 24,202I
5. REFERENCES
5.1
5,2
5.3
Trade ReferenCeS: NC Machinery, MackTruck.
Bank ReferenceS I Banner Bank, Eric Scroggins 425-739-1069' 11431Willows Rd. NW, STE 140, Redmond, WA 98052
Su rety: Liberty Mutual lnsurance Company
5.3.1 Name of bonding company:
5.3.2 Name and address of agent:
Propel lnsurance, Jim Binder
206-948-3819
925 Fourth Ave., STE 3200
Seattle, WA 98104-1 159
6.
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
FINANCING
6.1 Financial Statement. Willbe submitted upon award of contract
6.L.2
6.2
After bid opening, the City may require the following financial information
from any of the three apparent low bidders. If so required, the selected
bidder(s) must respond with this financial information within 24 hours of
the City's request for that information. The City's request for this
information shall not be construed as an award or as an intent to award
the contract. A bidder's failure or refusal to provide this information may
result in rejection of that bidder's bid.
6.1.1 Attach a financial statement, preferably audited, including your
organization's latest balance sheet and income statement
showing the following items:
Current Assets (e.9., cash, joint venture accounts, accounts
receivable, notes receivable, accrued income, deposits, materials
inventory and prepaid expenses);
Net Fixed Assets;
Other Assets;
6.1,3 Is the attached financial statement for the identical organization
named on page one?
6.L,4 If not, explain the relationship and financial responsibility of the
organization whose financial statement is provided (e.9., parent-
subsidiary).
Will the organization whose financial statement is attached act as
guarantor of the contract for construction?
Current Liabilities (e.g., accounts payable, notes payable,
accrued expenses, provision for income taxes, advances, accrued
salaries and accrued payroll taxes); Other Liabilities (e.9.,
capital, capital stock, authorized and outstanding shares par
values, earned surplus and retained earnings).
Name and address of firm preparing attached financial
statement, and date thereof:
26 May 24,2O2L
7. SIGNATURE
7.L Dated at this 8th day of June ,202I
Name of Organization rsell
By:
Title:Vice dent
7.2 Bob Scarsella being duly sworn, deposes and says that the
information provided herein is true and sufficiently complete so as not to
be misleading.
Subscribed and sworn before me this 8th 6ut 91 June 202L.
Notary Public
My Commission Expires:
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
RY
PUBLIC
27 May 24,2021
STATE OFWASHINGTONProfit CorporationSCARSELLA BROS. INC.SCARSELLA BROS., INC.8404 S 196TH STKENT, WA 98031-1884UNEMPLOYMENT INSURANCE . ACTIVEMINOR WORK PERMIT - ACTIVEBUSINESS LICENSElssue Date: Apr 03, 2020Unified Business lD #: 578O35242Business lD #: 001Location: 0001Expires:Jun 30, 2021)l:ll:.1|i:Lrlrtrir.t,Flr,,,!rrlTNDUSTRIAL INSURANCE . ACTIVETAX REGISTRATION - ACTIVE'rCIry ENDORSEMENTS:BELLINGHAM GENERAL BUSINESS #055363 - ACTIVESHELTON GENERAL BUSTNESS - NON-RESTDENT #0066980 (EXPIRES 10t31t2020) - ACTIVECARBONADO GENERAL BUS]NESS - NON.RESIDENT. ACTIVELACEY GENERAL BUSINESS - NON-RESIDENT #6172 - ACTIVEMARYSVILLE GENERAL BUSINESS - NON-RESIDENT #7173CON919 - ACTIVEOLYMPIA GENERAL BUSINESS - NON-RESIDENT #26435 - ACTIVEPORT ORCHARD GENERAL BUSINESS - NON-RESIDENT - ACTIVERICHLAND GENERAL BUSINESS - NON-RESIDENT - ACTIVESUMNER GENERAL BUSINESS - NON-RESIDENT - ACTIVETUKWILA GENERAL BUSINESS - NON-RESIDENT - ACTIVESEATAC GENERAL BUSINESS - NON-RESIDENT (EXPIRES 6t3Al2A2O) - ACTIVELYNNWOOD GENERAL BUSTNESS - NON-RESTDENT #8US002276-07-2019 (EXPIRES 7131t2O20) - ACTIVEMOUNTLAKE TERRACE GENERAL BUSINESS. NON.RESIDENT #14OOB (EXPIRES 1OI31I2O2O) - ACTIVEDUTIES OF MINORS:Ages 16-17: Yard work, manuallabor around shop area.LICENSING RESTRICTIONS:It is the business's responsibility to comply with minor work permit requirements. See WAC 296-125-030 and WAC296-125-033 for Non-Agricultural and WAC 296-131-125 for Agricultural guidelines and restricted activities.Minors may not operate or work in close proximity to heavy equipment. WAC 296-125-030(17)This document !ists the registraiions. endorsements, and licenses autho.ized for the businessnamed above" Bv aceepting this document. the licerrsee cerliiies the information on tha applicationwas complete, true. and accurate lo lhe best of his or her knowledge, and thal business will ber cnnrlrrnfpr{ in.nhnlittta with 2li ranlir:hlq W:chinatnn ct5t6 .^r'rt\/ anrl .it\/ /d^r'i2}i^^c
KENT
SCARSELLA BROS INC
PO BOX 68697
SEATTLE, WA 98168-0697
Citv of Kent
Business License
Please tear at perforation
llVA I H, N G T o N
KENT
tsUSINESS LICENSE
LICENSE MUST BE PAID ANNUALLY BY
JANUARY lstTO AVOID PENALTY
Issuance of License Does Not Imply Licensee's
Compliance with State snd Local Laws
Per RCW 82.14 local sales
and use tax mrst be coded
No. 1715 for all qualified
sales within the city of
Kent.
WAsxlNGtotr
THIS LICENSE MUST BE POSTED IN A CONSPICUOUS
PLACE. NOT TRANSFERABLE OR ASSIGNABLE 2021
NAME AND ADDRESS OF BUSINESS
BLC-8809640
SCARSELLA BROS INC
8404 S 196 ST
KENt, WA 98031
D tutp-
MAYOR
Tax Registration
Endorsement
The City of Kent
Ar ?20 4TIl AVt S0
K!NT. WASHIIICTON 98032
BTJSSiltsSS.LICENSE
r,tcnxsg'Musr Bb FArbAmrult lynv
reNulnv lit To AvoD PENALfY
Igs uSWe of blgcnre Does Ns!, tt-qpt1;Lbentee'r
Cdrifilloole fvlth St{te agd lhtal Lawe
ACON$FICUOUS
farr Fpglpranon
Endore6ntAnt
2,0t0
D *^*g-
.MAYOR .
'The CiE of .Kent
erzzocrfinVaso :
rglri vinsENsroN crolz
Por (CW 8{.14 local caloe
and use,tax drqef be'codrd
No. 1715 turallluallfied
8alQ,e lvithin a-he gity of
Kdnt.
THIS
PDACT.
Brc.8809640
SCAR$EILABROS Ii{C
's404 s'rqr $r :
KENr,WA9803.1
NAMEANDADI'BNSS
THIS LICENSE MUST BE POSTED IN A CONSPICSOUS
PLACE. NOT TN.ANSFERAf,LE OR ASSIGNABLE
NAil{E AND ADDRESS OF BUSINFSS
BLC-8809640
SCARSELLA BROS rNC
8404 S 196 ST
KENT, WA98O3T.
3USINESS LTCENSE
LICENSEMUST BE PAID AI{I{UALLY BY
JANUARY lst TO AVOID PENALTY
- Iss ilsncc of lJcotua lloes ilot knply tJcunrtce'r
Cbnlrlluuct ultft Slnt{ strd l,actl [,rtfri
Tlx Rcglrtrallon
Endorremgnt
2019
D*1o-?-$^
Per RCW 82.1{ local gsles
afld use tax nu"st be coded
No.'1715 for all qualtfied
saleg withln $e city of
Kent,
The City of Kent
MAYOR
Ar ?20 4TE AVB S0 -
KEN?, WASHINO?ON 98032
', F, It
COMPLETED Cq SSTRUCITON PROJECTS {j(}N'll t{.1{ :"r_ Aivlr } u N:l c:r }8I P L fi'l' lt}N D;!l'E
Si,rurema Quaale Upper Revetment Reconsfruction $6,565,495.00
Conffact No. 974t5
King Counly, 201 S. Jackson, Ste. 600. Seaftle. WA 98 i04-3855
Chase Barton, 2A6-47 7 -485-1, chase.barton@kingcounry.gov
Type ol Work: Bank RevetmentlSite Work (Prime), Estirnated Cost of Prime Work 70%
allL7
BNSF WSDOT ARR{-fask 3 Eavan I Slope Enhancement S854,652.00 lzll6
Contract No. 9986
Burlington Northem & Santa Fe Railrvay Co.,2454 Occidsntal Ave. S., Suite 2D, Seaftle, WA 98134
Ryan Chan, 2A 6-625 -6423, ryan.chan@bnsf.com
Type of Work: Embankmert fPrime), Estimaled Cost of Prime Work 90%
Runway l6C - 34C Reconskuction Project 551,844,At2.i2 12116
Conffact No. 3 1B l3 I
Port of Seattle, 2529 So. 194rh St., SeaTac, WA 98188
Todd Rehm, 206-787 -5747, rehm.t@portofse aftle .org
Type of Work: Itunwarv Reconstnrction iBid as Scarsella Bros. lnc. - Acme, A Joint Venftrre), (Prime)
Estimated Cost of Scarsella Bros. inc. Work 40%
START DAl
a6122il5
a8/f lt6
a3/16i15
3115t16
a9t01/16
09/12/t6
06l2atrc
04,13'l5
West Snoqualmie Valley Rd NE (NE 80* St. ts Ames Lake- S1,824,901.00
Carnation Rd NE)
Contract No. 994 i 5
King Coung, 401 Fifth Ave. -1'd Floor, Seatfle, WA 98104
Jeff McCarthy, 2A6-423 - 1086. jeff.mcc artlty@kingcomry.gov
Type of Work: Road Consfmction, (Prime), Estimated Cost of Prime Work 507o
S. Spokane St. @ I-5 Seismic Backbone S1,1i6071.00
contract No. 2015-080
City of Seattle, P.O. Box 94687, Seaftle, WA 98124-4687
Shaunie Cochran, 2A 6 -25 5 -67 13, Shaunie.cochran@sealtle.gov
Type of Work: Utilities, (Prime), Estirnated Cost of Prime Work 80%
121t6
| 1i16
r0116
L0t t6
i0" l6
So.22Bt\ St Grade Separation @ UPRR
Pier 2 Bridge Shaft Construction
Conffact No. 07-3022
Ovrner: Ciry of Kent,22A 1'h Ave S., Kent, WA 98032-5895
Jason Barry, 2 53 -8 5 6-5 5 4 6, jbarry @kenlwa.gov
Type of Work: Srte Work. (Subcontractor to SB Sfructures, Ll,C)
s t43,280.00
SR5 18 [/C Restoration at Des lvloines Memarial Dr. 5982,701.00
Contract No. 3 18406
Po* of Sealtle, P.O. Box 68727, SeaTac, WA 98168
T'odd Rhem, 20 6 -7 87 - 5i 47, rehm. t@pofi seatt le. org
Type of Work: lnterchange Restoration (Prime). Estimaled Cost of Prime Work 40%
l-90 Muilan to Vlontana State Line. WB & EB Lanes 56,279,043 0i)
Ctxlract No. 7875
Idaho Transportation Departmenl. 600 W. Prairie Ave., Cioeur d'Alene, lD 83815-8764
J chn Pert'ect, 2 A 8 -7 i ? - 122 -'1. j o hn.perfecti!) itd. idaho. go v
-fy1:e olWork: Flighwav lPrlme), Estimated Cost cf Plime fiiork 40%
Crrnstruclion Logistics Expansitrn $2,29 1,641 .()A
Conlract ltio. i i 8i l-5
Port oiSeirttle, P.O. Flox 6872'i. SeaTac. WA 93168
A lisa O' Ha ver-Ayala. 2A 6-'7 B'l -444?. O' Haver. Al@portseirft le. org
T'ype of Work: Srle Work iPnme). Estirnateci Cost oi Prim,: Work 9()'7n
til,th *zt 19i t6
, 'i rr
COMPLETE-D CONSTRUCTTON PRQJECTS. CPNTRACT AryIOU}iT COMPT-ITIOry_DATE
snSSffi Fork Hylebos Creek-Fish Passage $ 1,140.282.0A A6l16
Conrract No. 8698
WSDOT,6431 Corson Ave. So., Seirrtle, WA 98148-3445
M ike Askari an, 206-7 68 -5 862, askarim@wsdot. wa. gov
Tlpe of Work: Creek Realignment (Prime), Estimated Cost of Prime Work 6004
START DAl
a6l0ln5
a6t18n4
a5/a2lI6
03/211t6
az/}lit6
a7/6t12
8/l't l15
a51A5tI4
4627il I
Bogard Roacl Extension Ea-st $19'436'852.00
Conlract No. l4l2 I
Matanuska-susirna Borough, 350 East Dahlia Ave., Palner, AK 99645
P ierre S fragier, P. E., I 07 -86 I -7 7 27, p ierre.stragier@matsugov.us
Type of Work: Highway (Prime), Estirnated Cost of Prime Work 6092o
Tumwater Auto Dealership Project S186'700.00
Conrract No. 16-04
BJR Holdings, i-LC, 2225 Carnage Dr. SW. Olympia, IVA 98502
Lorenz Schock, (Schock & Co, - Confi'actor) 360-918-6204,Lotenz@schockandco.com
Type of Work: Site Work (Subconrractor lo Schock &. Co.)
Retreat Meadows - 356'h St. Sewer
Contract No. 2016.01
Landmark Homes, Inc., P.O. Box26116, Federal Way, WA 98093
David Litowitz, 253-927 -6i 16, djlito@comcast.net
Type of lVork: Sewer (Prime), Estimated Cost of Prime Work 1009/n
$ l J 6,605.0t1
Spencer Creek Busfuress Park Site Pre-Load 5l'039'900.00
Conffact No, 2015-47
Port of Kalama, 110 W. Marine Dr., Kalama, WA 98525-9500
Eric Yakovi cb, 3 6A -67 3 -23 37, eyakovich@portofl<alama.com
Type of Work: Site Work, (Prime), Estimated Cost of Prime Work 1000uir
i-405, NE 6s St. to I-5 Widening & Express Toll Lanes S16'977,701.00
Confract No. 3800
WSDOT, P.O. Box 47354, Olympia, WA 98504-7354
BiIly Gaynor, {Flatrion-Prime Conhactor) 760-9I6-9100, bgalnor@flatironcorp.com
Type of'Work: Higirway (Subconfractor to Flatiron)
Grading & Drainage FFO-US20 PME: UPRR-Eddy'ville (Ph. 3)
Corvallis-Newport Hwy. $41.567,71q.00
Contract No. 14670
Oregon DOT, 3700 SW Philomath Blvd., Corvallis, OR 97333
Steve Schultz, P .M., 541-7 51-41 04, steven.schultz@odot.stat€.or.us
Type of Work: Highway {Prime), Estirrated Cost ol Prime Work 409'6
Snohornish Rj'rer Bridge to US 2 Vic-Widening & Sal'ery $77, !38,C81.0i)
Contracl No. 8128
wSDOI',9029 El Capitan Wa;r, F.vereft, wA 98208-3637
-l im NaLr., 425 -2:2 5 -81'26 . nattt(Ar,vsdot. r,ra- go l'
Tvpe of V/ork: F{igh way & Rridge W,:rrk {-Prime). Estinraled Cosi ol Prinre lVork 40'%
BNSF WSDOT ARRA Task 17 Slope Scabilization 93,716,271.00 03i 16
Contract No. 8259
Burlington Northern & Santa Fe Railway Co.,2454 Occidental Ave. S., Suile lD. Seaftle, WA 98 134
Ryan B lume r, 2A6 -62 5 -6 I 46, james.blumer@bnsf.com
Type of Work: Stope Stabilization (Prime). Estimated Cost of Prime Work 60%
06il6
051r6
ayt6
05i16
04116
'J3 i lb
r.l) I I
coNrl,JETEDCw
Spokane Int'lAirport, f'axiway Reconfigwatior, Ph II i20i5)
CONTRA AMOUNT CO}IPLE
$2,0:0,4 14.00 a7lt5
TTON DATE $TART pA'I
aua7il5
Reelclingtorr Levee Setback 57 ,7i3,980 .t)0 061 I 5
Contract No. 8 l7l3
King County, 401 Fifth Ave., C-NK-E,S-0340, Seatt.le, WA 98104
Erik Peters, 206-47 "7 -47 97, erik.peters@kingcotrnly' gov
Type ol lVork: Levee lmprovemenls (Prime), Percent Complete 987o, Estimated Cosl ol Prime Work 80%
Conlract No. l2l1
Spokane International Airport, P.O. Box 19186, Spokane, WA 9921 9-9186
Robert Segheni (Prime Conlact) 5A9-242-1234
Type of Work: Site Work (Subcontractor to Acme Concrete Paving, [nc')
Williarn R. Fairchild Int'l Airport CA Developmenl-Access Rd Impr. S985,483.00
Cioniract No. 3 5300
Port of Port Angeles, P.O. Box 1350, Port tuigeles, WA 98362
David Williams (Consultant: WH Paciiic, Inc.),425-95l-4876. dwilliams@whpacific.com
Type of Work: Taxiway Site Work (Prime), Estimated Cost of Prime Work 50%
Soutlr of Laurel-RR Overpass 99,877,043.44
Conlract No. 3813
Montana DOT , P.O. Box 20 100 I . llelena, MT -59620- l00l
Suzry Price, 406-144-621 5, suprice@mt.gov
T'1pe oi Work: Highway (Prime). Estimated Cost ol Prime Work '10'%
US 95, Garwooci to Sagte, Athol interchange $28,470'384.00
Confract No. 7-589
Idaho 1'ranspofiation Depaftment, District l, 600 W Prailie Ave., Coeur d'Alene, lD 8-18 i -i
Marviir Fem, 20 8 -77 2 - 12 5 3, rnarv in. fbnn@itd. idaho. gov
Type of Work: F"{ighway (Prime). Estirrated Cost ol Prirne Work 50%o
Porhole & Fix Water l,eak Act-i. ro Fed-Ex Bldg. $41,114.18
Contract No. 15002
Porl of Sealtle, P.O. B<tx 68727 , SeaTac, WA 98 168
A-nrra L,ear, 2 5 3 -627 -B I 5 5, al ear(@ generalrnechanical. cotn
Type of, Work: Water Leak Repair (SLrbcontractor to General ivleciranical)
Sonoma Villcro Drainagc lrnprovcmcuts $600,935'00
Contract No. 3802001
Sonorna Villero Homeowners Association, lt2ll SlaterAve. NE, Ste. li0, Kkkland. WA 980,1,1
M ichael Al ten, 206-l 2 I -9 I 84, coachmal len@gmail. corn
l ype of Work: Drainage Improvemsnts (Prinie), Estimated Cost of Prime Work 1009',r
Dike 3 Seepage & Seismic Mitigation Project $49i,520.30
Contract No. 54694
Cassade Water Alliance, 520 - I 12'h Ave. NE, Suite 400, Bellevue. WA 98004
J on S h imada, 42 5 -2n -A36 7, j shimada(@cas c adervaler. org
-fype olWor[<: Dike Seepage & Seismic Mitigation (Prime), Estjmated Ci]st of Prime Work 9tl9'"
47 15
07il5
06it5
05/1 5
04,1s
03i15
06109 14
09/l0ll l
{}61t0/13
091 tzt t1
a4t22lL5
IU tTl r4
tzla*14
Delta Yard ltevisions-Phiise llB, Everelt, WA $ 1,094,861.00 05/15
Cr:nfract No. 6852
BurlingronNorrhern&SantaFeRailwayCo.,2454Occidental Ave.S.,Suite2D,Seaflle,WA 98114
Tzryl or Srnith, 20 6 - 62 5 - 63 86, Tay [or. Srn i th(] bnsl . corl
Type of Work: Site Work (Prirne), Percent Complete 95%. Estimated Cost ol Prime Work 100%
r! Yi, 1,,
goMft!'l't:p d;OtYS't'RU!:'T'tflrj I,ROJIitrl.s CQNT&{CT AMOLiNT COI-IPLETION DATE
Deer Park{JS 101 lntersection Improvemeut $5,I 10,321.00 OBi 14
Conkact No. 1202
Clallam Counry, 223 E. Fourth St., Ste. 6. Porl Angeles, WA 9t361
Joe Donisi, PE, I 60-4 I 7 -24A4, jdon is i1@co.clal h"trn.wa. us
Type of Work: Highway (Prime), Estimated Cost oi Prime Work 409'o
STABT pA'{
08i0511"1
0aa4iu
07129113
04/23it2
ay18l13
09n6lt3
a9/rc/13
agl l2l t3
061Ay !3
Index Calena Road MP 5.8 $195,280.70
Contract No. 9 i4
Snohomish Counfy, lvXls #507, 1000 Rockefeller Ave." Evereft. WA 98201-4046
Clrarles Mathison, 425-388-3188, Ext. 667 3, charles. mathison@snoco.org
Tlpe oi Work: Site Work (Prime), Estirnated Cost of Prime Work 807o
Lauridsen Boulevard Bridge Replacenrent 54,685,578.00
Contract No. 4299
City of Port Angeles, P.O. Box I 1-i0, Port Angeles, WA 98362-0217
J im Mahlum, P .8., 3 6A-4 n -47 0 1, jmah lum@ciryoipa. us
Type of Work: HighwaylBridge (Prime), Estimaled Cost of Prime lVork 40o.zo
Trunk Road Reconstruction, Phaso II 514'233,817.00
Confract No. 5l 132
Alaska Deparfment ol Transportation, P.O. Box 1 95900, Anchorage. Alaska, 995 1 9-5900
John Waisanen, P.E., 907 -244-451 l, john.waisanen@alaska.gov
Type of Work: Highway (Prime), Estimated Cost ol Prims Work 600,6
KentlAubrlm Conveyance System [mprovements 54,522,861.00
Confract No. 42009
King County,20l S. Jackson St., Rn]. 508, N{S: KSC-NR-0508, Seanle, WA 98104-3855
Sue Hildreth, Capital Project lVlanager lIL,206-477-5537, susan.hildreth@kingcounf-v.gov
Type of Work: Pipeiine (Prime), Estimaled Cost of Prime\York750,6
Wesl of Richey - lVest 59,805,086.00
Contract No. I3 5 l-l
Montana DOT, P.O. Box 20 1001, Helena. IvlT 59020- 100 I
Suzy Price, 406-444-621 5" suprice@mt.gov
Type of Work: Highway (Prime), Estimated Cost of Prkne Work 75%
Micldle Nernah River Bridge, Replace Bridge
Connact No. 8i44
WSDO-I. 2408 Taliey \zVay, Keiso, WA 9,3626
C(xtacl: Denys -lak, 3 60-412- 1 3 4 i, iakden;rI@'"r'sdol.',va. gil';
1'ype of Work: Site \!'ork, iSubr--onliaclor lo SB SnLiclures, LL,C)
$ r,198,541.00
Sand to Lind Double Track Project $2,431,107.AA A&11
Conffact No. 4950
Burlington Northern & Santa Fe Railuva-v C.o.,2454 Occidental Ave. S., Suite 2D, Seaftle, WA 98134
Don Omsber g, 20 6 - 62 5 - 626 4, do nald. oms berg@brts t-.c,;m
Type of Work: Site Work (Prine), Percent Complete 84%o, Estim:rted Cost of Prime Work 60%
Cunningham to MP l0 1.3 Double Track Project S2.40i,201.00 A6il'I
Conlract No. 495 i
Burlington Northern & Santa Fe Railway Co.,2154 OccidentalAve. S., Suite 2D, Seanle, WA 98134
Don Omsber g, 206 -625 -62 6 4, do nald.o ms berg@bns f. com
Type of Work: Site Work (Prime), Percent Complete 960,/o, Eslintated Cost t-rf Prime lVork 609i,
81li 4
aSiA
0Bil4
08t i4
05i l1
A''.i14
coMpLETEp CONSTRUCTION PROJE,CTS_ EONTRAST AiVIO_UNT COMPLETION DATE
US-30, S Main St to Jct SH-i4, Soda Springs S73Z,A21.A0 A7tl3
Contract No" 77 l5
ldaho Transportation Dept., 3 j t I W. State Sl., Boise, ID 8370i
Tom Cole 208-23 9 -337 7, tom.cole(@ itd. idaho.go v
'fype of Work: Highway (Prime), Estimated Cost ol Prime lVork i0o;i'
M Street SE Grade Separation $ I 1,827,023.00 07i13
Conlract No. I l0l
Cify of Aubum,25 West Main St., Aubum, wA s8001-4998
Ryan Vondrak, P.8., 253-93 I -3086, rvonclrak@ar-tburnwa.com
Type of Work: Crade SeparationiBridge Underpass (Prinre), Estirnaled Cost of Prime Work 507o
START D4:
a5il3/13
02t2ll2
0-li rSll i
10il0t12
t010ul2
06129it2
0 ti07 I 13
AliQtt li I
Weil l -lransrnission Main S 1,,512,092.0i1
Cr:nfract No. 1204
City of Aubum, ?5 West Main St., Auburu, WA 98001-4998
Robert E. Lee III. 251-804--507l. rlee@aubLutLva.gov
'I'ype of'Work: Water Transmission Main (Prime). Lsf.imated (lost ol'Prime Woll' 709i,
05t t3
lvlcAliisterTransrnission Main $j,l-50.176.86 05/13
Contract No. 37
City of Olympia, P.O. Box 1967, Olympia, WA 98,507-1967
linr fu chardson, P. E., 3 60-7 53 -81 49, h'ichard@c i. r: lyr p i a. wa. u.s
Type of Work: Welded Steel Water T'ransmission l'{ain (Prime), Estinrated Cost olPrirne Work 60%o
Cashmere Milt Site Remediation $l'047,655.00
Contract No. 208020
Port of Chelan County, 238 Otd Station Rd., Ste. A, Wenatchee, lVA 98801
Laurir Jaecks, -509-66 I -3 I 18, Laura@ccpd.cont
Type of Work: Site Remediation (Prime). Estimirted Cosl ol Prime Work 8070
Grading & Drainage FFO-US20 PtvlE: UPRR-Edcly'ville
Corvallis-Newport FIwy. $7,545,029.00
Contract No. 14473
C)regon DOT, :i700 SW Philomath Btvd., Corvallis. Ot{ 97331
Steve Schultz, 541-7 57.tr I 04, steven.schultz@)odot.state.or.us
Type of Work: Highway (Prime), Estimated Cost of Prime Work 4596
Wahkiakum County Run-Off Rd & lntersection Safety 545,-507,80
Contract No. 4201 I
Wahiakum Counfy, P.O. Box 97, Cathlamet, WA 98512
Carl Stewarl, (Frank Gu-rney, Inc.-Prime Contractor) 509-515-3t''}69,tgtrnsyt@colltca.sc.net
Tlpe of Work: Site Work (Subconhactor to Frank Gurnel'. Ino.)
SR 410, White River Bridge -Bridge Scour :l'217 ,2i7 .40
Confract No. 8087
WSDOT, 11203 Bridgeport Way SW, Lakewood. Wi\ 98499
Jcn DefFeirbacher. PE, 25 3 - 5 B 9 -6 I 00, Cc lfenj ilt)u'sdot. wa. gcrv
Type ol Work: Bridge Scour (Prime), Estirnated (ji:st o-f Prin"le Wolk ?ti9'i'
agl3
04i
'3
03il 3
Ferrum to Wisler. CA on Railroad's Yuma Sr,rbdivisii.rn 5)7.391,918.50 0:it3
Confract Nr:. 47617
Union Pacif-rc Railroad Compauty, 631 S. 7d' Si., Pll>enix, AZ 850i4
Danny King, 97 ] -404-6022. dking@up.com
T1,pe olWork: Gradingtsubballast tbr 22 Vtiies ol'Nelv lul:rin Tracl< (Prirne). Estimtried Cosi o1'Prime Work 75%
r,)1,13 07106li I
I .,, Fr ,rrr ,cotrtr,erEn qorysrBgctlo_il pRo;Eqrs cr_oNTR{Er AMQLiN! CIQI4II.E:IQNI8AT.E
Siding Extsnsion at Wapi, lclaho $7 37 ,74A.15 09ll]
Contract No. 50720
UPR& 280 S. 400 W., Suite 35C, Salt Lake Ci!.v-, UT 8410 I
Erin E. Cu11y, 502-32A-8547, eecullyi@up.com
Tlpe of work: Siding Extension (Prime), Estimated ctrsr of'Prime work 9t)ozi,
$I..4.Br pAr
a5l t4ti2
04tav12
041 t6t 12
t0/01/i l
a5/44/09
ffilat/ta
08i0 li l I
07lll/t I
04t23il2
Hawks Prairie Park & Ride Faciliry Constn:ction 82,912,9i2.4A
Conti'act No. 1203
Intercify Transit, P.O. Box 659, Ol1'rnpia, WA 98507-0659
Robert Holcomb, P.E. (Consultant-KPFF Engineers) 36A-292-7230, bob.holcomb@kpff.conr
Type of Work: Site Work (Prime), Estimated Cost of Prime Work 509/o
Site Preparation & Water System Extension $ 1'794'058.01
Confract No. 1201
City of Palrner,23l W. Evergreen Ave.. Palmer, AK 99615
Tom Cohenour, Public Works Director 90i-745-327 l, tcohenour@palmerak.org
Type of Work: Site Prep. & Water Sys. Ext. (Prime), Estimated Cost of Prime Work 90%
Conslruct Roadbed lbr Srvitching Lead in the Pocatello Subdivision $995,997.20
Conffact No. 49141
union Pacit'ic Railroad Company, ,5424 SE Mcloughlin Blvd., Portlanct, oR sl2a2
Ken Bobert, 503 -7 02-6973, kabobert@llp.com
Type of Work: Site Work (Prime), Estirnated Cost olPrime Work9SYo
Porrneuf zuver Bridges $22,286'580.00
Contract No.72L7
Idaho Transportation Department, P.O. Box 4TAA, Pocatello, lD 83205'4744
Joe Pihlaj a, P .8., 2A B -2 3 9 -33 37, j oe.pihlaja(@ild. idaho. gov
Type of Work: Highway/Bridge (Prime), Estimated Cost oF Prime Work 407o
Soutlicenter Parkway Extension $ 16,906,3 i 8.00
Contract No. 2508
City of Tulovila,620A Southcenter Pkrvy., Tukwila, WA 98 188
Bob Giberson, Public Works Director, 206-433-0179, publicworks@rukwilawa.gov
Type of Work: Road Construction (Prime) Estimated Cost of Prime Work 509'o
Sultan Basin Road Phase III $ 1,578,j29'00
Contract No. 6824
City of Sultan, 319 Nlain Sr., #200, Sukan,WA 98291
Sam fu chard (Consultant-WH Pacifi c) 425 -9 5 I -4860. srichard@whpacifi c.com
Type of Work; Highway (Prime), Estimatecl Cost of Prinre Work 60%
Ao,l)
08it2
081t2
av12
B7IL2
ailQ
06i t7
a6t2
Sylvesler Roacl Bridge # l0-52A
Contract No. C006l7C I I
King County,20l S. Jackson Sl., Room 700, Sea*le, lv.{ 98104
J e ff Mc C arth y " 2A 6 - Q3 - I' 0 8 6, j e ff. mc c a:'t hyr@kingc cr u nty. go v
Type of Work: Site trVork iSubcontractor to SB StrLrctures LLC)
$ 196,i20.00
Chilco West Waterline Extension Projecl S:8'i.05 l'00
Conhact No. 41070
North KootenaiWaler Districl, l84l W. Hayden Ave., Hayden. ID Bi8i,5
M il<c G a Lant e, 2 A I -7 7 2 -3 6 I 9, mike g(A,ak rv s ti. c o m
Type of Work: Waterline Extension (Pi:ime). Estinratecl Cosi ,:f Prirne \'\i ork 909/u
(j{) NT' RA{ T' A iVI{} t"Jw'l' {:OFIPL E'rt{}N l}A'f r
a21t2
START D-A]
l2/19ltLChiico East Waterline Extension Project S 169,859.80
Contract No,41052
North Kootenai Water District, t841 W. Hayden Ave., Hayden, ID 83835
Mike Galante, 208-7 72-3 619
Type of Work; Waterline Extension (Prime), Estimated Cost of Prime Work 909'o
Lincoln Avenue Grade Separation 521.6t7 ,618.0A
Con*act No. 68036
Port of Tacoma, P.O. Box 1837, Tacoma, WA 98401-i837
Trevor Thomsley, 253 -3 83 -S 84 I, tthorns ley@ponoft acoma. com
Type of Work: Highway/Bridge (Prime), Estimated Cost of Prime Work 409lo
021t2 0a24/a9
D.4rarbnent of Labor and Indusnies
PO Box 44450
Olytrpia, WA 98504 -4450
SCARSELLA BROS INC
P O BOX 68697
SBATTLE WA 981680697
Ec,liftsgrt"e BRos INc
8388
Law as:
ssj
t
I
Heavy - Highway
Construction An Equol
Opportunity
Employer
June8,202l
1. STATUATORY REQUIREMENTS
I.4 STATEMENT
To Whom It May Concern:
This statement is to certifl/ that Scarsella Bros., Inc. has not been disqualified from bidding on any
public works contract under RCW 39.06.010 or 39J2.A5(3) in the past three (3) years'
Should you have any questions or concerns, please feel free to call.
Sincerely,
Bob Scarsella
Vice President
P,O. Box 68697 . Seattle, Washington 98168-0697 . Tel: (253) 872-7 t73 ' Fax: (253) 395-1209
AKLic. #34'll4 . AZLic.#FiOC24921.6 . CALic.#779354. IDLic.#10394-Unlimited-1-2
MTLic. #t46627 ' NDLic. #44ffi7 ' ORLic. #96884' WAUc.#SCARSBI183B8
W SCARSELLA
s/rvce rgA5
BR0S., tNC
RACr
Heavy - Highway
Construction An Equal
Opponuniry
Employer
June 8,2021
1. STATUATORY RN,QUIREMENTS
1.5 STATEMENT
To Whom It May Concern:
'[his statement is to ccrtify that Scarsella Bros., lnc. has not been a "willful" violator as defined in
RCW 48.48.082, of any provisions of chapters 49.46,49.48, ar 49.52 RCW in the past threc (3)
years.
Should you have any questions or concerns, please feel free to call.
Sincerely,
Bob Scarsella
Vice President
P.0. Box 68697 . Seattle, Washington 98f68-0697 . Tel: (253) 872-7173 ' Fax: (253) 395'1209
AKLic. #34174 , AZLiq#ROC249216 . CALic.#779354. IDLic.#10394-Unlimited-1-2
MTLic. #146627 . NDLic. #44ffi7 ' ORLic.#96884 ' WALic.#SCARSBI183B8
W SCARSELLA
BROS, INC,
1945
o&sBAC}
Heavy - Highway
Construction
June 8, 2021
An Equal
Opportuniry
Empl.oyer
4.EXPERIENCE
4.6 CONSTRUCTION EXPERIENCE OF' KEY INDIVIDUALS
A. Scarsella Bros., Inc. has worked with the City of Kent on several projects.
B. The following is a list of Scarsella Bros., Inc. supervisory force, along with their current
position/experience and current commitments that may be valuable for the work on the
S. 212th St Preservation project.
l. Don Scarsella, Secretary
45 Years' experience, current project commitments 5-7 projects-
2. Robert Scarsella, Vice President
40 Years' experience, current project commitments 5-7 projects.
3. Richard Scarsella, Vice President
35 Years' experience, current project commitments 5-7 projects.
4. Jeff Blumberg, Superintendent
l5 Years' experience on various City, County and state projects,
Current Commitment: Available for this project
P.O. Box 68697 . Seattle, Washington 98168-0697 . Tel: (253) 872-7t73 ' Faxr (253) 395-1209
AK Lic. #34'714 ' AZLic. #ROC2492I6 . CA Lic. #779354 . ID Lic. #10394-Unlimited-1-2
MTLic. #146627 ' NDLic. #44607 ' ORI-ic.#96884 ' WALic.#'SCARSRTI8?RR
SCARSELLA
BROS.. INC,
s/tvce rgA5
BA
4 tj I
Heavy - Highway
Construction
Otv Descrintion
Track Dozers
2
2
t2
2
5
t4
4
Cat623E,F
Cat 631D
Cat 631E
Cat637D,E
Water Wagons
2 Cat 6318, C
Motor Graders
1 Cat l20G
2 Cat 130G
7 Cat 140G, H
7 Cat 14G, H
3 Cat l6G
Major Equipment List
An Equal
Opportunily
Employer
Cat or JD 650D, G TCLT
Cat or JD 550G, LGP
Cat D-6D, G, G LGP, H, H LGP, R or
JD65O
Cat D-7H, R
Cat D-8H, K, N, R
Cat D-9H, N, R
Cat D-10N, R
Rubber Tire Dozers
3 Cat 8248,C
Scrapers
10 Cat CS563
2 Cat825C Compactor
Rubber Tire/Track Loaders
7 Cat IT-28,930G
I JD 6448
3 Trojan i500, 1700
4 Cat 950G
1 Cat 966F
3 Cat 980C, F, F, II, G
Rubber Tire Loader/Backhoes
12 Case 580C, E, Super E, SuPer K, L, SE
o Track Excavators
)
14
4
7
1 Komatsu PC 78
2 Komatsu PC 128US-2
3 Komatsu PCI60LC
5 Komatsu PC 200LC-6,7
4 Komatsu PC228LC-3, USLC-3, US-2
5 Komatsu PC300LC-6,7
3 Cat 320CL
6 KomatsuPC400LC-5,6,7
2 Cat245, B, B Mass Excavator
3 Komatsu PC600LC-7
2 Komatsu PC750LC-6
1 Komatsu PC1000LC-1A
I Komatsu PC1100LC-6
Offroad Truck Tractors
Roller/Compactors 6 Mack CL7l3
2 Mack CL713 Tri-Driv
P.O. Box 68697 . Seattle, Washington 98168-0697 ' Tel: (253) 872-7173 ' Fax: (253) 395.1209
AK Lic. #347t4 , AZLic. #ROc249216 . CA Lic. #'.779354 . ID Lic. #10394-Unlimited-1-2
MT Lic. #146627 . ND Lic. #44607 ' OR Lic. #96884 ' WA Lic. #SCARSBIl83B8
SCARSELLA
. BB0S,,lNC.
E 1945
c
Heavy - Highway
Construction
4.4 Major Construction Proiects
Job: SR 6, Two Tributaries to Chehalis River Fish Passage
Owner: Washington Department of Transportation
Engineer: WSDOT
contract Amount: 56,447,023.58
Percent Complete: 50%
Schedule Completion: August 2021
Job: SH-41, E. Prairie Ave to Boekel Rd
Owner: State of ldaho Transportation Department
Engineer: T-D Engineers
Contract Amount: S31,553,456.42
Percent Complete: 55%
Schedule Completion: November 2021
Job: US 101, MP 253.32 to MP 257.00- Bagley & siebert creeks Remove Fish Barrier
Owner: Washington Department of Transportation
Engineer: WSDOT
contract Am ou nt; $22,329,329,29
Percent Complete; 60%
Schedule ComPletion: August 2021
Job: Alaskan Way Viaduct - Replacement of South Access Surface Streets
Owner: Washington Department of Transportation
Engineer: WSDOT
contract Amount: s23,685,378.39
Percent Complete: 0%
Schedule Completion: October 2021
Job: Covington Connector, 204th Ave SE and SR516
Owner: City of Covington
Engineer: PACE
contract Amount: s23,685,378.39
Percent Complete: 40%
Schedule Completion: lanuarY 2022
Job: Ridgeline Drive Construct lnterchange
Owner: Washington State Department of Transportation
Engineer: WSDOT
Contract Amount: S12,331,610.69
Percent Complete: 30%
Schedule Completion: August 2022
An Equal
Opportunity
Employer
P.O, Box 68697 ' Seattle, Washington 98168-0697 ' Tel: (253) 872-7173 ' Fax: {253) 395-1209
AK Lic. #34714 . AZLic. #ROC2492I6 . CA Lic. #'779354 . IIJ Lic. #i0394-Unlimited-1-2
MTLic. #L46627 . NDLic. #446A7 . ORLic, #96884' WALic.#SCARSBI183B8
SCARSELLA
BR0s., rNc.
RAC
1945
BIDDER RESPONSIBILITY CRITERIA
Statement that Bidder Has Not Been Disqualified
This statement is required by state law (RCW 39.04.350(1)(d)) to be submitted to
the City before the contract can be awarded.
The bidder hereby certifies that, within the three-year period immediately preceding
the bid solicitation date (June 8,202L), the bidder has not been disqualified from
bidding on any public works contract under RCW 39,06.010 or 39.12.065(3).
Scarsella Bros lnc.
Bidder's Busi
Signatu Authorized Officialx
Bob Scarsella
Printed Name
Vice President
Title
June 8,2021 Kent WA
Date City State
* If a corporation, proposal must be executed in the corporate name by the president
or vice-president (or any other corporate officer accompanied by evidence of
authority to sign). If a co-partnership, proposal must be executed by a partner.
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
28 May 24,202L
BIDDER RESPONSIBILITY CRITERIA
Certification of Compliance with Wage Payment Statutes
This certification is required by stafe taw (RCW 39.04.350(2)) to be submitted to
the City before the contract can be awarded.
The bidder hereby certifies that, within the three-year period immediately preceding
the bid solicitation date (June 8,202L), the bidder is not a "willful" violator, as defined
in RCW 49.48.082, of any provision of chapters 49.46, 49'48, or 49.52 RCW, as
determined by a final and binding citation and notice of assessment issued by the
Department of Labor and Industries or through a civil judgment entered by a court of
limited or general jurisdiction.
I certify under penalty of perjury under the laws of the State of Washington that the
foregoing is true and correct,
Scarsella Bros., lnc.
Bidder's Bu
Signa Autho zed Officialxo
Bob Scarsella
Printed Name
Vice President
Title
June 8,2021 Kent WA
Date City State
* If a corporation, proposal must be executed in the corporate name by the president
or vice-president (or any other corporate officer accompanied by evidence of
authority to sign). If a co-partnership, proposal must be executed by a partner.
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
29 May 24,2O2l
PROPOSAL SIGNATURE PAGE
The undersigned bidder hereby proposes and agrees to start construction work on the
Contract, if lwarded to him/her, on or before ten (10) calendar days from the date of
the Notice to Proceed, and agrees to complete the Contract within one hundred fifty
(15O) working days after issuance of the City's Notice to Proceed.
The undersigned bidder hereby agrees to submit all insurance documents,
performancJ bonds and signed contracts within ten (10) calendar days after City
awards the Contract. The -ity anticipates issuance of the Notice to Proceed on the day
of the preconstruction meeting'
No bidder may withdraw his/her bid for a period of sixty (60) calendar days after the
day of bid opening,
The required bid security consisting of a bid bond, cashier's check or cash in an
amount equal to 5olo of the total amount is hereto attached,
Notice of acceptance of this bid or request for additional information shall be
addressed to the undersigned at the address stated below.
Receipt of Addendum No.', I ,
-, -,
to the plans and/or
specifications is hereby acknowledged. Failure to acknowledge receipt of the addenda
may be considered an irregularity in this proposal.
By signing this Proposal Signature Page, the undersigned bidder agrees to accept all
contrlct fbrms and docu.ents included within the bid packet and to be bound by all
terms, requirements and representations listed in the bid documents whether set forth
by the City or the Bidder.
rr'{Scarsella
DATE:
NAM
nature of Authorized Representative
Bob Scarsella, Vice President
(Print Name and Title)
P.O Box 68697
Address
Seattle, WA 98168
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
30 May 24,2O2L
BID BOND FORM
KNOW ALL MEN BY THESE PRESENTS:
That we, Scarsella Bros. lnc. , as Principal,
"n6
Liberty Mutual lnsurance Company , as Surety, are held and firmly
bound unto the CITY OF KENT, as Obligee, in the penal sum of Five Percent (5%) of Bid Amount
Dollars, for the payment of which the Principal and the Surety bond themselves, their
heirs, executors, administrators, successors and assigns, jointly and severally, by
these presents.
The condition of this obligation is such that if the Obligee shall make any award
to the Principal for Summit Landsburg Road and Rock Greek Culvert
Replacement/Project Number: 13-3OO7 .5
According to the terms of the proposal or bid made by the Principal thereof, and the
principal shall duly make and enter into a contract with the Obligee in accordance with
the terms of said proposal or bid and award and shall give bond for the faithful
performance thereof, with Surety or Sureties approved by the Obligee; or if the
principal shall, in case of failure so to do, pay and forfeit to the Obligee the penal
amount of the deposit specified in the invitation to bid, then this obligation shall be
null and void; otherwise it shall be and remain in full force and effect and the Surety
shall forthwith pay and forfeit to the Obligee, as penalty and liquidated damaged, the
amount of this bond.
SIGNED, SEALED AND DATED THIS 8th p4y 6p June 202L
Mutual lnsu Company
SU Cynthia L. Jay,act
IPALPRI
Li
2n
Received return of deposit in the sum of
Rock Creek Cu lvert Replacement/Lincoln
Project Number: 13-3007.5
31 May 24,202t
thir Pourer ol Attorney limlte the acte of iho* mmod heruln, and they have no authorlty to
bird the Company orcept ln tha mamsr rnd i0 tftE ortsnt h0rcln ttated,
Li$rertv
lVlutu;{[
Liberty Mutual lnsurance ComPanY
The Ohio Casualty lnsutance Company
West American lnsuranre GomPanY
POWER OF ATTORNEY
cerrilicate No: 82031 81.013049
suRgr''d
KNOWN ALL
Liborty Mr[ual
under the laws
lJ. Iliurlcu Bmnd<rn K.Jrrs'ob'l'. lladdoc*-: Diatte Ii{.
siale more one true
execute.
of these
pef$on3.
seal,0n behalf a3
thereto this :sth dav of Febrnlrv :0?0
Liborty Mutual lnsuranc€ Company
'lhe Ohio Casualty lnsurance Company
We$lnsurance Company
By:
Assiohnt Secrelary
any and all bonds, remgnizances and ober surety obligations, in pursuance
presents arxl ehall be as binding upon the Companios as if they have been duly signod by tho prosident and attested by the secretary of the Companies ilt their own proper
Slate of PENNSYLVANIA ^^
CountyofMONTGOMERY "
On lhis 2Sth day of Februnr] _ ,
Company, The Ohio Casualty Company,
1020 before me personally appeared David M, Carey, lvho acknowledged himselt to be
ffiiAnrerican lnsurance Company, and that he, as such. being authsized so to do,
tfi'rc
ttuqc,g
c
Ett
cc
uIl
lhe Assistant Secretary of Liberty Mutual lnsurance
exscute he f0fegoing instrument for fie purposes
contained by signing on behalf of the corporations by himselfas a duly authorized oftoer
#
Wl[ilg$g WHEREOF, I have hereunto subscdbed rny name and affixed ny notarial seal at King ol Prussta, Pennsfvania, on the day and year ftrst above vnitten.
Norrlrisi $e6l
lerar8 Pas',elle. Nolan/ Ptrbir"
Ufpsr trtonotlTsp., hin{gori*ly Co{,nty
[Jv Qornrn,sg,ur Ergr€s ltafch ?8.?021 ereea Pastella.
l",lotl]4cL Ponmliyan*: As6o4ltll0ri
Powet of Atlorney is made and executed punuant lo and by auhori$of the folloaing By-laws and Authorizations of The Ohio Casualty lnsurance Company. Liberty Mutual
lnsuranc€ Company, and Wesl American lnsurance 0ornpany which lesolulions are novv in full fotce and effect reading as follows:
, and Weet American lnsurance Company do
said Companros, is in full torc6 and efiect and
Ec
(v:t
cfi
E(t
ARTICIE lV- OFFICER$I Sectim 12. Power of Attorney.
have full power to bind the Corporation by their signaturo and execution of any suoh instrumenta and to attach ttretelo the geal of the Corporation. Wrcn so execuled, such
instrumenis shall be as binding as if signed by the President and attesbd to by the Secretary. Any power or authority granted to any lepresenbtive or attomey-in-fact under the
pmvisions ol frh arhcle may bi revoked at any time by tho goard, the Ch€trman. lhe Presidenl or by he officer ot ofiicers granting such powet or authority.
ARTICLE Xlll - Executlon ol Conlracts: Section 5. Surety Bonds and Undertakings.
rhill appoint such attorney*in-fact, as may be neoo$sary to aciln behalf ol lhe Company to make. execute, seal, acknowledge and deliver as surety atly and ell undefhkings,
Company bi thgir signslun and execution of any such insbumente and t0 athch thereto the geal of tle Company. When so executed sudl instrumcnts thall bs as binding ao ff
srgned by he preddent and attested by fto secretary.
fact as may be nec6rsary to act on behalf of the Company h make, ex6cuh, seal, acknowledge and deliver as surely any and all undertakings. bonds, recognizances and other surety
obligations.
Cumpany, whereva appeadng upon a certifred copy of any powr ot attornsy i$$ued by the Company in connection wiih rurety bonds, shall be valid and binding upon the Company with
lhe same force and effect as trough manually alfixed.
By:/-frlh
\t(\G
c-*
CC
0Fc
qo
o
J
il
$
'r5
(a
d,
o
(u
{ttL
t912 1919 199{
1912 1991
LMS'rlE73 tMlC OCIC V,/AIG Multi Co-l2/,lS
By:
>-/
CITY OF KENT
COMBINED DECLARATION FORM:
NON-COLLUSTON, MINTMUM WAGE
NON-COLLUSION DECLARATION
I, by signing the proposal, hereby declare, under penalty of perjury under the
taws of the United States that the following statements are true and correct:
1. That the undersigned person(s), firm, association or corporation has
(have) not, either directly or indirectly, entered into any agreement'
participated in any collusion, or otherwise taken any action in
iestraint of free competitive bidding in connection with the project
for which this proposal is submitted.
Z. That by signing the signature page of this proposal, I am deemed to
have signed and to have agreed to the provisions of this declaration.
AND
MINIMUM WAGE AFFIDAVIT FORM
I, the undersigned, having duly sworn, deposed, say and certify that in connection
with the performance of the work of this project, I will pay each classification of
laborer, workman, or mechanic employed in the performance of such work not less
than the prevailing rate of wage or not less than the minimum rate of wage as
specified in the principal contract; that I have read the above and foregoing statement
and certificate, know the contents thereof and the substance as set forth therein is
true to my knowledge and belief.
Summit Landsburg Road and Rock Creek Culvert Replacement
Project Number; 13-3OO7.5
NAME OF PROJECT
Scarsella Bros., lnc.
NAME DD
SIGNATURE O THORIZED REPRESENTATIVE OF BIDD ER
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
32 May 24,2021
This chanoe order form is for example purooses onlv. BY submittino a bid- the
ffie bound by the terms of this chanqe order form for anv
chanoe orders.
CHANGE ORDER NO. [Enter # L, 2, 3, etc.]
NAME OF CONTRACTOR:IInsert Companv Namel ("Contractor")
CoNTRACT NAME & PROJECT NUMBER:llnsert Name of original contract & Project #. if aPPlicablel
oRIGINAL coNTRAcr DATE' llnsert Date original Contract was Signedl
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect' For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section 1 of the Contract is hereby modified to revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equiPment necessarY to:
[Insert detailed description of additional materials, services, etc., that
are needed which necessitate this change order - Be as detailed as
possible. You may also refer to an attached exhibit, but clearly
identify the exhibit by title and datel
Z. The contract amount and time for performance provisions of Section 1 of the
Contract are also modified as follows:
Original Contract Sum,
(including appticable alternates and
wssT)
$
Net Change by Previous Change Orders
(incl. applicable WSST)
$
Current Contract Amount
(incl. Previous Change Orders)
$
Current Change Order $
Applicable WSST Tax on this Change
Order
$
Revised Contract Sum $
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
33 May 24,2O2L
Original Time for ComPletion
(insert date)
Revised Time for ComPletion under
prior Change Orders
(insert date)
Days Required (+) for this Change
Order
working days
Revised Time for ComPletion
(insert date)
In accordance with Sections L-04.4 and 1-04.5 of the Kent Special Provisions and
wsDoT standard specifications, and section VII of the Agreement, the contractor accepts all
requirements of this Change Order by signing below. Also, pursuant to the above-referenced
contract, Contractor ag.eeJ to waive any protest it may have regarding this Change order and
acknowledges and acclpts that this Change Order constitutes final settlement of all claims of
any kind oi nature arising from or connected with any work either covered or affected by this
Change Order, including, without limitation, claims related to contract time, contract
acceleration, onsite or home office overhead, or lost profits. This Change Order, unless
otherwise provided, does not relieve the Contractor from strict compliance with the guarantee
and warranty provisions of the original contract, particularly those pertaining to substantial
completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR:
By:
(signature)
Print Name:
I
(titte)
DATE:
CITY OF KENT:
By
(signature)
Print Name:Chad Bieren. P,E.
W
(title)
DATE:
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007.5
34 May 24,2021
BIDDER'S CHECKLIST
The following checklist is a guideline to help the Contractor make sure all forms are
complete. The bidder's attention is especially called to the following forms. Failure to
execute these forms as required may result in rejection of any bid. Bidder's
Package should include the followingl
Bid Document Cover Sheet filled out with Bidder's Name
Order of Contents...........
Invitation to Bid
Contractor Compliance Statement...'..'...
Date
Have/have not participated acknowledgment.....'..
Signature and address
Declaration - City of Kent Equal Employment Opportunity Policy
Date and signature
Administrative Policy
Proposal
First line of proposal - filled in ..........
Unit prices are correct
Minimum bid prices are correct..
SUbCOntraCtOr LiSt (contracts over $lM - HVAC, Plumbing, & Electrical).......,...,
Subcontractors listed ProPerlY
Signature .......,...
Subcontractor List (contracts over $1M - Structural Steel & Rebar Installation) .. tr
Subcontractors listed properly
Date and signature
Contractor's Qualification Statement
Complete and notarized
Statement that Bidder Has Not Been Disqualified
Certification of Compliance with Wage Payment Statutes
Proposal Signature Page
All Addenda acknowledged
Date, signature and address
Bid Bond Form
Signature, sealed and dated ...........
Power of Attorney..........
(Amount of bid bond shall equal 5o/o ol the total bid amount)
Combined Declaration Form
Signature ...........
Change Order Form (Example)............
Bidder's Checklist
The following forms are to be executed afterthe Contract is awarded:
A) CONTRACT
This agreement is to be executed by the successful bidder.
B) PAYMENTAND PERFORMANCE BOND
To be executed by the successful bidder and its surety company.
The following form is to be executed after the Contract is completed:
A) CITY OF KENT EQUAL EMPLOYMENT OPPORTUNITY COMPLIANCE STATEMENT
To be executed by the successful bidder AFTER COMPLETION of this contract.
Rock Creek Culvert Replacement/Lincoln
Project Number: 13-3007,5
tr
tr
tr
tr
tr
tr
tr
tr
tr
tr
tr
tr
tr
!
tr
tr
tr
tr
u
tr
tr
u
tr
tr
tr
tr
tr
tr
tr
tr
tr
!
tr
35 May 24,202I
Bond No. 023218615
KENT
PAYMENT AND PERFORMANGE BOND
TO CITV OF KENT
KNOW ALL MEN BY THESE PRESENTS
That we, the undersigned,Scarsella Bros. lnc.
as Principal, and Libertv Mutual lnsurance Company
a Corporation organized and existing under the laws of the State of XIQ€0{X$Iffi, as a
Surety Corporation, and qualified under the laws of the State of Washington to
become Surety upon bonds of Contractors with Municipal Corporations, as Surety, are
jointly and severally held and firmly bound to the CITY OF KENT in the penal sum of
$2,288,875.U , together with any aQjustments, up or down, in the total contract
price because of changes in the contract work, for the payment of which sum on
demand we bind ourselves and our successors, heirs, adrninistrators or personal
representatives, as the case may be.
This obligation is entered into in pursuance of the statutes of the State of
Washington, and the Codes and Ordinances of the CITY OF KENT.
Nevertheless, the conditions of the above obligation are such that:
WHEREAS, under and pursuant to a motion, duly made, seconded and passed
by the City Council of the City of Kent. King County. Washington, the Mayor of the
City of Kent has let or is about to let to the above bounden Principal, a certain
contract, the said contract providing for construction of Summit Landsburg Road
and Rock Greek Culvert Replacement/Project Number: 13-3OO7.5 (which
contract is referred to herein and is made a part hereof as though attached hereto),
and
WHEREAS, the Principal has accepted, or is about to accept, the contract, and
undertake to perform the work therein provided for in the manner and within the time
set forth:
NOW, THEREFORE, for non-FHWA projects only, if the Principal shall faithfully
perform all the provisions of said contract in the manner and within the time herein
set forth, or within such extensions of time as may be granted under the said
contract, and shall pay all laborers, mechanics, subcontractors and material men, and
all persons who shall supply the Principal or subcontractors with provisions and
supplies for the carrying on of said work and shall indemnify and hold the CITY OF
KENT harmless from any damage or expense by reason of failure of performance as
specified in said contract or from defects appearing or developing in the material or
workmanship provided or performed under said contract, then and in that event this
obligation shall be void; but otherwise it shall be and remain in full force and effect.
lN WITNESS WHEREOF, the above bounden parties have executed this
instrument under their separate seals. The name and corporate seal (if required by
law) of each corporate party is hereto affixed and duly signed by its undersigned
representatives pursuant to authority of its governing body.
Rock Creek Culvert Replacement/Lincoln
Preject Number: 1 3-3007.5
36 June 3, 202'l
TWO WITNESSES
.Tdie lbris
DATE t lslzl
.IIie kfudz
PRINT NAME
DArE: t ltlet
CORPORATE SEAL:
Rock Creek Culvert Replacement/Lincoln
Prqject Number: 1 3-3007.5
Bros. lnc-
PRINCI
TITLE: Hc SanseLla, \lic Hresdffi.
DATE: l lalzt
CORPORATE SEAL
Liberty Mutual Insurance Company
BY
SURETY
BY /1^^J,1'A-.^ ; /h
DATE: 71812021
TITLE: Katharine J. Snider, Attorney-in-Fact
ADDRESS: 1001 4th Avenue,Suite 3700
Seattle, WA 98154
GERTIFIGATE AS TO CORPORATE SEAL
I hereby certify that I am the (Assistant) Secretary of the Corporation named as
Principal in the within Bond;that b brseilla
Who signed the said bond on behalf of the Principal grnrel]a R1.F- TrY":
of the said Corporation; that I know his signature thereto is genuine, and that said
Bond was duly signed, sealed, and attested for in behalf of said Corporation by
authority of its governing body.
SE RETARY OR ASSISTANT SECRETARY
37 June 3, 2Q21
This Power of Afromey limits the acls of those naned herein, and they have no authority lo
bind lhe Gompany except in tte manner and to the extent herein stated.
SURETY
Liberg Mutual lnsurance Company
The Ohio Casualty lnsurance Company
West American lnsurance Company
POWER OF ATTORNEY
KNOWN ALL PERSONS BY TI{ESE PRESENTS: That The Ohio Casualty lnsurance Company is a corporation duly organized under the laws of lhe State of New Hampshke, that
Liberty Mufual lnsurance Company is a corporalion duly organized under tlre laws of the Slate of Massachusetts, and West Amedcan lnsurance Company is a corporalion
under the laws of lhe Stale ol lndiana (herein collectively called the 'Companies'), pursuant lo and by authodty herein set forlh, does hereby name, conslitute and appoint,
duty organized
By:
Libertv
Mutudl.Certificate No: 8205061'023{149
Aliceon
J.AmeliaG Annelies M.Brandon K.Brent E.M.
Terrie
alloflhecityofTacomastateofgeachindividuallyifherebemorethanonenamed,itstrueandlawfulaftomey.in-factlomak€,
execute,seal,a@behallassure!an1asitsactanddeed,anyandallundertakings,hnds,recognizancesandothersuretyobligalions'inpursuance
of trese presenls and shall be as binding upon the Companies as if lhey have been duly signed by the president and attested by the secretary of the Companies in their own proper
persons.
It{ WIINESS WHEREOF, fris Pwver of Attomey has been subscribed by an authorized officer or official of the Companies and the corporale seals of the Companies have been afiixed
therelothis l9th dayof March ,2021
Liberty Mufual lnsurance Company
The Ohio Casualty lnsurance Company
West lnsurance Company
By:
David M. Carey, Assistant
ofPENNSYLVANIA ss
ofMONTGOMERY
lhis lgth day of March , 2021 before me penonally appeared David M. Carey, who acknowledged himself to be the Assistant Secretary of Liberty Mutual lnsurance
Casru-aityEornp'anfr, ail'lfrfAmerican lnsurance Company, and that he, as such, being authodzed so to do, execute the foregoing insfument for the purposes
conlained by signing on behalf of lhe corporalions by himself as a duly authorized oflicer
lN WINESS WHEREOF, I have hereunto subsuibed my name and affixed my notarial seal at King of Prussia, Pennsylvania, on fte day and year first above wdtten.
Commmalth ot PenNylvania - Notary Seal
Teresa Pastella, Notary Public
Mmtgomery Couoty
My mmi$im expires March 28, 2025
Commission oumbs'1126044
Msmber, Ponnsylvania As$ciaiion of Notaries
This Power of Attomey is made and executed pursuant to and by aulhority of the {ollor,ving By-laws and Authorizations of The Ohio Casualty lnsurance Company, Liberty Mufual
Insurance Company, and West funerican lnsurance Company whidr resolulions are now in full force and effect reading as follows:
ARTICLE lV- OFFICER$: Section 12. Powerof Attomey.
Any officer or other official of the Corporation authorized for hat purpose in writing by the Chairman or the President, and subject to such limitation as the Chaitman or the
have full power to bind he Corporation by their signature and execution of any such instruments and to attadl thereto the seal of lhe Corporation. When so execuled, such
insbumenb shall be as binding as if signed by he President and attested to by the Secretary. Any power or aulhority granted l0 any representative or altomey-in-fa6{ under lhe
provisions of this article may be revoked ai any time by the Board, the Chairman, he Presidenl or by lhe officer or officers granting sudt power or aufotity.
ARTICIE Xll - Execution of Contracts: Section 5. Surety Bonds and Undertakings.
shall appoint such attornsysin-fad, as may be necessary to act in behalf of the Company to make, execute, seal, adtnowledge and deliver as surety any and all undertakings,
Company by fieir signafure and exeqdion of any such inshuments and to attadr thereto the seal of the Company. When so executed sudr inslruments shall be as binding as if
signed by the president ard atested by the secretary.
fact as may be necessary to act on behalf of lhe Company to make, exeofe, seal, acknowledge and deliver as surety any and all undertakings, bonds, recognizances and olher surety
obligations.
the same force and effect as though manually affxed.
l, Renee C. Llewellyn, the undersigned, Assistant Secretary, The Ohio Casualty lnsurance Company, Liberty Mutual lnsurane Company, and West Amedcan lnsurance Company do
has not been revoked.
lN IESTIMONY WIIEREOF, I have hereunlo set my hand and affixed lhe seals of said Companies this 8th day of ,luty , 2021
/-filb
Eric A.Erica E.Heather L.Edward
=o
o3
(u
6
JE'6
E
Lo
o
og
1912 1919 1991 Eoo
Loot(\I6Ic\I(Y).?()
(o
(go
1912 1919 1991
LMS-12873 LMlc OCIC WAIC Multi Co 02/21
By:
1
CONTRACT
THIS AGREEMENT, is entered into between the CITY OF KENT, a Washington
municipal corporation ("City"), and Scarsella Bros, Inc.
organized un der the laws of the State of Washington , located and doin I
business at Kent, Washington ("Contractor")
WITN ESS:
In consideration of the terms and conditions contained in this Agreement and in
the project documents, plans, and specifications all of which are a part of this
Agreement, the parties agree as follows:
The Contractor shall do all work and furnish all tools, materials, and equipment
for: Summit Landsburg Road and Rock Creek Culvert
Replacement/Project Number: 13-3OO7.5 in accordance with and as
described in the Contract and shall perform any alterations in or additions to
the work provided under the Contract and every part thereof. The Contract shall
include all project specifications, provisions, and plans; the City's general and
special conditions; the 2A2L Standard Specifications for Road, Bridge, and
Municipal Construction, as prepared by the Washington State Department of
Transportation and the Washington State Chapter of the American Public Works
Association, including all published amendments issued by those organizations,
if applicable ("Standard Specifications"); the City's bid documents; and the
Contractor's response to the City's bid. The Contractor is responsible to obtain
copies of the 2O2t WSDOT Standard Specifications including the latest
amendments issued by WSDOT as of the date of bid opening. Unless otherwise
directed by the City, work shall start within ten (10) days after the City issues
its Notice to Proceed and work shall be physically completed within one
hundred fifty (15O) working days. The terrn of this Contract shall continue
until all work has been completed, Final Acceptance has occurred, and all
Contractor obligations have been fulfilled.
The Contractor shall provide and bear all expense of all equipment, work, and
labor of any sort whatsoever that may be required for the transfer of materials
and for constructing and completing all the work provided for in the Contract,
except where the specifications allocate that responsibility to the City. The total
contract amount for all Work performed under this Contract, including
Washington State Sales Tax, is *2,288,875.34
The City hereby promises and agrees with the Contractor to employ, and does
employ, the Contractor to provide the materials and to do and cause to be done
the above described work and to complete and finish the same according to the
Contract and the terms and conditions herein contained and hereby contracts to
pay for the same according to the Contract and the schedule of unit or itemized
prices provided by Contractor in its response to the City's bid, at the time and
in the manner and upon the conditions provided for in the Contract.
The Contractor for itself, and for its heirs, executors, administrators,
successors, and assigns, does hereby agree to the full performance of all
covenants herein contained upon the part of the Contractor.
Rock Creek Culvert Replacement/Lincoln
Projeci Nunrber: 13-3007.5
2
3
38 June 9, 2021
4
5
6
7
B
It is further provided that no liability shall attach to the City by reason of
entering into this contract, except as expressly provided herein.
Contractor shall defend, indemnify, and hold the City, its officers, officials,
employees, agents. volunteers and assigns harmless from any and all claims,
iqjuries, damages, losses or suits, including all legal costs and attorney fees,
arising out of or in connection with the performance of this contract, except for
iqjuries and damages caused by the sole negligence of the City.
The City's inspection or acceptance of any of Contractor's work when completed
shall not be grounds to avoid any of these covenants of indemnification.
Should a court of competentjurisdiction determine that this contract is suQject
to RCW 4.24.115, then, in the event of liability for damages arising out of bodily
iryiury to persons or damages to property caused by or resulting from the
concurrent negligence of the Contractor and the City, its officers, officials,
employees, agents and volunteers, the Contractor's liability hereunder shall be
only to the extent of the contractor's negligence,
IT IS FURTHER SPECIFICALLY AND EXPRESSLY UNDERSTOOD THAT THt
INDEMNIFICATION PROVIDED HEREIN CONSTITUTES THE CONTRACTOR'S
wArvER oF TMMUNTTY UNDER INDUSIR.IAL INSURAI\C.E, TIrLE 51 RCW,
SOLELY FOR THE PURPOSES OF THIS INDEMNIFICATION. THE PARTIES
FURTHER ACKNOWLEDGE THAT THEY HAVE MUTUALLY NEGOTIATED THIS
WAIVER,
The provisions of this section shall survive the expiration or termination of this
contract.
Contractor agrees, upon the City's written demand, to make all books and
records available to the City for inspection, review, photocopying, and audit in
the event of a contract related dispute, claim, modification, or other contract
related action at reasonable times (not to exceed three (3) business days) and
at places designated by the City,
The Contractor shall procure and maintain, during the term of construction and
throughout the specified term of maintenance, insurance of the types and in the
amounts described in Exhibit A attached and incorporated by this reference.
Contractor is responsible for locating any underground utilities affected by the
work and is deemed to be an excavator for purposes of RCW Ch. 19.122, as
amended. Contractor shall be responsible for compliance with RCW Ch. 19.1?2,
including utilization of the "one call" locator service before commencing any
excavation activities,
Rock Creek Culvert Replacernent/Lincoln
Prqiect Number: 13-3OO7.5
'lo Jurrc 3, 2421
CITY OF KENT
BY
DANA RALPH, MAYOR
DATE:
ATTEST:
KIMBERLEY A. KOMOTO, CITY CLERK
APPROVED AS TO FORM:
KENT LAW DEPARTMENT
CONTRACT
BY
PRINT NAME: Bob Scarsella
TITLE: Viee President
DATE L
Rock Creel( Culvert Replaccrncnt/Lincoln
Project Number: 1 3-3007. 5
4A June 3, 2021
07/20/2021
EXH I BIT A
r NSURANCE REQU I REMENTS FOR
GONSTRUGTION PROJECTS
lnsurance
The Contractor shall procure and maintain for the duration of the Agreement,
insurance against claims for irjuries to persons or damage to property which may
arise from or in connection with the performance of the work hereunder by the
Contractor, their agents, representatives, employees or subcontractors.
A. Minimum Scope of Insurance
Contractor shall obtain insurance of the types described below
1, Gommercial General Liability insurance shall be written on ISO
occurrence form CG OO 01 or its equivalent, with minimum limits of
$3,OOO,OOO per occurrence and in the aggregate for each 1 year policy
period. This coverage may be any combination of primary, umbrella or
excess liability coverage affording total liability limits of not less than
$3,OOO,OOO per occurrence and in the aggregate. Products and Completed
Operations coverage shall be pr.ovided for a period of 3 years following
Substantial Completion of the work. The Commercial General Liability
insurance shall be endorsed to provide the Aggregate per Project
Endorsement ISO form CG 25 03 11 85. The Gity shall be named as an
Additional lnsured under the Gontactor's Commercial General
Liability insurance policy with respect to the work performed for the
Gity. All endorsements adding Additional lnsureds shall be issued on
form CG 2() 1O 11 85 or a form deemed equivalent, providing the
Additional lnsureds with all policies and endorsements set forth in
this section.
2. Automobile Liability insurance covering all owned, non-owned, hired and
leased vehicles. Coverage shall be written on lnsurance Services Office
(lSO) form CA OO 01 or a substitute form providing equivalent liability
coverage. lf necessary, the policy shall be endorsed to provide contractual
liability coverage.
3, Workers'Gompensation coverage as required by the lndustrial lnsurance
laws of the State of Washington.
B. Minimum Amounts of I nsurance
Contractor shall maintain the following insurance limits
1. Gommercial General Liability insurance shall be written with minimum
limits of $3,OOO,OO0 per occurrence and in the aggregate for each 1 year
policy period. This coverage may be any combination of primary, umbrella or
excess liability coverage affording total liability limits of not less than
$3,O0O,OOO per occurrence and in the aggregate. Products and Completed
Operations coverage shall be provided for a period of 3 years following
Substantial Completion of the work.
Rock Creek Culvert Replacement/Lincoln
Project Number: 1 3-3007.5
41 June 3, 2021
EXHIBIT A (Gontinued)
2. Automobile Liability insurance with a minimum combined single limit for
bodily iryury and property damage of $1,OOO,OOO per accident,
G. Other I nsurance Provisions
The insurance policies are to contain, or be endorsed to contain, the following
provisions for Automobile Liability and Commercial General Liability:
1. The Contractor's insurance coverage shall be primary insurance as respect
the City. Any insurance, self-insurance, or insurance pool coverage
maintained by the City shall be excess of the Contractor's insurance and
shall not contribute with it.
2. The Contractor's insurance shall be endorsed to state that coverage shall not
be cancelled by either party, except after thirty (30) days prior written
notice by certified mail, return receipt requested, has been given to the City.
3. The City of Kent shall be named as an additional insured on all policies
(except Professional Liability) as respects work performed b'y or on behalf 'of
the contractor and a copy of the endorsement naming the City as additional
insured shall be attached to the Certificate of lnsurance. The City reserves
the right to receive a certified copy of all required insurance policies. The
Contractor's Commercial General Liability insurance shall also contain a
clause stating that coverage shall apply separately to each insured against
whom claim is made or suit is brought, except with respects to the limits of
the insurer's liability.
D. Gontractor's I nsurance for Other Losses
The Contractor shall assume full responsibility for all loss or damage from any cause
whatsoever to any tools, Contractor's employee owned tools, machinery, equipment,
or motor vehicles owned or rented by the Contractor, or the Contractor's agents,
suppliers or contractors as well as to any temporary structures, scaffolding and
protective fences,
E. Waiver of Subrogation
The Contractor and the City waive all rights against each other any of their
Subcontractors, Sub-subcontractors, agents and employees, each of the other, for
damages caused by fire or other perils to the extend covered by Builders Risk
insurance or other property insurance obtained pursuant to the lnsurance
Requirements Section of this Contract or other property insurance applicable to the
work. The policies shall provide such waivers by endorsement or otherwise.
Rock Creek Culvert Replacement/Lincoln
Project Number: 1 3-3007.5
42 June 3, 2021
EXHIBIT A (Gontinued)
F. Acceptability of lnsurers
lnsurance is to be placed with insurers with a current A.M, Best rating of not less than
A:Vll.
G. Verification of Goverage
Contractor shall furnish the City with original certificates and a copy of the
amendatory endorsements, including but not necessarily limited to the additional
insured endorsement, evidencing the Automobile Liability and Commercial General
Liability insurance of the Contractor before commencement of the work.
H. Subcontractors
Contractor shall include all subcontractors as insureds under its policies or shall
furnish separate certificates and endorsements for each subcontractor. All coverages
for subcontractors shall be subject to all of the same insurance requirements as stated
herein for the Contractor,
Rock Creek Culvert Replacement/Lincoln
Project Number: 1 3-3007.5
43 June 3, 2021
Client#:111013 SCARBROSI
ACORD,. CERTIFICATE OF LIABILITY INSURANCE DATE (MM/DD/YYYY)
710912021
THTS cTR, 'jIcATE Is ISSUED As A MATTER oF INFoBMATIoN oNLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHOBIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: lf the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed.
lf SUBROGATION lS WAIVED, subiect to the terms and conditions of the policy, certain policies may require an endorsement. A statement on
this certificate does not confer any rights to the certificate holder in lieu of such endorsement(s).
PFODUCER
Propel lnsurance
Tacoma Commercial lnsurance
1201 Pacific Ave, Suite 1000
Tacoma, WA 98402
Sharnel Di Vona
ljl8.*fi . .,u, 800 499-0933 866 577-1326
sharnel.divona linsurance,com
INSURER(S'} AFFORDING COVERAGE NAIC #
;NSTJRER A: Liberty Mutual Fire lnsurance Company 23035
INSURED
Scarsella Bros. lnc.
PO Box 68697
Seattle, WA 98168-0697
tNsuRER B. Navigators Specialty lnsurance Company 360s6
tNsuRER c , Axis Surplus lnsurance Company 26620
tNsuRER D: Allied World Assurance Company (US) lnc 1 9489
INSURER E:
INSURER F:
COVERAGES CERTIFICATE NUMBER REVISION NUMBER
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVEBEENISSUED TOTHF INSURED NAMEDABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITIONOF ANY CONTRACTOR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSRlTn TYPE OF INSUFANCE NCH
UBF
UVN POLICY NUMBEF
POLICY EXP.MM/ND/VVYYI LIMITS
A COMMERCIAL GENERAL LIABILITY
CLAIMS-MADE OCCUR
Bl/PD Ded: $15,000
GEN'L AGGREGATE LIMIT APPLIES PER:
POLICY
OTHER:
PRO-JEcr I I roc
X
x
TB2291454734101 )510112021 0510112022 EACH OCCURRENCE s1.000.000
AGE TO RENTED\rlqFS lFa ^..'rr.an.al s1.000.000
MED EXP (Any one person)s5.000
PERSONAL & ADV INJURY s1.000.000
GENERAL AGGREGATE s2.000.000
PRODUCTS - COMP/OP AGG s2.000.000
Stop Gap $1,000,000
A AUTOMOBILE LIABILITY
X ANY AUTO
OWNED
AUTOS ONLY
HIRED
AUTOS ONLY
SCHEDULED
AUTOS
NON.OWNED
AUTOS ONLYXx
X 10/13
4s.2291454734031 )510112021 0510112022 s1,000,000
BODILY INJURY (Per person)$
BODILY INJURY (Per accident)$
PR $
$
B UMBRELLA LIAB
EXCESS LIAB
x OCCUR
CLAII\i1S-MADE
sE21 EXC749623lC 0510112021 0510112022 EACH OCCURRENCF s3.000.000
x AGGRFGATE s3,000.000
nFn prrrrurroru *n/a $
A WORKEBS COMPENSATION
AND EMPLOYERS' LIABILITY
ANY PROPRIETORYPARTNER/EXECUTIVE
OFFICER/MEMBER EXCLUDED?
(Mandalory in NH)
lf yes, describe under
DFScRIPTION OF OPERATIONS below
Y/NN N/A
TB.22914s4734101
(WA Stop Gap only)
0510112021 0510112022 P
TIITF
OTH-
E.L. EACH ACCIDENT s1.000,000
E.L. DISEASE. EA EMPLOYEE s1,000,000
E,L, DISEASE - POLICY LIMIT s1,000,000
c
D
2nd Layer Excess
Contr Pollution
P001 0001 2965003
0308-3387
,510112021
,510112021
0510112022
o51o112023
$2,000,000 (x $3m)
$5,000,000 ea.condition
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Hemarks Schedule, may be attached il more space is required)
RE: 13-3007.5 - Summit Landsburg Road and Rock Creek Culvert Replacement.
Additional lnsured Status applies per attached lorm(s).
Waiver of Subrogation applies per attached form(s).
ACORD 25 (2016/03) I of 1
#s4695700/M4600263
CANCE
@ 1988-2015 ACORD CORPORATION. All rights reserved
The ACOFD name and logo are registered marks of ACORD
KTROO
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFOBE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
,f,t.*l- 0.*$[*.-"*flr-6*
AUTHORIZED FEPRESENTATIVE
City of Kent
400 West Gowe
Kent, WA 98032
This page haq been left blank intentionally
I
Policy Number fB2-791-454734- r}r
lssued by Liberly Mutual Fire lnsurance Co.
This endorsement modifies insurance proVded under the following:
COMMERCIAL GENERAL LIAB ILITY COVERAGE PART
lndex of modifled items:
Reasonable Force
Non-Owned Watercraft Extension
Damage To Premises Rented To You - Expanded Coverage
Bodily Injury To Co-Employees
Health Care Professionals As lnsureds
Knowledge Of Occurrence Or Offense
Notice Of Occurrence Or Offense
Unintentional Failure To Disclose
Bodily lnjury Redefined
Supplementary Payments - lncreased Limits
Property ln Your Care, Custody Or Control
M obile Equipment Redefined
Newly Formed Or Acquired Entities
Waiver Of Right Of Recovery By Written Contract Or Agreement
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY
COMMERCIAL GENERAL LIABILITY ENHANCEMENT FOR CONTRACTORS
Item 1.
Item 2.
Item 3.
Item 4.
Item 5.
Item 6.
Item 7.
Item 8.
Item 9.
Item 10.
Item 11.
Item 12.
Item 13.
Item 14.
Item 1. Reasonable Force
Exclusion a. of Section I - Coverage A - Bodily Injury And Property Damage Liability is replaced by the
following:
a. Expected Or lntended lnjury
"Bodily inju$' or "properly damage" expected or intended ftom the standpoint of the insured. This exclusion
does not apply to "bodily injun/' or "property damage" resulting from the use of reasonable force to protect
persons or properly.
Item 2. Non-Owned Watercraft Extension
Paragraph (2) of Exclusion g. of Section | - Coverage A - Bodily lnjury And Property Damage Liability is
replaced by the following:
(2) A watercraft you do not own that is:
(a) Less than 55 feet long; and
(b) Not being used to carry persons or propertyfor a charge;
Item 3. Damage To Premises Rented To You - Expanded Coverage
A. The final paragraph of 2. Exclusions of Section | - Coverage A - Bodily Injury And Property Damage
Liability is replaced bythe following:
@ 2018 Liberty Mdual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., Wth its permission.
LC 04 43 11 18 Page 1 of 5
Lxclusions c. through n. do not apply to damage by fire, lightning or explosion or subsequent damages resulting
from such fire, lightning or explosion including water damage to premises while rented to you or temporarily
occupied by you with permission of the oumer. A separate limit of insurance applies to this coverage as
described in Section lll- Limits Of lnsurance.
B. Paragraph 6. of Section lll- Limits Of lnsurance is replaced bythe following
6. Subject to Paragraph 5. above, the Damage To Premises Rented To You Limit is the most we will pay
under Coverage Afor damages because of "property damage" to any one premises, while rented to you, or
inthe case of damage byfire, lightning, eplosion orsubsequent damages resulting from such fire, lightning
or explosion including water damage to premises while rented to you or temporarily occupied by you with
permission of the owner.
The Damage To Premises Rented To You Limit is the greater ot
a. $300,000;or
b. The Damage To Premises Rented To You Limit shown on the Declarations.
C. Paragraph 9.a. of the definition of "insured contract" in Section V - Definitions is replaced by the following:
a. A contract for a lease of premises. However, that portion of the contract for a lease of premises that
indemnifies any person or organization for damage by fire, lightning, explosion or subsequent damages
resulting from such fire, liglrtning or oplosion including water damage to premises while rented to you or
temporarily occupied byyou with permission of the ov'mer is not an "insured contract';
D. The paragraph immediatelyfollowing Paragraph (6)of Exclusion j.of Sectionl-CoverageA-Bodilylnjury
And Property Damage Liability is replaced bythe followlng:
Paragraphs (1), (3) and (4) of this exclusion do not apply to "property damage" (other than damage by fire,
liglrtning or explosion or subsequent damages resulting from such fire, lightning or eplosion including water
damage) to premises, including the contents of such premises, rented to you for a period of seven or fewer
consecutive days. A separate limit of insurance applies to Damage To Premises Rented To You as described in
Section lll- Limits of lnsurance.
Item 4. Bodily lnjury To Co-Employees
A. Paragraph 2. of Section ll - Who ls An lnsured is amended to include
Each of the following is also an insured:
Your "employees" (other than either your "executive officers" (if you are an organization other than a
partnership, joint venture or limited liability company) or your managers (if you are a limited liability company))
or"volunteer workers" are insureds while inthe course of theiremploynent orwhile performing duties related to
the conduct of your business with respect to "bodily injury/':
(1) Toyou;
(2) To your partners or members (if you are a partnership or joint venture);
(3) To your members (if you are a limited liability company); or
(4) To a co-"employee" or "volunteer workef' while that co-"employee" or "volunteer worker" is either in the
course of his or her employment by you or while performing duties related to the conduct of your business
(i nclud i ng partici pati on i n any recreational actiMties sponsored by you).
Paragraph 2.a.(1Xa) of Section ll- Who ls An lnsured does not apply to "bodily injut'' for which insurance is
proMded by this paragraph.
@ 2018 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance SeMces Office, lnc., with its permission.
LC 04 43 11 18 Page 2 of 5
B. h" inrur"n.e proVded by this ltem 4. for "bodily injurt'' to a co-"employee" or "volunteer worke/' will not apply
if the injured co-"employee's" or "volunteer worker's" sole remedy for such injury is provided under a workers'
compensation law or any similar law.
C. Other lnsurance
The insurance provided by this ltem 4. is excess over any other valid and collectible insurance available to the
insured, whether primary, excess, contingent or on any other basis.
Item 5. Health Care Professionals As lnsureds
A. Paragraph 2.a.(1Xd) of Section ll - Who ls An lnsured is replaced by the following
(d) Arising out of his or her proVding or fuilure to proVde professional health care seMces. However, any
"employee" or "volunteer worker" of the Named lnsured who is acting as a Good Samaritan in response to
a public or medical emergerrcy or who is a "designated health care proVdef is an insured with respect to
"bodily injuryi' and "personal and advertising injury/' that:
(i) Arises outof the providing of orfuilure to provide professional health care seMces; and
(ii) Occurs in the course of and within the scope of such "employee's" or "volunteer worke/s" employment
bythe Named lnsured.
B. With respect to "employees" and "volunteer workers" providing professional health care seMces, the following
exclusions are added to Paragraph 2. Exclusions of Section I - Coverage A - Bodily lnjury And Property
Damage Liability and Paragraph 2. Exclusions of Section I - Coverage B - Personal And Advertising
Injury Liability:
This insurance does not applyto:
(1) Liabilityassumedunderan"insuredcontract"oranyothercontractoragreement;
(2) Liability arising out of the providing of professional health care services in Molation of law;
(3) LiabiliV arising out of the providing of any professional health care seMces while in any degree under the
influence of intoicants or narcotics;
(a) Liabilityarisingoutofanydishonest,ftaudulent,maliciousorknowinglywrongfulactorfailuretoact;or
(5) Punitive or exemplary damages, fines or penalties.
C. The following definition is added to Section V - Definitions:
"Designated health care provide/' means any "employee" or "volunteer worker" of the Named lnsured whose
duties include proVding professional health care seMces, including but not limited to doctors, nurses,
emergency medicaltechnicians or designated first aid personnel.
D. Other lnsurance
The insurance proMded by this ltem 5. is excess over any other wlid and collectible insurance available to the
insured, whether primary, excess, contingent or on any other basis.
Item 6. Knowledge Of Occurrence Or Offense
Knowledge of an "occunence" or offense byyour agent, servant or "employee" will not in itself constitute knowledge
by you unless your "executive office/' or "employee" designated by you to noti! us of an "occurrence" or offense
has knowledge ofthe "occurence" oroffense.
O 2018 Liberty Mutual lnsurance
lncludes copyighted material of lnsurance Services Office, lnc., Wth its permission.
LC 04 43 11 18 Page 3 of 5
)
Item 7. Notice Of Occurrence Or Offense
For purposes of Paragraph 2.a. of Section lV - Commercial General Liability Conditions, you refers to your
"executive office/' or "employee" thatyou have designated to give us notice.
Item 8. Unintentional Failure To Disclose
Unintentional hilure of the Named lnsured to disclose all hazards eisting at the inception of this Policy shall not be
a basis for denial of any coverage afforded by this Policy. However, you must report such an enor or omission to us
as soon as practicable after its discovery.
This provision does not affect our riglrt to collect additional premium or exercise our right of cancellation or
non-renewal.
Item 9. Bodily lnjury Redefined
The definition of "bodily injury'' in Section V - Definitions is replaced by the following
"Bodily injur!' means:
a. Bodily injury, sickness or disease sustained by a person, including death resulting fom any of these at any time;
and
b. Mental anguish, shock or humiliation arising or.rt of injury as defined in Paragraph a. above. Mental anguish
means anyWe of mental or emotional illness or distress.
Item 10. Supplementary Payments - lncreased Limits
Paragraphs 1.b. and 1.d. of Section l- Supplementary Payments - Coverages AAnd B are replaced by the
following:
b. Up to $3,000 for the cost of bail bonds required because of accidents or traffic law violations arising out of the
use of any vehicle to which Bodily lnjury Liability Coverage applies. We do not have to furnish these bonds.
d. All reasonable erpenses incuned by the insured at our request to assist in the investigation or defense of the
claim or "suit', including actual loss of earnings up to $500 a day because of time off ftom work.
Item 11. Property In Your Care, Custody Or Control
A. Paragraphs (3) and (4) of Exclusion j. of Section I - Coverage A - Bodily lnjury And Property Damage
Liability are deleted.
B. AdditionalExclusion
Coverage provided bythis endorsementdoes notapplyto "propertydamage" to propertywhile intransit.
C. Limits of lnsurance
Subject to Paragraphs 2., 3., and 5. of Section lll- Limits Of lnsurance, the most we will pay for insurance
proVded by Paragraph A. above is:
$10,000 Each Occurrence Limit
$ZS,OOO Aggregate Limit
The Each Occunence Limit for this coverage applies to all damages as a result of any one "occurrence"
regardless of the number of persons or organizations who sustain damage because of that "occurrence".
@ 2018 Libefi Mdual lnsurance
lncludes copyrighted material of lnsurance Services ffice, lnc., with its permission.
LC 04 43 11 18 Page 4 of 5
The Aggregate Limit is the most we will pay for the sum of all damages under this ltem 1 1 .
D. Other Insurance
This insurance does not apply to any portion of a loss for which the insured has avaibbb any other valid and
collectible insurance, whether primary, excess, contingent, or on any other basis, unless such other insurance
was specifically purchased bythe insured to apply in excess of this Policy.
Item 12. Mobile Equipment Redefined
The def nition of "mobib equipment' in Section V - Definitions is amended to include self-propelled vehicles with
permanently attached equipment less than 1000 pounds gross vehicle weight that are primarily designed for:
(1) Snowremoral;
(2) Road maintenance, but not construction or resurfacing; or
(3) Streetcleaning.
Item 13. Newly Formed Or Acquired Entities
A. Paragraph 3. of Section ll - Who ls An lnsured is replaced by the following:
3. Any organization you newly acquire or form, other than a partnership or joint venture, and over which you
maintain majority ownership ormajority interest, will quali! asa Named lnsured if there isno other similar
insurance available to that organization. However:
a. Coverage underthis provision is afforded only until:
(1) The 1 B0th day after you acquire or form the organization;
(2) Separate coverage is purchased for the organization; or
(3) lhe end of the policyperiod
whichever is earlier;
b. Section I - Coverage A - Bodily lnjury And Property Damage Liability does not apply to "bodily
injury/' or "property damage" that occurred before you acquired orformed the organization; and
c. Section I - Coverage B - Personal And Advertising lnjury Liability does not apply to "personal and
advertising injury/' arising out of an offense committed before you acquired or formed the organization.
B. The insurance afforded to any organization as a Named lnsured under this ltem 13. does not apply if a Broad
Form Named lnsured endorsement attached to this Policyapplies to that organization.
Item 14. Waiver Of Right Of Recovery By Written Contract Or Agreement
The following is added to Paragraph 8. Transfer Of Rights Of Recovery Against Others To Us of Section lV -
Commercial General Liability Conditions:
We waive any right of recovery because of payments we make under this Policy for injury or damage arising out of
your ongoing operations or "your work" included in the "products-completed operations hazard" that we may have
against any person or organization with whom you have agreed in a written contract or agreement to waive your
rights of recovery but only if the "bodily injun/' or "propefi damage" occurs, or offense giving rise to "personal and
advertising injuS' is committed subsequent to the execurtion of the written contract or agreement.
O 20'18 Liberly Mtltual lnsurance
lncludes copyighted material of Insurance Services ffice, lnc., with its permission.
LC 04 43 11 18 Page 5 of 5
PolicyNumber T82-291-454734- rlt
lssued by Libefi Mutual Fire lnsurance Co.
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIAB ILII-Y COVERAGE PART
lndex of modif ed items:
Item 1.
Item 2.
Item 3.
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
COM M ERCIAL GENERAL LIABILITY
ADDITIONAL INSURED ENHANCEMENT FOR CONTRACTORS
Blanket Additional lnsured Where Required By Written Agreement
Lessors of Leased Equipment
Managers or Lessors of Premises
Mortgagees, Assignees or Receivers
Owners, Lessees or Contractors
Architects, Engi neers or S urveyors
Any Person or Organization
Blanket Additional lnsured - Grantor Of Permits
Other lnsurance Amendment
Item 1. Blanket Additional lnsured Where Required By Written Agreement
Paragraph 2. of Section ll - Who ls An lnsuredis amended to add the following:
Additional lnsured By Written Agreement
The following are insureds under the Policy when you have agreed in a wriften agreement to proVde them coverage
as additional insureds under your policy:
1. Lessors of Leased Equipment: The person(s) or organization(s) from whom you lease equipment, but only
with respect to liability for "bodily injun/', "property damage" or "personal and advertising injuryi' caused, in
whole or in part, by your maintenance, operation or use of equipment leased to you by such person(s) or
organization(s).
This insurance does not applyto any "occurrence" which takes place after the equipment lease expires.
2. Managers or Lessors of Premises: Any manager(s) or lessor(s) of premises leased to you in which the unitten
lease agreement obligates you to procure additional insured coverage.
The coverage afforded to the additional insured is limited to liability in connection with the ownership,
maintenance or use of the premises leased to you and caused, in whole or in part, by some negligent act(s) or
omission(s) of you, your "employees", your agents or your subcontractors. There is no coverage for the
additional insured for liability arising or.rt of the sole negligence of the additional insured or those acting on
behalf of the additional insured, except as provided below.
lf the written agreement obligates you to procure additional insured coverage for the additional insured's sole
negligence, then the coverage for the additional insured shall conform to the agreement, but only if the
applicable law would allow you to indemni! the additional insured for liability arising out of the additional
insured's sole negli gence.
@ 201 8 Liberty Mutual lnsurance
lncludes copyighted material of lnsurance SeMces Office, lnc., with its permission.
LC 20 58 11 18 Page 1 of 4
This insurance does not applyto:
a. Any "occuffence" which takes place after you cease to be a tenant in that premises or to lease that land;
b. Structural alterations, new construction or demolition operations performed by or on behalf of that manager
or lessor; or
c. Any premises for which coverage is excluded by endorsement.
3. Mortgagees, Assignees or Receivers: Any person(s) or organization(s) with respect to their liability as
mortgagee, assignee or receiver and arising out of your oumership, maintenance or use of the premises.
This insurance does not apply to structural alterations, new construction and demolition operations performed
by or on behalf of srch person(s) or organization(s).
4. Owners, Lessees or Contractors: Any person(s) or organization(s) to whom you are obligated to procure
additional insured coverage, burt only with respect to liability for "bodily inju$', "propefi damage" or "personal
and advertising injurt'' caused, in whole or in part, by your act(s) or omission(s) or the act(s) or omission(s) of
your "employees", your agents, oryour subcontractors, in the performance of your ongoing operations.
This insurance does not apply to "bodily injury/', "property damage", or "personal and advertising injury/' arising
or.rt of "your work" included in the "products-completed operations hazard" unless you are required to provide
such coverage for the additional insured by the written agreement, and then only for the period of time required
by the written agreement and only for liability caused, in whole or in part, by your act(s) or omission(s) or the
act(s) or omission(s) of your "employees", your agents, or your subcontractors.
There is no coverage for the additional insured for liability arising out of the sole negligence of the additional
insured or those acting on behalf of the additional insured, except as proVded below.
lf the written agreement obligates you to procure additional insured coverage for the additional insured's sole
negligence, then the coverage for the additional insured shall conform to the agreement, but only if the
applicable law would allow you to indemnify the additional insured for liability arising out the additional insured's
sole negligence.
This insurance does not apply to "bodily injurj', "propefty damage" or "personal and advertising injuryi' arising
out of the rendering of, or failure to render, any professional architectural, engineering or survelng services,
including:
a. The preparing, approMng, or failing to prepare or approve, maps, shop drawings, opinions, reports, surve)s,
field orders, change orders or drawings and specif cations; or
b. SupeMsory, inspection, architectural or engineering actiMties.
This exclusion applies even if the claims against any insured allege negligence or other wrongdoing in the
supeMsion, hiring, employnent, training or monitoring of others by that insured, if the "occurrence" which
caused the "bodily injut'' or "property damage", or the offense which caused the "personal and advertising
injury'', involved the rendering of orfailure to renderany professional services.
5. Architects, Engineers or Surveyors: Any architect, engineer, or surveyor engaged by you but only with
respect to liability for "bodily injuryi', "property damage" or "personal and advertising injuS' caused, in whole or
in part, by your act(s) or omission(s) or the act(s) or omission(s) of those acting on your behalf:
a. ln connection with your premises; or
b. ln the performance of your ongoing operations.
This insurance does not apply to "bodily inju$', "property damage" or "personal and advertising injun/' arising
ourtofthe renderingoforfailuretorenderanyprofessional servicesbyorforyou,including:
@ 201 B Liberty Mutual lnsurance
lncludes copyighted material of lnsurance SeMces ffice, lnc., with its permission.
LC 20 58 11 18 Page 2 of 4
;. The preparing, approMng, or failing to prepare or approve, maps, shop drawings, opinions, reports, surveys,
field orders, change orders or drawings and specifications; or
b. SupeMsory, inspection, architectural or engineering actiMties.
This exclusion applies even if the claims against any insured allege negligence or other wrongdoing in the
supeMsion, hiring, employment, training or monitoring of others by that insured, if the "occurrence" which
caused the "bodily injury/' or "property damage", or the offense which caused the "personal and advertising
inju$', involved the rendering of or failure to render any professional seMces by or for you.
6. Any Person or Organization Other Than a Joint Venture: Any person(s) or organization(s) (other than a joint
venture of which you are a member) for whom you are obligated to procure additional insured coverage, but
only with respect to liability for "bodily injuS', "property damage" or "personal and advertising inju$' caused, in
whole or in part, by your act(s) or omission(s) or the act(s) or omission(s) of those acting on your behaff:
a. ln the performance of your ongoing operations; or
b. ln connection with premises owned by or rented to you.
This insurance does not applyto:
a. Any person(s) or organization(s) more specifically covered in Paragraphs 1. through 5. above;
b. Any construction, renovation, demolition or installation operations performed by or on behalf of you, or
those operating on your behalf; or
c. Any person(s) or organization(s) whose profession, business or occupation is that of an architect, surveyor
or engineer Wth respect to liability arising out of the rendering of, or failure to render, atry professional
architectural, engineering or survelng seMces, including:
(1) The preparing, approving or failing to prepare or approve, maps, drawings, opinions, reports, surveys,
field orders, change orders, designs and specif cations; or
(2) SupeMsory, inspedion, architectural or engineering actiMties.
This exclusion applies even if the claims against any insured allege negligence or other wrongdoing in the
supeMsion, hiring, employment, training or monitoring of others by that insured, if the "occurrence" which
caused the "bodily injury/' or "property damage", or the offense which caused the "personal and adveftising
injuS', involved the rendering of or failure to render any professional seMces by or on behalf of you, or those
operating on your behalf.
The insurance afforded to any person(s) or organization(s) as an insured under this ltem 1.:
1. Applies to the extent permitted by law;
2. Applies only to the scope of coverage and the minimum limits of insurance required by the written agreement,
burt in no event exceeds either the scope of coverage or the limits of insurance provided by this Policy
3. Does not apply to any person(s) or organization(s) for any "bodily inju$', "property damage" or "personal and
advertising injun/' if any other additional insured endorsement athached to this Policy applies to such person(s)
or organization(s) with regard to the "bodily injurf', "propefi damage" or "personal and advertising injury/';
4. Applies only if the "bodily injun/' or "propefi damage" occurs, or the offense giving rise to the "personal and
advertising injuryi ' is committed, subsequent to the execution of the written agreement; and
5. Appliesonly if the written agreement isineffect atthe time the "bodilyinju$' or"property damage" occurs, orat
the time the offense giving rise to the "personal and advertising injun/' is commifted.
@ 2018 Liberty Mdual lnsurance
lncludes copyighted material of lnsurance Services ffice, lnc., with its permission.
LC 20 58 11 18 Page 3 of 4
Item 2. Blanket Additional lnsured - Grantor Of Permits
Paragraph 2. of Section ll - Who ls An lnsuredis amended to add the folloWng:
Any state, municipality or political subdivision that has issued you a permit in connection with any operations
performed by you or on your behalf, or in connection with premises you owr, rent or control, and to which this
insurance applies, burt only to the extent that you are required to proVde additional insured status to the state,
municipality or political subdiMsion as a condition of receiving and maintaining the permit. Such state, municipality or
political subdivision that has issued you a permit is an insured only with respect to their liability as grantor of such
permitto you.
However, with respect to the state, municipality or political subdivision:
1. Coverage will be no broaderthan required; and
2. Limits of insurance will not exceed the minimum limits of insurance required as a condition for receiving or
maintaining the permit;
blt neither the scope of coverage nor the limits of insurance will exceed those provided bythis Policy.
This insurance does not applyto:
1. "Bodily injur/', "property damage" or "personal and advertising injun/' arising or.ft of operations performed for
the state, municipality or political subdivision;
2. Any "bodily injun/' or "propeft5l damage" included within the "products-completed operations hazard", except
when required bywritten agreement initiated priorto loss; or
3. "Bodily injut'', "properly damage" or "personal and advertising injuryi', unless negligently caused, in whole or in
part, byyou orthose acting onyour behalf.
Item 3. Other lnsurance Amendment
lf you are obligated under a written agreement to provide liability insurance on a primary, excess, contingent, or any
other basis for any person(s) or organization(s) that qualifies as an additional insured on this Policy, this Policy will
apply solely on the basis required by such written agreement and Paragraph 4. Other Insurance of Section lV -
Commercial General Liability Conditions will not apply. Where the applicable wriften agreement does not specify
on what basis the liability insurance will apply, the proMsions of Paragraph 4. Other lnsurance of Section lV -
Commercial General Liability Conditions will apply. However, this insurance is excess over any other insurance
awilable to the additional insured for which it is also covered as an additional insured for the same "occurrence",
claim or "suit".
O 2018 Liberty Mutual lnsurance
lncludes copyighted material of lnsurance Services ffice, lnc., with its permission.
LC 20 s8 11 18 Page 4 of 4
This page has,been left blank intentionally
Policy Number AS2-291 - 4541 34-031
lssued by Liberty Mutual Fire lnsurance Co.
This endorsement modifies insurance provided under the following:
BUSINESS AUTO COVERAGE FORM
t.
il.
ilt.
tv.
V.
vt.
vil.
vilt.
tx.
X.
xt.
xil.
xill.
XIV.
XV.
XVI.
XVII.
XVIII
XIX.
XX.
XXI.
XXII.
XXIII
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
WASHINGTON AUTO ENHANCEMENT ENDORSEMENT
Newly Acquired or Formed Organizations
Employees as lnsureds
Lessor - Additional lnsured and Loss Payee
Supplementary Payments - lncreased Limits
Fellow Employee Coverage
Personal Property of Others
Additional Transportation Expense and Cost to Recover Stolen Auto
Airbag Coverage
Tapes, Records and Discs Coverage
Physical Damage Deductible - Single Deductible
Physical Damage Deductible - Glass
Physical Damage Deductible - Vehicle Tracking System
Duties in Event of Accident, Claim, Suit or Loss
Unintentional Failure to Disclose Hazards
Worldwide Liability Coverage - Hired and Nonowned Autos
Hired Auto Physical Damage
Auto Medical Payments Coverage lncreased Limits
Drive Other Car Coverage - Broadened Coverage for Designated lndividuals
Rental Reimbursement Coverage
Notice of Cancellation or Nonrenewal
Loan/Lease Payoff Coverage
Limited Mexico Coverage
Waiver of Subrogation
I. NEWLY ACQUIRED OR FORMED ORGANIZATIONS
Throughout this policy, the words "you" and "your" also refer to any organization you newly acquire or form,
other than a partnership or joint venture, and over which you maintain ownership of more than 50 percent
interest, provided:
A. There is no similar insurance available to that organization;
B. Unless you notify us to add coverage to your policy, the coverage under this provision is afforded only
until:
1. The 90th day after you acquire or form the organization; or
2. The end of the policy period,
whichever is earlier; and
C. The coverage does not apply to an "accident" which occurred before you acquired or formed the
organization.
a 2017 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., with its permission
AC 84 94 11 17 Page 1 of 10
II. EMPLOYEES AS INSUREDS
Paragraph A.1. Who ls An lnsured of SEGTION ll - COVERED AUTOS LIABILITY COVERAGE is
amended to add the following:
Your "employee" is an "insured" while using with your permission a covered "auto" you do not own, hire or
borrow in your business or your personal affairs.
III. LESSOR - ADDITIONAL INSURED AND LOSS PAYEE
A. Any "leased auto" will be considered an "auto" you own and not an "auto" you hire or borrow. The
coverages provided under this section apply to any "leased auto" until the expiration date of this policy or
until the lessor or his or her agent takes possession of the "leased auto" whichever occurs first.
B. For any "leased auto" that is a covered "auto" under SECTION ll - COVERED AUTOS LIABILITY
COVERAGE, Paragraph A.1. Who ls An lnsured provision is changed to include as an "insured" the
lessor of the "leased auto". However, the lessor is an "insured" only for "bodily injury" or "property
damage" resulting from the acts or omissions by:
1. You.
2. Any of your "employees" or agents; or
3. Any person, except the lessor or any "employee" or agent of the lessor. operating a "leased auto"
with the permission of any of the above.
C. Loss Payee Clause
1, We will pay. as interests may appear, you and the lessor of the "leased auto" for "loss" to the covered
"leased auto".
2. The insurance covers the interest of the lessor of the "leased auto" unless the "loss" results from
fraudulent acts or omissions on your part.
3. lf we make any payment to the lessor of a "leased auto", we will obtain his or her rights against any
other party.
D. Cancellation
1. lf we cancel the policy, we will mail notice to the lessor in accordance with the Cancellation Common
Policy Condition.
2. lf you cancel the policy, we will mail notice to the lessor
3. Cancellation ends this agreement
E. The lessor is not liable for payment of your premiums
F. For purposes of this endorsement, the following definitions apply
"Leased auto" means an "auto" which you lease for a period of six months or longer for use in your
business, including any "temporary substitute" of such "leased auto".
"Temporary substitute" means an "auto" that is furnished as a substitute for a covered "auto" when the
covered "auto" is out of service because of its breakdown, repair, servicing, "loss" or destruction.
@ 2017 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., with its permission.
AC849411 17 Page 2 of 10
IV. SUPPLEMENTARY PAYMENTS. INCREASED LIMITS
Subparagraphs A.2.a.(2) and A.2.a.(4) of SECTION ll - COVERED AUTOS LIABILITY COVERAGE are
deleted and replaced by the following:
(2) Up to $3,000 for cost of bail bonds (including bonds for related traffic law violations) required because of
an "accident" we cover. We do not have to furnish these bonds.
(4) All reasonable expenses incurred by the "insured" at our request, including actual loss of earnings up to
$500 a day because of time off from work.
V. FELLOW EMPLOYEE COVERAGE
A. Exclusion 8.5. of SECTION ll - COVERED AUTOS LIABILITY COVERAGE does not apply.
B. For the purpose of Fellow Employee Coverage only, Paragraph 8.5. of SECTION lV - BUSINESS AUTO
CONDITIONS is changed as follows:
This Fellow Employee Coverage is excess over any other collectible insurance.
VI. PERSONAL PROPERTY OF OTHERS
Exclusion 6. in SEGTION ll- COVERED AUTOS LIABILITY COVERAGE for a covered "auto" is amended to
add the following:
This exclusion does not apply to "property damage" or "covered pollution cost or expense" involving "personal
property" of your "employees" or others while such property is carried by the covered "auto". The Limit of
lnsurance for this coverage is $5,000 per "accident". Payment under this coverage does not increase the
Limit of lnsurance.
For the purpose of this section of this endorsement, "personal property" is defined as any property that is not
used in the individual's trade or business or held for the production or collection of income.
VII. ADDITIONAL TRANSPORTATION EXPENSE AND COST TO RECOVER STOLEN AUTO .
A. Paragraph A.4.a. of SECTION lll - PHYSICAL DAMAGE COVERAGE is amended as follows:
The amount we will pay is increased to $50 per day and to a maximum limit of $1,000.
B. Paragraph A.4.a. of SECTION lll - PHYSICAL DAMAGE COVERAGE is amended to add the following:
lf your business is shown in the Declarations as something other than an auto dealership, we will also
pay up to $1,000 for reasonable and necessary costs incurred by you to return a stolen covered "auto"
from the place where it is recovered to its usual garaging location.
VIII. AIRBAG COVERAGE
Exclusion B.3.a. in SECTION lll - PHYSICAL DAMAGE COVERAGE is amended to add the following
This exclusion does not apply to the accidental discharge of an airbag
IX. TAPES, RECORDS AND DISCS COVERAGE
Exclusion 8.4.a. of SECTION lll - PHYSICAL DAMAGE COVERAGE is deleted and replaced by the
following:
a. Tapes, records, discs or other similar audio, visual or data electronic devices designed for use with audio,
visual or data electronic equipment except when the tapes, records, discs or other similar audio, visual or
data electronic devices:
@ 2017 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., with its permission
AC849411 17 Page 3 of 10
(1) Are your property or that of a family member; and
(2) Are in a covered "auto" at the time of "loss".
The most we will pay for "loss" is $200. No Physical Damage Coverage deductible applies to this
coverage.
X. PHYSICAL DAMAGE DEDUCTIBLE. SINGLE DEDUCTIBLE
Paragraph D. in SECTION lll- PHYSICAL DAMAGE COVERAGE is deleted and replaced by the following:
D. Deductible
For each covered "auto", our obligation to pay for, repair, return or replace damaged or stolen property
will be reduced by the applicable deductible shown in the Declarations. Any Comprehensive Coverage
deductible shown in the Declarations does not apply to "loss" caused by fire or lightning.
When two or more covered "autos" sustain "loss" in the same collision, the total of all the "loss" for all the
involved covered "autos" will be reduced by a single deductible, which will be the largest of all the
deductibles applying to all such covered "autos".
XI. PHYSICAL DAMAGE DEDUCTIBLE - GLASS
Paragraph D. in SECTION lll- PHYSICAL DAMAGE COVERAGE is amended to add the following
No deductible applies to "loss" to glass if you elect to patch or repair it rather than replace it.
XII. PHYSICAL DAMAGE DEDUCTIBLE. VEHICLE TRACKING SYSTEM
Paragraph D. in SECTION lll- PHYSICAL DAMAGE COVERAGE is amended to add:
Any Comprehensive Coverage Deductible shown in the Declarations will be reduced by 50% for any "loss"
caused by theft if the vehicle is equipped with a vehicle tracking device such as a radio tracking device or a
global positioning device and that device was the method of recovery of the vehicle.
XIII. DUTIES IN EVENT OF ACCIDENT, CLAIM, SUIT OR LOSS
Subparagraphs A.2.a. and A.2.b. of SEGTION lV- BUSINESS AUTO CONDITIONS are changed to:
a. ln the event of "accident", claim, "suit" or "loss", your insurance manager or any other person you
designate must notify us as soon as reasonably possible of such "accident", claim, "suit" or "loss". Such
notice must include:
(1) How, when and where the "accident" or "loss" occurred;
(2) The "insured's" name and address; and
(3) To the extent possible, the names and addresses of any injured persons and witnesses.
Knowledge of an "accident", claim, "suit" or "loss" by your agent, servant or "employee" shall not be
considered knowledge by you unless you, your insurance manager or any other person you designate
has received notice of the "accident", claim, "suit" or "loss" from your agent, servant or "employee".
b. Additionally, you and any other involved "insured" must:
(1) Assume no obligation, make no payment or incur no expense without our consent, except at the
"insured's" own cost.
a 2017 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., with its permission
AC849411 17 Page 4 of 10
(2) lmmediately send us copies of any request, demand, order, notice, summons or legal paper received
concerning the claim or "suit".
(3) Cooperate with us in the investigation or settlement of the claim or defense against the "suit".
(4) Authorize us to obtain medical records or other pertinent information.
(5) Submit to examination, at our expense, by physicians of our choice, as often as we reasonably
require.
XIV. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS
Paragraph B.2.in SECTION lV - BUSINESS AUTO CONDITIONS is amended to add the following:
Any unintentional failure to disclose all exposures or hazards existing as of the effective date of the Business
Auto Coverage Form or at any time during the policy period will not invalidate or adversely affect the
coverage for such exposure or hazard. However, you must report the undisclosed exposure or hazard to us
as soon as reasonably possible after its discovery.
XV. WORLDWIDE LIABILITY COVERAGE. HIRED AND NONOWNED AUTOS
Condition B.7. in SECTION lV - BUSINESS AUTO CONDITIONS is amended to add the following:
For "accidents" resulting from the use or operation of covered "autos" you do not own, the coverage territory
means all parts of the world subject to the following provisions:
a. lf claim is made or "suit" is brought against an "insured" outside of the United States of America, its
territories and possessions, Puerto Rico and Canada, we shall have the right, but not the duty to
investigate, negotiate, and settle or defend such claim or "suit".
lf we do not exercise that right, the "insured" shall have the duty to investigate, negotiate, and settle or
defend the claim or "suit" and we will reimburse the "insured" for the expenses reasonably incurred in
connection with the investigation, settlement or defense. Reimbursement will be paid in the currency of
the United States of America at the rate of exchange prevailing on the date of reimbursement.
The "insured" shall provide us with such information we shall reasonably request regarding such claim or
"suit" and its investigation, negotiation, and settlement or defense.
The "insured" shall not agree to any settlement of the claim or "suit" without our consent. We shall not
unreasonably withhold consent.
b. We are not licensed to write insurance outside of the United States of America, its territories or
possessions, Puerto Rico and Canada.
We will not furnish certificates of insurance or other evidence of insurance you may need for the purpose
of complying with the laws of other countries relating to auto insurance.
Failure to comply with the auto insurance laws of other countries may result in fines or penalties. This
insurance does not apply to such fines or penalties.
XVI. HIRED AUTO PHYSICAL DAMAGE
lf no deductibles are shown in the Declarations for Physical Damage Coverage for Hired or Borrowed Autos,
the following will apply:
A. We will pay for "loss" under Comprehensive and Collision coverages to a covered "auto" of the private
passenger type hired without an operator for use in your business
@ 2017 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., with its permission.
AC849411 17 Page 5 of 10
1, The most we will pay for coverage afforded by this endorsement is the lesser of
a. The actual cost to repair or replace such covered "auto" with other property of like kind and
quality; or
b. The actual cash value of such covered "auto" at the time of the "loss"
2. An adustment for depreciation and physical condition will be made in determining actual cash value
in the event of a total "loss".
3. We may deduct for betterment for parts normally subject to repair and replacement during the useful
life of the "auto". ln this event, deductions shall be limited to the lesser of:
a. An amount equal to the proportion that the expired life of the part to be repaired or replaced
bears to the normal useful life of that paru or
b. The amount which the resale value of the "auto" is increased from the repair or replacement.
B. For each covered "auto", our obligation to pay for, repair, return or replace the covered "auto" will be
reduced by any deductible shown in the Declarations that applies to private passenger "autos" that you
own. lf no applicable deductible is shown in the Declarations, the deductible will be $250.
lf the Declarations show other deductibles for Physical Damage Coverages for Hired or Borrowed Autos,
this Section XVI of this endorsement does not apply.
C. Paragraph A.4.b. of SECTION lll - PHYSICAL DAMAGE COVERAGE is replaced by the following:
b. Loss of Use Expenses
For Hired Auto Physical Damage provided by this endorsement, we will pay expenses for which an
"insured" becomes legally responsible to pay for loss of use of a private passenger vehicle rented or
hired without a driver, under a written rental contract or agreement. We will pay for loss of use
expenses caused by:
(1) Other than collision only if the Declarations indicate that Comprehensive Coverage is provided for
any covered "auto";
(2) Specified Causes of Loss only if the Declarations indicate that Specified Causes of Loss
Coverage is provided for any covered "auto"; or
(3) Collision only if the Declarations indicate that Collision Coverage is provided for any covered
"auto".
However, the most we will pay under this coverage is $30 per day, subject to a maximum of $900.
XVII, AUTO MEDICAL PAYMENTS COVERAGE.INCREASED LIMITS
For any covered "loss", the Limit of lnsurance for Auto Medical Payments will be double the limit shown in the
Declarations if the "insured" was wearing a seat belt at the time of the "accident". This is the maximum
amount we will pay for all covered medical expenses, regardless of the number of covered "autos",
"insureds", premiums paid, claims made, or vehicles involved in the "accident".
lf no limit of insurance for Auto Medical Payments is shown on the Declarations, this paragraph Section XVll
of this endorsement does not apply.
XVIII. DRIVE OTHER CAR COVERAGE. BROADENED COVERAGE FOR DESIGNATED INDIVIDUALS
A. This endorsement amends only those coverages indicated with an "X" in the Drive Other Car section of
the Schedule to this endorsement.
@ 2017 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., with its permission
AC849411 17 Page 6 of 10
B. SECTION ll - COVERED AUTOS LIABILITY COVERAGE is amended as follows:
1. Any "auto" you don't own, hire or borrow is a covered "auto" for Liability Coverage while being
used by any individual named in the Drive Other Car section of the Schedule to this endorsement
or by his or her spouse while a resident of the same household except:
a. Any "auto" owned by that individual or by any member of his or her household; or
b. Any "auto" used by that individual or his or her spouse while working in a business of selling,
servicing, repairing or parking "autos".
2. The following is added to Who ls An lnsured:
Any individual named in the Drive Other Car section of the Schedule to this endorsement and his or
her spouse, while a resident of the same household, are "insureds" while using any covered "auto"
described in Paraqraph B.1. of this endorsement.
C. Auto Medical Payments, Uninsured Motorist, and Underinsured Motorist Coverages are amended as
follows:
The following is added to Who ls An lnsured:
Any individual named in the Drive Other Car section of the Schedule to this endorsement and his or her
"family members" are "insured" while "occupying" or while a pedestrian when struck by any "auto" you
don't own except:
Any "auto" owned by that individual or by any "family member".
D. SECTION lll- PHYSICAL DAMAGE COVERAGE is changed as follows:
Any private passenger type "auto" you don't own, hire or borrow is a covered "auto" while in the care,
custody or control of any individual named in the Drive Other Car section of the Schedule to this
endorsement or his or her spouse while a resident of the same household except:
1. Any "auto" owned by that individual or by any member of his or her household; or
2. Any "auto" used by that individual or his or her spouse while working in a business of selling,
servicing, repairing or parking "autos".
E. For purposes of this endorsement, SECTION V - DEFINITIONS is amended to add the following:
"Family member" means a person related to the individual named in the Drive Other Car section of the
Schedule to this endorsement by blood, marriage or adoption who is a resident of the individual's
household, including a ward or foster child.
XIX. RENTAL REIMBURSEMENT COVERAGE
A. For any owned covered "auto" for which Collision and Comprehensive Coverages are provided, we will
pay for rental reimbursement expenses incurred by you for the rental of an "auto" because of a covered
physical damage "loss" to an owned covered "auto". Such payment applies in addition to the otherwise
applicable amount of physical damage coverage you have on a covered "auto". No deductibles apply to
this coverage.
B. We will pay only for those expenses incurred during the policy period beginning 24 hours after the "loss"
and ending with the earlier of the return or repair of the covered "auto", or the exhaustion of the coverage
limit.
C. Our payment is limited to the lesser of the following amounts:
1. Necessary and actual expenses incurred; or
AC 84 94 11 17 a 2017 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., with its permission
Page 7 of '10
2. $30 per day with a maximum of $900 in any one period.
D. This coverage does not apply:
1. While there are spare or reserve "autos" available to you for your operations; or
2. lf coverage is provided by another endorsement attached to this policy.
E. lf a covered "loss" results from the total theft of a covered "auto" of the private passenger type, we will
pay under this coverage only that amount of your rental reimbursement expenses which is not already
provided for under Paragraph A.4. Coverage Extensions of SECTION lll - PHYSICAL DAMAGE
COVERAGE of the Business Auto Coverage Form or Section Vll of this endorsement.
XX. NOTICE OF CANCELLATION OR NONRENEWAL
A. Paragraph A.2. of rhe COMMON POLICY CONDITIONS is changed to:
2. We may cancel or non-renew this policy by mailing written notice of cancellation or non-renewal to
the Named lnsured, and to any name(s) and address(es) shown in the Cancellation and Non-renewal
Schedule:
a. For reasons of non-payment, the greater of:
(1) 10 days; or
(2) The number of days specified in any other Cancellation Condition attached to this policy; or
b. For reasons other than non-payment, the greater of:
(1) 60 days;
(2) The number of days shown in the Cancellation and Non-renewal Schedule; or
(3) The number of days specified in any other Cancellation Condition attached to this policy,
prior to the effective date of the cancellation or non-renewal.
B. All orher rerms of Paragraph A. of the COMMON POLICY CONDITIONS, and any amendmenrs rhereto,
remain in full force and effect.
XXI. LOAN/LEASE PAYOFF COVERAGE
The following is added to Paragraph C. Limits Of lnsurance of SECTION lll - PHYSICAL DAMAGE
COVERAGE:
ln the event of a total "loss" to a covered "auto" of the private passenger type shown in the schedule or
declarations for which Collision and Comprehensive Coverage apply, we will pay any unpaid amount due on
the lease or loan for that covered "auto", less:
1. The amount paid under the PHYSICAL DAMAGE COVERAGE SECTION of the policy; and
2. Any:
a. Overdue lease/loan payments at the time of the "loss";
b. Financial penalties imposed under a lease for excessive use, abnormal wear and tear or high
mileage;
c. Security deposits not returned by the lessor;
@ 2017 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., with its permission
AC849411 17 Page B of 10
d. Costs for extended warranties, Credit Life lnsurance, Health, Accident or Disability
purchased with the loan or lease; and
e. Carry-over balances from previous loans or leases.
This coverage is limited to a maximum of $1,500 for each covered "auto".
XXII.LIMITED MEXICO COVERAGE
lnsurance
WARNING
AUTO ACCIDENTS IN MEXICO ARE SUBJECT TO THE LAWS OF MEXICO ONLY - NOT THE LAWS OF THE
UNITED STATES OF AMERICA. THE REPUBLIC OF MEXICO CONSIDERS ANY AUTO ACCIDENT A
CRIMINAL OFFENSE AS WELL AS A CIVIL MATTER.
IN SOME CASES THE COVERAGE PROVIDED UNDER THIS ENDORSEMENT MAY NOT BE RECOGNIZED
BY THE MEXICAN AUTHORITIES AND WE MAY NOT BE ALLOWED TO IMPLEMENT THIS COVERAGE AT
ALL IN MEXICO. YOU SHOULD CONSIDER PURCHASING AUTO COVERAGE FROM A LICENSED
MEXICAN INSURANCE COMPANY BEFORE DRIVING INTO MEXICO.
THIS ENDORSEMENT DOES NOT APPLY TO ACCIDENTS OR LOSSES WHICH OCCUR BEYOND 25 MILES
FROM THE BOUNDARY OF THE UNITED STATES OF AMERICA.
A. Coverage
1. Paragraph B.7. of SECTION lV - BUSINESS AUTO CONDITIONS is amended by the addition of the
following:
The coverage territory is extended to include Mexico but only if all of the following criteria are met:
a. The "accidents" or "loss" occurs within 25 miles of the United States border; and
b. While on a trip into Mexico for 10 days or less.
2. For coverage provided by this section of the endorsement, Paragraph 8.5. Other lnsurance in
SECTION lV - BUSINESS AUTO CONDITIONS is replaced by the following:
The insurance provided by this endorsement will be excess over any other collectible insurance.
B. Physical Damage Coverage is amended by the addition of the following:
lf a "loss" to a covered "auto" occurs in Mexico, we will pay for such "loss" in the United States. lf the
covered "auto" must be repaired in Mexico in order to be driven, we will not pay more than the actual
cash value of such "loss" at the nearest United States point where the repairs can be made.
C. Additional Exclusions
The following additional exclusions are added:
This insurance does not apply:
1. lf the covered "auto" is not principally garaged and principally used in the United States.
2. To any "insured" who is not a resident of the United States.
XXIII. WAIVER OF SUBROGATION
Paragraph A.5. in SECTION lV - BUSINESS AUTO CONDITIONS does not apply to any person or
organization where the Named lnsured has agreed, by written contract executed prior to the date of
"accident", to waive rights of recovery against such person or organization.
@ 2017 Liberty Mutual lnsurance
lncludes copyrighted material of lnsurance Services Office, lnc., with its permission.
AC 84 94 11 17 Page 9 of 10
Premium
Liability lncluded
Physical Damage
Total Premium
lncluded
lncluded
Schedule
LIAB MP UMXVll. Drive Other Car
Name of lndividual
Not Applicable
XX. Notice of Cancellation or Nonrenewal
Name and Address
UIM COMP COLL
Number ol Days
30
rncrudes copyrishted '","','3lJ/'*r?fil#E:ij:::'51fi!3, ,n,., with irs permission
AC849411 17 Page 10 of 10
POLICY NUMBER: AS2-291 -454734-031 COMMERCIAL AUTO
cA 20 70 10 13
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
COVERAGE FOR CERTAIN OPERATIONS
IN CONNECTION WITH RAILROADS
This endorsement modifies insurance provided under the following
AUTO DEALERS COVERAGE FORM
BUSINESS AUTO COVERAGE FORM
MOTOR CARRIER COVERAGE FORM
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless
modified by the endorsement.
SCHEDULE
Scheduled Railroad Designated Job Site
Where required by written contract Where required by written contract
lnformation required to complete this Schedule, if not shown above, will be shown in the Declarations.
With respect to the use of a covered "auto" in
operations for or affecting a railroad designated in the
Schedule at a Designated Job Site, the two exceptions
contained in the definition of "insured contract" relating
to construction or demolition operations performed
within 50 feet of a railroad do not apply.
cA 20 70 10 13 @ lnsurance Services Office, lnc., 201 1 Page 1 of 1
Policy Number: AS2 - z9i.- 4s4734 - 03 l-
lssued by: Li-berty Mutual- Fire rnsurance Co
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
DESIGNATED INSURED . NONCONTRIBUTING
This endorsement modifies insurance provided under the following
BUSINESS AUTO COVERAGE FORM
GARAGE COVERAGE FORM
MOTOR CARRIERS COVERAGE FORM
TRUCKERS COVERAGE FORM
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless
modified by this endorsement.
This endorsement identifies person(s) or organization(s) who are "insureds" under the Who ls An lnsured
Provision of the Coverage Form. This endorsement does not alter coverage provided in the Coverage form.
Schedule
Name of Person(s) or Organizations(s):
Any person or organization whom you agreed in writing as an additional insured,but -on1y for the"coverage and miirimum-l-imits of insuiance required by thewritten aqreement, and in no evenL to exceed either the scope of coverage or thelimits of"insuran6e provided in this policy.
Regarding Designated Contract or Proiect:
Each person or organization shown in the Schedule of this endorsement is an "insured" for Liability Coverage, but
only to the extent that person or organization qualifies as an "insured" under the Who ls An lnsured Provision
contained in Section ll of the Coverage Form.
The following is added to the Other lnsurance Condition:
lf you have agreed in a written agreement that this policy will be primary and without right of contribution
from any insurance in force for an Additional lnsured for liability arising out of your operations, and the
agreement was executed prior to the "bodily injury" or "property damage", then this insurance will be
primary and we will not seek contribution from such insurance.
@ 2010, Liberty Mutual Group of Companies. All rights reserved.
lncludes copyrighted material of lnsurance Services Office, lnc.,
with its permission.
AC 84 23 08 11 Page 1 of 1
POLICY N UMBER: AS.2-Z,91 - 454734-03 1 COMMERCIAL AUTO
cA 20 48 10 13
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
DESIGNATED INSURED FOR
COVERED AUTOS LIABILITY COVERAGE
This endorsement modifies insurance provided under the following:
AUTO DEALERS COVERAGE FORM
BUSINESS AUTO COVERAGE FORM
MOTOR CARRIER COVERAGE FORM
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless
modified by the endorsement.
This endorsement identifies person(s) or organization(s) who are "insureds" for Covered Autos Liability Coverage
under the Who ls An lnsured provision of the Coverage Form. This endorsement does not alter coverage
provided in the Coverage Form.
SCHEDULE
Name Of Person(s) Or Organization(s):
Any person or organization whom you have agreed in writing to add as an additional insured, but only to
coverage and minimum limits of insurance required by the written agreement, and in no event to exceed either
the scope of coverage or the limits of insurance provided in this policy.
lnformation required to complete this Schedule, if not shown above, will be shown in the Declarations.
Each person or organization shown in the Schedule is
an "insured" for Covered Autos LiabilityCoverage, but
only to the extentthat person or organization qualifies
as an "insured" under the Who ls An lnsured provision
contained in Paragraph A.1. of Section ll - Covered
Autos Liability Coverage in the Business Auto and
Motor Carrier Coverage Forms and Paragraph D.2. of
Section I - Covered Autos Coverages of the Auto
Dealers Coverage Form.
cA 20 48 10 13 @ lnsurance Services Office, lnc., 201 1 Page 1 of 1
This page has.been left blank intentionally
Rock Creek Culvert Replacement/Lincoln 1 June 3, 2021
Project Number: 13-3007.5
KENT SPECIAL PROVISIONS
TABLE OF CONTENTS
PAGE
DIVISION 1 GENERAL REQUIREMENTS ..................................... 1-1
1-01 Definitions and Terms ...................................................... 1-1
1-02 Bid Procedures and Conditions .......................................... 1-2
1-03 Award and Execution of Contract....................................... 1-5
1-04 Scope of the Work .......................................................... 1-5
1-05 Control of Work .............................................................. 1-8
1-06 Control of Material .......................................................... 1-16
1-07 Legal Relations and Responsibilities to the Public ................. 1-19
1-08 Prosecution and Progress ................................................. 1-25
1-09 Measurement and Payment .............................................. 1-30
1-10 Temporary Traffic Control ................................................ 1-31
DIVISION 2 EARTHWORK .......................................................... 2-1
2-01 Clearing, Grubbing, and Roadside Cleanup ......................... 2-1
2-02 Removal of Structures and Obstructions ............................. 2-2
2-03 Roadway Excavation and Embankment .............................. 2-7
2-06 Subgrade Preparation ...................................................... 2-10
2-12 Construction Geosynthetic ................................................ 2-11
DIVISION 4 BASES .................................................................... 4-1
4-03 Gravel Borrow ................................................................ 4-1
4-04 Ballast and Crushed Surfacing .......................................... 4-1
DIVISION 5 SURFACE TREATMENTS AND PAVEMENTS .............. 5-1
5-02 Bituminous Surface Treatment .......................................... 5-1
5-04 Hot Mix Asphalt .............................................................. 5-1
DIVISION 6 STRUCTURES ......................................................... 6-1
6-02 Concrete Structures ........................................................ 6-1
DIVISION 7 DRAINAGE STRUCTURES, STORM SEWERS, SANITARY
SEWERS, WATER MAINS, AND CONDUITS .............. 7-1
7-05 Temporary Stream Diversion ............................................ 7-1
7-08 General Pipe Installation Requirements .............................. 7-9
7-09 Water Mains ................................................................... 7-14
7-14 Hydrants ....................................................................... 7-28
7-17 Sanitary Sewers ............................................................. 7-31
DIVISION 8 MISCELLANEOUS CONSTRUCTION ......................... 8-1
8-01 Erosion Control and Water Pollution Control ........................ 8-1
8-02 Roadside Restoration ....................................................... 8-5
8-10 Guide Posts .................................................................... 8-12
8-11 Guard Rail ..................................................................... 8-13
Rock Creek Culvert Replacement/Lincoln 2 June 3, 2021
Project Number: 13-3007.5
TABLE OF CONTENTS
PAGE
DIVISION 8 MISCELLANEOUS CONSTRUCTION
8-15 Riprap ........................................................................... 8-13
8-19 Streambed Gravel ........................................................... 8-15
8-20 Illumination, Traffic Signal Systems, Intelligent Transportation
Systems, and Electrical .................................................... 8-16
8-22 Pavement Marking .......................................................... 8-17
8-26 Anchored Logs and Habitat Logs ....................................... 8-19
8-28 Pothole Utilities .............................................................. 8-20
8-30 Resolution of Utility Conflicts ............................................ 8-22
8-31 Field Trailer .................................................................... 8-23
DIVISION 9 MATERIALS ............................................................ 9-1
9-03 Aggregates .................................................................... 9-1
9-13 Riprap, Quarry Spalls, Slope Protection, and Rock for
Erosion and Scour Protection and Rock Walls ...................... 9-3
9-14 Erosion Control and Roadside Planting ............................... 9-3
9-16 Fence and Guardrail ........................................................ 9-7
9-28 Signing Materials and Fabrication ...................................... 9-7
9-30 Water Distribution Materials ............................................. 9-8
APPENDIX A SCWSD ROCK CREEK CULVERT CROSSING (02-2020S)
SPECIFICIATION – SUPPLEMENTAL CRITERIA ...... A-1
APPENDIX B WASHINGTON STATE DEPARTMENT OF FISH AND
WILDLIFE HPA ....................................................... A-2
APPENDIX C UNITED STATES ARMY CORPS OF ENGINEERS
NATIONWIDE PERMIT ........................................... A-3
APPENDIX D TRAFFIC CONTROL PLANS ..................................... A-4
APPENDIX E PREVAILING WAGE RATES ..................................... A-5
APPENDIX F GEOTECHNICAL REPORT ........................................ A-6
Rock Creek Culvert Replacement/Lincoln 1 - 1 June 3, 2021
Project Number: 13-3007.5
KENT SPECIAL PROVISIONS
The Kent Special Provisions (“Kent Special Provisions” or “KSP”) modify and supersede
any conflicting provisions of the 2021 Standard Specifications for Road, Bridge, and
Municipal Construction, as prepared by the Washington State Department of
Transportation and the Washington State Chapter of the American Public Works
Association, including all published amendments issued by those organizations
(“WSDOT Standard Specifications”). Otherwise all provisions of the WSDOT Standard
Specifications shall apply. All references in the WSDOT Standard Specifications to the
State of Washington, its various departments or directors, or to the contracting
agency, shall be revised to include the City and/or City Engineer, except for references
to State statutes or regulations. Finally, all of these documents are a part of this
contract.
DIVISION 1 – GENERAL REQUIREMENTS
1-01 DEFINITIONS AND TERMS
SECTION 1-01.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
1-01.1 General
When these Kent Special Provisions make reference to a “Section,” for
example, “in accordance with Section 1-01,” the reference is to the
WSDOT Standard Specifications as modified by these Kent Special
Provisions.
SECTION 1-01.2(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
1-01.2(2) Items of Work and Units of Measurement
EA Each
Eq. Adj. Equitable Adjustment
FA Force Account
HR Hour
M GAL Thousand gallons
NIC Not In Contract
SF Square Feet
SECTION 1-01.3, “CONTRACT” DEFINITION, IS DELETED AND REPLACED
WITH THE FOLLOWING:
1-01.3 Definitions
Contract
The written agreement between the Contracting Agency and the
Contractor. It describes, among other things:
1. What work will be done, and by when;
2. Who provides labor and materials; and
Rock Creek Culvert Replacement/Lincoln 1 - 2 June 3, 2021
Project Number: 13-3007.5
3. How Contractors will be paid.
The Contract includes the Contract (agreement) Form, Bidder’s
completed Proposal Form, Kent Special Provisions, Contract Provisions,
Contract Plans, WSDOT Standard Specifications (also including
amendments to the Standard Specifications issued by WSDOT as of the
later date of bid advertisement or any subsequent addenda), Kent
Standard Plans, Addenda, various certifications and affidavits,
supplemental agreements, change orders, and subsurface boring logs
(if any).
Also incorporated in the Contract by reference are:
1. Standard Plans (M21-01) for Road, Bridge and Municipal
Construction as prepared by the Washington State Department of
Transportation and the American Public Works Association, current
edition;
2. Manual on Uniform Traffic Control Devices for Streets and
Highways, current edition, and;
3. American Water Works Association Standards, current edition;
4. The current edition of the “National Electrical Code.”
Responsibility for obtaining these publications rests with the Contractor.
SECTION 1-01.3, “DEFINITIONS” IS SUPPLEMENTED BY ADDING THE
FOLLOWING DEFINITION:
Incidental Work
The terms “incidental to the project,” “incidental to the involved bid
item(s),” etc., as used in the Contract shall mean that the Contractor is
required to complete the specified work and the cost of such work shall
be included in the unit contract prices of other bid items as specified in
Section 1-04.1 (Intent of the Contract). No additional payment will be
made.
1-02 BID PROCEDURES AND CONDITIONS
SECTION 1-02.1 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-02.1 Qualification of Bidders
Bidders shall be qualified by ability, experience, financing, equipment,
and organization to do the work called for in the Contract. The City
reserves the right to take any action it deems necessary to ascertain
the ability of the Bidder to perform the work satisfactorily. This action
includes the City’s review of the qualification information in the bid
documents. The City will use this qualification data in its decision to
determine whether the lowest responsive bidder is also responsible and
able to perform the contract work. If the City determines that the
lowest bidder is not the lowest responsive and responsible bidder, the
City reserves its unqualified right to reject that bid and award the
Rock Creek Culvert Replacement/Lincoln 1 - 3 June 3, 2021
Project Number: 13-3007.5
contract to the next lowest bidder that the City, in its sole judgment,
determines is also responsible and able to perform the contract work
(the “lowest responsive and responsible bidder”).
SECTION 1-02.2 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-02.2 Plans and Specifications
Upon awarding the Contract, the City shall supply to the Contractor, for
its own use, up to ten (10) copies of the plans and specifications. If the
Contractor requests more than ten (10) copies, the City may require
the Contractor to purchase the additional sets.
SECTION 1-02.5 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-02.5 Proposal Forms
Prospective bidders may obtain Bid Documents including a “Bid
Proposal” for the advertised project by downloading at no charge at
KentWA.gov/doing-business/bids-procurement; however, a prospective
bidder remains responsible to obtain Bid Documents, even if unable to
download all or any part of the documents, whether or not inability to
access is caused by the bidder’s or the City’s technology.
SECTION 1-02.6 IS REVISED BY DELETING THE THIRD PARAGRAPH AND
REPLACING WITH THE FOLLOWING:
1-02.6 Preparation of Proposal
It is the Bidder’s sole responsibility to obtain and incorporate all issued
addenda into the bid. In the space provided on the Proposal Signature
Page, the Bidder shall confirm that all Addenda have been received. All
blanks in the proposal forms must be appropriately filled in.
SECTION 1-02.6 IS SUPPLEMENTED BY ADDING THE FOLLOWING TO THE
LAST PARAGRAPH:
Proposals must contain original signature pages. FACSIMILES OR
OTHER FORMS OF ELECTRONIC DELIVERY ARE NOT ACCEPTABLE
AND ARE CONSIDERED NON-RESPONSIVE SUBMITTALS.
SECTION 1-02.7 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-02.7 Bid Deposit
A deposit of at least 5 percent of the total Bid shall accompany each
Bid. This deposit may be cash, cashier’s check, or a proposal bond
(Surety bond). Any proposal bond shall be on the City’s bond form and
shall be signed by the Bidder and the Surety. A proposal bond shall not
be conditioned in any way to modify the minimum 5-percent required.
The Surety shall: (1) be registered with the Washington State
Insurance Commissioner, and (2) appear on the current Authorized
Rock Creek Culvert Replacement/Lincoln 1 - 4 June 3, 2021
Project Number: 13-3007.5
Insurance List in the State of Washington published by the Office of the
Insurance Commissioner.
The failure to furnish a Bid deposit of a minimum of 5 percent with the
Bid shall make the Bid nonresponsive and shall cause the Bid to be
rejected by the Contracting Agency.
SECTION 1-02.9 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-02.9 Delivery of Proposal
All bids must be sealed and delivered in accordance with the “Invitation
to Bid.” Bids must be received at the City Clerk’s office by the stated
time, regardless of delivery method, including U.S. Mail.
SECTION 1-02.10 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-02.10 Withdrawing, Revising, or Supplementing Proposal
After submitting a Bid Proposal to the Contracting Agency, the Bidder
may withdraw or revise it if:
1. The Bidder submits a written request signed by an authorized
person, and
2. The Contracting Agency receives the request before the time for
opening Bids.
The original Bid Proposal may be revised and resubmitted as the official
Bid Proposal if the Contracting Agency receives it before the time for
opening Bids.
SECTION 1-02.11 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-02.11 Combination and Multiple Proposals
No person, firm or corporation shall be allowed to make, file, or be
interested in more than one bid for the same work unless alternate bids
are specifically called for; however, a person, firm, or corporation that
has submitted a subproposal to a bidder, or that has quoted prices of
materials to a bidder is not disqualified from submitting a subproposal
or quoting prices to other bidders or from making a prime proposal.
SECTION 1-02.13 IS REVISED BY DELETING ITEM 1(a) AND REPLACING ITEM
1(a) WITH THE FOLLOWING:
1-02.13 Irregular Proposals
a. The bidder is not prequalified when so required.
SECTION 1-02.14 IS REVISED BY DELETING ITEM 3 AND REPLACING WITH
THE FOLLOWING:
Rock Creek Culvert Replacement/Lincoln 1 - 5 June 3, 2021
Project Number: 13-3007.5
1-02.14 Disqualification of Bidders
3. The bidder is not qualified for the work or to the full extent of the
bid.
1-03 AWARD AND EXECUTION OF CONTRACT
SECTION 1-03.1 IS REVISED BY INSERTING THE FOLLOWING PARAGRAPH
AFTER THE SECOND PARAGRAPH IN THAT SECTION:
1-03.1 Consideration of Bids
The City also reserves the right to include or omit any or all schedules
or alternates of the Proposal and will award the Contract to the lowest
responsive, responsible bidder based on the total bid amount, including
schedules or alternates selected by the City.
SECTION 1-03.2 IS REVISED BY REPLACING “45 CALENDAR DAYS” WITH “60
CALENDAR DAYS” RELATING TO CONTRACT AWARD OR BID REJECTION.
1-03.2 Award of Contract
SECTION 1-03.3 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-03.3 Execution of Contract
No claim for delay shall be granted to the Contractor due to its failure
to submit the required documents to the City in accordance with the
schedule provided in these Kent Special Provisions.
SECTION 1-03.7 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-03.7 Judicial Review
Any decision made by the City regarding the award and execution of
the contract or bid rejection shall be conclusive subject to the scope of
judicial review permitted under Washington State Law. Such review, if
any, shall be timely filed in the King County Superior Court, located in
Kent, Washington.
1-04 SCOPE OF THE WORK
1-04.1 Intent of the Contract
SECTION 1-04.1(2) IS DELETED AND REPLACED WITH THE FOLLOWING:
1-04.1(2) Bid Items Not Included in the Proposal
The Contractor shall include all costs of doing the work within the bid
item prices. If the contract plans, contract provisions, addenda, or any
other part of the contract require work that has no bid item price in the
proposal form, the entire cost of labor and materials required to
Rock Creek Culvert Replacement/Lincoln 1 - 6 June 3, 2021
Project Number: 13-3007.5
perform that work shall be incidental and included with the bid item
prices in the contract.
SECTION 1-04.2 IS SUPPLEMENTED BY ADDING THE WORDS, “KENT SPECIAL
PROVISIONS, KENT STANDARD PLANS” FOLLOWING THE WORDS,
“CONTRACT PROVISIONS” IN THE FIRST SENTENCE OF THE FIRST
PARAGRAPH.
SECTION 1-04.2 IS REVISED BY DELETING ITEMS 1 THROUGH 7 IN THE
SECOND PARAGRAPH AND REPLACING WITH THE FOLLOWING 8 ITEMS:
1-04.2 Coordination of Contract Documents, Plans, Special Provisions,
Specifications, and Addenda
1. Approved Change Orders
2. The Contract Agreement
3. Kent Special Provisions
4. Contract Plans
5. Amendments to WSDOT Standard Specifications
6. WSDOT Standard Specifications
7. Kent Standard Plans
8. WSDOT Standard Plans
SECTION 1-04.4 IS REVISED BY DELETING THE THIRD PARAGRAPH
(INCLUDING SUBPARAGRAPHS A AND B).
1-04.4 Changes
SECTION 1-04.4 IS REVISED BY DELETING THE FIFTH PARAGRAPH AND
REPLACING IT WITH THE FOLLOWING:
For Item 2, increases or decreases in quantity for any bid item shall be
paid at the appropriate bid item contract price, including any bid item
increase or decrease by more than 25 percent from the original planned
quantity.
SECTION 1-04.4 IS REVISED BY DELETING THE EIGHTH PARAGRAPH (NEXT
TO THE LAST PARAGRAPH) AND REPLACING WITH THE FOLLOWING:
Within 14 calendar days of delivery of the change order the Contractor
shall endorse and return the change order, request an extension of time
for endorsement or respond in accordance with Section 1-04.5. The
Contracting Agency may unilaterally process the change order if the
Contractor fails to comply with these requirements. Changes normally
noted on field stakes or variations from estimated quantities, will not
require a written change order. These changes shall be made at the
unit prices that apply. The Contractor shall respond immediately to
changes shown on field stakes without waiting for further notice.
Rock Creek Culvert Replacement/Lincoln 1 - 7 June 3, 2021
Project Number: 13-3007.5
SECTION 1-04.4(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
For items on bid Schedule III, payment or credits for changes
amounting to $25,000 or less may be made under the pay item Minor
Change in lieu of the more formal procedures for Change Orders as
outlined in the General Conditions. A Minor Change will be documented
by a Written Order for a Minor Change signed by the Contractor or by a
notation of an oral agreement. The Contractor will be provided a copy
of the completed order for a Minor Change. For the purpose of
providing a common Proposal, the Owner has entered an amount for
Minor Changes in the Proposal to become part of the total Bid by the
Contractor. However, the Owner does not warrant expressly or by
implication that the actual amount of Work will correspond to the
estimated amount in the Proposal.
SECTION 1-04.6 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-04.6 Variation in Estimated Quantities
Payment to the Contractor will be made only for the actual quantities of
Work performed and accepted in conformance with the Contract.
SECTION 1-04.9 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-04.9 Use of Private Properties
Staging and storage locations needed for the Project must be properly
permitted for that use.
Limits of construction are indicated or defined on the plans. The
Contractor shall confine all construction activities within these limits. If
a staging and storage area is shown on the plans, the City will obtain all
permits and approvals necessary for the Contractor’s use.
Whether the City does or does not provide a staging area, if the
Contractor selects its own staging and storage area(s), it is the
Contractor’s sole responsibility to obtain all necessary
permits/approvals to use the private property, specifically including,
without limitation, all permits or approvals subject to State
Environmental Policy Act, Shoreline Management Act, and critical areas
regulations. Before using any other property as a staging or storage
area (or for any other use), the Contractor shall thoroughly investigate
the property for the presence of critical areas, buffers of critical areas,
or other regulatory restrictions as defined in Kent City Code, county,
state or federal regulations, and the Contractor shall provide the City
written documentation that the property is not subject to other
regulatory requirements or that the Contractor has obtained all
necessary rights of entry, permits and approvals needed to use the
property as the Contractor intends.
Upon vacating the private property, the Contractor shall provide the
City written verification that it has obtained all releases and/or
Rock Creek Culvert Replacement/Lincoln 1 - 8 June 3, 2021
Project Number: 13-3007.5
performed all mitigation work as required by the conditions of the
permit/approval and/or agreement with the property owner.
The Contractor shall not be entitled to additional compensation or an
extension of the time of completion of the Contractor for any work
associated with the permitting, mitigation or use of private property.
SECTION 1-04.11 ITEM 2 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-04.11 Final Cleanup
2. Remove from the project all unapproved and/or unneeded material
left from grading, surfacing, paving, or temporary erosion control
measures.
1-05 CONTROL OF WORK
SECTION 1-05.4 IS REVISED BY DELETING THE LAST FOUR PARAGRAPHS.
1-05.4 Conformity With and Deviations From Plans and Stakes
SECTION 1-05.4 IS REVISED BY ADDING THE FOLLOWING PARAGRAPH
AFTER PARAGRAPH 7:
To the extent a conflict exists between the requirements of WSDOT
Section 1-05.4 and Kent Special Provision Section 1-05.8, the
requirements of KSP Section 1-05.8 will prevail.
Contractor shall have the following water appurtenances shown on the
Contract Plans staked and marked: Waterline connection points
(proposed pipe to existing pipe); Waterline fitting locations including
tees, crosses, horizontal and vertical bends, valves, hydrants, caps,
plugs, thrust blocking, permanent blow off assemblies, tapping sleeve
and valve assemblies, reducers and other fittings noted in the Contract
plans; Offset points to establish line and grade for water main between
fitting locations including water main pipe deflection points.
SECTION 1-05.7 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
1-05.7 Removal of Defective and Unauthorized Work
If the Contractor fails to remedy defective or unauthorized work within
the time specified by the Engineer, or fails to perform any part of the
work required by the contract, the Engineer may provide the Contractor
written notice establishing a date after which the City will correct and
remedy that work by any means that the Engineer may deem
necessary, including the use of City forces or other contractors.
If the Engineer determines that the Contractor’s failure to promptly
correct any defective or any unauthorized work creates a situation that
could be potentially unsafe or might cause serious risk of loss or
damage to the public, the Engineer may have the defective and
Rock Creek Culvert Replacement/Lincoln 1 - 9 June 3, 2021
Project Number: 13-3007.5
unauthorized work corrected immediately, have the rejected work
removed and replaced, or have the work the Contractor refuses to
perform completed by using City or other forces.
Direct and indirect costs incurred by the City attributable to correcting
and remedying defective or unauthorized work, or work the Contractor
failed or refused to perform, shall be paid by the Contractor. Payment
may be deducted by the Engineer from monies due, or to become due,
the Contractor. Direct and indirect costs shall include, without
limitation, compensation for additional professional services required,
compensation and engineering and inspection services required, and
costs for repair and replacement of work of others destroyed or
damaged by correction, removal, or replacement of the Contractor’s
unauthorized work.
No increase in contract time or compensation will be allowed because of
the delay in the performance of the work attributable to the exercise of
the City’s rights provided by this section nor shall the exercise of this
right diminish the City’s right to pursue any other remedy available
under law with respect to the Contractor’s failure to perform the work
as required.
DIVISION 1 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTIONS:
1-05.8 City Provided Construction Staking
1-05.8(1) General
As used in this Section 1-05.5, the words, “stake,” “mark,” “marker,” or
“monument” will be deemed to include any kind of survey marking,
whether or not set by the City.
The City will supply construction stakes and marks establishing lines,
slopes and grades as set forth in Sections 1-05.8(2) through 1-05.8(6)
of the Kent Special Provisions. The Contractor shall assume full
responsibility for detailed dimensions, elevations, and excavation slopes
measured from these City furnished stakes and marks.
The Contractor shall provide a work site clear of equipment, stockpiles
and obstructions which has been prepared and maintained to permit
construction staking to proceed in a safe and orderly manner. A City
survey crew can stake a finite amount of work in a single day (see
Section 1-05.8(6) of the Kent Special Provisions). The Contractor shall
provide staking requests for a reasonable amount of work to the
Engineer at least 3 working days in advance to allow the survey crew
adequate time for setting stakes. If the work site is obstructed so that
survey work cannot be done, a new request for work shall be submitted
by the Contractor so that the survey can be rescheduled once the site is
properly prepared. Up to an additional 3 working days may be required
depending on work load for the city survey crew to complete the
rescheduled work. Note: A surveyor working day is a consecutive eight
hour period between 7:00 AM and 6:00 PM, Monday through Friday,
except holidays as listed in Section 1-08.5.
Rock Creek Culvert Replacement/Lincoln 1 - 10 June 3, 2021
Project Number: 13-3007.5
It is illegal under Revised Code of Washington 58.09.130 and
Washington State Administrative Code 332-120 to willfully destroy
survey markers. Stakes, marks, and other reference points set by City
forces, and existing City, State or Federal monumentation, shall be
carefully preserved by the Contractor. The Contractor shall notify the
Engineer immediately if it becomes apparent that a survey marker will
be disturbed due to construction. The Contractor will allow ample time
for City Survey Department personnel to acquire adequate information
so that the monument may be replaced in its original position after
construction. If the City is not notified, and a stake, marker or
monument is disturbed or destroyed the Contractor will be charged at a
rate of $300/hour for a city survey crew to replace the stake, marker or
monument that was not to be disturbed or damaged by the Contractor’s
operations. This charge will be deducted from monies due or to become
due to the Contractor.
Any claim by the Contractor for extra compensation by reason of
alterations or reconstruction work allegedly due to error in the
Surveyor’s line and grade will not be allowed unless the original control
points set by the Surveyor still exist, or unless the Contractor can
provide other satisfactory substantiating evidence to prove the error
was caused by incorrect city-furnished survey data. Three consecutive
points set on line or grade shall be the minimum points used to
determine any variation from a straight line or grade. Any such
variation shall, upon discovery, be reported to the Engineer. In the
absence of such report, the Contractor shall be liable for any error in
alignment or grade.
1-05.8(2) Environmental Surveys
The Engineer shall furnish to the Contractor, one time only, all principal lines,
grades and measurements the Engineer deems necessary for completion of the
work. The Engineer shall provide a design CAD file used in creating the plan
set of the work being completed in the City of Kent’s currently used horizontal
and vertical datums. The CAD file shall be in a final state reflecting the final
layers represented in the final plan set issued for construction.
1-05.8(3) Control Stakes
Stakes that constitute reference points for all construction work will be
conspicuously marked with an appropriate color of flagging tape. It will be the
responsibility of the Contractor to inform its employees and subcontractors of
the importance and necessity to preserve the stakes.
The Contractor shall determine appropriate construction stake offset distances
to prevent damage to stakes by its construction equipment. Should it become
necessary, for any reason, to replace these control stakes, the Contractor will
be charged at the rate of $300/hour for a city survey crew to replace the
stakes. The Contractor may not charge the City for any standby or “down”
time as a result of any replacement of control stakes. If the removal of a
control stake or monument is required by the construction operations of the
Contractor or its subcontractors, and advance notice of at least three (3) full
working days is given to the City, the City will reference, remove, and later
replace the stakes or monument at no cost to the Contractor.
Rock Creek Culvert Replacement/Lincoln 1 - 11 June 3, 2021
Project Number: 13-3007.5
1-05.8(4) Roadway and Utility Surveys
The Engineer shall furnish to the Contractor, one time only, all principal
lines, grades and measurements the Engineer deems necessary for
completion of the work. These shall generally consist of one initial set
of:
1. Cut or fill stakes for establishing grade and embankments,
2. Curb or gutter grade stakes,
3. Centerline finish grade stakes for pavement sections wider than 25
feet as set forth in Section 1-05.8(5), subsection 2, and
4. Offset points to establish line and grade for underground utilities
such as water, sewers, storm drains, illumination and signalization.
No intermediate stakes shall be provided between curb grade and
centerline stakes.
On alley construction projects with minor grade changes, the Engineer
shall provide offset hubs on one side of the alley to establish the
alignment and grade. Alleys with major grade changes shall have
embankments staked to establish grade before offset hubs are set.
1-05.8(5) Bridge, Structure and Retaining Wall Surveys
For all structural work such as bridges and retaining walls, the
Contractor shall retain as a part of Contractor organization an
experienced team of surveyors under direct supervision of a licensed
surveyor. The Contractor shall ensure that required field measurements
and locations match the plan dimensions. The Contractor shall provide
all surveys required to complete the structure, except the following
primary survey control which will be provided by the City.
1. Sufficient horizontal control points to allow the Contractor to
establish centerline, abutments and pier centerline positioning and
stationing.
2. Up to 6 bench marks in close proximity to the work area.
3. Permanent monuments as shown on the drawings or as given by
the City.
The Contractor shall establish all secondary survey controls, both
horizontal and vertical, as necessary to assure proper placement of all
project elements based on the primary control points provided by the
City. Survey work shall be within the following tolerances:
1. Stationing +.01 foot
2. Alignment +0.1 foot (between successive points)
3. Superstructure Elevations +0.1 foot (from plan elevations)
4. Substructure Elevations +0.5 foot (from plan elevations)
Rock Creek Culvert Replacement/Lincoln 1 - 12 June 3, 2021
Project Number: 13-3007.5
During the progress of the work, the Contractor shall make available to
the City all filed books including survey information, footing elevations,
cross sections and quantities.
The Contractor shall be fully responsible for the close coordination of
field locations and measurements within appropriate dimensions of
structural members being fabricated.
1-05.8(6) Control Stakes
Stakes that constitute reference points for all construction work will be
conspicuously marked with an appropriate color of flagging tape. It will
be the responsibility of the Contractor to inform its employees and
subcontractors of the importance and necessity to preserve the stakes.
The Contractor shall determine appropriate construction stake offset
distances to prevent damage to stakes by its construction equipment.
Should it become necessary, for any reason, to replace these control
stakes, the Contractor will be charged at the rate of $300/hour for a
city survey crew to replace the stakes. The Contractor may not charge
the City for any standby or “down” time as a result of any replacement
of control stakes. If the removal of a control stake or monument is
required by the construction operations of the Contractor or its
subcontractors, and advance notice of at least three (3) full working
days is given to the City, the City will reference, remove, and later
replace the stakes or monument at no cost to the Contractor.
1-05.8(7) Staking Services
Work requests must be made at least 3 working days in advance
of the required staking.
The City will furnish the following stakes and reference marks:
1. Clearing Limits - One set of clearing limit stakes will be set at
approximately 25-foot stations where needed.
2. Rough Grading - One set of rough grade stakes will be set along
the construction centerline of streets at 50-foot stations as
required. (If superelevations require intermediate stakes along
vertical curves, the City will provide staking at closer intervals.)
One set of primary cut and fill stakes will be set for site work. One
set of secondary final grade cut and fill stakes will be set where
deemed applicable as determined by the Engineer.
3. Storm Sewers - Two cut or fill stakes for each inlet, catch basin or
manhole will be set at appropriate offsets to the center of the
structure. After installation and backfill, inverts will be checked for
correctness.
4. Sanitary Sewers - Two cut or fill stakes for each manhole or
cleanout location will be set at appropriate offsets to the center of
the structure. After installation and backfill, inverts will be checked
for correctness.
Rock Creek Culvert Replacement/Lincoln 1 - 13 June 3, 2021
Project Number: 13-3007.5
5. Water Main - One set of line stakes will be furnished for water
mains at 50-foot stations. Additionally, two reference stakes for
each valve, hydrant, tee and angle point location will be set
concurrently with these line stakes.
6. Staking for Embankments - Catch points and one line stake will be
set in those cases where the vertical difference in elevation from
the construction centerline to the toe or top of a cut or fill slope
exceeds 3 feet. In all other areas, stakes shall be set at an
appropriate offset to the street centerline to allow for the
preservation of said offsets through the rough grading phase. In
both cases the stakes shall be clearly marked with appropriate
information necessary to complete the rough grading phase.
7. Curb and Gutters - One set of curb and gutter stakes shall be set
at an appropriate offset at 25-foot intervals, beginning and end
points of curves and curb returns, wheelchair ramps, driveways,
and sufficient mid-curve points to establish proper alignment.
8. Base and Top Course - One set of final construction centerline
grade hubs will be set for each course, at not less than 50-foot
stations. No intermediate stakes shall be provided unless
superelevations require them. In those circumstances, one grade
hub left and right of construction centerline at the transition
stations will be set at an appropriate offset to centerline not less
than 25-foot stations.
9. Adjacent or Adjoining Wetlands - One set of stakes delineating
adjacent wetland perimeters will be set at 25 to 50-foot stations as
required.
10. Illumination and Traffic Signals System - One set of stakes for
luminaires and traffic signal pole foundations will be set as
required. One set of stakes for vaults, junction boxes, and conduits
will be set, only if curb and gutter is not in place at the time of the
survey request. If curb and gutter is in place, staking for vaults,
junction boxes, and conduits will be provided at an additional
expense to the Contractor.
When deemed appropriate by the Engineer, cut sheets will be supplied
for curb, storm, sanitary sewer and water lines. Cuts or fills may be
marked on the surveyed points but should not be relied on as accurate
until a completed cut sheet is supplied.
The Contractor, at its own expense, shall stake all other items not listed
above to construct the project per the Plans and Specifications. Staking
for channelization, traffic loops, and all other items not listed above
shall be the sole responsibility and expense of the Contractor. The City
may, at its sole discretion, provide additional staking at the request of
the Contractor at the rate of $300/hour.
1-05.8(8) Survey Requests
It shall be the Contractor’s responsibility to properly schedule survey
crews and coordinate staking requests with construction activities. A
survey crew may be reasonably expected to stake any one of the
following items, in the quantity shown, in a single day:
Rock Creek Culvert Replacement/Lincoln 1 - 14 June 3, 2021
Project Number: 13-3007.5
Roadway grading +/-1500 lineal feet of centerline
Storm or sanitary sewer Approximately 8-10 structures
Water main +/-1500 lineal feet of pipe
Curb and gutter +/-1300 lineal feet (one side only)
Base and top course +/-1000 lineal feet of centerline
Slope staking +/-800-1200 lineal feet (top and toe)
Illumination/signalization Approximately 15-20 structures
Actual quantities may vary based on the complexity of the project, line
of sight considerations, traffic interference, properly prepared work site,
and other items that could affect production.
The Contractor shall be aware that length does not always translate
directly into stationing. For example, a survey request for storm sewer
pipe from Station 3+00 to 8+00 is 500 lineal feet in length. There may
be 1000 lineal feet, or more, of storm sewer pipe, if the pipe is placed
on both sides of the roadway and interconnected.
SECTION 1-05.9 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SUBSECTION:
1-05.9 Equipment
1-05.9(1) Operational Testing
It is the intent of the City to have at the Physical Completion Date a
complete and operable system. Therefore when the work involves the
installation of machinery or other mechanical equipment, street
lighting, electrical distribution of signal systems, building or other
similar work, it may be desirable for the Engineer to have the
Contractor operate and test the work for a period of time after final
inspection but prior to the Physical Completion Date.
Whenever items of work are listed in the contract provisions for
operational testing they shall be fully tested under operating conditions
for the time period specified to ensure their acceptability prior to the
Physical Completion Date. In the event the contract does not specify
testing time periods, the default testing time period shall be twenty-one
(21) calendar days.
During and following the test period, the Contractor shall correct any
items of workmanship, materials, or equipment that prove faulty or that
are not in first class operating condition. Equipment, electrical controls,
meters, or other devices and equipment to be tested during this period
shall be tested under the observation of the Engineer, so that the
Engineer may determine their suitability for the purpose for which they
were installed. The Physical Completion Date cannot be established
until testing and corrections have been completed to the satisfaction of
the Engineer.
The costs for power, gas, labor, material, supplies, and everything else
needed to successfully complete operational testing shall be included in
Rock Creek Culvert Replacement/Lincoln 1 - 15 June 3, 2021
Project Number: 13-3007.5
the various contract bid item prices unless specifically set forth
otherwise in the contract.
Operational and test periods, when required by the Engineer, shall not
affect a manufacturer’s guaranties or warranties furnished under the
terms of the Contract.
SECTION 1-05.10 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-05.10 Guarantees
In addition to any other warranty or guarantee provided for at law or in
the parties’ contract, the Contractor shall furnish to the Contracting
Agency any guarantee or warranty furnished as a customary trade
practice in connection with the purchase of any equipment, materials,
or items incorporated into the project.
Upon receipt of written notice of any required corrective work, the
Contractor shall pursue vigorously, diligently, and without disrupting
city facilities, the work necessary to correct the items listed in the
notice. Approximately sixty (60) calendar days prior to the one year
anniversary of final acceptance, the Contractor shall be available to tour
the project, with the Engineer, in support of the Engineer’s effort to
establish a list of corrective work then known and discovered.
SECTION 1-05.13 IS REVISED BY INSERTING THE FOLLOWING PARAGRAPH
AFTER THE FIRST PARAGRAPH:
1-05.13 Superintendents, Labor, and Equipment of Contractor
Within ten (10) days of contract award, the Contractor shall designate
the Contractor's project manager and superintendent for the contract
work.
SECTION 1-05.13 IS REVISED BY INSERTING THE FOLLOWING PARAGRAPH
AFTER THE THIRD PARAGRAPH (AS PRINTED IN THE 2021 WSDOT
STANDARD SPECIFICATIONS):
If at any time during the contract work, the Contractor elects to replace
the contract manager or superintendent, the Contractor shall only do so
after obtaining the Engineer's prior written approval.
THE LAST PARAGRAPH OF 1-05.13 IS DELETED AND REPLACED WITH THE
FOLLOWING:
Whenever the City evaluates the Contractor’s qualifications or
prequalifications pursuant to Section 1-02.1 or RCW 47.28.070, the City
may take these or other Contractor performance reports into account.
SECTION 1-05.14 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
1-05.14 Cooperation With Other Contractors
Rock Creek Culvert Replacement/Lincoln 1 - 16 June 3, 2021
Project Number: 13-3007.5
Details of known projects are as follows: N/A
SECTION 1-05 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTIONS:
1-05.16 Water and Power
The Contractor shall make necessary arrangements, and shall bear the
costs for power and water necessary for the performance of the work,
unless the Contract includes power or water as bid items, or unless
otherwise provided for in other bid items.
1-05.17 Oral Agreements
No oral agreement or conversation with any officer, agent, or employee
of the City, either before or after execution of the contract, shall affect
or modify the terms or obligations contained in any of the documents
comprising the contract. Such oral agreement or conversation shall be
considered unofficial information and in no way binding upon the City,
unless subsequently recorded and/or put in writing and signed by an
authorized agent of the City.
1-06 CONTROL OF MATERIAL
1-06.2 Acceptance of Materials
SECTION 1-06.2(2) IS DELETED IN ITS ENTIRETY.
1-06.2(2) Statistical Evaluation of Materials for Acceptance
SECTION 1-06 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTIONS:
1-06.7 Submittals
1-06.7(1) Submittal Procedures
All information submitted by the Contractor shall be clear, sharp, high
contrast copies. Contractor shall accompany each submittal with a letter
of transmittal containing the following information:
1. Contractor’s name and the name of Subcontractor or supplier who
prepared the submittal.
2. The project name and identifying number.
3. Each new submittal shall be sequentially numbered (1, 2, 3, etc.).
Each resubmittal shall include the original number with a
sequential alpha letter added (1A, 1B, 1C, etc.).
4. Description of the submittal and reference to the Contract
requirement or technical specification section and paragraph
number being addressed.
5. Bid item(s) where product will be used.
Rock Creek Culvert Replacement/Lincoln 1 - 17 June 3, 2021
Project Number: 13-3007.5
1-06.7(2) Schedule of Submittals
The Contractor shall create and submit three (3) copies of a schedule of
submittals showing the date by which each submittal required for
product review or product information will be made. The schedule can
be modified, deducted, or added to by the City. The schedule shall be
available at the preconstruction conference (see 1-08.0 of the Kent
Special Provisions). The schedule of submittals must be accepted prior
to the City making the first progress payment. The schedule shall
identify the items that will be included in each submittal by listing the
item or group of items and the Specification Section and paragraph
number and bid item under which they are specified. The schedule shall
indicate whether the submittal is required for product review of
proposed equivalents, shop drawings, product data or samples or
required for product information only.
The Contractor shall allow a minimum of 21 days for the Engineer’s
review of each submittal or resubmittal. All submittals shall be in
accordance with the approved schedule of submittals. Submittals shall
be made early enough to allow adequate time for manufacturing,
delivery, labor issues, additional review due to inadequate or
incomplete submittals, and any other reasonably foreseeable delay.
1-06.7(3) Shop Drawings, Product Data, and Samples
The Contractor shall submit the following for the Engineer’s review:
1. Shop Drawings: Submit an electronic copy or three paper copies.
Submittals will be marked, stamped and returned to the
Contractor. The Contractor shall make and distribute any required
copies for its superintendent, subcontractors and suppliers.
2. Product Data: Submit an electronic copy or three paper copies.
Submittals will be marked, stamped and returned to the
Contractor. The Contractor shall make and distribute any required
copies for its superintendent, subcontractors and suppliers.
3. Samples: Submit three labeled samples or three sets of samples
of manufacturer’s full range of colors and finishes unless otherwise
directed. One approved sample will be returned to the Contractor.
Content of submittals:
1. Each submittal shall include all of the items required for a
complete assembly or system.
2. Submittals shall contain all of the physical, technical and
performance data required to demonstrate conclusively that the
items comply with the requirements of the Contract.
3. Each submittal shall verify that the physical characteristics of items
submitted, including size, configurations, clearances, mounting
points, utility connection points and service access points, are
suitable for the space provided and are compatible with other
interrelated items.
Rock Creek Culvert Replacement/Lincoln 1 - 18 June 3, 2021
Project Number: 13-3007.5
4. The Contractor shall label each Product Data submittal, Shop
Drawing or Sample with the bid item number and, if a lump sum
bid item, provide a reference to the applicable KSP paragraph. The
Contractor shall highlight or mark every page of every copy of all
Product Data submittals to show the specific items being submitted
and all options included or choices offered.
The City encourages a creative approach to complete a timely,
economical, and quality project. Submittals that contain deviations from
the requirements of the Contract shall be accompanied by a separate
letter explaining the deviations. The Contractor’s letter shall:
1. Cite the specific Contract requirement including the Specification
Section bid item number and paragraph number for which approval
of a deviation is sought.
2. Describe the proposed alternate material, item or construction,
explain its advantages, and explain how the proposed alternate
meets or exceeds the Contract requirements.
3. State the reduction in Contract Price, if any, which is offered to the
City.
The Engineer retains the exclusive right, at his or her sole discretion, to
accept or reject any proposed deviation with or without cause.
The Engineer will stamp and mark each submittal prior to returning it to
the Contractor. The stamps will indicate one of the following:
1. “APPROVED AS SUBMITTED” – Accepted subject to its compatibility
with the work not covered in this submission. This response does
not constitute approval or deletion of specified or required items
not shown in the partial submission.
2. “APPROVED AS NOTED” – Accepted subject to minor corrections
that shall be made by the Contractor and subject to its
compatibility with the work not covered in this submission. This
response does not constitute approval or deletion of specified or
required items not shown in the partial submission. No
resubmission is required.
3. “AMEND AND RESUBMIT” – Rejected because of major
inconsistencies, errors or insufficient information that shall be
resolved or corrected by the Contractor prior to subsequent re-
submittal. An amended resubmission is required.
Re-submittals that contain changes that were not requested by the
Engineer on the previous submittal shall note all changes and be
accompanied by a letter explaining the changes.
1-06.7(4) Proposed Equivalents
The Engineer retains the exclusive right, at his or her sole discretion, to
accept or reject any proposed equivalent with or without cause.
Rock Creek Culvert Replacement/Lincoln 1 - 19 June 3, 2021
Project Number: 13-3007.5
1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC
1-07.2 State Taxes
SECTION 1-07.2(1) IS REVISED BY DELETING THE SECOND PARAGRAPH AND
REPLACING WITH THE FOLLOWING:
1-07.2(1) State Sales Tax: WAC 458-20-171—Use Tax
Without waiving the Contractor’s obligation to understand and apply
these tax rules correctly, the City has indicated those parts of the
project that are subject to use tax under Section 1-07.2(1) in the
proposal bid items.
SECTION 1-07.2(2) IS REVISED BY DELETING THE SECOND PARAGRAPH AND
REPLACING WITH THE FOLLOWING:
1-07.2(2) State Sales Tax: WAC 458-20-170—Retail Sales Tax
Without waiving the Contractor’s obligation to understand and apply
these tax rules correctly, the City has indicated those parts of the
project that are subject to retail sales tax under Section 1-07.2(2) in
the proposal bid items.
SECTION 1-07.4(2) IS DELETED AND REPLACED WITH THE FOLLOWING:
1-07.4(2) COVID-19 Job Site Requirements
Before commencing any work on the Project site, the Contractor shall
develop and post at each job site a comprehensive COVID-19 exposure
control, mitigation, and recovery plan that complies with the Phase 1
Construction Restart COVID-19 Job Site Requirements issued by the
Governor, or subsequent modifications or phase amendments as the
Governor may issue. Contractor must further meet and maintain all
requirements of the plan, including providing materials, schedules, and
equipment required to comply with those job site requirements or any
future adjustments that may be made to job site requirements by the
Governor or any applicable federal or state agency during the COVID-
19 emergency.
A copy of the COVID-19 job site safety plan, along with the
identification and contact information for the COVID-19 Supervisor,
shall be provided to the Engineer.
SECTION 1-07.6 IS SUPPLEMENTED BY INSERTING THE FOLLOWING
PARAGRAPH BEFORE THE FIRST PARAGRAPH:
1-07.6 Permits and Licenses
The City has obtained the following permits: None
Rock Creek Culvert Replacement/Lincoln 1 - 20 June 3, 2021
Project Number: 13-3007.5
SECTION 1-07.6 IS SUPPLEMENTED BY INSERTING THE FOLLOWING
PARAGRAPHS AFTER THE LAST PARAGRAPH:
A copy of each permit and/or license obtained by the Contractor shall
be furnished to the City. Approved permits shall be furnished to the City
upon completion of the project and prior to final acceptance.
The Contractor shall promptly notify the City in writing of any variance
in the contract work arising from the issuance of any permit.
1-07.9 Wages
SECTION 1-07.9(1) IS SUPPLEMENTED BY INSERTING THE FOLLOWING
PARAGRAPH AFTER THE SIXTH PARAGRAPH:
1-07.9(1) General
To the extent allowed by law, the wage rates that will be in effect
during the entire contract work period are those in effect on the day of
bid opening, unless the City does not award the Contract within six
months of the bid opening.
SECTION 1-07.9(3) IS DELETED AND REPLACED WITH THE FOLLOWING:
FOLLOWING:
1-07.9(3) Apprentices
All contracts with an estimated construction cost greater than
$1,000,000 (one million dollars) shall require that no less than 15
percent of the labor hours performed by workers subject to prevailing
wages employed by the contractor or its subcontractors be performed
by apprentices enrolled in a state-approved apprenticeship program.
Definitions
For the purposes of this specification, the following definitions apply:
1. Apprentice Utilization Requirement is expressed as a percentage of
the project Labor Hours performed by Apprentices.
2. Labor Hours are the total hours performed by all workers receiving
an hourly wage who are directly employed on the project site
including hours performed by workers employed by the prime
Contractor and all Subcontractors. Labor Hours do not include
hours performed by foremen, superintendents, owners, and
workers who are not subject to prevailing wage requirements.
3. Apprentice is a person enrolled in a State-approved Apprenticeship
Training Program.
4. State-approved Apprenticeship Training Program is an
apprenticeship training program approved by the Washington
State Apprenticeship Council.
5. Good Faith Effort is a demonstration that the Contractor has
strived to meet the Apprenticeship Utilization Requirement
Rock Creek Culvert Replacement/Lincoln 1 - 21 June 3, 2021
Project Number: 13-3007.5
including but not necessarily limited to the specific steps as
described elsewhere in this specification.
Plan
The Contractor shall submit an “Apprentice Utilization Plan” within 30
calendar days of Notice of Award, demonstrating how they intend to
achieve the Apprentice Utilization Requirement. The plan shall be
updated and resubmitted as appropriate as the Work progresses. The
intent is to provide the City with enough information to track progress
in meeting the utilization requirements.
Reporting
The Contractor shall submit a “Monthly Apprentice Reporting Form” on
a monthly basis. The report shall be submitted to the City by the last
working day of the subsequent month, until the Physical Completion
Date. The date reported shall be cumulative to date and consolidated to
include the Contractor and all Subcontractors. At the Contractor’s
request, the Engineer may suspend this reporting requirement during
periods of minimal or no applicable work activities on the project. The
Contractor shall submit documentation of their Good Faith Effort if: (1)
they are unable to provide a plan demonstrating how they intend to
meet the Apprentice Utilization Requirement; or (2) the project has
been completed without meeting the Apprentice Utilization
Requirement.
Contacts
The Contractor may obtain information on State-approved
Apprenticeship Training Programs by contacting the Department of
Labor and Industries at: Specialty Compliance Services Division,
Apprenticeship Section, P.O. Box 44530, Olympia, WA 98504-4530 or
by phone at (360) 902-5320.
Compliance
In the event that the Contractor is unable to accomplish the Apprentice
Utilization Requirement, the Contractor shall demonstrate that a Good
Faith Effort has been made as described within this specification. Failure
to comply with the requirements as specified is subject to penalties for
noncompliance as set forth in KCC 6.01.030(E).
Good Faith Efforts
In fulfilling the Good Faith Effort, the Contractor shall perform and,
when appropriate, require its Subcontractors to perform the following
steps:
1. Solicit Apprentice(s) from State-approved Apprenticeship Training
Program(s).
2. Document the solicitation and, in the event Apprentice(s) are not
available, obtain supporting documentation from the solicited
program(s).
3. Demonstrate that the plan was updated as required within this
specification.
Rock Creek Culvert Replacement/Lincoln 1 - 22 June 3, 2021
Project Number: 13-3007.5
4. Provide documentation demonstrating what efforts the Contractor
has taken to require Subcontractors to solicit and employ
Apprentice(s).
In the event that the preceding steps have been followed, the
Contractor may also supplement the Good Faith Efforts documentation
with the following documentation:
5. Submit documentation demonstrating successful Apprentice
utilization on previous contracts.
6. Submit documentation indicating company-wide Apprentice
utilization efforts and percentages of attainment.
Payment
Compensation for all costs involved with complying with the conditions
of this specification is included in payment for the associated Contract
items of work.
1-07.13 Contractor’s Responsibility for Work
SECTION 1-07.13(4) IS REVISED BY DELETING THE SECOND SENTENCE OF
THE FIRST PARAGRAPH AND DELETING THE LAST PARAGRAPH.
1-07.13(4) Repair of Damage
SECTION 1-07.14 IS REVISED BY ADDING THE FOLLOWING TO THE
BEGINNING OF THAT SECTION:
1-07.14 Responsibility for Damage
To the extent a conflict exists between the terms of this Section
1-07.14 and Section 5 of the Contract, the terms of the Contract will
control. Any reference to the State, Governor, Commission, Secretary,
or all officers and employees of the State also will include the City, its
officers and employees.
1-07.15 Temporary Water Pollution Prevention
SECTION 1-07.15(1) IS REVISED BY ADDING THE FOLLOWING PARAGRAPH
AFTER THE LAST PARAGRAPH:
1-07.15(1) Spill Prevention, Control, and Countermeasures Plan
When the proposal form includes multiple bid schedules and the “SPCC
Plan” bid item is present in only one bid schedule, the lump sum
payment item for the “SPCC Plan” in that one schedule will apply to all
bid schedules for all costs associated with creating and updating the
accepted SPCC Plan, and all costs associated with the setup of
prevention measures and for implementing the current SPCC Plan as
required by this Specifications.
Rock Creek Culvert Replacement/Lincoln 1 - 23 June 3, 2021
Project Number: 13-3007.5
SECTION 1-07.17 IS REVISED BY ADDING THE FOLLOWING SENTENCE TO
THE END OF THE SECOND PARAGRAPH:
1-07.17 Utilities and Similar Facilities
If a utility is known to have or suspected of having underground
facilities within the area of the proposed excavation and that utility is
not a subscriber to the utilities underground location center, the
Contractor shall give individual notice to that utility within the same
time frame prescribed in RCW 19.122.030 for subscriber utilities.
SECTION 1-07.17 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTIONS:
1-07.17(3) Utility Markings
Once underground utilities are marked by the utility owner or its agent,
and/or once new underground facilities have been installed by the
Contractor, the Contractor/excavator is responsible to determine the
precise location of underground facilities that may conflict with other
underground construction. The Contractor shall maintain the marks or a
record of the location of buried facilities for the duration of time needed
to avoid future damage until installation of all planned improvements at
that location is complete.
1-07.17(4) Payment
All costs to comply with subsection 1-07.17(3) and for the protection
and repair of all identified or suspected underground utilities specified
in RCW 19.122 are incidental to the contract and are the responsibility
of the Contractor/excavator. The Contractor shall include all related
costs in the unit bid prices of the contract. No additional time or
monetary compensation shall be made for delays caused by utility re-
marking or repair of damaged utilities due to the Contractor’s failure to
maintain marks or to locate utilities in accordance with this section.
1-07.17(5) Notification of Excavation
Within ten business days but not less than two business days prior to
the commencement of excavation, the Contractor shall provide written
notice (or other form of notice acceptable to the Engineer) to all owners
of underground facilities, whether public or private, that excavation will
occur, and when excavation will occur.
1-07.17(6) Site Inspection
Contractor warrants and represents that it has personally, or through
its employees, agents and/or subcontractors, examined all property
affected by this project and that it is knowledgeable of specific locations
for water, gas, telephone, electric power and combined sewerage
utilities within those areas.
Rock Creek Culvert Replacement/Lincoln 1 - 24 June 3, 2021
Project Number: 13-3007.5
The following list of contacts is provided only as a convenience
to the Contractor. It may not be accurate and may not constitute
a complete list of all affected utilities.
CenturyLink/Lumen
Jesse Patjens
425-429-5722
Comcast
Todd Zimny
253-266-4741
Todd_Zimny@comcast.com
Puget Sound Energy Gas
Glenn Helton
253-395-6926
425-559-4647 (cell)
Puget Sound Energy Power
Jason Airey
206-348-9637
Jason.Airey@pse.com
Verizon
Scott Christenson
425-636-6046
425-471-1079 (cell)
SECTION 1-07.18 IS REVISED BY ADDING THE FOLLOWING PARAGRAPH
BEFORE THE FIRST PARAGRAPH:
1-07.18 Public Liability and Property Damage Insurance
To the extent a conflict exists between the terms of this Section
1-07.18 and the insurance requirements in Section 7 of the Contract,
the terms of the Contract will control. Any reference to the State,
Governor, Commission, Secretary, or all officers and employees of the
State also will include the City, its officers and employees.
SECTION 1-07.24 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-07.24 Rights of Way
Street right of way lines, limits of easements and limits of construction
are indicated or defined on the plans. The Contractor's construction
activities shall be confined within these limits, unless arrangements for
use of private property are made.
It is anticipated that the City will have obtained all right of way,
easements or right of entry agreements prior to the start of
construction. Locations where these rights have not been obtained will
be brought to the Contractor's attention prior to start of construction.
The Contractor shall not proceed with any portion of the work in areas
where right of way, easements or rights of entry have not been
acquired until the Engineer certifies to the Contractor that the right of
way or easement is available or that the right of entry has been
received.
Rock Creek Culvert Replacement/Lincoln 1 - 25 June 3, 2021
Project Number: 13-3007.5
SECTION 1-07.26 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-07.26 Personal Liability of Public Officers
Neither the City, the Engineer, nor any other official, officer or
employee of the City shall be personally liable for any acts or failure to
act in connection with the contract, it being understood that, in these
matters, they are acting solely as agents of the City.
1-08 PROSECUTION AND PROGRESS
SECTION 1-08 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
1-08.0 Preconstruction and Preconstruction Conference
The Engineer will furnish the Contractor with up to ten (10) copies of
the plans and specifications. Additional documents may be purchased
from the City at the price specified by the City or in the Invitation to
Bid. Prior to undertaking each part of the work, the Contractor shall
carefully study and compare the Contract and check and verify all
pertinent figures shown and all applicable field measurements. The
Contractor shall promptly report in writing to the Engineer any conflict,
error or discrepancy that the Contractor discovers.
After the Contract has been executed, but prior to the Contractor
beginning the work, a preconstruction conference will be held with the
Contractor, the Engineer and any other interested parties that the City
determines to invite. The purpose of the preconstruction conference will
be:
1. To review the initial progress schedule.
2. To establish a working understanding among the various parties
associated or affected by the work.
3. To establish and review procedures for progress payment,
notifications, approvals, submittals, etc.
4. To verify normal working hours for the work.
5. To review safety standards and traffic control.
6. To discuss any other related items that may be pertinent to the
work.
The Contractor shall prepare and submit for approval, at or prior to the
preconstruction conference the following:
1. A price breakdown of all lump sum items.
2. A preliminary construction schedule.
3. A list of material sources for approval, if applicable.
4. Schedule of submittals. (See 1-06.6(2))
5. Temporary Erosion/Sedimentation Control Plan (TESCP) for
approval.
6. Traffic Control Plan (TCP) for approval.
Rock Creek Culvert Replacement/Lincoln 1 - 26 June 3, 2021
Project Number: 13-3007.5
7. Request to sublet, for approval by the Engineer, of all
subcontractors.
SECTION 1-08.4 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-08.4 Notice to Proceed, Prosecution and Hours of Work
Notice to Proceed will be given after the contract has been executed
and the contract bond and evidence of required insurance have been
approved by and filed with the City. Unless otherwise approved in
writing by the Engineer, the Contractor shall not commence the work
until the Notice to Proceed has been given by the Engineer. The
Contractor shall commence construction activities on the Project Site
within ten working days of the Notice to Proceed Date. The Work
thereafter shall be prosecuted diligently, vigorously, and without
unauthorized interruption until physical completion of the work.
Voluntary shutdown or slowing of operations by the Contractor shall not
relieve the Contractor of the responsibility to complete the work within
the time(s) specified in the Contract.
Except in the case of emergency or unless otherwise approved by the
Engineer, the normal straight time working hours for the Contractor
shall be any consecutive 8 hour period between 7:00 a.m. and 6:00
p.m. Monday through Friday, unless otherwise specified in the Kent
Special Provisions, with a 5-day work week, plus allowing a maximum
one-hour lunch break in each working day. The normal straight time
8-hour working period for the contract shall be established at the
preconstruction conference or prior to the Contractor commencing
work.
If a Contractor desires to perform work on holidays, Saturdays,
Sundays, or before 7:00 a.m. or after 6:00 p.m. on any day, the
Contractor shall apply in writing to the Engineer for permission to work
those times. The Contractor shall notify the Engineer at least 48 hours
in advance (72 hours in advance for weekend work) so that the
Inspector's time may be scheduled. Permission to work longer than an
8-hour period between 7:00 a.m. and 6:00 p.m. is not required. For
any work outside of normal straight time working hours that requires
city surveyors, all reasonable efforts shall be made by the Contractor to
allow time for surveying to be completed during normal straight time
hours. If city surveyors are required to work other than normal straight
time hours at the convenience of the Contractor, all such work shall be
reimbursed by the Contractor.
Permission to work between the hours of 10:00 p.m. and 7:00 a.m.
during weekdays and between the hours of 10:00 p.m. and 9:00 a.m.
on weekends or holidays may also be subject to noise control
requirements. Approval to continue work during these hours may be
revoked at any time the Contractor exceeds the City’s noise control
regulations or the city receives complaints from the public or adjoining
property owners regarding noise from the Contractor’s operations. The
Rock Creek Culvert Replacement/Lincoln 1 - 27 June 3, 2021
Project Number: 13-3007.5
Contractor shall have no claim for damages or delays should this
permission be revoked for these reasons.
The Engineer may grant permission to work Saturdays, Sundays,
holidays or other than the agreed upon normal straight time working
hours, but may be subject to other conditions established by the City or
Engineer. These conditions may include, but are not limited to the
following: hours worked by City employees; impacts to the construction
schedule; or accommodations to adjoining properties affected by the
contract work.
1-08.4(A) Reimbursement for Overtime Work of City Employees
Following is a non-exclusive list of work that may require Contractor
reimbursement for overtime of City employees. The City will bill the
Contractor at the OVERTIME RATE in order for locate crews to
complete other work. If the locate request is for nights, weekend,
holidays or at other times when locate crews are not normally working,
all locate work and expenses, including travel, minimum call out times,
and/or Holiday premiums will be borne by the Contractor.
1. Locate work required to re-establish marks for City-owned
underground facilities that were not maintained or recorded by the
Contractor in accordance with RCW 19.122.030.
2. Work required by city survey crew(s) as the result of reestablishing
survey stakes or markings that were not maintained or recorded
by the Contractor or other work deemed to be for the convenience
of the Contractor and not required of the City by the contract.
3. Work required by City personnel or independent testing
laboratories to re-test project materials, utility pressure or vacuum
tests, camera surveys or water purity tests as the result of initial
test failure on the part of the Contractor.
1-08.4(B) General
The City allocates its resources to a contract based on the total time
allowed in the contract. The City will accept a progress schedule
indicating an early physical completion date but cannot guarantee the
City resources will be available to meet the accelerated schedule. No
additional compensation will be allowed if the Contractor is not able to
meet its accelerated schedule due to the unavailability of City resources
or for other reasons beyond the City's control.
Unless previously approved by the Engineer, the original and all
supplemental progress schedules shall not conflict with any time and
order-of-work requirements in the contract.
If the Engineer deems that the original or any necessary supplemental
progress schedule does not provide adequate information, the City may
withhold progress payments until a schedule containing needed
information has been submitted by the Contractor and approved by the
Engineer.
Rock Creek Culvert Replacement/Lincoln 1 - 28 June 3, 2021
Project Number: 13-3007.5
The Engineer's acceptance of any schedule shall not transfer any of the
Contractor's responsibilities to the City. The Contractor alone shall
remain responsible for adjusting forces, equipment, and work schedules
to ensure completion of the work within the times specified in the
contract.
SECTION 1-08.5 IS REVISED BY DELETING THE THIRD PARAGRAPH AND
REPLACING WITH THE FOLLOWING:
1-08.5 Time for Completion
Contract time shall begin on the day of the Notice to Proceed. The
Contract Provisions may specify another starting date for Contract time,
in which case, time will begin on the starting date specified.
SECTION 1-08.6 IS REVISED BY DELETING THE FIFTH, SIXTH, AND SEVENTH
PARAGRAPHS AND REPLACING WITH THE FOLLOWING:
1-08.6 Suspension of Work
If the performance of all or any part of the Work is suspended for an
unreasonable period of time by an act of the Contracting Agency in the
administration of the Contract, or by failure to act within the time
specified in the Contract (or if no time is specified, within a reasonable
time), the Engineer will make an adjustment for any increase in the
cost or time for the performance of the Contract (excluding profit)
necessarily caused by the suspension. However, no adjustment will be
made for any suspension if (1) the performance would have been
suspended by any other cause, including the fault or negligence of the
Contractor, or (2) an equitable adjustment is provided for or excluded
under any other provision of the Contract.
If the Contactor believes that the performance of the Work is
suspended for an unreasonable period of time and such suspension is
the responsibility of the Contracting Agency, the Contractor shall
immediately submit a written notice of protest to the Engineer as
provided in Section 1-04.5. No adjustment shall be allowed for any
costs incurred more than 10 calendar days before the date the Engineer
receives the Contractor’s written notice to protest. In any event, no
protest will be allowed later than the date of the Contractor’s signature
on the Final Pay Estimate. The Contractor shall keep full and complete
records of the costs and additional time of such suspension, and shall
permit the Engineer to have access to those records and any other
records as may be deemed necessary by the Engineer to assist in
evaluating the protest.
The Engineer will determine if an equitable adjustment in cost or time is
due as provided in this Section. The equitable adjustment for increase
in costs, if due, shall be subject to the limitations provided in Section
1-09.4, provided that no profit of any kind will be allowed on any
increase in cost necessarily caused by the suspension.
Rock Creek Culvert Replacement/Lincoln 1 - 29 June 3, 2021
Project Number: 13-3007.5
SECTION 1-08.7 MAINTENANCE DURING SUSPENSION IS REVISED BY
DELETING THE FOURTH AND SIXTH PARAGRAPHS.
SECTION 1-08.9 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-08.9 Liquidated Damages
Time is of the essence of the Contract. Delays inconvenience the
traveling public, obstruct traffic, interfere with and delay commerce,
and increase risk to Highway users. Delays also cost tax-payers undue
sums of money, adding time needed for administration, engineering,
inspection, and supervision. Because the Contracting Agency finds it
impractical to calculate the actual cost of delays, it has adopted the
following formula to calculate liquidated damages for failure to complete
the physical Work of a Contract on time. Accordingly, the Contractor
agrees:
1. To pay (according to the following formula) liquidated damages for
each working day beyond the number of working days established
for Physical Completion, and
2. To authorize the Engineer to deduct these liquidated damages
from any money due or coming due to the Contractor.
Liquidated Damages Formula
LD = (0.15C)/T
Where:
LD = liquidated damages per working day (rounded to the nearest
dollar)
C = original Contract amount
T = original time for Physical Completion
When the Contract Work has progressed to the extent that the
Contracting Agency has full use and benefit of the facilities, both from
the operational and safety standpoint, all the initial plantings are
completed and only minor incidental Work, replacement of temporary
substitute facilities, plant establishment periods, or correction or repair
remains to physically complete the total Contract, the Engineer may
determine the Contract Work is substantially complete. The Engineer
will notify the Contractor in writing of the Substantial Completion Date.
For overruns in Contract time occurring after the date so established,
the formula for liquidated damages shown above will not apply. For
overruns in Contract time occurring after the Substantial Completion
Date, liquidated damages shall be assessed on the basis of direct
engineering and related costs assignable to the project until the actual
Physical Completion Date of all the Contract Work. The Contractor shall
complete the remaining Work as promptly as possible. Upon request by
the Engineer, the Contractor shall furnish a written schedule for
completing the physical Work on the Contract. Liquidated damages will
not be assessed for any days for which an extension of time is granted.
Rock Creek Culvert Replacement/Lincoln 1 - 30 June 3, 2021
Project Number: 13-3007.5
No deduction or payment of liquidated damages will, in any degree,
release the Contractor from further obligations and liabilities to
complete the entire Contract.
For Substantial Completion, SE Summit Landsberg shall be open to
vehicular traffic no later than Friday of August 26, 2022, ahead of the
first day of school for the Tahoma School District.
1-09 MEASUREMENT AND PAYMENT
SECTION 1-09.7 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
1-09.7 Mobilization
For Schedule III Sewer, the lump sum Bid price for Mobilization shall
not exceed eight (8) percent of the total cost of that schedule’s Bid.
1-09.9 Payments
SECTION 1-09.9 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
1-09.9(2) City’s Right to Withhold Certain Amounts
In addition to the amount that the City may otherwise retain under the
Contract, the City may withhold a sufficient amount of any payments
otherwise due to the Contractor, including nullifying the whole or part
of any previous payment, because of subsequently discovered evidence
or subsequent inspections that, in the City's judgment, may be
necessary to cover the following:
1. The cost of defective work not remedied.
2. Fees incurred for material inspection, and overtime engineering
and inspection for which the Contractor is obligated under this
Contract.
3. Fees and charges of public authorities or municipalities.
4. Liquidated damages.
5. Engineering and inspection fees beyond Completion Date.
6. Cost of City personnel to re-establish locate marks for City-owned
facilities that were not maintained by the Contractor in accordance
with RCW 19.122.030 (3).
7. Additional inspection, testing and lab fees for re-doing failed,
water, other utility tests.
1-09.11 Disputes and Claims
SECTION 1-09.11(3) IS DELETED AND REPLACED WITH THE FOLLOWING:
1-09.11(3) Time Limitations and Jurisdiction
Rock Creek Culvert Replacement/Lincoln 1 - 31 June 3, 2021
Project Number: 13-3007.5
This contract shall be construed and interpreted in accordance with the
laws of the State of Washington. The venue of any claims or causes of
action arising from this contract shall be exclusively in the Superior
Court of King County, located in Kent, Washington.
For convenience of the parties to this contract, it is mutually agreed
that any claims or causes of action which the Contractor has against the
City arising from this contract shall be brought within 180 days from
the date of Final Acceptance of the contract by the City. The parties
understand and agree that the Contractor’s failure to bring suit within
the time period provided shall be a complete bar to any such claims or
causes of action.
It is further mutually agreed by the parties that when any claims or
causes of action that a Contractor asserts against the City arising from
this contract are filed with the City or initiated in court, the Contractor
shall permit the City to have timely access to any records deemed
necessary by the City to assist in evaluating the claims or actions.
SECTION 1-09.13 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-09.13 Final Decision and Appeal
All disputes arising under this contract shall proceed pursuant to
Section 1-04.5 and 1-09.11 of the WSDOT Standard Specifications and
any Kent Special Provisions provided for in the contract for claims and
resolution of disputes. The provisions of these sections and the Kent
Special Provisions must be complied with as a condition precedent to
the Contractor’s right to seek an appeal of the City’s decision. The City’s
decision under Section 1-09.11 will be final and conclusive. Thereafter,
the exclusive means of Contractor’s right to appeal shall only be by
filing suit exclusively under the venue, rules and jurisdiction of the
Superior Court of King County, located in Kent, Washington, unless the
parties agree in writing to an alternative dispute resolution process.
1-10 TEMPORARY TRAFFIC CONTROL
1-10.2 Traffic Control Management
SECTION 1-10.2(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
1-10.2(1) General
The TCS shall be certified as a work site traffic control supervisor by
one of the following:
Evergreen Safety Council
401 Pontius Avenue North
Seattle, WA 98109
1-800-521-0778 or 206-382-4090
Rock Creek Culvert Replacement/Lincoln 1 - 32 June 3, 2021
Project Number: 13-3007.5
The Northwest Laborers-Employers Training Trust
27055 Ohio Avenue
Kingston, WA 98346
360-297-3035
The American Traffic Safety Services Association
15 Riverside Parkway, Suite 100
Fredericksburg, VA 22406-1022
Training Dept. Toll Free (877) 642-4637 or (540) 368-1701
1-10.3 Traffic Control Labor, Procedures, and Devices
1-10.3(3) Traffic Control Devices
SECTION 1-10.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
1-10.3(3)L Temporary Traffic Control Devices
When the bid proposal includes an item for “Temporary Traffic Control
Devices,” the work required for this item shall be furnishing barricades,
flashers, cones, traffic safety drums, and other temporary traffic control
devices, unless the contract provides for furnishing a specific temporary
traffic control device under another item. The item “Temporary Traffic
Control Devices” includes:
1. Initial delivery to the project site (or temporary storage) in good
repair and in clean usable condition,
2. Repair or replacement when they are damaged and they are still
needed on the project, and
3. Removal from the project site when they are no longer on the
project.
SECTION 1-10.5 IS DELETED AND REPLACED WITH THE FOLLOWING:
1-10.5 Payment
Payment will be made in accordance with Section 1-04.1, for the
following bid items when they are included in the Proposal:
The unit contract price for “Portable Changeable Message Sign (PCMS)”
per day shall be full pay for all costs for furnishing, transporting, initial
installation within the project limits, maintaining and removing the
PCMS, and associated work described in Section 1-10.3(3)C of the
WSDOT Standard Specifications. Relocation of the PCMS within the
project limits will be paid under the item “Traffic Control Labor.”
When the proposal does not include a bid item for a specific bid item
listed in the WSDOT Standard Specifications and/or the Kent Special
Provisions, all costs for the work described for those traffic control bid
items shall be included by the Contractor in the unit contract prices for
the various other bid items contained within the proposal. The
Rock Creek Culvert Replacement/Lincoln 1 - 33 June 3, 2021
Project Number: 13-3007.5
Contractor shall estimate these costs based on the Contractor’s
contemplated work procedures.
When traffic control bid items are included in the bid proposal, payment
is limited to the following work areas:
1. The entire construction area under contract and for a distance to
include the initial warning signs for the beginning of the project
and the END OF CONSTRUCTION sign. Any warning signs for side
streets on the approved TCP are also included. If the project
consists of two or more sections, the limits will apply to each
section individually.
2. A detour provided in the plans or approved by the City’s Traffic
Control Supervisor for by-passing all or any portion of the
construction, irrespective of whether or not the termini of the
detour are within the limits of the Contract.
No payment will be made to the Contractor for traffic control items
required in connection with the movement of equipment or the hauling
of materials outside of the limits of 1 and 2 above, or for temporary
road closures subject to the provisions of Section 1-07.23(1) of the
WSDOT Standard Specifications.
Rock Creek Culvert Replacement/Lincoln 2 - 1 June 3, 2021
Project Number: 13-3007.5
DIVISION 2 – EARTHWORK
2-01 CLEARING, GRUBBING, AND ROADSIDE CLEANUP
SECTION 2-01.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-01.1 Description
This Section is supplemented with the following:
Clearing and grubbing shall be restricted to the minimum amount
needed to construct roadway improvements and shall not exceed the
limits established on the Plans, staked by the Contractor, and approved
by the Engineer.
Do not remove trees, shrubs, and other vegetation indicated to remain.
Existing landscaping and vegetation outside the limits shall be protected
from damage by the Contractor’s operations. All landscaping damaged
by the Contractor’s operations outside the limits shall be replaced in
coordination with the property owner at the Contractor’s expense.
Fill depressions caused by clearing and grubbing operations with
satisfactory soil material unless further excavation or earthwork is
indicated. Place fill material in horizontal layers not exceeding eight (8)
inches in loose depth and compact each layer to a density equal to
adjacent original ground.
Clearing of trees shall include the removal and disposal of the entire
tree including roots, stump, and all associated debris. If it is determined
by the Engineer that the removal of the entire trunk is NOT feasible, the
Contractor shall cut the trunk flush with ground level.
SECTION 2-01.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-02.2 Disposal of Usable Material and Debris
Disposal Method No.1, Open Burning, as specified in Section 2-01.2(3)
will not be allowed.
2-02.3 Construction Requirements
SECTION 2-02.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
2-01.3(5) Tree Protection
High visibility fence shall be installed around trees indicated on the
Plans to be protected. Under the field direction of the Engineer, the
Contractor shall prune minor roots and branches of trees indicated to
remain in a manner that will not compromise the survivability of the
trees, where such roots and branches obstruct installation of new
construction. Any roots to be cut or accidentally broken shall be cut
Rock Creek Culvert Replacement/Lincoln 2 - 2 June 3, 2021
Project Number: 13-3007.5
smoothly and any cut roots over two (2) inches in diameter shall be
covered with wet fabric until backfill can be placed.
SECTION 2-01.4 IS SUPPLEMENTED WITH THE FOLLOWING:
2-01.4 Measurement
Tree protection is included in Clearing and Grubbing and will not be
measured separately.
SECTION 2-01.5 IS SUPPLEMENTED WITH THE FOLLOWING:
2-01.5 Payment
All costs for the protection of trees will be included in the lump sum
contract price for “Clearing and Grubbing”.
2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS
SECTION 2-02.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-02.1 Description
This work also includes the repair of adjacent improvements that were
not designated for removal, but that were damaged by the Contractor’s
operations.
For the purpose of bid preparation, the removal of structure and
obstruction work is described below.
Removal of Structure and Obstruction shall include, but not be limited
to:
• Rock Creek culverts
• Fence, salvage for re-use per Special Provision Section 8-12
SECTION 2-02.3 IS REVISED BY REPLACING THE LAST THREE PARAGRAPHS
WITH THE FOLLOWING:
2-02.3 Construction Requirements
All improvements that are not designated for removal, but that are
damaged by the Contractor’s operations shall be replaced, restored, or
repaired at the Contractor’s sole expense. The Engineer’s determination
regarding what replacement, restoration, or repair must be made by
the Contractor to repair damage caused by the Contractor’s removal
operations is final.
SECTION 2-02.3 IS SUPPLEMENTED WITH THE FOLLOWING:
2-02.3(2) Removal of Bridges, Box Culverts, and other Drainage Structures
The Contractor shall remove the existing culverts at the Summit
Landsburg Road crossing as called for on the plans. The removal shall
Rock Creek Culvert Replacement/Lincoln 2 - 3 June 3, 2021
Project Number: 13-3007.5
not commence until Rock Creek has been diverted to the proposed new
stream channel.
SECTION 2-02.3(3) IS DELETED AND REPLACED WITH THE FOLLOWING:
2-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters
In removing pavement, sidewalks, and curbs the Contractor shall:
1. Haul broken-up pieces of concrete and asphalt pavement into the
roadway embankment, or to some off-project site, unless
otherwise directed by the Engineer, or permitted by the Kent
Special Provisions.
2. Material that is to be incorporated into the embankment shall be
broken into pieces not exceeding 18 inches in any dimension, and
no part of any piece shall be within three feet of the top, side or
end surface of the embankment or any structure.
3. Make a vertical saw cut between any existing pavement, sidewalk,
or curb that is to remain and the portion to be removed. When
asphalt pavements are being widened, the vertical saw cut shall be
made at least 1-foot from the edge of the existing pavement, and
at least 2-feet from the closest edge of any cement concrete curb
that will remain or be replaced, unless otherwise directed by the
Engineer.
4. Replace at no expense to the City any existing pavement
designated to remain that is damaged during the removal of other
pavement, sidewalks, or curbs.
5. When cement concrete sidewalk, cement concrete pavement, or
cement concrete curb is being removed, and the removal would
result in a remaining strip of cement concrete less than 5 feet
long, or where in the opinion of the Engineer the remaining portion
of the sidewalk, pavement or curb would be damaged by the
cutting required for the removal, then the entire sidewalk,
pavement or curb shall be removed to the next expansion joint.
Existing pavement shall be sawcut and removed at the locations shown
on the Plans or as approved by the Engineer. Removal shall be
accomplished by making a neat longitudinal vertical cut along the
boundaries of the area to be removed. Care shall be taken during
removal so as not to damage any of the existing pavement to remain in
place. Remaining pavement damaged due to the Contractor’s
operations shall be replaced by the Contractor, to the satisfaction of the
Engineer, at the Contractor’s expense.
When a construction joint is near removal limits, the joint may be used
as the removal limit if approved by the Engineer.
SECTION 2-02.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTIONS:
Rock Creek Culvert Replacement/Lincoln 2 - 4 June 3, 2021
Project Number: 13-3007.5
2-02.3(4) Sawcutting
Care shall be taken to prevent damage to the existing pavement to
remain. Damage to existing pavement to remain shall be repaired in
accordance with Section 1-07.13.
Where sawcutting is required, the sawcut shall be three inches deep
minimum. Where the existing pavement is more than three inches
thick, the portion below the top three inches may be broken after the
sawcut is made, with the exception of the concrete panels.
The Contractor shall perform all sawcutting work, including
containment, collection and disposal of sawcutting debris and
wastewater, in accordance with Section 1 07.5(3).
2-02.3(5) Removing Existing Water Facilities
The Contractor shall remove the existing water facilities, including
mains, valves, valve boxes, hydrants, hydrant laterals, hydrant
assemblies, fittings, thrust blocks, water service connections, steel
casing(s) and other appurtenances as shown and noted in the Plans, as
may be directed by the Engineer, and as set forth in these contract
provisions.
Removal shall be conducted in such a manner as to prevent damage to
other facilities, including existing water facilities, storm sewers, sanitary
sewers, power poles, underground utilities, or other improvements that
are to remain. Any facilities not designated for removal, including but
not limited to water facilities, storm sewers, sanitary sewers, power
poles, underground utilities, or other improvements, damaged due to
the Contractor’s operations, shall be repaired or replaced by the
Contractor to the satisfaction of the Engineer at no additional expense
to the Contracting Agency.
Water main removal shall include the pipe and associated fittings,
corporation stops, saddles, repair bands, spools, sleeves, couplings,
and thrust blocks, if a separate contract bid item is not included for
removal of structures and obstructions or for one or more specifically
identified components.
Water valve removal shall include disconnecting the valve from the
attached pipe and/or fitting(s), and removing the valve, together with
the associated valve box, including the base, middle, upper and
sections as applicable, risers if any, and lid, and associated asphalt or
concrete pad, if any.
Hydrant assemblies shall be removed to the branch of the hydrant tee
at the water main where shown on the Plans, or as may be directed by
the Engineer. Where the hydrant assembly is connected to existing
water main that is designated for removal, the hydrant assembly tee
shall be removed with the water main.
Rock Creek Culvert Replacement/Lincoln 2 - 5 June 3, 2021
Project Number: 13-3007.5
All removed water facilities shall become the property of the Contractor
and shall be processed, hauled, and disposed in accordance with the
contract provisions, unless otherwise noted on the Plans or specified in
the Special Provisions. If designated on the Plans or Special Provisions,
removed hydrants, valves, fittings, and/or special water facility
components shall be salvaged to the Contracting Agency, and shall be
delivered to a location as specified in the Contract or as may be
directed by the Contracting Agency’s inspector. Cast iron, ductile iron,
or steel pipe may be salvaged by the Contractor, or disposed by the
Contractor at a permitted site.
Where the remaining portion of the existing water main is to remain in
service following removal of the designated water main, valve, hydrant
assembly, or water service connection, the Contractor shall perform one
or more of the following as applicable and as may be directed by the
Engineer:
Water Main:
• Install permanent cast iron or ductile iron cap or plug with
associated fittings, and thrust block if shown on the Plans; or
• Install temporary blowoff in accordance with Covington Water
District Standard Plan 27; or
• Install temporary blind flange or restrained MJ plug at exposed run
or branch of a tee to remain if a temporary blowoff will not be
necessary as determined by the Engineer.
Following satisfactory removal of the water facilities, and water facility
decommissioning as applicable, the vacant trench or excavation shall be
backfilled, and completed to grade.
In public rights-of-way, the trench shall be backfilled to subgrade with
Crushed Surfacing Top Course for Trench Backfill, compacted in
accordance with Method C compaction as provided in Section 2-03.3,
and graded to provide a firm, smooth and uniform surface for
placement of subsequent surfacing materials to finish grade.
SECTION 2-02.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-02.4 Measurement
“Remove and Salvage Water Valve, 12-Inch” will be measured per
each.
“Remove Ductile Iron Water Main, 12-Inch” will be measured by the
linear foot
along the centerline of the water main pipe removed, including fittings
and shall not consider size of water main removed.
“Remove Steel Casing, 24-Inch” will be measured by the linear foot
along the
centerline of the water main pipe removed and shall not consider size of
the casing removed.
Rock Creek Culvert Replacement/Lincoln 2 - 6 June 3, 2021
Project Number: 13-3007.5
“Remove and Salvage Hydrant Assembly” will be measured per each.
SECTION 2-02.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-02.5 Payment
Whether included above, or shown on the plans, any removal of
structure and obstruction work required to complete the project work
not covered under other removal items shall be included in the bid item
for “Removal of Structures and Obstructions” in accordance with
Section 1-04.1.
Payment will be made in accordance with Section 1-04.1, for the
following bid items when they are included in the Proposal:
The unit Contract price per each for “Remove and Salvage Water Valve,
12-Inch” shall be full compensation for all costs to remove the existing
water valve as specified in Section 2-02.3(5).
The unit Contract price per linear foot for “Remove Ductile Iron Water
Main, 12-Inch,” shall be full compensation for all costs incurred to
perform the Work described in Section 2-02.3(5), including: removal of
pipe, fittings, restrained joints, spools, sleeves, couplings, repair bands,
and associated corporation stops and saddles for water service lines;
compacted trench backfill; removal of concrete thrust blocks;
coordinating with Covington Water District for main isolation, cutting
the pipe, and draining water to approved steel roll off tank, disposal of
removed pipe including haul and required permits; filling the exposed
ends of pipe to remain with concrete, or permanently or temporarily
capping or plugging the exposed ends of water main to remain in
service, excavating including haul, temporary stockpiling, stockpile
protection; backfilling the trench with crushed surfacing as specified;
material handling, processing, salvaging if specified; and haul to and
disposal at a site permitted to receive removed material.
The unit Contract price per linear foot for “Remove Steel Casing, 24-
Inch,” shall be full compensation for all costs incurred to perform the
Work described in Section 2-02.3(5), including: removal and disposal of
steel casing, casing spacers, casing supports, casing backfill, end seals
and associated appurtenances.
The unit Contract price per each for “Remove and Salvage Hydrant
Assembly” shall be full compensation for all costs to remove the
existing hydrant assembly as specified in Section 2-02.3(5).
Payment will be made in accordance with Section 1-04.1, for the
following bid items when they are included in the Proposal:
The unit contract price per square yard for “Remove Existing Asphalt
Concrete Pavement” constitutes complete compensation for all labor,
materials, tools, supplies and equipment required to remove existing
asphalt from sidewalk for a depth of 3 inches, and from roads for a
depth of 6 inches. Included in this price is the cost of hauling and
Rock Creek Culvert Replacement/Lincoln 2 - 7 June 3, 2021
Project Number: 13-3007.5
disposal of the asphalt pavement. Should the Contractor encounter
pavement to be removed which is thicker than 6 inches it shall be paid
according to the following formula:
actual depth in inches
(square yards) x 6 inches = quantity
For example, if the Contractor encounters pavement to be removed
which is 8 inches thick and 100 square yards then the quantity would
be:
8
100’ x 6 = 133 S.Y. No other compensation shall be allowed.
The unit price contract price per lineal foot for “Saw Cut Existing
Asphalt Concrete Pavement” constitutes complete compensation for all
materials, labor and equipment required to saw cut existing pavement
to a depth of 6 inches in accordance with the plans and specifications.
Should the Contractor encounter pavement to be removed which is
thicker than 6 inches, it shall be paid according to the following
formula:
actual depth in inches
(length) x 6 inches = quantity
For example, if the Contractor encounters pavement to be saw cut
which is 8 inches thick and 100 linear feet then the quantity would be:
8
length x 6 = 133 LF. No other compensation shall be allowed.
A vertical saw cut shall be required between any existing pavement,
sidewalk, or curb that is to remain and the portion to be removed. The
costs of other types of pavement cutting, such as “wheel cutting”, shall
be considered incidental to other bid items and no payment will be
allowed under this item unless the pavement is actually saw cut.
2-03 ROADWAY EXCAVATION AND EMBANKMENT
2-03.3 Construction Requirements
SECTION 2-03.3(7) IS REVISED AS FOLLOWS:
2-03.3(7) Disposal of Surplus Material
A waste site has not been provided by the Engineer for the disposal
and/or storage of surplus materials and debris.
It shall be the responsibility of each bidder to thoroughly plan for
material disposal at the time of project planning and bid preparation.
The Contractor shall provide the Engineer with copies of all permits for
disposal and/or storage of surplus materials within ten (10) calendar
Rock Creek Culvert Replacement/Lincoln 2 - 8 June 3, 2021
Project Number: 13-3007.5
days after award of the contract. The Engineer will review the permit(s)
and waste site(s) and either allow the use of or reject the disposal
and/or storage site(s) within fourteen (14) calendar days after receipt
of the permits. The Contractor is responsible for obtaining permits from
the appropriate agency.
SECTION 2-03.3(7)C IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-03.3(7)C Contractor-Provided Disposal Site
The City has not provided a waste site. The Contractor shall arrange for
disposal and provide any necessary disposal sites in accordance with
Section 2-03.3(7)C of the WSDOT Standard Specifications.
The Contractor is responsible for determining which permits are
required for the selected disposal sites.
Within the City, wetlands are identified by using the Corps of Engineers
Wetlands Delineation Manual dated January 1987.
SECTION 2-03.3(14)B IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-03.3(14)B Earth Embankment Construction
The Contractor shall prioritize use of suitable native material over
Gravel Borrow, including stockpiling these materials as necessary. Any
remaining materials shall be removed at end of the project.\
SECTION 2-03.3(14)C IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-03.3(14)C Compacting Earth Embankments
Compaction Method C shall be used.
SECTION 2-03.3(14)D IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-03.3(14)D Compaction and Moisture Control Tests
Maximum density will be determined by the Modified Proctor Method
ASTM D-1557.
All compaction tests if required will be performed by the City.
SECTION 2-03.3(14)M IS SUPPLEMENTED WITH THE FOLLOWING:
2-03.3(14)M Excavation of Channels and Ditches
Channel Excavation Incl. Haul
The work described in this section includes excavation and grading of
stream channels, including haul, placement, grading and compacting
excavated material, or otherwise disposing of the material.
Rock Creek Culvert Replacement/Lincoln 2 - 9 June 3, 2021
Project Number: 13-3007.5
Definitions
Excavated Material: All materials excavated from stream channels to
the lines, grades and elevations included in the plans.
Backfill: Suitable excavated materials from the site to be reused in
grading are as shown on the plans.
Unauthorized Excavations: Excavations outside the lines, grades and
elevations included in the plans, without approval by the Engineer.
The Contractor shall:
A. Excavate to the lines, grades, and elevations shown on the Plans.
No additional compensation will be made for excess excavation
beyond the lines, grades, and elevations shown in the Plans unless
approved by the Engineer.
B. Repair unauthorized excavations beyond the lines and grades shown
in the Plans, at no additional cost to the Owner.
C. Shape the surface of the excavation, grading, and fill area to
uniform slopes and cross-sections and eliminate all ruts and low-
places on the fill that could hold water. Cut out soft spots, fill low
spots and trim high spots to comply with required surface
tolerances.
D. Not construct embankments during periods where the fill material
may freeze while being placed. Do not place fill material on frozen
soil.
Excavation shall be performed in a manner and sequence that will
provide proper drainage, water and turbidity control at all times.
Repair unauthorized excavations beyond the lines and grades shown
on the plans, at no additional cost to the Owner.
Unsuitable materials as identified by the Engineer shall be
characterized and placed in temporary stockpile and removed and
disposed at off-site location as required by the Engineer.
SECTION 2-03.4 IS REVISED AS FOLLOWS:
2-03.4 Measurement
Computation of Excavation and Embankment Quantities
Only one determination of the original ground elevation will be made on
this project. Measurement for Roadway Excavation including Haul,
Embankment Compaction, and Channel Excavation Including Haul will
be based on the original ground elevation recorded previous to the
award of this contract and neat lines as shown in the Plans. These
quantities are listed in the Bid Proposal. Deductions have been made to
Roadway Excavation calculations to account for the removal of material
during clearing and grubbing and pavement removal. It is anticipated
that depth of removal of organic material during clearing and grubbing
for this project will vary and a factor of minus 6 inches has been used
Rock Creek Culvert Replacement/Lincoln 2 - 10 June 3, 2021
Project Number: 13-3007.5
to determine ground elevation after clearing and grubbing, and a factor
of 12 inches has been used in areas of pavement removal.
If discrepancies are discovered in the ground elevations which will
materially affect the quantities of earthwork, the original computations
of earthwork quantities will be adjusted accordingly. Earthwork
quantities will be computed, either manually or by means of electronic
data processing equipment, by use of the average end area method or
by the finite element analysis method utilizing digital terrain modeling
techniques.
SECTION 2-03.5 IS SUPPLEMENTED WITH THE FOLLOWING:
2-03.5 Payment
The unit Contract price per cubic yard for “Channel Excavation Incl.
Haul”, shall be full pay for all labor, equipment, materials work as
specified, including excavation, loading, hauling, stockpiling, placing,
grading and compacting, or otherwise disposing of excavated material.
Stockpiling of excavated material shall be included in the Contract unit
bid items for excavation. No additional payment will be made for
stockpiling, double or re-handling of excavated material.
2-06 SUBGRADE PREPARATION
2-06.3 Construction Requirements
SECTION 2-06.3(1) ITEM 6 IS DELETED AND REPLACED WITH THE
FOLLOWING:
2-06.3(1) Subgrade for Surfacing
6. The prepared subgrade shall be compacted in the top 0.50 foot to
95 percent of maximum dry density per ASTM D-1557 for a cut
section. If the underlying subgrade is too soft to permit
compaction of the upper 0.5 foot layer, the Contractor shall loosen
(or excavate and remove), and compact the subgrade until the top
layer can meet compaction requirements. Fill sections shall be
prepared in accordance with the Standard Specification Section
2-03.3(14)C, Method B except ASTM D-1557 shall determine the
maximum density.
SECTION 2-06.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-06.5 Measurement and Payment
The cost for work required for compaction of the subgrade shall be
included by the Contractor in the unit contract price of other bid items.
Rock Creek Culvert Replacement/Lincoln 2 - 11 June 3, 2021
Project Number: 13-3007.5
2-12 CONSTRUCTION GEOSYNTHETIC
SECTION 2-12.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-12.1 Description
This work shall consist of furnishing and installing non-woven geotextile
fabric at the locations shown on the plans and described in the
specifications.
SECTION 2-12.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-12.2 Materials
Non-woven geotextile fabric shall meet the material requirements of
Section 9-33 of the WSDOT Standard Specifications for high
survivability, separation and soil stabilization, and underground
drainage for each geotextile use as specified on the plans or in the Kent
Special Provisions.
SECTION 2-12.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-12.3 Construction Requirements
The Contractor shall take all necessary precautions to not tear or
damage the fabric during installation. The fabric shall be laid down by
hand. Folds or creases in the fabric shall be pulled flat. The fabric sides
and ends shall be anchored or weighted sufficiently to prevent
slouching. Joints or seams shall be overlapped a minimum of two (2)
feet.
SECTION 2-12.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-12.4 Measurement
Non-woven geotextile fabric shall be measured per square yard of
materials placed.
SECTION 2-12.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
2-12.5 Payment
The unit contract price per square yard for “Geotextile Fabric, Non-
Woven” constitutes complete compensation for all labor, materials,
tools, supplies, and equipment necessary to furnish and install the
fabric at the locations shown on the plans and described in the
specifications.
Rock Creek Culvert Replacement/Lincoln 4 - 1 June 3, 2021
Project Number: 13-3007.5
DIVISION 4 – BASES
DIVISION 4 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW SECTION:
4-03 GRAVEL BORROW
4-03.1 Description
This work shall consist of constructing one or more layers of gravel
borrow upon a prepared subgrade in accordance with these
specifications and in conformity with the lines, grades, depths, and
typical cross-section shown in the plans or as established by the
Engineer.
4-03.2 Materials
Materials shall meet the minimum requirements of the following section
in the Kent Special Provisions:
Gravel Borrow .......................... 9-03.14(1)
4-03.3 Construction Requirements
Gravel borrow shall be uniformly spread upon the prepared subgrade to
the depth, width, and cross-sections shown in the plans. Construction
methods used shall meet the appropriate requirements of Section
4-04.3.
4-03.4 Measurement
Gravel borrow will be measured in the same manner prescribed for the
measurement of crushed surfacing materials as set forth in Section
4-04.4.
4-03.5 Payment
Payment will be made in accordance with Section 1-04.1, for the
following bid item when they are included in the Proposal:
The unit contract price per ton for “Gravel Borrow, Including Haul and
Compaction” constitutes complete compensation for furnishing all labor,
materials, tools, supplies, and equipment necessary to haul, place,
finish grade, and compact the gravel borrow as shown on the plans and
described in the specifications. This item shall be used for roadway
subbase, backfill for water, storm sewer, electrical conduit trenches,
and other excavation backfill and compaction unless otherwise noted.
4-04 BALLAST AND CRUSHED SURFACING
4-04.3 Construction Requirements
Rock Creek Culvert Replacement/Lincoln 4 - 2 June 3, 2021
Project Number: 13-3007.5
SECTION 4-04.3(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
4-04.3(2) Subgrade
The Contractor is responsible for any delays or costs incurred as a
result of placing ballast or surface materials before approval is received
from the Engineer.
SECTION 4-04.3(5) IS DELETED AND REPLACED WITH THE FOLLOWING:
4-04.3(5) Shaping and Compaction
Surfacing shall be compacted in depths not to exceed 6 inches except
top course shall not exceed 2 inches unless otherwise directed. Density
shall be at least 95 percent of maximum density per ASTM D-1557
using a nuclear gauge. Compaction of each layer must be approved by
the Engineer before the next succeeding layer of surfacing or pavement
is placed thereon.
SECTION 4-04.3(7) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
4-04.3(7) Miscellaneous Requirements
The Contractor is solely responsible for any delays or additional costs
incurred as a result of placing ballast or succeeding courses of surfacing
materials before approval to proceed is received from the Engineer.
SECTION 4-04.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
4-04.5 Payment
“Crushed Surfacing Top Course, 5/8 Inch Minus”
“Crushed Surfacing Base Course, 1-1/4 Inch Minus”
The unit contract price per ton for the above items constitutes complete
compensation for furnishing all labor, materials, tools, supplies, and
equipment necessary to haul, place, finish grade, and compact the
material as shown on the plans and described in the specifications.
These items shall also be used for roadway or driveway remedial work
or patching as requested by the Engineer. Quantities used for pipe zone
bedding shall be measured and paid separately under the appropriate
bid item.
Rock Creek Culvert Replacement/Lincoln 5 - 1 June 3, 2021
Project Number: 13-3007.5
DIVISION 5 – SURFACE TREATMENTS AND PAVEMENTS
NOTE: If the contract also includes underground utility construction, permanent
surface treatments and pavements shall not be placed until an as-built survey and
testing of the new underground utilities have been completed.
Verification that utility construction conforms to the line and grade requirements of
Section 7-08.3(2)B of the WSDOT Standard Specifications shall be made by the
Engineer prior to authorizing paving to begin. Also, each new utility must pass all
appropriate tests specified herein for the type of utility prior to paving.
5-02 BITUMINOUS SURFACE TREATMENT
SECTION 5-02.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
5-02.5 Payment
Anti-stripping additive shall be included in the price of asphalt (grade)
per ton. The quantity of asphalt material shall not be reduced by the
quantity of anti-stripping additive.
5-04 HOT MIX ASPHALT
SECTION 5-04 IS DELETED AND REPLACED IN ITS ENTIRETY WITH THE
FOLLOWING:
5-04.1 Description
This Work shall consist of providing and placing one or more layers of
plant-mixed hot mix asphalt (HMA) on a prepared foundation or base in
accordance with these Specifications and the lines, grades, thicknesses,
and typical cross-sections shown in the Plans. The manufacture of HMA
may include warm mix asphalt (WMA) processes in accordance with
these Specifications. WMA processes include organic additives, chemical
additives, and foaming.
HMA shall be composed of asphalt binder and mineral materials as may
be required, mixed in the proportions specified to provide a
homogeneous, stable, and workable mixture.
5-04.2 Materials
Materials shall meet the requirements of the following sections:
Portland Cement 9-01
Asphalt Binder 9-02.1(4)
Cationic Emulsified Asphalt 9-02.1(6)
Anti-Stripping Additive 9-02.4
HMA Additive 9-02.5
Sand 9-03.1(2)
(As noted in 5-04.3(5)C for crack sealing)
Aggregates 9-03.8
Recycled Asphalt Pavement 9-03.8(3)B
Rock Creek Culvert Replacement/Lincoln 5 - 2 June 3, 2021
Project Number: 13-3007.5
Mineral Filler 9-03.8(5)
Recycled Material 9-03.21
Joint Sealant 9-04.2
Foam Backer Rod 9-04.2(3)A
The Contract documents may establish that the various mineral
materials required for the manufacture of HMA will be furnished in
whole or in part by the Contracting Agency. If the documents do not
establish the furnishing of any of these mineral materials by the
Contracting Agency, the Contractor shall be required to furnish such
materials in the amounts required for the designated mix. Mineral
materials include coarse and fine aggregates, and mineral filler.
The Contractor may choose to utilize recycled asphalt pavement (RAP)
in the production of HMA. The RAP may be from pavements removed
under the Contract, if any, or pavement material from an existing
stockpile.
The Contractor may use up to 20 percent RAP by total weight of HMA
with no additional sampling or testing of the RAP. The RAP shall be
sampled and tested at a frequency of one sample for every 1,000 tons
produced and not less than ten samples per project. The asphalt
content and gradation test data shall be reported to the Contracting
Agency when submitting the mix design for approval on the QPL. The
Contractor shall include the RAP as part of the mix design as defined in
these Specifications.
The grade of asphalt binder shall be as required by the Contract.
Blending of asphalt binder from different sources is not permitted.
The Contractor may only use warm mix asphalt (WMA) processes in the
production of HMA with 20 percent or less RAP by total weight of HMA.
The Contractor shall submit to the Engineer for approval the process
that is proposed and how it will be used in the manufacture of HMA.
Production of aggregates shall comply with the requirements of Section
3-01.
Preparation of stockpile site, the stockpiling of aggregates, and the
removal of aggregates from stockpiles shall comply with the
requirements of Section 3-02.
ESAL's
The minimum number of ESAL's for the design and acceptance of the
HMA in the contract shall be 11 million.
5-04.2(1) How to Get an HMA Mix Design on the QPL
If the contractor wishes to submit a mix design for inclusion in the
Qualified Products List (QPL), comply with each of the following:
Develop the mix design in accordance with WSDOT SOP 732.
Rock Creek Culvert Replacement/Lincoln 5 - 3 June 3, 2021
Project Number: 13-3007.5
Develop a mix design that complies with Sections 9-03.8(2) and 9-
03.8(6).
Develop a mix design no more than 6 months prior to submitting it
for QPL evaluation.
Submit mix designs to the WSDOT State Materials Laboratory in
Tumwater, including WSDOT Form 350-042.
Include representative samples of the materials that are to be
used in the HMA production as part of the mix design submittal.
Identify the brand, type, and percentage of anti-stripping additive
in the mix design submittal.
Include with the mix design submittal a certification from the
asphalt binder supplier that the anti-stripping additive is
compatible with the crude source and the formulation of asphalt
binder proposed for use in the mix design.
Do not include warm mix asphalt (WMA) additives when
developing a mix design or submitting a mix design for QPL
evaluation. The use of warm mix asphalt (WMA) additives is not
part of the process for obtaining approval for listing a mix design
on the QPL. Refer to Section 5-04.2(2)B.
The Contracting Agency’s basis for approving, testing, and evaluating
HMA mix designs for approval on the QPL is dependent on the
contractual basis for acceptance of the HMA mixture, as shown in Table
1.
Table 1
Basis for Contracting Agency Evaluation of HMA Mix Designs for
Approval on the QPL
Contractual Basis for
Acceptance of HMA
Mixture
[see Section
5-04.3(9)]
Basis for Contracting
Agency Approval of
Mix Design for
Placement on QPL
Contracting Agency
Materials Testing for
Evaluation of the Mix
Design
Statistical Evaluation WSDOT Standard
Practice QC-8
The Contracting Agency will
test the mix design materials
for compliance with Sections
9-03.8(2) and 9-03.8(6).
Visual Evaluation Review of Form 350-042
for compliance with
Sections 9-03.8(2) and
9-03.8(6)
The Contracting Agency may
elect to test the mix design
materials, or evaluate in
accordance with WSDOT
Standard Practice QC-8, at
its sole discretion.
If the Contracting Agency approves the mix design, it will be listed on
the QPL for 12 consecutive months. The Contracting Agency may
extend the 12 month listing provided the Contractor submits a
certification letter to the Qualified Products Engineer verifying that the
aggregate source and job mix formula (JMF) gradation, and asphalt
binder crude source and formulation have not changed. The Contractor
may submit the certification no sooner than three months prior to
expiration of the initial 12 month mix design approval. Within 7
calendar days of receipt of the Contractor’s certification, the
Rock Creek Culvert Replacement/Lincoln 5 - 4 June 3, 2021
Project Number: 13-3007.5
Contracting Agency will update the QPL. The maximum duration for
approval of a mix design and listing on the QPL will be 24 months from
the date of initial approval or as approved by the Engineer.
5-04.2(1)A Vacant
5-04.2(2) Mix Design – Obtaining Project Approval
No paving shall begin prior to the approval of the mix design by the
Engineer.
Nonstatistical evaluation will be used for all HMA not designated as
Commercial HMA in the contract documents.
Commercial evaluation will be used for Commercial HMA and for other
classes of HMA in the following applications: sidewalks, road
approaches, ditches, slopes, paths, trails, gores, prelevel, and
pavement repair. Other nonstructural applications of HMA accepted by
commercial evaluation shall be as approved by the Project Engineer.
Sampling and testing of HMA accepted by commercial evaluation will be
at the option of the Project Engineer. The Proposal quantity of HMA that
is accepted by commercial evaluation will be excluded from the
quantities used in the determination of nonstatistical evaluation.
Nonstatistical Mix Design. Fifteen days prior to the first day of
paving the contractor shall provide one of the following mix design
verification certifications for Contracting Agency review;
The WSDOT Mix Design Evaluation Report from the current WSDOT
QPL, or one of the mix design verification certifications listed
below.
The proposed HMA mix design on WSDOT Form 350-042 with the
seal and certification (stamp and signature) of a valid licensed
Washington State Professional Engineer.
The Mix Design Report for the proposed HMA mix design developed
by a qualified City or County laboratory that is within one year of
the approval date.
The mix design shall be performed by a lab accredited by a national
authority such as Laboratory Accreditation Bureau, L-A-B for
Construction Materials Testing, The Construction Materials Engineering
Council (CMEC’s) ISO 17025 or AASHTO Accreditation Program (AAP)
and shall supply evidence of participation in the AASHTO: resource
proficiency sample program.
Mix designs for HMA accepted by Nonstatistical evaluation shall;
Have the aggregate structure and asphalt binder content determined in
accordance with WSDOT Standard Operating Procedure 732 and meet
the requirements of Sections 9-03.8(2), except that Hamburg testing
for ruts and stripping are at the discretion of the Engineer, and
9-03.8(6).
Rock Creek Culvert Replacement/Lincoln 5 - 5 June 3, 2021
Project Number: 13-3007.5
Have anti-strip requirements, if any, for the proposed mix design
determined in accordance with AASHTO T 283 or T 324, or based on
historic anti-strip and aggregate source compatibility from previous
WSDOT lab testing.
At the discretion of the Engineer, agencies may accept verified mix
designs older than 12 months from the original verification date with a
certification from the Contractor that the materials and sources are the
same as those shown on the original mix design.
Commercial Evaluation Approval of a mix design for “Commercial
Evaluation” will be based on a review of the Contractor’s submittal of
WSDOT Form 350-042 (For commercial mixes, AASHTO T 324
evaluation is not required) or a Mix Design from the current WSDOT
QPL or from one of the processes allowed by this section. Testing of the
HMA by the Contracting Agency for mix design approval is not required.
For the Bid Item Commercial HMA, the Contractor shall select a class of
HMA and design level of Equivalent Single Axle Loads (ESAL’s) specified
herein.
5-04.2(2)B Using Warm Mix Asphalt Processes
The Contractor may elect to use additives that reduce the optimum
mixing temperature or serve as a compaction aid for producing HMA.
Additives include organic additives, chemical additives and foaming
processes. The use of Additives is subject to the following:
Do not use additives that reduce the mixing temperature more
than allowed in Section 5-04.3(6) in the production of mixtures.
Before using additives, obtain the Engineer’s approval using
WSDOT Form 350-076 to describe the proposed additive and
process.
5-04.3 Construction Requirements
5-04.3(1) Weather Limitations
Do not place HMA for wearing course on any Traveled Way beginning
October 1st through March 31st of the following year without written
concurrence from the Engineer.
Do not place HMA on any wet surface, or when the average surface
temperatures are less than those specified below, or when weather
conditions otherwise prevent the proper handling or finishing of the
HMA.
Rock Creek Culvert Replacement/Lincoln 5 - 6 June 3, 2021
Project Number: 13-3007.5
Minimum Surface Temperature for Paving
Compacted Thickness
(Feet)
Wearing Course Other Courses
Less than 0.10 55◦F 45◦F
0.10 to 0.20 45◦F 35◦F
More than 0.20 35◦F 35◦F
5-04.3(2) Paving Under Traffic
When the Roadway being paved is open to traffic, the requirements of
this Section shall apply.
The Contractor shall keep intersections open to traffic at all times
except when paving the intersection or paving across the intersection.
During such time, and provided that there has been an advance
warning to the public, the intersection may be closed for the minimum
time required to place and compact the mixture. In hot weather, the
Engineer may require the application of water to the pavement to
accelerate the finish rolling of the pavement and to shorten the time
required before reopening to traffic.
Before closing an intersection, advance warning signs shall be placed
and signs shall also be placed marking the detour or alternate route.
During paving operations, temporary pavement markings shall be
maintained throughout the project. Temporary pavement markings
shall be installed on the Roadway prior to opening to traffic. Temporary
pavement markings shall be in accordance with Section 8-23.
All costs in connection with performing the Work in accordance with
these requirements, except the cost of temporary pavement markings,
shall be included in the unit Contract prices for the various Bid items
involved in the Contract.
5-04.3(3) Equipment
5-04.3(3)A Mixing Plant
Plants used for the preparation of HMA shall conform to the following
requirements:
1. Equipment for Preparation of Asphalt Binder – Tanks for the
storage of asphalt binder shall be equipped to heat and hold the
material at the required temperatures. The heating shall be
accomplished by steam coils, electricity, or other approved means
so that no flame shall be in contact with the storage tank. The
circulating system for the asphalt binder shall be designed to
ensure proper and continuous circulation during the operating
period. A valve for the purpose of sampling the asphalt binder shall
be placed in either the storage tank or in the supply line to the
mixer.
2. Thermometric Equipment – An armored thermometer, capable
of detecting temperature ranges expected in the HMA mix, shall be
Rock Creek Culvert Replacement/Lincoln 5 - 7 June 3, 2021
Project Number: 13-3007.5
fixed in the asphalt binder feed line at a location near the charging
valve at the mixer unit. The thermometer location shall be
convenient and safe for access by Inspectors. The plant shall also
be equipped with an approved dial-scale thermometer, a mercury
actuated thermometer, an electric pyrometer, or another approved
thermometric instrument placed at the discharge chute of the drier
to automatically register or indicate the temperature of the heated
aggregates. This device shall be in full view of the plant operator.
3. Heating of Asphalt Binder – The temperature of the asphalt
binder shall not exceed the maximum recommended by the
asphalt binder manufacturer nor shall it be below the minimum
temperature required to maintain the asphalt binder in a
homogeneous state. The asphalt binder shall be heated in a
manner that will avoid local variations in heating. The heating
method shall provide a continuous supply of asphalt binder to the
mixer at a uniform average temperature with no individual
variations exceeding 25°F. Also, when a WMA additive is included
in the asphalt binder, the temperature of the asphalt binder shall
not exceed the maximum recommended by the manufacturer of
the WMA additive.
4. Sampling and Testing of Mineral Materials – The HMA plant
shall be equipped with a mechanical sampler for the sampling of
the mineral materials. The mechanical sampler shall meet the
requirements of Section 1-05.6 for the crushing and screening
operation. The Contractor shall provide for the setup and operation
of the field testing facilities of the Contracting Agency as provided
for in Section 3-01.2(2).
5. Sampling HMA – The HMA plant shall provide for sampling HMA
by one of the following methods:
a. A mechanical sampling device attached to the HMA plant.
b. Platforms or devices to enable sampling from the hauling
vehicle without entering the hauling vehicle.
5-04.3(3)B Hauling Equipment
Trucks used for hauling HMA shall have tight, clean, smooth metal beds
and shall have a cover of canvas or other suitable material of sufficient
size to protect the mixture from adverse weather. Whenever the
weather conditions during the work shift include, or are forecast to
include, precipitation or an air temperature less than 45°F or when time
from loading to unloading exceeds 30 minutes, the cover shall be
securely attached to protect the HMA.
The Contractor shall provide an environmentally benign means to
prevent the HMA mixture from adhering to the hauling equipment.
Excess release agent shall be drained prior to filling hauling equipment
with HMA. Petroleum derivatives or other coating material that
contaminate or alter the characteristics of the HMA shall not be used.
For live bed trucks, the conveyer shall be in operation during the
process of applying the release agent.
Rock Creek Culvert Replacement/Lincoln 5 - 8 June 3, 2021
Project Number: 13-3007.5
5-04.3(3)C Pavers
HMA pavers shall be self-contained, power-propelled units, provided
with an internally heated vibratory screed and shall be capable of
spreading and finishing courses of HMA plant mix material in lane
widths required by the paving section shown in the Plans.
The HMA paver shall be in good condition and shall have the most
current equipment available from the manufacturer for the prevention
of segregation of the HMA mixture installed, in good condition, and in
working order. The equipment certification shall list the make, model,
and year of the paver and any equipment that has been retrofitted.
The screed shall be operated in accordance with the manufacturer’s
recommendations and shall effectively produce a finished surface of the
required evenness and texture without tearing, shoving, segregating, or
gouging the mixture. A copy of the manufacturer’s recommendations
shall be provided upon request by the Contracting Agency. Extensions
will be allowed provided they produce the same results, including ride,
density, and surface texture as obtained by the primary screed.
Extensions without augers and an internally heated vibratory screed
shall not be used in the Traveled Way.
When specified in the Contract, reference lines for vertical control will
be required. Lines shall be placed on both outer edges of the Traveled
Way of each Roadway. Horizontal control utilizing the reference line will
be permitted. The grade and slope for intermediate lanes shall be
controlled automatically from reference lines or by means of a mat
referencing device and a slope control device. When the finish of the
grade prepared for paving is superior to the established tolerances and
when, in the opinion of the Engineer, further improvement to the line,
grade, cross-section, and smoothness can best be achieved without the
use of the reference line, a mat referencing device may be substituted
for the reference line. Substitution of the device will be subject to the
continued approval of the Engineer. A joint matcher may be used
subject to the approval of the Engineer. The reference line may be
removed after the completion of the first course of HMA when approved
by the Engineer. Whenever the Engineer determines that any of these
methods are failing to provide the necessary vertical control, the
reference lines will be reinstalled by the Contractor.
The Contractor shall furnish and install all pins, brackets, tensioning
devices, wire, and accessories necessary for satisfactory operation of
the automatic control equipment.
If the paving machine in use is not providing the required finish, the
Engineer may suspend Work as allowed by Section 1-08.6. Any cleaning
or solvent type liquids spilled on the pavement shall be thoroughly
removed before paving proceeds.
Rock Creek Culvert Replacement/Lincoln 5 - 9 June 3, 2021
Project Number: 13-3007.5
5-04.3(3)E Rollers
Rollers shall be of the steel wheel, vibratory, oscillatory, or pneumatic
tire type, in good condition and capable of reversing without backlash.
Operation of the roller shall be in accordance with the manufacturer’s
recommendations. When ordered by the Engineer for any roller planned
for use on the project, the Contractor shall provide a copy of the
manufacturer’s recommendation for the use of that roller for
compaction of HMA. The number and weight of rollers shall be sufficient
to compact the mixture in compliance with the requirements of Section
5-04.3(10). The use of equipment that results in crushing of the
aggregate will not be permitted. Rollers producing pickup, washboard,
uneven compaction of the surface, displacement of the mixture or other
undesirable results shall not be used.
5-04.3(4) Preparation of Existing Paved Surfaces
When the surface of the existing pavement or old base is irregular, the
Contractor shall bring it to a uniform grade and cross-section as shown
on the Plans or approved by the Engineer.
Preleveling of uneven or broken surfaces over which HMA is to be
placed may be accomplished by using an asphalt paver, a motor patrol
grader, or by hand raking, as approved by the Engineer.
Compaction of preleveling HMA shall be to the satisfaction of the
Engineer and may require the use of small steel wheel rollers, plate
compactors, or pneumatic rollers to avoid bridging across preleveled
areas by the compaction equipment. Equipment used for the
compaction of preleveling HMA shall be approved by the Engineer.
Before construction of HMA on an existing paved surface, the entire
surface of the pavement shall be clean. All fatty asphalt patches, grease
drippings, and other objectionable matter shall be entirely removed
from the existing pavement. All pavements or bituminous surfaces shall
be thoroughly cleaned of dust, soil, pavement grindings, and other
foreign matter. All holes and small depressions shall be filled with an
appropriate class of HMA. The surface of the patched area shall be
leveled and compacted thoroughly. Prior to the application of tack coat,
or paving, the condition of the surface shall be approved by the
Engineer.
A tack coat of asphalt shall be applied to all paved surfaces on which
any course of HMA is to be placed or abutted; except that tack coat
may be omitted from clean, newly paved surfaces at the discretion of
the Engineer. Tack coat shall be uniformly applied to cover the existing
pavement with a thin film of residual asphalt free of streaks and bare
spots at a rate between 0.02 and 0.10 gallons per square yard of
retained asphalt. The rate of application shall be approved by the
Engineer. A heavy application of tack coat shall be applied to all joints.
For Roadways open to traffic, the application of tack coat shall be
limited to surfaces that will be paved during the same working shift.
Rock Creek Culvert Replacement/Lincoln 5 - 10 June 3, 2021
Project Number: 13-3007.5
The spreading equipment shall be equipped with a thermometer to
indicate the temperature of the tack coat material.
Equipment shall not operate on tacked surfaces until the tack has
broken and cured. If the Contractor’s operation damages the tack coat
it shall be repaired prior to placement of the HMA.
The tack coat shall be CSS-1, or CSS-1h emulsified asphalt. The CSS-1
and CSS-1h emulsified asphalt may be diluted once with water at a rate
not to exceed one part water to one part emulsified asphalt. The tack
coat shall have sufficient temperature such that it may be applied
uniformly at the specified rate of application and shall not exceed the
maximum temperature recommended by the emulsified asphalt
manufacturer.
5-04.3(4)A Crack Sealing
5-04.3(4)A1 General
When the Proposal includes a pay item for crack sealing, seal all cracks
¼ inch in width and greater.
Cleaning: Ensure that cracks are thoroughly clean, dry and free of all
loose and foreign material when filling with crack sealant material. Use
a hot compressed air lance to dry and warm the pavement surfaces
within the crack immediately prior to filling a crack with the sealant
material. Do not overheat pavement. Do not use direct flame dryers.
Routing cracks is not required.
Sand Slurry: For cracks that are to be filled with sand slurry,
thoroughly mix the components and pour the mixture into the cracks
until full. Add additional CSS-1 cationic emulsified asphalt to the sand
slurry as needed for workability to ensure the mixture will completely
fill the cracks. Strike off the sand slurry flush with the existing
pavement surface and allow the mixture to cure. Top off cracks that
were not completely filled with additional sand slurry. Do not place the
HMA overlay until the slurry has fully cured.
The sand slurry shall consist of approximately 20 percent CSS-1
emulsified asphalt, approximately 2 percent portland cement, water (if
required), and the remainder clean Class 1 or 2 fine aggregate per
Section 9-03.1(2). The components shall be thoroughly mixed and then
poured into the cracks and joints until full. The following day, any
cracks or joints that are not completely filled shall be topped off with
additional sand slurry. After the sand slurry is placed, the filler shall be
struck off flush with the existing pavement surface and allowed to cure.
The HMA overlay shall not be placed until the slurry has fully cured. The
requirements of Section 1-06 will not apply to the portland cement and
sand used in the sand slurry.
In areas where HMA will be placed, use sand slurry to fill the cracks.
In areas where HMA will not be placed, fill the cracks as follows:
Rock Creek Culvert Replacement/Lincoln 5 - 11 June 3, 2021
Project Number: 13-3007.5
1. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant.
2. Cracks greater than 1 inch in width – fill with sand slurry.
Hot Poured Sealant: For cracks that are to be filled with hot poured
sealant, apply the material in accordance with these requirements and
the manufacturer’s recommendations. Furnish a Type 1 Working
Drawing of the manufacturer’s product information and
recommendations to the Engineer prior to the start of work, including
the manufacturer’s recommended heating time and temperatures,
allowable storage time and temperatures after initial heating, allowable
reheating criteria, and application temperature range. Confine hot
poured sealant material within the crack. Clean any overflow of sealant
from the pavement surface. If, in the opinion of the Engineer, the
Contractor’s method of sealing the cracks with hot poured sealant
results in an excessive amount of material on the pavement surface,
stop and correct the operation to eliminate the excess material.
5-04.3(4)A2 Crack Sealing Areas Prior to Paving
In areas where HMA will be placed, use sand slurry to fill the cracks.
5-04.3(4)A3 Crack Sealing Areas Not to be Paved
In areas where HMA will not be placed, fill the cracks as follows:
a. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant.
b. Cracks greater than 1 inch in width – fill with sand slurry.
5-04.3(4)B Vacant
5-04.3(4)C Pavement Repair
The Contractor shall excavate pavement repair areas and shall backfill
these with HMA in accordance with the details shown in the Plans and
as marked in the field. The Contractor shall conduct the excavation
operations in a manner that will protect the pavement that is to remain.
Pavement not designated to be removed that is damaged as a result of
the Contractor’s operations shall be repaired by the Contractor to the
satisfaction of the Engineer at no cost to the Contracting Agency. The
Contractor shall excavate only within one lane at a time unless
approved otherwise by the Engineer. The Contractor shall not excavate
more area than can be completely finished during the same shift,
unless approved by the Engineer.
Unless otherwise shown in the Plans or determined by the Engineer,
excavate to a depth of 1.0 feet. The Engineer will make the final
determination of the excavation depth required. The minimum width of
any pavement repair area shall be 40 inches unless shown otherwise in
the Plans. Before any excavation, the existing pavement shall be
sawcut or shall be removed by a pavement grinder. Excavated
materials will become the property of the Contractor and shall be
Rock Creek Culvert Replacement/Lincoln 5 - 12 June 3, 2021
Project Number: 13-3007.5
disposed of in a Contractor-provided site off the Right of Way or used in
accordance with Sections 2-02.3(3) or 9-03.21.
Asphalt for tack coat shall be required as specified in Section
5-04.3(4). A heavy application of tack coat shall be applied to all
surfaces of existing pavement in the pavement repair area.
Placement of the HMA backfill shall be accomplished in lifts not to
exceed 0.35-foot compacted depth. Lifts that exceed 0.35-foot of
compacted depth may be accomplished with the approval of the
Engineer. Each lift shall be thoroughly compacted by a mechanical
tamper or a roller.
5-04.3(5) Producing/Stockpiling Aggregates and RAP
Aggregates and RAP shall be stockpiled according to the requirements
of Section 3-02. Sufficient storage space shall be provided for each size
of aggregate and RAP. Materials shall be removed from stockpile(s) in a
manner to ensure minimal segregation when being moved to the HMA
plant for processing into the final mixture. Different aggregate sizes
shall be kept separated until they have been delivered to the HMA
plant.
5-04.3(5)A Vacant
5-04.3(6) Mixing
After the required amount of mineral materials, asphalt binder,
recycling agent and anti-stripping additives have been introduced into
the mixer the HMA shall be mixed until complete and uniform coating of
the particles and thorough distribution of the asphalt binder throughout
the mineral materials is ensured.
When discharged, the temperature of the HMA shall not exceed the
optimum mixing temperature by more than 25°F as shown on the
reference mix design report or as approved by the Engineer. Also, when
a WMA additive is included in the manufacture of HMA, the discharge
temperature of the HMA shall not exceed the maximum recommended
by the manufacturer of the WMA additive. A maximum water content of
2 percent in the mix, at discharge, will be allowed providing the water
causes no problems with handling, stripping, or flushing. If the water in
the HMA causes any of these problems, the moisture content shall be
reduced as directed by the Engineer.
Storing or holding of the HMA in approved storage facilities will be
permitted with approval of the Engineer, but in no event shall the HMA
be held for more than 24 hours. HMA held for more than 24 hours after
mixing shall be rejected. Rejected HMA shall be disposed of by the
Contractor at no expense to the Contracting Agency. The storage
facility shall have an accessible device located at the top of the cone or
about the third point. The device shall indicate the amount of material
in storage. No HMA shall be accepted from the storage facility when the
HMA in storage is below the top of the cone of the storage facility,
Rock Creek Culvert Replacement/Lincoln 5 - 13 June 3, 2021
Project Number: 13-3007.5
except as the storage facility is being emptied at the end of the
working shift.
Recycled asphalt pavement (RAP) utilized in the production of HMA shall
be sized prior to entering the mixer so that a uniform and thoroughly
mixed HMA is produced. If there is evidence of the recycled asphalt
pavement not breaking down during the heating and mixing of the
HMA, the Contractor shall immediately suspend the use of the RAP until
changes have been approved by the Engineer. After the required
amount of mineral materials, RAP, new asphalt binder and asphalt
rejuvenator have been introduced into the mixer the HMA shall be
mixed until complete and uniform coating of the particles and thorough
distribution of the asphalt binder throughout the mineral materials, and
RAP is ensured.
5-04.3(7) Spreading and Finishing
The mixture shall be laid upon an approved surface, spread, and struck
off to the grade and elevation established. HMA pavers complying with
Section 5-04.3(3) shall be used to distribute the mixture. Unless
otherwise directed by the Engineer, the nominal compacted depth of
any layer of any course shall not exceed the following:
HMA Class 1”
wearing course/final lift 0.17 feet
other courses 0.35 feet
HMA Class ¾” and HMA Class ½”
wearing course/final lift 0.17 feet
other courses 0.25 feet
HMA Class ⅜” 0.17 feet
On areas where irregularities or unavoidable obstacles make the use of
mechanical spreading and finishing equipment impractical, the paving
may be done with other equipment or by hand.
When more than one JMF is being utilized to produce HMA, the material
produced for each JMF shall be placed by separate spreading and
compacting equipment. The intermingling of HMA produced from more
than one JMF is prohibited. Each strip of HMA placed during a work shift
shall conform to a single JMF established for the class of HMA specified
unless there is a need to make an adjustment in the JMF.
Reference Section 8-20.3(14)C of the Kent Special Provisions for the
placement of traffic signal detection loops.
5-04.3(8) Aggregate Acceptance Prior to Incorporation in HMA
For HMA accepted by nonstatistical evaluation the aggregate properties
of sand equivalent, uncompacted void content and fracture will be
evaluated in accordance with Section 3-04. Sampling and testing of
aggregates for HMA accepted by commercial evaluation will be at the
option of the Engineer.
Rock Creek Culvert Replacement/Lincoln 5 - 14 June 3, 2021
Project Number: 13-3007.5
5-04.3(9) HMA Mixture Acceptance
Acceptance of HMA shall be as provided under nonstatistical, or
commercial evaluation.
Nonstatistical evaluation will be used for the acceptance of HMA unless
Commercial Evaluation is specified.
Commercial evaluation will be used for Commercial HMA and for other
classes of HMA in the following applications: sidewalks, road
approaches, ditches, slopes, paths, trails, gores, prelevel, temporary
pavement, and pavement repair. Other nonstructural applications of
HMA accepted by commercial evaluation shall be as approved by the
Engineer. Sampling and testing of HMA accepted by commercial
evaluation will be at the option of the Engineer.
The mix design will be the initial JMF for the class of HMA. The
Contractor may request a change in the JMF. Any adjustments to the
JMF will require the approval of the Engineer and may be made in
accordance with this section.
HMA Tolerances and Adjustments
1. Job Mix Formula Tolerances – The constituents of the mixture
at the time of acceptance shall be within tolerance. The tolerance
limits will be established as follows:
For Asphalt Binder and Air Voids (Va), the acceptance limits are
determined by adding the tolerances below to the approved JMF
values. These values will also be the Upper Specification Limit
(USL) and Lower Specification Limit (LSL) required in Section
1-06.2(2)D2
Property Non-Statistical Evaluation Commercial Evaluation
Asphalt Binder +/- 0.5% +/- 0.7%
Air Voids, Va 2.5% min. and 5.5% max N/A
For Aggregates in the mixture:
a. First, determine preliminary upper and lower acceptance
limits by applying the following tolerances to the approved
JMF.
Aggregate Percent Passing Non-Statistical
Evaluation
Commercial
Evaluation
1”, ¾”, ½”, and 3/8” sieves +/- 6% +/- 8%
No. 4 sieve +/-6% +/- 8%
No. 8 Sieve +/- 6% +/-8%
No. 200 sieve +/- 2.0% +/- 3.0%
b. Second, adjust the preliminary upper and lower acceptance
limits determined from step (a) the minimum amount
necessary so that none of the aggregate properties are
outside the control points in Section 9-03.8(6). The resulting
Rock Creek Culvert Replacement/Lincoln 5 - 15 June 3, 2021
Project Number: 13-3007.5
values will be the upper and lower acceptance limits for
aggregates, as well as the USL and LSL required in Section
1-06.2(2)D2.
2. Job Mix Formula Adjustments – An adjustment to the aggregate
gradation or asphalt binder content of the JMF requires approval of
the Engineer. Adjustments to the JMF will only be considered if the
change produces material of equal or better quality and may
require the development of a new mix design if the adjustment
exceeds the amounts listed below.
a. Aggregates –2 percent for the aggregate passing the 1½″,
1″, ¾″, ½″, ⅜″, and the No. 4 sieves, 1 percent for
aggregate passing the No. 8 sieve, and 0.5 percent for the
aggregate passing the No. 200 sieve. The adjusted JMF shall
be within the range of the control points in Section
9-03.8(6).
b. Asphalt Binder Content – The Engineer may order or
approve changes to asphalt binder content. The maximum
adjustment from the approved mix design for the asphalt
binder content shall be 0.3 percent
5-04.3(9)A Vacant
5-04.3(9)B Vacant
5-04.3(9)C Mixture Acceptance – Nonstatistical Evaluation
HMA mixture which is accepted by Nonstatistical Evaluation will be
evaluated by the Contracting Agency by dividing the HMA tonnage into
lots.
5-04.3(9)C1 Mixture Nonstatistical Evaluation – Lots and Sublots
A lot is represented by randomly selected samples of the same mix
design that will be tested for acceptance. A lot is defined as the total
quantity of material or work produced for each Job Mix Formula placed.
Only one lot per JMF is expected. A sublot shall be equal to one day’s
production or 800 tons, whichever is less except that the final sublot
will be a minimum of 400 tons and may be increased to 1200 tons.
All of the test results obtained from the acceptance samples from a
given lot shall be evaluated collectively. If the Contractor requests a
change to the JMF that is approved, the material produced after the
change will be evaluated on the basis of the new JMF for the remaining
sublots in the current lot and for acceptance of subsequent lots. For a
lot in progress with a CPF less than 0.75, a new lot will begin at the
Contractor’s request after the Engineer is satisfied that material
conforming to the Specifications can be produced.
Sampling and testing for evaluation shall be performed on the
frequency of one sample per sublot.
Rock Creek Culvert Replacement/Lincoln 5 - 16 June 3, 2021
Project Number: 13-3007.5
5-04.3(9)C2 Mixture Nonstatistical Evaluation Sampling
Samples for acceptance testing shall be obtained by the Contractor
when ordered by the Engineer. The Contractor shall sample the HMA
mixture in the presence of the Engineer and in accordance with
AASHTO T 168. A minimum of three samples should be taken for each
class of HMA placed on a project. If used in a structural application, at
least one of the three samples shall to be tested.
Sampling and testing HMA in a Structural application where quantities
are less than 400 tons is at the discretion of the Engineer.
For HMA used in a structural application and with a total project
quantity less than 800 tons but more than 400 tons, a minimum of one
acceptance test shall be performed. In all cases, a minimum of 3
samples will be obtained at the point of acceptance, a minimum of one
of the three samples will be tested for conformance to the JMF:
If the test results are found to be within specification
requirements, additional testing will be at the Engineer’s
discretion.
If test results are found not to be within specification
requirements, additional testing of the remaining samples to
determine a Composite Pay Factor (CPF) shall be performed.
5-04.3(9)C3 Mixture Nonstatistical Evaluation – Acceptance Testing
Testing of HMA for compliance of Va will be at the option of the
Contracting Agency. If tested, compliance of Va will use WSDOT SOP
731.
Testing for compliance of asphalt binder content will be by WSDOT FOP
for AASHTO T 308.
Testing for compliance of gradation will be by FOP for WAQTC T 27/T
11.
5-04.3(9)C4 Mixture Nonstatistical Evaluation – Pay Factors
For each lot of material falling outside the tolerance limits in
5-04.3(9), the Contracting Agency will determine a Composite Pay
Factor (CPF) using the following price adjustment factors:
Table of Price Adjustment Factors
Constituent Factor “f”
All aggregate passing: 1½″, 1″, ¾″, ½″, ⅜″ and No.4 sieves 2
All aggregate passing No. 8 sieve 15
All aggregate passing No. 200 sieve 20
Asphalt binder 40
Air Voids (Va) (where applicable) 20
Rock Creek Culvert Replacement/Lincoln 5 - 17 June 3, 2021
Project Number: 13-3007.5
Each lot of HMA produced under Nonstatistical Evaluation and having all
constituents falling within the tolerance limits of the job mix formula
shall be accepted at the unit Contract price with no further evaluation.
When one or more constituents fall outside the nonstatistical tolerance
limits in the Job Mix Formula shown in Table of Price Adjustment
Factors, the lot shall be evaluated in accordance with Section 1-06.2 to
determine the appropriate CPF. The nonstatistical tolerance limits will
be used in the calculation of the CPF and the maximum CPF shall be
1.00. When less than three sublots exist, backup samples of the
existing sublots or samples from the Roadway shall be tested to provide
a minimum of three sets of results for evaluation.
5-04.3(9)C5 Vacant
5-04.3(9)C6 Mixture Nonstatistical Evaluation – Price Adjustments
For each lot of HMA mix produced under Nonstatistical Evaluation when
the calculated CPF is less than 1.00, a Nonconforming Mix Factor
(NCMF) will be determined. The NCMF equals the algebraic difference of
CPF minus 1.00 multiplied by 60 percent. The total job mix compliance
price adjustment will be calculated as the product of the NCMF, the
quantity of HMA in the lot in tons, and the unit Contract price per ton of
mix.
If a constituent is not measured in accordance with these
Specifications, its individual pay factor will be considered 1.00 in
calculating the Composite Pay Factor (CPF).
5-04.3(9)C7 Mixture Nonstatistical Evaluation - Retests
The Contractor may request a sublot be retested. To request a retest,
the Contractor shall submit a written request within 7 calendar days
after the specific test results have been received. A split of the original
acceptance sample will be retested. The split of the sample will not be
tested with the same tester that ran the original acceptance test. The
sample will be tested for a complete gradation analysis, asphalt binder
content, and, at the option of the agency, Va. The results of the retest
will be used for the acceptance of the HMA in place of the original
sublot sample test results. The cost of testing will be deducted from any
monies due or that may come due the Contractor under the Contract at
the rate of $500 per sample.
5-04.3 (9)D Mixture Acceptance – Commercial Evaluation
If sampled and tested, HMA produced under Commercial Evaluation and
having all constituents falling within the tolerance limits of the job mix
formula shall be accepted at the unit Contract price with no further
evaluation. When one or more constituents fall outside the commercial
tolerance limits in the Job Mix Formula shown in 5-04.3(9), the lot shall
be evaluated in accordance with Section 1-06.2 to determine the
appropriate CPF. The commercial tolerance limits will be used in the
calculation of the CPF and the maximum CPF shall be 1.00. When less
Rock Creek Culvert Replacement/Lincoln 5 - 18 June 3, 2021
Project Number: 13-3007.5
than three sublots exist, backup samples of the existing sublots or
samples from the street shall be tested to provide a minimum of three
sets of results for evaluation.
For each lot of HMA mix produced and tested under Commercial
Evaluation when the calculated CPF is less than 1.00, a Nonconforming
Mix Factor (NCMF) will be determined. The NCMF equals the algebraic
difference of CPF minus 1.00 multiplied by 60 percent. The Job Mix
Compliance Price Adjustment will be calculated as the product of the
NCMF, the quantity of HMA in the lot in tons, and the unit Contract
price per ton of mix.
If a constituent is not measured in accordance with these
Specifications, its individual pay factor will be considered 1.00 in
calculating the Composite Pay Factor (CPF).
5-04.3(10) HMA Compaction Acceptance
HMA mixture accepted by nonstatistical evaluation that is used in traffic
lanes, including lanes for intersections, ramps, truck climbing, weaving,
and speed change, and having a specified compacted course thickness
greater than 0.10-foot, shall be compacted to a specified level of
relative density. The specified level of relative density shall be a
Composite Pay Factor (CPF) of not less than 0.75 when evaluated in
accordance with Section 1-06.2, using a LSL of 92.0 (minimum of 92
percent of the maximum density). The maximum density shall be
determined by WSDOT FOP for AASHTO T 729. The specified level of
density attained will be determined by the evaluation of the density of
the pavement. The density of the pavement shall be determined in
accordance with WSDOT FOP for WAQTC TM 8, except that gauge
correlation will be at the discretion of the Engineer, when using the
nuclear density gauge and WSDOT SOP 736 when using cores to
determine density.
Tests for the determination of the pavement density will be taken in
accordance with the required procedures for measurement by a nuclear
density gauge or roadway cores after completion of the finish rolling.
If the Contracting Agency uses a nuclear density gauge to determine
density the test procedures FOP for WAQTC TM 8 and WSDOT SOP T
729 will be used on the day the mix is placed and prior to opening to
traffic.
Roadway cores for density may be obtained by either the Contracting
Agency or the Contractor in accordance with WSDOT SOP 734. The core
diameter shall be 4-inches minimum, unless otherwise approved by the
Engineer. Roadway cores will be tested by the Contracting Agency in
accordance with WSDOT FOP for AASHTO T 166.
If the Contract includes the Bid item “Roadway Core” the cores shall be
obtained by the Contractor in the presence of the Engineer on the same
day the mix is placed and at locations designated by the Engineer. If
Rock Creek Culvert Replacement/Lincoln 5 - 19 June 3, 2021
Project Number: 13-3007.5
the Contract does not include the Bid item “Roadway Core” the
Contracting Agency may obtain the cores.
For a lot in progress with a CPF less than 0.75, a new lot will begin at
the Contractor’s request after the Engineer is satisfied that material
conforming to the Specifications can be produced.
HMA mixture accepted by commercial evaluation and HMA constructed
under conditions other than those listed above shall be compacted on
the basis of a test point evaluation of the compaction train. The test
point evaluation shall be performed in accordance with instructions
from the Engineer. The number of passes with an approved compaction
train, required to attain the maximum test point density, shall be used
on all subsequent paving.
HMA for preleveling shall be thoroughly compacted. HMA that is used
for preleveling wheel rutting shall be compacted with a pneumatic tire
roller unless otherwise approved by the Engineer.
Test Results
For a sublot that has been tested with a nuclear density gauge that did
not meet the minimum of 92 percent of the reference maximum density
in a compaction lot with a CPF below 1.00 and thus subject to a price
reduction or rejection, the Contractor may request that a core be used
for determination of the relative density of the sublot. The relative
density of the core will replace the relative density determined by the
nuclear density gauge for the sublot and will be used for calculation of
the CPF and acceptance of HMA compaction lot.
When cores are taken by the Contracting Agency at the request of the
Contractor, they shall be requested by noon of the next workday after
the test results for the sublot have been provided or made available to
the Contractor. Core locations shall be outside of wheel paths and as
determined by the Engineer. Traffic control shall be provided by the
Contractor as requested by the Engineer. Failure by the Contractor to
provide the requested traffic control will result in forfeiture of the
request for cores. When the CPF for the lot based on the results of the
HMA cores is less than 1.00, the cost for the coring will be deducted
from any monies due or that may become due the Contractor under the
Contract at the rate of $200 per core and the Contractor shall pay for
the cost of the traffic control.
5-04.3(10)A HMA Compaction – General Compaction Requirements
Compaction shall take place when the mixture is in the proper condition
so that no undue displacement, cracking, or shoving occurs. Areas
inaccessible to large compaction equipment shall be compacted by
other mechanical means. Any HMA that becomes loose, broken,
contaminated, shows an excess or deficiency of asphalt, or is in any
way defective, shall be removed and replaced with new hot mix that
shall be immediately compacted to conform to the surrounding area.
Rock Creek Culvert Replacement/Lincoln 5 - 20 June 3, 2021
Project Number: 13-3007.5
The type of rollers to be used and their relative position in the
compaction sequence shall generally be the Contractor’s option,
provided the specified densities are attained. Unless the Engineer has
approved otherwise, rollers shall only be operated in the static mode
when the internal temperature of the mix is less than 175°F.
Regardless of mix temperature, a roller shall not be operated in a mode
that results in checking or cracking of the mat. Rollers shall only be
operated in static mode on bridge decks.
5-04.3(10)B HMA Compaction – Cyclic Density
Low cyclic density areas are defined as spots or streaks in the
pavement that are less than 90 percent of the theoretical maximum
density. At the Engineer’s discretion, the Engineer may evaluate the
HMA pavement for low cyclic density, and when doing so will follow
WSDOT SOP 733. A $500 Cyclic Density Price Adjustment will be
assessed for any 500-foot section with two or more density readings
below 90 percent of the theoretical maximum density.
5-04.3(10)C Vacant
5-04.3(10)D HMA Nonstatistical Compaction
5-04.3(10)D1 HMA Nonstatistical Compaction – Lots and Sublots
HMA compaction which is accepted by nonstatistical evaluation will be
based on acceptance testing performed by the Contracting Agency
dividing the project into compaction lots.
A lot is represented by randomly selected samples of the same mix
design that will be tested for acceptance. A lot is defined as the total
quantity of material or work produced for each Job Mix Formula placed.
Only one lot per JMF is expected. A sublot shall be equal to one day’s
production or 400 tons, whichever is less except that the final sublot
will be a minimum of 200 tons and may be increased to 800 tons.
Testing for compaction will be at the rate of 5 tests per sublot per
WSDOT T 738.
The sublot locations within each density lot will be determined by the
Engineer. For a lot in progress with a CPF less than 0.75, a new lot will
begin at the Contractor’s request after the Engineer is satisfied that
material conforming to the Specifications can be produced.
HMA mixture accepted by commercial evaluation and HMA constructed
under conditions other than those listed above shall be compacted on
the basis of a test point evaluation of the compaction train. The test
point evaluation shall be performed in accordance with instructions
from the Engineer. The number of passes with an approved compaction
train, required to attain the maximum test point density, shall be used
on all subsequent paving.
Rock Creek Culvert Replacement/Lincoln 5 - 21 June 3, 2021
Project Number: 13-3007.5
HMA for preleveling shall be thoroughly compacted. HMA that is used to
prelevel wheel ruts shall be compacted with a pneumatic tire roller
unless otherwise approved by the Engineer.
5-04.3(10)D2 HMA Compaction Nonstatistical Evaluation – Acceptance
Testing
The location of the HMA compaction acceptance tests will be randomly
selected by the Engineer from within each sublot, with one test per
sublot.
5-04.3(10)D3 HMA Nonstatistical Compaction – Price Adjustments
For each compaction lot with one or two sublots, having all sublots
attain a relative density that is 92 percent of the reference maximum
density the HMA shall be accepted at the unit Contract price with no
further evaluation. When a sublot does not attain a relative density that
is 92 percent of the reference maximum density, the lot shall be
evaluated in accordance with Section 1-06.2 to determine the
appropriate CPF. The maximum CPF shall be 1.00, however, lots with a
calculated CPF in excess of 1.00 will be used to offset lots with CPF
values below 1.00 but greater than 0.90. Lots with CPF lower than 0.90
will be evaluated for compliance per 5-04.3(11). Additional testing by
either a nuclear moisture-density gauge or cores will be completed as
required to provide a minimum of three tests for evaluation.
For compaction below the required 92% a Non-Conforming Compaction
Factor (NCCF) will be determined. The NCCF equals the algebraic
difference of CPF minus 1.00 multiplied by 40 percent. The Compaction
Price Adjustment will be calculated as the product of CPF, the quantity
of HMA in the compaction control lot in tons, and the unit Contract price
per ton of mix.
5-04.3(11) Reject Work
5-04.3(11)A Reject Work General
Work that is defective or does not conform to Contract requirements
shall be rejected. The Contractor may propose, in writing, alternatives
to removal and replacement of rejected material. Acceptability of such
alternative proposals will be determined at the sole discretion of the
Engineer. HMA that has been rejected is subject to the requirements in
Section 1-06.2(2) and this specification, and the Contractor shall
submit a corrective action proposal to the Engineer for approval.
5-04.3(11)B Rejection by Contractor
The Contractor may, prior to sampling, elect to remove any defective
material and replace it with new material. Any such new material will be
sampled, tested, and evaluated for acceptance.
Rock Creek Culvert Replacement/Lincoln 5 - 22 June 3, 2021
Project Number: 13-3007.5
5-04.3(11)C Rejection Without Testing (Mixture or Compaction)
The Engineer may, without sampling, reject any batch, load, or section
of Roadway that appears defective. Material rejected before placement
shall not be incorporated into the pavement. Any rejected section of
Roadway shall be removed.
No payment will be made for the rejected materials or the removal of
the materials unless the Contractor requests that the rejected material
be tested. If the Contractor elects to have the rejected material tested,
a minimum of three representative samples will be obtained and tested.
Acceptance of rejected material will be based on conformance with the
nonstatistical acceptance Specification. If the CPF for the rejected
material is less than 0.75, no payment will be made for the rejected
material; in addition, the cost of sampling and testing shall be borne by
the Contractor. If the CPF is greater than or equal to 0.75, the cost of
sampling and testing will be borne by the Contracting Agency. If the
material is rejected before placement and the CPF is greater than or
equal to 0.75, compensation for the rejected material will be at a CPF of
0.75. If rejection occurs after placement and the CPF is greater than or
equal to 0.75, compensation for the rejected material will be at the
calculated CPF with an addition of 25 percent of the unit Contract price
added for the cost of removal and disposal.
5-04.3(11)D Rejection - A Partial Sublot
In addition to the random acceptance sampling and testing, the
Engineer may also isolate from a normal sublot any material that is
suspected of being defective in relative density, gradation or asphalt
binder content. Such isolated material will not include an original
sample location. A minimum of three random samples of the suspect
material will be obtained and tested. The material will then be
statistically evaluated as an independent lot in accordance with Section
1-06.2(2).
5-04.3(11)E Rejection - An Entire Sublot
An entire sublot that is suspected of being defective may be rejected.
When a sublot is rejected a minimum of two additional random samples
from this sublot will be obtained. These additional samples and the
original sublot will be evaluated as an independent lot in accordance
with Section 1-06.2(2).
5-04.3(11)F Rejection - A Lot in Progress
The Contractor shall shut down operations and shall not resume HMA
placement until such time as the Engineer is satisfied that material
conforming to the Specifications can be produced:
1. When the Composite Pay Factor (CPF) of a lot in progress drops
below 1.00 and the Contractor is taking no corrective action, or
Rock Creek Culvert Replacement/Lincoln 5 - 23 June 3, 2021
Project Number: 13-3007.5
2. When the Pay Factor (PF) for any constituent of a lot in progress
drops below 0.95 and the Contractor is taking no corrective action,
or
3. When either the PFi for any constituent or the CPF of a lot in
progress is less than 0.75.
5-04.3(11)G Rejection - An Entire Lot (Mixture or Compaction)
An entire lot with a CPF of less than 0.75 will be rejected.
5-04.3(12) Joints
5-04.3(12)A HMA Joints
5-04.3(12)A1 Transverse Joints
The Contractor shall conduct operations such that the placing of the top
or wearing course is a continuous operation or as close to continuous as
possible. Unscheduled transverse joints will be allowed and the roller
may pass over the unprotected end of the freshly laid mixture only
when the placement of the course must be discontinued for such a
length of time that the mixture will cool below compaction temperature.
When the Work is resumed, the previously compacted mixture shall be
cut back to produce a slightly beveled edge for the full thickness of the
course.
A temporary wedge of HMA constructed on a 20H:1V shall be
constructed where a transverse joint as a result of paving or planing is
open to traffic. The HMA in the temporary wedge shall be separated
from the permanent HMA by strips of heavy wrapping paper or other
methods approved by the Engineer. The wrapping paper shall be
removed and the joint trimmed to a slightly beveled edge for the full
thickness of the course prior to resumption of paving.
The material that is cut away shall be wasted and new mix shall be laid
against the cut. Rollers or tamping irons shall be used to seal the joint.
5-04.3(12)A2 Longitudinal Joints
The longitudinal joint in any one course shall be offset from the course
immediately below by not more than 6 inches nor less than 2 inches. All
longitudinal joints constructed in the wearing course shall be located at
a lane line or an edge line of the Traveled Way. A notched wedge joint
shall be constructed along all longitudinal joints in the wearing surface
of new HMA unless otherwise approved by the Engineer. The notched
wedge joint shall have a vertical edge of not less than the maximum
aggregate size or more than ½ of the compacted lift thickness and then
taper down on a slope not steeper than 4H:1V. The sloped portion of
the HMA notched wedge joint shall be uniformly compacted.
5-04.3(12)B Bridge Paving Joint Seals
Rock Creek Culvert Replacement/Lincoln 5 - 24 June 3, 2021
Project Number: 13-3007.5
5-04.3(12)B1 HMA Sawcut and Seal
Prior to placing HMA on the bridge deck, establish sawcut alignment
points at both ends of the bridge paving joint seals to be placed at the
bridge ends, and at interior joints within the bridge deck when and
where shown in the Plans. Establish the sawcut alignment points in a
manner that they remain functional for use in aligning the sawcut after
placing the overlay.
Submit a Type 1 Working Drawing consisting of the sealant
manufacturer’s application procedure.
Construct the bridge paving joint seal as specified on the Plans and in
accordance with the detail shown in the Standard Plans. Construct the
sawcut in accordance with the detail shown in the Standard Plan.
Construct the sawcut in accordance with Section 5-05.3(8)B and the
manufacturer’s application procedure.
5-04.3(12)B2 Paved Panel Joint Seal
Construct the paved panel joint seal in accordance with the
requirements specified in Section 5-04.3(12)B1 and the following
requirement:
Clean and seal the existing joint between concrete panels in accordance
with Section 5-01.3(8) and the details shown in the Standard Plans.
5-04.3(13) Surface Smoothness
The completed surface of all courses shall be of uniform texture,
smooth, uniform as to crown and grade, and free from defects of all
kinds. The completed surface of the wearing course shall not vary more
than ⅛ inch from the lower edge of a 10-foot straightedge placed on
the surface parallel to the centerline. The transverse slope of the
completed surface of the wearing course shall vary not more than ¼
inch in 10 feet from the rate of transverse slope shown in the Plans.
When deviations in excess of the above tolerances are found that result
from a high place in the HMA, the pavement surface shall be corrected
by one of the following methods:
1. Removal of material from high places by grinding with an approved
grinding machine, or
2. Removal and replacement of the wearing course of HMA, or
3. By other method approved by the Engineer.
Correction of defects shall be carried out until there are no deviations
anywhere greater than the allowable tolerances.
Deviations in excess of the above tolerances that result from a low
place in the HMA and deviations resulting from a high place where
corrective action, in the opinion of the Engineer, will not produce
satisfactory results will be accepted with a price adjustment. The
Rock Creek Culvert Replacement/Lincoln 5 - 25 June 3, 2021
Project Number: 13-3007.5
Engineer shall deduct from monies due or that may become due to the
Contractor the sum of $500.00 for each and every section of single
traffic lane 100 feet in length in which any excessive deviations
described above are found.
When utility appurtenances such as manhole covers and valve boxes
are located in the traveled way, the utility appurtenances shall be
adjusted to the finished grade prior to paving. This requirement may be
waived when requested by the Contractor, at the discretion of the
Engineer or when the adjustment details provided in the project plan or
specifications call for utility appurtenance adjustments after the
completion of paving.
Utility appurtenance adjustment discussions will be included in the Pre-
Paving planning (5-04.3(14)B3). Submit a written request to waive this
requirement to the Engineer prior to the start of paving.
5-04.3(14) Planing (Milling) Bituminous Pavement
The planing plan must be approved by the Engineer and a pre planing
meeting must be held prior to the start of any planing. See Section
5-04.3(14)B2 for information on planing submittals.
Planing operations shall be performed no more than 7 calendar days
ahead of the time the planed area is to be paved, unless otherwise
allowed by the Engineer in writing.
Locations of existing surfacing to be planed are as shown in the
Drawings.
Where planing an existing pavement is specified in the Contract, the
Contractor must remove existing surfacing material and to reshape the
surface to remove irregularities. The finished product must be a
prepared surface acceptable for receiving an HMA overlay.
Use the cold milling method for planing unless otherwise specified in
the Contract. Do not use the planer on the final wearing course of new
HMA.
Conduct planing operations in a manner that does not tear, break,
burn, or otherwise damage the surface which is to remain. The finished
planed surface must be slightly grooved or roughened and must be free
from gouges, deep grooves, ridges, or other imperfections. The
Contractor must repair any damage to the surface by the Contractor’s
planing equipment, using an Engineer approved method.
Repair or replace any metal castings and other surface improvements
damaged by planing, as determined by the Engineer.
A tapered wedge cut must be planed longitudinally along curb lines
sufficient to provide a minimum of 4 inches of curb reveal after
placement and compaction of the final wearing course. The dimensions
Rock Creek Culvert Replacement/Lincoln 5 - 26 June 3, 2021
Project Number: 13-3007.5
of the wedge must be as shown on the Drawings or as specified by the
Engineer.
A tapered wedge cut must also be made at transitions to adjoining
pavement surfaces (meet lines) where butt joints are shown on the
Drawings. Cut butt joints in a straight line with vertical faces 2 inches
or more in height, producing a smooth transition to the existing
adjoining pavement.
After planing is complete, planed surfaces must be swept, cleaned, and
if required by the Contract, patched and preleveled.
The Engineer may direct additional depth planing. Before performing
this additional depth planing, the Contractor must conduct a hidden
metal in pavement detection survey as specified in Section
5-04.3(14)A.
5-04.3(14)A Pre-Planing Metal Detection Check
Before starting planing of pavements, and before any additional depth
planing required by the Engineer, the Contractor must conduct a
physical survey of existing pavement to be planed with equipment that
can identify hidden metal objects.
Should such metal be identified, promptly notify the Engineer.
See Section 1-07.16(1) regarding the protection of survey
monumentation that may be hidden in pavement.
The Contractor is solely responsible for any damage to equipment
resulting from the Contractor’s failure to conduct a pre-planing metal
detection survey, or from the Contractor’s failure to notify the Engineer
of any hidden metal that is detected.
5-04.3(14)B Paving and Planing Under Traffic
5-04.3(14)B1 General
In addition the requirements of Section 1-07.23 and the traffic controls
required in Section 1-10, and unless the Contract specifies otherwise or
the Engineer approves, the Contractor must comply with the following:
1. Intersections:
a. Keep intersections open to traffic at all times, except when
paving or planing operations through an intersection requires
closure. Such closure must be kept to the minimum time
required to place and compact the HMA mixture, or plane as
appropriate. For paving, schedule such closure to individual
lanes or portions thereof that allows the traffic volumes and
schedule of traffic volumes required in the approved traffic
control plan. Schedule work so that adjacent intersections are
not impacted at the same time and comply with the traffic
control restrictions required by the Traffic Engineer. Each
Rock Creek Culvert Replacement/Lincoln 5 - 27 June 3, 2021
Project Number: 13-3007.5
individual intersection closure or partial closure, must be
addressed in the traffic control plan, which must be submitted
to and accepted by the Engineer, see Section 1-10.2(2).
b. When planing or paving and related construction must occur
in an intersection, consider scheduling and sequencing such
work into quarters of the intersection, or half or more of an
intersection with side street detours. Be prepared to sequence
the work to individual lanes or portions thereof.
c. Should closure of the intersection in its entirety be necessary,
keep such closure to the minimum time required to place and
compact the HMA mixture, plane, remove asphalt, tack coat,
and as needed.
d. Any work in an intersection requires advance warning in both
signage and a number of Working Days advance notice as
determined by the Engineer, to alert traffic and emergency
services of the intersection closure or partial closure.
e. Allow new compacted HMA asphalt to cool to ambient
temperature before any traffic is allowed on it. Traffic is not
allowed on newly placed asphalt until approval has been
obtained from the Engineer.
2. Temporary centerline marking, post-paving temporary marking,
temporary stop bars, and maintaining temporary pavement
marking must comply with Section 8-23.
3. Permanent pavement marking must comply with Section 8-22.
5-04.3(14)B2 Submittals – Planing Plan and HMA Paving Plan
The Contractor must submit a separate planing plan and a separate
paving plan to the Engineer at least 5 Working Days in advance of each
operation’s activity start date. These plans must show how the moving
operation and traffic control are coordinated, as they will be discussed
at the pre-planing briefing and pre-paving briefing. When requested by
the Engineer, the Contractor must provide each operation’s traffic
control plan on 24 x 36 inch or larger size Shop Drawings with a scale
showing both the area of operation and sufficient detail of traffic
beyond the area of operation where detour traffic may be required. The
scale on the Shop Drawings is 1 inch = 20 feet, which may be changed
if the Engineer agrees sufficient detail is shown.
The planing operation and the paving operation include, but are not
limited to, metal detection, removal of asphalt and temporary asphalt
of any kind, tack coat and drying, staging of supply trucks, paving
trains, rolling, scheduling, and as may be discussed at the briefing.
When intersections will be partially or totally blocked, provide
adequately sized and noticeable signage alerting traffic of closures to
come, a minimum 2 Working Days in advance. The traffic control plan
must show where police officers will be stationed when signalization is
or may be, countermanded, and show areas where flaggers are
proposed.
At a minimum, the planing and the paving plan must include:
Rock Creek Culvert Replacement/Lincoln 5 - 28 June 3, 2021
Project Number: 13-3007.5
1. A copy of the accepted traffic control plan, see Section
1-10.2(2), detailing each day’s traffic control as it relates to the
specific requirements of that day’s planing and paving. Briefly
describe the sequencing of traffic control consistent with the
proposed planing and paving sequence, and scheduling of
placement of temporary pavement markings and channelizing
devices after each day’s planing, and paving.
2. A copy of each intersection’s traffic control plan.
3. Haul routes from Supplier facilities, and locations of temporary
parking and staging areas, including return routes. Describe the
complete round trip as it relates to the sequencing of paving
operations.
4. Names and locations of HMA Supplier facilities to be used.
5. List of all equipment to be used for paving.
6. List of personnel and associated job classification assigned to each
piece of paving equipment.
7. Description (geometric or narrative) of the scheduled sequence of
planing and of paving, and intended area of planing and of paving
for each day’s work, must include the directions of proposed
planing and of proposed paving, sequence of adjacent lane paving,
sequence of skipped lane paving, intersection planing and paving
scheduling and sequencing, and proposed notifications and
coordination to be timely made. The plan must show HMA joints
relative to the final pavement marking lane lines.
8. Names, job titles, and contact information for field, office, and
plant supervisory personnel.
9. A copy of the approved Mix Designs.
10. Tonnage of HMA to be placed each day.
11. Approximate times and days for starting and ending daily
operations.
5-04.3(14)B3 Pre-Paving and Pre-Planing Briefing
At least 2 Working Days before the first paving operation and the first
planing operation, or as scheduled by the Engineer for future paving
and planing operations to ensure the Contractor has adequately
prepared for notifying and coordinating as required in the Contract, the
Contractor must be prepared to discuss that day’s operations as they
relate to other entities and to public safety and convenience, including
driveway and business access, garbage truck operations, Metro transit
operations and working around energized overhead wires, school and
nursing home and hospital and other accesses, other contractors who
may be operating in the area, pedestrian and bicycle traffic, and
emergency services. The Contractor, and Subcontractors that may be
part of that day’s operations, must meet with the Engineer and discuss
the proposed operation as it relates to the submitted planing plan and
paving plan, approved traffic control plan, and public convenience and
safety. Such discussion includes, but is not limited to:
1. General for both Paving Plan and for Planing Plan:
a. The actual times of starting and ending daily operations.
Rock Creek Culvert Replacement/Lincoln 5 - 29 June 3, 2021
Project Number: 13-3007.5
b. In intersections, how to break up the intersection, and
address traffic control and signalization for that operation,
including use of peace officers.
c. The sequencing and scheduling of paving operations and of
planing operations, as applicable, as it relates to traffic
control, to public convenience and safety, and to other
contractors who may operate in the Project Site.
d. Notifications required of Contractor activities, and
coordinating with other entities and the public as necessary.
e. Description of the sequencing of installation and types of
temporary pavement markings as it relates to planing and to
paving.
f. Description of the sequencing of installation of, and the
removal of, temporary pavement patch material around
exposed castings and as may be needed.
g. Description of procedures and equipment to identify hidden
metal in the pavement, such as survey monumentation,
monitoring wells, street car rail, and castings, before planing,
see Section 5-04.3(14)B2.
h. Description of how flaggers will be coordinated with the
planing, paving, and related operations.
i. Description of sequencing of traffic controls for the process of
rigid pavement base repairs.
j. Other items the Engineer deems necessary to address.
2. Paving – additional topics:
a. When to start applying tack and coordinating with paving.
b. Types of equipment and numbers of each type of equipment
to be used. If more pieces of equipment than personnel are
proposed, describe the sequencing of the personnel operating
the types of equipment. Discuss the continuance of operator
personnel for each type of equipment as it relates to meeting
Specification requirements.
c. Number of JMFs to be placed, and if more than one JMF how
the Contractor will ensure different JMFs are distinguished,
how pavers and MTVs are distinguished if more than one JMF
is being placed at the time, and how pavers and MTVs are
cleaned so that one JMF does not adversely influence the
other JMF.
d. Description of contingency plans for that day’s operations
such as equipment breakdown, rain out, and Supplier
shutdown of operations.
e. Number of sublots to be placed, sequencing of density testing,
and other sampling and testing.
5-04.3(15) Sealing Pavement Surfaces
Apply a fog seal where shown in the plans. Construct the fog seal in
accordance with Section 5-02.3. Unless otherwise approved by the
Engineer, apply the fog seal prior to opening to traffic.
5-04.3(16) HMA Road Approaches
Rock Creek Culvert Replacement/Lincoln 5 - 30 June 3, 2021
Project Number: 13-3007.5
HMA approaches shall be constructed at the locations shown in the
Plans or where staked by the Engineer. The Work shall be performed in
accordance with Section 5-04.
5-04.3(17) Pavement Reinforcement
The Contractor shall install the asphalt interlay fabric at the locations
and to the dimensions shown on the Plans and as directed by the
Engineer. The interlay fabric shall be placed on existing asphalt or
concrete pavement to be overlaid with HMA mix specified in the
contract.
CONSTRUCTION REQUIREMENTS
All equipment, tools, and machines used in the performance of the work
shall be subject to the approval of the Engineer and shall be maintained
in satisfactory working condition at all times.
Equipment for surface cleaning shall be capable of effectively removing
oil, grease, dust, dirt or other objectionable materials from the
pavement.
Application equipment shall consist of suitable brooms, distributor, and
laydown machine as required.
The distributor shall have a capacity of not less than 1,000 gallons and
shall be so designed, equipped, maintained and operated that asphalt
material of an even heat shall be uniformly applied at the required rate.
It shall be insulated and equipped with an adequate heating device. It
shall be equipped with a 10-foot spray bar with extensions, pressure
pump and gauge, with a volume gauge so located as to be observed
easily by the inspector from the ground, a tachometer to control
accurately the speed and spread of asphalt, and two thermometers, one
to be installed permanently in the tank to indicate temperature of the
asphalt at all times. The power for operating the pressure pump shall
be supplied by an independent power unit which will develop a
minimum of 25 pounds per square inch pressure at the spray bar.
The laydown machine shall consist of a small tractor with attachment
for the fabric installation. Bucket loaders or backhoes are not permitted
for installation.
The Contractor shall not begin application of the interlay fabric until he
has demonstrated, to the satisfaction of the Engineer, that all labor,
equipment, and materials necessary to apply the interlay fabric are
either on hand or readily available.
MATERIALS
The approved products are:
1. TenCate Mirafi MPM30 (PGM-30)
2. Tensar GlasPave 25
3. Roadmat RM35
Rock Creek Culvert Replacement/Lincoln 5 - 31 June 3, 2021
Project Number: 13-3007.5
The material properties of the asphalt interlay fabric shall conform to all
design and nominal performance standards of TenCate Mirafi MPM30
(PGM-30), Tensar GlasPave 25, Roadmat RM35 or the properties listed
below in Table 2.01. Submittals shall include independent confirmation
of the material properties.
Table 2.01 – Physical Properties of the asphalt interlay fabric
Property ASTM Test
Method
Units Min. Avg.
Roll Value
Tensile Strength @ 0º
Tensile Strength @ 90º D5035 lbs/in 200
200
Tensile Elongation % < 5.0
Melting Point (glass) D276 °F (°C ) 450º (232º)
Asphalt Retention D6140 gal/yd² 0.10
Mass per Unit Area D5261 oz/yd² 4.0
STORAGE
The paving interlayer rolls shall be labeled, with a durable label
indicating manufacturer, product name or style number, roll and lot
number, and roll dimensions shall be attached to each roll.
The paving interlayer rolls shall be delivered and handled in a manner
to prevent damage and shall be inspected for defects and damage prior
to use.
The paving interlayer shall be stored in a dry covered condition, free
from dust, dirt, off the ground, flat to prevent bowing, protected from
precipitation, ultraviolet radiation, strong chemicals, sparks and flames,
temperatures in excess 71 °C (160 °F) and other environmental
condition that could cause damage.
WEATHER AND MOISTURE LIMITATIONS
Work shall not be done during wet weather conditions nor when the
pavement and ambient air temperatures are below 50°F. The pavement
shall be surface-dry at the time of the application of the asphalt.
SURFACE PREPARATION
All areas of base failure shall be removed and replaced to acceptable
industry standards for the specific traffic loads and condition of the
project.
Pre-Leveling, if necessary, shall be done prior to placing paving
interlayer. The pavement surface shall be free of all foreign materials
such as dirt, grease, etc. Prior to applying the asphalt, all dust and
loose material shall be removed from the pavement surface with
compressed air. Existing cracks shall be filled as specified elsewhere
under “Crack Sealing.”
In an overlay or milled surface application, repair all failed pavement
areas prior to installation of the paving interlayer. Fill all cracks ¼” or
greater with approved material.
Rock Creek Culvert Replacement/Lincoln 5 - 32 June 3, 2021
Project Number: 13-3007.5
Immediately prior to placement of paving interlayer, the pavement
surface shall be dry, cleaned of anything that would interfere with
adhesion, for e.g., vegetation, moss, dirt, gravel or water.
A leveling or "scratch" course is recommended when road surface is not
acceptable and shall be of proper gradation and sufficient thickness to
achieve a smooth, level surface with no gaps greater than ¼” depth
and width or be acceptable to the project engineer.
A finish grind may be used as an alternative to an asphalt leveling
course being placed, when you can achieve the final surface texture has
no cracks, gaps or vertical angles greater the ¼” depth and width or be
acceptable to the project engineer. In all cases the surface must be
clean and dry and the application rate of the Hot PG grade asphalt
binder shall be increased to insure complete interlayer saturation and
bonding.
INSTALLATION
A. Apply the asphalt interlay fabric in a hot PG graded asphalt binder.
Asphalt Emulsion is NOT acceptable for placing paving interlayer
due to time delay for it to break and the difficulty in insuring
quality as installed.
B. Asphalt Binder
1. A hot asphalt binder shall be applied to saturate the paving
interlayer (min. to be the asphalt retention rate) plus amount
needed to bond to existing surface and the new overlay. The
asphalt binder to be used shall be PG58H –22 (PG64 -22) or
higher. Sustained ambient temperatures (above 90º) may
require a stiffer binder gradation like PG58V –22 (PG70 -22)
or higher to improve set time and reduce risk of fabric pick-up
under construction traffic.
2. The hot asphalt binder shall be applied per the paving
interlayer manufacturer or as directed by the Engineer. For
TenCate Mirafi MPM30 the hot asphalt binder shall be applied
at a rate of 0.10 Gal/SY on a new HMA leveling surface. On an
old smooth surface or a clean fine milled surface apply hot
asphalt binder shall be applied at a rate of 0.12 Gal/SY. For
Tensar GlasPave 25 the hot asphalt binder shall be applied at
a rate of 0.15 Gal/SY on a new pavement surface, 0.17
Gal/SY on an aged oxidized surface, and a rate of 0.2 Gal/SY
on a milled surface.
3. Spray application shall extend four (4) inches wider than
width of paving interlayer on lap side. Hot asphalt binder
application shall be wide enough to cover the entire width of
engineered paving mat material overlaps. The hot asphalt
binder shall be applied only as far in advance of the
engineered paving mat material installation as is appropriate
to ensure a tacky surface at the time of the engineered
paving mat material placement. Traffic shall not be allowed on
the hot asphalt binder.
Rock Creek Culvert Replacement/Lincoln 5 - 33 June 3, 2021
Project Number: 13-3007.5
4. The hot asphalt binder shall be applied by a distributor truck
in a smooth uniform manner at as low a temperature as is
possible to achieve the right application rate, depending on
ambient and road surface temperatures and type of PG
asphalt binder used. Temperature of the hot asphalt binder
shall be sufficiently high enough to permit uniform spray
pattern and shall be between 350º F and 400º F. The air
temperature shall be 50º F and rising for placement of the hot
asphalt binder coat.
C. The paving interlayer shall be installed with equipment in good
working order that is capable of installing the fabric without
wrinkles or manually as needed and recommended by
manufacturer.
1. Initial alignment of the interlay fabric is very important, since
the fabric direction cannot be changed appreciably without
causing wrinkles. If the alignment of the interlay fabric must
be changed, the fabric shall be cut and realigned, overlapping
the previous material and proceeding as before.
2. If manual lay-down methods are used, the paving fabric shall
be unrolled, aligned, and placed in increments of
approximately thirty (30) feet or as project engineer suggest.
3. The material shall be placed flat and wrinkle-free. The paving
interlayer installation may require hand brooming as
necessary to eliminate ripples that may occur during
installation.
4. Brooming or squeegee of paving interlayer is required to
insure adequate adhesion into the hot asphalt binder before
the hot asphalt binder has cooled and lost tackiness. If the
interlayer wrinkles more than 1” height during installation, the
wrinkle shall be cut and lapped in the direction of paving. In
these repaired areas, additional hot asphalt binder shall be
applied as needed to achieve a sound bond to the substrate.
Damaged engineered paving mat shall be removed and
replaced, per the manufacturer's recommendations, at the
contractor's expense with the same type of material.
5. To ease installations around curves, the paving fabric can be
placed in shortened lengths by mechanical equipment or by
hand.
6. Paving interlayer shall be lapped two (2) to four (4) inches
longitudinally and two (2) to four (4) inches transversely.
Transverse laps shall be in the direction of the asphalt
concrete overlay placement insuring hot asphalt binder is
placed under the overlap. The interlay fabric shall be neatly
cut and contoured at all joints.
Rock Creek Culvert Replacement/Lincoln 5 - 34 June 3, 2021
Project Number: 13-3007.5
7. Excess hot asphalt binder that bleeds through the engineered
paving mat under normal construction traffic shall be
countered by broadcasting clean sand or hot mix to create a
bond break between the excess hot asphalt binder and the
construction equipment tires. Excess blotting sand shall be
removed from the interlayer prior to placing the HMA overlay.
No other material, such as asphalt release agents or diesel,
shall be used for this purpose.
8. No traffic, except necessary construction traffic or emergency
vehicles, shall be driven on the engineered paving mat, unless
approved by the engineer. If traffic on the interlayer is
approved by the engineer, clean sand shall be lightly
broadcasted over the engineered paving mat interlayer, and
any loose sand shall be removed prior to paving.
9. Turning of construction equipment and other vehicles shall be
gradual and kept to a minimum to avoid damage to the
paving interlayer. Caution: Parking on the installed paving
fabric prior to final overlay for extended periods could cause
damage to the interlayer.
10. Placement of the first lift of the HMA overlay shall closely
follow placement of the engineered paving mat. All areas in
which the engineered paving mat has been placed shall be
paved during the same day, unless approved otherwise by the
engineer. In the event of rainfall on the engineered paving
mat prior to the placement of the first HMA overlay lift, the
engineered paving mat shall be allowed to dry before the HMA
is placed. The compacted thickness of the first lift of the HMA
overlay on the engineered paving mat shall not be less than
1.5 inches, and the temperature of the mix at placement shall
not exceed the engineered paving mat melting point
temperature. Where the total HMA overlay thickness is less
than 1.5 inches, engineered paving mat shall not be placed.
NOTE: Minimum lift thickness should be at least 3 times the
nominal maximum aggregate size to ensure aggregate can
align themselves during compaction to achieve required
density and also to ensure mix is impermeable.
11. Paving interlayer should never be installed when it or the
pavement surface is wet.
12. The Contractor shall not place more interlay fabric on the
roadway than can be overlaid the same day with Hot Mix
Asphalt. No fabric, except that which is required for normal
lapped joints, shall be exposed to traffic.
13. In the event of breakdown of the paving operation, the
interlay fabric which has not been overlaid shall be dusted
with sand to break the tackiness of the sealant so traffic does
not pick up the fabric. The application rate shall uniformly
dust the roadway as approved by the Engineer. More than one
Rock Creek Culvert Replacement/Lincoln 5 - 35 June 3, 2021
Project Number: 13-3007.5
application of sand may be required. Before placing the
asphalt concrete, the fabric surface shall be broomed to
remove the excess sand as directed by the Engineer. The
sand shall meet the graduation requirements of the Section
9-03.1(2)B of the WSDOT Standard Specifications.
WORKMANSHIP AND QUALITY CONTROL
A Technical Representative for the manufacturer of the paving
interlayer shall be on the project to work with the Contractor’s
personnel and to provide the necessary technical assistance to ensure
the satisfactory placement of the interlay fabric and HMA overlay. The
representative shall not leave the project until the Engineer is satisfied
that the Contractor has a full understanding of what is required to place
the interlay fabric satisfactorily. The installing contractor shall give
sufficient notice of planned work schedule such that proper inspection
of workmanship is accomplished.
1. Daily, the Contractor shall certify that interlayer was installed per
plans and specifications and confirm, by weight tickets and
measuring asphalt used, that the hot asphalt binder usage equates
to the specified amount for proper interlayer saturation and
bonding.
2. Hot asphalt binder application rate shall not be reduced without
the Engineer’s approval.
3. Certification of compliance from the binder supplier shall be
provided for each load of hot asphalt binder delivered to the
jobsite, showing the type and quality of material delivered.
4. The Contractor shall provide satisfactory confirmation to the
Engineer, for each Street Section, showing the total quantity of
asphalt binder installed, at the proper application rate as published
by the manufacturer.
5-04.4 Measurement
No measurement will be made for the installation, maintenance, and
removal of temporary pavement markings.
Temporary Pavement will be measured by the ton in accordance with
Section 1-09.2, with no deduction being made for the weight of asphalt
binder, mineral filler, or any other component of the mixture. If the
Contractor elects to remove and replace mix as allowed by Section 5-
04.3(11), the material removed will not be measured.
5-04.5 Payment
Payment will be made for each of the following Bid items that are
included in the Proposal:
“HMA Cl. ½” PG 58H-22”
Rock Creek Culvert Replacement/Lincoln 5 - 36 June 3, 2021
Project Number: 13-3007.5
The unit contract price per ton for the above items shall be full
compensation for all costs incurred to carry out the requirements of
Section 5-04 except for those costs included in other items which are
included in the Subsection and which are included in the Proposal. This
work shall include the cost to install an asphalt thickened edge and/or
the pre-leveling work in the areas identified on the plans. The cost for
anti-stripping additive and water shall be included in this bid item.
No payment will be made for temporary pavement markings.
Temporary pavement markings shall be incidental to the project and
cost shall be included in the various items of the Contract.
Included in the cost per ton for “Temporary Pavement” shall be
placement and compaction of hot mix asphalt, cold mix asphalt,
additives, roadway excavation to proposed subgrade depths, haul and
disposal of temporary pavement.
Rock Creek Culvert Replacement/Lincoln 6 - 1 June 3, 2021
Project Number: 13-3007.5
DIVISION 6 – STRUCTURES
6-02 CONCRETE STRUCTURES
SECTION 6-02.2 IS SUPPLEMENTED WITH THE FOLLOWING:
6-02.2 Materials
(June 26, 2000)
Inserts shall be of the type and model specified in the Plans. Inserts
shall be galvanized in accordance with AASHTO M 111.
(September 3, 2019)
Hanger rods, and associated nuts and washers, shall conform to Section
9-06.5(1), and shall be galvanized in accordance with ASTM F2329.
Steel bars and plates shall conform to ASTM A 36 and shall be
galvanized in accordance with AASHTO M 111.
(September 3, 2019)
Horizontal strut bolts or threaded rods, and associated nuts and
washers, shall conform to Section 9-06.5(1), and shall be galvanized in
accordance with ASTM F2329.
Pre-formed fabric pads shall be composed of multiple layers of duck,
impregnated and bound with high quality oil resistant synthetic rubber,
compressed into resilient pads. The pre-formed fabric pads shall
conform to latest edition of MIL C 882 and the following requirements.
The number of plies shall be as required to produce the specified
thickness, after compression and vulcanizing.
Pre-formed fabric pads shall have a shore A hardness of 90+5 in
accordance with ASTM D 2240.
Pre-formed fabric pads for bridge utility supports will be accepted based
on the Manufacturer’s Certificate of Compliance that the material
furnished conforms to these specifications.
(June 26, 2000)
Pipe rolls or pipe saddles shall be of the type and model specified in the
Plans.
SECTION 6-02.3 IS SUPPLEMENTED WITH THE FOLLOWING:
6-02.3 Construction Requirements
Bridge Supported Utilities
(August 3, 2015)
The Contractor shall furnish and install inserts for the bridge utility
supports as shown in the Plans. The Contractor shall verify that the
hanger rods freely hang plumb in their inserts, and shall make
Rock Creek Culvert Replacement/Lincoln 6 - 2 June 3, 2021
Project Number: 13-3007.5
adjustments to the inserts as necessary and as accepted by the
Engineer prior to utility installation.
(******)
The Contractor shall furnish and install the bridge utility supports and
steel casing under approach slabs for sanitary sewer and water lines as
shown in the Plans. Utility pipes and casings will be installed on utility
supports on the bridge and through the steel casings under approach
slabs by others.
6-02.3(14) Finishing Concrete Surfaces
SECTION 6-02.3(14)C IS SUPPLEMENTED WITH THE FOLLOWING:
6-02.3(14)C Pigmented Sealer for Concrete Surfaces
Pigmented Sealer Materials
(April 6, 2009)
The color of the pigmented sealer shall be Washington Gray.
SECTION 6-02.5 IS SUPPLEMENTED WITH THE FOLLOWING:
6-02.5 Payment
The unit Contract price per square yard for “Bridge Approach Slab” shall
be full pay for excavation; providing and installing steel casing for
sanitary sewer and water lines; providing, placing, and compacting the
crushed surfacing base course; furnishing and placing Class 4000A
concrete; and furnishing and installing compression seal, anchors, and
reinforcing steel.
(June 26, 2000)
Bridge and Structures Minor Items
For the purpose of payment, such bridge and structures items as ***
anchor bolts, blockout forms, concrete inserts, joint material,
elastomeric bearing and stop pads, *** etc., for which there is no pay
item included in the proposal, are considered as bridge and structures
minor items. All costs in connection with furnishing and installing these
bridge and structures minor items as shown and noted in the Plans and
as outlined in these specifications and in the Standard Specifications
shall be included in the *** various bid items for which these minor
items are embedded, attached, or become part. ***
(******)
Bridge Supported Utilities
All costs in connection with placing utility supports on the bridge for
sanitary sewer and water lines as shown in the Plans shall be included
in the cost of prestressed girders.
Rock Creek Culvert Replacement/Lincoln 7 - 1 June 3, 2021
Project Number: 13-3007.5
DIVISION 7 – DRAINAGE STRUCTURES, STORM SEWERS,
SANITARY SEWERS, WATER MAINS, AND CONDUITS
SECTION 7-6 IS DELETED AND REPLACED WITH THE FOLLOWING:
7-06 TEMPORARY STREAM DIVERSION
7-06.1 Description
This work shall include designing, installing, operating, maintaining,
removing, and disposing of the temporary stream diversion,
environmental compliance and other Work as detailed in these
Specifications.
7-06.2 Materials
All materials shall be as detailed in the Contractor’s Temporary Stream
Diversion (TSD) Plan.
7-06.3 Construction Requirements
7-06.3(1) General
The Work shall include compliance with Washington State Water Quality
Standards in WAC 173-201A, project permits, environmental
commitments and these Provisions.
The temporary stream diversion may be either a gravity or a pumped
system. Pump screens must comply with the requirements in Section 7-
06.3(4) of these Special Provisions. Once a pumped diversion begins,
the pump must run continuously until it is no longer necessary to
bypass flows. The Contractor shall have back-up pumps on site and
shall provide twenty-four hour monitoring of the pumping operation.
Monitoring can be achieved by providing monitoring personnel on site
or through remote sensing and instrumentation to verify operation of
the bypass. If the Contractor elects to monitor by remote sensing and
instrumentation, a Type 2 Working Drawing shall be submitted outlining
how system operation will be monitored, how alerts will be made and
how personnel will respond to a diversion system failure.
The temporary stream diversion including water that is retained by the
temporary stream diversion and any dewatering system shall be located
within the permitted impact areas as shown in the Plans. The upstream
diversion dam shall be constructed to a height sufficient to prevent
stream flow from entering the work area. Scour protection shall be
provided at the outfall of the temporary stream diversion systems and
dewatering system to prevent flow re-entering the stream channel from
mobilizing streambed and embankment sediments. When a temporary
stream diversion is located in or near an intertidal zone the temporary
stream diversion design shall take tidal influence into consideration.
Rock Creek Culvert Replacement/Lincoln 7 - 2 June 3, 2021
Project Number: 13-3007.5
The Contractor shall have a contingency plan for the temporary stream
diversion to be used in the event of a storm producing streamflow in
excess of the design flow requirement, equipment failure, vandalism, or
other incident. The equipment and materials for the contingency
system shall be exclusive to a specific temporary stream diversion. The
Contractor shall immediately implement the contingency system when
required or specified by the Engineer. The contingency system shall be
designed to be fully operational within 2 hours.
For each temporary stream diversion the Contractor shall arrange a
meeting with the Engineer prior to implementation of the TSD Plan. At
this meeting the Contractor shall explain to the Engineer the Work to be
completed for the temporary stream diversion. The meeting shall be a
minimum of seven (7) calendar days prior to start of the temporary
stream diversion work.
The TSD shall be operational prior to performing any other work below
the Ordinary High Water Line.
7-06.3(2) Temporary Stream Diversion Plan
7-06.3(2)A General Plan Requirements
The Contractor shall submit a Temporary Stream Diversion Plan in
accordance with the requirements of a Type 2E Working Drawing and
these Specifications. A separate TSD Plan shall be prepared and
submitted for each temporary stream diversion that is required. The
Contractor shall include the details of the contingency system in the
TSD Plan as described in Section 7-06.3(2)C of these Special
Provisions. The TSD Plan shall consist of a narrative and drawings
detailing all temporary stream diversion requirements and shall
encompass and protect all the areas affected by the Contractor’s
temporary stream diversion Work.
The Contractor shall fully implement the TSD Plan throughout the
duration of the associated Work. The Contractor shall update the TSD
Plan throughout project construction to reflect actual site conditions and
the Contractor’s Work. Changes to plan shall comply with WAC 196-23-
020. At the request of the Engineer an updated TSD Plan shall be
submitted as a Type 2E Working Drawing. A copy of the TSD Plan shall
be on the project site at all times.
The TSD Plan shall describe measures that will be taken to comply with
Washington State Water Quality Standards in WAC 173-201A,
applicable permits, environmental commitments and these Provisions.
The Contractor shall incorporate the Diversion Schedule and Sequence
into their Progress Schedule.
Rock Creek Culvert Replacement/Lincoln 7 - 3 June 3, 2021
Project Number: 13-3007.5
7-06.3(2)B Stream Flows
Minimum Stream Flows
At all times of operation the Contractor’s temporary stream diversion
shall be designed to convey the following minimum flow rate of water in
cubic feet per second:
Rock Creek 16 cfs (Anticipated Seasonal 2-year Peak flow)
During all phases of the bypass installation and decommissioning, the
Contractor shall maintain flows downstream of the project site.
The minimum flow rates are provided for the Contractor’s convenience,
it is the Contractor’s responsibility to verify all pipes and pumps, where
applicable, are appropriately sized to ensure the stream flows will be
sufficiently bypassed. If the Contractor finds that the bypass pipe or
pump(s) is undersized, the Contractor shall notify the Engineer
immediately. The Contractor shall monitor the weather reports and if
precipitation in excess of the capacity of the diversion system is
forecast within 24 hours, the Contractor shall initiate the Contingency
System described below.
Contingency System
A Contingency System is required for this Project. The capacity of the
combined temporary stream diversion system and the Contingency
System shall be designed to convey the following minimum flow rate of
water in cubic feet per second:
Rock Creek 26 cfs (Anticipated Seasonal 5-year Peak flow)
The Contractor shall provide pumps, generators, hoses, and personnel
as backup to the stream diversion system in the event the diversion
becomes non-operational during construction. Pumps shall be
continuously monitored at night and during non-working hours in the
event of a power failure as described in 7-06.3(1).
Any emergency bypass pump intake shall be screened in order to
protect juvenile fish, in accordance with Section 7-06.3(4). The
Contractor shall inspect and remove any debris accumulated on the
face of the screen during the inspections described in Section 7-
06.3(5).
7-06.3(2)C Plan Requirements
The TSD Plan shall provide the following information in the following
order:
1. Description and Location of the temporary stream diversion
Rock Creek Culvert Replacement/Lincoln 7 - 4 June 3, 2021
Project Number: 13-3007.5
a. Identify the name of the water body where the temporary
stream diversion will be placed. Provide a description of the
temporary stream diversion.
b. Provide drawings showing the location of the temporary stream
diversion, including proposed access routes and equipment to
be used to construct the diversion.
2. Schedule and Sequence
a. Provide a sequence of Work, dates, and durations for when the
following will occur, in accordance with the in-water work
window in the Special Provisions:
i. Fish exclusion.
ii. TSD Plan Implementation Meeting
iii. TSD installation.
iv. Dewatering of the isolated Work area.
v. Restoration and stabilization of the temporary stream
diversion Work area to prevent erosion.
vi. Any relocations of the temporary stream diversion to
accommodate the Work sequence (if needed).
vii. Channel rewatering.
viii. Removal of the TSD.
ix. Fish block removal (performed by Contracting Agency).
b. Include other Work that needs to be coordinated with the TSD
(e.g., temporary erosion control).
3. Calculations and Materials
a. Detail all elements of the temporary stream diversion; including
but not limited to pipes, pumps, and other equipment.
b. Calculations shall demonstrate the diversion system conveys the
minimum peak flow specified by the Contracting Agency and
include tidal influence where applicable.
c. Temporary stream diversion shall include a water conveyance
system to be used for dewatering and rewatering that is capable
of conveying the flow required for the temporary stream
diversion.
Rock Creek Culvert Replacement/Lincoln 7 - 5 June 3, 2021
Project Number: 13-3007.5
d. Methods for anchoring temporary stream diversion pipe and
associated hardware; include calculations to demonstrate the
devices ability to anchor the pipe and associated hardware.
e. Specifications for all materials and equipment to be used as part
of the diversion including pump or diversion capacities and hose
sizes. For example, provide the type, profile, and size of pipe.
f. Provide the size of fish screens (mesh size and surface area) to
be used, in accordance with Section 7-06.3(5) of these Special
Provisions.
4. Stream Flow Blocking and Dewatering
a. Provide the method(s), including locations and details (narrative
and drawings) for blocking both the upstream and downstream
ends of the diversion. Describe how minor leakage from
upstream and downstream will be addressed.
b. Include provisions for scour protection at the temporary stream
diversion outfalls.
c. Identify the means and methods for dewatering water and
disposal of the water.
5. Contingency Plan
a. The Contractor shall include the details of the system in the TDS
Plan sections that are applicable.
b. Describe the Work that will be implemented to prevent the work
area from becoming inundated.
c. Provide the type and size of materials that will be used in the
event of the Work area becoming inundated, including fish
exclusion if the block nets are compromised.
d. Describe how the contingency equipment and materials will be
stored, inspected and maintained so they are ready for use if
required.
e. Describe how the contingency system will deployed and
operational within 2 hours.
6. Inspection and Maintenance
a. Provide the schedule and frequency for inspection of the
temporary stream diversion; include weekends and holidays.
b. Describe how maintenance will be conducted when inspections
identify deficiencies in the temporary stream diversion. These
Rock Creek Culvert Replacement/Lincoln 7 - 6 June 3, 2021
Project Number: 13-3007.5
include, but are not limited to removal and disposal of trapped
sediment or debris and repairing leaks.
c. The Contractor shall keep a record of all inspections and
maintenance of the temporary stream diversion.
7. Rewatering the Stream Channel
a. Detail how the stream channel will be rewatered to comply with
water quality requirements.
b. Identify measures that will prevent the stranding of fish during
rewatering (i.e. describe methods, rates, and durations of the
rewatering process knowing that flows downstream of the fish
block must be maintained to protect fish).
8. Removal of the Temporary Stream Diversion
a. Describe the sequence that will be used for removing the
temporary stream diversion and methods to prevent water
quality impacts.
b. Describe how disturbed soil will be permanently stabilized.
c. Describe any temporary pipes to remain (requires approval of
the Engineer): their type, pipe class, size, location, and plugging
procedure.
9. Other Work required for the Contractor’s temporary stream diversion
7-06.3(3) Fish and Aquatic Species Exclusion and Notifications
Prior to installing a temporary stream diversion, the Contractor (1)
install fish block nets upstream and downstream of the in-water Work
area; and (2) safely capture and relocate any fish and other aquatic
organisms that become trapped between the block nets. No Work
within the limits of the Ordinary High Water Line will be allowed prior to
installation of fish block nets and completion of fish exclusion activities.
Fish Removal
The Contractor shall provide for and coordinate with an experienced,
local fisheries Biologist for fish removal of the stream reach being
isolated by the temporary stream bypass system. The Contractor shall
submit the qualifications of the fisheries biologist to the Engineer for
approval. The fisheries Biologist, in accordance with any permits, shall
perform the following tasks:
1. Fish shall be removed from the stream reach to be diverted by first
installing fish screens upstream and downstream of the in-water
work area. The fish screens shall remain in place for the duration of
the construction activities. Once the fish screens are in place, a
Rock Creek Culvert Replacement/Lincoln 7 - 7 June 3, 2021
Project Number: 13-3007.5
beach seine net should be dragged downstream while guiding all fish
to the downstream net and collecting the fish at this end.
2. During dewatering of the reach, fish stranded in remaining pools
shall be removed with dip nets and if necessary, by conducting four-
pass electrofishing. If Chinook are found during the fish removal
activities, electrofishing should cease immediately. Electrofishing
must be conducted according to the NMFS (2000) Guidelines for
Electrofishing Waters Containing Salmonids Listed Under the
Endangered Species Act.
3. Upon removal, fish should be transported in clean buckets half-filled
with stream water and immediately reintroduced into the stream
downstream of the project site. Fish transportation equipment
should be ready and on the job site in advance.
7-06.3(4) Dewatering Work Area
Dewatering the isolated in-water Work area (between the upstream and
downstream diversion dams) shall occur at a rate slow enough to allow
safe capture and relocation all fish species and other aquatic organisms
to avoid stranding, as determined by the Engineer.
All pumps used for dewatering shall have an intake covered with a fish
screen, operated, and maintained in accordance with RCW 77.57.010
and RCW 77.57.070. Appropriate fish screens are as follows:
1. Perforated plate: 0.094 inch (maximum opening diameter);
2. Profile bar: 0.069 inch (maximum width opening); or
3. Woven wire: 0.094 inch (maximum opening measured on the
diagonal).
The minimum open area for all types of fish screens is twenty-seven
percent. The screened intake facility must have enough surface area to
ensure that the velocity through the screen is less than 0.4 feet per
second. The fish screen must remain in place whenever water is
withdrawn until the Contracting Agency Biologists confirm all fish have
been removed. At that point, the Contractor may remove the fish
screen to finish dewatering the work area.
7-06.3(5) Inspection and Maintenance
At a minimum, the Contractor shall perform the following activities once
per day (including weekends and holidays):
1. Check for and correct leaks;
2. Ensure the fish block nets remain sealed to the channel substrate.
Rock Creek Culvert Replacement/Lincoln 7 - 8 June 3, 2021
Project Number: 13-3007.5
The fish block nets shall be kept clear of debris that could jeopardize
the integrity of the nets. The Contractor shall perform the following
activities a minimum of three times per day or when requested by the
Engineer. On working days, these activities shall be performed at the
start, middle, and at the end of the working day. On non-working days,
these activities shall be performed between 6:00 am and 8:00 am,
between 11:00 am and 1:00 pm, and between 4:00 pm and 6:00 pm:
1. Inspect the upstream and downstream fish block nets and remove
debris;
2. Inspect the upstream fish block net and all screens and similar
facilities for impinged fish;
a. The Contractor shall immediately notify the Contracting Agency
when impinged fish are discovered.
b. Removal of impinged fish will be performed by the Contracting
Agency.
The Contractor shall maintain a written record of all inspection and
maintenance activities; record to be available at the request of the
Engineer.
7-06.3(6) Rewatering the Stream Channel
The Contractor shall notify the Engineer a minimum of 7 calendar days
in advance of rewatering the stream channel.
The Contractor shall introduce water to the new stream channel section
and trap sediments until the stream section meets the requirements of
these Provisions. Rewatering shall occur at a rate to avoid loss of
surface water downstream while the new channel section is rewatered.
7-06.3(7) Removal of the Temporary Stream Diversion
The Contractor shall notify the Engineer two business days in advance
of beginning the temporary stream diversion removal sequence.
Once the water in the new stream channel will meet the applicable
turbidity standards the Contractor may begin removal of the temporary
stream diversion and the stream channel opened to flows.
The Contractor shall immediately take all corrective actions necessary
to prevent the water from exceeding the turbidity standards should the
stream turbidity increase. All Work within the channel, except for
removal of the temporary erosion control items, shall be completed
before the temporary stream diversion is removed. The Contractor
must finish all construction activities within the limits of the Ordinary
High Water Line, including but not limited to culvert installation and
creek bed channel restoration, before the Contracting Agency will
remove the fish block nets.
Rock Creek Culvert Replacement/Lincoln 7 - 9 June 3, 2021
Project Number: 13-3007.5
All materials used for the diversion shall become the property of the
Contractor and removed from the project limits, with the exception of
any materials supplied by the Contracting Agency, unless otherwise
specified by the Engineer.
7-06.4 Vacant
7-06.5 Payment
Payment will be made for the following Bid items when included in the
proposal:
The lump sum Contract price for “Temporary Stream Diversion” shall be
full payment to perform the Work as specified. Progress payments for
the lump sum item “Temporary Stream Diversion” will be made as
follows:
1. Twenty-five percent of the bid amount will be paid following
completion of the TSD Plan including resolution of all Contracting
Agency review comments.
2. The remaining seventy-five percent of the bid amount shall be paid
in accordance with Section 1-09.9.
The lump sum contract price(s) above shall be full pay for all labor,
material, tools, and equipment, including but not be limited to:
temporary bypass plan submittals, installing and maintaining fish
exclusion screens, fish removal, all temporary bypass pipes, temporary
bypass pumps, isolation berms or structures, temporary erosion and
stabilization measures for the temporary stream diversion, and all
incidentals necessary to satisfactorily complete the work of the above
bid item(s) as defined in the plans, specifications, and special
provisions.
7-08 GENERAL PIPE INSTALLATION REQUIREMENTS
SECTION 7-08.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-08.2 Materials
All pipe shall be of the type and material specified in the bid proposal,
shown on the plans or specified herein.
All materials used for construction of sanitary sewer and storm drainage
systems and appurtenances shall be new and undamaged. All materials
used shall be subject to inspection by the City prior to use. The
Contractor shall provide the City with shop drawings, manufacturer’s
specifications and certificates of materials as requested.
Rock Creek Culvert Replacement/Lincoln 7 - 10 June 3, 2021
Project Number: 13-3007.5
The materials referred to herein, shall conform to the applicable
provisions of the WSDOT Standard Specifications, the Kent Special
Provisions and the manufacturer’s recommended installation
procedures. See the following Sections of the WSDOT Standard
Specifications and the Kent Special Provisions:
Hot Mix Asphalt ............................... 5-04.2
Cement Concrete Pavement .............. 5-05.2
Culvert Pipe .................................... 7-02.2
Storm Sewers ................................. 7-04.2
Manholes, Inlets and Catch Basins...... 7-05.2
Sanitary Sewer ................................ 7-17.2
Side Sewers .................................... 7-18.2
Crushed Surfacing ........................... 9-03.9(3)
Gravel Backfill for Pipe Zone Bedding .. 9-03.12(3)
Gravel Borrow ................................. 9-03.14(1)
Foundation Material Class I and II ...... 9-03.17
Bank Run Gravel for Trench Backfill .... 9-03.19
7-08.3 Construction Requirements
SECTION 7-08.3(1)A IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-08.3(1)A Trenches
If well points are used for dewatering pipe trenches, they shall be
adequately spaced to provide the necessary dewatering and shall be
sandpacked and/or other means used to prevent pumping of fine sands
or silts from the sub-surface. A continual check by the Contractor shall
be maintained to insure that the sub-surface soil is not being removed
by the dewatering operation.
Once commenced, the dewatering operation shall be continuous until
construction and backfilling in the dewatered area is complete. Pump
shutdown shall be accomplished in an approved gradual manner. The
Contractor shall provide enough facilities and personnel to maintain
continuous operation once commenced. Such continuous operation shall
be the responsibility of the Contractor.
In the event of damage to the trench foundation as determined by the
Engineer, or to the ditch walls, or other operations resulting from the
failure of the Contractor to maintain the dewatering operation, the
complete cost of all repairs shall be borne by the Contractor.
It shall be the sole responsibility of the Contractor to dispose of all
waters resulting from its dewatering operation. This responsibility also
includes choice of method, obtaining regulatory agency approvals,
complying with state water quality standards and other agency
requirements.
Rock Creek Culvert Replacement/Lincoln 7 - 11 June 3, 2021
Project Number: 13-3007.5
Each individual project and dewatering operation shall be evaluated
individually to determine exact requirements; however, in general the
following conditions will apply.
1. Disposal into the existing storm drain facilities (pipes, channels,
ditches, etc.) may be acceptable if the Contractor obtains the
necessary permits and approvals.
2. Discharge to existing storm drain facilities shall not result in a
violation of state water quality standards for surface water,
Chapter 173-203 WAC.
3. The Contractor shall monitor discharge and receiving water(s) as
required to verify that water quality standards are being met.
4. If necessary to meet standards and approval requirements, the
Contractor shall treat the water prior to discharge. A settling pond
may be an acceptable method of treatment.
Any damage, as determined by the Engineer to properties or
improvements resulting from an inadequate disposal (water) operation
shall be the responsibility of the Contractor, including repairs,
replacements and/or restoration.
Where required or where directed by the Engineer, stabilization of the
trench bottom shall be in accordance with Section 7-08.3(1)A of the
WSDOT Standard Specifications. Excavation of the unsuitable material
shall be considered as trench excavation. The unsuitable material shall
be disposed of by the Contractor.
Backfill unsuitable material excavations with Foundation Material Class I
or II meeting the requirements of Section 9-03.17 of the Kent Special
Provisions with the class called for in the bid proposal, on the plans or
by the Engineer in the field.
Trench excavation shall include the required pavement removal for
construction of the trench. See Section 2-02.3(3) of the Kent Special
Provisions.
SECTION 7-08.3(1)C IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-08.3(1)C Bedding the Pipe
Bedding shall be placed in accordance with Standard Plan B-55.20-00.
Bedding material shall be in accordance with Section 9-03.12(3) of the
Kent Special Provisions.
Bedding material shall be tamped in layers under, around and above
the pipe to adequately support and protect the pipe. The Contractor
shall use compaction equipment approved by the Engineer to obtain
adequate compaction of the bedding material. Unless otherwise
approved by the Engineer, adequate compaction shall be construed to
mean to at least 95 percent of the maximum density measured in
accordance with ASTM D-1557.
Rock Creek Culvert Replacement/Lincoln 7 - 12 June 3, 2021
Project Number: 13-3007.5
The pipe shall be protected from damage when compacting. At least
two feet of cover is required over the pipe prior to using heavy
compaction equipment.
SECTION 7-08.3(2)B IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-08.3(2)B Pipe Laying - General
At locations of pipe crossing between new or existing pipes the
minimum vertical clearance shall be one and one-half foot unless
otherwise approved by the Engineer. If this clearance cannot be
obtained, the Contractor shall install a 2-inch thick 1-2 PSF styrofoam
cushion between the pipes. The cushion shall be installed longitudinally
with the lower pipe. The cushion width shall be equal to the lower pipe
diameter and the length shall be one foot greater than the upper pipe
diameter.
It should be noted that field adjustment of specified slopes for storm
and sanitary side sewers are permissible, if approved by the Design
Engineer, to obtain the minimum clearances.
External or internal grouting or repair by use of collars on the new
sanitary or storm sewer line will not be an acceptable means of repair,
should repair be necessary.
All pipe, adaptors, tees, and other fittings shall be used for the purpose
intended by the manufacturer and shall be installed according to
manufacturer’s recommendations.
SECTION 7-08.3(2)G IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-08.3(2)G Jointing of Dissimilar Pipe
Connections of Ductile or Cast Iron Pipe to Concrete Pipe or PVC Pipe
will be done by the use of Cast Transition or reducing couplings (Romac
501 or equivalent).
SECTION 7-08.3(2)H IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-08.3(2)H Sewer Line Connections
Where indicated on the plans or where directed by the Engineer,
connections shall be made to the existing storm drain/sewer systems
by the Contractor in accordance with applicable portions of the WSDOT
Standard Specifications and Kent Special Provisions in a workmanlike
manner satisfactory to the Engineer.
SECTION 7-08.3(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
7-08.3(2)K Vertical Clearance Between Utility Lines
Rock Creek Culvert Replacement/Lincoln 7 - 13 June 3, 2021
Project Number: 13-3007.5
Vertical clearance between water line and sanitary sewer, drainage and
other utilities shall comply with CWD Standards and Specifications
Section 3.05, 3.06 and 5.49, when discrepancies between plans and
Specifications are present, the 2016 CWD Standards and Specifications
shall prevail.
7-08.3(2)K Pipe Laying - PVC
For PVC pipe, the Contractor shall maintain a cover over the pipe to
prevent temperature deformation caused by the sun and shall remove
such cover only for a sufficient time to allow the pipe to be installed.
When making field cuts of PVC pipe, a new reference line shall be
marked on the spigot end a distance of 4-5/8 inches from said end.
Said end will provide a visual means of determining whether full
insertion of the spigot into the bell has been made during installation.
SECTION 7-08.3(3) IS REVISED AS FOLLOWS:
7-08.3(3) Backfilling
The Third, Fourth, and Fifth sentences of the fourth paragraph are
deleted.
The sixth paragraph is deleted.
SECTION 7-08.3(4) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-08.3(4) Plugging Existing Pipe
Existing pipes being plugged shall be plugged with concrete at both
ends and shall otherwise be in accordance with Section 7-08.3(4) of the
WSDOT Standard Specifications.
SECTION 7-08.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
7-08.3(5) Street Restoration
Unless otherwise shown on the plans, street restoration shall be in
accordance with the following requirements:
Where cuts have been made in either asphalt concrete pavement,
or in oil mats, the Contractor shall reconstruct the trench areas
with a 3 inch thick asphalt concrete patch placed on a 2 inch
thickness of crushed surfacing top course over a 4 inch thickness
of crushed surfacing base course or as directed by the Engineer in
the field. However, where cuts have been made in an asphalt
concrete pavement section to be overlayed, the Contractor shall
reconstruct the trench with a 2 inch thick asphalt concrete patch
with a 2 inch asphalt overlay for a total of 4 inches of asphalt
Rock Creek Culvert Replacement/Lincoln 7 - 14 June 3, 2021
Project Number: 13-3007.5
concrete pavement over 2 inches of crushed surfacing top course
over 4 inches crushed surfacing base course.
In all cases, the asphalt and crushed surfacing thickness for the
patch shall meet or exceed the existing pavement section. Upon
approval of the Engineer, Controlled Density Fill may be used to
back fill the narrow trenches where it is difficult to compact
crushed surfacing. In these cases the asphalt concrete layer shall
increase to a minimum of 2 inches greater than the existing
section.
Where cuts have been made in cement concrete pavement, the
Contractor shall reconstruct the trench area with a 6 inch thick
cement concrete patch placed on a 6 inch thickness of crushed
surfacing top course. In all cases, the cement concrete and
crushed surfacing thickness for the patch shall meet or exceed the
existing pavement section.
Where there is an existing asphalt overlay over cement concrete
pavement, the cement concrete shall be patched to original grade
as above and then overlaid with an asphalt concrete patch to
existing grade.
All gravel shoulders shall be restored to their original condition and
shape. The Contractor shall spread a 2 inch thick layer of crushed
surfacing on the shoulder. The shoulder shall be finished with a grader
after backfilling and compacting and before spreading the crushed
surfacing.
Permanent surface treatments and pavements shall not be placed until
an as-built survey and testing of the new underground utilities have
been completed. Verification that utility construction conforms to the
line and grade requirements of Section 7-08.3(2)B of the WSDOT
Standard Specifications shall be made by the Engineer prior to
authorizing paving to begin. Also, each new utility must pass all
appropriate tests specified herein for the type of utility prior to paving.
SECTION 7-08.4 IS REVISED BY DELETING THE FIRST PARAGRAPH AND
REPLACING WITH THE FOLLOWING:
7-08.4 Measurement
Gravel backfill for foundation and gravel backfill for pipe zone bedding
shall be measured by the ton, including haul.
7-09 WATER MAINS
SECTION 7-09.1 IS DELETED AND REPLACED WITH THE FOLLOWING:
Rock Creek Culvert Replacement/Lincoln 7 - 15 June 3, 2021
Project Number: 13-3007.5
7-09.1 Description
This work consists of constructing water mains 16 inches in diameter
and smaller in accordance with the Plans; the Covington Water District
Standard Plans and Specifications; these Standard Specifications; the
Special Provisions and the Standard Plans, at the location shown on the
Plans. For water main related work, the Covington Water District
Standard Plans and Specifications shall take precedence.
SECTION 7-09.1(1)D IS DELETED AND REPLACED WITH THE FOLLOWING:
7-09.1(1)D Pipe Zone Backfill
Pipe zone backfill includes material placed above the gravel backfill for
pipe zone bedding up to the depths shown in the Covington Water
District Standard Plans.
SECTION 7-09.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-09.2 Materials
Pipe Zone Backfill 9-03.12(3)
Crushed Surfacing Top Course for Trench Backfill 9-03.9(3)
Steel Casing 9-30.2(11)
Spacers and Seals for Steel Casing Pipe 9-30.2(12)
Pipe Insulation 9-30.2(13)
7-09.3 Construction Requirements
SECTION 7-09.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-09.3(1) General
All construction to be in accordance with Covington Water District
Standards and Specifications.
For outages (shutdowns) customers must be notified 48hrs before the
shutdown. Contractor must schedule the shutdowns with Covington
Water District (CWD) inspector at least 10 working days before.
Customers must be notified with door hangers (CWD will provide
them).
SECTION 7-09.3(9) IS DELETED AND REPLACED WITH THE FOLLOWING:
7-09.3(9) Bedding the Pipe
All backfill for pipe zone bedding shall be import. No native material
shall be allowed for pipe zone bedding.
SECTION 7-09.3(10) IS DELETED AND REPLACED WITH THE FOLLOWING:
Rock Creek Culvert Replacement/Lincoln 7 - 16 June 3, 2021
Project Number: 13-3007.5
7-09.3(10) Backfilling Trenches
All backfill for trenches shall be import. No native material shall be
allowed for trench backfill unless screened to specifications and
approved by the Covington Water District and Transportation Authority
SECTION 7-09-3(13) IS REVISED BY ADDING THE FOLLOWING TO THE LAST
PARAGRAPH:
7-09.3(13) Handling of Pipe
The open ends of pipe shall be covered with temporary bags, caps or
plugs from the manufacturer or supplier to the project site, and
maintained by the contractor until such time as the pipe is installed in
the trench.
SECTION 7-09.3(15)A THE LAST SENTENCE OF THE FIRST PARAGRAPH IS
DELETED AND REPLACED WITH THE FOLLOWING:
7-09.3(15)A Ductile Iron Pipe
For water mains 12-inch diameter or less, pipe joint deflections shall
not exceed 3-degrees per joint for unrestrained pipe and 1-1/2 degrees
per joint for restrained pipe. Joint deflections shall not exceed 11
inches for every 18-feet of unrestrained pipe, or 5.5-inches for every
18-feet of restrained pipe. Joint deflection requirements for pipe larger
than 12-inch diameter shall be at the discretion of the District Engineer.
The use of short pipe segments to achieve a greater rate of deflection is
prohibited. Angle fittings may be required to maintain proper water
main alignment within public right-of-way easements.
SECTION 7-09.3(15)A IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-09.3(15)A Ductile Iron Pipe
Laying water main pipe will comply with CWD Standards and
Specifications section 5.25. When discrepancies between plans and
Specifications are present, the 2016 CWD Standards and Specifications
shall prevail.
SECTION 7-09.3(19)A PARAGRAPH ONE IS DELETED AND REPLACED WITH
THE FOLLOWING:
7-09.3(19)A Connections to Existing Mains
Points of connection to existing water mains shall be exposed prior to
trenching of the new mains, and not less than 48 hours prior to the
anticipated connection time. The Contractor is responsible for giving at
least five (5) working day notice to the District for the required water
main shutdown and following the planned shut down schedule
immediately after the pre-construction meeting. Water main shutdown
shall not be scheduled to take place on Fridays, or on the day before a
Rock Creek Culvert Replacement/Lincoln 7 - 17 June 3, 2021
Project Number: 13-3007.5
holiday, unless otherwise approved by the District. Only District staff
shall operate valves in the existing system and shut down the water
mains. Connection to the existing water system shall be done only after
the new mains are flushed and have passed pressure and purity tests.
The District may delay the planned shutdown if complications to system
operation is expected, and will notify the Contractor that alternate plans
will be required. The Contractor shall submit a plan for providing
immediate thrust restraint at connection points requiring thrust blocks.
The plan must be approved by the District prior to commencing with
the connection. All connections to the existing water system must be
approved by the District and in the presence of the District Inspector.
SECTION 7-09.3(19)A PARAGRAPH TWO IS SUPPLEMENTED WITH THE
FOLLOWING:
7-09.3(19)A Connections to Existing Mains
When connecting to Asbestos Cement Pipe, conform to Federal and
State requirements for removal, handling and disposal of Asbestos Pipe.
SECTION 7-09.3(19)A PARAGRAPHS FIVE AND SIX ARE DELETED AND
REPLACED WITH THE FOLLOWING:
7-09.3(19)A Connections to Existing Mains
If the connection to the existing system involves turning off the water,
the District shall plan the shutdown and notify the affected customers
and Fire Authority.
Where cut-ins are required to be made in existing pipes, the work shall
be conducted at such a time and in such a manner as to minimize the
interruption of service. The necessary pipe, fittings and gate valves
shall be assembled at the site ready for installation prior to shut-off of
water in the existing main. The interiors of all pipe and fittings,
particularly couplings and sleeves, to be used in the final cut-in
connection shall be swabbed or sprayed with a minimum 12.5%
hypochlorite solution before they are installed. The pipe and fittings to
be treated by swabbing and spraying shall consist of less than one full
stick of pipe. The remainder of the new main shall be disinfected and
accepted as a whole, previous to the connection process. Flushing shall
start as soon as repairs or connections are completed and shall be
continued until discolored water and air is eliminated. Flushing shall be
supervised by the District.
SECTION 7-09.3(19)A IS SUPPLEMENTED WITH THE FOLLOWING:
7-09.3(19)A Connections to Existing Mains
In non-residential areas, all effort will be made not to interrupt service
to a commercial business during business hours. Contractor shall
accommodate temporary water service to businesses should they be
out of service during business hours. Temporary water service shall be
Rock Creek Culvert Replacement/Lincoln 7 - 18 June 3, 2021
Project Number: 13-3007.5
provided in accordance with requirements of the International Plumbing
Code for potable water supply. Residential customers shall not be
placed out of service for any period in excess of 8 hours.
The Contractor shall ensure that existing fittings are in accordance with
the approved plans and that the connection can be made in accordance
with the plans. The contractor shall immediately notify the District
Engineer and the Design Engineer if the connection cannot be made in
accordance with the plans so that the connection details may be revised
and approved by the District.
Connections to the existing water system may be made under pressure
with a tapping machine by determining the size and type of pipe and
installing a tapping tee with a tapping gate valve for instances where
valves are not being added at the tee. Tapping tees shall be installed as
shown on the Covington Water District’s Standard Details; Appendix A.
Work shall not start until all materials, equipment, and labor are on-site
and ready. The tapping tee and valve shall be installed in a horizontal
position so that the valve stem is vertical. Once the water main has
been shut off, the work shall be prosecuted vigorously and shall not be
halted until the water main is back in service. District inspection shall
be provided throughout the connection process and the Contractor shall
compensate the District for any required overtime to complete the
work. Scheduling of the work shall be only as approved by the District.
SECTION 7-09.3(21) IS SUPPLEMENTED WITH THE FOLLOWING:
7-09.3(21) Concrete Thrust Blocking
Concrete thrust blocking will comply with CWD standards and
Specifications section 3.15. When discrepancies between plans and
Specifications are present, the 2016 CWD standards and specifications
shall prevail.
SECTION 7-09.3(22) IS SUPPLEMENTED WITH THE FOLLOWING:
7-09.3(22) Blowoff Assemblies
Blowoff assemblies will comply with CWD standards and specifications
Section 3.20, 4.19 and 5.31. When discrepancies between plans and
Specifications are present, the 2016 CWD standards and specifications
shall prevail.
SECTION 7-09.3(23) IS DELETED AND REPLACED WITH THE FOLLOWING:
7-09.3(23) Hydrostatic Pressure Test
Prior to calling the Inspector for pressure test, the Contractor shall have
all equipment set up for operation and shall have successfully
performed a pre-test to ensure that the pipe is capable of meeting test
Rock Creek Culvert Replacement/Lincoln 7 - 19 June 3, 2021
Project Number: 13-3007.5
conditions. All service lines shall be flushed, before scheduling the
pressure test.
Water main, appurtenances and service connections shall be tested in
sections of convenient lengths under a hydrostatic pressure of 200 psi
to 210 psi for 15 minutes.
Pumps, gauges, plugs, saddles, corporation stops, miscellaneous hose
and piping, and measuring equipment necessary for performing the test
shall be furnished and operated by the Contractor. The Contractor shall
demonstrate the gauge is working properly before the testing begins.
Sections to be tested shall normally be limited to 1,000 feet.
The pipe shall be backfilled sufficiently to prevent movement of the pipe
under pressure. Thrust blocking shall be in place for an adequate time
for concrete to cure before testing. Where permanent blocking is not
required, the Contractor shall furnish and install temporary blocking
and remove it after testing. Thrust-blocking shall meet the performance
requirements of the details shown in Standard Drawings for specific
orientations of the main. In no case shall pressure be applied before 48
hours cure time of the thrust blocking.
The Contractor shall use a meter cart rented from the District to fill new
water mains for testing and flushing. New water mains shall be filled
and remain under 100 psi to 200 psi pressure for 24 to 48 hours to
allow air to escape and the lining of the pipe to absorb water.
The pressure test shall be accomplished by pumping the main up to 200
psi to 210 psi and maintaining the pressure, stopping the pump for 15
minutes, and pumping the main up to the test pressure again. During
the test, the section being tested shall be observed to detect any visible
leakage.
A clean container shall be used for holding water for pumping up
pressure on the main being tested. This makeup water shall be
sterilized by the addition of chlorine to a concentration of 50 ppm.
The quantity of water required to restore the pressure shall be
accurately determined by pumping through a positive displacement
water meter. The meter shall be approved by the District. Essentially no
loss will be allowed.
There shall not be an appreciable or abrupt loss in pressure during the
15 minute test period. Any visible leakage detected shall be corrected
by the Contractor regardless of the allowable leakage specified above.
Should the tested section fail to meet the pressure test successfully as
specified, the Contractor shall locate and repair the defects and then
retest the pipeline. There shall be no additional cost to the District for
failed tests.
Tests shall be made with the hydrant auxiliary gate valves open and the
hydrant valve in the closed position. Once the new line is successfully
Rock Creek Culvert Replacement/Lincoln 7 - 20 June 3, 2021
Project Number: 13-3007.5
tested, each valve shall be tested by closing each in turn and relieving
the pressure behind it. The mains shall be tested between valves.
Insofar as possible, no hydrostatic pressure shall be placed against the
opposite side of the valve being tested. This test of the valve will be
acceptable if there is no immediate loss of pressure on the gauge when
the pressure comes against the valve being checked. The Contractor
shall verify that the pressure differential across the valve does not
exceed the rated working pressure of the valve.
Defective materials or workmanship discovered as a result of
hydrostatic field test shall be replaced by the Contractor. Whenever it is
necessary to replace defective material or correct the workmanship, the
hydrostatic test shall be repeated to the satisfaction of the District.
SECTION 7-09.3(24) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-09.3(24) Disinfection of Water Mains
Following the pressure test, flushing procedure and disinfection of the
pipe, the Contractor shall arrange with the Public Works Inspector for
coliform (purity) tests to be taken by the Water Department. Two
samples taken 24-hours apart, with no flushing between samples is
required to be taken from each apparatus. The Contractor may elect to
contract with a City-approved lab for the tests. Contractor shall pay for
purity tests as required by the City.
The Contractor shall install corporation stops at all locations required to
take bacteriological test samples. If the original test sample proves
unsatisfactory, an additional charge will be assessed to the Contractor
for processing each additional sample.
SECTION 7-09.3(24) IS DELETED AND REPLACED WITH THE FOLLOWING:
7-09.3(24) Disinfection of Water Mains
Before being placed into service, new water mains and repaired
portions of existing mains shall be chlorinated and thoroughly flushed
followed by a minimum of two bacteriological samples at each sampling
point collected consecutively 24 hours apart by Covington Water District
staff.
Water samples will be submitted to a certified laboratory and
confirmation of satisfactory results will be received on a DOH approved
form utilized by the certified laboratory. Disinfection of water mains
shall be accomplished by the Contractor in accordance with the
requirements of the Washington State Department of Health, AWWA
Standard C651 and in a manner satisfactory to the District. All filling
and flushing shall be done through a hydrant meter cart rented from
the District. A chlorination apparatus capable of accurately introducing
chlorine solution shall be used for the disinfection process. Refer to
Section 7-09.3(19) for disinfection of connections and repairs. Flush
Rock Creek Culvert Replacement/Lincoln 7 - 21 June 3, 2021
Project Number: 13-3007.5
and sample from the downstream flow. Sampling criteria shall be as
follows: First day samples shall reflect flow through a hydrant meter to
all end points and arterials. The system should set dormant for 24
hours and second set of samples taken which shall be representative of
the water in the pipe; there should be no additional flushing in order to
obtain a representative sample of water remaining in the pipe for 24
hours.
7-09.3(24)A Flushing
The section to be disinfected shall be first flushed to remove any solids
or contaminatedmaterial that may have become lodged in the pipe at
maximum flow established by the District Engineer prior to chlorination.
If a hydrant is not installed at the end of the water main, the Contractor
shall provide a tap large enough to develop a flow velocity of at least
2.5 feet/sec in the water main or adequate flushing facilities such as a
blow-off described in these specifications. The flushing period must be
approved by the District Engineer.
The source water used for disinfection and pressure testing shall be
flushed by District Staff prior to its use to ensure that contaminants or
debris are not introduced into the new pipe.
Taps for temporary or permanent release of air, introduction of chlorine
or flushing purposes shall be provided by the Contractor as a part of the
construction of water mains. Temporary taps shall be plugged after use
with threaded brass plugs.
7-09.3(24)B Requirement of Chlorine
The section to be tested shall be chlorinated so that a free residual of
no less than 25 ppm (parts per million) is measured at the end of all
main arterials. At a minimum, flush each service line to disinfect those
portions allowing the chlorinated water to remain in facilities, blow offs,
hydrant spools, and service lines, etc. for a minimum of 24 hours. The
initial chlorine content of the water shall not be less than 50 ppm nor
more than 100 ppm. The forms of chlorine that may be used in the
disinfection operations are liquid chlorine injection at 12.5%.
Liquid Chlorine: Chlorine shall be applied by solution fed at one end of
the section with a Service or hydrant at the opposite end open
sufficiently to permit a flow through during chlorine application. The
chlorine solution shall be fed into the pipeline already mixed by an
automatically proportioning applicator to provide a steady application
target rate of 50 ppm chlorine. Hydrants, services and blow-offs along
the chlorinated section shall be open during application until the
presence of chlorine has definitely been detected in each hydrant and
service run.
When a chlorine concentration no less than 25 ppm has been
established throughout the line, the valves shall be closed and the line
left undisturbed for 24 hours. If the chlorine concentration in the
Rock Creek Culvert Replacement/Lincoln 7 - 22 June 3, 2021
Project Number: 13-3007.5
pipeline exceeds 100 ppm, the pipeline shall be flushed immediately
and the process shall start over.
Granulated hypochlorite designed for pools and hot tubs are
unacceptable for use on water mains.
The main shall be filled with water at a rate to ensure that the water
within the main will flow at a velocity no greater than 1ft/s. Precautions
shall be taken to ensure that air pockets are eliminated. When a
chlorine concentration of not less than 25 ppm and not more than 100
ppm has been established throughout the line, the valves shall be
closed and the line left undisturbed for 24 hours. If chlorine
concentration exceeds 100ppm the Contractor will immediately effect a
reduction in the concentration by properly flushing the main and
removing chlorine at the discharge. If the water temperature is less
than 41 degrees F, the water shall remain in the pipe for at least 48
hours to complete disinfection. The line shall then be thoroughly flushed
and water samples taken. The Contractor shall exercise special care in
flushing to avoid damage to surrounding property and to conform to
Covington Water District Standards. The Contractor shall provide an
accurate written report of the procedure used to the construction
inspector.
7-09.3(24)C Final Flushing and Testing
Following chlorination, chlorinated water shall be flushed from the new
water main until the replacement water throughout its length shows
residuals equal to background chlorine levels in the system.
After final flushing and before the new water main is connected to the
distribution system, two consecutive sets of acceptable samples, taken
at least 24 hours apart, shall be collected from the new main. The
Contractor shall schedule the sample collection with the District a
minimum of three (3) work days in advance of test. The number of
samples from the source and the number of representative sample
points required will be determined by the District. Appropriate sample
taps shall be furnished by the Contractor. No hose or fire hydrant shall
be used in the collection of samples unless directed by District
Engineer.
At least one set of samples shall be collected from every 1,200 feet of
the new water main, plus one set from the end of the line and at least
one set from each branch. All samples shall be tested for total coliform
bacteria and for heterotrophic bacteria by the heterotrophic plate count
(HPC) analysis. The maximum allowable coliform content of the flushed
sample shall be zero. The maximum allowable HPC population count in
all source samples shall be 300/ml. Any source sample that exceeds a
count of 300/ml shall be ruled as an indeterminate test and a new set
of source and construction samples for analysis shall be required. The
maximum allowable HPC population count from any construction
sample shall be no greater than twenty (20) counts above the highest
source HPC population count.
Rock Creek Culvert Replacement/Lincoln 7 - 23 June 3, 2021
Project Number: 13-3007.5
Before placing the lines into service, a satisfactory report shall be
received by the District from the certified laboratory evidencing
successful tests on samples collected from representative points in the
system extension.
Should the initial test result in an unsatisfactory bacteriological test,
additional chlorination using the procedure as specified above shall be
repeated by the Contractor until satisfactory results are obtained. The
Contractor shall be responsible for disposal of treated water flushed
from the mains including de-chlorination as necessary to protect the
environment.
Chlorinated water shall never be flushed into the storm drain without
local agency approval or to a natural body of water. This includes lakes,
rivers, streams, storm drainage systems, and any and all other waters
where fish or other natural aquatic life can be expected. Chlorinated
water may be discharged to an available sanitary sewer system with
the appropriate sewer District’s approval and where the rate of
discharge will not overload the sanitary sewer.
SECTION 7-09.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
7-09.3(25) Minor Change for Water Improvements
Payments or credits for changes for items of Work under Schedule II
amounting to $10,000 or less may be made under the Bid item “Minor
Change for Water Improvements.” At the discretion of the Contracting
Agency, this procedure for Minor Change for Water Facilities may be used
in lieu of the more formal procedure as outlined in Section 1-04.4,
Changes.
The Contractor will be provided a copy of the completed order for Minor
Change for Water Facilities. The agreement for the Minor Change for
Water Facilities will be documented by signature of the Contractor, or
notation of verbal agreement. If the Contractor is in disagreement with
anything required by the order for Minor Change for Water Facilities, the
Contractor may protest the order as provided in Section 1-04.5.
SECTION 7-09.3 ADD THE FOLLOWING NEW SECTION:
7-09.3(26) Steel Casing
Water main casing method of installation shall be determined by the
Contractor and submitted for Engineer approval.
Contractor Submittals
Submit all procedures or material descriptions requiring the Engineer’s
approval prior to mobilizing. Include the following information in the
operations and design submittal:
Rock Creek Culvert Replacement/Lincoln 7 - 24 June 3, 2021
Project Number: 13-3007.5
Submittal requirements include, but are not limited to the following:
1. Verification of Line and grade calculations relative to diaphragm
knockouts, to water main installation and final cement concrete
approach slab thickness.
2. Copies of field notes used to establish grade.
3. Material list.
4. Details on casing spacer and end seal materials, dimensions and
installation procedures and recommendations.
SECTION 7-09.3 ADD THE FOLLOWING NEW SECTION:
7-09.3(27) Pipe Insulation
The Contractor shall field install watermain insulation that is precisely two
(2) inches thick as well as the insulation jacketing. Insulation shall cover
all portions of the suspended water main between end diaphragms
including intermediate diaphragm(s), pipe bells and bridge hangers. The
insulation shall terminate within 1-foot on either side of the flexible
double ball joint and abut the end diaphragms.
Insulation shall be installed per manufactures recommendations.
SECTION 7-09.5 IS REVISED AS FOLLOWS:
7-09.5 Payment
The unit contract price per linear foot for “D.I. Water Main – 12-inch
Diameter” shall be full compensation for all Work to complete the
installation of the water main, including but not limited to, pipe, fittings,
bends, restrained joints, thrust blocks, trench excavation, bedding the
pipe, import pipe bedding material, backfilling the pipe, import trench
backfill material, laying and jointing pipe and fittings, backfilling
compacting, concrete thrust blocking, testing, disinfection, flushing,
dechlorination of disinfecting water, and cleanup. Additionally, the
contract price shall be compensation for:
All costs associated with removal, haul, and disposal of native
material excavated from trench.
Locating existing utilities, water mains and services and
potholing in advance to determine their horizontal and vertical
locations.
Trench dewatering (if needed).
Providing, placing and compacting import pipe bedding
material.
Providing, placing and compacting import trench backfill
material.
Rock Creek Culvert Replacement/Lincoln 7 - 25 June 3, 2021
Project Number: 13-3007.5
Deflecting pipe as required to cross buried utilities or maintain
alignment.
Performing backfill compaction tests and furnishing test reports
to the Engineer.
Hand digging that may be required to protect existing
improvements and utilities.
All complete in place, fully operational and ready for use.
Modify the last sentence of the fourth paragraph to read:
If no pay items for restoration are included in the Proposal, restoration
shall be considered incidental to the Work of constructing the water
main, and all costs thereof shall be included in the unit Contract price
Bid for “D.I. Water Main ___ -inch Diameter”, Strike from this section
the following two paragraphs:
“Removal and Replacement of Unsuitable Material”, per cubic yard.
“Bank Run Gravel for Trench Backfill”, per cubic yard.
Revise paragraph eleven to read:
“Shoring”, per square foot.
Add the following to this section:
The unit contract price per linear foot for “D.I. Water Main – 12-inch
Diameter on Bridge” shall be full compensation for all work to complete
the installation of the water main from end diaphragm to end
diaphragm, including but not limited to, pipe, fittings, restrained joints,
force balanced flexible double ball joint fittings (flexible expansion
joint), bends, thrust blocks, installing the pipe in the hangers and
supports, installing the main through the end and intermediate
diaphragms, laying and jointing pipe and fittings, concrete thrust
blocking, testing, disinfection, flushing, dechlorination of disinfecting
water, and cleanup.
The unit Contract price per pound for "Additional Ductile Iron Fittings"
shall be full payment for all costs of the Work to furnish and install
additional cast iron fittings not shown on the Plans, but required by the
Engineer to provide a complete system, and shall include all costs
necessary for a complete installation in full working order, tested and
disinfected, as herein specified and otherwise shown on the Plans,
including associated thrust or restraint blocks, or restrained joint(s).
No additional payment shall be made for fittings and couplings which
would be normally anticipated in the Work shown on the Plans, even
though said fittings and couplings were not specifically shown on the
Plans.
Rock Creek Culvert Replacement/Lincoln 7 - 26 June 3, 2021
Project Number: 13-3007.5
The unit Contract price per Linear Foot for “Steel Casing, 20-Inch
Diameter” shall be included within 6-02.5 and be full payment for all
costs of the work to furnish and install the steel casing, casing spacers,
end seal and link seal materials, splicing casings together, placement
within the end diaphragms, casing backfill and all necessary
appurtenances to install the casing as shown on the plans and
described herein.
The lump sum Contract price for “Pipe Insulation” shall be full payment
for all costs of the work to furnish and install the pipe insulation
including, but not limited to the insulation, jacketing, insulated pipe
hanger supports, and end seals as shown on the contract plans and
described herein.
The unit contract price per each “Connection to Existing Water Main __-
Inch Diameter” shall be full compensation for all work to connect new
water main to existing water main including but not limited to
excavating and backfilling as shown on the contract plans. The
measurement shall include removing existing pipe and fittings from
connection point, cleaning and disinfecting mating surfaces, all
transition couplings, pipe spools, thrust blocking, import pipe bedding
material, import trench backfill material, miscellaneous material,
equipment, and labor as set forth in Section 7-09.3(19)A except that, in
addition, valves will be paid at their appropriate unit prices bid. All
joints shall be mechanically restrained, in addition to thrust blocks and
temporary blocks, to provide restraint following activation, and shall be
incidental to the unit price. The unit price also includes abandonment,
plugging and/or removal of existing waterline as shown on the Plans.
Additionally, the contract price shall be compensation for:
Locating existing utilities, water mains, and services and
potholing in advance to
determine their horizontal and vertical locations.
Removing and disposing of pavement, curbs, gutters, sidewalks
and the like.
Trench dewatering (if needed).
Providing, placing and compacting import pipe bedding material.
Providing, placing and compacting import trench backfill material.
Performing backfill compaction testing and furnishing test reports
to the Engineer.
All costs associated with removal, haul, and disposal of native
material excavated from trench.
Furnishing, installing and removing a temporary two-inch feeder
to maintain water service to affected parties.
Rock Creek Culvert Replacement/Lincoln 7 - 27 June 3, 2021
Project Number: 13-3007.5
Replacing, protecting, restoring and maintaining existing utilities.
Hand digging as required to complete construction and protect
existing improvements and utilities.
All complete in place, fully operational and ready for use.
“Minor Change for Water Improvements,” per estimated (Est.).
To provide a common proposal for all bidders, the Contracting Agency
has estimated the amount for “Minor Change” and entered the amount
in the proposal to become a part of the total bid by the Contractor. The
actual amount shall be determined by field conditions as the work
progresses and as set forth in this section. No reliance shall be placed
on the amount estimated; the provisions of Section 1 04.6 shall not
apply to this item. Payment or credits will be determined in accordance
with Section 1 09.4.
7-12 VALVES FOR WATER MAINS
SECTION 7-12.2 IS REVISED BY SUPPLEMENTING IT WITH THE FOLLOWING:
7-12.2 Materials
Gate valves and combination air valve for watermains will comply with
CWD Standards and Specifications section 4.12, 5.29, 4.18 and 5.30.
When Discrepancies between plans and specifications are present, the
2016 CWD Standards and Specifications shall prevail.
SECTION 7-12.3 PARAGRAPH ONE IS SUPPLEMENTED BY ADDING THE
FOLLOWING:
7-12.3 Construction Requirements
Valves shall be inspected for approved part numbers/manufacturers;
cleanliness of valve ports especially seating surfaces, handling damage
and cracks. Defective valves shall be rejected.
A valve box or vault shall be provided for every valve.
SECTION 7-12.3 THE LAST TWO SENTENCES OF PARAGRAPH TWO ARE
DELTED AND REPLACED WITH THE FOLLOWING:
Backfill around valves shall be carefully compacted in 6-inch lifts for the
full depth of the trench with the valve box in place. Valve box top
sections shall be adjusted flush with the finished pavement, finished
grade of landscaping and, in those areas to be excavated for future
roadway grades, enough adjustment shall be provided in the valve box
to allow the top of the box to be adjusted to the required grade. Provide
a minimum of 3’ x 3’ x 4’ asphalt or concrete collar for valves installed
in gravel or unpaved areas as indicated in the Covington Water District
Standard Details.
Rock Creek Culvert Replacement/Lincoln 7 - 28 June 3, 2021
Project Number: 13-3007.5
SECTION 7-12.3 IS REVISED BY SUPPLEMENTING IT WITH THE FOLLOWING
NEW PARAGRAPHS:
Valves on active mains shall be accessible at all times for operation.
Separate payment will not be made for maintaining accessibility to
existing valves.
Valves 12-inch and larger shall be supported by a concrete block or
”paver” stone on a sufficiently tamped trench bottom so that the pipe
will not be required to support the weight of the valve. In no case shall
valves be used to bring misaligned pipe into alignment during
installation. Pipe and fittings shall be supported in such a manner as to
prevent stress on the valve.
Where a valve operating nut is more than 3-feet below finished grade,
a valve stem extension conforming to the Covington Water District
Standard Details must be installed.
Tapping valves shall be water tested prior to tapping the water main.
Testing the tapping assembly and valve with air prior to performing the
tap is also acceptable.
SECTION 7-12.5 IS DELETED AND REPLACED WITH THE FOLLOWING:
7-12.5 Payment
The unit contract price per each for “Gate Valve, 12-Inch” shall be full
pay for all work to furnish and install the valve complete in place on the
water main, including trenching, joining, blocking of valve, painting,
disinfecting, hydrostatic testing, valve box and accessories, crushed
rock backfill, operator extension if required, and adjustment of valve
box for temporary and permanent surfacing.
The unit contract price per each for “Adjust Existing Valve Box Top
Section and Lid to Finished Grade” constitutes complete compensation
for furnishing all labor, materials, tools, supplies, and equipment
necessary to adjust the valve box top to final finished grade as shown
on the plans and described in the specifications. This work includes but
shall not be limited to: referencing for future locates prior to overlay,
excavating, backfilling, compacting, surfacing and restoration. Any
adjustments made prior to the final finished elevation shall be
considered incidental to this bid item. Reference Kent Standard Plan
3-7.
7-14 HYDRANTS
7-14.3 Construction Requirements
SECTION 7-14.3(1) IS DELETED AND REPLACED WITH THE FOLLOWING:
7-14.3(1) Setting Hydrants
Rock Creek Culvert Replacement/Lincoln 7 - 29 June 3, 2021
Project Number: 13-3007.5
Where shown on Plans, hydrants shall be installed in accordance with
the Covington Water District Standard Details. A minimum 3-foot radius
unobstructed working area shall be provided around all hydrants.
All hydrants shall be inspected upon delivery in the field to ensure
proper working order. After
installation, fire hydrants, auxiliary gate valves, and other
appurtenances thereto shall be
subjected to a hydro static test and disinfection procedures as specified
in Section 7-09.
The portion of the hydrant above ground shall be painted with two
coats of Sherwin Williams Hi Gloss Safety Yellow Industrial Enamel.
Paint shall be applied by brush to an acceptable
appearance. Ensure paint adheres to shop coated surfaces.
All hydrants shall be set on concrete blocks as shown in the Covington
Water District Standard
Details.
All hydrants shall stand plumb and shall have their nozzles parallel with
or at right angles to the curb, subject to the Fire Marshall’s discretion.
The steamer port shall be pointed toward the street, or where directed,
toward the paved vehicle approach area.
Hydrants shall be set to the established grade, with the centerline of
the lowest nozzle at least 18-inches but no greater than 24-inches
above the surrounding ground or as directed by the District Engineer.
Traffic model hydrants shall be installed such that the breakaway flange
shall be installed not less than 4-inches, or more than 8-inches, above
finished grade.
When a dry barrel hydrant is set in soil that is pervious, drainage shall
be provided at the base of the hydrant by placing at least one (1) cubic
yard of 1 ½-inch washed rock from the bottom of the trench to at least
6-inches above the drain-port opening in the hydrant and to a distance
of 1-foot around the elbow. Where ground water rises above the drain
port or when the hydrant is located within 10 feet horizontally (or the
distance required by the applicable regulatory agency) of a sanitary
sewer main, the drain port shall be plugged and water pumped from
the hydrant where freezing may occur. Hydrants with plugged drain
holes shall be specifically identified for District personnel to mark them
and map the locations.
When a dry-barrel hydrant with an open drain port is set in clay or
other impervious soil, or at the discretion of the District’s
representative, a drainage pit 2’ x 2’ x 2’ shall be excavated around
each hydrant. The drainage pit shall be lined with a geotextile material
allowing water to exfiltrate and then filled with 1 ½-inch washed rock
around the elbow of the hydrant and to a level of 6-inches above the
drain port.
Rock Creek Culvert Replacement/Lincoln 7 - 30 June 3, 2021
Project Number: 13-3007.5
In unpaved areas, a concrete hydrant pad shall be installed, with
minimum dimensions of 5’ x 5’ x6’ or to neat edges between curb and
sidewalk. The concrete pad shall be poured at or near the ground line
around the hydrant barrel to provide adequate resistance to avoid
transmitting shock moment to the lower barrel and inlet connection in
the case of vehicle impact. The center of the hydrant shall be at the
center of the concrete pad. Prior to pouring concrete, the ground shall
be compacted according to the section of Trench Backfill and
Compaction in the Covington Water District Standards. Woven wire
mesh reinforcing (9 ga.) shall be placed and suspended 2-inches above
the bottom of the slab.
When fire hydrants are located in parking lots, hydrant guard posts
shall be installed where the hydrant is not otherwise protected by a
concrete curb (or extruded curb per Covington Water District Standard
Details) on all sides where vehicles may have access. Guard posts shall
be installed according to the minimum dimensions shown in the
Standard Details.
The Contractor shall exercise care in establishing and placing hydrants
at specified elevations to avoid adjustments during construction. No
extension kits shall be allowed for new construction. Hydrants not
installed properly will be removed and re-set to proper grades.
SECTION 7-14.3(2)A IS DELTED AND REPLACED WITH THE FOLLOWING:
7-14.3(2)A Hydrant Restraints
Hydrant laterals shall be restrained in accordance with the Covington
Water District Standard Details and paragraph 9-30.2(6).
SECTION 7-14.3(2)B IS DELTED AND REPLACED WITH THE FOLLOWING:
7-14.3(2)B Auxiliary Gate Valves and Boxes
Auxiliary gate valves and valve boxes shall be installed in accordance
with section 7-12. End connections shall be compatible with the
restraint system.
SECTION 7-14.3(4) IS SUPPLEMENTED WITH THE FOLLOWING:
7-14.3(4) Moving Existing Hydrants
Existing hydrants cannot be reused.
SECTION 7-14.3(6) IS SUPPLEMENTED WITH THE FOLLOWING:
7-14.3(6) Hydrant Extensions
Rock Creek Culvert Replacement/Lincoln 7 - 31 June 3, 2021
Project Number: 13-3007.5
Hydrant extensions are not allowed on this contract. Setting of Flange
shall provide a minimum clearance per CWD details from the top of
concrete pad.
SECTION 7-14.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-14.5 Payment
The unit contract price per each for the “Hydrant Assembly” shall be full
pay for all work to furnish and install the hydrant assembly complete
including, but not limited to trenching, ductile iron pipe, valve, hydrant,
blocking, disinfecting, hydrostatic testing, valve box and accessories,
crushed rock backfill, operator extension if required, and all
components as shown in the fire hydrant assembly standard detail.
7-17 SANITARY SEWERS
SECTION 7-17.2 IS DELETED AND REPLACED WITH THE FOLLOWING:
7-17.2 Materials
Material for Sanitary Sewer Force-main shall be as described in
Appendix A: SCWSD Rock Creek Culvert Crossing (02-2020S)
Specification - Supplemental Criteria
SECTION 7-17.3 IS DELETED AND REPLACED WITH THE FOLLOWING:
7-17.3 Construction Requirements
Sanitary Sewer Force-main shall be installed using the construction
requirements for Water Mains described under Section 7-09.3, as
amended by Appendix A: SCWSD Rock Creek Culvert Crossing (02-
2020S) Specification - Supplemental Criteria
SECTION 7-17.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
7-17.5 Payment
The contract bid prices of the following bid items shall be in
conformance of the pay descriptions given in Appendix A: SCWSD Rock
Creek Culvert Crossing (02-2020S) Specification - Supplemental
Criteria:
“Abandon Existing Sanitary Sewer Force Main”
“6-Inch Sewer Force Main, C900”
“16-Inch Steel Casing”
“Connection to Existing Sewer Force Main”
“Trench Shoring Systems in Compliance with WISHA”
Rock Creek Culvert Replacement/Lincoln 8 - 1 June 3, 2021
Project Number: 13-3007.5
DIVISION 8 – MISCELLANEOUS CONSTRUCTION
8-01 EROSION CONTROL AND WATER POLLUTION CONTROL
SECTION 8-01.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-01.1 Description
This work consists of temporary erosion and sedimentation control
procedures (TESCP) as shown on the construction plans, specified in
these Kent Special Provisions, and ordered by the Engineer as work
proceeds. The TESCP are intended to minimize erosion and
sedimentation as well as protect waters of the state and the city’s
municipal separate storm sewer system (MS4) as required by law.
SECTION 8-01.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-01.2 Materials
Materials shall meet the requirements of the following sections of the
Kent Special Provisions and the WSDOT Standard Specifications:
Seed .................................... 9-14.3
Fertilizer ............................... 9-14.4
Mulch and Amendments .......... 9-14.5
Tackifier ............................... 9-14.5(7)
8-01.3 Construction Requirements
SECTION 8-01.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-01.3(1) General
Preventing and controlling pollution, erosion, runoff, and related
damage requires the Contractor to install temporary stormwater best
management practices (BMPs) as per the plans and as directed by the
City.
As site conditions dictate, additional BMPs may be required. The
Contractor shall anticipate the need for additional best management
practices and propose necessary changes to the City.
Should the Contractor fail to install the required temporary erosion and
sediment control (TESC) measures or to perform maintenance in a
timely manner, or fail to take immediate action to install additional
approved measures, all fines, cost of cleanup, costs for delays and
down time shall be borne by the Contractor.
All cost for this work shall be paid for under the unit contract bid prices.
The upgrading of the TESCP facilities shall not constitute a basis for
additional working days for this project.
The Contractor shall provide the Engineer a minimum of two working
days notice prior to clearing adjacent to any wetland, creek or other
Rock Creek Culvert Replacement/Lincoln 8 - 2 June 3, 2021
Project Number: 13-3007.5
sensitive area. During the construction period, no disturbance beyond
the flagged clearing limits shall be permitted. The flagging shall be
maintained by the Contractor for the duration of construction.
The TESC facilities shall be in accordance with and conform to the Kent
Surface Water Design Manual, the WSDOT Standards Specifications,
and the Ecology Construction Stormwater General Permit (if applicable),
except as modified by the Kent Design and Construction Standards or
these Kent Special Provisions.
It shall be the responsibility of the Contractor to notify the City at once
of any TESC deficiencies or changes in conditions such as rutting and or
erosion that may occur during construction. The Contractor may
recommend possible solutions to the Engineer in order to resolve any
problems that are occurring.
The requirements of this section shall apply to all areas of the site
subject to construction activity as described in the WSDOT Standard
Specifications, the Kent Special Provisions and contract plans, including
Contractor construction support facilities, Contractor personnel parking
areas, equipment and material storage/laydown areas, and other areas
utilized by the Contractor for completion of the work. Nothing in this
section shall relieve the Contractor from complying with other contract
requirements.
SECTION 8-01.3(1)A IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-01.3(1)A Submittals
Prior to the start of any construction activities, the Contractor shall
submit for the Engineer’s review and approval, the following, as
necessitated by the work:
1. Dewatering Plan
2. Spill Prevention Control and Countermeasures Plan
3. Stream Bypass Plan for in-water work
4. Name and contact info for Contractor’s CESCL
SECTION 8-01.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTIONS:
8-01.3(1)F Applicable Regulations and Criteria
All construction activities are subject to applicable federal, state, and
local permits. The Contractor shall comply with requirements of
applicable state and local regulatory requirements, including, but not
limited to the following:
1. WAC 173-201A Water Quality Standards for Surface Waters of the
State of Washington
2. RCW 90.48.080 Discharge of pollutants in waters prohibited
3. City of Kent 2017 Surface Water Design Manual
Rock Creek Culvert Replacement/Lincoln 8 - 3 June 3, 2021
Project Number: 13-3007.5
4. Construction Stormwater General Permit – WA Department of
Ecology
8-01.3(1)G Water Quality Monitoring
Sampling of site stormwater discharges is only required if the project is
covered under the WA Department of Ecology Construction Stormwater
General Permit or if there is a suspected discharge that exceeds state
water quality standards.
If the project is covered under the Construction Stormwater General
Permit, then the Contractor shall conduct sampling as per the
conditions listed in the permit.
Any results that are outside the appropriate range of compliance will
require immediate implementation of adaptive management as outlined
in applicable permits, stormwater pollution prevention plan, and as
directed by the Engineer.
All sampling records shall be submitted to the Engineer by the last day
of the monitoring period. All necessary adaptive management
requirements shall be the responsibility of the Contractor to implement
and maintain.
All costs for this work shall be included in the various unit contract bid
prices.
SECTION 8-01.3(2)E IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-01.3(2)E Tackifiers
Unless specified otherwise, wood cellulose fiber mulch per Section
9-14(5)10 of the Standard Specifications shall have tackifier
incorporated into the mulch fiber during manufacture. If additional
tackifier is required, the tackifier shall be organic tackifier as specified
in Section 9-14.5(7)A of the WSDOT Standard Specifications. When
specified, tackifiers shall be applied in accordance with the
manufacturer's recommendations.
8-01.3(9) Sediment Control Barriers
SECTION 8-01.3(9)D IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-01.3(9)D Inlet Protection
Cleaning and maintenance of inlet protection shall not flush sediment,
or sediment-laden water into the downstream system.
SECTION 8-01.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
8-01.3(17) Vehicle Maintenance and Storage
Rock Creek Culvert Replacement/Lincoln 8 - 4 June 3, 2021
Project Number: 13-3007.5
Handling and storage of fuel, oil and chemicals shall not take place
within 50 feet of waterways. Storage shall be in dike tanks and barrels
with drip pans provided under the dispensing area. Shut-off and lock
valves shall be provided on hoses. Fuel, oil, and chemicals shall be
dispensed only during daylight hours unless approved by the engineer.
Fencing shall be provided around storage area. Locks shall be provided
on all valves, pumps, and tanks. Materials used to clean up fuel, oil,
and chemical spills shall be disposed of as directed by the engineer.
Water used for washing vehicles and equipment shall not be allowed to
enter storm drains or other State waters. No processed waste water(s)
of any kind shall be discharged onto the ground, to surface waters, or
to stormwater conveyance systems.
SECTION 8-01.5(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-01.5(2) Item Bids
The unit contract price per acre for “Seeding, Fertilizing, and Mulching”
shall be full pay for all labor, materials tools and equipment necessary
to complete the above said hydroseeding, seeding, fertilizing and
mulching at the locations shown on the plans, including the following
areas:
1. All planter areas or areas disturbed by the Contractor's operations
behind the sidewalk, even where it is only a narrow strip.
2. All biofiltration swales.
3. Detention pond site.
4. Other areas as directed by the Engineer.
Water, fertilizer and mulch shall be provided by the Contractor as
necessary to maintain and establish the seeded areas and is considered
incidental to this bid item. Topsoil Type B is considered incidental to this
bid item unless a specific bid item is listed in the proposal. The cost of
baffling or blocking over spray as required to prevent over spray onto
the sidewalk, curbing and non-planter areas is incidental to the unit
price.
The unit bid price per square yard for “Biodegradable Erosion Control
Blanket” constitutes complete compensation for all labor, tools,
materials, supplies and equipment necessary to construct and install
the biodegradable erosion control blanket as shown on the plans,
including fabric and stakes. This bid item also includes: maintenance
throughout the project; and removal and disposal of the blanket and
accumulated sediment as directed by the Engineer.
“High Visibility Filter Fabric Fence”
“Filter Fabric Fence”
The unit bid price per lineal foot for the above items constitutes
complete compensation for all labor, tools, materials, supplies and
equipment necessary to construct and install the fence as shown on the
plans, including fabric, posts and gravel to anchor fabric. This bid item
also includes: maintenance throughout the project; and removal and
Rock Creek Culvert Replacement/Lincoln 8 - 5 June 3, 2021
Project Number: 13-3007.5
disposal of the fence and accumulated sediment as directed by the
Engineer.
The unit bid price per lineal foot for “High Visibility Fence” constitutes
complete compensation for all labor, tools, materials, supplies and
equipment necessary to construct and install the fence as shown on the
plans, including fabric, posts and gravel to anchor fabric. This bid item
also includes: maintenance throughout the project; and removal and
disposal of the fence and accumulated sediment as directed by the
Engineer.
The unit contract price per hour for “ESC Lead” shall be full pay for all
duties outlined in Section 8-01.3(1)B (Erosion and Sediment Control
(ESC) Lead) in per hour increments.
8-02 ROADSIDE RESTORATION
SECTION 8-02.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.1 Description
Drawings and Specifications:
Definitions: The word “provide” means “furnish and install” (for
landscaping only).
Dimensions and Measurements: Dimensions govern when shown. Scale
is approximate. Contractor shall check all dimensions in the field and
verify them with respect to adjacent or incorporated work. Any
discrepancies in the drawings shall be brought to the immediate
attention of the Engineer before work proceeds further.
Number of Specified Items Required: Wherever in these Kent Special
Provisions an article, device or piece of equipment is referred to in the
singular number, such reference shall include as many such items as
are shown on drawings or required to complete the installation.
SECTION 8-02.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
8-02.1(1) Submittals
The Contractor shall submit within 20 days after Notice to Proceed date
a list of all plant material indicating source of supply, order invoice, size
and quantity for such species or variety.
All plant materials shall meet requirements of State and Federal laws
with respect to inspection for plant diseases and infestations. Inspection
certificates required by law shall accompany each shipment of plant
material and submitted to the Engineer.
SECTION 8-02.2 IS DELETED AND REPLACED WITH THE FOLLOWING:
Rock Creek Culvert Replacement/Lincoln 8 - 6 June 3, 2021
Project Number: 13-3007.5
8-02.2 Materials
Materials shall meet the requirements of the following sections:
Topsoil Type A, Type B, and Type C ............. 9-14.2(1), (2), (3)
Seed ....................................................... 9-14.3
Fertilizer .................................................. 9-14.4
Mulch and Amendments ............................. 9-14.5
Wood Cellulose Fiber ................................. 9-14.5(10)
Erosion Control Devices ............................. 9-14.6
Plant Materials .......................................... 9-14.7
Street Trees ............................................. 9-14.7(1)A
Stakes, Guys and Wrapping ....................... 9-14.8
Tree Ties ................................................. 9-14.8(1)
Water for Plants........................................ 9-25.2
Botanical identification and nomenclature of plant materials shall be
based on descriptions by Bailey in “Hortus Third” or superseding
editions and amendments.
8-02.3 Construction Requirements
SECTION 8-02.3(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(1) Responsibility During Construction
The Contractor shall at all times keep the planted areas free from
accumulations of waste materials or rubbish. Upon completion of the
planting work, the Contractor shall immediately remove all refuse and
debris resulting from the planting activities. The project will not receive
either preliminary or final approval if the cleanup does not meet with
the approval of the Engineer.
SECTION 8-02.3(3) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(3) Weed and Pest Control
During the maintenance period, all weeds are to be removed by hand.
SECTION 8-02.3(5)A IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(5)A Seeding Area Preparation
The Contractor shall excavate planting pits to a depth of three feet
below the top of adjacent sidewalks, or adjacent ground if trees are not
being planted in sidewalk cutouts. Tree pits shall be about three feet in
diameter, and shall be neat and uniform basins around each tree. The
Contractor shall then place special planting mixture into the tree basins,
bringing to grade about one and one-half foot below the top of the
planter by compaction by repeated watering.
Refer to Section 8-02.3(4) of the WSDOT Standard Specifications.
Rock Creek Culvert Replacement/Lincoln 8 - 7 June 3, 2021
Project Number: 13-3007.5
SECTION 8-02.3(7) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(7) Layout of Planting, Lawn and Seeding Areas
The location of plantings shall be according to the landscaping details,
unless otherwise directed by the Engineer. The Contractor shall layout
tree, shrub and herbaceous plant locations and receive the approval of
the Engineer before planting begins.
SECTION 8-02.3(8) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(8) Planting
All plants shall be carefully placed in excavated holes to prevent
damage to fibrous root systems during placement and backfilling
operations, with burlap or container removed. Plants shall be set
vertically in the center of the pits, backfilled with native soil, watered
and settled so that the crown of the root ball will have the same
relation to finished grade as it bore to the grade of the ground from
which it was dug. All street trees shall be planted in general
conformance to Kent Standard Plan 6-55.
SECTION 8-02.3(8)C IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(8)C Pruning, Staking, Guying, and Wrapping
Pruning shall be limited to the minimum amount necessary to remove
injured twigs and branches. Only cut injured limbs to the nearest lateral
bud. Do not apply tree wound paint or petroleum product to tree cuts.
The Contractor shall use rootball bracing (triangle method) rather than
staking or guying to support new trees.
8-02.3(9) Seeding, Fertilizing and Mulching
SECTION 8-02.3(9)A IS REVISED BY DELETING THE FIRST THREE
PARAGRAPHS AND REPLACING WITH THE FOLLOWING:
8-02.3(9)A Dates for Application of Seed
Unless otherwise approved by the Engineer, the final application of
seeding, fertilizing, and mulching of slopes shall be performed during
the following periods:
West of the summit of the Cascade Range - March 1 to May 15 and
August 15 to October 1. Where contract timing is appropriate, seeding,
fertilizing, and mulching shall be accomplished during the spring period
listed above. Written permission to seed after October 1 will only be
given when physical completion of the project is imminent and the
environmental conditions are conducive to satisfactory growth.
SECTION 8-02.3(9)B IS DELETED AND REPLACED WITH THE FOLLOWING:
Rock Creek Culvert Replacement/Lincoln 8 - 8 June 3, 2021
Project Number: 13-3007.5
8-02.3(9)B Seeding and Fertilizing
Topsoil and all other unpaved and unsodded areas within easements and
right-of-way disturbed as part of this project shall be seeded. Hydroseeding
shall be the method of seed application. Hydroseed shall consist of a slurry
composed of water, seed, fertilizer, tackifier, and mulch and shall be evenly
broadcast over areas to be seeded. All work shall conform in all respects to
Section 8-01 of the WSDOT Standard Specifications, except as modified
herein.
The Contractor shall notify the Engineer not less than 48 hours in
advance of any hydroseeding operation and shall not begin the work
until areas prepared or designated for hydroseeding have been
approved. Following the Engineer's approval, hydroseeding of the
approved slopes shall begin immediately.
Hydroseeding shall not be done during windy weather or when the
ground is frozen, excessively wet, or otherwise untillable.
Hydroseed mixture to be applied by an approved hydro seeder which
utilizes water as the carrying agent, and maintains continuous agitation
through paddle blades. It shall have an operating capacity sufficient to
agitate, suspend, and mix into a homogeneous slurry the specified
amount of seed and water or other material. Distribution and discharge
lines shall be large enough to prevent stoppage and shall be equipped
with a set of hydraulic discharge spray nozzles that will provide a
uniform distribution of the slurry.
The seed and fertilizer cannot be placed in the tank more than 30
minutes prior to application. The seed and fertilizer shall have a tracer
added to visibly aid uniform application. This tracer shall not be harmful
to plant and animal life. If wood cellulose fiber is used as a tracer, the
application rate shall not exceed 25 pounds per acre.
Areas where hydroseeding is not practical, must be seeded by approved
hand methods as approved by the engineer. When seeding by hand,
Contractor shall incorporate seed into the top 1/4 inch of soil.
The hydroseed slurry shall consist of the following materials mixed
thoroughly together and applied in the quantities indicated.
1. Grass Seed: Mixture shall be fresh, clean, new crop seed. Seed to
be mixed mechanically on the site or may be mixed by the dealer.
If seed is mixed on site, each variety shall be delivered in the
original containers bearing the dealer’s guaranteed analysis. If
seed is mixed by the dealer, the Contractor shall furnish to the
Engineer the Dealer’s guaranteed statement of the composition of
the mixture and the percentage of purity and germination of each
variety.
Grass seed shall be purchased from a recognized distributor and
shall be composed of the varieties mixed in the proportions
indicated in the WSDOT Standard Specifications and Kent Special
Rock Creek Culvert Replacement/Lincoln 8 - 9 June 3, 2021
Project Number: 13-3007.5
Provisions. Seed shall meet the minimum percentages of purity
and germination specified in Section 9-14.3 of the Kent Special
Provisions. Seed shall be applied at the rate of 120 pounds per
acre.
The Contractor shall protect seed from hydration, contamination,
and heating during delivery, storage, and handling. Seed shall be
stored in a cool dry location away from contaminants.
Mix A shall be used as the standard hydroseed mix unless
otherwise specified herein or on approved project plans.
Mix B shall be used exclusively for seeded areas adjacent to grass
lawns, within seeded medians, and within seeded traffic islands. In
addition, Mix B shall be used for all seeded areas not specifically
showing Mix A on the plans, or where otherwise directed by the
Engineer.
2. Water: The Contractor shall begin maintenance immediately after
seeding for a minimum of ten (10) weeks or longer as needed.
Water seeded areas before hydroseed slurry has completely dried
out. Water slowly and thoroughly with fine spray nozzle. Water the
hydroseeded areas at least twice daily (in the early morning and
late afternoon) until the grass is well established as determined by
the Engineer. Repeat watering operation as required by climatic
conditions to keep areas moist for a minimum period of 2 weeks
from the day of first watering and as necessary for healthy growth.
3. Mulch: As needed to meet requirements of Sections 8-01.3(11)A
and 9-14.5.
4. Fertilizer: All areas which are seeded shall receive fertilizer of the
following proportions and formulation applied at the rate of 400
pounds per acre. All areas which are seeded shall receive fertilizer
meeting the requirements of Section 9-14.4 of the Kent Special
Provisions.
Fertilizer shall not be applied on any creek sideslopes in order to
avoid contamination of these creeks.
5. Hand Seeding: Seeding shall be applied at the rate of 6 pounds per
1,000 square feet. The seed shall be applied by an approved hand
held spreader. The seed shall be evenly distributed over the
disturbed area. Apply seed mix after fertilizing and rake the seed
into the surface soil to a depth of 1/4-inch.
6. If the slurry is used for temporary erosion control it shall be applied
at the following rates:
EROSION CONTROL:
Seed 170 lbs/acre of “Mix A” unless otherwise directed
by Engineer.
Fertilizer 400 lbs/acre
Rock Creek Culvert Replacement/Lincoln 8 - 10 June 3, 2021
Project Number: 13-3007.5
Wood Fiber 2,000 lbs/ acre
Tackifier 80 lbs/acre
SECTION 8-02.3(9)D IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(9)D Inspection
Inspection of seeded areas shall be made upon completion of seeding
operations, at the end of the maintenance period, and at any time
during the maintenance period. The Contractor shall reseed, re-mulch
or re-fertilize as required to establish a uniform, thick stand of grass. A
uniform stand of grass shall be defined as any grass area with no spots
greater than one square foot.
Areas failing to show a uniform thick, healthy stand of grass after the
maintenance period shall be reseeded consistent with the Kent Special
Provisions at the Contractor's expense. Reseeded areas will be subject
to inspection for acceptance.
SECTION 8-02.3(9)E IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(9)E Protection and Care of Seeded Areas
Protect adjacent property, public walks, curbs and pavement from
damage. Do not place soil directly on paved surfaces. Locate all
underground utilities prior to the commencement of work. Keep streets
and area drains open and free flowing. Protect all seeding against wind,
storm, and trespassing. Replace any plants that become damaged or
injured. In seeded areas, treat and reseed damaged spots larger than
one square foot.
SECTION 8-02.3(11)A IS DELETED AND REPLACED WITH THE FOLLOWING:
8-02.3(11)A Mulch for Seeding Areas
Wood cellulose fiber mulch conforming to Section 9-14.5(10) of the
Standard Specifications shall be used where mulch is called for on this
project. The application rate shall be 2,000 pounds to the acre in
accordance with Section 8-01 of the WSDOT Standard Specifications.
Mulch shall be incorporated into the slurry of seed and fertilizer.
Mulch of the type specified in Section 9-14.5 shall be included in the
hydroseeding process. Wood cellulose fiber used as a mulch shall be
suitable for application with hydroseeders as specified in Section
8-01.3(9)B. The application of seed, fertilizer, and mulch shall be
required in a single operation for all seed applications, unless otherwise
directed. Mulch materials, shall be furnished, hauled, and evenly
applied at the rates indicated, and shall be spread on seeded areas
immediately after seeding unless otherwise specified.
Distribution of straw mulch material shall be by means of an approved
type mulch spreader, which utilizes forced air to blow mulch material on
seeded areas. In spreading straw mulch, the spreader shall not cut or
Rock Creek Culvert Replacement/Lincoln 8 - 11 June 3, 2021
Project Number: 13-3007.5
break the straw into short stalks. Straw mulch shall be applied at a rate
to achieve a loose, overall thickness of three (3) inches.
Areas not accessible by mulching equipment shall be mulched by
approved hand methods and shall achieve similar results.
Mulch sprayed on signs or sign structures shall be removed the same
day.
SECTION 8-02.3(11)B IS REVISED AS FOLLOWS:
8-02.3(11)B Bark or Woodchip Mulch
Revise all references in this section from bark or wood chip mulch to
“wood chip mulch.”
Add “A sample of the wood chip mulch shall be provided to the Engineer
or project Ecologist in a 1-gallon re-closable bag at least seven (7) days
prior to application.”
Bark mulch or wood chip mulch shall be placed to a uniform non-
compacted depth 3 inches over all planting areas. Bark or wood chip
mulch shall not be placed in areas of standing or flowing water.
SECTION 8-02.3(13) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(13) Plant Establishment
The Contractor is responsible for maintaining all trees and shrubs in a
clean and thriving condition for a period of not less than two calendar
years. The period of maintenance shall begin upon final installation and
inspection of work, and subsequent written notification by the Engineer.
Maintenance shall include all necessary cleaning, weeding, pruning,
watering, and one supplemental feeding with approved fertilizer.
The Contractor shall water all trees and shrubs a minimum of once per
week during the months of June through September to establish the
vegetation during the dry summer months. Maintenance of this
watering schedule is critical to the survival of the trees and shrubs.
SECTION 8-02.3(14) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.3(14) Plant Replacement
The Contractor shall replace all trees and shrubs which, in the opinion
of the City Nursery Supervisor, have failed to establish themselves
during the maintenance period at its sole expense. All replacement
planting shall be conducted in conformance to these specifications.
SECTION 8-02.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
8-02.3(17) Plant and Site Protection During Entire Construction Period
Rock Creek Culvert Replacement/Lincoln 8 - 12 June 3, 2021
Project Number: 13-3007.5
The Contractor shall:
1. Protect existing trees to remain and new plants against injury and
damage, including but not limited to: cutting, breaking, or
skinning of roots, trunk or branches, or smothering by stockpiling
construction material, or compaction by equipment.
2. Keep all heavy equipment (e.g., backhoe) outside of the drip lines
of all existing trees, so as not to damage the root systems.
3. Notify Engineer immediately if a conflict arises between
construction activity and the protection of trees and shrubs; alter
methods as necessary and as approved by the Engineer.
SECTION 8-02.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-02.5 Payment
The unit contract price per cubic yard for “Topsoil Type A” constitutes
complete compensation for all labor, materials, tools and equipment
necessary to supply and spread the topsoil in the areas shown on the
plans, or where directed by the Engineer. This item includes but is not
limited to the labor required for raking and compacting the topsoil,
cleanup and complete preparation ready for seeding.
The unit contract price per cubic yard for “Wood Chip Mulch” constitutes
complete compensation for all labor, materials, tools and equipment
necessary to supply and spread the wood chip mulch in the areas
shown on the plans, or where directed by the Engineer. This item
includes but is not limited to the labor required for raking the wood chip
mulch and cleanup.
8-10 GUIDE POSTS
SECTION 8-10.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-10.1 Description
This Work shall consist of furnishing and placing flexible guardrail
reflectors to all the guardrail posts, at the locations indicated in the
Plans or where designated by the Engineer.
SECTION 8-10.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-10.2 Materials
Flexible guardrail reflectors shall be post mounted onto guardrail posts,
and shall be Pexco Hinged guardrail reflectors, or approved equal.
SECTION 8-10.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-10.3 Construction Requirements
Rock Creek Culvert Replacement/Lincoln 8 - 13 June 3, 2021
Project Number: 13-3007.5
Flexible guardrail reflectors shall be installed according to the
manufacturer’s recommendations.
The Contractor shall submit a Type 1 Working Drawing consisting of the
manufacturer’s
recommended installation procedures.
SECTION 8-10.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-10.4 Measurement
Flexible guardrail reflectors will be measured by the unit for each post
furnished and installed.
SECTION 8-10.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-10.5 Payment
“Flexible Guardrail Reflectors,” per each.
8-11 GUARDRAIL
SECTION 8-11.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-11.2 Materials
Guardrail shall consist with metal posts and composite blocks.
Guardrail shall include post mounted flexible guardrail reflectors per
Section 8-10.
8-15 RIPRAP
SECTION 8-15.1 THE SECOND PARAGRAPH IS DELETED AND REPLACED WITH
THE FOLLOWING:
8-15.1 Description
Riprap will be classified as Rock for Erosion and Scour Protection, Class
B.
SECTION 8-15.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-15.2 Materials
Materials shall meet the requirements of the following section:
Rock for Erosion and Scour Protection, Class B 9-13.4(2)
SECTION 8-15.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-15.3 Construction Requirements
Rock Creek Culvert Replacement/Lincoln 8 - 14 June 3, 2021
Project Number: 13-3007.5
Riprap
Rock for Erosion and Scour Protection shall be placed in such a manner
that all relatively large stones shall be essentially in contact with each
other. All voids in the Rock for Erosion and Scour Protection shall be
filled with Streambed Gravel to provide a well graded compact mass.
Rock for Erosion and Scour Protection shall be dumped in a manner that
will ensure the rock attains its specified thickness in one operation.
When dumping or placing, care shall be used to avoid disturbing the
underlying material. Placing in layers parallel to the slope will not be
permitted. A 12-inch tolerance for Rock for Erosion and Scour
Protection will be allowed from slope plan and grade line in finished
surface.
Backhoes and excavators may be used to place Rock for Erosion and
Scour Protection provided that their bucket volume can place a full
layer thickness of well graded riprap with each bucket pass. Dump
trucks, bulldozers, and loaders shall not be used for the placement of
Rock for Erosion and Scour Protection.
Rock for Erosion and Scour Protection shall be placed in a systematic
manner to produce a well graded rock mass with a minimum amount of
void space and shall follow these Specifications:
1) Rock for Erosion and Scour Protection shall be placed to its full
course thickness in one operation and in such a manner as to
minimize segregation of rock sizes and avoid displacing underlying
material.
2) Rock for Erosion and Scour Protection shall not be dumped into
chutes allowing it to roll downhill, pushed into place, or by any
similar methods that would cause segregation of the various sizes.
3) Work loose pieces or pieces out of tolerance to interlock and
stabilize them within the rock layer.
4) Buckets or other equipment shall not be used to hammer or
otherwise attempt to smooth the rock surface.
5) The finished surface shall be free of pockets of small rocks and
clusters of large rocks.
6) Operation of equipment directly on the completed stone protection
system is not permitted.
SECTION 8-15.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-15.4 Measurement
Rock for Erosion and Scour Protection, Class B will be measured by the
ton of rock actually placed.
SECTION 8-15.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
Rock Creek Culvert Replacement/Lincoln 8 - 15 June 3, 2021
Project Number: 13-3007.5
8-15.5 Payment
Payment will be made for each of the following bid items that are
included in the proposal:
The contract unit price per ton of “Rock for Erosion and Scour
Protection, Class B” shall be full compensation for all labor, materials,
and equipment necessary to complete the work as specified, including
furnishing, and any necessary grading required to place material, to the
satisfaction of the engineer.
SECTION 8-19 IS DELETED AND REPLACED WITH THE FOLLOWING:
8-19 STREAMBED GRAVEL
8-19.1 Description
This work shall consist of furnishing, mixing, and placing streambed
gravel to the lines, dimensions, and grades designated in the Plans or
established by the Engineer. Aggregates for streambed gravel will
include streambed sediment, and streambed cobbles.
8-19.2 Materials
Materials shall meet the requirements of the following sections:
Streambed Sediment .................... 9-03.11(1)
Streambed Cobbles ___ In. ............. 9-03.11(2)
8-19.3 Construction Requirements
Streambed Gravel
The streambed gravel placed throughout the stream channel shall
consist of a blend of Streambed Sediment and Streambed Cobbles in
the ratio as specified in the Plans.
The streambed aggregate shall be placed to the limits shown in the
Plans. The Contractor shall ensure that stratification of material sizes
does not occur and that the resulting placed material is uniformly
distributed within the streambed aggregate matrix. After placement,
the streambed gravel shall be shaped to form the low flow channel, side
slopes, and benches to the dimensions specified in the plans.
8-19.4 Measurement
Streambed Gravel will be measured by the of rock actually placed.
8-19.5 Payment
Payment will be made in accordance with Section 1-04.1, for the
following Bid items:
Rock Creek Culvert Replacement/Lincoln 8 - 16 June 3, 2021
Project Number: 13-3007.5
The unit Contract price for “Streambed Gravel” per ton, shall be full
payment for all labor, material, tools and equipment necessary to
procure, haul, and construct the streambed aggregate as shown in the
Plans and as designated by the Engineer.
8-20 ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, INTELLIGENT
TRANSPORTATION SYSTEMS, AND ELECTRICAL
SECTION 8-22.1 IS REVISED BY ADDING THE FOLLOWING:
8-22.1 Description
This work also includes the furnishing and installation conduit and the
furnishing of a utility vault as directed by the Engineer in consultation
with representatives of CenturyLink.
SECTION 8-22.2 IS REVISED BY ADDING THE FOLLOWING:
8-22.2 Materials
Conduit
Conduit shall be Schedule 40 conduit meeting the requirements of
section 9-29.1(5)B of the Standard Specifications as approved by the
Engineer and CenturyLink.
Utility Vault
Utility Vault shall be an Oldcastle Precast TA-25 or approved equal.
SECTION 8-22.3 IS REVISED BY ADDING THE FOLLOWING:
8-20.3(5)D Conduit Placement
Conduit shall be installed in locations as directed by Engineer in
consultation with CenturyLink.
Conduit shall be connected to utility vaults as directed by Engineer in
consultation with CenturyLink.
SECTION 8-22.4 IS REVISED BY ADDING THE FOLLOWING:
8-20.4 Measurement
“Furnish and Install 4-Inch Diameter Schedule 40 Conduit”, per Linear
Foot
“Furnish 25-TA Vault”, per each
SECTION 8-22.4 IS REVISED BY ADDING THE FOLLOWING:
8-20.5 Payment
Rock Creek Culvert Replacement/Lincoln 8 - 17 June 3, 2021
Project Number: 13-3007.5
The unit Contract price per linear foot for “Furnish and Install 4-Inch
Diameter Schedule 40 Conduit”, shall be full pay for furnishing all pipe,
pipe connections, elbows, bends, caps, reducers, conduits, unions, and
fittings; for placing the pipe in accordance with the above provisions,
including all excavation, jacking, or drilling required, backfilling of any
voids around casing, conduits, pits, or trenches; restoration of native
vegetation disturbed by the operation, chipping of pavement, and
bedding of the pipe; connecting the conduits to utility vaults; and all
other Work necessary for the construction of the conduit.
The unit Contract price per each for “Furnish 25-TA Vault”, shall be full
pay for furnishing the utility vault and delivering it to site for installation
by CenturyLink as directed by the Engineer in consultation with
CenturyLink.
8-22 PAVEMENT MARKING
SECTION 8-22.1 IS REVISED AS FOLLOWS:
8-22.1 Description
THE TEXT UNDER CROSSWALK STRIPE IS REPLACED WITH THE FOLLOWING:
A series of pairs of parallel SOLID WHITE lines, 8-feet long, 8 inches
wide, aligned parallel with the direction of traffic, with an 8 inch space
between the lines. Pairs are located as shown in Kent Standard Plan
6-75.
THE TEXT UNDER TWO WAY LEFT TURN STRIPE IS REPLACED WITH THE
FOLLOWING:
A SOLID YELLOW line, 4 inches wide, with a BROKEN YELLOW line, 4
inches wide, separated by a 4 inch space. The broken or “skip” pattern
shall be based upon the City’s 12-foot line and a 30-foot space, except
where the existing paint markings use a different pattern in which case
the existing pattern will be used. The solid line shall be installed to the
right of the broken line in the direction of travel.
THE FOLLOWING NEW PAVEMENT MARKING IS ADDED:
Yellow Painted Curb
A SOLID YELLOW stripe, just wide enough to completely cover the
concrete curbing.
SECTION 8.22.2 IS DELETED AND REPLACED WITH THE FOLLOWING:
8-22.2 Materials
Material for pavement and curb markings shall be white or yellow paint
as noted in the Proposal and Bid Item Descriptions. All paint, including
the paint for the concrete curbs, shall be described in the Qualified
Products List as “Temporary Pavement Marking Paint – Low VOC
Rock Creek Culvert Replacement/Lincoln 8 - 18 June 3, 2021
Project Number: 13-3007.5
Solvent Based.” Paint and sprayed material shall be applied with a top
dressing of glass beads.
All Paint shall comply with the specifications for no heat, instant dry
pavement markings.
Glass beads shall be AC-110 Highway Street Spheres, or pre-approved
equal.
Material for pavement markings shall be paint, plastic or Raised
Pavement Markings (RPMs) as noted in the bid item. Paint and plastic
shall be selected from materials listed in the Qualified Products list
(QPL). Material for RPMs shall meet the requirements for Section
8-09.2.
Plastic pavement marking shall be Type D (MMA) material per Section
9-34.3(4).
8-22.3 Construction Requirements
SECTION 8-22.3(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING
PARAGRAPH TO THE END OF THIS SECTION:
8-22.3(2) Preparation of Roadway Surfaces
The preparation of roadway surfaces related to the installation of RPMs
shall meet the requirements of Section 8-09.3(1).
SECTION 8-22.3(3) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-22.3(3) Marking Application
The Contractor is responsible for providing traffic control and traffic
control devices as necessary to direct vehicular traffic away from
freshly painted traffic stripes until such time as the marking paint has
completely dried. Failure to ensure reasonable protection for the
undried paint stripes will result in the Engineer’s decision to adjust the
method of payment for damaged paint stripes. The Engineer’s decision
regarding the means of payment adjustment for vehicle damaged paint
stripes is final in this matter.
Type 2 markers may be warmed prior to setting by heating to a
maximum temperature of 120 F for a maximum of 10 minutes.
The second coat of yellow paint applied to concrete curbs shall have
glass beads applied at the rate of 12 pounds per 100 linear feet of
curbing.
SECTION 8-22.3(5) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
8-22.3(5) Installation Instructions
RPMs shall be installed per the requirements of Section 8-09.3(4).
Rock Creek Culvert Replacement/Lincoln 8 - 19 June 3, 2021
Project Number: 13-3007.5
SECTION 8-26 IS DELETED AND REPLACED WITH THE FOLLOWING:
8-26 ANCHORED LOGS AND HABITAT LOGS
8-26.1 Description
This work shall consist of furnishing, mixing, and placing streambed
gravel to the lines, dimensions, and grades designated in the Plans or
established by the Engineer. Aggregates for streambed gravel will
include streambed sediment, and streambed cobbles.
8-26.2 Materials
Logs
All logs shall consist of Western Red Cedar or Douglas Fir. The
Contractor may substitute other coniferous species if requested in
writing and approved by the Engineer. Hemlock is not acceptable. The
source of supply of logs shall be approved by the Engineer before
delivery to the site.
Logs shall be sound and free of rot, insect damage, or any preservative
such as creosote. Logs shall not be incrusted with silt and fines. The log
diameter shall be measured at 4.5 feet from the base end of the log.
Log diameters shall be as specified in the Plans.
Crunch broken ends to disguise saw cuts at the exposed end of the log.
Exposed ends of logs shall have no blunt ends.
Anchors
Anchored logs shall be anchored with three-man streambed boulders
with rock bolts installed and attached to chains tightened around the
logs.
The contractor shall submit materials for the rock bolt, chain, and the
connection of chains to the rock bolts to the Engineer for approval. The
rock bolts shall be cement-grouted rock bolt anchors, and the bolt and
cement grout shall provide a minimum working load limit of 7,500 lbs.
The rock bolts shall be steel and corrosion-resistant. Galvanized steel is
not acceptable.
The connections between the rock bolt and chain shall be eye nuts,
shackles, or other materials consisting of steel, with a minimum
working load limit of 7,500 lbs. The connecting materials shall
corrosion-resistant. Galvanized steel is not acceptable.
Chain shall be grade 43 steel chain (natural finish), with a minimum
7/16” thickness and a minimum working load limit of 7,500 lbs.
Three-man streambed boulders shall meet the requirements of Section
9-03.11(3).
Rock Creek Culvert Replacement/Lincoln 8 - 20 June 3, 2021
Project Number: 13-3007.5
8-26.3 Construction Requirements
Anchored Logs and Habitat Logs
The Contractor shall install logs as shown on the Plans. The Contractor
shall notify the Engineer at least 24 hours prior to any log installation
activities. Logs shall be approved on site by the Engineer prior to
installation. Care shall be taken to protect all logs and rootwads during
log installation. The Engineer will be present during placement of log
structures and may require the Contractor to adjust the placement to fit
the field conditions.
Backfill and compact any open trenches as required per Section 2-
09.3(1)E to return the site to the design grade.
Anchors
Cement-grouted Rock bolts shall be installed per the manufacturer's
requirements. The anchor hole shall be drilled into the boulder 1/16
inch larger in diameter than the anchor. The hole shall be cleaned of all
dust and debris. Cement grouting shall be installed in accordance with
the manufacturer’s instructions.
Logs shall be scored to remove bark where chain will be attached. Logs
shall be double-wrapped with chain and pulled tight and connected to
anchors.
8-26.4 Measurement
Anchored Logs and Habitat Logs will be measured per each for each log
installed.
8-26.5 Payment
Payment will be made in accordance with Section 1-04.1, for the
following Bid Item(s):
“Anchored Log Type B”
“Habitat Log Type __”
The unit Contract price per each for the above items shall include, but
not be limited to, furnishing materials, trenching and excavation
required to place the log structures, cutting and notching logs,
streambed boulders for dead man anchors, rock bolt anchors, cement
grout, chains, connections, and miscellaneous items and accessories
that comprise the log structures; backfill required to secure log
structures in place; and any final field adjustment of log structures as
directed in the field by the Engineer, and incidentals necessary to
satisfactorily complete the work.
SECTION 8-28 IS DELETED AND REPLACED WITH THE FOLLOWING:
8-28 POTHOLE UTILITIES
8-28.1 Description
Rock Creek Culvert Replacement/Lincoln 8 - 21 June 3, 2021
Project Number: 13-3007.5
This work shall consist of potholing utilities at the locations shown on
the plans and described in the specifications. The Contractor shall notify
the Engineer, a minimum of 24 hours before the pothole work is
performed, to coordinate the work with Survey. Each pothole shall
include standby time to allow Surveyors to accurately measure the
location and depths of existing utilities.
At the general locations as shown in the Plans, and/or at such locations
as may be directed by the Engineer, the Contractor shall excavate to
and expose a sufficient extent or portion of the utility or utilities to
confirm the horizontal location(s), depth(s), alignment(s), diameter(s),
material(s), pipe joint or fitting configuration of the utility or respective
utilities to establish the associated connection, extension and/or
clearance requirements relative to the information included in the Plans
and Contract provisions.
The Contractor shall exercise extra precautions in excavating to and
exposing the utility or utilities to protect the utility(ies) from damage
and service disruptions. Special equipment, such as vacuum
excavators, or excavation with hand tools may be necessary for this
work.
Prior to backfilling, the exposed utility or utilities shall also be reviewed
by the Engineer or the Contracting Agency Inspector. Following
documentation and review, the exposed utility or utilities shall be
carefully covered with suitable native material. Backfill for the pothole
shall be compacted to match the adjoining materials, to 95 percent of
maximum density, or as the Engineer may direct. For potholes outside
the limits of Project improvements, the surface shall be restored to
match the pre-existing condition and adjacent section. Otherwise,
temporary surfacing may be used subject to the provisions of Section 1
07.23(1).
8-28.2 Materials
Backfill and surfacing material shall match conditions of pothole
location. Pothole work located in asphalt concrete pavement, shall be
backfilled with gravel borrow and crushed rock, then patched with
asphalt cold mix. Pothole work located in cement concrete shall be
backfilled with gravel borrow, then patched with cement concrete.
Pothole work not on paved surfaces shall be backfilled with native
material.
8-28.3 Construction Requirements
The pothole shall be of sufficient size and depth to expose existing
utilities to determine potential conflicts and verify compatibility with
designs. Excavation; hauling, dewatering; backfill, compaction, surface
restoration, and cleanup are included with this work.
8-28.4 Measurement
Rock Creek Culvert Replacement/Lincoln 8 - 22 June 3, 2021
Project Number: 13-3007.5
Utility potholing will be measured per each location excavated, utility or
utilities exposed, measured documented, backfilled and surface
restored at the location(s) as shown on the Plans or as may be directed
by the Engineer. No separate measurement or payment will be made
for potholes within a five foot radius of each other.
8-28.5 Payment
Payment will be made in accordance with Section 1-04.1, for the
following bid items when they are included in the Proposal:
The contract price per each for “Utility Pothole” constitutes complete
compensation for all Work to excavate, expose, measure, and
document the existing underground utility or utilities at the locations as
shown on the Plans or as may be directed by the Engineer, and to place
and compact backfill, and restore the surface as specified.
No payment for “Utility Pothole” will be made where Contractor is to
determine water main depth, type and size at and when installing
temporary blow off assemblie(s). This will be considered incidental to
“Connection to Existing Water Main ____-Inch Diameter,” in special
provision 7-09.
DIVISION 8 IS SUPPLEMENTED WITH THE FOLLOWING NEW SECTION:
8-30 RESOLUTION OF UTILITY CONFLICTS
8-30.1 Description
This work involves the identification and resolution of utility conflicts
not identified in the plans between proposed improvements and existing
utilities. The Contracting Agency will pay these costs by force account
if the work proves to be acceptable and the Contractor has performed
the work with the authority of and due notice to the Engineer.
8-30.3 Construction Requirements
In the event that a conflict arises between the proposed improvements
and an existing utility, the Resolution of Utility Conflicts item will
compensate the Contractor for standby time and additional work in the
following manner:
1. Standby time resulting from existing utility conflicts:
Standby time is defined as time the Contractor is unable to proceed
with progression of a specific work item (i.e. storm drainage,
underground utility installation etc.) due to conflicts with existing
facilities. However, payment for standby time shall be limited to:
a. For each agreed upon conflict, a maximum of four (4) hours of
standby time will be paid for actual delay of labor and equipment
due to a utility conflict. The Contractor shall be responsible to
adjust his work schedule and/or reassign his work forces and
equipment to other areas of work to minimize standby time.
b. If the conflict is resolved within one (1) hour of notification to the
Engineer, no standby time will be paid.
Rock Creek Culvert Replacement/Lincoln 8 - 23 June 3, 2021
Project Number: 13-3007.5
2. Additional work required to resolve utility conflicts will be paid for at
the bid unit prices for the associated work. Work that can be
measured and paid for at the unit contract prices shall not be
identified as force account work. This work includes but is not limited
to:
a. Water fittings, valves, and pipe realignment of line and/or grade
for the water facilities to avoid existing utilities.
b. Additional water fittings, valves and pipe required by a change in
alignment, and/or grade, not exceeding the limits set in section 1-
04.4 of the Standard Specifications.
8-30.4 Measurement
Measurement and payment for “Resolution of Utility Conflicts” shall be
by force account per 1-09.6 of the Standard Specifications.
8-30.5 Payment
Payment will be made in accordance with Section 1-04.1 for the
following bid items when included in the proposal:
"Resolution of Utility Conflicts" will be paid by force account as
provided in Section 1- 09.6.
All costs for resolving utility conflicts will be paid for by force account in
accordance with section 1-09.6. To provide a common proposal for all
bidders, the Contracting Agency has estimated the amount for
“Resolution of Utility Conflicts” and entered the amounts in the proposal
to become a part of the total bid by the Contractor. No reliance shall be
placed on the amount estimated; the provisions of Section 1 04.6 shall
not apply to this item. Payment or credits will be determined in
accordance with Section 1 09.4. Utility conflicts due to the Contractor’s
actions or operations shall be resolved by the Contractor at no expense
to the Contracting Agency. Utility conflicts due to the Contractor’s
actions or operations shall be resolved by the Contractor at no expense
to the Contracting Agency.
DIVISION 8 IS SUPPLEMENTED WITH THE FOLLOWING NEW SECTION:
8-31 FIELD TRAILER
8-31.1 Description
This work shall consist of locating and leasing/renting a field trailer on
the project site area for City use within 600 feet of the project limits
with the same or approved equal amenities.
8-31.2 Materials
All labor, materials, tools, supplies, and equipment used for this work
shall be furnished by the Contractor.
8-31.3 Construction Requirements
Rock Creek Culvert Replacement/Lincoln 8 - 24 June 3, 2021
Project Number: 13-3007.5
The Contractor shall furnish and install a temporary field trailer for the
sole use of the City. The trailer shall be set up adjacent to the
Contractor’s site trailer or at an approved on-site location. The trailer
shall be established within the first ten (10) working days of NTP and
shall be maintained until two (2) weeks after final acceptance of the
contract. The office shall be weather tight, and be provided with the
following minimum requirements.
Floor space: 450 square feet (consisting of at least two offices of
approximately 100 square feet each - with doors, and conference
room space of at least 250 square feet). The trailer shall be a
minimum of 12 feet wide.
Above ground floor with side boards around crawl space to retain
heat
Electrical power, providing lights and heat to all rooms, energized
within 10 days of NTP
Broadband internet services depending on availability at the job
site.
The following options are listed in preferred order:
Cable Broadband Internet, download Bandwidth Minimum 75
Mbps
If this is unavailable then:
DSL or phone circuit internet, download Bandwidth Minimum
20 Mbps
If this is unavailable then:
Sierra Wireless Airlink series Gateway with Internet Service
Contract, bandwidth Minimum 4G LTE
Provide new or reconditioned copier, MFD Cannon Copier or
equivalent with monthly service contract for life of project.
Minimum features include: 2 paper trays plus by-pass handling;
paper tray sized from5-1/2” x 8-1/2” to 11” x 17”; duplex
copying; print and scan; scan to email and network share folder,
auto feed, grouping and sorting.
No desk phone or fax line required.
Adequate windows for ventilation. Windows shall include security
bars or screen
Shelves: Twenty (20) lineal feet (divided equally between the
offices)
Minimum of four (4) 30-inch x 60-inch, double pedestal desks
with office chairs (2 each per office)
One (1) plan table: 42” x 72”, at end of conference room
Four (4) conference tables: 30” x 72”, and ten (10) stacking
chairs in the conference room
Four (4) four drawer legal size filing cabinets
Cylinder door lock, and six keys
Portable toilet facilities adjacent to the trailer
Stairs with landing and safety hand rails leading to each entrance
door
Rock Creek Culvert Replacement/Lincoln 8 - 25 June 3, 2021
Project Number: 13-3007.5
Minimum, two (2) entrance doors
Rain cap/porch cover at each entrance door
A/C powered, electronic burglar alarm system with auto phone
dialer 24 hour monitoring system and battery backup. Includes
minimum of two (2) 18’ x 24” signs or placards on exterior of
trailer indicating the presence of an alarm video surveillance
system.
Crushed rock or paved parking area and walkway for minimum
four (4) vehicles
Extra secure locking system for all exterior doors
Water service (i.e., Crystal Springs or equal, etc.) including water
cooler
Exterior sign indicating address of trailer and phone number to call
in case of emergency
“White board” dry erase in conference room – 36” x 48” minimum
The Contractor shall coordinate utility hook-ups for telephone and
electrical power, including all permits, fees, and/or licenses. Monthly
charges for telephone, power, and portable toilet facilities shall also be
included with this bid price.
8-31.4 Measurement
No specific unit of measurement shall apply to the lump sum bid item
“Field Trailer”.
8-31.5 Payment
Payment will be made in accordance with Section 1-04.1. The unit
contract price per lump sum for “Field Trailer” shall be full
compensation to furnish all labor, materials, tools, supplies, and
equipment necessary to furnish and install the field office described
above in the specifications.
Payment also includes removal of trailer and restoration of the surface
after completion of the project, or close out of rented office space.
Payment will be made on the following basis:
30-percent of lump sum total upon set-up of office space in
accordance with Section 8-35.3.
Progress payments between 30-percent and 90-percent of lump
sum total commensurate with overall construction progression.
100-percent of lump sum total after removal of trailer and
restoration of site, or close out of office space.
Rock Creek Culvert Replacement/Lincoln 9 - 1 June 3, 2021
Project Number: 13-3007.5
DIVISION 9 – MATERIALS
9-03 AGGREGATES
9-03.12 Gravel Backfill
SECTION 9-03.12(3) IS REVISED BY DELETING THE GRAVEL SPECIFICATION
AND REPLACING IT WITH THE FOLLOWING:
9-03.12(3) Gravel Backfill for Pipe Zone Bedding
Pipe bedding shall be 5/8 inch minus crushed rock. Pea gravel is not
allowed. All material shall conform with the following gradation:
Sieve Size Passing
3/4 Inch 100%
5/8 Inch 95 - 100%
1/4 Inch 45 - 65%
US No. 40 6 - 18%
US No. 200 7.5 max. %
% Fracture 75 min.
Sand Equivalent 40 min.
L.A. wear 500 rev. 35 percent max., degradation 25 percent min. Free
from wood waste, bark and other deleterious material.
9-03.14 Borrow
SECTION 9-03.14(1) IS DELETED AND REPLACED WITH THE FOLLOWING:
9-03.14(1) Gravel Borrow
Gravel Borrow material shall consist of pit-run granular material
conforming to the following gradation:
Sieve Size Percent Passing
3 Inch* 100
3/4 Inch 65 - 100
U.S. No. 4 25 - 70
U.S. No. 10 10 - 50
U.S. No. 40 0- 30
U.S. No. 200 0 - 5
Sand equivalent 50 min.
The maximum passing the U.S. No. 200 sieve is limited to five percent
(5%) based on the minus #4 inch fraction.
Sieve analysis shall be used to verify that this requirement is met.
Recycled materials such as broken concrete or asphalt, shall not be
allowed unless specifically authorized in advance by the Engineer.
Rock Creek Culvert Replacement/Lincoln 9 - 2 June 3, 2021
Project Number: 13-3007.5
Where additional materials are required to formulate the street sub-
base to the cross section denoted in the plans, said additional material
shall be Gravel Borrow.
* The maximum size of stone for geosynthetic reinforced walls or slopes
shall be 100 percent passing 1 1/4 inch square sieve and 90 to 100
percent passing 1 inch square sieve. All other sieve values continue to
apply.
SECTION 9-03.17 IS DELETED AND REPLACED WITH THE FOLLOWING:
9-03.17 Foundation Material Class I and Class II
Foundation Material Class I and Class II shall be used to replace
unsuitable material removed from unstable pipe trench bottoms.
Foundation Material Class I and Class II shall conform to the following
gradations:
Percent Passing
Sieve Size Class I Class II
6” square 100 ---
4” square --- 100
2” square 0 65-85
1” square --- 40-70
1/4” square --- 20 max
All percentages are by weight.
In addition, all rock shall be sound, angular ledge rock or recycled
cement concrete pavement meeting the following specifications.
Suppliers of recycled cement concrete products shall have a quality
assurance program reviewed and approved by the City.
Each rock or piece of recycled cement concrete pavement shall have at
least two fractured faces.
Adsorption 3% max
(Corps of Engineers CRD-C-107)
Accelerated Expansion (15) days 15% max
Soundness 5% max loss
Density (solid volume) 155 pcf min
Specific Gravity 2.48 min
9-03.21 Recycled Material
SECTION 9-03.21(1)D IS SUPPLEMENTED BY ADDING THE FOLLOWING:
Rock Creek Culvert Replacement/Lincoln 9 - 3 June 3, 2021
Project Number: 13-3007.5
9-03.21(1)D Recycled Glass (glass cullet)
Recycle glass (glass cullet) shall not be used for any purposes.
9-13 RIPRAP, QUARRY SPALLS, SLOPE PROTECTION, AND ROCK FOR
EROSION AND SCOUR PROTECTION AND ROCK WALLS
SECTION 9-13 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
9-13.8 Rock for Ditches
Rocks for ditches shall meet the following requirements for grading:
Sieve Size Percent Passing
12” 95 to 100
6” 40 to 60
3” 10 to 20
3/4” 0 to 5
9-14 EROSION CONTROL AND ROADSIDE PLANTING
9-14.2 Topsoil
SECTION 9-14.2(1) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
9-14.2(1) Topsoil Type A
The topsoil shall be Cedar Grove Composting 3-Way Topsoil or
approved equal. To be equal, source should be a commercial operation
with expertise in production of topsoil, an established method of
screening materials to verify no pollutant contamination and that all
materials are biodegradable and produce a product that is equal in
quality to the source listed. A quality topsoil product is at a minimum a
sandy loam soil with fine compost amendments, rich in nutrients, free
draining, and weed free.
Submit one-gallon sample, source, and letter of certification from the
supplier for approval prior to installation.
Topsoil Type A shall meet the following requirements:
1. Cation exchange capacity (CEC) of Topsoil Type A shall be a
minimum of 10 milliequivalents CEC/100 g dry soil (U.S. EPA Method
9081).
2. Organic content greater than 10-percent but less than 15-percent as
measured on a dry weight basis using AASHTO T 267 Determination
of Organic Content in Soils by Loss on Ignition.
3. pH shall be between 6.0 and 7.5.
4. Soluble salt contents shall be less than 3.0 hos/com.
Rock Creek Culvert Replacement/Lincoln 9 - 4 June 3, 2021
Project Number: 13-3007.5
5. Conductivity shall be less than 3 mmhs/cm.
Topsoil Type A shall be 50-percent to 65-percent Sandy Loam and 50-
percent to 35-percent Fine Compost by volume. The Fine Compost shall
conform to the requirements of Section 9-14.5(8). Sandy Loam shall be
as defined by the US Department of Agriculture Soil Classification
System, meeting the requirements of Table 1; and be free of phyto-
toxic materials, and viable seeds, rhizomes or roots of State-listed
noxious weeds.
Table 1. Particle Size Analysis for Loam
Sieve Size % Passing
3/4” 100%
1/2” 90-100%
3/8” 85-100%
#4 75-90%
#10 55-75%
#20 45-60%
#30 40-55%
#60 20-40%
#100 20-30%
#200 <30%
#270 <25%
2 μm <20%
Topsoil Type A Submittal Requirements
At least 10 Working Days prior to placement of any Topsoil Type A, the
Contractor shall submit the following test results from an independent
accredited soil testing laboratory, for samples gathered and tested less
than 90 days prior. The laboratory analysis shall be with a sample size
of no less than 2 pounds.
1. Grain size analysis results for Sandy Loam using method ASTM D422
2. STA / Washington State Department of Transportation Technical
Data Sheet for Compost, from a STA accredited lab.
3. Test results from an accredited soil laboratory for all soil mixes,
including the following parameters:
a. Cation exchange capacity (CEC)
b. Grain size analysis results using method ASTM D422 for
Sandy Loam
c. Soluble salt contents reported as hos/com.
d. Total and Soluble Nitrogen (NO3 + NH3)
e. Phosphorus
f. Potassium
g. pH
h. Organic Matter % (Loss on Ignition method)
i. Conductivity
Rock Creek Culvert Replacement/Lincoln 9 - 5 June 3, 2021
Project Number: 13-3007.5
j. Calcium
k. Sulfur
l. Boron
Recommendations. Fertilizer and amendment recommendations from
an accredited Soil Scientist or Agronomist; for the specified plant type
and soil application depth.
Mix Samples. Two one (1) gallon samples of each soil mix.
Topsoil Type A Acceptance
Contractor shall not place any soils until the Engineer has reviewed and
confirmed the following:
1. Deliver tickets must show that the full delivered amount of soil
matches the product type, volume and Manufacturer named in
the submittals.
2. Delivered product shall be compared to the submitted sample to
verify that it matches the submitted sample
The Engineer may inspect any loads of soil and/or delivery tickets on
delivery and stop placement if the delivered soil does not appear to
match the submittals; and require sampling and testing of the delivered
soil before authorizing soil placement. All testing cost shall be the
responsibility of the contractor.
SECTION 9-14.2 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
9-14.2(4) Sandy Loam
Sandy loam shall consist of soil having a maximum clay content of ten
percent by weight. In addition, soil particles shall meet the following
requirements for grading:
Passing 1 inch sieve (square opening) ......... 100%
Passing 1 mm sieve .................................. 80% minimum
Passing 0.15 mm sieve .............................. 15% maximum
SECTION 9-14.3 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
9-14.3 Seed
Seed mix shall be Sunmark Seeds Native Roadside seed mix or
approved equal. Sunmark Seeds international, Inc., PO Box 1210,
Fairview, Oregon 97024; (503)241-7333. Above seed mix shall be
applied at the rate of three (3) pounds live seed per 1,000 square feet.
SECTION 9-14.4 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
9-14.4 Fertilizer
Rock Creek Culvert Replacement/Lincoln 9 - 6 June 3, 2021
Project Number: 13-3007.5
Tree and shrub planting fertilizer shall be Mirimichi Green Organic 3-2-3
for Trees and Shrubs or approved equal. Application rates shall be as
directed by the manufacturer. Mirimichi Green products may be
obtained from Horizon in Renton, WA or at Ewing in Auburn, WA.
Seed mix fertilizer shall be Nutriturf 3-2-3 Turf Fertilizer (Mirimichi
Green product) or approved equal. Application rates shall be as directed
by the manufacturer. Mirimichi Green products may be obtained from
Horizon in Renton, WA or at Ewing in Auburn, WA.
9-14.5 Mulch and Amendments
SECTION 9-14.5(8) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
9-14.5(8) Compost
Compost shall not contain any sawdust, straw, green or under-
composed organic matter, under-sterilized manure or toxic or otherwise
harmful materials.
SECTION 9-14.5 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
9-14.5(10) Wood Cellulose Fiber
Wood cellulose mulch shall be specially processed 100 percent virgin
wood fiber containing no growth or germination-inhibiting ingredients.
It shall be manufactured in such a manner that after addition and
agitation in slurry tanks with water, the fibers in the material will
become uniformly suspended to form a homogenous slurry. When
hydraulically sprayed on the ground, the material shall allow the
absorption and percolation of moisture.
Wood cellulose fiber shall be Weyerhaeuser Silva-Fiber Plus w/Tackifier
or approved equal.
Organic matter content shall be at least 93 percent on an oven-dry
basis as determined by ASTM D 586. The moisture content shall be no
more than 15 percent as determined by oven dried weight. Each
package of the cellulose fiber shall be marked by the manufacturer to
show the dried weight content.
9-14.7 Plant Materials
SECTION 9-14.7(1) IS SUPPLEMENTED WITH THE FOLLOWING:
9-14.7(1) Description
Plant materials described as plugs include 5.5 cubic-inch containers and
10 cubic-inch containers. These plants are started and grown in a
continuous sheet with plug cells that are non-detachable.
Rock Creek Culvert Replacement/Lincoln 9 - 7 June 3, 2021
Project Number: 13-3007.5
9-14.8 Stakes, Guys, and Wrapping
SECTION 9-14.8 IS SUPPLEMENTED BY ADDING THE FOLLOWING NEW
SECTION:
9-14.8(1) Tree Ties
Tree ties shall be patent “Tre-Ties” sufficient in size and number to
adequately support the trees as determined by Quentin Poil, Nursery
Supervisor at 253-856-5127.
9-16 FENCE AND GUARDRAIL
9-16.1 Chain Link Fence and Gates
SECTION 9-16.1(1)B IS DELETED AND REPLACED WITH THE FOLLOWING:
9-16.1(1)B Chain Link Fence Fabric
Chain link fabric shall consist of 9 gage wire (0.148-inch diameter) for
all fences unless specified otherwise. The fabric wire shall be:
Galvanized steel wire conforming to ASTM A 392. Galvanizing shall
be Class I performed by the hot dip process.
The wire shall be woven into approximately 2-inch diamond mesh. The
width and top and bottom finish of the fabric shall be as shown in the
plans.
9-28 SIGNING MATERIALS AND FABRICATION
SECTION 9-28.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
9-28.1 General
All signs shall be reflectorized except for City Project Signs. ALL
PERMANENT SIGNS, EXCEPT “NO PARKING ANYTIME” SIGNS SHALL
HAVE VIP SIGNS AND CLASS A TEMPORARY DIAMOND GRADE RETRO-
REFLECTORIZED SHEETING, UNLESS NOTED OTHERWISE IN THE
PLANS. “NO PARKING ANYTIME” signs shall have engineer grade retro-
reflectorized sheeting.
9-28.14 Sign Support Structures
SECTION 9-28.14(2) IS SUPPLEMENTED BY ADDING THE FOLLOWING:
9-28.14(2) Steel Structures and Posts
Truss chords, struts, and diagonals, end posts, and end post struts and
diagonals for sign bridge structures and cantilever sign structures shall
conform to either ASTM A 36 or ASTM A 53 Grade B Type E or S. The
nominal pipe diameter and the pipe wall thickness shall be as specified
in the plans or Standard Plans. All other structural steel for sign bridge
Rock Creek Culvert Replacement/Lincoln 9 - 8 June 3, 2021
Project Number: 13-3007.5
structures and cantilever sign structures shall conform to ASTM A 36.
Truss member connection hardware shall conform to Section 9-06.5(3).
Pipe members for bridge mounted sign brackets shall conform to ASTM
A 53 Grade B Type E or S, and shall be Schedule 40 unless otherwise
specified. All other structural steel for bridge mounted sign brackets
shall conform to ASTM A 36. U bolts, and associated nuts and washers,
shall be stainless steel conforming to Section 9-28.11, and shall be
fabricated hot.
Anchor rods, nuts and washers for sign bridge structure foundations
shall conform to Section 9-06.5(4). Anchor rods for cantilever sign
structure foundations shall conform to ASTM F 1554 Grade 104,
including the appropriate supplemental requirements for grade and
manufacturer’s identification, and charpy impact testing (15 foot-
pounds minimum at 40F). Nuts and washers for cantilever sign
structure foundations shall conform to AASHTO M 291 Grade DH and
AASHTO M 293, respectively.
Anchor rods for sign bridge structures and cantilever sign structures
shall be galvanized after fabrication a minimum of 1’-0” at the exposed
end in accordance with AASHTO M 232. Anchor rod templates shall
conform to ASTM A 36, but need not be galvanized.
Steel sign structures and posts shall be galvanized after fabrication in
accordance with AASHTO M 111, unless noted otherwise in the plans.
All bolts, nuts, and washers shall be galvanized after fabrication in
accordance with AASHTO M 232. Unless otherwise specified in the plans
or Kent Special Provisions, metal surfaces shall not be painted.
Minor fabricating and modifications necessary for galvanizing will be
allowed if not detrimental to the end product as determined by the
Engineer. If such modifications are contemplated, the Contractor shall
submit to the Engineer, for approval six copies of the proposed
modifications, prior to fabrication.
9-30 WATER DISTRIBUTION MATERIALS
SECTION 9-30.1 IS SUPPLEMENTED BY ADDING THE FOLLOWING:
9-30.1 Pipe
The pipe manufacturer shall test all pipe and fittings as required by
these Specifications and the standards referenced. The pipe
manufacturer shall submit to the Engineer two copies of all test results,
including a certification that material to be delivered is represented by
the samples tested and that such delivered materials meet or exceed
the specified requirements. No pipe shall be delivered until test results
and certifications are received by the Engineer.
The Engineer shall have free access to all testing and records pertaining
to material to be
Rock Creek Culvert Replacement/Lincoln 9 - 9 June 3, 2021
Project Number: 13-3007.5
delivered to the job site. The Engineer may elect to be present at any
or all material testing
operations.
In addition all water main pipe for this project shall be per CWD
Standards and Specifications section 4.01 and 4.02.
SECTION 9-30.1(1) IS DELETED AND REPLACED WITH THE FOLLOWING:
9-30.1(1) Ductile Iron Pipe
Ductile iron pipe shall be cement-lined unless otherwise specified and
shall conform to AWWA C151 standards. Ductile iron pipe shall be
thickness class 52 or greater. Standard thickness of cement-mortar
lining shall be in accordance with AWWA C104 standards. Greater
thickness or pressure class may be required where the pipe will be
exposed to high external loads, depth of bury outside of District
Standards or as directed by the District Engineer. Special design
submittal will be required in such circumstances. Ductile iron pipe shall
be manufactured by an approved manufacturer as indicated in the most
recent version of the Covington Water District Standards and
Specifications Approved Materials List; Appendix C.
Push-on joint gaskets are not interchangeable between brands, and
shall be of the same manufacturer as the pipe provided. The Contractor
shall assure the use of correct gaskets.
SECTION 9-30.2 IS SUPPLEMENTED WITH THE FOLLOWING:
9-30.2 Fittings
In addition all water main pipe fittings for this project shall be per CWD
Standards and specifications section 4.08.
SECTION 9-30.2(1) IS DELETED AND REPLACED WITH THE FOLLOWING:
9-30.2(1) Ductile Iron Pipe
All fittings for ductile iron and PVC pipe shall be ductile iron with
cement-mortar lining conforming to AWWA C104. Mechanical joint
fittings shall be compact fittings conforming to AWWA C153, with
ductile iron follower gland conforming to AWWA C111. Flanged fitting
shall conform to AWWA C110. Fittings shall utilize gaskets and
hardware in accordance with AWWA C111.
Ductile iron fittings shall be manufactured by an approved manufacturer
as indicated in the most recent version of the Covington Water District
Standards and Specifications Approved Materials List; Appendix C.
Gaskets shall be rubber, either ring or full face and 1/8-inch thick
unless otherwise specified. Gaskets shall fully comply with AWWA
C111/A21.11-00.
Rock Creek Culvert Replacement/Lincoln 9 - 10 June 3, 2021
Project Number: 13-3007.5
Restraining devices provided shall be intended for the pipe material on
which they are installed (D.I. or PVC).
SECTION 9-30.2(6) IS DELETED AND REPLACED WITH THE FOLLOWING:
9-30.2(6) Restrained Joints
Restrained joints shall be either bolted or boltless design and flexible
after assembly. Any device utilizing set screws is not permitted.
Restrained joint devices shall not be used on plain end fittings. Use of
shackle rods on ductile iron bell-and-spigot pipe is not permitted.
Thrust blocks shall be provided in addition to the joint restraint system
unless otherwise approved by the District. Restrained joint waterlines
greater than 16-inches are specialty design which may require
additional considerations not addressed in this specification.
Boltless designs shall utilize gripping gaskets suitable for a 350 psi
working pressure.
Gripping gaskets shall be rubber gaskets with stainless steel teeth for
wedging action on bell-and-spigot DI pipe, 16-inch diameter and
smaller. Gasket material and dimensions shall conform to AWWA C111.
Gaskets shall only be used on compatible pipe as recommended by the
manufacturer.
Bolted joint restraint systems shall utilize multiple gripping wedges
incorporated into a ductile iron retainer gland. The gland body and
wedges shall be cast from grade 65-45-12 ductile iron in conformance
with ASTM A536. Glands for mechanical joints shall be compatible with
all mechanical joints conforming to AWWA C111. Split designs are only
allowed on mid-pipe installations for embedment into concrete for
thrust restraint. The working pressure of the joint restraint system
when used on ductile iron pipe shall be a minimum of 350 psi for pipe
diameters of 16-inches or less. Wedge-action joint restraint systems
used on PVC pipe shall have a working pressure rating equal to the
pipe rating with a minimum safety factor of two.
Bolted restraint for C900 and C905 PVC bell-and-spigot pipe joints
shall utilize a full-circle bell restraint harness with stainless steel
clamping hardware. Harnesses shall be split design, provide full 360
degree contact and support of pipe and incorporate serrations on the
inner face to provide full restraint. Restraint harnesses shall be epoxy
coated grade 65-45-12 ductile iron. Use of a back-up ring against the
pipe bell is prohibited. Threaded thrust rods and nuts used to connect
the harnesses over the bell shall be constructed of high strength low
alloy steel in accordance with AWWA C111. After assembly, thrust
restraint hardware shall be field coated with an epoxy designed for
underground conditions. Bell-and-spigot restraint systems used on
PVC pipe shall have a working pressure rating equal to the pipe rating
with a minimum safety factor of two. Wedge-action retainers designed
for PVC pipe meeting the requirements herein may be utilized in lieu of
serrated harnesses.
Rock Creek Culvert Replacement/Lincoln 9 - 11 June 3, 2021
Project Number: 13-3007.5
Joint Restrain Systems shall be manufactured by an approved
manufacturer as indicated in the most recent version of the Covington
Water District Standards and Specifications Approved Materials List;
Appendix C.
SECTION 9-30.2(8) IS DELETED AND REPLACED WITH THE FOLLOWING:
9-30.2(8) Flexible Expansion Joints
1. Flexible expansion joints shall be installed in the locations indicated
on the drawings and shall be manufactured of ductile iron
conforming to the material requirements of ASTM A536 and
ANSI/AWWA C153/A21.53. Foundry certification of material shall
be readily available upon request.
2. Each flexible expansion joint shall be pressure tested prior to
shipment against its own restraint to a minimum of 350 PSI for 3
inch through 16 inch and 250 PSI for 18 inch and greater. A
minimum 2:1 safety factor, determined from the published
pressure rating, shall apply.
3. Each flexible expansion joint shall consist of an expansion joint
designed and cast as an integral part of a ball and socket type
flexible joint, having a minimum per ball deflection of: 20º for
sizes 4-inch through 12-inch; 15º for sizes 14-inch through 36-
inch and 12 º for size 48-inch. The flexible expansion fitting shall
not expand or exert an axial imparting thrust under internal water
pressure. The flexible expansion fitting shall not increase or
decrease the internal water volume as the unit expands or
contracts. The minimum total linear travel shall be 8-inches.
4. All internal surfaces (wetted parts) shall be lined with a minimum
of 15 mils of fusion bonded epoxy conforming to the applicable
requirements of ANSI/AWWA C213. Sealing gaskets shall be
constructed of EPDM. The coating shall meet ANSI/NSF-61.
5. Exterior surfaces shall be coated with a minimum of 6 mils of
fusion bonded epoxy conforming to the applicable requirements of
ANSI/AWWA C116/A21.16.
6. Polyethylene sleeves, meeting ANSI/AWWA C105/A21.5, shall be
included for direct buried applications.
7. Manufacturer’s certification of compliance to the above standards
and requirements shall be readily available upon request. The
purchaser (or owner) shall reserve the right to inspect the
manufacturer’s facility for compliance. All flexible expansion joints
shall be manufactured by an approved manufacturer as indicated
in the most recent version of the Covington Water District
Standards and Specifications Approved Materials List; Appendix C.
SECTION 9-30.2(11) IS DELETED AND REPLACED WITH THE FOLLOWING:
9-30.2(11) Steel Casing
Steel casing shall be black steel pipe conforming to ASTM A 53. Before
installation, coat casing exterior with shop-applied anticorrosive
coating conforming to AWWA C210. Minimum coating thickness shall
be 16 mils dry film thickness (DFT); however, thickness shall not
Rock Creek Culvert Replacement/Lincoln 9 - 12 June 3, 2021
Project Number: 13-3007.5
exceed manufacturer’s recommended thickness. Coating type shall be
a polyamide epoxy-coal tar equal to Tnemec Hi-Build Theme-Tar,
Series 46H-413.
Casing wall thickness shall be 0.50 inch minimum for casings 20 inch
in diameter.
SECTION 9-30.2 SUPPLEMENTED WITH THE FOLLOWING NEW SUBSECTION:
9-30.2(12) Spacers and Seals for Casing Pipe
Casing spacers shall be “centered positioning” type bands at least 12
inch in width, and shall be either stainless steel or heavy duty fusion
bonded epoxy coated steel. Runners shall be 2-inch wide glass
reinforced plastic securely bonded to the spacer, and shall be aligned
on the spacer along the axis of insertion of the water main into the
casing pipe. Runner length shall approximate the width of the spacer.
Securing the spacer to the water main shall be in accordance with the
manufacturer’s instruction. The height of the risers and runners
combined shall be sufficient to keep the carrier pipe bell, couplings or
fittings at least 0.75 inch from the casing pipe wall at all times and
provide at least 1-inch clearance between the runners and the top of
the casing wall, to prevent jamming during installation.
Acceptable spacers and end seals manufacturers are Pipeline Seal and
Insulator model S12G-2 for stainless steel and model C12G-2, C8G-2
for fusion-bonded and coated steel, Cascade Waterworks Mfg. Co.,
Advance Products & Systems, Inc. or approved equal.
SECTION 9-30.2 SUPPLEMENTED WITH THE FOLLOWING NEW SUBSECTION:
9-30.2(13) Pipe Insulation
Insulation shall be cellular glass and meet ASTM C552 (FoamGlas or
approved equal). Insulation shall be wrapped in jacketing using 50 mil
thickness PittWrap or approved equal. Jacketing edging shall be sealed
off using approved taping provided by the same manufacturer as the
jacketing.
Insulation at hangers shall be insulated hanger supports by Aeroflex,
Foamglas or approved equal.
SECTION 9-30.3(4) SUPPLEMENTED WITH THE FOLLOWING:
9-30.3(4) Valve Boxes
All valve boxes shall be as per CWD Standards and Specification
section 4.16. When discrepancies between plans and specifications are
present, the 2016 CWD Standards and Specifications shall prevail.
SECTION 9-30.3(5) SUPPLEMENTED WITH THE FOLLOWING:
Rock Creek Culvert Replacement/Lincoln 9 - 13 June 3, 2021
Project Number: 13-3007.5
9-30.3(5) Valve Marker Posts
All valve marker posts shall be as per CWD Standards and
Specifications section 4.15. When discrepancies between plans and
Specifications are present, the 2016 CWD Standards and Specifications
shall prevail.
SECTION 9-30.3(6) SUPPLEMENTED WITH THE FOLLOWING:
9-30.3(6) Valve Stem Extensions
All valve stem extensions shall be as per CWD Standards and
Specifications detail sheet 9.
SECTION 9-30.3(6) SUPPLEMENTED WITH THE FOLLOWING:
9-30.3(6) Tapping Sleeve and Valve Assembly
In addition all tapping sleeve and valve assembly shall be per CWD
Standards and Specifications section 4.21.
Rock Creek Culvert Replacement/Lincoln A - 1 June 3, 2021
Project Number: 13-3007.5
APPENDIX A
SCWSD ROCK CREEK CULVERT CROSSING
(02-2020S) SPECIFICATION –
SUPPLEMENTAL CRITERIA
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
SCWSD Rock Creek Culvert Crossing (02-2020S)
Specification - Supplemental Criteria
III-7 TRENCH SHORING SYSTEMS IN COMPLIANCE WITH WISHA
A. Description
This Work shall consist of construction and removal of shoring and cribbing for all excavation,
backfill, compaction and other Work required for compliance with WISHA, Chapter 49.17
RCW.
Also included in this Work are all excavations, backfill, compaction and other Work required
when extra excavation is used in lieu of shoring and cribbing for compliance with WISHA,
Chapter 49.17 RCW.
B. Measurement
Measurement shall be per lineal foot measured horizontally along the centerline of the pipe,
through fittings and valves.
C. Payment
The unit price Bid per lineal foot shall be considered full payment for all labor, materials, tools
and equipment necessary for furnishing, installing and removing shoring and cribbing or for
all excavation, backfill, compaction and other Work required when extra excavation is used
in lieu of shoring and cribbing for compliance with WISHA, Chapter 49.17 RCW. Costs for
WISHA compliance shall not be incidental to any other Bid items.
D. Material
Material shall be as specified in the Standard Specifications or as modified herein, to include
but not be limited to shoring, cribbing, select backfill, and any extra restoration materials
needed when extra excavation is used in lieu of shoring and cribbing.
E. Construction Requirements
Any trench exceeding four (4) feet in depth shall be provided with adequate safety systems
meeting the requirements of the Washington State Industrial Safety and Health Act (WISHA),
Chapter 49.17 RCW, and all regulations adopted pursuant thereto. CONTRACTOR shall
have a structural engineer prepare and stamp any and all shoring plans and calculations.
The CONTRACTOR alone shall be responsible for Worker safety and the OWNER and the
ENGINEER assume no responsibility.
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
III-7 ABANDON EXISTING SEWER FORCE MAIN
A. Description
This Work shall consist of filling the existing PVC force main with water, disinfection of the
existing force main, capping the existing force main, and abandoning the existing force main
in place.
B. Measurement
Measurement shall be per lump sum. No measurement shall be made for clearing and
grubbing, removal of existing protection of existing utilities and services, trench excavation
and backfill, bedding the pipe, compaction of backfill, removal and/or disposal of pipe, de-
chlorination activities, pumping, material placement, and/or trench dewatering.
C. Payment
The unit price Bid per lump sum shall be considered full payment for all labor, materials, tools
and equipment necessary to fill the existing force main with water, disinfect the force main,
cap, and abandon the existing 6-inch PVC force main as shown on the plans.
End caps shall be paid und the Bid Item PVC Fittings.
D. Material
All fittings and end caps shall be of the same type and class of the pipe.
E. Construction Requirements
CONTRACTOR shall abandon all existing sewer utilities that are to be replaced.
CONTRACTOR shall cut, cap with end cap couplings, fill the existing force main with water,
and disinfect said sewer force main. CONTRACTOR shall strive to leave abandoned pipe in
place, but if existing pipe is disturbed, the CONTRACTOR shall disinfect, remove said pipe,
re-cap the exposed section of existing force main, and dispose of pipe at approved disposal
site.
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
III-13 6-INCH SEWER FORCE MAIN, C900
III-14 PVC Fittings
A. Description
Work shall be as described in Section 7-09.1, 7-17.1 and 7-18.1 of the Standard
Specifications and as modified and supplemented herein.
B. Measurement
Delete Sections 7-08.4, 7-09.4, 7-17.4, and 7-18.4 of the Standard Specifications.
Pipe shall be measured by the lineal foot from center from connections, through tees or
fittings, on the horizontal for lines having less than 10 percent slope. For lines with 10 percent
or greater slope, the pay measurement shall be along the centerline of the pipe.
Measurement shall be per lineal foot for each size, class and type of pipe as stated in the
Proposal.
Measurement shall include all dewatering efforts required to maintain "dry" conditions in all
trenches and excavations associated with the installation of the PVC pipe, to include but not
be limited to installation, maintenance, and removal of any temporary piping, pumps, and
accessories.
No measurement shall be made for clearing and grubbing, removal of existing protection of
existing utilities and services, trench excavation and backfill, bedding the pipe, compaction
of backfill, trench dewatering, and pressure tests of pipes. No measurement shall be made
for potholing at other utility crossings.
PVC Fittings shall be measured in pounds based on the equivalent weight of similar ductile
iron fittings with mechanical joints at both ends as indicated on ANSI/AWWA C110/A21.0.
The equivalent weight shall not include the weight of any bolt kits, gaskets, and backup rings.
The joint restraint devices for the fittings shall be measured in pounds based on weights
provided by the manufacturer and indicated on the invoice for this project.
Pipe insulation shall be measured per lineal foot along the centerline of the insulated pipe.
C. Payment
Delete Sections 7-08.5, 7-09.5, 7-17.5, and 7-18.5 of the Standard Specifications.
The unit price Bid per linear foot of pipe per size, class, and type designated shall constitute
full payment for all Work, labor, materials, and equipment necessary to furnish and install
said pipe, including but not limited to the following:
Trench excavation, bedding, laying and jointing the pipe, backfilling with imported
material and compacting backfill.
All fittings, and installation of fittings.
Clearing, grubbing, pavement removals, grading for haul roads, trenching operations,
and disposal of debris.
Dewatering and installing clay dams where necessary.
All costs involved in maintaining traffic control
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
All costs associated with furnishing and maintaining temporary cold or hot mix
patches on all disturbed paved surfaces.
All costs involved in maintaining and/or replacing any public or private utilities,
structures, or other improvements that are disturbed or damaged by the
CONTRACTOR.
All costs associated with the abandonment and disinfection of the existing 6-inch PVC
force main.
Payment shall include all dewatering efforts required to maintain "dry" conditions in all
trenches and excavations associated with the installation of the PVC.
The unit price Bid shall also include, but not be limited to pipeline cleaning and testing.
CONTRACTOR shall furnish all testing materials. CONTRACTOR shall bear all costs
incurred in correcting any deficiencies found during testing, including the cost of any
additional testing that may be required by the OWNER to verify the correction of said
deficiency.
Partial payment for pipe shall be as follows:
(1) Excavation and backfill complete. 80 percent of unit price Bid.
(2) Testing complete including 10 percent of unit price Bid.
satisfactory compaction.
(3) Satisfactory cleanup and 10 percent of unit price Bid.
substantial completion of Sewer.
Satisfactory cleanup shall not be considered complete until disturbed road surfaces have
been permanently patched and all shoulders and non-paved areas restored.
CONTRACTOR is therefore encouraged to complete this Work as soon as possible in order
to minimize the amount of disturbance to the City.
Payment for safety systems and extra excavation to meet the requirements of WISHA,
Chapter 49.17 RCW shall be paid for under the Bid item "Trench Shoring in Compliance with
WISHA". The lineal foot measurement of this Bid item shall be extended through any valve
or fitting.
OWNER shall pay all costs in connection with the initial compaction testing. CONTRACTOR
shall pay all costs in connection with any retesting where initial compaction does not meet
Specification requirements.
The unit price Bid for Fittings shall constitute full compensation for all Work, Labor, materials,
and equipment necessary to furnish and install the required fittings and accessories. Fittings
and accessories shall include but not be limited to all bends, tees, flange adapters, joint
restraint devices, backup rings, gaskets, and bolt kits required to assemble the pipe,
complete in place.
Detectable sewer marking tape and stainless steel tracer wire shall be installed with all PVC
force mains and shall be considered incidental to this Bid Item with no additional payment
made for either item installed.
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
D. Materials
The materials shall be as described in Section 7-09.2, 7-17.2, and 7-18.2 of the Standard
Specifications as herein modified and supplemented.
1. Delete the first paragraph with first table of Section 7-09.2.
2. Delete the first paragraph with first table, and the fourth paragraph with second table
of Section 7-17.2
PVC sewer force main shall meet the requirements of AWWA C900. PVC pipe conforming
to AWWA C900 and shall be a minimum of DR18. Pipe shall be listed by Underwriters'
Laboratories, Inc.
PVC pipe shall be considered flexible conduit.
PVC compound shall meet the requirements of ASTM D 1784 for Class 12454-B PVC.
PVC compound shall meet the requirements of ASTM D1784 for Class 12454-B PVC.
All fittings shall be of the same type and class of the pipe. PVC sewer pipe and fittings shall
be furnished with bells and spigots which are integral with the pipe wall. PVC pipe joints shall
be rubber gasket types. Solvent cement joints shall not be used. All PVC fittings shall have
the appropriate concrete thrust block or have restrained joints.
Detectable sewer marking tape and stainless steel tracer wire shall be installed with all PVC
force mains and shall meet the requirements of Section 9-15.18 of the Standard
Specifications. Marking tape and tracer wire shall be considered incidental to this Bid Item.
Bedding material for PVC pipe shall conform to Section 9-03.16 of the Standard
Specifications. Backfill material shall conform to the material requirements under the
appropriate Bid item description contained in these Specifications.
The restraining of PVC pipe and fittings shall be the Series 2500, as manufactured by EBAA
Iron, Inc. or approved equal. Any device utilizing round point set screws shall not be
permitted.
E. Construction Requirements
Work shall be as described in Section 7-08.3, 7-09.3, 7-17.3 and 7-18.3 of the Standard
Specifications and as modified and supplemented herein.
Delete the second paragraph of Section 7-08.3(1)B.
(1) Delete the third, fourth, and fifth sentences of the fourth paragraph of Section 7-
08.3(3).
(2) Delete the sixth paragraph of Section 7-08.3(3).
(3) Replace the last sentence of Section 7-09.3(3) with the following sentences:
All material from clearing and grubbing shall be hauled to an approved waste disposal
site provided by the CONTRACTOR. No onsite burning shall be allowed.
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
(4) Replace the first sentence of the first paragraph of Section 7-09.3(7) with the following
sentences:
Trench excavation shall be unclassified. The CONTRACTOR shall excavate all
materials encountered to the depth shown on the Drawings or as directed by the
ENGINEER. No extra payment shall be allowed for bedrock, boulders, hard pan,
cemented gravel, or any other material encountered.
(5) Replace the sixth and seventh paragraphs of Section 7-09.3(7) with the following
paragraphs:
Any trench exceeding four feet in depth shall be provided with adequate safety
systems meeting the requirements of the Washington State Industrial Safety and
Health Act (WISHA), Chapter 49.17 RCW, and all regulations adopted pursuant
thereto. CONTRACTOR shall have a structural engineer prepare and stamp any and
all shoring plans and calculations. The CONTRACTOR alone shall be responsible
for Worker safety and the OWNER and the ENGINEER assume no responsibility.
All ledge rock, boulders, and stones shall be removed to provide a minimum of four
inches clearance under all portions of the pipe. All rock larger than two inches in
diameter shall be disposed of at a site obtained by the CONTRACTOR, and shall not
be used for trench backfill.
(6) Delete Section 7-09.3(7)B.
(7) Add the following paragraphs to Section 7-09.3(9):
When native material at the trench bottom is stony or otherwise non-uniform, the
trench shall be over-excavated a minimum of 6 inches below the specified grade and
a layer of pipe bedding material shall be placed to the specified grade. After the pipe
is in place, additional hand selected native material meeting the bedding material
gradation shall be placed and tamped around the pipe for a minimum of 4 inches over
the crown of the pipe.
If the native material at the trench bottom is unsuitable for foundation purposes or will
have difficulty providing uniform bearing for the pipe, such material shall be removed
and replaced with a minimum of 6 inches of compacted foundation material.
The bedding material shall be carried up evenly on both sides of the pipe
simultaneously in approximately 6-inch layers and each layer thoroughly compacted
with appropriate tools in such manner as to avoid injuring or disturbing the completed
pipeline. All bedding and native material shall be stored away from the edges of
excavation and off the paved roadway and shoulder.
(8) Replace the second and third paragraphs of Section 7-09.3(10) with the following
paragraphs:
Backfill material shall consist of 100% imported crushed surfacing material.
In cuts transverse to the road alignment and at all utility crossings, the entire trench
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
shall be backfilled with crushed surfacing. Backfill shall be placed and mechanically
compacted in 1-foot maximum lifts. After backfill and compaction, an immediate cold
mix patch shall be placed and maintained in a manner acceptable to the governing
agency’s inspector until replaced with a permanent hot mix patch.
CONTRACTOR shall be responsible for the disposal of any excess excavated soil
material.
(9) Replace Section 7-09.3(11) with the following paragraphs:
All trench backfill shall be mechanically compacted to 95% of maximum density within
the right of way and in all areas (paved and unpaved) where streets, roadway
shoulders, and driveways. All densities shall be determined by testing per the
Modified Proctor Method, ASTM D1557.
Backfill shall be placed in uniform loose layers no more than 12-inches thick and
mechanically compacted as specified. In any trench where the specified compaction
cannot be achieved with native backfill, the top 4 feet shall be replaced and
compacted to 95% of the maximum density with Bank Run Gravel for Trench Backfill
as specified in Section 9-03.19 of the Standard Specifications. The ENGINEER
reserves the right to request a compaction test at any time on the backfill material.
(10) Delete Sections 7-09.3(17) and 7-09.3(19).
(11) Rename Section 7-09.3(20), Detectable Tracer Wire and replace with the following:
Detectable sewer marking tape and stainless steel tracer wire shall be installed with
all PVC force mains and shall meet the requirements of Section 9-15.18 of the
Standard Specifications. Marking tape and tracer wire shall be considered incidental
to this Bid Item.
(12) Replace the first sentence in the first paragraph of Section 7-09.3(23) with the
following sentences.
The CONTRACTOR shall perform all clearing necessary for the proper installation of
all piping and appurtenances in the locations shown on the Drawings.
Minimum separation of potable water mains and sewer force main lines shall be 10
feet horizontally for parallel pipe, and 1½ feet vertically for perpendicular or oblique
crossings, measured from outside edge to outside edge. Situations occurring with
less than minimum separation shall require construction in accordance with Chapter
C1-1.9.1.1 of the Criteria for Sewage Works Design, published by the Washington
State Department of Ecology (DOE) as revised August 2008. Minimum separation
between other utilities except sanitary sewers shall be six inches with a sand cushion.
All pipe and fittings shall be laid "in the dry" unless otherwise approved by
ENGINEER. Trench excavations shall be dewatered by using well point systems,
sumps with pumps or other methods approved by the ENGINEER. Dewatering
systems shall be used in accordance with good standard practice and shall be
efficient enough to lower the water level in advance of the excavation and maintain it
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
continuously to keep the trench bottom and sides firm and dry. CONTRACTOR shall
submit the dewatering plan to ENGINEER for review at least 10 days prior to
commencing any dewatering work.
Groundwater shall be controlled such that softening of the bottom of excavations or
formation of "quick" conditions or "boils" during excavation shall be prevented and no
soil shall be eroded into the excavation from the sides of excavation. Dewatering
systems shall be designed and operated so as to prevent removal of the natural soils.
CONTRACTOR shall at all times have on hand sufficient pumping equipment and
machinery in good working condition for all ordinary emergencies, including power
outages, and shall have available at all times competent workers for the operation of
said equipment.
CONTRACTOR shall control surface runoff so as to prevent entry or collection of
water in excavations. CONTRACTOR shall maintain the undisturbed state of the
foundation soils and allow the placement of any backfill to the required density. The
release of groundwater to its static level shall be performed in such a manner as to
maintain the undisturbed state of the natural foundation soils, prevent disturbance of
compacted backfill, and prevent flotation or movement of structures and pipelines.
CONTRACTOR shall be responsible for complying with all permit requirements and
provisions for monitoring and managing water discharged from the excavation.
C900 Pipe Insulation
The 6-inch C900 pipe is to be insulated to prevent the pipe from freezing for the
length of pipe inside the steel casing. Pipe insulation shall be a minimum of 2-
inches thick and prevent pipe freezing up to, and including, when ambient temp
reaches 20-degrees Fahrenheit. The CONTRACTOR shall submit pipe insulation
cut sheets to the ENGINEER for approval prior to force main installation. Pipe
insulation shall be installed for the length of the 6-inch force main in the steel
casing.
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
III-15 16-INCH STEEL CASING
A. Description
Work shall include the construction and installation of one (1) casing segment installed as
shown on the Drawings.
B. Measurement
Measurement shall be per lineal foot along the centerline of the casing.
C. Payment
The price per lineal foot price shall be full payment for all materials, labor, equipment, and
other incidental costs for furnishing and installing the complete steel casing as shown on
the Drawings.
Payment for safety systems and extra excavation to meet the requirements of WISHA,
shall be paid for under the Bid item Trench Shoring Systems in Compliance with WISHA.
The carrier pipe shall be paid for under Bid item “6-Inch Sewer Force Main, C900”.
D. Materials
Steel Casing
Steel casing shall meet the following requirements:
(1) New, smooth wall carbon steel pipe fabricated in sections in accordance with
AWWA C200.
(2) No interior lining or exterior coating is required.
(3) Shall conform to ASTM Specification A572/50 with a Specified Minimum Yield
Strength (SMYS) of 50,000 psi or greater.
(4) Capacity to withstand the maximum axial force anticipated with a safety factor of
2.0. The casing shall also be installed to withstand long-term soil and groundwater
loads.
(5) Diameter as shown on the Drawings. Casing wall thickness shall be determined
by the Contractor but shall be a minimum of 0.5-inch for 16-inch casing. Casing
lengths shall be determined by the Contractor but shall not be less than 20 feet.
(6) Difference in roundness between the major and the minor outside diameters not
exceeding 1% of the specified nominal outside diameter, or ¼ inch, whichever is
less.
(7) Outside circumference which is within 1% of the nominal circumference, or ½ inch,
whichever is less.
(8) Minimum allowable straightness deviation in any 10-foot length of 1/8 inch.
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
Joints
Steel casing joints shall meet the following requirements:
(1) Steel casing joints shall be full-penetration fully circumferential butt welds
conforming to ANSI/AWS D1.1 – Structural Welding Code.
(2) Steel casing for welding shall be square cut with beveled ends.
(3) Bevels shall be 30 degrees + 5 degrees/- 0 degrees and with a width of root face
of 1/16th inch +/- 1/32 inch.
Casing Spacers
(1) Refer to Contract Drawings for casing spacer placement and orientation of carrier
pipe. Follow Manufacturer’s requirements for spacing placement on carrier pipes.
(2) Spacers shall provide for effective control of vertical grade of the carrier pipe and
any necessary field adjustments due to casing deviations.
(3) Heavy duty fusion bonded epoxy coated steel spacers, minimum 8-inch width,
glass reinforced plastic runners.
(4) Minimum of four runners at bottom and two top runners.
(5) Shell and riser constructed of welded T304 stainless steel, thickness as required
for application (12-gauge minimum).
(6) Split case design for attaching to carrier pipe with side flanges. Stainless steel
bolts: Minimum 5/16-inch diameter, straps are not allowed.
(7) Runners constructed of ultra high molecular weight polymer plastic, with low
coefficient of friction: 0.11 (per ASTM D1894) or better.
Carrier Pipe
Carrier pipe shall be PVC C900 6-inch pipe and conform to the requirements for the Bid
Item 6-Inch Sewer Force Main, C900.
End Seals
Each open end of the steel casing shall have watertight end seals installed. Installation shall
be per end seal manufacturers specifications.
Casing Bridge Supports and Anchors
16-inch steel casing bridge supports and anchors shall be installed per plan.
CONTRACTOR to submit cut sheets to the ENGINEER for approval prior to casing
installation.
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
E. Construction Requirements
Where shown on the Drawings, the Contractor shall install steel casing pipe for the Force
Main.
All joints shall be welded by operators who have been qualified by testing as prescribed by
the AWS in “Standard Qualifications Procedure” and are certified to perform the type of
work required. The quality of welding shall conform to the current edition AWS D1.1
Structural Welding Code, Section 3, Workmanship.
Casing spacers shall electrically isolate the outer casing pipe from the inserted Force
Main. The spacers (also known as “casing insulators”, “crossing insulators”, and “casing
isolators”) shall meet the requirements of Section 9-30.2(15)B. There shall be a
minimum of two spacers per length of pipe, and the spacing between any two (2)
spacers shall not exceed 10-feet. For 4-inch through 12-inch diameter pipe, each spacer
shall have at least four (4) runners. At least two (2) runners shall be located on the upper
half of the spacer for all diameter Force Main. At least two (2) runners shall be located
on the lower half of the spacer for 4-inch through 12-inch diameter Force Main. Actual
locations of runners on the spacer shall be as recommended by the manufacturer.
Casing spacers shall first be installed on the Force Main and then the Force Main
inserted in the casing pipe in accordance with the manufacturer’s instructions.
The Contractor shall submit the spacer and end seal manufacturer’s catalog cuts and
installation instruction to the Engineer at least five (5) Working Days in advance of this
work.
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
III-16 CONNECTION TO EXISTING SEWER FORCE MAIN
A. Description
Work shall involve connecting the new sewer force main to the existing sewer force main.
C900 PVC force main spools, as shown and as required at a connection, shall be incidental
to this Bid item.
B. Measurement
Connection to existing sewer system shall be measured per each for permanent connections
only. Fittings and couplings associated with a connection shall be incidental to this Bid item.
C. Payment
The unit price Bid per each permanent connection to the existing sewer system shall
constitute full compensation for all Work, labor, materials, and equipment necessary to make
a proper connection or cut-in of the new force mains to the existing sewer system. This shall
include, but shall not be limited to, the following items:
Coordination with the OWNER for shutdown of existing system to make the
connections or cut-ins.
Verifying inverts and fittings required for the connection prior to construction.
Replacing existing concrete blocking with temporary bracing on all fittings that
are disturbed by the connection.
Installing any temporary blocking necessary to make the connection.
Furnishing and installing pipe spools as necessary.
Temporary air relief valves and blow-offs necessary to aid in filling and draining
the existing and proposed pipes.
Properly removing and disposing in a legal and safe manner of any existing
sewer force main and/or fittings that cannot be abandoned in place.
Excavation, dewatering, and backfill necessary for each connection shall be included in the
unit price Bid per lineal foot for the pipe. Permanent fittings indicated at existing system
connections shall be paid under separate Bid item.
6-inch diameter PVC sewer force main spools used at connections, shall meet the material
requirements of Bid item 6Inch Sewer Force Main, C900 but shall be considered incidental
to this Bid item.
D. Materials
Materials shall be as shown on the Drawings and as modified and supplemented herein.
Fittings, and thrust blocks shall meet the material specifications for each as described in their
respective Bid items.
SCWSD Rock Creek Culvert
Schedule III – Special Provisions
E. Construction Requirements
Work shall be as described in Section 7-09.3(19)A of the Standard Specifications and as
modified and supplemented herein.
(1) Replace the last sentence in the sixth paragraph of Section 7-09.3(19)A with the
following sentence:
CONTRACTOR shall not operate any valve of the existing sewer system at any time,
without prior approval of the OWNER.
(2) Delete the last paragraph of Section 7-09.3(19)A.
The CONTRACTOR shall notify the DISTRICT’s field representative and other utilities at
least 96-hours in advance of any construction and make the necessary arrangements with
the DISTRICT’s field representative for the connection to the existing sewer force main.
The CONTRACTOR shall furnish all material, equipment and labor necessary for making
the connection under the supervision of the DISTRICT. The 96-hour notice requirement
shall not count Saturdays, Sundays, or holidays.
Work shall not be started until all of the material, equipment and labor necessary to
properly complete work is assembled on the site. Once work is started on a connection,
it shall proceed continuously without interruption and as rapidly as possible until the
connection is completed. Before ordering materials for any connection to an existing sewer
main, CONTRACTOR shall excavate the sewer main and verify the type of pipe and
outside diameter of all pipes for determination of types of fittings to be used. The
CONTRACTOR shall coordinate all work with the DISTRICT's field representative.
CONTRACTOR shall verify the location and depth of all existing utilities affected by the
connection prior to the start of any of this Work. CONTRACTOR shall pothole and verify all
existing fittings and pipe configurations prior to scheduling a shutdown of the existing system
for connections.
Due to the nature of the site’s existing conditions it is possible that the existing force main
may be filled above the connection points to the existing force main. If this is the case the
CONTRACTOR will be required to pump the existing force main down to a level such that
when they cut into the existing force main at the lowest connection point no effluent is left in
the main so that zero spillage from the main occurs. No additional payment will be made for
pumping, trucking, or disposal of the effluent if this situation occurs. Any force main pumped
effluent may be transported to the nearest Soos Creek Water and Sewer District gravity
sewer manhole and disposed of there at no cost to the CONTRACTOR.
Rock Creek Culvert Replacement/Lincoln A - 2 June 3, 2021
Project Number: 13-3007.5
APPENDIX B
WASHINGTON STATE DEPARTMENT OF
FISH AND WILDLIFE HPA
PERMITTEE AUTHORIZED AGENT OR CONTRACTOR
City of Kent
ATTENTION: Stephen Lincoln
400 W Gowe St
Kent, WA 98032-6019
Project Name:Rock Creek Culvert Replacement at Summit Landsburg Road
Project Description:The project intends to remove the existing Rock Creek Culvert at Summit-Landsburg Road,
replace it with a bridge, and restore the original Rock Creek Stream Bed in order to restore
Salmon access to Rock Creek upstream of Summit Landsburg Road.
PROVISIONS
TIMING - PLANS - INVASIVE SPECIES CONTROL
1. TIMING LIMITATION: You may begin the project immediately and you must complete the project by October 22,
2025, provided work within the wetted perimeter of Rock Creek must occur only between June 16 and August 31.
2. APPROVED PLANS: You must accomplish the work per plans and specifications submitted with the application and
approved by the Washington Department of Fish and Wildlife entitled, "SUMMIT LANDSBURG ROAD AND ROCK
CREEK CULVERT REPLACEMENT", dated October 12, 2020, except as modified by this Hydraulic Project Approval
(HPA). You must have a copy of these plans and this HPA available on site during all phases of the project
construction.
3. INVASIVE SPECIES CONTROL: Thoroughly clean all equipment and gear before arriving and leaving the job site to
prevent the transport and introduction of aquatic invasive species. Properly dispose of any water and chemicals used to
clean gear and equipment. You can find additional information in the Washington Department of Fish and Wildlife's
Invasive Species Management Protocols (November 2012), available online at
http://wdfw.wa.gov/publications/01490/wdfw01490.pdf.
NOTIFICATION REQUIREMENTS
4. PRE-, DURING, AND POST-CONSTRUCTION NOTIFICATION: You, your agent, or contractor must contact the
Washington Department of Fish and Wildlife by e-mail to larry.fisher@dfw.wa.gov and to
HPAapplications@dfw.wa.gov; mail to Post Office Box 43234, Olympia, Washington 98504-3234; or fax to (360) 902-
2946 at least three business days before starting work, one day before removing the temporary bypass and again
within seven days after completing the work. The notification must include the permittee's name, project location,
starting date for work or date the work was completed, and the permit number. The Washington Department of Fish
and Wildlife may conduct inspections during and after construction; however, the Washington Department of Fish and
Wildlife will notify you or your agent before conducting the inspection.
5. PHOTOGRAPHS: You, your agent, or contractor must take photographs of the job site before the work begins and
after the work is completed. You must upload the photographs to the post-permit requirement page in the Aquatic
Protection Permitting System (APPS) or mail them to Washington Department of Fish and Wildlife at Post Office Box
43234, Olympia, Washington 98504-3234 within 30-days after the work is completed.
6. FISH KILL/ WATER QUALITY PROBLEM NOTIFICATION: If a fish kill occurs or fish are observed in distress at the
Page 1 of 7
HYDRAULIC PROJECT APPROVAL
Washington Department of
Fish & Wildlife
PO Box 43234
Olympia, WA 98504-3234
(360) 902-2200
Permit Number: 2020-4-842+01
FPA/Public Notice Number: N/A
Application ID: 21610
Project End Date: October 22, 2025
Issued Date: October 23, 2020
job site, immediately stop all activities causing harm. Immediately notify the Washington Department of Fish and
Wildlife Habitat Biologist at 425-449-6790 of the problem. If the likely cause of the fish kill or fish distress is related to
water quality, also notify the Washington Military Department Emergency Management Division at 1-800-258-5990.
Activities related to the fish kill or fish distress must not resume until the Washington Department of Fish and Wildlife
gives approval. The Washington Department of Fish and Wildlife may require additional measures to mitigate impacts.
STAGING, JOB SITE ACCESS, AND EQUIPMENT
7. Establish staging areas (used for equipment storage, vehicle storage, fueling, servicing, and hazardous material
storage) in a location and manner that will prevent contaminants such as petroleum products, hydraulic fluid, fresh
concrete, sediments, sediment-laden water, chemicals, or any other toxic or harmful materials from entering waters of
the state.
8. Clearly mark boundaries to establish the limit of work associated with site access and construction.
9. This HPA authorizes only the removal of the large woody vegetation shown in the approved plan. Clearly mark all
large woody vegetation authorized for removal before starting work.
10. Retain all natural habitat features on the bed or banks including large woody material and boulders. You may move
these natural habitat features during construction but you must place them near the preproject location before leaving
the job site.
11. Confine the use of equipment to the specific access and work corridor shown in the approved plans.
12. Check equipment daily for leaks and complete any required repairs in an upland location before using the
equipment in or near the water.
13. Use environmentally acceptable lubricants composed of biodegradable base oils such as vegetable oils, synthetic
esters, and polyalkylene glycols in equipment operated in or near the water.
CONSTRUCTION-RELATED SEDIMENT, EROSION AND POLLUTION CONTAINMENT
14. Work in the dry watercourse (when no natural flow is occurring in the channel, or when flow is diverted around or
through the job site).
15. Protect all disturbed areas from erosion. Maintain erosion and sediment control until all work and cleanup of the job
site is complete.
16. All erosion control materials that will remain onsite must be composed of 100% biodegradable materials.
17. Straw used for erosion and sediment control, must be certified free of noxious weeds and their seeds.
18. Stop all hydraulic project activities except those needed to control erosion and siltation, if flow conditions arise that
will result in erosion or siltation of waters of the state.
19. Prevent project contaminants, such as petroleum products, hydraulic fluid, fresh concrete, sediments, sediment-
laden water, chemicals, or any other toxic or harmful materials, from entering or leaching into waters of the state.
20. Route construction water (wastewater) from the project to an upland area above the limits of anticipated floodwater.
Remove fine sediment and other contaminants before discharging the construction water to waters of the state.
21. Deposit waste material from the project, such as construction debris, silt, excess dirt, or overburden, in an upland
area above the limits of anticipated floodwater unless the material is approved by the Washington Department of Fish
and Wildlife for reuse in the project.
22. Deposit all trash from the project at an appropriate upland disposal location.
CONSTRUCTION MATERIALS
23. Store all construction and deconstruction material in a location and manner that will prevent contaminants such as
petroleum products, hydraulic fluid, fresh cement, sediments, sediment-laden water, chemicals, or any other toxic or
harmful materials from entering waters of the state.
Page 2 of 7
HYDRAULIC PROJECT APPROVAL
Washington Department of
Fish & Wildlife
PO Box 43234
Olympia, WA 98504-3234
(360) 902-2200
Permit Number: 2020-4-842+01
FPA/Public Notice Number: N/A
Application ID: 21610
Project End Date: October 22, 2025
Issued Date: October 23, 2020
24. Do not stockpile construction material waterward of the ordinary high water line.
25. Use only clean, suitable material as fill material (no trash, debris, car bodies, tires, asphalt, concrete, etc.).
IN-WATER WORK AREA ISOLATION USING A TEMPORARY BYPASS
26. Isolate flows from the work areas by using either a total or partial bypass or coffer dam to reroute the stream flows.
27. Sequence the work to minimize the duration of dewatering.
28. Use the least-impacting feasible method to temporarily isolate water from the work areas. Consider the physical
characteristics of the site and the anticipated volume of water flowing through the work area.
29. The hydraulic capacity of a stream bypass must be equal to or greater than the 25-year peak flow event expected
when the bypass will be operated.
30. Design the temporary bypass to minimize the length of the dewatered stream channel.
31. During all phases of bypass installation and decommissioning, maintain flows downstream of the project site to
ensure survival of all downstream fish.
32. Install the temporary bypass before starting other construction work in the wetted perimeter.
33. Install a cofferdam or similar device at the upstream and downstream end of the bypass to prevent backwater from
entering the work area.
34. Return diverted water to the channel immediately downstream of the work area. Dissipate flow energy from the
diversion to prevent scour or erosion of the channel and bank.
35. If the diversion inlet is a gravity diversion that provides fish passage, place the diversion outlet where it facilitates
gradual and safe reentry of fish into the stream channel.
36. If the bypass is a pumped diversion, once started it must run continuously until it is no longer necessary to bypass
flows. This requires back-up pumps on-site and twenty-four-hour monitoring for overnight operation.
37. If the diversion inlet is a pump diversion in a fish-bearing stream, the pump intake structure must have a fish screen
installed, operated, and maintained in accordance with RCW 77.57.010 and 77.57.070. Screen the pump intake with
one of the following:
a) Perforated plate: 0.094 inch (maximum opening diameter);
b) Profile bar: 0.069 inch (maximum width opening); or
c) Woven wire: 0.087 inch (maximum opening in the narrow direction).
The minimum open area for all types of fish screens is twenty-seven percent. The screened intake facility must have
enough surface area to ensure that the velocity through the screen is less than 0.4 feet per second. Maintain fish
screens to prevent injury or entrapment of fish.
38. The fish screen must remain in place whenever water is withdrawn from the stream through the pump intake.
39. Remove fish screens on dewatering pumps in the isolated work area only after all fish are safe and excluded from
the work area.
40. Isolate pump hose intakes with block nets so that fish cannot get near the intake.
FISH LIFE REMOVAL
41. All persons participating in capture and removal must have training, knowledge, and skills in the safe handling of
fish life.
42. If electrofishing is conducted, a person with electrofishing training must be on-site to conduct or direct all
electrofishing activities.
43. Place block nets upstream and downstream of the in-water work area before capturing and removing fish life.
44. Capture and safely move fish life from the work area to the nearest suitable free-flowing water.
Page 3 of 7
HYDRAULIC PROJECT APPROVAL
Washington Department of
Fish & Wildlife
PO Box 43234
Olympia, WA 98504-3234
(360) 902-2200
Permit Number: 2020-4-842+01
FPA/Public Notice Number: N/A
Application ID: 21610
Project End Date: October 22, 2025
Issued Date: October 23, 2020
LOCATION #1:Site Name: Summit-Landsburg Rd Rcok Creek
, Kent, WA 98051
WORK START:October 23, 2020 WORK END:October 22, 2025
WRIA Waterbody:Tributary to:
08 - Cedar - Sammamish Rock Creek Cedar River
1/4 SEC:Section:Township:Range:Latitude:Longitude:County:
BRIDGE
45. Design and construct the bridge to pass water, ice, large wood, and associated woody material and sediment likely
to move under the bridge during the 100-year flood flows.
46. The authorized water crossing structure is a full span bridge with a 53.5 foot clear span, a length of 35.1 feet, and a
minimum three feet of clearance above the 100 year flood elevation.
47. Embed the top of bridge footings well below potential local scour depth to prevent exposure of the footing surface
and undermining.
48. Protect structural fill associated with the bridge installation from erosion to the 100-year peak flow.
LARGE WOODY MATERIAL
49. Place large woody material consistent with natural stream processes waterward of the ordinary high water line as
shown in the approved plans (Provision 2).
50. Use fir, cedar, or other coniferous species to construct the large wood fish habitat structures, and secure them in a
manner to withstand a 100 year flood event.
DEMOBILIZATION AND CLEANUP
51. Do not relocate removed or replaced structures within waters of the state. Remove and dispose of these structures
in an upland area above the limits of anticipated floodwater.
52. Upon completion of the project, restore the disturbed bed, banks, and riparian zone to preproject condition to the
extent possible.
53. To minimize sediment delivery to the stream or stream channel, do not return in-stream flows to the work area until
all in-channel work is completed and the bed and banks are stabilized.
54. Seed areas disturbed by construction activities with a native seed mix suitable for the site that has at least one
quick-establishing plant species.
55. Replace native riparian zone vegetation damaged or destroyed by construction with native trees and native shrubs.
Plant trees 10 feet on center, and shrubs five feet on center. Complete installation of the restoration plants prior to the
end of the first dormant season (late fall through late winter) after installation of the water crossing structure per the
approved plan (Provision 2). Maintain plantings for at least three years to ensure at least eighty percent survival of each
species or a contingency species approved by the Habitat Biologist. Failure to achieve the eighty percent survival in
year three will require you to submit a plan with follow-up measures to achieve requirements or reasons to modify
requirements.
56. Upon completion of the project, remove all materials or equipment from the site and dispose of all excess spoils
and waste materials in an upland area above the limits of anticipated floodwater.
Page 4 of 7
HYDRAULIC PROJECT APPROVAL
Washington Department of
Fish & Wildlife
PO Box 43234
Olympia, WA 98504-3234
(360) 902-2200
Permit Number: 2020-4-842+01
FPA/Public Notice Number: N/A
Application ID: 21610
Project End Date: October 22, 2025
Issued Date: October 23, 2020
APPLY TO ALL HYDRAULIC PROJECT APPROVALS
This Hydraulic Project Approval pertains only to those requirements of the Washington State Hydraulic Code,
specifically Chapter 77.55 RCW. Additional authorization from other public agencies may be necessary for this project.
The person(s) to whom this Hydraulic Project Approval is issued is responsible for applying for and obtaining any
additional authorization from other public agencies (local, state and/or federal) that may be necessary for this project.
This Hydraulic Project Approval shall be available on the job site at all times and all its provisions followed by the person
(s) to whom this Hydraulic Project Approval is issued and operator(s) performing the work.
This Hydraulic Project Approval does not authorize trespass.
The person(s) to whom this Hydraulic Project Approval is issued and operator(s) performing the work may be held liable
for any loss or damage to fish life or fish habitat that results from failure to comply with the provisions of this Hydraulic
Project Approval.
Failure to comply with the provisions of this Hydraulic Project Approval could result in civil action against you, including,
but not limited to, a stop work order or notice to comply, and/or a gross misdemeanor criminal charge, possibly
punishable by fine and/or imprisonment.
All Hydraulic Project Approvals issued under RCW 77.55.021 are subject to additional restrictions, conditions, or
revocation if the Department of Fish and Wildlife determines that changed conditions require such action. The person(s)
to whom this Hydraulic Project Approval is issued has the right to appeal those decisions. Procedures for filing appeals
are listed below.
W 1/2 26 22 N 06 E 47.3662 -122.0138 King
Location #1 Driving Directions
5p. Provide driving directions from the closest highway to the project location, and attach a map. [help]
From Northbound Interstate 405 take exit 4 to WA SR-169 S towards maple valley for 14 miles, turn left onto Kent-Kangley
Road for 0.2 Miles, Turn Left onto Summit-Landsburg Road and proceed for 0.25 miles.
Page 5 of 7
HYDRAULIC PROJECT APPROVAL
Washington Department of
Fish & Wildlife
PO Box 43234
Olympia, WA 98504-3234
(360) 902-2200
Permit Number: 2020-4-842+01
FPA/Public Notice Number: N/A
Application ID: 21610
Project End Date: October 22, 2025
Issued Date: October 23, 2020
MINOR MODIFICATIONS TO THIS HPA: You may request approval of minor modifications to the required work timing
or to the plans and specifications approved in this HPA unless this is a General HPA. If this is a General HPA you must
use the Major Modification process described below. Any approved minor modification will require issuance of a letter
documenting the approval. A minor modification to the required work timing means any change to the work start or end
dates of the current work season to enable project or work phase completion. Minor modifications will be approved only
if spawning or incubating fish are not present within the vicinity of the project. You may request subsequent minor
modifications to the required work timing. A minor modification of the plans and specifications means any changes in the
materials, characteristics or construction of your project that does not alter the project's impact to fish life or habitat and
does not require a change in the provisions of the HPA to mitigate the impacts of the modification. If you originally
applied for your HPA through the online Aquatic Protection Permitting System (APPS), you may request a minor
modification through APPS. A link to APPS is at http://wdfw.wa.gov/licensing/hpa/. If you did not use APPS you must
submit a written request that clearly indicates you are seeking a minor modification to an existing HPA. Written requests
must include the name of the applicant, the name of the authorized agent if one is acting for the applicant, the APP ID
number of the HPA, the date issued, the permitting biologist, the requested changes to the HPA, the reason for the
requested change, the date of the request, and the requestor's signature. Send by mail to: Washington Department of
Fish and Wildlife, PO Box 43234, Olympia, Washington 98504-3234, or by email to HPAapplications@dfw.wa.gov. You
should allow up to 45 days for the department to process your request.
MAJOR MODIFICATIONS TO THIS HPA: You may request approval of major modifications to any aspect of your HPA.
Any approved change other than a minor modification to your HPA will require issuance of a new HPA. If you originally
applied for your HPA through the online Aquatic Protection Permitting System (APPS), you may request a major
modification through APPS. A link to APPS is at http://wdfw.wa.gov/licensing/hpa/. If you did not use APPS you must
submit a written request that clearly indicates you are requesting a major modification to an existing HPA. Written
requests must include the name of the applicant, the name of the authorized agent if one is acting for the applicant, the
APP ID number of the HPA, the date issued, the permitting biologist, the requested changes to the HPA, the reason for
the requested change, the date of the request, and the requestor's signature. Send your written request by mail to:
Washington Department of Fish and Wildlife, PO Box 43234, Olympia, Washington 98504-3234. You may email your
request for a major modification to HPAapplications@dfw.wa.gov. You should allow up to 45 days for the department to
process your request.
APPEALS INFORMATION
If you wish to appeal the issuance, denial, conditioning, or modification of a Hydraulic Project Approval (HPA),
Washington Department of Fish and Wildlife (WDFW) recommends that you first contact the department employee who
issued or denied the HPA to discuss your concerns. Such a discussion may resolve your concerns without the need for
further appeal action. If you proceed with an appeal, you may request an informal or formal appeal. WDFW encourages
you to take advantage of the informal appeal process before initiating a formal appeal. The informal appeal process
includes a review by department management of the HPA or denial and often resolves issues faster and with less legal
complexity than the formal appeal process. If the informal appeal process does not resolve your concerns, you may
advance your appeal to the formal process. You may contact the HPA Appeals Coordinator at (360) 902-2534 for more
information.
A. INFORMAL APPEALS: WAC 220-660-460 is the rule describing how to request an informal appeal of WDFW actions
taken under Chapter 77.55 RCW. Please refer to that rule for complete informal appeal procedures. The following
information summarizes that rule.
Page 6 of 7
HYDRAULIC PROJECT APPROVAL
Washington Department of
Fish & Wildlife
PO Box 43234
Olympia, WA 98504-3234
(360) 902-2200
Permit Number: 2020-4-842+01
FPA/Public Notice Number: N/A
Application ID: 21610
Project End Date: October 22, 2025
Issued Date: October 23, 2020
A person who is aggrieved by the issuance, denial, conditioning, or modification of an HPA may request an informal
appeal of that action. You must send your request to WDFW by mail to the HPA Appeals Coordinator, Department of
Fish and Wildlife, Habitat Program, PO Box 43234, Olympia, Washington 98504-3234; e-mail to
HPAapplications@dfw.wa.gov; fax to (360) 902-2946; or hand-delivery to the Natural Resources Building, 1111
Washington St SE, Habitat Program, Fifth floor. WDFW must receive your request within 30 days from the date you
receive notice of the decision. If you agree, and you applied for the HPA, resolution of the appeal may be facilitated
through an informal conference with the WDFW employee responsible for the decision and a supervisor. If a resolution
is not reached through the informal conference, or you are not the person who applied for the HPA, the HPA Appeals
Coordinator or designee may conduct an informal hearing or review and recommend a decision to the Director or
designee. If you are not satisfied with the results of the informal appeal, you may file a request for a formal appeal.
B. FORMAL APPEALS: WAC 220-660-470 is the rule describing how to request a formal appeal of WDFW actions
taken under Chapter 77.55 RCW. Please refer to that rule for complete formal appeal procedures. The following
information summarizes that rule.
A person who is aggrieved by the issuance, denial, conditioning, or modification of an HPA may request a formal appeal
of that action. You must send your request for a formal appeal to the clerk of the Pollution Control Hearings Boards and
serve a copy on WDFW within 30 days from the date you receive notice of the decision. You may serve WDFW by mail
to the HPA Appeals Coordinator, Department of Fish and Wildlife, Habitat Program, PO Box 43234, Olympia,
Washington 98504-3234; e-mail to HPAapplications@dfw.wa.gov; fax to (360) 902-2946; or hand-delivery to the Natural
Resources Building, 1111 Washington St SE, Habitat Program, Fifth floor. The time period for requesting a formal
appeal is suspended during consideration of a timely informal appeal. If there has been an informal appeal, you may
request a formal appeal within 30 days from the date you receive the Director's or designee's written decision in
response to the informal appeal.
C. FAILURE TO APPEAL WITHIN THE REQUIRED TIME PERIODS: If there is no timely request for an appeal, the
WDFW action shall be final and unappealable.
Habitat Biologist Larry.Fisher@dfw.wa.gov for Director
WDFWLarry Fisher 425-449-6790
Page 7 of 7
HYDRAULIC PROJECT APPROVAL
Washington Department of
Fish & Wildlife
PO Box 43234
Olympia, WA 98504-3234
(360) 902-2200
Permit Number: 2020-4-842+01
FPA/Public Notice Number: N/A
Application ID: 21610
Project End Date: October 22, 2025
Issued Date: October 23, 2020
Rock Creek Culvert Replacement/Lincoln A - 3 June 3, 2021
Project Number: 13-3007.5
APPENDIX C
UNITED STATES ARMY CORPS OF
ENGINEERS NATIONWIDE PERMIT
DEPARTMENT OF THE ARMY
CORPS OF ENGINEERS, SEATTLE DISTRICT
P.O. BOX 3755
SEATTLE, WASHINGTON 98124-3755
Regulatory Branch May 12, 2021
Mr. Stephen Lincoln
City of Kent
400 West Gowe Street
Kent, Washington 98032
Reference: NWS-2020-526
Kent, City of
(Rock Creek Culvert
Replacement)
Dear Mr. Lincoln:
We have reviewed your application to discharge up to 130 cubic yards of fill in 0.04 acre of
stream to replace a 36-inch diameter corrugated metal pipe culvert with a 54-foot long by 35-foot
wide by 6-inch foot high bridge in Rock Creek near Enumclaw, King County, Washington.
Based on the information you provided to us, Nationwide Permit (NWP) 14, Linear
Transportation Projects (Federal Register January 6, 2017, Vol. 82, No. 4), authorizes your
proposal as depicted on the enclosed drawings dated March 02, 2020.
In order for this authorization to be valid, you must ensure the work is performed in
accordance with the enclosed NWP 14, Terms and Conditions and the following special
conditions:
a. In order to meet the requirements of the Endangered Species Act (ESA) and Magnuson-
Stevens Fishery Conservation and Management Act (MSA) programmatic consultation Fish
Passage and Restoration Actions in Washington State (FPRP III) (National Marine Fisheries
Service (NMFS) Reference Number WCRO-2014-00004), you must implement and abide by the
ESA requirements and/or agreements set forth in the Biological Opinion (BO) dated June 21,
2017, and the Project Information Form dated September 16, 2020 in the enclosed document
Appendix A: FPRP III Guidelines and Implementation Forms (NMFS Reference Number
WCRO-2014-00004-2251). The BO is available on the U.S. Army Corps of Engineers (Corps)
website (Permit Guidebook, Endangered Species, Programmatic Consultations, Fish Passage and
Restoration Programmatic Consultations). Within 45 days of completing the permitted work in
waters of the U.S., you must provide the Corps the information requested in the FPRP Action
Completion Reporting Form in the enclosed document Appendix A: FPRP III Guidelines and
-2-
Implementation Forms. If fish salvage occurs as part of your project, you must also provide the
Corps the information requested in the FPRP Fish Salvage Reporting Form in the enclosed
document Appendix A: FPRP III Guidelines and Implementation Forms, within 45 days of
completing the permitted work in waters of the U.S. All information must prominently display
the reference number NWS-2020-526. Failure to comply with these requirements constitutes
non-compliance with the ESA and your Corps permit. The NMFS is the appropriate authority to
determine compliance with the terms and conditions of their BO and with the ESA. If you
cannot comply with the terms and conditions of this programmatic consultation, you must, prior
to commencing construction, contact the Corps, Seattle District, Regulatory Branch for an
individual consultation in accordance with the requirements of the ESA and/or the MSA.
b. Incidents where any individuals of fish species, marine mammals and/or sea turtles listed
by National Oceanic and Atmospheric Administration Fisheries (NOAA Fisheries) under the
Endangered Species Act appear to be injured or killed as a result of discharges of dredged or fill
material into waters of the U.S. or structures or work in navigable waters of the U.S. authorized
by this Nationwide Permit verification shall be reported to NOAA Fisheries, Office of Protected
Resources at (301) 713-1401 and the Regulatory Office of the Seattle District of the U.S. Army
Corps of Engineers at (206) 764-3495. The finder should leave the animal alone, make note of
any circumstances likely causing the death or injury, note the location and number of individuals
involved and, if possible, take photographs. Adult animals should not be disturbed unless
circumstances arise where they are obviously injured or killed by discharge exposure or some
unnatural cause. The finder may be asked to carry out instructions provided by NOAA Fisheries
to collect specimens or take other measures to ensure that evidence intrinsic to the specimen is
preserved.
c. In order to meet the requirements of the Endangered Species Act (ESA) 2008 Fish
Passage and Restoration Programmatic Consultation (U.S. Fish and Wildlife Service (USFWS)
Reference Number 1341-2008-FWS-#F-0209), you must comply with the conditions included in
the Biological Evaluation, dated September 16, 2020 (USFWS Reference Number 01EWFW00-
2020-TA-1703). If you cannot comply with the terms and conditions of this programmatic
consultation, you must, prior to commencing construction, contact the U.S. Army Corps of
Engineers, Seattle District, Regulatory Branch for an individual consultation in accordance with
the requirements of the ESA.
d. In order to meet the requirements of the Endangered Species Act you may conduct the
authorized activities from June 15th through September 30th in any year this permit is valid. You
shall not conduct work authorized by this permit from October 1st through June 14th in any year
this permit is valid.
-3-
We have reviewed your project pursuant to the requirements of the Endangered Species Act,
the Magnuson-Stevens Fishery Conservation and Management Act and the National Historic
Preservation Act. We have determined this project complies with the requirements of these laws
provided you comply with all of the permit general and special conditions.
Please be reminded that Special Condition “a” of your permit requires that you implement
and abide by the Endangered Species Act (ESA) requirements set forth in the programmatic
Biological Opinion (BO) for this project. In particular, within 45 days of project completion,
you must provide the Action Completion Reporting Form and Fish Salvage Reporting Form, as
described in the BO.
The authorized work complies with the Washington State Department of Ecology’s
(Ecology) Water Quality Certification (WQC) requirements and Coastal Zone Management
(CZM) consistency determination response for this NWP. No further coordination with Ecology
for WQC and CZM is required.
You have not requested a jurisdictional determination for this proposed project. If you
believe the U.S. Army Corps of Engineers does not have jurisdiction over all or portions of your
project you may request a preliminary or approved jurisdictional determination (JD). If one is
requested, please be aware that we may require the submittal of additional information to
complete the JD and work authorized in this letter may not occur until the JD has been
completed.
Our verification of this 2017 NWP authorization is valid until March 18, 2022, unless the
NWP is modified, reissued, or revoked prior to that date. If the authorized work for the 2017
NWP authorization has not been completed by that date and you have commenced or are under
contract to commence this activity before March 18, 2022, you will have until March 18, 2023,
to complete the activity under the enclosed terms and conditions of this NWP. Failure to comply
with all terms and conditions of this NWP verification invalidates this authorization and could
result in a violation of Section 404 of the Clean Water Act. You must also obtain all local, State,
and other Federal permits that apply to this project.
-4-
Upon completing the authorized work, you must fill out and return the enclosed Certificate
of Compliance with Department of the Army Permit. All compliance reports should be submitted
to the U.S. Army Corps of Engineers, Seattle District, Regulatory Branch electronically at
nws.compliance@usace.army.mil. Thank you for your cooperation during the permitting
process. We are interested in your experience with our Regulatory Program and encourage you
to complete a customer service survey. Referenced documents and information about our
program are available on our website at www.nws.usace.army.mil, select “Regulatory Permit
Information”. If you have any questions, please contact me at
kristin.l.mcdermott@usace.army.mil or (206) 316-3975.
Sincerely,
Kristin McDermott, Project Manager
Regulatory Branch
Enclosures
cc:
Washington Department of Ecology at ecyrefedpermits@ecy.wa.gov
NATIONWIDE PERMIT 14
Terms and Conditions
Effective Date: March 19, 2017
A. Description of Authorized Activities
B. U.S. Army Corps of Engineers (Corps) National General Conditions for all NWPs
C. Corps Seattle District Regional General Conditions
D. Corps Regional Specific Conditions for this NWP
E. Washington Department of Ecology (Ecology) Section 401 Water Quality Certification (401
Certification): General Conditions
F. Ecology 401 Certification: Specific Conditions for this NWP
G. Coastal Zone Management Consistency Response for this NWP
In addition to any special condition that may be required on a case-by-case basis by the District Engineer,
the following terms and conditions must be met, as applicable, for a Nationwide Permit (NWP)
authorization to be valid in Washington State.
A. DESCRIPTION OF AUTHORIZED ACTIVITIES
Linear Transportation Projects. Activities required for crossings of waters of the United States associated
with the construction, expansion, modification, or improvement of linear transportation projects (e.g.,
roads, highways, railways, trails, airport runways, and taxiways) in waters of the United States. For linear
transportation projects in non-tidal waters, the discharge cannot cause the loss of greater than 1/2-acre of
waters of the United States. For linear transportation projects in tidal waters, the discharge cannot cause
the loss of greater than 1/3-acre of waters of the United States. Any stream channel modification,
including bank stabilization, is limited to the minimum necessary to construct or protect the linear
transportation project; such modifications must be in the immediate vicinity of the project.
This NWP also authorizes temporary structures, fills, and work, including the use of temporary mats,
necessary to construct the linear transportation project. Appropriate measures must be taken to maintain
normal downstream flows and minimize flooding to the maximum extent practicable, when temporary
structures, work, and discharges, including cofferdams, are necessary for construction activities, access
fills, or dewatering of construction sites. Temporary fills must consist of materials, and be placed in a
manner, that will not be eroded by expected high flows. Temporary fills must be removed in their entirety
and the affected areas returned to pre-construction elevations. The areas affected by temporary fills must
be revegetated, as appropriate.
This NWP cannot be used to authorize non-linear features commonly associated with transportation
projects, such as vehicle maintenance or storage buildings, parking lots, train stations, or aircraft hangars.
Notification: The permittee must submit a pre-construction notification to the district engineer prior to
commencing the activity if: (1) the loss of waters of the United States exceeds 1/10-acre; or (2) there is a
discharge in a special aquatic site, including wetlands. (See general condition 32.) (Authorities: Sections
10 and 404)
Note 1: For linear transportation projects crossing a single waterbody more than one time at separate and
distant locations, or multiple waterbodies at separate and distant locations, each crossing is considered a
single and complete project for purposes of NWP authorization. Linear transportation projects must
comply with 33 CFR 330.6(d). Note 2: Some discharges for the construction of farm roads or forest
2
roads, or temporary roads for moving mining equipment, may qualify for an exemption under section
404(f) of the Clean Water Act (see 33 CFR 323.4). Note 3: For NWP 14 activities that require pre-
construction notification, the PCN must include any other NWP(s), regional general permit(s), or
individual permit(s) used or intended to be used to authorize any part of the proposed project or any
related activity, including other separate and distant crossings that require Department of the Army
authorization but do not require pre-construction notification (see paragraph (b) of general condition 32).
The district engineer will evaluate the PCN in accordance with Section D, “District Engineer’s Decision.”
The district engineer may require mitigation to ensure that the authorized activity results in no more than
minimal individual and cumulative adverse environmental effects (see general condition 23).
B. CORPS NATIONAL GENERAL CONDITIONS FOR ALL NWPs
To qualify for NWP authorization, the prospective permittee must comply with the following general
conditions, as applicable, in addition to any regional or case-specific conditions imposed by the division
engineer or district engineer. Every person who may wish to obtain permit authorization under one or
more NWPs, or who is currently relying on an existing or prior permit authorization under one or more
NWPs, has been and is on notice that all of the provisions of 33 CFR 330.1 through 330.6 apply to every
NWP authorization. Note especially 33 CFR 330.5 relating to the modification, suspension, or revocation
of any NWP authorization.
1. Navigation. (a) No activity may cause more than a minimal adverse effect on navigation. (b) Any
safety lights and signals prescribed by the U.S. Coast Guard, through regulations or otherwise, must be
installed and maintained at the permittee's expense on authorized facilities in navigable waters of the
United States. (c) The permittee understands and agrees that, if future operations by the United States
require the removal, relocation, or other alteration, of the structure or work herein authorized, or if, in the
opinion of the Secretary of the Army or his authorized representative, said structure or work shall cause
unreasonable obstruction to the free navigation of the navigable waters, the permittee will be required,
upon due notice from the Corps of Engineers, to remove, relocate, or alter the structural work or
obstructions caused thereby, without expense to the United States. No claim shall be made against the
United States on account of any such removal or alteration.
2. Aquatic Life Movements. No activity may substantially disrupt the necessary life cycle movements of
those species of aquatic life indigenous to the waterbody, including those species that normally migrate
through the area, unless the activity's primary purpose is to impound water. All permanent and temporary
crossings of waterbodies shall be suitably culverted, bridged, or otherwise designed and constructed to
maintain low flows to sustain the movement of those aquatic species. If a bottomless culvert cannot be
used, then the crossing should be designed and constructed to minimize adverse effects to aquatic life
movements.
3. Spawning Areas. Activities in spawning areas during spawning seasons must be avoided to the
maximum extent practicable. Activities that result in the physical destruction (e.g., through excavation,
fill, or downstream smothering by substantial turbidity) of an important spawning area are not authorized.
4. Migratory Bird Breeding Areas. Activities in waters of the United States that serve as breeding areas
for migratory birds must be avoided to the maximum extent practicable.
5. Shellfish Beds. No activity may occur in areas of concentrated shellfish populations, unless the activity
is directly related to a shellfish harvesting activity authorized by NWPs 4 and 48, or is a shellfish seeding
or habitat restoration activity authorized by NWP 27.
3
6. Suitable Material. No activity may use unsuitable material (e.g., trash, debris, car bodies, asphalt, etc.).
Material used for construction or discharged must be free from toxic pollutants in toxic amounts (see
section 307 of the Clean Water Act).
7. Water Supply Intakes. No activity may occur in the proximity of a public water supply intake, except
where the activity is for the repair or improvement of public water supply intake structures or adjacent
bank stabilization.
8. Adverse Effects From Impoundments. If the activity creates an impoundment of water, adverse effects
to the aquatic system due to accelerating the passage of water, and/or restricting its flow must be
minimized to the maximum extent practicable.
9. Management of Water Flows. To the maximum extent practicable, the pre-construction course,
condition, capacity, and location of open waters must be maintained for each activity, including stream
channelization, storm water management activities, and temporary and permanent road crossings, except
as provided below. The activity must be constructed to withstand expected high flows. The activity must
not restrict or impede the passage of normal or high flows, unless the primary purpose of the activity is to
impound water or manage high flows. The activity may alter the pre-construction course, condition,
capacity, and location of open waters if it benefits the aquatic environment (e.g., stream restoration or
relocation activities).
10. Fills Within 100-Year Floodplains. The activity must comply with applicable FEMA-approved state
or local floodplain management requirements.
11. Equipment. Heavy equipment working in wetlands or mudflats must be placed on mats, or other
measures must be taken to minimize soil disturbance.
12. Soil Erosion and Sediment Controls. Appropriate soil erosion and sediment controls must be used and
maintained in effective operating condition during construction, and all exposed soil and other fills, as
well as any work below the ordinary high water mark or high tide line, must be permanently stabilized at
the earliest practicable date. Permittees are encouraged to perform work within waters of the United
States during periods of low-flow or no-flow, or during low tides.
13. Removal of Temporary Fills. Temporary fills must be removed in their entirety and the affected areas
returned to pre-construction elevations. The affected areas must be revegetated, as appropriate.
14. Proper Maintenance. Any authorized structure or fill shall be properly maintained, including
maintenance to ensure public safety and compliance with applicable NWP general conditions, as well as
any activity-specific conditions added by the district engineer to an NWP authorization.
15. Single and Complete Project. The activity must be a single and complete project. The same NWP
cannot be used more than once for the same single and complete project.
16. Wild and Scenic Rivers. (a) No NWP activity may occur in a component of the National Wild and
Scenic River System, or in a river officially designated by Congress as a “study river” for possible
inclusion in the system while the river is in an official study status, unless the appropriate Federal agency
with direct management responsibility for such river, has determined in writing that the proposed activity
will not adversely affect the Wild and Scenic River designation or study status. (b) If a proposed NWP
activity will occur in a component of the National Wild and Scenic River System, or in a river officially
designated by Congress as a “study river” for possible inclusion in the system while the river is in an
official study status, the permittee must submit a pre-construction notification (see general condition 32).
The district engineer will coordinate the PCN with the Federal agency with direct management
4
responsibility for that river. The permittee shall not begin the NWP activity until notified by the district
engineer that the Federal agency with direct management responsibility for that river has determined in
writing that the proposed NWP activity will not adversely affect the Wild and Scenic River designation or
study status. (c) Information on Wild and Scenic Rivers may be obtained from the appropriate Federal
land management agency responsible for the designated Wild and Scenic River or study river (e.g.,
National Park Service, U.S. Forest Service, Bureau of Land Management, U.S. Fish and Wildlife
Service). Information on these rivers is also available at: http://www.rivers.gov/.
17. Tribal Rights. No NWP activity may cause more than minimal adverse effects on tribal rights
(including treaty rights), protected tribal resources, or tribal lands.
18. Endangered Species. (a) No activity is authorized under any NWP which is likely to directly or
indirectly jeopardize the continued existence of a threatened or endangered species or a species proposed
for such designation, as identified under the Federal Endangered Species Act (ESA), or which will
directly or indirectly destroy or adversely modify the critical habitat of such species. No activity is
authorized under any NWP which “may affect” a listed species or critical habitat, unless ESA section 7
consultation addressing the effects of the proposed activity has been completed. Direct effects are the
immediate effects on listed species and critical habitat caused by the NWP activity. Indirect effects are
those effects on listed species and critical habitat that are caused by the NWP activity and are later in
time, but still are reasonably certain to occur. (b) Federal agencies should follow their own procedures for
complying with the requirements of the ESA. If pre-construction notification is required for the proposed
activity, the Federal permittee must provide the district engineer with the appropriate documentation to
demonstrate compliance with those requirements. The district engineer will verify that the appropriate
documentation has been submitted. If the appropriate documentation has not been submitted, additional
ESA section 7 consultation may be necessary for the activity and the respective federal agency would be
responsible for fulfilling its obligation under section 7 of the ESA. (c) Non-federal permittees must
submit a pre-construction notification to the district engineer if any listed species or designated critical
habitat might be affected or is in the vicinity of the activity, or if the activity is located in designated
critical habitat, and shall not begin work on the activity until notified by the district engineer that the
requirements of the ESA have been satisfied and that the activity is authorized. For activities that might
affect Federally-listed endangered or threatened species or designated critical habitat, the pre-construction
notification must include the name(s) of the endangered or threatened species that might be affected by
the proposed activity or that utilize the designated critical habitat that might be affected by the proposed
activity. The district engineer will determine whether the proposed activity “may affect” or will have “no
effect” to listed species and designated critical habitat and will notify the non-Federal applicant of the
Corps’ determination within 45 days of receipt of a complete pre-construction notification. In cases where
the non-Federal applicant has identified listed species or critical habitat that might be affected or is in the
vicinity of the activity, and has so notified the Corps, the applicant shall not begin work until the Corps
has provided notification that the proposed activity will have “no effect” on listed species or critical
habitat, or until ESA section 7 consultation has been completed. If the non-Federal applicant has not
heard back from the Corps within 45 days, the applicant must still wait for notification from the Corps.
(d) As a result of formal or informal consultation with the FWS or NMFS the district engineer may add
species-specific permit conditions to the NWPs. (e) Authorization of an activity by an NWP does not
authorize the “take” of a threatened or endangered species as defined under the ESA. In the absence of
separate authorization (e.g., an ESA Section 10 Permit, a Biological Opinion with “incidental take”
provisions, etc.) from the FWS or the NMFS, the Endangered Species Act prohibits any person subject to
the jurisdiction of the United States to take a listed species, where "take" means to harass, harm, pursue,
hunt, shoot, wound, kill, trap, capture, or collect, or to attempt to engage in any such conduct. The word
“harm” in the definition of “take'' means an act which actually kills or injures wildlife. Such an act may
include significant habitat modification or degradation where it actually kills or injures wildlife by
significantly impairing essential behavioral patterns, including breeding, feeding or sheltering.
5
(f) If the non-federal permittee has a valid ESA section 10(a)(1)(B) incidental take permit with an
approved Habitat Conservation Plan for a project or a group of projects that includes the proposed NWP
activity, the non-federal applicant should provide a copy of that ESA section 10(a)(1)(B) permit with the
PCN required by paragraph (c) of this general condition. The district engineer will coordinate with the
agency that issued the ESA section 10(a)(1)(B) permit to determine whether the proposed NWP activity
and the associated incidental take were considered in the internal ESA section 7 consultation conducted
for the ESA section 10(a)(1)(B) permit. If that coordination results in concurrence from the agency that
the proposed NWP activity and the associated incidental take were considered in the internal ESA section
7 consultation for the ESA section 10(a)(1)(B) permit, the district engineer does not need to conduct a
separate ESA section 7 consultation for the proposed NWP activity. The district engineer will notify the
non-federal applicant within 45 days of receipt of a complete pre-construction notification whether the
ESA section 10(a)(1)(B) permit covers the proposed NWP activity or whether additional ESA section 7
consultation is required. (g) Information on the location of threatened and endangered species and their
critical habitat can be obtained directly from the offices of the FWS and NMFS or their world wide web
pages at http://www.fws.gov/ or http://www.fws.gov/ipac and http://www.nmfs.noaa.gov/pr/species/esa/
respectively.
19. Migratory Birds and Bald and Golden Eagles. The permittee is responsible for ensuring their action
complies with the Migratory Bird Treaty Act and the Bald and Golden Eagle Protection Act. The
permittee is responsible for contacting appropriate local office of the U.S. Fish and Wildlife Service to
determine applicable measures to reduce impacts to migratory birds or eagles, including whether
“incidental take” permits are necessary and available under the Migratory Bird Treaty Act or Bald and
Golden Eagle Protection Act for a particular activity.
20. Historic Properties. (a) In cases where the district engineer determines that the activity may have the
potential to cause effects to properties listed, or eligible for listing, in the National Register of Historic
Places, the activity is not authorized, until the requirements of Section 106 of the National Historic
Preservation Act (NHPA) have been satisfied. (b) Federal permittees should follow their own procedures
for complying with the requirements of section 106 of the National Historic Preservation Act. If pre-
construction notification is required for the proposed NWP activity, the Federal permittee must provide
the district engineer with the appropriate documentation to demonstrate compliance with those
requirements. The district engineer will verify that the appropriate documentation has been submitted. If
the appropriate documentation is not submitted, then additional consultation under section 106 may be
necessary. The respective federal agency is responsible for fulfilling its obligation to comply with section
106. (c) Non-federal permittees must submit a pre-construction notification to the district engineer if the
NWP activity might have the potential to cause effects to any historic properties listed on, determined to
be eligible for listing on, or potentially eligible for listing on the National Register of Historic Places,
including previously unidentified properties. For such activities, the pre-construction notification must
state which historic properties might have the potential to be affected by the proposed NWP activity or
include a vicinity map indicating the location of the historic properties or the potential for the presence of
historic properties. Assistance regarding information on the location of, or potential for, the presence of
historic properties can be sought from the State Historic Preservation Officer, Tribal Historic Preservation
Officer, or designated tribal representative, as appropriate, and the National Register of Historic Places
(see 33 CFR 330.4(g)). When reviewing pre-construction notifications, district engineers will comply
with the current procedures for addressing the requirements of section 106 of the National Historic
Preservation Act. The district engineer shall make a reasonable and good faith effort to carry out
appropriate identification efforts, which may include background research, consultation, oral history
interviews, sample field investigation, and field survey. Based on the information submitted in the PCN
and these identification efforts, the district engineer shall determine whether the proposed NWP activity
has the potential to cause effects on the historic properties. Section 106 consultation is not required when
the district engineer determines that the activity does not have the potential to cause effects on historic
properties (see 36 CFR 800.3(a)). Section 106 consultation is required when the district engineer
6
determines that the activity has the potential to cause effects on historic properties. The district engineer
will conduct consultation with consulting parties identified under 36 CFR 800.2(c) when he or she makes
any of the following effect determinations for the purposes of section 106 of the NHPA: no historic
properties affected, no adverse effect, or adverse effect. Where the non-Federal applicant has identified
historic properties on which the activity might have the potential to cause effects and so notified the
Corps, the non-Federal applicant shall not begin the activity until notified by the district engineer either
that the activity has no potential to cause effects to historic properties or that NHPA section 106
consultation has been completed. (d) For non-federal permittees, the district engineer will notify the
prospective permittee within 45 days of receipt of a complete pre-construction notification whether
NHPA section 106 consultation is required. If NHPA section 106 consultation is required, the district
engineer will notify the non-Federal applicant that he or she cannot begin the activity until section 106
consultation is completed. If the non-Federal applicant has not heard back from the Corps within 45 days,
the applicant must still wait for notification from the Corps. (e) Prospective permittees should be aware
that section 110k of the NHPA (54 U.S.C. 306113) prevents the Corps from granting a permit or other
assistance to an applicant who, with intent to avoid the requirements of section 106 of the NHPA, has
intentionally significantly adversely affected a historic property to which the permit would relate, or
having legal power to prevent it, allowed such significant adverse effect to occur, unless the Corps, after
consultation with the Advisory Council on Historic Preservation (ACHP), determines that circumstances
justify granting such assistance despite the adverse effect created or permitted by the applicant. If
circumstances justify granting the assistance, the Corps is required to notify the ACHP and provide
documentation specifying the circumstances, the degree of damage to the integrity of any historic
properties affected, and proposed mitigation. This documentation must include any views obtained from
the applicant, SHPO/THPO, appropriate Indian tribes if the undertaking occurs on or affects historic
properties on tribal lands or affects properties of interest to those tribes, and other parties known to have a
legitimate interest in the impacts to the permitted activity on historic properties.
21. Discovery of Previously Unknown Remains and Artifacts. If you discover any previously unknown
historic, cultural or archeological remains and artifacts while accomplishing the activity authorized by this
permit, you must immediately notify the district engineer of what you have found, and to the maximum
extent practicable, avoid construction activities that may affect the remains and artifacts until the required
coordination has been completed. The district engineer will initiate the Federal, Tribal, and state
coordination required to determine if the items or remains warrant a recovery effort or if the site is
eligible for listing in the National Register of Historic Places.
22. Designated Critical Resource Waters. Critical resource waters include, NOAA-managed marine
sanctuaries and marine monuments, and National Estuarine Research Reserves. The district engineer may
designate, after notice and opportunity for public comment, additional waters officially designated by a
state as having particular environmental or ecological significance, such as outstanding national resource
waters or state natural heritage sites. The district engineer may also designate additional critical resource
waters after notice and opportunity for public comment. (a) Discharges of dredged or fill material into
waters of the United States are not authorized by NWPs 7, 12, 14, 16, 17, 21, 29, 31, 35, 39, 40, 42, 43,
44, 49, 50, 51, and 52 for any activity within, or directly affecting, critical resource waters, including
wetlands adjacent to such waters. (b) For NWPs 3, 8, 10, 13, 15, 18, 19, 22, 23, 25, 27, 28, 30, 33, 34, 36,
37, 38, and 54, notification is required in accordance with general condition 32, for any activity proposed
in the designated critical resource waters including wetlands adjacent to those waters. The district
engineer may authorize activities under these NWPs only after it is determined that the impacts to the
critical resource waters will be no more than minimal.
23. Mitigation. The district engineer will consider the following factors when determining appropriate and
practicable mitigation necessary to ensure that the individual and cumulative adverse environmental
effects are no more than minimal: (a) The activity must be designed and constructed to avoid and
minimize adverse effects, both temporary and permanent, to waters of the United States to the maximum
7
extent practicable at the project site (i.e., on site). (b) Mitigation in all its forms (avoiding, minimizing,
rectifying, reducing, or compensating for resource losses) will be required to the extent necessary to
ensure that the individual and cumulative adverse environmental effects are no more than minimal.
(c) Compensatory mitigation at a minimum one-for-one ratio will be required for all wetland losses that
exceed 1/10-acre and require pre-construction notification, unless the district engineer determines in
writing that either some other form of mitigation would be more environmentally appropriate or the
adverse environmental effects of the proposed activity are no more than minimal, and provides an
activity-specific waiver of this requirement. For wetland losses of 1/10-acre or less that require pre-
construction notification, the district engineer may determine on a case-by-case basis that compensatory
mitigation is required to ensure that the activity results in only minimal adverse environmental effects.
(d) For losses of streams or other open waters that require pre-construction notification, the district
engineer may require compensatory mitigation to ensure that the activity results in no more than minimal
adverse environmental effects. Compensatory mitigation for losses of streams should be provided, if
practicable, through stream rehabilitation, enhancement, or preservation, since streams are difficult-to-
replace resources (see 33 CFR 332.3(e)(3)). (e) Compensatory mitigation plans for NWP activities in or
near streams or other open waters will normally include a requirement for the restoration or enhancement,
maintenance, and legal protection (e.g., conservation easements) of riparian areas next to open waters. In
some cases, the restoration or maintenance/protection of riparian areas may be the only compensatory
mitigation required. Restored riparian areas should consist of native species. The width of the required
riparian area will address documented water quality or aquatic habitat loss concerns. Normally, the
riparian area will be 25 to 50 feet wide on each side of the stream, but the district engineer may require
slightly wider riparian areas to address documented water quality or habitat loss concerns. If it is not
possible to restore or maintain/protect a riparian area on both sides of a stream, or if the waterbody is a
lake or coastal waters, then restoring or maintaining/protecting a riparian area along a single bank or
shoreline may be sufficient. Where both wetlands and open waters exist on the project site, the district
engineer will determine the appropriate compensatory mitigation (e.g., riparian areas and/or wetlands
compensation) based on what is best for the aquatic environment on a watershed basis. In cases where
riparian areas are determined to be the most appropriate form of minimization or compensatory
mitigation, the district engineer may waive or reduce the requirement to provide wetland compensatory
mitigation for wetland losses. (f) Compensatory mitigation projects provided to offset losses of aquatic
resources must comply with the applicable provisions of 33 CFR part 332.
(1) The prospective permittee is responsible for proposing an appropriate compensatory mitigation
option if compensatory mitigation is necessary to ensure that the activity results in no more than
minimal adverse environmental effects. For the NWPs, the preferred mechanism for providing
compensatory mitigation is mitigation bank credits or in-lieu fee program credits (see 33 CFR
332.3(b)(2) and (3)). However, if an appropriate number and type of mitigation bank or in-lieu credits
are not available at the time the PCN is submitted to the district engineer, the district engineer may
approve the use of permittee-responsible mitigation. (2) The amount of compensatory mitigation
required by the district engineer must be sufficient to ensure that the authorized activity results in no
more than minimal individual and cumulative adverse environmental effects (see 33 CFR
330.1(e)(3)). (See also 33 CFR 332.3(f)). (3) Since the likelihood of success is greater and the
impacts to potentially valuable uplands are reduced, aquatic resource restoration should be the first
compensatory mitigation option considered for permittee-responsible mitigation. (4) If permittee-
responsible mitigation is the proposed option, the prospective permittee is responsible for submitting
a mitigation plan. A conceptual or detailed mitigation plan may be used by the district engineer to
make the decision on the NWP verification request, but a final mitigation plan that addresses the
applicable requirements of 33 CFR 332.4(c)(2) through (14) must be approved by the district engineer
before the permittee begins work in waters of the United States, unless the district engineer
determines that prior approval of the final mitigation plan is not practicable or not necessary to ensure
timely completion of the required compensatory mitigation (see 33 CFR 332.3(k)(3)). (5) If
mitigation bank or in-lieu fee program credits are the proposed option, the mitigation plan only needs
8
to address the baseline conditions at the impact site and the number of credits to be provided. (6)
Compensatory mitigation requirements (e.g., resource type and amount to be provided as
compensatory mitigation, site protection, ecological performance standards, monitoring requirements)
may be addressed through conditions added to the NWP authorization, instead of components of a
compensatory mitigation plan (see 33 CFR 332.4(c)(1)(ii)).
(g) Compensatory mitigation will not be used to increase the acreage losses allowed by the acreage limits
of the NWPs. For example, if an NWP has an acreage limit of 1/2-acre, it cannot be used to authorize any
NWP activity resulting in the loss of greater than 1/2-acre of waters of the United States, even if
compensatory mitigation is provided that replaces or restores some of the lost waters. However,
compensatory mitigation can and should be used, as necessary, to ensure that an NWP activity already
meeting the established acreage limits also satisfies the no more than minimal impact requirement for the
NWPs. (h) Permittees may propose the use of mitigation banks, in-lieu fee programs, or permittee-
responsible mitigation. When developing a compensatory mitigation proposal, the permittee must
consider appropriate and practicable options consistent with the framework at 33 CFR 332.3(b). For
activities resulting in the loss of marine or estuarine resources, permittee-responsible mitigation may be
environmentally preferable if there are no mitigation banks or in-lieu fee programs in the area that have
marine or estuarine credits available for sale or transfer to the permittee. For permittee-responsible
mitigation, the special conditions of the NWP verification must clearly indicate the party or parties
responsible for the implementation and performance of the compensatory mitigation project, and, if
required, its long-term management. (i) Where certain functions and services of waters of the United
States are permanently adversely affected by a regulated activity, such as discharges of dredged or fill
material into waters of the United States that will convert a forested or scrub-shrub wetland to a
herbaceous wetland in a permanently maintained utility line right-of-way, mitigation may be required to
reduce the adverse environmental effects of the activity to the no more than minimal level.
24. Safety of Impoundment Structures. To ensure that all impoundment structures are safely designed,
the district engineer may require non-Federal applicants to demonstrate that the structures comply with
established state dam safety criteria or have been designed by qualified persons. The district engineer may
also require documentation that the design has been independently reviewed by similarly qualified
persons, and appropriate modifications made to ensure safety.
25. Water Quality. Where States and authorized Tribes, or EPA where applicable, have not previously
certified compliance of an NWP with CWA section 401, individual 401 Water Quality Certification must
be obtained or waived (see 33 CFR 330.4(c)). The district engineer or State or Tribe may require
additional water quality management measures to ensure that the authorized activity does not result in
more than minimal degradation of water quality.
26. Coastal Zone Management. In coastal states where an NWP has not previously received a state coastal
zone management consistency concurrence, an individual state coastal zone management consistency
concurrence must be obtained, or a presumption of concurrence must occur (see 33 CFR 330.4(d)). The
district engineer or a State may require additional measures to ensure that the authorized activity is
consistent with state coastal zone management requirements.
27. Regional and Case-By-Case Conditions. The activity must comply with any regional conditions that
may have been added by the Division Engineer (see 33 CFR 330.4(e)) and with any case specific
conditions added by the Corps or by the state, Indian Tribe, or U.S. EPA in its section 401 Water Quality
Certification, or by the state in its Coastal Zone Management Act consistency determination.
28. Use of Multiple Nationwide Permits. The use of more than one NWP for a single and complete
project is prohibited, except when the acreage loss of waters of the United States authorized by the NWPs
does not exceed the acreage limit of the NWP with the highest specified acreage limit. For example, if a
9
road crossing over tidal waters is constructed under NWP 14, with associated bank stabilization
authorized by NWP 13, the maximum acreage loss of waters of the United States for the total project
cannot exceed 1/3-acre.
29. Transfer of Nationwide Permit Verifications. If the permittee sells the property associated with a
nationwide permit verification, the permittee may transfer the nationwide permit verification to the new
owner by submitting a letter to the appropriate Corps district office to validate the transfer. A copy of the
nationwide permit verification must be attached to the letter, and the letter must contain the following
statement and signature: “When the structures or work authorized by this nationwide permit are still in
existence at the time the property is transferred, the terms and conditions of this nationwide permit,
including any special conditions, will continue to be binding on the new owner(s) of the property. To
validate the transfer of this nationwide permit and the associated liabilities associated with compliance
with its terms and conditions, have the transferee sign and date below.”
_____________________________________________
(Transferee)
_____________________________________________
(Date)
30. Compliance Certification. Each permittee who receives an NWP verification letter from the Corps
must provide a signed certification documenting completion of the authorized activity and
implementation of any required compensatory mitigation. The success of any required permittee-
responsible mitigation, including the achievement of ecological performance standards, will be addressed
separately by the district engineer. The Corps will provide the permittee the certification document with
the NWP verification letter. The certification document will include: (a) A statement that the authorized
activity was done in accordance with the NWP authorization, including any general, regional, or activity-
specific conditions; (b) A statement that the implementation of any required compensatory mitigation was
completed in accordance with the permit conditions. If credits from a mitigation bank or in-lieu fee
program are used to satisfy the compensatory mitigation requirements, the certification must include the
documentation required by 33 CFR 332.3(l)(3) to confirm that the permittee secured the appropriate
number and resource type of credits; and (c) The signature of the permittee certifying the completion of
the activity and mitigation. The completed certification document must be submitted to the district
engineer within 30 days of completion of the authorized activity or the implementation of any required
compensatory mitigation, whichever occurs later.
31. Activities Affecting Structures or Works Built by the United States. If an NWP activity also requires
permission from the Corps pursuant to 33 U.S.C. 408 because it will alter or temporarily or permanently
occupy or use a U.S. Army Corps of Engineers (USACE) federally authorized Civil Works project (a
“USACE project”), the prospective permittee must submit a pre-construction notification. See paragraph
(b)(10) of general condition 32. An activity that requires section 408 permission is not authorized by
NWP until the appropriate Corps office issues the section 408 permission to alter, occupy, or use the
USACE project, and the district engineer issues a written NWP verification.
32. Pre-Construction Notification. (a) Timing. Where required by the terms of the NWP, the prospective
permittee must notify the district engineer by submitting a pre-construction notification (PCN) as early as
possible. The district engineer must determine if the PCN is complete within 30 calendar days of the date
of receipt and, if the PCN is determined to be incomplete, notify the prospective permittee within that 30
day period to request the additional information necessary to make the PCN complete. The request must
specify the information needed to make the PCN complete. As a general rule, district engineers will
request additional information necessary to make the PCN complete only once. However, if the
prospective permittee does not provide all of the requested information, then the district engineer will
notify the prospective permittee that the PCN is still incomplete and the PCN review process will not
10
commence until all of the requested information has been received by the district engineer. The
prospective permittee shall not begin the activity until either:
(1) He or she is notified in writing by the district engineer that the activity may proceed under the
NWP with any special conditions imposed by the district or division engineer; or
(2) 45 calendar days have passed from the district engineer’s receipt of the complete PCN and the
prospective permittee has not received written notice from the district or division engineer. However, if
the permittee was required to notify the Corps pursuant to general condition 18 that listed species or
critical habitat might be affected or are in the vicinity of the activity, or to notify the Corps pursuant to
general condition 20 that the activity might have the potential to cause effects to historic properties, the
permittee cannot begin the activity until receiving written notification from the Corps that there is “no
effect” on listed species or “no potential to cause effects” on historic properties, or that any consultation
required under Section 7 of the Endangered Species Act (see 33 CFR 330.4(f)) and/or section 106 of the
National Historic Preservation Act (see 33 CFR 330.4(g)) has been completed. Also, work cannot begin
under NWPs 21, 49, or 50 until the permittee has received written approval from the Corps. If the
proposed activity requires a written waiver to exceed specified limits of an NWP, the permittee may not
begin the activity until the district engineer issues the waiver. If the district or division engineer notifies
the permittee in writing that an individual permit is required within 45 calendar days of receipt of a
complete PCN, the permittee cannot begin the activity until an individual permit has been obtained.
Subsequently, the permittee’s right to proceed under the NWP may be modified, suspended, or revoked
only in accordance with the procedure set forth in 33 CFR 330.5(d)(2).
(b) Contents of Pre-Construction Notification: The PCN must be in writing and include the following
information:
(1) Name, address and telephone numbers of the prospective permittee;
(2) Location of the proposed activity;
(3) Identify the specific NWP or NWP(s) the prospective permittee wants to use to authorize
the proposed activity;
(4) A description of the proposed activity; the activity’s purpose; direct and indirect adverse
environmental effects the activity would cause, including the anticipated amount of loss of wetlands,
other special aquatic sites, and other waters expected to result from the NWP activity, in acres, linear
feet, or other appropriate unit of measure; a description of any proposed mitigation measures intended
to reduce the adverse environmental effects caused by the proposed activity; and any other NWP(s),
regional general permit(s), or individual permit(s) used or intended to be used to authorize any part of
the proposed project or any related activity, including other separate and distant crossings for linear
projects that require Department of the Army authorization but do not require pre-construction
notification. The description of the proposed activity and any proposed mitigation measures should be
sufficiently detailed to allow the district engineer to determine that the adverse environmental effects
of the activity will be no more than minimal and to determine the need for compensatory mitigation
or other mitigation measures. For single and complete linear projects, the PCN must include the
quantity of anticipated losses of wetlands, other special aquatic sites, and other waters for each single
and complete crossing of those wetlands, other special aquatic sites, and other waters. Sketches
should be provided when necessary to show that the activity complies with the terms of the NWP.
(Sketches usually clarify the activity and when provided results in a quicker decision. Sketches should
contain sufficient detail to provide an illustrative description of the proposed activity (e.g., a
conceptual plan), but do not need to be detailed engineering plans);
(5) The PCN must include a delineation of wetlands, other special aquatic sites, and other
waters, such as lakes and ponds, and perennial, intermittent, and ephemeral streams, on the project
site. Wetland delineations must be prepared in accordance with the current method required by the
Corps. The permittee may ask the Corps to delineate the special aquatic sites and other waters on the
project site, but there may be a delay if the Corps does the delineation, especially if the project site is
large or contains many wetlands, other special aquatic sites, and other waters. Furthermore, the 45
day period will not start until the delineation has been submitted to or completed by the Corps, as
appropriate;
11
(6) If the proposed activity will result in the loss of greater than 1/10-acre of wetlands and a
PCN is required, the prospective permittee must submit a statement describing how the mitigation
requirement will be satisfied, or explaining why the adverse environmental effects are no more than
minimal and why compensatory mitigation should not be required. As an alternative, the prospective
permittee may submit a conceptual or detailed mitigation plan.
(7) For non-Federal permittees, if any listed species or designated critical habitat might be
affected or is in the vicinity of the activity, or if the activity is located in designated critical habitat,
the PCN must include the name(s) of those endangered or threatened species that might be affected
by the proposed activity or utilize the designated critical habitat that might be affected by the
proposed activity. For NWP activities that require pre-construction notification, Federal permittees
must provide documentation demonstrating compliance with the Endangered Species Act;
(8) For non-Federal permittees, if the NWP activity might have the potential to cause effects
to a historic property listed on, determined to be eligible for listing on, or potentially eligible for
listing on, the National Register of Historic Places, the PCN must state which historic property might
have the potential to be affected by the proposed activity or include a vicinity map indicating the
location of the historic property. For NWP activities that require pre-construction notification, Federal
permittees must provide documentation demonstrating compliance with section 106 of the National
Historic Preservation Act;
(9) For an activity that will occur in a component of the National Wild and Scenic River
System, or in a river officially designated by Congress as a “study river” for possible inclusion in the
system while the river is in an official study status, the PCN must identify the Wild and Scenic River
or the “study river” (see general condition 16); and
(10) For an activity that requires permission from the Corps pursuant to 33 U.S.C. 408
because it will alter or temporarily or permanently occupy or use a U.S. Army Corps of Engineers
federally authorized civil works project, the pre-construction notification must include a statement
confirming that the project proponent has submitted a written request for section 408 permission from
the Corps office having jurisdiction over that USACE project.
(c) Form of Pre-Construction Notification: The standard individual permit application form (Form ENG
4345) may be used, but the completed application form must clearly indicate that it is an NWP PCN and
must include all of the applicable information required in paragraphs (b)(1) through (10) of this general
condition. A letter containing the required information may also be used. Applicants may provide
electronic files of PCNs and supporting materials if the district engineer has established tools and
procedures for electronic submittals. (d) Agency Coordination: (1) The district engineer will consider any
comments from Federal and state agencies concerning the proposed activity’s compliance with the terms
and conditions of the NWPs and the need for mitigation to reduce the activity’s adverse environmental
effects so that they are no more than minimal. (2) Agency coordination is required for: (i) all NWP
activities that require pre-construction notification and result in the loss of greater than 1/2-acre of waters
of the United States; (ii) NWP 21, 29, 39, 40, 42, 43, 44, 50, 51, and 52 activities that require pre-
construction notification and will result in the loss of greater than 300 linear feet of stream bed; (iii) NWP
13 activities in excess of 500 linear feet, fills greater than one cubic yard per running foot, or involve
discharges of dredged or fill material into special aquatic sites; and (iv) NWP 54 activities in excess of
500 linear feet, or that extend into the waterbody more than 30 feet from the mean low water line in tidal
waters or the ordinary high water mark in the Great Lakes. (3) When agency coordination is required, the
district engineer will immediately provide (e.g., via e-mail, facsimile transmission, overnight mail, or
other expeditious manner) a copy of the complete PCN to the appropriate Federal or state offices (FWS,
state natural resource or water quality agency, EPA, and, if appropriate, the NMFS). With the exception
of NWP 37, these agencies will have 10 calendar days from the date the material is transmitted to notify
the district engineer via telephone, facsimile transmission, or e-mail that they intend to provide
substantive, site-specific comments. The comments must explain why the agency believes the adverse
environmental effects will be more than minimal. If so contacted by an agency, the district engineer will
wait an additional 15 calendar days before making a decision on the pre-construction notification. The
district engineer will fully consider agency comments received within the specified time frame
12
concerning the proposed activity’s compliance with the terms and conditions of the NWPs, including the
need for mitigation to ensure the net adverse environmental effects of the proposed activity are no more
than minimal. The district engineer will provide no response to the resource agency, except as provided
below. The district engineer will indicate in the administrative record associated with each pre-
construction notification that the resource agencies’ concerns were considered. For NWP 37, the
emergency watershed protection and rehabilitation activity may proceed immediately in cases where there
is an unacceptable hazard to life or a significant loss of property or economic hardship will occur. The
district engineer will consider any comments received to decide whether the NWP 37 authorization
should be modified, suspended, or revoked in accordance with the procedures at 33 CFR 330.5.
(4) In cases of where the prospective permittee is not a Federal agency, the district engineer will provide a
response to NMFS within 30 calendar days of receipt of any Essential Fish Habitat conservation
recommendations, as required by section 305(b)(4)(B) of the Magnuson-Stevens Fishery Conservation
and Management Act. (5) Applicants are encouraged to provide the Corps with either electronic files or
multiple copies of pre-construction notifications to expedite agency coordination.
District Engineer’s Decision: 1. In reviewing the PCN for the proposed activity, the district engineer will
determine whether the activity authorized by the NWP will result in more than minimal individual or
cumulative adverse environmental effects or may be contrary to the public interest. If a project
proponent requests authorization by a specific NWP, the district engineer should issue the NWP
verification for that activity if it meets the terms and conditions of that NWP, unless he or she determines,
after considering mitigation, that the proposed activity will result in more than minimal individual and
cumulative adverse effects on the aquatic environment and other aspects of the public interest and
exercises discretionary authority to require an individual permit for the proposed activity. For a linear
project, this determination will include an evaluation of the individual crossings of waters of the United
States to determine whether they individually satisfy the terms and conditions of the NWP(s), as well as
the cumulative effects caused by all of the crossings authorized by NWP. If an applicant requests a waiver
of the 300 linear foot limit on impacts to streams or of an otherwise applicable limit, as provided for in
NWPs 13, 21, 29, 36, 39, 40, 42, 43, 44, 50, 51, 52, or 54, the district engineer will only grant the waiver
upon a written determination that the NWP activity will result in only minimal individual and cumulative
adverse environmental effects. For those NWPs that have a waivable 300 linear foot limit for losses of
intermittent and ephemeral stream bed and a 1/2-acre limit (i.e., NWPs 21, 29, 39, 40, 42, 43, 44, 50, 51,
and 52), the loss of intermittent and ephemeral stream bed, plus any other losses of jurisdictional waters
and wetlands, cannot exceed 1/2-acre. 2. When making minimal adverse environmental effects
determinations the district engineer will consider the direct and indirect effects caused by the NWP
activity. He or she will also consider the cumulative adverse environmental effects caused by activities
authorized by NWP and whether those cumulative adverse environmental effects are no more than
minimal. The district engineer will also consider site specific factors, such as the environmental setting in
the vicinity of the NWP activity, the type of resource that will be affected by the NWP activity, the
functions provided by the aquatic resources that will be affected by the NWP activity, the degree or
magnitude to which the aquatic resources perform those functions, the extent that aquatic resource
functions will be lost as a result of the NWP activity (e.g., partial or complete loss), the duration of the
adverse effects (temporary or permanent), the importance of the aquatic resource functions to the region
(e.g., watershed or ecoregion), and mitigation required by the district engineer. If an appropriate
functional or condition assessment method is available and practicable to use, that assessment method
may be used by the district engineer to assist in the minimal adverse environmental effects determination.
The district engineer may add case-specific special conditions to the NWP authorization to address site-
specific environmental concerns. 3. If the proposed activity requires a PCN and will result in a loss of
greater than 1/10-acre of wetlands, the prospective permittee should submit a mitigation proposal with the
PCN. Applicants may also propose compensatory mitigation for NWP activities with smaller impacts, or
for impacts to other types of waters (e.g., streams). The district engineer will consider any proposed
compensatory mitigation or other mitigation measures the applicant has included in the proposal in
determining whether the net adverse environmental effects of the proposed activity are no more than
13
minimal. The compensatory mitigation proposal may be either conceptual or detailed. If the district
engineer determines that the activity complies with the terms and conditions of the NWP and that the
adverse environmental effects are no more than minimal, after considering mitigation, the district
engineer will notify the permittee and include any activity-specific conditions in the NWP verification the
district engineer deems necessary. Conditions for compensatory mitigation requirements must comply
with the appropriate provisions at 33 CFR 332.3(k). The district engineer must approve the final
mitigation plan before the permittee commences work in waters of the United States, unless the district
engineer determines that prior approval of the final mitigation plan is not practicable or not necessary to
ensure timely completion of the required compensatory mitigation. If the prospective permittee elects to
submit a compensatory mitigation plan with the PCN, the district engineer will expeditiously review the
proposed compensatory mitigation plan. The district engineer must review the proposed compensatory
mitigation plan within 45 calendar days of receiving a complete PCN and determine whether the proposed
mitigation would ensure the NWP activity results in no more than minimal adverse environmental effects.
If the net adverse environmental effects of the NWP activity (after consideration of the mitigation
proposal) are determined by the district engineer to be no more than minimal, the district engineer will
provide a timely written response to the applicant. The response will state that the NWP activity can
proceed under the terms and conditions of the NWP, including any activity-specific conditions added to
the NWP authorization by the district engineer. 4. If the district engineer determines that the adverse
environmental effects of the proposed activity are more than minimal, then the district engineer will
notify the applicant either: (a) that the activity does not qualify for authorization under the NWP and
instruct the applicant on the procedures to seek authorization under an individual permit; (b) that the
activity is authorized under the NWP subject to the applicant’s submission of a mitigation plan that would
reduce the adverse environmental effects so that they are no more than minimal; or (c) that the activity is
authorized under the NWP with specific modifications or conditions. Where the district engineer
determines that mitigation is required to ensure no more than minimal adverse environmental effects, the
activity will be authorized within the 45-day PCN period (unless additional time is required to comply
with general conditions 18, 20, and/or 31, or to evaluate PCNs for activities authorized by NWPs 21, 49,
and 50), with activity-specific conditions that state the mitigation requirements. The authorization will
include the necessary conceptual or detailed mitigation plan or a requirement that the applicant submit a
mitigation plan that would reduce the adverse environmental effects so that they are no more than
minimal. When compensatory mitigation is required, no work in waters of the United States may occur
until the district engineer has approved a specific mitigation plan or has determined that prior approval of
a final mitigation plan is not practicable or not necessary to ensure timely completion of the required
compensatory mitigation.
Further Information: 1. District Engineers have authority to determine if an activity complies with the
terms and conditions of an NWP. 2. NWPs do not obviate the need to obtain other federal, state, or local
permits, approvals, or authorizations required by law. 3. NWPs do not grant any property rights or
exclusive privileges. 4. NWPs do not authorize any injury to the property or rights of others. 5. NWPs do
not authorize interference with any existing or proposed Federal project (see general condition 31).
C. CORPS SEATTLE DISTRICT REGIONAL GENERAL CONDITIONS: The following conditions
apply to all NWPs for the Seattle District in Washington State, unless specified.
1. Project Drawings: Drawings must be submitted with pre-construction notification (PCN). Drawings
must provide a clear understanding of the proposed project, and how waters of the U.S. will be affected.
Drawings must be originals and not reduced copies of large-scale plans. Engineering drawings are not
required. Existing and proposed site conditions (manmade and landscape features) must be drawn to
scale.
2. Aquatic Resources Requiring Special Protection: Activities resulting in a loss of waters of the
United States in mature forested wetlands, bogs and peatlands, aspen-dominated wetlands, alkali
14
wetlands, vernal pools, camas prairie wetlands, estuarine wetlands, wetlands in coastal lagoons, and
wetlands in dunal systems along the Washington coast cannot be authorized by a NWP, except by the
following NWPs:
NWP 3 – Maintenance
NWP 20 – Response Operations for Oil and Hazardous Substances
NWP 32 – Completed Enforcement Actions
NWP 38 – Cleanup of Hazardous and Toxic Waste
In order to use one of the above-referenced NWPs in any of the aquatic resources requiring special
protection, prospective permittees must submit a PCN to the Corps of Engineers (see NWP general
condition 32) and obtain written authorization before commencing work.
3. New Bank Stabilization in Tidal Waters of Puget Sound: Activities involving new bank
stabilization in tidal waters in Water Resource Inventory Areas (WRIAs)
8, 9, 10, 11 and 12 (within the areas identified on Figures 1a through 1e on Corps website) cannot be
authorized by NWP.
4. Commencement Bay: The following NWPs may not be used to authorize activities located in the
Commencement Bay Study Area (see Figure 2 on Corps website):
NWP 12 – Utility Line Activities (substations)
NWP 13 – Bank Stabilization
NWP 14 – Linear Transportation Projects
NWP 23 – Approved Categorical Exclusions
NWP 29 – Residential Developments
NWP 39 – Commercial and Institutional Developments
NWP 40 – Agricultural Activities
NWP 41 – Reshaping Existing Drainage Ditches
NWP 42 – Recreational Facilities
NWP 43 – Stormwater and Wastewater Management Facilities
5. Bank Stabilization: All projects including new or maintenance bank stabilization activities require
PCN to the Corps of Engineers (see NWP general condition 32). For new bank stabilization projects only,
the following must be submitted to the Corps of Engineers:
a. The cause of the erosion and the distance of any existing structures from the area(s) being
stabilized.
b. The type and length of existing bank stabilization within 300 feet of the proposed project.
c. A description of current conditions and expected post-project conditions in the waterbody.
d. A statement describing how the project incorporates elements avoiding and minimizing adverse
environmental effects to the aquatic environment and nearshore riparian area, including vegetation
impacts in the waterbody.
In addition to a. through d., the results from any relevant geotechnical investigations can be submitted
with the PCN if it describes current or expected conditions in the waterbody.
6. Crossings of Waters of the United States: Any project including installing, replacing, or modifying
crossings of waters of the United States, such as culverts or bridges, requires submittal of a PCN to the
Corps of Engineers (see NWP general condition 32). If a culvert is proposed to cross waters of the U.S.
where salmonid species are present or could be present, the project must apply the stream simulation
design method from the Washington Department of Fish and Wildlife located in the Water Crossing
Design Guidelines (2013), or a design method which provides passage at all life stages at all flows where
the salmonid species would naturally seek passage. If the stream simulation design method is not applied
for a culvert where salmonid species are present or could be present, the project proponent must provide a
rationale in the PCN sufficient to establish one of the following:
a. The existence of extraordinary site conditions.
15
b. How the proposed design will provide equivalent or better fish passage and fisheries habitat
benefits than the stream simulation design method.
If a culvert is proposed to cross waters of the U.S. where salmonid species are present or could be present,
project proponents must provide a monitoring plan with the PCN that specifies how the proposed culvert
will be assessed over a five-year period from the time of construction completion to ensure its
effectiveness in providing passage at all life stages at all flows where the salmonid species would
naturally seek passage. Culverts installed under emergency authorization that do not meet the above
design criteria will be required to meet the above design criteria to receive an after-the-fact nationwide
permit verification.
7. Stream Loss: A PCN is required for all activities that result in the loss of any linear feet of stream
beds. No activity shall result in the loss of any linear feet of perennial stream beds or the loss of greater
than 300 linear feet of intermittent and/or ephemeral stream beds. A stream may be rerouted if it is
designed in a manner that maintains or restores hydrologic, ecologic, and geomorphic stream processes,
provided there is not a reduction in the linear feet of stream bed. Streams include brooks, creeks, rivers,
and historical waters of the U.S. that have been channelized into ditches. This condition does not apply to
ditches constructed in uplands. Stream loss restrictions may be waived by the district engineer on a case-
by-case basis provided the activities result in net increases of aquatic resource functions and services.
8. Mitigation: Pre-construction notification is required for any project that will result in permanent
wetland losses that exceed 1,000 square feet. In addition to the requirements of General Condition 23
(Mitigation), compensatory mitigation at a minimum one-to-one ratio will be required for all permanent
wetland losses that exceed 1,000 square feet. When a PCN is required for wetland losses less than 1,000
square feet, the Corps of Engineers may determine on a case-by-case basis that compensatory mitigation
is required to ensure that the activity results in minimal adverse effects on the aquatic environment.
Compensatory mitigation for impacts to marine waters, lakes, and streams will be determined on a case-
by-case basis. If temporary impacts to waters of the U.S. exceed six months, the Corps of Engineers may
require compensatory mitigation for temporal effects.
9. Magnuson-Stevens Fishery Conservation and Management Act – Essential Fish Habitat
Essential Fish Habitat (EFH) is defined as those waters and substrate necessary to fish for spawning,
breeding, feeding, or growth to maturity. If EFH may be adversely affected by a proposed activity, the
prospective permittee must provide a written EFH assessment with an analysis of the effects of the
proposed action on EFH. The assessment must identify the type(s) of essential fish habitat (i.e., Pacific
salmon, groundfish, and/or coastal-pelagic species) that may be affected. If the Corps of Engineers
determines the project will adversely affect EFH, consultation with NOAA Fisheries will be required.
Federal agencies should follow their own procedures for complying with the requirements of the
Magnuson-Stevens Fishery Conservation and Management Act. If PCN is required for the proposed
activity, Federal permittees must provide the district engineer with the appropriate documentation to
demonstrate compliance with those requirements.
10. Forage Fish: For projects in forage fish spawning habitat, in-water work must occur within
designated forage fish work windows, or when forage fish are not spawning. If working outside of a
designated work window, or if forage fish work windows are closed year round, work may occur if the
work window restriction is released for a period of time after a forage fish spawning survey has been
conducted by a biologist approved by the Washington State Department of Fish and Wildlife (WDFW).
Forage fish species with designated in-water work windows include Pacific sand lance (Ammodytes
hexapterus), Pacific herring (Clupea pallasi), and surf smelt (Hypomesus pretiosus). This RGC does not
apply to NWP 48, Commercial Shellfish Aquaculture Activities. Please see specific regional conditions
for NWP 48.
16
11. Notification of Permit Requirements: The permittee must provide a copy of the nationwide permit
authorization letter, conditions, and permit drawings to all contractors and any other parties performing
the authorized work prior to the commencement of any work in waters of the U.S. The permittee must
ensure all appropriate contractors and any other parties performing the authorized work at the project site
have read and understand relevant NWP conditions as well as plans, approvals, and documents referenced
in the NWP letter. A copy of these documents must be maintained onsite throughout the duration of
construction.
12. Construction Boundaries: Permittees must clearly mark all construction area boundaries before
beginning work on projects that involve grading or placement of fill. Boundary markers and/or
construction fencing must be maintained and clearly visible for the duration of construction. Permittees
should avoid and minimize removal of native vegetation (including submerged aquatic vegetation) to the
maximum extent possible.
13. Temporary Impacts and Site Restoration
a. Temporary impacts to waters of the U.S. must not exceed six months unless the prospective permittee
requests and receives a waiver by the district engineer. Temporary impacts to waters of the U.S. must
be identified in the PCN.
b. No more than 1/2 acre of waters of the U.S. may be temporarily filled unless the prospective permittee
requests and receives a waiver from the district engineer (temporary fills do not affect specified limits
for loss of waters associated with specific nationwide permits).
c. Native soils removed from waters of the U.S. for project construction should be stockpiled and used
for site restoration. Restoration of temporarily disturbed areas must include returning the area to pre-
project ground surface contours. If native soil is not available from the project site for restoration,
suitable clean soil of the same textural class may be used. Other soils may be used only if identified in
the PCN.
d. The permittee must revegetate disturbed areas with native plant species sufficient in number, spacing,
and diversity to restore affected functions. A maintenance and monitoring plan commensurate with
the impacts, may be required. Revegetation must begin as soon as site conditions allow within the
same growing season as the disturbance unless the schedule is approved by the Corps of Engineers.
Native plants removed from waters of the U.S. for project construction should be stockpiled and used
for revegetation when feasible. Temporary Erosion and Sediment Control measures must be removed
as soon as the area has established vegetation sufficient to control erosion and sediment.
e. If the Corps determines the project will result in temporary impacts of submerged aquatic vegetation
(SAV) that are more than minimal, a monitoring plan must be submitted. If recovery is not achieved
by the end of the monitoring period, contingencies must be implemented, and additional monitoring
will be required.
This RGC does not apply to NWP 48, Commercial Shellfish Aquaculture Activities. Please see specific
regional conditions for NWP 48.
D. CORPS REGIONAL SPECIFIC CONDITIONS FOR THIS NWP:
1. Private residential driveways in waters of the U.S. with footprints wider than 22 feet
or longer than 200 feet are not authorized by this NWP. For this requirement, “footprint” refers to
the bottom width of the roadway fill prism.
2. A pre-construction notification must be submitted to the district engineer (see NWP general
condition 32) for linear transportation project crossings in tidal waters.
E. ECOLOGY 401 CERTIFICATION: GENERAL CONDITIONS
17
In addition to all the Corps National and Seattle Districts’ Regional permit conditions, the following State
General Section 401 Water Quality Certification (Section 401) conditions apply to all Nationwide Permits
whether certified or partially certified in the State of Washington.
1. For in-water construction activities. Ecology Section 401 review is required for projects or
activities authorized under NWPs that will cause, or may be likely to cause or contribute to an exceedance
of a State water quality standard (Chapter 173-201A WAC) or sediment management standard (Chapter
173-204 WAC). State water quality standards and sediment management standards are available on
Ecology’s website. Note: In-water activities include any activity within a wetland and/or activities below
the ordinary high water mark (OHWM).
2. Projects or Activities Discharging to Impaired Waters. Ecology Section 401 review is required for
projects or activities authorized under NWPs if the project or activity will occur in a 303(d) listed
segment of a waterbody or upstream of a listed segment and may result in further exceedances of the
specific listed parameter. To determine if your project or activity is in a 303(d) listed segment of a
waterbody, visit Ecology’s Water Quality Assessment webpage for maps and search tools.
3. Application. For projects or activities that will require Ecology Section 401 review, applicants must
provide Ecology with a Joint Aquatic Resources Permit Application (JARPA) along with the
documentation provided to the Corps, as described in National General Condition 32, Pre-Construction
Notification, including, when applicable: (a) A description of the project, including site plans, project
purpose, direct and indirect adverse environmental effects the project would cause, best management
practices (BMPs), and any other Department of the Army or federal agency permits used or intended to be
used to authorize any part of the proposed project or any related activity. (b) Drawings indicating the
Ordinary High Water Mark (OHWM), delineation of special aquatic sites and other waters of the state.
Wetland delineations must be prepared in accordance with the current method required by the Corps and
shall include Ecology’s Wetland Rating form. Wetland rating forms are subject to review and verification
by Ecology staff. Guidance for determining the OHWM is available on Ecology’s website. (c) A
statement describing how the mitigation requirement will be satisfied. A conceptual or detailed mitigation
or restoration plan may be submitted. See State General Condition 5 for details on mitigation
requirements. (d) Other applicable requirements of Corps Nationwide Permit General Condition 32,
Corps Regional Conditions, or notification conditions of the applicable NWP. (e) Within 180 calendar
days from receipt of applicable documents noted above and a copy of the final authorization letter from
the Corps providing coverage for a proposed project or activity under the NWP Program Ecology will
provide the applicant notice of whether an individual Section 401 will be required for the project. If
Ecology fails to act within a year after receipt of both of these documents, Section 401 is presumed
waived.
4. Aquatic resources requiring special protection. Certain aquatic resources are unique, difficult-to-
replace components of the aquatic environment in Washington State. Activities that would affect these
resources must be avoided to the greatest extent possible. Compensating for adverse impacts to high
value aquatic resources is typically difficult, prohibitively expensive, and may not be possible in some
landscape settings. Ecology Section 401 review is required for activities in or affecting the following
aquatic resources (and not prohibited by Seattle District Regional General Condition): (a) Wetlands with
special characteristics (as defined in the Washington State Wetland Rating Systems for western and
eastern Washington, Ecology Publications #14-06-029 and #14-06-030):
• Estuarine wetlands.
• Wetlands of High Conservation Value.
• Bogs.
• Old-growth and mature forested wetlands.
• Wetlands in coastal lagoons.
• Interdunal wetlands.
18
• Vernal pools.
• Alkali wetlands.
(b) Fens, aspen-dominated wetlands, camas prairie wetlands. (c) Marine water with eelgrass (Zostera
marina) beds (except for NWP 48). (d) Category I wetlands. (e) Category II wetlands with a habitat score
≥ 8 points. This State General Condition does not apply to the following Nationwide Permits:
NWP 20 – Response Operations for Oil and Hazardous Substances, NWP 32 – Completed Enforcement
Actions
5. Mitigation. Applicants are required to show that they have followed the mitigation sequence and
have first avoided and minimized impacts to aquatic resources wherever practicable. For projects
requiring Ecology Section 401 review with unavoidable impacts to aquatics resources, adequate
compensatory mitigation must be provided.
(a) Wetland mitigation plans submitted for Ecology review and approval shall be based on the most
current guidance provided in Wetland Mitigation in Washington State, Parts 1 and 2 (available on
Ecology’s website) and shall, at a minimum, include the following:
i. A description of the measures taken to avoid and minimize impacts to wetlands and other waters of
the U.S.
ii. The nature of the proposed impacts (i.e., acreage of wetlands and functions lost or degraded).
iii. The rationale for the mitigation site that was selected.
iv. The goals and objectives of the compensatory mitigation project.
v. How the mitigation project will be accomplished, including construction sequencing, best
management practices to protect water quality, proposed performance standards for measuring success
and the proposed buffer widths.
vi. How it will be maintained and monitored to assess progress towards goals and objectives.
Monitoring will generally be required for a minimum of five years. For forested and scrub-shrub
wetlands, 10 years of monitoring will often be necessary.
vii. How the compensatory mitigation site will be legally protected for the long term.
Refer to Wetland Mitigation in Washington State – Part 2: Developing Mitigation Plans (Ecology
Publication #06-06-011b) and Selecting Wetland Mitigation Sites Using a Watershed Approach (Ecology
Publications #09-06-032 (Western Washington) and #10-06-007 (Eastern Washington)) for guidance on
selecting suitable mitigation sites and developing mitigation plans. Ecology encourages the use of
alternative mitigation approaches, including credit/debit methodology, advance mitigation, and other
programmatic approach such as mitigation banks and in-lieu fee programs. If you are interested in
proposing use of an alternative mitigation approach, consult with the appropriate Ecology regional staff
person. Information on alternative mitigation approaches is available on Ecology’s website.
(b) Mitigation for other aquatic resource impacts will be determined on a case-by-case basis.
6. Temporary Fills. Ecology Section 401 review is required for any project or activity with temporary
fill in wetlands or other waters of the state for more than 90 days, unless the applicant has received
written approval from Ecology. Note: This State General Condition does not apply to projects or activities
authorized under NWP 33, Temporary Construction, Access, and Dewatering
7. Stormwater pollution prevention: All projects that involve land disturbance or impervious surfaces
must implement stormwater pollution prevention or control measures to avoid discharge of pollutants in
stormwater runoff to waters of the State.
(a) For land disturbances during construction, the applicant must obtain and implement permits (e.g.,
Construction Stormwater General Permit) where required and follow Ecology’s current stormwater
manual.
(b) Following construction, prevention or treatment of on-going stormwater runoff from impervious
surfaces shall be provided.
Ecology’s Stormwater Management and Design Manuals and stormwater permit information are available
on Ecology’s website.
19
8. State Section 401 Review for PCNs not receiving 45-day response from the Seattle District. In the
event the Seattle District Corps does not issue a NWP authorization letter within 45 calendar days of
receipt of a complete pre-construction notification, the applicant must contact Ecology for Section 401
review prior to commencing work.
F. ECOLOGY 401 CERTIFICATION: SPECIFIC CONDITIONS FOR THIS NWP:
Certified subject to conditions. Ecology Section 401 review is required for projects or activities
authorized under this NWP if:
1. The project or activity impacts more than more than 1/3 acre of waters of the state.
2. The project includes fill related to a residential and/or commercial development.
3. The project or activity is in or adjoining a known contaminated or cleanup site.
G. COASTAL ZONE MANAGEMENT CONSISTENCY RESPONSE FOR THIS NWP:
(Note: This is only applies in the following counties: Clallam, Grays Harbor, Island, Jefferson, King,
Kitsap, Mason, Pacific, Pierce, San Juan, Skagit, Snohomish, Thurston, Wahkiakum and Whatcom)
Response: Ecology concurs that this NWP is consistent with the CZMP, subject to the following
condition: An individual Coastal Zone Management Consistency Determination is required for project or
activities under this NWP if State Section 401 review is required.
General Conditions: For Non-Federal Permittees
1. Necessary Data and Information. A Coastal Zone Management Program “Certification of
Consistency” form is required for projects located within a coastal county. “Certification of Consistency”
forms are available on Ecology’s website. The form shall include a description of the proposed project or
activity and evidence of compliance with the applicable enforceable policies of the Washington Coastal
Zone Management Program (CZMP). Also, a map of the site location is required.
2. Timing. Within 6 months from receipt of the necessary data and information, Ecology will provide a
federal consistency determination for the proposed project or activity. If Ecology fails to act within the 6
month period, concurrence with the CZMP is presumed.
General Conditions: For Federal Permittees (Agencies)
1. Necessary Data and Information. Federal agencies shall submit the determination, information, and
analysis required by 15 CFR 930.39 to obtain a federal consistency determination.
2. Timing. Within 60 days from receipt of the necessary data and information, Ecology will provide a
federal consistency determination for the proposed project or activity. If Ecology fails to act within the
60 day period, concurrence with the CZMP is presumed.
-1-
FPRP Guidelines & Forms
WCR-2014-1857
Appendix A: FPRP Programmatic Email Guidelines and Implementation Forms
Use the FPRP Programmatic email box (fprp-wa.wcr@noaa.gov) to transmit the following
information to NMFS regarding use of this Programmatic Biological Opinion (opinion):
Send only one project per email submittal, attach all related documents preferably in pdf format;
and ensure the final project is being submitted to avoid multiple submittals and withdrawals.
Please send:
1. Action Implementation Form, containing Action Notification and Action Completion and
Fish Salvage reports (if fish salvage is conducted).
2. Map(s) and project design drawings (if applicable)
3. Final project plan.
If a withdrawal is necessary, please specify in the email subject line that the project is being
withdrawn. Simply state the reason for the withdrawal and submit to the email box, following the
email titling conventions. If a previously-withdrawn notification is resubmitted later, this
resubmittal will be regarded as a new action notification.
An automatic reply will be sent upon receipt, but no other communication will be sent from the
programmatic email box; this box is used for Incoming Only. All other pre-decisional
communication should be conducted outside the use of the fprp-wa.wcr@noaa.gov email boxes.
In the subject line of the email (see below for requirements), clearly identify the specific
submittal category (action notification, project completion, withdrawal, or salvage report), and
Corps number. The submitted documents will contain identifying information, including the
Applicant Name, County, Waterway, and State.
Email Titling Conventions
Use caution when entering the necessary information in the subject line. If these titling
conventions are not used, the email will not be accepted. Ensure that you clearly identify:
1. The specific submittal category: (a) Action Notification; (b) Action Completion Report;
(c) Fish Salvage Report; or (d) Annual Report
2. Corps number
3. Applicant Name
4. County
5. Waterway
6. State
-2-
FPRP Guidelines & Forms
WCR-2014-1857
FPRP Implementation Forms
NMFS Review and Certification Corps project managers shall submit this form with the Action
Notification portion completed to NMFS at fprp-wa.wcr@noaa.gov for notification or approval.
The Following Actions Require Certification from NMFS as consistent with FPRP before that
action is authorized by the Corps:
Hydraulic design of culverts
Stream simulation culverts
No-slope culverts
Tidally influenced road crossings
Tidegates with fish passage
Screens for diversions over 20 cfs
Structures to provide fish passage over dams 0
Starter channels
Fishway Designs that Exceed 3 feet
Removal of dams larger than 10 feet high
Use of steel piles larger than 12 inches to anchor ELJs
Channel reconstruction with significant grade control
NMFS will notify the Corps within 30 calendar days if the action is certified or disqualified.
When requested, NMFS will provide an estimate of the time necessary to complete the review
based on the complexity of the proposed action and work load considerations at the time of the
request. Certification may be delayed if a substandard design is submitted for review during the
post-design or action implementation stage and significant revision is necessary. These reviews
are best initiated in the context of technical assistance during the preliminary development
project phase, when project team members are developing goals and objectives with
stakeholders.
Attach information to e-mail message if required or relevant to NMFS’ review, such as:
Erosion and pollution control plan
Engineering designs
Project Reporting. The project manager shall submit the following reports as necessary:
Action Completion Reporting. Submit this form to NMFS within 60 days of completing all
work below ordinary high water (OHW).
Fish Salvage Reporting. Submit this form to NMFS within 60 days of completing a capture and
release as part of an action completed under FPRP.
The fprp-wa.wcr@noaa.gov email is to be used for incoming only.
-3-
FPRP Guidelines & Forms
WCR-2014-1857
FPRP Project Information Form
DATE OF REQUEST: NMFS TRACKING #: WCRO-2014-00004
TYPE OF REQUEST:
ACTION NOTIFICATION
ACTION NOTIFICATION (NMFS REVIEW AND CERTIFICATION REQUIRED)
Statutory Authority: ESA-ONLY EFH-ONLY ESA & EFH
COMBINED
Action Agency Contact: Corps Permit#:
Project Name:
6th Field HUC & Name:
Latitude & Longitude
Longitude (in signed degrees
format: DDD.dddd)
Proposed Construction
Period: Start Date: End Date:
Proposed Length of Channel
and/or Riparian
Modification in linear feet:
Proposed Area of Herbicide
Application in acres:
Project Description:
-4-
FPRP Guidelines & Forms
WCR-2014-1857
Type of Action: Identify the type of action proposed.
Actions Consistent with Limit 8
Fish Passage
Installation of In-Water Habitat and Streambank Stabilization Features
Levee Removal, Modification, and Public Access
Channel Restoration and Reconnection
Salmonid Spawning Gravel Restoration
Beach Nourishment, Bioengineering or Living Shoreline, and Benefical Use of Landslide
Material
Livestock Crossings
Irrigation Screen Installation and Replacement
Debris and Structure Removal
Mitigation and Conservation Bank Construction
Invasive Plant Treatement
NMFS Species/Critical Habitat Present in Action Area: Identify the species and critical
habitats present in the action area (N/A means not applicable):
Species
Critical
Habitat EFH Species
LCR Chinook salmon Salmon, Chinook
UCR spring-run Chinook salmon Salmon, coho
SR spring/summer-run Chinook salmon Salmon, pink
SR fall-run Chinook salmon Coastal Pelagics
PS Chinook salmon Groundfish
CR chum salmon
HC summer-run chum salmon
LCR coho salmon
SR sockeye salmon
Lake Ozette sockeye salmon
LCR steelhead
MCR steelhead
UCR steelhead
SRB steelhead
PS steelhead
Southern DPS eulachon
Project Modifications: Check any applicable project modifications. Each modifications must be
certified by NMFS.
Variance to the timing of inwater
work
Location of staging/refueling area
where applicant cannot meet the
required distance due to site constraints
Use of substances other than
vegetable oil in hydraulic lines
-5-
FPRP Guidelines & Forms
WCR-2014-1857
Activities Requiring NMFS Certification:
Hydraulic design of culverts Stream simulation culverts
No-slope culverts Tidally influenced road crossings
Tidegates with fish passage Screens for diversions over 20 cfs
Structures to provide fish passage over
dams
Starter channels
Fishway Designs that Exceed 3 feet Removal of dams larger than 10 feet
high
Use of steel piles larger than 12 inches
to anchor ELJs
Channel reconstruction with significant
grade control
-6-
FPRP Guidelines & Forms
WCR-2014-1857
FPRP Action Completion Reporting Form
Within 60 days of completing all work below ordinary high water (OHW) as part of an action completed
under FPRP, submit the completed Action Completion Form with the following information to NMFS at
fprp-wa.wcr@noaa.gov
Actual Start and End Dates for the
Completion of In-water Work: Start:
End:
Actual Linear-feet of Riparian and/or
Channel Modification:
Actual Acreage of Herbicide Treatment
Turbidity Monitoring/Sampling
Completed
Yes (include details
below) No
Please include the following:
1. Photos of habitat conditions before, during, and after action completion.
2. A summary of the results of pollution and erosion control inspections, including any erosion
control failure, contaminant release, and correction effort.
3. Records of turbidity monitoring (visual or by turbidimeter) including dates, times and location of
monitoring. Include any exceedances and steps taken to reduce turbidity observed.
-7-
FPRP Guidelines & Forms
WCR-2014-1857
FPRP Fish Salvage Reporting Form
If applicable: Within 60 days of completing a capture and release as part of an action completed under
FPRP, submit a complete Salvage Reporting Form, with the following information to NMFS at fprp-
wa.wcr@noaa.gov.
Date(s) of Fish Salvage
Operation(s):
Supervisory Fish Biologist:
Address
Telephone Number
Describe methods that were used to isolate the work area and remove fish
-8-
FPRP Guidelines & Forms
WCR-2014-1857
Fish Salvage Data
Water Temperature:
Air Temperature:
Time of Day:
ESA-Listed Species10 Number Handled Number Injured Number Killed
Juvenile Adult Juvenile Adult Juvenile Adult
Lower Columbia River Chinook salmon
Upper Columbia River spring-run Chinook
salmon
Snake River spring/summer run Chinook salmon
Snake River fall-run Chinook salmon
Puget Sound Chinook salmon
Hood Canal chum salmon
Columbia River chum salmon
Lower Columbia River coho salmon
Lower Columbia River steelhead
Middle Columbia River steelhead
Upper Columbia River steelhead
Snake River Basin steelhead
Puget Sound steelhead
Lake Ozette Sockeye salmon
10 Fish should be identified to the degree possible. When species is in doubt, use best professional judgement when
filling out table.
01VICINITY MAPNORTHPROJECT LOCATIONNORTHVICINITY MAPROCK CREEK CULVERT REPLACEMENTSUMMIT LANDSBURG ROADPROJECT LOCATIONPROJECT LOCATIONAPPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEY47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6EI 90I 405HWY 169HWY 18HWY 167I 5HWY 99HWY 518I 5HWY 167HWY 515HWY 164HWY 516SE KENT KANGLEY ROADSE SUMMITSE 248TH STHWY 516LANDSBURG ROADHWY 169NWS-2020-526
02INDE; SHEETAPPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEYSHEET INDE;SHEET #DESCRIPTION01VICINITY MAP02INDE; SHEET03INDE; MAP AND E;ISTING CONDITIONS04STREAM GRADING PLAN05STREAM PROFILE AND SECTION06BRIDGE LAYOUT PLAN07BRIDGE LAYOUT ELEVATION08STREAM BYPASS PLAN09SUMMARY OF WETLAND AND BUFFER IMPACTS10PLANTING PLAN11PLANTING SCHEDULENWS-2020-526
550555548
549551552553554550555547547548549551552553554550550 549549551551552550546
547548549550546547548549551552550547548549551552550548549551552553560556557558
559555555E;ISTING 36 DIAMCONC CULVERTS;3SE SUMMIT LANDSBURG ROADROCK CREEKROCK CREEKOHWLROCK CREEKOHWLROCK CREEKTHALWEGROCK CREEKTHALWEGWETLAND AWETLAND BWETLAND CWETLAND EWETLAND FWETLAND DWETLANDBUFFER TYPSTREAM BUFFERTYPWETLANDBUFFER TYPSTREAM BUFFERTYP03INDE; MAP AND E;ISTING CONDITIONS0160'80APPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEYNWS-2020-526
553552551550549548 548549550
551552
5535525515505495485515525485491150120012501030010400SE SUMMIT LANDSBURG ROADROCK CREEKFLOWDIRECTION04STREAM GRADING PLANAPPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEY04020ROCK CREEKOHWLROCK CREEKTHALWEGWETLAND C294 SFAREA OFDISTURBANCENWS-2020-526
US EDGEOF ROWDS EDGEOF ROWE;ISTING GRADESTATION 126076FG 5469'STATION 116206FG 5475'FINISHED GRADEE;PECTED LONGTERMAVG CHANNEL REGRADEAPPRO; 10 SLOPEE;ISTING 36 DIAM CMPCULVERT ;3US IE 5467'DS IE 5469'E;ISTING THALWEGAVG DS SLOPE 16E;ISTING THALWEGAVG US SLOPE 11S 0654435' BANKFULL WIDTH CHANNELSTREAMBEDGRAVEL, 2' THICKRESTORATION PLANTINGPER PLANTING PLAN TYP2'4'355'4'FILL SCOUR POOLE;ISTING GRADEFINISHED GRADEOHWRESTORATION PLANTINGPER PLANTING PLAN TYP2H:1V2H:1V05STREAM PROFILE AND SECTIONAPPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEY06030TYPICAL CHANNEL SECTIONNOT TO SCALEPROFILENOT TO SCALENWS-2020-526
05010012'0 LANEE;ISTING CULVERTSTO BE REMOVED CREEK STA 07401 CONSTRUCTION STA 130676SE SUMMIT LANDSBURG ROAD10'0WING WALL, TYPFLOWDIRECTIONEDGE OF E;ISTINGPAVEMENTORDINARY HIGHWATER12'0 LANEORDINARY HIGHWATER1300135053'6 CLEAR SPAN548554553551548550551552ORDINARY HIGHWATER550551552553554 CL CL06BRIDGE LAYOUT PLANAPPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEYPLAN020'10'NOTE:ALL UTILITIES MAY NOT BE SHOWN UTILITYLOCATIONS SHOWN ARE APPRO;IMATE ASBUILTLOCATIONS ARE NOT AVAILABLE AT THIS TIMEUTILITY LOCATIONS TO BE DETERMINED DURINGFORTHCOMING DESIGNNWS-2020-526
E;ISTING GROUND 1750'LTE;ISTING GROUND 1750'RT100YEARWSE 5496'53'6 CLEAR SPANE;ISTING CULVERTSTO BE REMOVED, TYPABUTMENT, TYPFOOTING, TYPWING WALL, TYP3'0 MIN FREEBOARDE;ISTING GROUNDAT ℄ CONSTRUCTION1'0MINFINISH GROUND07BRIDGE LAYOUT ELEVATIONAPPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEYELEVATION020'10'NWS-2020-526
550555548
549551552553554550555547547548549551552553554550547548549551552550548549551552553556557558 55511001200130008STREAM BYPASS PLANTEMPORARY ISOLATION BERMTEMPORARY FISH SCREENAPPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEY08040SE SUMMIT LANDSBURG ROADROCK CREEKTEMPORARY 30PIPE ;3NWS-2020-526
APPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEY09SUMMARY OF WETLAND AND BUFFER IMPACTSTABLE 1: SUMMARY OF WETLAND AND STREAM IMPACTSWETLAND OR WATERCOURSE TEMPORARY IMPACTSPERMANENT IMPACTSWETLAND A0 SF0 SFWETLAND B0 SF0 SFWETLAND C0 SF294 SFWETLAND D0 SF0 SFWETLAND E0 SF0 SFWETLAND F0 SF0 SFSTREAM A707 SF1,760 SFTABLE 2. SUMMARY OF TOTAL WETLAND AND BUFFER IMPACTSIMPACT AREATOTAL PERMANENT IMPACT AREA (SF) KING COUNTY (SF) CITY OF KENT (SF)WETLAND294 SF0 SF294 SFWETLAND BUFFER0 SF0 SF0 SFSTREAM BUFFER0 SF0 SF0 SFNO MITIGATION PROPOSEDNWS-2020-526
550555548
549551552553554550555547547548549551552553554550547548549551552550548549551552553556557558 55511001200130010PLANTING PLANHYDROSEEDSTREAM BUFFER PLANTINGAPPLICANT:REFERENCE #:ADJACENT PROPERTY OWNERS:SEE JARPA ATTACHMENT CPURPOSE:LAT/LONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENTKINGSTATE:WASHEET OF 11ROCK CREEKROCK CREEK CULVERT REPLACEMENTCITY OF KENT47 21' 95 N, 122 00' 50 N24607 SE SUMMIT LANDSBURG RD RAVENSDALE, WA 98051NW SEC26 T22N R6ESW SEC26 T22N R6ESITE LOCATION ADDRESS:MAPLE VALLEY08040SE SUMMIT LANDSBURG ROADROCK CREEKNWS-2020-526
STREAM BUFFER PLANTING SCHEDULESCIENTIFIC NAME COMMON NAMESIZESPACING QUANTITYACER CIRCINATUMVINE MAPLE2 GAL 16 FT O.C. 9SAMBUCUS RACEMOSARED ELDERBERRY2 GAL 8 FT O.C. 12HOLODISCUS DISCOLOROCEAN SPRAY2 GAL 8 FT O.C. 12ROSA PISOCARPAPEAFRUIT ROSE1 GAL 4 FT O.C. 50RUBUS SPECTABILISSALMONBERRY1 GAL 4 FT O.C. 50SYMPHORICARPOS ALBUSSNOWBERRY1 GAL 3 FT O.C. 100PLANTING SCHEDULES NOTE: SPACING APPLIES TO SAME PLANT SPECIES WITH PLUGS CLUSTERED IN GROUPS OF 3'S. USE SMALLESTSPACING DIMENSION TO DETERMINE DISTANCE BETWEEN DIFFERENT SPECIES PLANTING LOCATIONS.NOTE: MULCH SHALL BE PLACED THROUGHOUT WETLAND AND STREAM BUFFER PLANTING AREA TO3-INCH DEPTH. ARBORIST MULCH IS ENCOURAGED TO BE USED AS IT CAN BE OBTAINED FOR FREE.USE CHIPDROP.COM.11PLANTING SCHEDULEAPPLICANT:REFERENCE :ADJACENT PROPERTY OWNERS:"SEE JARPA ATTACHMENT C"PURPOSE:LATLONG:PROPOSED PROJECT:WATER BODY:NEAR:COUNTY:DATE: 02, MARCH 2020ENVIRONMENTAL ENHANCEMENT.INGSTATE:WASHEET OF 11ROC. CREE.ROC. CREE. CULVERT REPLACEMENTCITY OF .ENT47° 21' 95" N, 122° 00' 50" N24607 SE SUMMIT LANDSBURG RD. RAVENSDALE, WA 98051NW SEC-26 T-22-N R-6-ESW SEC-26 T-22-N R-6-ESITE LOCATION ADDRESS:MAPLE VALLEYNWS-2020-526
CERTIFICATE OF COMPLIANCE
WITH DEPARTMENT OF THE ARMY PERMIT
Permit Number: NWS-2020-526
Name of Permittee:
Date of Issuance:
Upon completion of the activity authorized by this permit, please check the applicable boxes below, date
and sign this certification, and return it to the following email or mailing address:
Department of the Army
U.S. Army Corps of Engineers
Seattle District, Regulatory Branch
Post Office Box 3755
Seattle, Washington 98124-3755
Please note that your permitted activity is subject to a compliance inspection by a U.S. Army Corps of
Engineers representative. If you fail to comply with the terms and conditions of your authorization, your
permit may be subject to suspension, modification, or revocation.
The work authorized by the above-referenced permit has been completed in accordance with the terms and
conditions of this permit.
Date work complete: __________________________________
Photographs and as-built drawings of the authorized work (OPTIONAL, unless required as a
Special Condition of the permit).
If applicable, the mitigation required (e.g., construction and plantings) in the above-referenced permit has
been completed in accordance with the terms and conditions of this permit (not including future
monitoring).
Date work complete: __________________________________ N/A
Photographs and as-built drawings of the mitigation (OPTIONAL, unless required as a Special
Condition of the permit).
Provide phone number/email for scheduling site visits (must have legal authority to grant property access).
Printed Name: ____________________________________________________________________
Phone Number: __________________________ Email: ___________________________________
Printed Name:
Signature:
Date:
NWS.Compliance@usace.army.mil OR
Kent, City of
May 12, 2021
Rock Creek Culvert Replacement/Lincoln A - 4 June 3, 2021
Project Number: 13-3007.5
APPENDIX D
TRAFFIC CONTROL PLANS
CHANNELIZATION DEVICE SPACING
MPH TAPER TANGENT
40
30
25
40
30
25
80
60
50
35 35 70
45 40 90
50 40 100
55 40 110
60 40 120
65 40 130
Merging Shifting Shoulder
25 or less
30
35
40
45
50
55
60
65
70
75
Taper Length In Feet
42'
60'
82'
107'
180'
200'
220'
240'
260'
280'
300'
200'
250'
305'
360'
425'
495'
570'
645'
730'
820'
155'63'
90'
123'
160'
270'
300'
330'
360'
390'
420'
450'
125'
180'
245'
320'
540'
600'
660'
720'
780'
840'
900'
Speed Buffer
SIGN SPACING
MPH
45+
35
30
25
40
"X"
100'
100'
350'
350'
500'
NOT
DRAWN
TO
SCALE
PERMIT:ADDRESS:
WORK HOURS: ______________________
REQUESTED DATES:__________________
24601 SE Summit Landsburg Rd Ravensdale, WA 98038
Job Summary:S T A T E W I D ES A F E T Y S Y S T E M S
720-343-2335
LEGEND
Type 3 Barricade
Trailer Mounted
Flashing Arrow Board
Sign
Flagger
Truck Mounted
Attenuator
M
Delineation Device
with lights
Portable Changeable
Message Sign (PCMS)
Traffic Flow
Advance Warning
Signs
Delineation DeviceWater barrier
No ParkingP
Hard Closure
Traffic Control Plan # 1
** ALL DEVICES SHALL CONFORM
TO CURRENT MUTCD**
Plan only valid under certification if work
is performed by preparing contractor
PO/JB#
Location: Summit Landsburg Rd
Ravensdale, WA 98038
For:City Of Kent
Name: Stephen Lincoln
Date: January 18, 2021
Drawn By: Alejandro Granillo
ATTSA Cert#: 493198
R
O
A
D
C
L
O
S
E
D ROADCLOSEDROAD
CLOSED
LOCAL TRAFFIC ONLY
DETOUR
SE Kent Kangley RdSE Summit Landsburg RdPVT DWPVT DWPVT DWPVT DW
PVT DWROADCLOSEDLOCAL TRAFFIC ONLYDETOURROADCLOSEDAHEADDETOURAHEADROADCLOSEDAHEAD ROADCLOSEDAHEADROADCLOSEDAHEAD350'
350'350'
350'
350'
DETOUR DE
TOU
R
DETOUR242nd Ave SEwww.statewidess.com
CHANNELIZATION DEVICE SPACING
MPH TAPER TANGENT
40
30
25
40
30
25
80
60
50
35 35 70
45 40 90
50 40 100
55 40 110
60 40 120
65 40 130
Merging Shifting Shoulder
25 or less
30
35
40
45
50
55
60
65
70
75
Taper Length In Feet
42'
60'
82'
107'
180'
200'
220'
240'
260'
280'
300'
200'
250'
305'
360'
425'
495'
570'
645'
730'
820'
155'63'
90'
123'
160'
270'
300'
330'
360'
390'
420'
450'
125'
180'
245'
320'
540'
600'
660'
720'
780'
840'
900'
Speed Buffer
SIGN SPACING
MPH
45+
35
30
25
40
"X"
100'
100'
350'
350'
500'
NOT
DRAWN
TO
SCALE
PERMIT:ADDRESS:
WORK HOURS: ______________________
REQUESTED DATES:__________________
24601 SE Summit Landsburg Rd Ravensdale, WA 98038
Job Summary:S T A T E W I D ES A F E T Y S Y S T E M S
720-343-2335
LEGEND
Type 3 Barricade
Trailer Mounted
Flashing Arrow Board
Sign
Flagger
Truck Mounted
Attenuator
M
Delineation Device
with lights
Portable Changeable
Message Sign (PCMS)
Traffic Flow
Advance Warning
Signs
Delineation DeviceWater barrier
No ParkingP
Detour Route
Traffic Control Plan # 2
** ALL DEVICES SHALL CONFORM
TO CURRENT MUTCD**
Plan only valid under certification if work
is performed by preparing contractor
PO/JB#
Location: Summit Landsburg Rd
Ravensdale, WA 98038
For:City Of Kent
Name: Stephen Lincoln
Date: January 18, 2021
Drawn By: Alejandro Granillo
ATTSA Cert#: 493198MMMDETOURDETOURDETOURDETOUR
DETOUR
DETOUR
DETOURD
E
T
O
U
R DETOURDETOURDETOURDETOURDETOURSE Kent Kangley Rd
SE Summit Landsbu
r
g
R
d
Black Diamond RdLandsburg Rd SESE Ravensd
a
l
e
W
ay268th Ave SE253rd St SE
Summit
Landsburg
Closed
Ahead
www.statewidess.com
Rock Creek Culvert Replacement/Lincoln A - 5 June 3, 2021
Project Number: 13-3007.5
APPENDIX E
PREVAILING WAGE RATES
State of Washington
Department of Labor & Industries
Prevailing Wage Section - Telephone 360-902-5335
PO Box 44540, Olympia, WA 98504-4540
Washington State Prevailing Wage
The PREVAILING WAGES listed here include both the hourly wage rate and the hourly rate of fringe
benefits. On public works projects, worker's wage and benefit rates must add to not less than this
total. A brief description of overtime calculation requirements are provided on the Benefit Code
Key.
Journey Level Prevailing Wage Rates for the Effective Date: 06/08/2021
County_
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
Trade
Asbestos Abatement Workers
Boilermakers
Brick Mason
Brick Mason
Building Service Employees
Building Service Employees
Building Service Employees
Building Service Employees
Cabinet Makers (In Shop).
Carpenters
Carpenters
Carpenters
Carpenters
Carpenters
Carpenters
Carpenters
Cement Masons
King Cement Masons
King Cement Masons
King Cement Masons
King
King
King
King
King
King
King
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Job Classification
Journey Level
Journey Level
Journey Level
Pointer -Caulker -Cleaner
Janitor
Traveling Waxer/Shampooer
Window Cleaner (Non -Scaffold)
Window Cleaner (Scaffold)
Journey Level
Acoustical Worker
Carpenter
Carpenters on Stationary Tools
Creosoted Material
Floor Finisher
Floor Layer
Scaffold Erector
Application of all Composition
Mastic
Application of all Epoxy
Material
Application of all Plastic
Material
Application of Sealing
Compound
Application of Underlayment
Building General
Composition or Kalman Floors
Concrete Paving
Curb Et Gutter Machine
Curb Et Gutter, Sidewalks
Curing Concrete
Wage Holiday Overtime Note
$52.39
$70.79
$60.57
$60.57
$26.28
$26.63
$29.98
$30.98
$22.74
$64.94
$64.94
$65.07
$65.07
$64.94
$64.94
$64.94
$64.84
5D
5N
7E
7E
5S
5S
5S
5S
7A
7A
7A
7A
7A
7A
7A
7A
$64.34 7A
$64.84 7A
$64.34 7A
1H
1C
1N
1N
2F
2F
2F
2F
1
4C
4C
4C
4C
4C
4C
4C
4U
*Risk
Class
View
View
View
View
View
View
View
View
View
View
View
View
View
View
View
View
View
4U
View
4U
View
4U
View
$64.84
7A
41J
View
$64.34
7A
41J
View
$64.84
7A
41J
View
$64.34
7A
41J
View
$64.84
7A
41J
View
$64.34
7A
41J
View
$64.34
7A
41J
View
King
King
King
King
King
King
King
King
King
King
King
King
King
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
Cement Masons
King
Cement
Masons
King
Cement
Masons
King
Cement
Masons
King
Cement
Masons
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
King
Cement Masons
Divers Et Tenders
Divers Et Tenders
Divers Et Tenders
Divers Et Tenders
Divers Et Tenders
Divers Et Tenders
Divers Et Tenders
Divers Et Tenders
Divers Et Tenders
Dredge Workers
Dredge Workers
Dredge Workers
Dredge Workers
Dredge Workers
Dredge Workers
Dredge Workers
Drywall Applicator
Drywall Tapers
Electrical Fixture Maintenance
Workers
Electricians - Inside
Electricians - Inside
Electricians - Inside
Finish Colored Concrete
Floor Grinding
Floor Grinding/Polisher
Green Concrete Saw, self -
powered
Grouting of all Plates
Grouting of all Tilt -up Panels
Gunite Nozzleman
Hand Powered Grinder
Journey Level
Patching Concrete
Pneumatic Power Tools
Power Chipping Et Brushing
Sand Blasting Architectural
Finish
Screed Et Rodding Machine
Spackling or Skim Coat
Concrete
Troweling Machine Operator
Troweling Machine Operator on
Colored Slabs
Tunnel Workers
Bell/Vehicle or Submersible
Operator (Not Under Pressure)
Dive Supervisor/Master
Diver
Diver On Standby
Diver Tender
Manifold Operator
Manifold Operator Mixed Gas
Remote Operated Vehicle
Operator/Technician
Remote Operated Vehicle
Tender
Assistant Engineer
Assistant Mate (Deckhand)
Boatmen
Engineer Welder
Leverman, Hydraulic
Mates
Oiler
Journey Level
Journey Level
Journey Level
$64.84 7A 4U View
$64.84 7A 4U View
$64.34 7A 4U View
$64.84 7A 4U View
$64.34
7A
4U
View
$64.34
7A
4U
View
$64.84
7A
4U
View
$64.84
7A
4U
View
$64.34
7A
4U
View
$64.34
7A
4U
View
$64.84
7A
4U
View
$64.84
7A
4U
View
$64.84
7A
4U
View
$64.84 7A 4U View
$64.34 7A 4U View
$64.84 7A 4U View
$64.84 7A 4U View
$64.84 7A 4U View
$118.80 7A 4C View
$81.98
7A
4C
View
$118.80
7A
4C
8V View
$76.98
7A
4C
View
$69.91
7A
4C
View
$69.91
7A
4C
View
$74.91
7A
4C
View
$69.91
7A
4C
View
$65.19 7A 4C View
$70.62
5D
3F
View
$70.07
5D
3F
View
$70.62
5D
3F
View
$71.97
5D
3F
View
$73.41
5D
3F
View
$70.62
5D
3F
View
$70.07
5D
3F
View
$64.94
5D
1 H
View
$65.31
5P
1 E
View
$31.99
5L
1 E
View
Cable Splicer $92.57 7C 4E View
Cable Splicer (tunnel) $99.46 7C 4E View
Certified Welder $89.44 7C 4E View
King
Electricians - Inside
Certified Welder (tunnel)
$96.02
7C
4E
View
King
Electricians - Inside
Construction Stock Person
$44.78
7C
4E
View
King
Electricians - Inside
Journey Level
$86.30
7C
4E
View
King
Electricians - Inside
Journey Level (tunnel)
$92.57
7C
4E
View
King
Electricians - Motor Shop
Journey Level
$47.53
5A
1 B
View
King
Electricians - Powerline
Cable Splicer
$82.39
5A
4D
View
Construction
King
Electricians - Powerline
Certified Line Welder
$75.64
5A
4D
View
Construction
King
Electricians - Powerline
Groundperson
$49.17
5A
4D
View
Construction
King
Electricians - Powerline
Heavy Line Equipment
$75.64
5A
4D
View
Construction
Operator
King
Electricians - Powerline
Journey Level Lineperson
$75.64
5A
4D
View
Construction
King
Electricians - Powerline
Line Equipment Operator
$64.54
5A
4D
View
Construction
King
Electricians - Powerline
Meter Installer
$49.17
5A
4D
8W
View
Construction
King
Electricians - Powerline
Pole Sprayer
$75.64
5A
4D
View
Construction
King
Electricians - Powerline
Powderperson
$56.49
5A
4D
View
Construction
King
Electronic Technicians
Journey Level
$53.57
7E
1 E
View
King
Elevator Constructors
Mechanic
$100.51
7D
4A
View
King
Elevator Constructors
Mechanic In Charge
$108.53
7D
4A
View
King
Fabricated Precast Concrete
All Classifications - In -Factory
$18.25
5B
1 R
View
Products
Work Only
King
Fence Erectors
Fence Erector
$44.40
7A
4V
8Y
View
King
Fence Erectors
Fence Laborer
$44.40
7A
4V
8Y
View
King
Flaggers
Journey Level
$44.40
7A
4V
8Y
View
King
Glaziers
Journey Level
$69.26
7L
1Y
View
King
Heat Et Frost Insulators And
Journeyman
$79.43
5J
4H
View
Asbestos Workers
King
Heating Equipment Mechanics
Journey Level
$89.61
7F
1 E
View
King
Hod Carriers Et Mason Tenders
Journey Level
$54.01
7A
4V
8Y
View
King
Industrial Power Vacuum
Journey Level
$13.69
1
View
Cleaner
King
Inland Boatmen
Boat Operator
$61.41
5B
1 K
View
King
Inland Boatmen
Cook
$56.48
5B
1 K
View
King
Inland Boatmen
Deckhand
$57.48
5B
1 K
View
King
Inland Boatmen
Deckhand Engineer
$58.81
5B
1 K
View
King
Inland Boatmen
Launch Operator
$58.89
5B
1 K
View
King
Inland Boatmen
Mate
$57.31
5B
1 K
View
King
Inspection/Cleaning/Sealing Of
Cleaner Operator, Foamer
$31.49
1
View
Sewer Et Water Systems By
Operator
Remote Control
King
Inspection/Cleaning/Sealing Of
Grout Truck Operator
$13.69
1
View
Sewer Et Water Systems By
Remote Control
King
Inspection/Cleaning/Sealing Of
Head Operator
$24.91
1
View
Sewer Et Water Systems By
Remote Control
King
Inspection/Cleaning/Sealing Of
Technician
$19.33
1
View
Sewer Et Water Systems By
Remote Control
King
Inspection/Cleaning/Sealing Of
Tv Truck Operator
$20.45
1
View
Sewer Et Water Systems By
Remote Control
King
Insulation Applicators
Journey Level
$64.94
7A
4C
T
View
King
Ironworkers
Journeyman
$76.78
7N
10
View
King
Laborers
Air, Gas Or Electric Vibrating
$52.39
7A
4V
8Y
View
Screed
King
Laborers
Airtrac Drill Operator
$54.01
7A
4V
8Y
View
King
Laborers
Ballast Regular Machine
$52.39
7A
4V
8Y
View
King
Laborers
Batch Weighman
$44.40
7A
4V
8Y
View
King
Laborers
Brick Pavers
$52.39
7A
4V
8Y
View
King
Laborers
Brush Cutter
$52.39
7A
4V
8Y
View
King
Laborers
Brush Hog Feeder
$52.39
7A
4V
8Y
View
King
Laborers
Burner
$52.39
7A
4V
8Y
View
King
Laborers
Caisson Worker
$54.01
7A
4V
8Y
View
King
Laborers
Carpenter Tender
$52.39
7A
4V
8Y
View
King
Laborers
Cement Dumper -paving
$53.35
7A
4V
8Y
View
King
Laborers
Cement Finisher Tender
$52.39
7A
4V
8Y
View
King
Laborers
Change House Or Dry Shack
$52.39
7A
4V
8Y
View
King
Laborers
Chipping Gun (30 Lbs. And
$53.35
7A
4V
8Y
View
Over)
King
Laborers
Chipping Gun (Under 30 Lbs.)
$52.39
7A
4V
8Y
View
King
Laborers
Choker Setter
$52.39
7A
4V
8Y
View
King
Laborers
Chuck Tender
$52.39
7A
4V
8Y
View
King
Laborers
Clary Power Spreader
$53.35
7A
4V
8Y
View
King
Laborers
Clean-up Laborer
$52.39
7A
4V
8Y
View
King
Laborers
Concrete Dumper/Chute
$53.35
7A
4V
8Y
View
Operator
King
Laborers
Concrete Form Stripper
$52.39
7A
4V
8Y
View
King
Laborers
Concrete Placement Crew
$53.35
7A
4V
8Y
View
King
Laborers
Concrete Saw Operator/Core
$53.35
7A
4V
8Y
View
Driller
King
Laborers
Crusher Feeder
$44.40
7A
4V
8Y
View
King
Laborers
Curing Laborer
$52.39
7A
4V
8Y
View
King
Laborers
Demolition: Wrecking Et Moving
$52.39
7A
4V
8Y
View
(Incl. Charred Material)
King
Laborers
Ditch Digger
$52.39
7A
4V
8Y
View
King
Laborers
Diver
$54.01
7A
4V
8Y
View
King
Laborers
Drill Operator (Hydraulic,
$53.35
7A
4V
8Y
View
Diamond)
King
Laborers
Dry Stack Walls
$52.39
7A
4V
8Y
View
King
Laborers
Dump Person
$52.39
7A
4V
8Y
View
King
Laborers
Epoxy Technician
$52.39
7A
4V
8Y
View
King
Laborers
Erosion Control Worker
$52.39
7A
4V
8Y
View
King
Laborers
Faller Et Bucker Chain Saw
$53.35
7A
4V
8Y
View
King
Laborers
Fine Graders
$52.39
7A
4V
8Y
View
King
Laborers
Firewatch
$44.40
7A
4V
8Y
View
King
Laborers
Form Setter
$52.39
7A
4V
8Y
View
King
Laborers
Gabian Basket Builders
$52.39
7A
4V
8Y
View
King
Laborers
General Laborer
$52.39
7A
4V
8Y
View
King
Laborers
Grade Checker Et Transit Person
$54.01
7A
4V
8Y
View
King
Laborers
Grinders
$52.39
7A
4V
8Y
View
King
Laborers
Grout Machine Tender
$52.39
7A
4V
8Y
View
King
Laborers
Groutmen (Pressure) Including
$53.35
7A
4V
8Y
View
Post Tension Beams
King
Laborers
Guardrail Erector
$52.39
7A
4V
8Y
View
King
Laborers
Hazardous Waste Worker (Level
$54.01
7A
4V
8Y
View
A)
King
Laborers
Hazardous Waste Worker (Level
$53.35
7A
4V
8Y
View
B)
King
Laborers
Hazardous Waste Worker (Level
$52.39
7A
4V
8Y
View
C)
King
Laborers
High Scaler
$54.01
7A
4V
8Y
View
King
Laborers
Jackhammer
$53.35
7A
4V
8Y
View
King
Laborers
Laserbeam Operator
$53.35
7A
4V
8Y
View
King
Laborers
Maintenance Person
$52.39
7A
4V
8Y
View
King
Laborers
Manhole Builder-Mudman
$53.35
7A
4V
8Y
View
King
Laborers
Material Yard Person
$52.39
7A
4V
8Y
View
King
Laborers
Motorman -Dinky Locomotive
$53.35
7A
4V
8Y
View
King
Laborers
Nozzleman (Concrete Pump,
$53.35
7A
4V
8Y
View
Green Cutter When Using
Combination Of High Pressure
Air Et Water On Concrete Et
Rock, Sandblast, Gunite,
Shotcrete, Water Blaster,
Vacuum Blaster)
King
Laborers
Pavement Breaker
$53.35
7A
4V
8Y
View
King
Laborers
Pilot Car
$44.40
7A
4V
8Y
View
King
Laborers
Pipe Layer Lead
$54.01
7A
4V
8Y
View
King
Laborers
Pipe Layer/Tailor
$53.35
7A
4V
8Y
View
King
Laborers
Pipe Pot Tender
$53.35
7A
4V
8Y
View
King
Laborers
Pipe Reliner
$53.35
7A
4V
8Y
View
King
Laborers
Pipe Wrapper
$53.35
7A
4V
8Y
View
King
Laborers
Pot Tender
$52.39
7A
4V
8Y
View
King
Laborers
Powderman
$54.01
7A
4V
8Y
View
King
Laborers
Powderman's Helper
$52.39
7A
4V
8Y
View
King
Laborers
Power Jacks
$53.35
7A
4V
8Y
View
King
Laborers
Railroad Spike Puller - Power
$53.35
7A
4V
8Y
View
King
Laborers
Raker - Asphalt
$54.01
7A
4V
8Y
View
King
Laborers
Re-timberman
$54.01
7A
4V
8Y
View
King
Laborers
Remote Equipment Operator
$53.35
7A
4V
8Y
View
King
Laborers
Rigger/Signal Person
$53.35
7A
4V
8Y
View
King
Laborers
Rip Rap Person
$52.39
7A
4V
8Y
View
King
Laborers
Rivet Buster
$53.35
7A
4V
8Y
View
King
Laborers
Rodder
$53.35
7A
4V
8Y
View
King
Laborers
Scaffold Erector
$52.39
7A
4V
8Y
View
King
Laborers
Scale Person
$52.39
7A
4V
8Y
View
King
Laborers
Sloper (Over 20")
$53.35
7A
4V
8Y
View
King
Laborers
Sloper Sprayer
$52.39
7A
4V
8Y
View
King
Laborers
Spreader (Concrete)
$53.35
7A
4V
8Y
View
King
Laborers
Stake Hopper
$52.39
7A
4V
8Y
View
King
Laborers
Stock Piler
$52.39
7A
4V
8Y
View
King
Laborers
Swinging Stage/Boatswain
$44.40
7A
4V
8Y
View
Chair
King
Laborers
Tamper Et Similar Electric, Air
$53.35
7A
4V
8Y
View
Et Gas Operated Tools
King
Laborers
Tamper (Multiple Et Self-
$53.35
7A
4V
8Y
View
propelled)
King
Laborers
Timber Person - Sewer (Lagger,
$53.35
7A
4V
8Y
View
Shorer Et Cribber)
King
Laborers
Toolroom Person (at Jobsite)
$52.39
7A
4V
8Y
View
King
Laborers
Topper
$52.39
7A
4V
8Y
View
King
Laborers
Track Laborer
$52.39
7A
4V
8Y
View
King
Laborers
Track Liner (Power)
$53.35
7A
4V
8Y
View
King
Laborers
Traffic Control Laborer
$47.48
7A
4V
9C
View
King
Laborers
Traffic Control Supervisor
$50.31
7A
4V
9C
View
King
Laborers
Truck Spotter
$52.39
7A
4V
8Y
View
King
Laborers
Tugger Operator
$53.35
7A
4V
8Y
View
King
Laborers
Tunnel Work -Compressed Air
$129.67
7A
4V
9B
View
Worker 0-30 psi
King
Laborers
Tunnel Work -Compressed Air
$134.70
7A
4V
9B
View
Worker 30.01-44.00 psi
King
Laborers
Tunnel Work -Compressed Air
$138.38
7A
4V
9B
View
Worker 44.01-54.00 psi
King
Laborers
Tunnel Work -Compressed Air
$144.08
7A
4V
9B
View
Worker 54.01-60.00 psi
King
Laborers
Tunnel Work -Compressed Air
$146.20
7A
4V
9B
View
Worker 60.01-64.00 psi
King
Laborers
Tunnel Work -Compressed Air
$151.30
7A
4V
9B
View
Worker 64.01-68.00 psi
King
Laborers
Tunnel Work -Compressed Air
$153.20
7A
4V
9B
View
Worker 68.01-70.00 psi
King
Laborers
Tunnel Work -Compressed Air
$155.20
7A
4V
9B
View
Worker 70.01-72.00 psi
King
Laborers
Tunnel Work -Compressed Air
$157.20
7A
4V
9B
View
Worker 72.01-74.00 psi
King
Laborers
Tunnel Work-Guage and Lock
$54.11
7A
4V
8Y
View
Tender
King
Laborers
Tunnel Work -Miner
$54.11
7A
4V
8Y
View
King
Laborers
Vibrator
$53.35
7A
4V
8Y
View
King
Laborers
Vinyl Seamer
$52.39
7A
4V
8Y
View
King
Laborers
Watchman
$40.36
7A
4V
8Y
View
King
Laborers
Welder
$53.35
7A
4V
8Y
View
King
Laborers
Well Point Laborer
$53.35
7A
4V
8Y
View
King
Laborers
Window Washer/Cleaner
$40.36
7A
4V
8Y
View
King
Laborers - Underground Sewer
General Laborer Et Topman
$52.39
7A
4V
8Y
View
Et Water
King
Laborers - Underground Sewer
Pipe Layer
$53.35
7A
4V
8Y
View
Et Water
King
Landscape Construction
Landscape
$40.36
7A
4V
8Y
View
Construction/Landscaping Or
Planting Laborers
King
Landscape Construction
Landscape Operator
$72.28
7A
3K
8X
View
King
Landscape Maintenance
Groundskeeper
$17.87
1
View
King
Lathers
Journey Level
$64.94
5D
1 H
View
King
Marble Setters
Journey Level
$60.57
7E
1 N
View
King
Metal Fabrication (In Shop).
Journey Level
$41.70
15F
11A
View
King
Millwright
Journey Level
$66.44
7A
4C
View
King
Modular Buildings
Cabinet Assembly
$13.69
1
View
King
Modular Buildings
Electrician
$13.69
1
View
King
Modular Buildings
Equipment Maintenance
$13.69
1
View
King
Modular Buildings
Plumber
$13.69
1
View
King
Modular Buildings
Production Worker
$13.69
1
View
King
Modular Buildings
Tool Maintenance
$13.69
1
View
King
Modular Buildings
Utility Person
$13.69
1
View
King
Modular Buildings
Welder
$13.69
1
View
King
Painters
Journey Level
$45.40
6Z
2B
View
King
Pile Driver
Crew Tender
$69.91
7A
4C
View
King
Pile Driver
Crew Tender/Technician
$69.91
7A
4C
View
King
Pile Driver
Hyperbaric Worker -
$80.76
7A
4C
View
Compressed Air Worker 0-30.00
PSI
King
Pile Driver
Hyperbaric Worker -
$85.76
7A
4C
View
Compressed Air Worker 30.01
44.00 PSI
King
Pile Driver
Hyperbaric Worker -
$89.76
7A
4C
View
Compressed Air Worker 44.01 -
54.00 PSI
King
Pile Driver
Hyperbaric Worker -
$94.76
7A
4C
View
Compressed Air Worker 54.01
60.00 PSI
King
Pile Driver
Hyperbaric Worker -
$97.26
7A
4C
View
Compressed Air Worker 60.01 -
64.00 PSI
King
Pile Driver
Hyperbaric Worker -
$102.26
7A
4C
View
Compressed Air Worker 64.01
68.00 PSI
King
Pile Driver
Hyperbaric Worker -
$104.26
7A
4C
View
Compressed Air Worker 68.01
70.00 PSI
King
Pile Driver
Hyperbaric Worker -
$106.26
7A
4C
View
Compressed Air Worker 70.01 -
72.00 PSI
King
Pile Driver
Hyperbaric Worker -
$108.26
7A
4C
View
Compressed Air Worker 72.01
74.00 PSI
King
Pile Driver
Journey Level
$65.19
7A
4C
View
King
Plasterers
Journey Level
$61.67
M
1 R
View
King
Playground Et Park Equipment
Journey Level
$13.69
1
View
Installers
King
Plumbers & Pipefitters
Journey Level
$92.19
6Z
1G
View
King
Power Equipment Operators
Asphalt Plant Operators
$73.49
7A
3K
8X
View
King
Power Equipment Operators
Assistant Engineer
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Barrier Machine (zipper)
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Batch Plant Operator: concrete
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Bobcat
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Brokk - Remote Demolition
$69.12
7A
3K
8X
View
Equipment
King
Power Equipment Operators
Brooms
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Bump Cutter
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Cableways
$73.49
7A
3K
8X
View
King
Power Equipment Operators
Chipper
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Compressor
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Concrete Finish Machine -
$69.12
7A
3K
8X
View
Laser Screed
King
Power Equipment Operators
Concrete Pump - Mounted Or
$72.28
7A
3K
8X
View
Trailer High Pressure Line
Pump, Pump High Pressure
King
Power Equipment Operators
Concrete Pump: Truck Mount
$73.49
7A
3K
8X
View
With Boom Attachment Over 42
M
King
Power Equipment Operators
Concrete Pump: Truck Mount
$72.84
7A
3K
8X
View
With Boom Attachment Up To
42m
King
Power Equipment Operators
Conveyors
$72.28
7A
3K
8X
View
King
Power Equipment Operators
Cranes friction: 200 tons and
$75.72
7A
3K
8X
View
over
King
Power Equipment Operators
Cranes: 100 tons through 199
$74.22
7A
3K
8X
View
tons, or 150' of boom
(including jib with
attachments)
King
Power Equipment Operators
Cranes: 20 Tons Through 44
$72.84
7A
3K
8X
View
Tons With Attachments
King
Power Equipment Operators
Cranes: 200 tons- 299 tons, or
$74.99
7A
3K
8X
View
250' of boom including jib with
attachments
King
Power Equipment Operators
Cranes: 300 tons and over or
$75.72
7A
3K
8X
View
300' of boom including jib with
attachments
King
Power Equipment Operators
Cranes: 45 Tons Through 99
$73.49
7A
3K
8X
View
Tons, Under 150' Of Boom
(including Jib With
Attachments)
King
Power Equipment Operators
Cranes: A -frame - 10 Tons And
$69.12
7A
3K
8X
View
Under
King
Power Equipment Operators
Cranes: Friction cranes through
$74.99
7A
3K
8X
View
199 tons
King
Power Equipment Operators
Cranes: through 19 tons with
$72.28
7A
3K
8X
View
attachments, A -frame over 10
tons
King
Power Equipment Operators
Crusher
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Deck Engineer/Deck Winches
$72.84
7A
3K
8X
View
(power)
King
Power Equipment Operators
Derricks, On Building Work
$73.49
7A
3K
8X
View
King
Power Equipment Operators
Dozers D-9 Ft Under
$72.28
7A
3K
8X
View
King
Power Equipment Operators
Drill Oilers: Auger Type, Truck
$72.28
7A
3K
8X
View
Or Crane Mount
King
Power Equipment Operators
Drilling Machine
$74.22
7A
3K
8X
View
King
Power Equipment Operators
Elevator And Man -lift:
$69.12
7A
3K
8X
View
Permanent And Shaft Type
King
Power Equipment Operators
Finishing Machine, Bidwell And
$72.84
7A
3K
8X
View
Gamaco Et Similar Equipment
King
Power Equipment Operators
Forklift: 3000 Lbs And Over
$72.28
7A
3K
8X
View
With Attachments
King
Power Equipment Operators
Forklifts: Under 3000 Lbs. With
$69.12
7A
3K
8X
View
Attachments
King
Power Equipment Operators
Grade Engineer: Using Blue
$72.84
7A
3K
8X
View
Prints, Cut Sheets, Etc
King
Power Equipment Operators
Gradechecker/Stakeman
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Guardrail Punch
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Hard Tail End Dump
$73.49
7A
3K
8X
View
Articulating Off- Road
Equipment 45 Yards. &t Over
King
Power Equipment Operators
Hard Tail End Dump
$72.84
7A
3K
8X
View
Articulating Off -road
Equipment Under 45 Yards
King
Power Equipment Operators
Horizontal/Directional Drill
$72.28
7A
3K
8X
View
Locator
King
Power Equipment Operators
Horizontal/Directional Drill
$72.84
7A
3K
8X
View
Operator
King
Power Equipment Operators
Hydralifts/Boom Trucks Over
$72.28
7A
3K
8X
View
10 Tons
King
Power Equipment Operators
Hydralifts/Boom Trucks, 10
$69.12
7A
3K
8X
View
Tons And Under
King
Power Equipment Operators
Loader, Overhead 8 Yards. Ft
$74.22
7A
3K
8X
View
Over
King
Power Equipment Operators
Loader, Overhead, 6 Yards. But
$73.49
7A
3K
8X
View
Not Including 8 Yards
King
Power Equipment Operators
Loaders, Overhead Under 6
$72.84
7A
3K
8X
View
Yards
King
Power Equipment Operators
Loaders, Plant Feed
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Loaders: Elevating Type Belt
$72.28
7A
3K
8X
View
King
Power Equipment Operators
Locomotives, All
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Material Transfer Device
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Mechanics, All (leadmen -
$74.22
7A
3K
8X
View
$0.50 Per Hour Over Mechanic)
King
Power Equipment Operators
Motor Patrol Graders
$73.49
7A
3K
8X
View
King
Power Equipment Operators
Mucking Machine, Mole, Tunnel
$73.49
7A
3K
8X
View
Drill, Boring, Road Header
And/or Shield
King
Power Equipment Operators
Oil Distributors, Blower
$69.12
7A
3K
8X
View
Distribution E. Mulch Seeding
Operator
King
Power Equipment Operators
Outside Hoists (Elevators And
$72.28
7A
3K
8X
View
Manlifts), Air Tuggers, Strato
King
Power Equipment Operators
Overhead, Bridge Type Crane:
$72.84
7A
3K
8X
View
20 Tons Through 44 Tons
King
Power Equipment Operators
Overhead, Bridge Type: 100
$74.22
7A
3K
8X
View
Tons And Over
King
Power Equipment Operators
Overhead, Bridge Type: 45 Tons
$73.49
7A
3K
8X
View
Through 99 Tons
King
Power Equipment Operators
Pavement Breaker
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Pile Driver (other Than Crane
$72.84
7A
3K
8X
View
Mount)
King
Power Equipment Operators
Plant Oiler - Asphalt, Crusher
$72.28
7A
3K
8X
View
King
Power Equipment Operators
Posthole Digger, Mechanical
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Power Plant
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Pumps - Water
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Quad 9, Hd 41, D10 And Over
$73.49
7A
3K
8X
View
King
Power Equipment Operators
Quick Tower - No Cab, Under
$69.12
7A
3K
8X
View
100 Feet In Height Based To
Boom
King
Power Equipment Operators
Remote Control Operator On
$73.49
7A
3K
8X
View
Rubber Tired Earth Moving
Equipment
King
Power Equipment Operators
Rigger and Bellman
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Rigger/Signal Person, Bellman
$72.28
7A
3K
8X
View
(Certified)
King
Power Equipment Operators
Rollagon
$73.49
7A
3K
8X
View
King
Power Equipment Operators
Roller, Other Than Plant Mix
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Roller, Plant Mix Or Multi -lift
$72.28
7A
3K
8X
View
Materials
King
Power Equipment Operators
Roto-mill, Roto-grinder
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Saws - Concrete
$72.28
7A
3K
8X
View
King
Power Equipment Operators
Scraper, Self Propelled Under
$72.84
7A
3K
8X
View
45 Yards
King
Power Equipment Operators
Scrapers - Concrete Et Carry All
$72.28
7A
3K
8X
View
King
Power Equipment Operators
Scrapers, Self-propelled: 45
$73.49
7A
3K
8X
View
Yards And Over
King
Power Equipment Operators
Service Engineers - Equipment
$72.28
7A
3K
8X
View
King
Power Equipment Operators
Shotcrete/Gunite Equipment
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Shovel, Excavator, Backhoe,
$72.28
7A
3K
8X
View
Tractors Under 15 Metric Tons
King
Power Equipment Operators
Shovel, Excavator, Backhoe:
$73.49
7A
3K
8X
View
Over 30 Metric Tons To 50
Metric Tons
King
Power Equipment Operators
Shovel, Excavator, Backhoes,
$72.84
7A
3K
8X
View
Tractors: 15 To 30 Metric Tons
King
Power Equipment Operators
Shovel, Excavator, Backhoes:
$74.22
7A
3K
8X
View
Over 50 Metric Tons To 90
Metric Tons
King
Power Equipment Operators
Shovel, Excavator, Backhoes:
$74.99
7A
3K
8X
View
Over 90 Metric Tons
King
Power Equipment Operators
Slipform Pavers
$73.49
7A
3K
8X
View
King
Power Equipment Operators
Spreader, Topsider Et
$73.49
7A
3K
8X
View
Screedman
King
Power Equipment Operators
Subgrader Trimmer
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Tower Bucket Elevators
$72.28
7A
3K
8X
View
King
Power Equipment Operators
Tower Crane Up To 175' In
$74.22
7A
3K
8X
View
Height Base To Boom
King
Power Equipment Operators
Tower Crane: over 175' through
$74.99
7A
3K
8X
View
250' in height, base to boom
King
Power Equipment Operators
Tower Cranes: over 250' in
$75.72
7A
3K
8X
View
height from base to boom
King
Power Equipment Operators
Transporters, All Track Or Truck
$73.49
7A
3K
8X
View
Type
King
Power Equipment Operators
Trenching Machines
$72.28
7A
3K
8X
View
King
Power Equipment Operators
Truck Crane Oiler/driver - 100
$72.84
7A
3K
8X
View
Tons And Over
King
Power Equipment Operators
Truck Crane Oiler/Driver Under
$72.28
7A
3K
8X
View
100 Tons
King
Power Equipment Operators
Truck Mount Portable Conveyor
$72.84
7A
3K
8X
View
King
Power Equipment Operators
Welder
$73.49
7A
3K
8X
View
King
Power Equipment Operators
Wheel Tractors, Farman Type
$69.12
7A
3K
8X
View
King
Power Equipment Operators
Yo Yo Pay Dozer
$72.84
7A
3K
8X
View
King
Power Equipment Operators-
Asphalt Plant Operators
$73.49
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Assistant Engineer
$69.12
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Barrier Machine (zipper)
$72.84
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Batch Plant Operator, Concrete
$72.84
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Bobcat
$69.12
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Brokk - Remote Demolition
$69.12
7A
3K
8X
View
Underground Sewer Et Water
Equipment
King
Power Equipment Operators-
Brooms
$69.12
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Bump Cutter
$72.84
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Cableways
$73.49
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Chipper
$72.84
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Compressor
$69.12
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Concrete Finish Machine -
$69.12
7A
3K
8X
View
Underground Sewer Et Water
Laser Screed
King
Power Equipment Operators-
Concrete Pump - Mounted Or
$72.28
7A
3K
8X
View
Underground Sewer Et Water
Trailer High Pressure Line
Pump, Pump High Pressure
King
Power Equipment Operators-
Concrete Pump: Truck Mount
$73.49
7A 3K 8X View
Underground Sewer Et Water
With Boom Attachment Over 42
M
King
Power Equipment Operators-
Concrete Pump: Truck Mount
$72.84
7A 3K 8X View
Underground Sewer Et Water
With Boom Attachment Up To
42m
King
Power Equipment Operators-
Conveyors
$72.28
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Cranes friction: 200 tons and
$75.72
7A 3K 8X View
Underground Sewer Et Water
over
King
Power Equipment Operators-
Cranes: 100 tons through 199
$74.22
7A 3K 8X View
Underground Sewer Et Water
tons, or 150' of boom
(including jib with
attachments)
King
Power Equipment Operators-
Cranes: 20 Tons Through 44
$72.84
7A 3K 8X View
Underground Sewer Et Water
Tons With Attachments
King
Power Equipment Operators-
Cranes: 200 tons- 299 tons, or
$74.99
7A 3K 8X View
Underground Sewer Et Water
250' of boom including jib with
attachments
King
Power Equipment Operators-
Cranes: 300 tons and over or
$75.72
7A 3K 8X View
Underground Sewer Et Water
300' of boom including jib with
attachments
King
Power Equipment Operators-
Cranes: 45 Tons Through 99
$73.49
7A 3K 8X I View
Underground Sewer Et Water
Tons, Under 150' Of Boom
(including Jib With
Attachments)
King
Power Equipment Operators-
Cranes: A -frame - 10 Tons And
$69.12
7A 3K 8X View
Underground Sewer Et Water
Under
King
Power Equipment Operators-
Cranes: Friction cranes through
$74.99
7A 3K 8X View
Underground Sewer Et Water
199 tons
King
Power Equipment Operators-
Cranes: through 19 tons with
$72.28
7A 3K 8X View
Underground Sewer Et Water
attachments, A -frame over 10
I
tons
King
Power Equipment Operators-
Crusher
$72.84
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Deck Engineer/Deck Winches
$72.84
7A 3K 8X View
Underground Sewer Et Water
(power)
King
Power Equipment Operators-
Derricks, On Building Work
$73.49
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Dozers D-9 Et Under
$72.28
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Drill Oilers: Auger Type, Truck
$72.28
7A 3K 8X View
Underground Sewer Et Water
Or Crane Mount
King
Power Equipment Operators-
Drilling Machine
$74.22
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Elevator And Man -lift:
$69.12
7A 3K 8X View
Underground Sewer Et Water
Permanent And Shaft Type
King
Power Equipment Operators-
Finishing Machine, Bidwell And
$72.84
7A 3K 8X View
Underground Sewer Et Water
Gamaco Et Similar Equipment
King
Power Equipment Operators-
Forklift: 3000 Lbs And Over
$72.28
7A 3K 8X View
Underground Sewer Et Water
With Attachments
King
Power Equipment Operators-
Forklifts: Under 3000 Lbs. With
$69.12
7A 3K 8X View
Underground Sewer Et Water
Attachments
King
Power Equipment Operators-
Grade Engineer: Using Blue
$72.84
7A 3K 8X View
Underground Sewer Et Water
Prints, Cut Sheets, Etc
King
Power Equipment Operators-
Gradechecker/Stakeman
$69.12
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Guardrail Punch
$72.84
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Hard Tail End Dump
$73.49
7A 3K 8X View
Underground Sewer Et Water
Articulating Off- Road
Equipment 45 Yards. Et Over
King
Power Equipment Operators-
Hard Tail End Dump
$72.84
7A 3K 8X View
Underground Sewer Et Water
Articulating Off -road
Equipment Under 45 Yards
King
Power Equipment Operators-
Horizontal/Directional Drill
$72.28
7A 3K 8X View
Underground Sewer Et Water
Locator
King
Power Equipment Operators-
Horizontal/Directional Drill
$72.84
7A 3K 8X View
Underground Sewer Et Water
Operator
King
Power Equipment Operators-
Hydralifts/Boom Trucks Over
$72.28
7A 3K 8X View
Underground Sewer Et Water
10 Tons
King
Power Equipment Operators-
Hydralifts/Boom Trucks, 10
$69.12
7A 3K 8X View
Underground Sewer Et Water
Tons And Under
King
Power Equipment Operators-
Loader, Overhead 8 Yards. Et
$74.22
7A 3K 8X View
Underground Sewer Et Water
Over
King
Power Equipment Operators-
Loader, Overhead, 6 Yards. But
$73.49
7A 3K 8X View
Underground Sewer Et Water
Not Including 8 Yards
King
Power Equipment Operators-
Loaders, Overhead Under 6
$72.84
7A 3K 8X View
Underground Sewer Et Water
Yards
King
Power Equipment Operators-
Loaders, Plant Feed
$72.84
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Loaders: Elevating Type Belt
$72.28
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Locomotives, All
$72.84
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Material Transfer Device
$72.84
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Mechanics, All (leadmen -
$74.22
7A 3K 8X View
Underground Sewer Et Water
$0.50 Per Hour Over Mechanic)
King
Power Equipment Operators-
Motor Patrol Graders
$73.49
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Mucking Machine, Mole, Tunnel
$73.49
7A 3K 8X View
Underground Sewer Et Water
Drill, Boring, Road Header
And/or Shield
King
Power Equipment Operators-
Oil Distributors, Blower
$69.12
7A 3K 8X View
Underground Sewer Et Water
Distribution Et Mulch Seeding
Operator
King
Power Equipment Operators-
Outside Hoists (Elevators And
$72.28
7A 3K 8X View
Underground Sewer Et Water
Manlifts), Air Tuggers, Strato
King
Power Equipment Operators-
Overhead, Bridge Type Crane:
$72.84
7A 3K 8X View
Underground Sewer Et Water
20 Tons Through 44 Tons
King
Power Equipment Operators-
Overhead, Bridge Type: 100
$74.22
7A 3K 8X View
Underground Sewer Et Water
Tons And Over
King
Power Equipment Operators-
Overhead, Bridge Type: 45 Tons
$73.49
7A 3K 8X View
Underground Sewer Et Water
Through 99 Tons
King
Power Equipment Operators-
Pavement Breaker
$69.12
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Pile Driver (other Than Crane
$72.84
7A 3K 8X View
Underground Sewer Et Water
Mount)
King
Power Equipment Operators-
Plant Oiler - Asphalt, Crusher
$72.28
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Posthole Digger, Mechanical
$69.12
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Power Plant
$69.12
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Pumps - Water
$69.12
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Quad 9, Hd 41, D10 And Over
$73.49
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Quick Tower - No Cab, Under
$69.12
7A 3K 8X View
Underground Sewer Et Water
100 Feet In Height Based To
Boom
King
Power Equipment Operators-
Remote Control Operator On
$73.49
7A 3K 8X View
Underground Sewer Et Water
Rubber Tired Earth Moving
Equipment
King
Power Equipment Operators-
Rigger and Bellman
$69.12
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Rigger/Signal Person, Bellman
$72.28
7A 3K 8X View
Underground Sewer Et Water
(Certified)
King
Power Equipment Operators-
Rollagon
$73.49
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Roller, Other Than Plant Mix
$69.12
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Roller, Plant Mix Or Multi -lift
$72.28
7A 3K 8X View
Underground Sewer Et Water
Materials
King
Power Equipment Operators-
Roto-mill, Roto-grinder
$72.84
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Saws - Concrete
$72.28
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Scraper, Self Propelled Under
$72.84
7A 3K 8X View
Underground Sewer Et Water
45 Yards
King
Power Equipment Operators-
Scrapers - Concrete Et Carry All
$72.28
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Scrapers, Self-propelled: 45
$73.49
7A 3K 8X View
Underground Sewer Et Water
Yards And Over
King
Power Equipment Operators-
Service Engineers - Equipment
$72.28
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Shotcrete/Gunite Equipment
$69.12
7A 3K 8X View
Underground Sewer Et Water
King
Power Equipment Operators-
Shovel, Excavator, Backhoe,
$72.28
7A 3K 8X View
Underground Sewer Et Water
Tractors Under 15 Metric Tons
King
Power Equipment Operators-
Shovel, Excavator, Backhoe:
$73.49
7A 3K 8X View
Underground Sewer Et Water
Over 30 Metric Tons To 50
Metric Tons
King
Power Equipment Operators-
Shovel, Excavator, Backhoes,
$72.84
7A 3K 8X View
Underground Sewer Et Water
Tractors: 15 To 30 Metric Tons
King
Power Equipment Operators-
Shovel, Excavator, Backhoes:
$74.22
7A 3K 8X View
Underground Sewer Et Water
Over 50 Metric Tons To 90
Metric Tons
King
Power Equipment Operators-
Shovel, Excavator, Backhoes:
$74.99
7A
3K
8X
View
Underground Sewer Et Water
Over 90 Metric Tons
King
Power Equipment Operators-
Slipform Pavers
$73.49
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Spreader, Topsider Et
$73.49
7A
3K
8X
View
Underground Sewer Et Water
Screedman
King
Power Equipment Operators-
Subgrader Trimmer
$72.84
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Tower Bucket Elevators
$72.28
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Tower Crane Up To 175' In
$74.22
7A
3K
8X
View
Underground Sewer Et Water
Height Base To Boom
King
Power Equipment Operators-
Tower Crane: over 175through
$74.99
7A
3K
8X
View
Underground Sewer Et Water
250' in height, base to boom
King
Power Equipment Operators-
Tower Cranes: over 250' in
$75.72
7A
3K
8X
View
Underground Sewer Et Water
height from base to boom
King
Power Equipment Operators-
Transporters, All Track Or Truck
$73.49
7A
3K
8X
View
Underground Sewer Et Water
Type
King
Power Equipment Operators-
Trenching Machines
$72.28
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Truck Crane Oiler/driver - 100
$72.84
7A
3K
8X
View
Underground Sewer Et Water
Tons And Over
King
Power Equipment Operators-
Truck Crane Oiler/Driver Under
$72.28
7A
3K
8X
View
Underground Sewer Et Water
100 Tons
King
Power Equipment Operators-
Truck Mount Portable Conveyor
$72.84
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Welder
$73.49
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Wheel Tractors, Farmall Type
$69.12
7A
3K
8X
View
Underground Sewer Et Water
King
Power Equipment Operators-
Yo Yo Pay Dozer
$72.84
7A
3K
8X
View
Underground Sewer Et Water
King
Power Line Clearance Tree
Journey Level In Charge
$55.03
5A
4A
View
Trimmers
King
Power Line Clearance Tree
Spray Person
$52.24
5A
4A
View
Trimmers
King
Power Line Clearance Tree
Tree Equipment Operator
$55.03
5A
4A
View
Trimmers
King
Power Line Clearance Tree
Tree Trimmer
$49.21
5A
4A
View
Trimmers
King
Power Line Clearance Tree
Tree Trimmer Groundperson
$37.47
5A
4A
View
Trimmers
King
Refrigeration Et Air
Journey Level
$87.01
6Z
1G
View
Conditioning Mechanics
King
Residential Brick Mason
Journey Level
$60.57
7E
1 N
View
King
Residential Carpenters
Journey Level
$36.44
1
View
King
Residential Cement Masons
Journey Level
$46.64
1
View
King
Residential Drywall Applicators
Journey Level
$64.94
7A
4C
View
King
Residential Drywall Tapers
Journey Level
$36.36
1
View
King
Residential Electricians
Journey Level
$48.80
1
View
King
Residential Glaziers
Journey Level
$28.93
1
View
King
Residential Insulation
Journey Level
$28.18
1
View
Applicators
King
Residential Laborers
Journey Level
$29.73
1
View
King
Residential Marble Setters
Journey Level
$27.38
1
View
King
Residential Painters
Journey Level
$23.47
1
View
King
Residential Plumbers Et
Journey Level
$92.19
6Z
1G
View
Pipefitters
King
Residential Refrigeration Et Air
Journey Level
$87.01
6Z
1G
View
Conditioning Mechanics
King
Residential Sheet Metal
Journey Level
$89.61
7F
1 E
View
Workers
King
Residential Soft Floor Layers
Journey Level
$51.91
5A
3J
View
King
Residential Sprinkler Fitters
Journey Level
$53.04
5C
2R
View
.(Fire Protection),
King
Residential Stone Masons
Journey Level
$60.57
7E
1 N
View
King
Residential Terrazzo Workers
Journey Level
$55.71
7E
1 N
View
King
Residential Terrazzo/Tile
Journey Level
$24.39
1
View
Finishers
King
Residential Tile Setters
Journey Level
$21.04
1
View
King
Roofers
Journey Level
$57.30
5A
3H
View
King
Roofers
Using Irritable Bituminous
$60.30
5A
3H
View
Materials
King
Sheet Metal Workers
Journey Level (Field or Shop)
$89.61
7F
1 E
View
King
Shipbuilding Et Ship Repair
New Construction Boilermaker
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction Carpenter
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction Crane
$38.54
7V
1
View
Operator
King
Shipbuilding Et Ship Repair
New Construction Electrician
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction Heat Et Frost
$79.43
5.1
4H
View
Insulator
King
Shipbuilding Et Ship Repair
New Construction Laborer
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction Machinist
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction Operating
$38.54
7V
1
View
Engineer
King
Shipbuilding Et Ship Repair
New Construction Painter
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction Pipefitter
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction Rigger
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction Sheet Metal
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction Shipfitter
$38.54
7V
1
View
King
Shipbuilding Et Ship Repair
New Construction
$38.54
7V
1
View
Warehouse/Teamster
King
Shipbuilding Et Ship Repair
New Construction Welder /
$38.54
7V
1
View
Burner
King
Shipbuilding Et Ship Repair
Ship Repair Boilermaker
$47.35
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Carpenter
$47.35
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Crane Operator
$45.06
7Y
4K
View
King
Shipbuilding Et Ship Repair
Ship Repair Electrician
$47.42
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Heat Et Frost
$79.43
5J
4H
View
Insulator
King
Shipbuilding Et Ship Repair
Ship Repair Laborer
$47.35
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Machinist
$47.35
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Operating Engineer
$45.06
7Y
4K
View
King
Shipbuilding Et Ship Repair
Ship Repair Painter
$47.35
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Pipefitter
$47.35
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Rigger
$47.35
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Sheet Metal
$47.35
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Shipwright
$47.35
7X
4J
View
King
Shipbuilding Et Ship Repair
Ship Repair Warehouse /
$45.06
7Y
4K
View
Teamster
King
Sign Makers Et Installers
Journey Level
$51.56
0
1
View
_(Electrical)
King
Sign Makers Et Installers (Non-
Journey Level
$33.20
0
1
View
Electrical).
King
Soft Floor Layers
Journey Level
$51.91
5A
3J
View
King
Solar Controls For Windows
Journey Level
$13.69
1
View
King
Sprinkler Fitters (Fire
Journey Level
$85.89
5C
1X
View
Protection)
King
Stage Rigging Mechanics (Non
Journey Level
$13.69
1
View
Structural),
King
Stone Masons
Journey Level
$60.57
7E
1N
View
King
Street And Parking Lot Sweeper
Journey Level
$19.09
1
View
Workers
King
Surveyors
Assistant Construction Site
$72.28
7A
3K
8X
View
Surveyor
King
Surveyors
Chainman
$69.12
7A
3K
8X
View
King
Surveyors
Construction Site Surveyor
$73.49
7A
3K
8X
View
King
Telecommunication Technicians
Journey Level
$53.57
7E
1 E
View
King
Telephone Line Construction -
Cable Splicer
$37.40
5A
2B
View
Outside
King
Telephone Line Construction -
Hole Digger/Ground Person
$25.04
5A
2B
View
Outside
King
Telephone Line Construction -
Telephone Equipment Operator
$31.22
5A
2B
View
Outside
(Light)
King
Telephone Line Construction -
Telephone Lineperson
$35.34
5A
2B
View
Outside
King
Terrazzo Workers
Journey Level
$55.71
7E
1N
View
King
Tile Setters
Journey Level
$55.71
7E
1N
View
King
Tile, Marble Et Terrazzo
Finisher
$46.54
7E
1N
View
Finishers
King
Traffic Control Stripers
Journey Level
$49.13
7A
1 K
View
King
Truck Drivers
Asphalt Mix Over 16 Yards
$64.55
5D
4Y
8L
View
King
Truck Drivers
Asphalt Mix To 16 Yards
$63.71
5D
4Y
8L
View
King
Truck Drivers
Dump Truck
$63.71
5D
4Y
8L
View
King
Truck Drivers
Dump Truck Et Trailer
$64.55
5D
4Y
8L
View
King
Truck Drivers
Other Trucks
$64.55
5D
4Y
8L
View
King
Truck Drivers - Ready Mix
Transit Mix
$64.55
5D
4Y
8L
View
King
Well Drillers Et Irrigation Pump
Irrigation Pump Installer
$17.71
1
View
Installers
King
Well Drillers Et Irrigation Pump
Oiler
$13.69
1
View
King
Installers
Well Drillers it Irrigation Pump
Installers
Well Driller
$18.00
i
View
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Overtime Codes
Overtime calculations are based on the hourly rate actually paid to the worker. On public works projects, the hourly rate
must be not less than the prevailing rate of wage minus the hourly rate of the cost of fringe benefits actually provided for
the worker.
ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE
PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.
B. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on
Sundays and holidays shall be paid at double the hourly rate of wage.
C. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday
shall be paid at one and one-half times the hourly rate of wage. All other overtime hours and all hours worked on
Sundays and holidays shall be paid at double the hourly rate of wage.
D. The first two (2) hours before or after a five -eight (8) hour workweek day or a four -ten (10) hour workweek day and
the first eight (8) hours worked the next day after either workweek shall be paid at one and one-half times the hourly
rate of wage. All additional hours worked and all worked on Sundays and holidays shall be paid at double the hourly
rate of wage.
E. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday
shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday,
and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.
F. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday
shall be paid at one and one-half times the hourly rate of wage. All other overtime hours worked, except Labor Day,
shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly
rate of wage.
G. The first ten (10) hours worked on Saturdays and the first ten (10) hours worked on a fifth calendar weekday in a four -
ten hour schedule, shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten
(10) hours per day Monday through Saturday and all hours worked on Sundays and holidays shall be paid at double
the hourly rate of wage.
H. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions or equipment
breakdown) shall be paid at one and one-half times the hourly rate of wage. All hours worked Monday through
Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate
of wage.
I. All hours worked on Sundays and holidays shall also be paid at double the hourly rate of wage.
The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday
shall be paid atone and one-half times the hourly rate of wage. All hours worked over ten (10) hours Monday through
Saturday, Sundays and holidays shall be paid at double the hourly rate of wage.
K. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours
worked on holidays shall be paid at double the hourly rate of wage.
M. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions) shall be paid
at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double
the hourly rate of wage.
N. All hours worked on Saturdays (except makeup days) shall be paid at one and one-half times the hourly rate of wage.
All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.
1of14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Overtime Codes Continued
O. The first ten (10) hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours
worked on Sundays, holidays and after twelve (12) hours, Monday through Friday and after ten (10) hours on Saturday
shall be paid at double the hourly rate of wage.
P. All hours worked on Saturdays (except makeup days if circumstances warrant) and Sundays shall be paid at one and
one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage.
Q. The first two (2) hours after eight (8) regular hours Monday through Friday and up to ten (10) hours worked on
Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten (10)
hours per day Monday through Saturday and all hours worked on Sundays and holidays (except Christmas day) shall
be paid at double the hourly rate of wage. All hours worked on Christmas day shall be paid at two and one-half times
the hourly rate of wage.
R. All hours worked on Sundays and holidays shall be paid at two times the hourly rate of wage.
U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on
Sundays and holidays (except Labor Day) shall be paid at two times the hourly rate of wage. All hours worked on
Labor Day shall be paid at three times the hourly rate of wage.
V. All hours worked on Sundays and holidays (except Thanksgiving Day and Christmas day) shall be paid at one and
one-half times the hourly rate of wage. All hours worked on Thanksgiving Day and Christmas day shall be paid at
double the hourly rate of wage.
W. All hours worked on Saturdays and Sundays (except make-up days due to conditions beyond the control of the
employer)) shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid
at double the hourly rate of wage.
X. The first four (4) hours after eight (8) regular hours Monday through Friday and the first twelve (12) hours on Saturday
shall be paid at one and one-half times the hourly rate of wage. All hours worked over twelve (12) hours Monday
through Saturday, Sundays and holidays shall be paid at double the hourly rate of wage. When holiday falls on
Saturday or Sunday, the day before Saturday, Friday, and the day after Sunday, Monday, shall be considered the
holiday and all work performed shall be paid at double the hourly rate of wage.
Y. All hours worked outside the hours of 5:00 am and 5:00 pm (or such other hours as may be agreed upon by any
employer and the employee) and all hours worked in excess of eight (8) hours per day (10 hours per day for a 4 x 10
workweek) and on Saturdays and holidays (except labor day) shall be paid at one and one-half times the hourly rate
of wage. (except for employees who are absent from work without prior approval on a scheduled workday during the
workweek shall be paid at the straight -time rate until they have worked 8 hours in a day (10 in a 4 x 10 workweek) or
40 hours during that workweek.) All hours worked Monday through Saturday over twelve (12) hours and all hours
worked on Sundays and Labor Day shall be paid at double the hourly rate of wage.
Z. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All
hours worked on holidays shall be paid the straight time rate of pay in addition to holiday pay.
2of14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Overtime Codes Continued
2. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE
PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.
B. All hours worked on holidays shall be paid at one and one-half times the hourly rate of wage.
F. The first eight (8) hours worked on holidays shall be paid at the straight hourly rate of wage in addition to the holiday
pay. All hours worked in excess of eight (8) hours on holidays shall be paid at double the hourly rate of wage.
M. This code appears to be missing. All hours worked on Saturdays, Sundays and holidays shall be paid at double the
hourly rate of wage.
O. All hours worked on Sundays and holidays shall be paid at one and one-half times the hourly rate of wage.
R. All hours worked on Sundays and holidays and all hours worked over sixty (60) in one week shall be paid at double
the hourly rate of wage.
U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked
over 12 hours in a day or on Sundays and holidays shall be paid at double the hourly rate of wage.
ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE
PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.
F. All hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on
Sunday shall be paid at two times the hourly rate of wage. All hours worked on paid holidays shall be paid at two and
one-half times the hourly rate of wage including holiday pay.
H. All work performed on Sundays between March 16th and October 14th and all Holidays shall be compensated for at
two (2) times the regular rate of pay. Work performed on Sundays between October 15th and March 15th shall be
compensated at one and one half (1-1/2) times the regular rate of pay.
All hours worked between the hours of 10:00 pm and 5:00 am, Monday through Friday, and all hours worked on
Saturdays shall be paid at a one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays
shall be paid at double the hourly rate of wage.
K. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when
four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or
outside the normal 5 am to 6pm shift, and all work on Saturdays shall be paid at one and one-half times the hourly
rate of wage. All work performed after 6:00 pm Saturday to 5:00 am Monday and Holidays, and all hours worked in
excess of twelve (12) hours in a single shift shall be paid at double the hourly rate of wage.
After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the
applicable overtime rate until such time as the employee has had a break of eight (8) hours or more. When an employee
returns to work without at least eight (8) hours time off since their previous shift, all such time shall be a continuation
of shift and paid at the applicable overtime rate until he/she shall have the eight (8) hours rest period.
4. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE
PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.
A. All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at double the hourly
rate of wage. All hours worked on Saturdays, Sundays and holidays shall be paid at double the hourly rate of wage.
3of14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Overtime Codes Continued
4. C. On Monday through Friday, the first four (4) hours of overtime after eight (8) hours of straight time work shall be
paid at one and one half (1-1/2) times the straight time rate of pay, unless a four (4) day ten (10) hour workweek has
been established. On a four (4) day ten (10) hour workweek scheduled Monday through Thursday, or Tuesday
through Friday, the first two (2) hours of overtime after ten (10) hours of straight time work shall be paid at one and
one half (1-1/2) times the straight time rate of pay. On Saturday, the first twelve (12) hours of work shall be paid at
one and one half (1-1/2) times the straight time rate of pay, except that if the job is down on Monday through Friday
due to weather conditions or other conditions outside the control of the employer, the first ten (10) hours on Saturday
may be worked at the straight time rate of pay. All hours worked over twelve (12) hours in a day and all hours worked
on Sunday and Holidays shall be paid at two (2) times the straight time rate of pay.
D. All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at double the hourly
rate of wage. All hours worked on Saturday, Sundays and holidays shall be paid at double the hourly rate of pay. Rates
include all members of the assigned crew.
EXCEPTION:
On all multipole structures and steel transmission lines, switching stations, regulating, capacitor stations, generating
plants, industrial plants, associated installations and substations, except those substations whose primary function is
to feed a distribution system, will be paid overtime under the following rates:
The first two (2) hours after eight (8) regular hours Monday through Friday of overtime on a regular workday, shall
be paid at one and one-half times the hourly rate of wage. All hours in excess of ten (10) hours will be at two (2) times
the hourly rate of wage. The first eight (8) hours worked on Saturday will be paid at one and one-half (1-1/2) times
the hourly rate of wage. All hours worked in excess of eight (8) hours on Saturday, and all hours worked on Sundays
and holidays will be at the double the hourly rate of wage.
All overtime eligible hours performed on the above described work that is energized, shall be paid at the double the
hourly rate of wage.
E. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday
shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday,
and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.
On a four -day, ten-hour weekly schedule, either Monday thru Thursday or Tuesday thru Friday schedule, all hours
worked after ten shall be paid at double the hourly rate of wage. The Monday or Friday not utilized in the normal four -
day, ten hour work week, and Saturday shall be paid at one and one half (1'h) times the regular shift rate for the first
eight (8) hours. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays
shall be paid at double the hourly rate of wage.
G. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked
Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at
double the hourly rate of wage.
H. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday
shall be paid at one and one-half times the hourly rate of wage. All other overtime hours worked, except Labor Day,
and all hours on Sunday shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid
at three times the hourly rate of wage.
I. The First eight (8) hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All
hours worked in excess of eight (8) per day on Saturdays shall be paid at double the hourly rate of wage. All hours
worked on Sundays and holidays shall be paid at double the hourly rate of wage.
4of14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Overtime Codes Continued
4. J. The first eight (8) hours worked on a Saturday shall be paid at one and one-half times the hourly rate of wage. All
hours worked in excess of eight (8) hours on a Saturday shall be paid at double the hourly rate of wage. All hours
worked over twelve (12) in a day, and all hours worked on Sundays and Holidays shall be paid at double the hourly
rate of wage.
K. All hours worked on a Saturday shall be paid at one and one-half times the hourly rate of wage, so long as Saturday
is the sixth consecutive day worked. All hours worked over twelve (12) in a day Monday through Saturday, and all
hours worked on Sundays and Holidays shall be paid at double the hourly rate of wage.
L. The first twelve (12) hours worked on a Saturday shall be paid at one and one-half times the hourly rate of wage. All
hours worked on a Saturday in excess of twelve (12) hours shall be paid at double the hourly rate of pay. All hours
worked over twelve (12) in a day Monday through Friday, and all hours worked on Sundays shall be paid at double
the hourly rate of wage. All hours worked on a holiday shall be paid at one and one-half times the hourly rate of wage,
except that all hours worked on Labor Day shall be paid at double the hourly rate of pay.
U. The first four (4) hours after eight (8) regular hours Monday through Friday and the first twelve (12) hours on Saturday
shall be paid at one and one-half times the hourly rate of wage. (Except on makeup days if work is lost due to inclement
weather, then the first eight (8) hours on Saturday may be paid the regular rate.) All hours worked over twelve (12)
hours Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly
rate of wage.
V. Work performed in excess of ten (10) hours of straight time per day when four ten (10) hour shifts are established or
outside the normal shift (5 am to 6pm), and all work on Saturdays, except for make-up days shall be paid at time and
one-half (1 ''/2) the straight time rate.
In the event the job is down due to weather conditions, then Saturday may, be worked as a voluntary make-up day at
the straight time rate. However, Saturday shall not be utilized as a make-up day when a holiday falls on Friday. All
work performed on Sundays and holidays and work in excess of twelve (12) hours per day shall be paid at double (2x)
the straight time rate of pay.
After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the
applicable overtime rate until such time as the employee has had a break of eight (8) hours.
When an employee returns to work without a break of eight (8) hours since their previous shift, all such time shall be
a continuation of shift and paid at the applicable overtime rate until such time as the employee has had a break of eight
(8) hours.
W. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions) shall be paid
at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double
the hourly rate of wage.
When an employee returns to work without at least eight (8) hours time off since their previous shift, all such time
shall be a continuation of shift and paid at the applicable overtime rate until such time as the employee has had a break
of eight (8) hours.
5of14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Overtime Codes Continued
4. X. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on
Sundays and holidays shall be paid at double the hourly rate of wage. Work performed outside the normal shift of 6
am to 6pm shall be paid at one and one-half the straight time rate, (except for special shifts or three shift operations).
All work performed on Sundays and holidays shall be paid at double the hourly rate of wage. Shifts may be established
when considered necessary by the Employer.
The Employer may establish shifts consisting of eight (8) or ten (10) hours of work (subject to WAC 296-127-022),
that shall constitute a normal forty (40) hour work week. The Employer can change from a 5-eight to a 4-ten hour
schedule or back to the other. All hours of work on these shifts shall be paid for at the straight time hourly rate. Work
performed in excess of eight hours (or ten hours per day (subject to WAC 296-127-022) shall be paid atone and one-
half the straight time rate.
When due to conditions beyond the control of the Employer, or when contract specifications require that work can
only be performed outside the regular day shift, then by mutual agreement a special shift may be worked at the straight
time rate, eight (8) hours work for eight (8) hours pay. The starting time shall be arranged to fit such conditions of
work.
When an employee returns to work without at a break of eight (8) hours since their previous shift, all such time shall
be a continuation of shift and paid at the applicable overtime rate until such time as the employee has had a break of
eight (8) hours.
Y. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when
four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or
outside the normal shift, and all work on Saturdays shall be paid at time and one-half the straight time rate. All work
performed after 6:00 pm Saturday to 6:00 am Monday and holidays shall be paid at double the straight time rate of
pay.
Any shift starting between the hours of 6:00 pm and midnight shall receive an additional one dollar ($1.00) per hour
for all hours worked that shift.
After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the
applicable overtime rate until such time as the employee has had a break of eight (8) hours or more.
Z. All hours worked between the hours of 6:00 pm and 6:00 am, Monday through Saturday, shall be paid at a premium
rate of 20% over the hourly rate of wage. Work performed on Sundays may be paid at double time. All hours worked
on holidays shall be paid at double the hourly rate of wage.
11. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE
PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.
A. The first ten (10) hours worked on Saturday and all hours worked on holidays shall be paid at one and one-half times
the hourly rate of wage. All hours worked over twelve (12) hours Monday through Saturday, and all hours worked on
Sundays shall be paid at double the hourly rate of wage.
After an employee has worked eight (8) hours, all additional hours worked shall be paid at the applicable overtime rate until
such time as the employee has had a break of eight (8) hours or more.
6of14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Holiday Codes
A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after
Thanksgiving Day, and Christmas Day (7).
B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after
Thanksgiving Day, the day before Christmas, and Christmas Day (8).
C. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the
Friday after Thanksgiving Day, And Christmas Day (8).
D. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and
Saturday after Thanksgiving Day, And Christmas Day (8).
H. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Day after Thanksgiving Day,
And Christmas (6).
I. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day
(6).
Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, Friday after Thanksgiving Day,
Christmas Eve Day, And Christmas Day (7).
K. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day,
Friday After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9).
L. Holidays: New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving
Day, Friday after Thanksgiving Day, And Christmas Day (8).
N. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Veterans' Day,
Thanksgiving Day, The Friday After Thanksgiving Day, And Christmas Day (9).
P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday And Saturday
After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9). If A Holiday Falls On Sunday, The
Following Monday Shall Be Considered As A Holiday.
Q. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas
Day (6).
R. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Day After
Thanksgiving Day, One -Half Day Before Christmas Day, And Christmas Day. (7 1/2).
S. Paid Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day,
And Christmas Day (7).
Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, the
Friday after Thanksgiving Day, And Christmas Day (8).
6. G. Paid Holidays: New Year's Day, Martin Luther King Jr. Day, Presidents' Day, Memorial Day, Independence Day,
Labor Day, Veterans' Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and Christmas Eve
Day (11).
H. Paid Holidays: New Year's Day, New Year's Eve Day, Memorial Day, Independence Day, Labor Day, Thanksgiving
Day, Friday After Thanksgiving Day, Christmas Day, The Day After Christmas, And A Floating Holiday (10).
7of14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Holiday Codes Continued
T. Paid Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day,
Thanksgiving Day, The Friday After Thanksgiving Day, The Last Working Day Before Christmas Day, And
Christmas Day (9).
Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after
Thanksgiving Day, And Christmas Day (7). If a holiday falls on Saturday, the preceding Friday shall be
considered as the holiday. If a holiday falls on Sunday, the following Monday shall be considered as the
holiday.
A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and
Saturday after Thanksgiving Day, And Christmas Day (8). Any Holiday Which Falls On A Sunday Shall Be Observed
As A Holiday On The Following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall
be a regular work day.
B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and
Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as
a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the
preceding Friday.
C. Holidays: New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving
Day, the Friday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be
observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday
on the preceding Friday.
D. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day,
the Friday after Thanksgiving Day, And Christmas Day (8). Unpaid Holidays: President's Day. Any paid holiday
which falls on a Sunday shall be observed as a holiday on the following Monday. Any paid holiday which falls on a
Saturday shall be observed as a holiday on the preceding Friday.
E. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after
Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on
the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.
F. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after
Thanksgiving Day, the last working day before Christmas day and Christmas day (8). Any holiday which falls on a
Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be
observed as a holiday on the preceding Friday.
G. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day
(6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday.
H. Holidays: New Year's Day, Martin Luther King Jr. Day, Independence Day, Memorial Day, Labor Day, Thanksgiving
Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (9). Any
holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on
a Saturday shall be observed as a holiday on the preceding Friday.
I. Holidays: New Year's Day, President's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, The
Friday After Thanksgiving Day, The Day Before Christmas Day And Christmas Day (9). Any holiday which falls on
a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be
observed as a holiday on the preceding Friday.
8of14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Holiday Codes Continued
Holidays: New Year's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day and Christmas Day (6).
Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which
falls on a Saturday shall be observed as a holiday on the preceding Friday.
K. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Friday and Saturday after
Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on
the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.
L. Holidays: New Year's Day, Memorial Day, Labor Day, Independence Day, Thanksgiving Day, the Last Work Day
before Christmas Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday
on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding
Friday.
N. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after
Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on
the following Monday. When Christmas falls on a Saturday, the preceding Friday shall be observed as a holiday.
P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after
Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on
the following Monday.
Q. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after
Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (8). Any holiday which falls on
a Sunday shall be observed as a holiday on the following Monday. If any of the listed holidays falls on a Saturday, the
preceding Friday shall be a regular work day.
S. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after
Thanksgiving Day, Christmas Day, the Day after Christmas, and A Floating Holiday (9). If any of the listed holidays
falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly.
V. Holidays: New Year's Day, President's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day,
the Friday after Thanksgiving Day, Christmas Day, the day before or after Christmas, and the day before or after New
Year's Day. If any of the above listed holidays falls on a Sunday, the day observed by the Nation shall be considered
a holiday and compensated accordingly.
W. Holidays: New Year's Day, Day After New Year's, Memorial Day, Independence Day, Labor Day, Thanksgiving
Day, the Friday after Thanksgiving Day, Christmas Eve Day, Christmas Day, the day after Christmas, the day before
New Year's Day, and a Floating Holiday.
X. Holidays: New Year's Day, Day before or after New Year's Day, Presidents' Day, Memorial Day, Independence Day,
Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and the day before or after
Christmas day. If a holiday falls on a Saturday or on a Friday that is the normal day off, then the holiday will be taken
on the last normal workday. If the holiday falls on a Monday that is the normal day off or on a Sunday, then the holiday
will be taken on the next normal workday.
Y. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the
Friday after Thanksgiving Day, and Christmas Day. (8) If the holiday falls on a Sunday, then the day observed by the
federal government shall be considered a holiday and compensated accordingly.
9of14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Holiday Codes Continued
G. New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The
Friday After Thanksgiving Day, the last scheduled workday before Christmas, and Christmas Day (9). If any of the
listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated
accordingly.
H. Holidays: New Year's Day, Martin Luther King Jr. Day, Independence Day, Memorial Day, Labor Day, Thanksgiving
Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (9). Any
holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on
a Saturday shall be observed as a holiday on the preceding Friday.
I. Holidays: New Year's Day, President's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, The
Friday After Thanksgiving Day, The Day Before Christmas Day And Christmas Day (9). Any holiday which falls on
a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be
observed as a holiday on the preceding Friday.
Holidays: New Year's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day and Christmas Day (6).
Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which
falls on a Saturday shall be observed as a holiday on the preceding Friday.
K. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Friday and Saturday after
Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on
the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.
L. Holidays: New Year's Day, Memorial Day, Labor Day, Independence Day, Thanksgiving Day, the Last Work Day
before Christmas Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday
on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding
Friday.
N. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after
Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on
the following Monday. When Christmas falls on a Saturday, the preceding Friday shall be observed as a holiday.
P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after
Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on
the following Monday.
Q. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after
Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (8). Any holiday which falls on
a Sunday shall be observed as a holiday on the following Monday. If any of the listed holidays falls on a Saturday, the
preceding Friday shall be a regular work day.
S. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after
Thanksgiving Day, Christmas Day, the Day after Christmas, and A Floating Holiday (9). If any of the listed holidays
falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly.
V. Holidays: New Year's Day, President's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day,
the Friday after Thanksgiving Day, Christmas Day, the day before or after Christmas, and the day before or after New
Year's Day. If any of the above listed holidays falls on a Sunday, the day observed by the Nation shall be considered
a holiday and compensated accordingly.
10 of 14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Holiday Codes Continued
7. W. Holidays: New Year's Day, Day After New Year's, Memorial Day, Independence Day, Labor Day, Thanksgiving
Day, the Friday after Thanksgiving Day, Christmas Eve Day, Christmas Day, the day after Christmas, the day before
New Year's Day, and a Floating Holiday.
X. Holidays: New Year's Day, Day before or after New Year's Day, Presidents' Day, Memorial Day, Independence Day,
Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and the day before or after
Christmas day. If a holiday falls on a Saturday or on a Friday that is the normal day off, then the holiday will be taken
on the last normal workday. If the holiday falls on a Monday that is the normal day off or on a Sunday, then the holiday
will be taken on the next normal workday.
Y. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the
Friday after Thanksgiving Day, and Christmas Day. (8) If the holiday falls on a Sunday, then the day observed by the
federal government shall be considered a holiday and compensated accordingly.
15. F. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after
Thanksgiving Day, the last scheduled workday before Christmas, and Christmas Day (8). If any of the listed holidays
falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly.
G. New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The
Friday After Thanksgiving Day, the last scheduled workday before Christmas, and Christmas Day (9). If any of the
listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated
accordingly.
Note Codes
8. D. Workers working with supplied air on hazmat projects receive an additional $1.00 per hour.
L. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $0.75, Level B: $0.50, And
Level C: $0.25.
M. Workers on hazmat projects receive additional hourly premiums as follows: Levels A & B: $1.00, Levels C & D:
$0.50.
N. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $1.00, Level B: $0.75, Level
C: $0.50, And Level D: $0.25.
S. Effective August 31, 2012 —A Traffic Control Supervisor shall be present on the project whenever flagging or spotting
or other traffic control labor is being utilized. Flaggers and Spotters shall be posted where shown on approved Traffic
Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued
by the State of Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31,
2012.
11 of 14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Note Codes Continued
8. T. Effective August 31, 2012 — A Traffic Control Laborer performs the setup, maintenance and removal of all temporary
traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian traffic during
construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or
where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of
Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31, 2012.
U. Workers on hazmat projects receive additional hourly premiums as follows — Class A Suit: $2.00, Class B Suit: $1.50,
And Class C Suit: $1.00. Workers performing underground work receive an additional $0.40 per hour for any and all
work performed underground, including operating, servicing and repairing of equipment. The premium for
underground work shall be paid for the entire shift worked. Workers who work suspended by a rope or cable receive
an additional $0.50 per hour. The premium for work suspended shall be paid for the entire shift worked. Workers who
do "pioneer" work (break open a cut, build road, etc.) more than one hundred fifty (150) feet above grade elevation
receive an additional $0.50 per hour.
V. In addition to the hourly wage and fringe benefits, the following depth and enclosure premiums shall be paid. The
premiums are to be calculated for the maximum depth and distance into an enclosure that a diver reaches in a day.
The premiums are to be paid one time for the day and are not used in calculating overtime pay.
Depth premiums apply to depths of fifty feet or more. Over 50' to 100' - $2.00 per foot for each foot over 50 feet. Over
10l' to 150' - $3.00 per foot for each foot over 101 feet. Over 15l' to 220' - $4.00 per foot for each foot over 220 feet.
Over 22 F - $5.00 per foot for each foot over 221 feet.
Enclosure premiums apply when divers enter enclosures (such as pipes or tunnels) where there is no vertical ascent
and is measured by the distance travelled from the entrance. 25' to 300' - $1.00 per foot from entrance. 300' to 600'
- $1.50 per foot beginning at 300'. Over 600' - $2.00 per foot beginning at 600'.
W. Meter Installers work on single phase 120/240V self-contained residential meters. The Lineman/Groundmen rates
would apply to meters not fitting this description.
X. Workers on hazmat projects receive additional hourly premiums as follows - Class A Suit: $2.00, Class B Suit:
$1.50, Class C Suit: $1.00, and Class D Suit: $0.50. Special Shift Premium: Basic hourly rate plus $2.00 per hour.
When due to conditions beyond the control of the Employer or when an owner (not acting as the contractor), a
government agency or the contract specifications requires that work can only be performed outside the normal 5 am
to 6pm shift, then the special shift premium will be applied to the basic hourly rate. When an employee works on a
special shift, they shall be paid a special shift premium for each hour worked unless they are in OT or Double-time
status. (For example, the special shift premium does not waive the overtime requirements for work performed on
Saturday or Sunday.)
Y. Tide Work: When employees are called out between the hours of 6:00 p.m. and 6:00 a.m. to work on tide work
(work located in the tide plane) all time worked shall be at one and one-half times the hourly rate of pay.
Swinging Stage/Boatswains Chair: Employees working on a swinging state or boatswains chair or under conditions
that require them to be tied off to allow their hands to be free shall receive seventy-five cents ($0.75) per hour above
the classification rate.
12 of 14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Note Codes Continued
8. Z. Workers working with supplied air on hazmat projects receive an additional $1.00 per hour.
Special Shift Premium: Basic hourly rate plus $2.00 per hour. When due to conditions beyond the control of the
Employer or when an owner (not acting as a contractor), a government agency or the contract specifications require
that more than (4) hours of a special shift can only be performed outside the normal 6 am to 6pm shift, then the
special shift premium will be applied to the basic straight time for the entire shift. When an employee works on a
special shift, they will be paid a special shift premium for each hour worked unless they are in overtime or double-
time status. (For example, the special shift premium does not waive the overtime requirements for work performed
on Saturday or Sunday.)
A. Workers working with supplied air on hazmat projects receive an additional $1.00 per hour.
Special Shift Premium: Basic hourly rate plus $2.00 per hour. When due to conditions beyond the control of the
Employer or when an owner (not acting as the contractor), a government agency or the contract specifications require
that more than four (4) hours of a special shift can only be performed outside the normal 6 am to 6pm shift, then the
special shift premium will be applied to the basic straight time for the entire shift. When an employee works on a
special shift, they shall be paid a special shift premium for each hour worked unless they are in overtime or double-
time status. (For example, the special shift premium does not waive the overtime requirements for work performed on
Saturday or Sunday.)
Certified Crane Operator Premium: Crane operators requiring certifications shall be paid $0.50 per hour above their
classification rate.
Boom Pay Premium: All cranes including tower shall be paid as follows based on boom length:
(A) — 130' to 199' — $0.50 per hour over their classification rate.
(B) — 200' to 299' — $0.80 per hour over their classification rate.
(C) — 300' and over — $1.00 per hour over their classification rate.
B. The highest pressure registered on the gauge for an accumulated time of more than fifteen (15) minutes during the
shift shall be used in determining the scale paid.
Tide Work: When employees are called out between the hours of 6:00 p.m. and 6:00 a.m. to work on tide work (work
located in the tide plane) all time worked shall be at one and one-half times the hourly rate of pay. Swinging
Stage/Boatswains Chair: Employees working on a swinging stage or boatswains chair or under conditions that require
them to be tied off to allow their hands to be free shall receive seventy-five cents ($0.75) per hour above the
classification rate.
C. Tide Work: When employees are called out between the hours of 6:00 p.m. and 6:00 a.m. to work on tide work (work
located in the tide plane) all time worked shall be at one and one-half times the hourly rate of pay. Swinging
Stage/Boatswains Chair: Employees working on a swinging stage or boatswains chair or under conditions that require
them to be tied off to allow their hands to be free shall receive seventy-five cents ($0.75) per hour above the
classification rate.
Effective August 31, 2012 — A Traffic Control Supervisor shall be present on the project whenever flagging or spotting
or other traffic control labor is being utilized. A Traffic Control Laborer performs the setup, maintenance and removal
of all temporary traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian
traffic during construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control
Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the
State of Washington, Oregon, Montana, or Idaho. These classifications are only effective on or after August 31, 2012.
13 of 14
Benefit Code Key — Effective 3/3/2021 thru 8/31/2021
Note Codes Continued
D. Industrial Painter wages are required for painting within industrial facilities such as treatment plants, pipelines,
towers, dams, bridges, power generation facilities and manufacturing facilities such as chemical plants, etc., or
anywhere abrasive blasting is necessary to prepare surfaces, or hazardous materials encapsulation is required.
E. Heavy Construction includes construction, repair, alteration or additions to the production, fabrication or
manufacturing portions of industrial or manufacturing plants, hydroelectric or nuclear power plants and atomic
reactor construction. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $1.00,
Level B: $0.75, Level C: $0.50, And Level D: $0.25.
F. Industrial Painter wages are required for painting within industrial facilities such as treatment plants, pipelines,
towers, dams, power generation facilities and manufacturing facilities such as chemical plants, etc., or anywhere
abrasive blasting is necessary to prepare surfaces, or hazardous materials encapsulation is required.
14 of 14
Rock Creek Culvert Replacement/Lincoln A - 6 June 3, 2021
Project Number: 13-3007.5
APPENDIX F
GEOTECHNICAL REPORT
Earth Science + Technology
Geotechnical Engineering Services Report
Summit Landsburg Road Culvert Replacement
Kent, Washington
for
City of Kent
November 13, 2019
Geotechnical Engineering Services Report
Summit Landsburg Road Culvert Replacement
Kent, Washington
for
City of Kent
November 13, 2019
1101 South Fawcett Avenue, Suite 200
Tacoma, Washington 98402
253.383.4940
Geotechnical Engineering Services Report
Summit Landsburg Road Culvert Replacement
Kent, Washington
File No. 0410-205-00
November 13, 2019
Prepared for:
City of Kent
220 Fourth Avenue South
Kent, Washington 98032-5895
Attention: Stephen Lincoln, PE
Prepared by:
GeoEngineers, Inc.
1101 South Fawcett Avenue, Suite 200
Tacoma, Washington 98402
253.383.4940
Brett E. Larabee, PE
Geotechnical Engineer
Ly J. Stone, PE
Associate, Geotechnical Engineer
CJL:OEL:lJ5:tt
Disclaimer: Any electronic form, facsimile or hard copy of the original document (email. text. table, and/or figure) if provided, and any attachments are only a copy
of the original document. The original document is stored by GeoEngineers Inc. and will serve as the official document of record
GMENGINEERS�
November 13, 2019 | Page i
File No. 0410-205-00
Table of Contents
1.0 INTRODUCTION AND PROJECT UNDERSTANDING .................................................................................... 1
2.0 SITE CONDITIONS ........................................................................................................................................ 1
2.1. Surface Conditions.................................................................................................................................. 1
2.2. Geologic Setting ...................................................................................................................................... 1
2.3. Subsurface Explorations and Laboratory Testing ................................................................................. 2
2.4. Subsurface Conditions ........................................................................................................................... 2
3.0 CONCLUSIONS AND RECOMMENDATIONS ............................................................................................... 2
3.1. Primary Geotechnical Considerations ................................................................................................... 2
3.2. Seismic Design Considerations .............................................................................................................. 3
3.2.1. General .................................................................................................................................... 3
3.2.2. Liquefaction............................................................................................................................. 3
3.2.3. Lateral Spreading Potential .................................................................................................... 4
3.2.4. Surface Rupture Potential ...................................................................................................... 4
3.3. Foundation Support ................................................................................................................................ 4
3.3.1. General .................................................................................................................................... 4
3.3.2. Foundation Bearing Surface Preparation .............................................................................. 4
3.3.3. Foundation Bearing Resistance ............................................................................................. 5
3.3.4. Lateral Resistance .................................................................................................................. 5
3.4. Conventional Retaining Walls and Subsurface Structures................................................................... 5
3.4.1. Subsurface Drainage .............................................................................................................. 5
3.4.2. Design Parameters ................................................................................................................. 6
3.5. Site Development and Earthwork .......................................................................................................... 7
3.5.1. General .................................................................................................................................... 7
3.5.2. Clearing, Stripping, and Demolition ....................................................................................... 7
3.5.3. Temporary Excavations, Shoring and Dewatering ................................................................ 7
3.5.4. Permanent Cut and Fill Slopes ............................................................................................. 10
3.5.5. Subgrade Preparation........................................................................................................... 10
3.5.6. Subgrade Protection and Wet Weather Considerations ..................................................... 10
3.6. Fill Materials .......................................................................................................................................... 11
3.6.1. Structural Fill ......................................................................................................................... 11
3.6.2. Select Granular Fill ............................................................................................................... 11
3.6.3. Recycled Materials ................................................................................................................ 11
3.6.4. On-Site Soils .......................................................................................................................... 12
3.7. Fill Placement and Compaction ........................................................................................................... 12
3.7.1. Fill Placement Below the Water Table ................................................................................. 12
4.0 LIMITATIONS ............................................................................................................................................. 13
LIST OF FIGURES
Figure 1. Vicinity Map
Figure 2. Site Plan
Figure 3. Shallow Foundation Bearing Resistance
November 13, 2019 | Page ii
File No. 0410-205-00
APPENDICES
Appendix A. Subsurface Explorations and Laboratory Testing
Figure A-1 – Key to Exploration Logs
Figures A-2 and A-3 – Logs of Borings
Figures A-4 and A-5 – Sieve Analysis Results
Appendix B. Report Limitations and Guidelines for Use
November 13, 2019 | Page 1
File No. 0410-205-00
1.0 INTRODUCTION AND PROJECT UNDERSTANDING
This report summarizes our investigations, analysis, and geotechnical design recommendations for the
Summit Landsburg Road Culvert Replacement project. The project site is located on SE Summit Landsburg
Road approximately 1,480 feet north of its intersection with SE Kent-Kangley Road as shown on the Vicinity
Map, Figure 1. We understand the project site is within a small noncontiguous area of the City of Kent,
which is surrounded by the City of Maple Valley and unincorporated King County. Our understanding of the
project is based on discussions with and information provided by City of Kent and the project structural
engineer (Otak).
We understand that the existing culvert system consists of three 36-inch diameter by 35-foot long culverts
that are barriers to fish passage. We understand that the existing culverts will be replaced with a system
that can accommodate fish passage. Based on our discussions with Otak, we understand that a new bridge
structure with a span length on the order of 50 feet will we constructed and span over the existing creek.
The new bridge structure will be designed based on the 2014 American Association of State Highway and
Transportation Officials (AASHTO) Load Resistance and Factor Design (LRFD) Bridge Design Specifications
(AASHTO LRFD). We anticipate that the existing culverts will be removed, and the stream bed will be
restored beneath the new bridge. We anticipate that existing pavements on Summit Landsburg Road within
and adjacent to the project site will likely either need to be repaired and overlaid or fully replaced as part
of this project.
Our services are being provided in accordance with our signed agreement executed April 22, 2019.
2.0 SITE CONDITIONS
2.1. Surface Conditions
SE Summit Landsburg Road is an asphalt paved two-lane roadway with gravel shoulders. Within the project
area the roadway is oriented northeast-southwest. Rock Creek crosses below the roadway and generally
flows southeast to northwest. The project site is bordered by residential parcels. The parcels on the north
and southeast sides of the culvert location are developed. The parcel to the southwest of the culvert is
undeveloped. The areas around the creek and roadway within the project area are densely vegetated with
underbrush and young to mature trees. The existing creek bed appears to be about 8 feet below the
roadway elevation.
2.2. Geologic Setting
We reviewed the published Geologic Map of the Black Diamond Quadrangle, King County, Washington
(Mullineaux 1965). The map indicates the site is underlain by Proglacial stratified drift (glacial drift),
outwash plain deposits (Qpo). This unit is described as mostly well-sorted sand, gravel and cobbles
deposited by meltwater along and beyond the retreating front of the Puget glacial lobe. Ground moraine
deposits (Qgt) are mapped in the near site vicinity and are described to consist of glacial till. Glacial till
typically consists of a highly compact mixture of clay, silt, sand and gravel deposited below glacial ice. Intact
deposits of glacial till are typically dense to very dense although the upper few feet of till can be weathered
and relatively less dense. Based on review of the geologic map, it appears that glacial drift deposits were
deposited over glacial till in the project area.
November 13, 2019 | Page 2
File No. 0410-205-00
2.3. Subsurface Explorations and Laboratory Testing
Subsurface conditions were explored by drilling two borings using hollow-stem auger methods. The borings
were advanced in the southwest bound lane of Summit Landsburg Road on either side of Rock Creek.
Boring B-1 was located on the southwest side of the creek crossing and was advanced to a depth of about
45 feet below ground surface (bgs). Boring B-2 was located on the northeast side of the creek crossing and
extended to an approximate depth of 35.5 feet bgs. The approximate location of each exploration is shown
in the Site Plan, Figure 2. Details regarding our subsurface exploration program, including summary logs
are included in Appendix A.
Select samples from our explorations were tested in our laboratory to confirm field classifications and
correlate with engineering properties. Details of our laboratory testing program and the testing results are
provided in Appendix A.
2.4. Subsurface Conditions
Asphalt pavement thickness in our borings was on the order of 12 inches. Below the asphalt, we observed
what we interpret to be roadway base comprised of very dense sand with gravel and dense gravel with silt,
and cobbles. Below the roadway base material, we observed what we interpret to be fill extending to around
5 feet bgs in B-1 and 6 feet bgs in B-2. Observed fill generally consisted of dense gravel with silt and sand
and loose to medium dense silty gravel with sand.
Below the fill in our borings we observed what we interpret to be glacial drift. Glacial drift observed in our
explorations typically consisted of medium dense to very dense gravel with sand and varying amounts of
silt and cobbles. Within the glacial drift we observed intermittent layering of sand with variable silt content.
In B-1, glacial drift soils extended to a depth of about 40 feet bgs and were underlain by what we interpret
to be glacial till. Glacial till typically consisted of dense to very dense silty sand with gravel and varying
amounts of cobbles. Cobbles in the glacial drift and glacial till were both observed directly and inferred by
drilling action. B-1 met practical refusal in glacial till at a depth of about 45 feet bgs. B-2 met practical
refusal within glacial drift soils at an approximate depth of 35.5 feet bgs.
We observed groundwater at about 10 feet bgs in B-1 and around 19 feet bgs in B-2 at the time of drilling.
We anticipate that groundwater levels will fluctuate throughout the year in response to water levels in the
creek and precipitation. In our experience groundwater levels are typically highest during the winter and
spring months.
3.0 CONCLUSIONS AND RECOMMENDATIONS
3.1. Primary Geotechnical Considerations
Based on our understanding of the project, the explorations performed for this study and our experience, it
is our opinion that the proposed improvements can be designed and constructed generally as envisioned
with regard to geotechnical considerations. A summary of the primary geotechnical considerations for the
project is provided below and is followed by our detailed recommendations.
■ We anticipate that the new bridge structure can be supported on shallow foundations bearing on glacial
drift soils. Fill, if present at the design foundation bearing surface elevation, should be removed and
replaced with compacted structural fill.
November 13, 2019 | Page 3
File No. 0410-205-00
■ We observed soils within the glacial drift deposits that could potentially liquify during the design
earthquake. The liquefiable layer identified is around 20 feet bgs. We expect that liquefaction-induced
surface settlements from this layer would be less than 1 inch.
■ Most of the soils observed at the site contain a significant amount of fines and could be difficult or
impossible to work with when wet or become easily disturbed if exposed to wet weather. Depending on
the intended use of the material and the prevailing conditions, it may be difficult to re-use site soils as
structural fill.
3.2. Seismic Design Considerations
3.2.1. General
We used map-based methods in conjunction with our explorations to develop seismic design parameters
in general accordance with the 2014 AASHTO LRFD methodology. The recommended seismic design
parameters are shown in Table 1.
TABLE 1. SEISMIC DESIGN CRITERIA
AASHTO 2014 Seismic Design Parameters
Spectral Response Acceleration at Short Periods (SS) 0.74g
Spectral Response Acceleration at 1-Second Periods (S1) 0.18g
Site Class D
Design Peak Ground Acceleration (As) 0.37g
Design Spectral Response Acceleration at Short Periods (SDS) 0.906g
Design Spectral Response Acceleration at 1-Second Periods (SD1) 0.38g
3.2.2. Liquefaction
Liquefaction refers to a condition where vibration or shaking of the ground, usually from earthquake forces,
results in development of excess pore pressures in saturated soils and a subsequent loss of soil strength.
In general, soils that are susceptible to liquefaction include loose to medium dense “clean” to silty sands
and non-plastic silts that are below the water table. We evaluated the soil profile for liquefaction potential
using methods developed by Idriss and Boulanger (2008). This method compares the predicted cyclic shear
stress (CSS) induced by the design earthquake to the cyclic shear resistance (CSR) determined by
correlations with SPT blow counts. The ratio of the CSR to the CSS is the cyclic shear ratio and is considered
the factor of safety against liquefaction.
Based on the results of our liquefaction analysis we anticipate that the risk of liquefaction occurring at this
site is low. We observed a layer of soil around 20 feet bgs in B-2 with “marginally” liquefiable soils (factor
of safety against liquefaction between 1.0 and 1.2). If this soil layer were to liquify in our opinion it is unlikely
that any settlement as the result of liquefaction would occur. If surface settlements were to occur, we
expect they would be on the order of 1 inch or less.
In our opinion, the liquefaction risk at the site is not significant enough to warrant mitigation. Further, based
on our discussions with Otek, we expect that shallow foundations can be designed to accommodate small
amounts of liquefaction-induced settlements so supporting the bridge on deep foundations bearing below
the potentially liquefiable layer is, in our opinion, not necessary.
November 13, 2019 | Page 4
File No. 0410-205-00
3.2.3. Lateral Spreading Potential
Lateral spreading related to seismic activity typically involves lateral displacement of large, surficial blocks
of non-liquefied soil when a layer of underlying soil loses strength during seismic shaking. Lateral spreading
usually develops in areas where sloping ground or large grade changes (including retaining walls) are
present. Based on our understanding of the liquefaction risk at the site and the proposed improvements it
is our opinion that the risk of lateral spreading is low.
3.2.4. Surface Rupture Potential
According to the Washington State Department of Natural Resources Interactive Natural Hazards Map
(accessed August 15, 2019), there are no known faults mapped within about 7 miles of the site. Based on
the proximity of the site to the nearest known fault, it is our opinion the risk for surface rupture at this site
is low.
3.3. Foundation Support
3.3.1. General
We understand that the anticipated foundation type for the proposed bridge is shallow foundations. We
expect that shallow foundations can provide adequate support provided the foundations bear on medium
dense to dense glacial drift soils. While not addressed in this report, driven pile foundations are also likely
feasible for use at this site. We can provide recommendations for design and construction of driven pile
foundations if requested.
We recommend that shallow foundations be established at least 2 feet below the lowest adjacent grade.
This minimum embedment depth does not consider the effects of scour or the impacts of establishing
foundations on a slope. We recommend footings have a minimum width of 2 feet. The sections below
provide our recommendations for foundation bearing surface preparation and foundation design
parameters.
3.3.2. Foundation Bearing Surface Preparation
Foundations should bear on existing proof compacted glacial drift soils or on structural fill extending to
these soils. The existing fill should be removed from below foundation elements. The bearing surface should
be compacted as necessary to a firm, unyielding condition. Loose or disturbed materials present at the
base of footing excavations should be removed or compacted.
If structural fill is placed below footings as either replacement of overexcavated soils or to establish a
bearing pad, we recommend the structural fill extend laterally beyond the foundation perimeter a distance
equal to the depth of fill (measured from the base of the footing), or 3 feet, whichever is less.
Foundation bearing surfaces should not be exposed to standing water. If water is present in the excavation,
it must be removed before placing formwork and reinforcing steel. Protection of exposed soil, such as
placing a 6-inch thick layer of crushed rock or a 3- to 4-inch layer of lean-mix concrete, could be used to
limit disturbance to bearing surfaces.
Prepared foundation bearing surfaces should be evaluated by a member of our firm prior to placement of
formwork or reinforcing steel to verify that bearing surface has been prepared in accordance with our
recommendations or to provide recommendations for remediating unsuitable bearing soils.
November 13, 2019 | Page 5
File No. 0410-205-00
3.3.3. Foundation Bearing Resistance
Shallow foundation bearing resistance was computed following methodology in the 2014 AASHTO LRFD
Bridge Design Specifications, Section 10.6.3.1.2. Figure 3 provides design bearing resistance for the
Service, Strength, and Extreme Limit States. The provided bearing resistances do not consider the effects
of sloping ground in front of the footings. If the edge of the footing will be located within a horizontal distance
of about 2 times the footing width from the slope as measured from the base of the footing, we should be
notified to provide revised design bearing resistances. The recommended bearing pressures assumes that
footings are established above the groundwater level. In our opinion foundation drains are not necessary
to maintain bearing support.
The Service Limit State assumes an allowable static settlement of 1 inch. The resistance factors for the
Extreme and Strength Limit States are 0.9 and 0.45, respectively. These resistance factors are based on
recommendations in the 2014 AASHTO LRFD and the 2015 Washington State Department of
Transportation (WSDOT) Geotechnical Design Manual (GDM).
3.3.4. Lateral Resistance
The ability of the soil to resist lateral loads is a function of the base friction, which develops on the base of
footings and slabs, and the passive resistance, which develops on the face of below-grade elements of the
structure as these elements move into the soil. For footings founded in accordance with the
recommendations presented above, the frictional resistance on the base of the footing may be computed
using a coefficient of friction of 0.6 applied to the vertical dead-load forces. The passive resistance on the
face of the footing may be computed using the passive resistance values summarized in the “3.4
Conventional Retaining Walls and Subsurface Structures” section of this report. The resistance factors
summarized in Table 2 below should be applied to the frictional and passive resistance values for design.
TABLE 2. LATERAL RESISTANCE FACTORS
Limit State
Resistance Factor
Shear Resistance to Sliding Passive Pressure resistance to
Sliding
Strength 0.8 0.5
Service 1.0 1.0
Extreme 0.9 0.9
3.4. Conventional Retaining Walls and Subsurface Structures
3.4.1. Subsurface Drainage
Subsurface structures and retaining walls will need to include drainage measures (drainpipes or weep
holes) to prevent buildup of excessive hydrostatic pressures or be designed for full hydrostatic pressures
and submerged structural fill values. Even with drainage measures included, we recommend the
subsurface structures be designed to withstand at least 1 foot of hydrostatic differential (i.e., a groundwater
level behind the structure 1 foot higher than the water level in the creek). This will allow for some time lag
in the drainage if the creek level drops suddenly or if the drainage becomes temporarily clogged. A larger
design differential might be required based on the location of the drainpipes or weep holes.
November 13, 2019 | Page 6
File No. 0410-205-00
We recommend a zone of free-draining material behind the retaining structure with perforated pipes to
collect seepage water. Most of the site soils encountered in our explorations contain a significant
percentage of fines (material passing the U.S. No. 200 sieve). Fine soils are susceptible to particle
migration, potentially clogging the drainage. We recommend one of the two following options for drainage
behind retaining walls:
■ Drainage material consisting of “gravel backfill for walls” described in Section 9-03.12(2) of the WSDOT
Standard Specifications. The drainage zone should extend horizontally at least 24 inches from the back
of the retaining structure.
■ Drainage material consisting of material similar to “gravel backfill for drains” described in Section
9-03.12(4) of the WSDOT Standard Specifications. The drainage zone should extend horizontally at
least 12 inches from the back of the retaining structure. A filter fabric designed for separation should
be placed between the gravel backfill and native site soils to prevent soil migration.
3.4.2. Design Parameters
Footings for retaining walls and other subsurface structures should be designed in accordance with the
“3.5 Shallow Foundations” recommendations provided in this report.
We recommend retaining walls, abutments and wing walls, and other subsurface structures be backfilled
with imported structural fill as described in our “3.8 Fill Materials” section below. Fill should be placed and
compacted as described in the “3.9 Fill Placement and Compaction” section of this report. The following
table provides lateral soil pressure parameters suitable for design of subsurface structures.
TABLE 3. LATERAL SOIL PRESSURE PARAMETERS FOR PERMANENT SUBSURFACE STRUCTURES
Soil Parameter Structural Fill/ Glacial Drift Submerged Structural Fill/ Glacial Drift
Soil Unit Weight Total Weight = 120 pcf Total Weight = 125 pcf
Buoyant Weight = 63 pcf
Friction Angle 35 degrees 35 degrees
Cohesion 0 psf 0 psf
Active Earth Pressure1 Ka = 0.27
Equivalent Fluid Pressure: Ka*Unit
Weight = 32.5 pcf
Ka = 0.27
Total Equivalent Fluid Pressure:
(Ka*Buoyant Unit Weight) + hydrostatic =
17 pcf + 62.4 pcf =79 pcf
At-rest Earth Pressure1 Ko = 0.43
Equivalent Fluid Pressure: Ko*Unit
Weight = 51 pcf
Ko = 0.43
Total Equivalent Fluid Pressure:
(Ko*Buoyant Unit Weight) + hydrostatic =
27 pcf + 62.4 pcf = 89 pcf
Passive Earth Pressure1,2 Kp = 3.7
Equivalent Fluid Pressure: Ko*Unit
Weight = 443 pcf
Kp = 3.7
Total Equivalent Fluid Pressure:
(Kp*Buoyant Unit Weight) + hydrostatic =
233 pcf + 62.4 pcf = 295 pcf
Notes:
1 Provided lateral soil pressure parameters are appropriate for the level backfill condition only.
2 The resistance factors in section 3.3.4 “Lateral Resistance” should be applied to the passive earth pressures summarized in this
table.
November 13, 2019 | Page 7
File No. 0410-205-00
If subsurface structures will be designed for seismic forces, we recommend the seismic loading be
approximated using a uniform lateral pressure equal to 10*H psf, where H is the height (in feet) of the
structure. This seismic lateral pressure is in addition to the static soil load and any anticipated hydrostatic
pressures. This assumes that the structure is free to yield somewhat during a seismic event.
The horizontal pressure from uniform vertical surcharge loads (e.g., typical 250 psf traffic loads) can be
estimated by multiplying the vertical pressure by the active (Ka) or at rest (Ko) earth pressure coefficients
provided in Table 3 for the appropriate wall restraint condition. The resulting horizontal pressure should be
applied as a uniform rectangular load acting over the exposed height of the wall. Other surcharge loads or
configurations should be considered on a case-by-case basis.
3.5. Site Development and Earthwork
3.5.1. General
We anticipate site development and earthwork activities will include demolishing existing pavements,
removing existing culverts, site grading, subgrade preparation and placing and compacting fill and backfill
materials. We expect site grading and earthwork can be accomplished with conventional earthmoving
equipment.
3.5.2. Clearing, Stripping, and Demolition
Areas of the site to be developed or graded must be cleared of surface and subsurface deleterious matter,
including any debris and organics. If voids are created during clearing and stripping, they should be
backfilled with compacted structural fill following the recommendations described in this report. During
demolition of existing pavement, excessive disturbance of surficial soils could occur, especially if left
exposed to wet weather conditions and construction or vehicle traffic. Disturbed soils may require
additional remediation during construction and grading. Based on our explorations, we anticipate native
site soils could have a high fines content (material passing the U.S. No. 200 sieve). If exposed, these soils
will be susceptible to disturbance when wet. Care should be taken to avoid allowing these soils to become
saturated and disturbed. We provide recommendations for subgrade protection in the “3.7.6 Subgrade
Protection and Wet Weather Considerations” section below.
We encountered coarse gravels and cobbles in our explorations. We did not observe boulders during our
explorations; however, they could be present in the glacial drift deposits. The contractor should be prepared
to manage these materials if encountered during grading or excavation. Voids caused by removal of large
cobbles or boulders should be backfilled with structural fill.
3.5.3. Temporary Excavations, Shoring and Dewatering
3.5.3.1. General
The proposed culvert replacement will require excavation within existing roadway areas to remove existing
culverts and construct the foundation for the new culvert. We anticipate shoring, groundwater management
(dewatering), and major surface water management (creek by-pass) will be required to construct the
proposed culvert foundations. Portions of construction such as fill placement will also affect the site soil
and how they respond to shoring and dewatering. Depending on the elevations of the culvert footings and
the level of Rock Creek at the time of construction, cofferdams may also be required to prevent water from
flowing into the culvert excavations.
November 13, 2019 | Page 8
File No. 0410-205-00
Excavation, shoring, dewatering, and creek by-pass are all interrelated; the design and implementation of
these elements must be coordinated and must consider the over-all construction staging to ensure a
consistent and compatible approach. For example, more extensive shoring systems that can cut off some
groundwater flow into the excavation will reduce the amount of dewatering that is required. Similarly,
dewatering systems that lower surrounding groundwater levels can be used to reduce pressures on the
shoring system.
Based on our experience it is likely unsupported excavations at the site will cave or slough, especially within
glacial drift soils below the groundwater table. Excavations will need to be sloped or shored to prevent the
sides from caving. Shoring will also be required to protect worker safety and to protect adjacent
improvements including utilities and pavements.
Excavations deeper than 4 feet must be shored or laid back at a stable slope if workers are required to
enter. Shoring and temporary slope inclinations must conform to the provisions of Title 296 Washington
Administrative Code (WAC), Part N, “Excavation, Trenching and Shoring”. Regardless of the soil type
encountered in the excavation shoring, trench boxes or sloped sidewalls will be required under Washington
Industrial Safety and Health Act (WISHA). We recommend the contract documents specify that the
contractor is responsible for selecting excavation and dewatering methods, monitoring the excavations for
safety and providing shoring, as required, to protect personnel and structures.
We recommend for planning purposes all temporary cut slopes be inclined no steeper than about 1.5H to
1V (horizontal to vertical) if workers are required to enter. This guideline assumes all surface loads are kept
at a minimum distance of at least one-half the depth of the cut away from the top of the slope and seepage
is not present on the slope face. Flatter cut slopes could be necessary where seepage occurs or if surface
surcharge loads are anticipated. Temporary covering with heavy plastic sheeting should be used to protect
these slopes during periods of wet weather.
We recommend that the contractor performing the work be made responsible for designing and installing
construction shoring and for controlling and collecting groundwater encountered. The contract documents
should also specify that the contractor is responsible for selecting excavation and dewatering methods,
monitoring the excavations for safety, and providing shoring, as required, to protect personnel and
structures. We recommend that all shoring be designed to accommodate at least 2 feet of overexcavation
of the subgrade. Excavation shoring, cofferdams, and dewatering systems must be designed by a qualified
engineer in accordance with WSDOT Standard Specifications Section 2-09.3(3) D “Shoring and
Cofferdams.” We recommend that we be retained to review the proposed shoring and dewatering plan
before construction.
3.5.3.2. Excavation Shoring
The soil pressures against a shoring wall are dependent on the type of wall, the soil retained, the method
of construction, and the extent of dewatering. For preliminary budgeting and planning purposes, we suggest
that loads against a shoring system be estimated using the soil properties in Table 4 below. These values
are based on our explorations and our experience. These values are for preliminary planning purposes. Soil
and water pressures used in final design must be determined by a qualified engineer and be based on the
specific shoring system that will be constructed. The shoring designer must also confirm that the soil
conditions observed during construction are consistent with the soil conditions assumed during design.
November 13, 2019 | Page 9
File No. 0410-205-00
TABLE 4. PRELIMINARY SOIL PARAMETERS FOR SHORING
Soil Type1
Friction Angle
(degrees)
Cohesion
(psf)
Total Moist Unit Weight
(pcf)
Fill (Existing) 34 – 36 0 125
Glacial Drift (GP-GM and GM) 34 – 36 0 125
Notes:
1 See boring logs for description of soil types and approximate locations.
psf – pounds per square foot.
pcf – pounds per cubic foot.
The shoring method must also consider installation requirements. The presence of large particles such as
cobbles and/or boulders could make installation of some shoring methods, such as sheet piles, difficult or
impractical.
3.5.3.3. Subgrade Stability
If the excavation is completed without lowering the water table outside the excavation, the difference in
pressure between the inside and the outside of the excavation could result in “quick” or boiling sand
conditions in the subgrade. This condition should be considered in the design. Methods to counteract this
include: (1) excavating “in the wet” and placing a filter graded drainage blanket at the subgrade elevation
or (2) installing deeper dewatering wells around the excavation perimeter or additional wells in the interior
of the excavation to reduce excess water pressure.
Heave of the excavation subgrade must also be considered in the shoring design. This condition is more
prone to occur with braced shoring in sand deposits but could also occur under other conditions as well.
Heave may be more pronounced if a less permeable stratum is underlain by a more permeable stratum
(e.g., silty gravel over sand) near the anticipated bottom of excavation. Sand deposits appear to be deeper
than expected excavation limits (on the order of 20 feet bgs); however, potential heaving conditions could
occur if a sand layer is encountered near the bottom of the excavation.
3.5.3.4. Dewatering
As previously discussed, glacial drift soils within about 20 feet of the ground surface consist predominantly
of gravel with variable sand and silt content. While these soils are relatively compact, the coarse-grained
nature of the soils indicates that they may transmit a significant amount of water. Different approaches to
dewatering will be appropriate in different materials and the contractor may need to change approaches
as construction progresses. In addition, dewatering may need to be adjusted to account for fluctuations in
the water table during construction. We anticipate that dewatering in excavation that extend to, or just
below the groundwater level may be achieved with sumps and pumps in the interior of the excavation.
Excavations extending more than a few feet below the groundwater level will likely require dewatering with
well points or dewatering wells to control seepage or heaving and boiling of the subgrade.
Dewatering with deep, widely spaced wells could leave perched groundwater above lenses of relatively less
permeable soils and may not fully dewater the excavation. This is less likely to occur with a series of closely
spaced well points. However, subgrade heave is more likely with well points than deeper wells.
November 13, 2019 | Page 10
File No. 0410-205-00
3.5.4. Permanent Cut and Fill Slopes
We recommend permanent slopes be constructed at a maximum inclination of 2H to 1V. Where 2H to 1V
permanent slopes are not feasible, protective facings and/or retaining structures should be considered.
This guideline assumes all surface loads are kept at a minimum distance of at least one-half the height of
the slope away from the top of the slope and seepage is not present on the slope face. Flatter cut slopes
or additional drainage measures could be necessary where seepage occurs or if surface surcharge loads
are anticipated.
To achieve uniform compaction, we recommend fill slopes be overbuilt and subsequently cut back to
expose well-compacted fill. Fill placement on existing slopes steeper than 5H to 1V should be benched into
the slope face. The configuration of benches depends on the equipment being used and the inclination of
the existing slope. Bench excavations should be level and extend into the existing slope face at least half
the width of the compaction equipment used.
Exposed areas should be re-vegetated as soon as practical to reduce the surface erosion and sloughing.
Temporary protection should be used until permanent protection is established.
3.5.5. Subgrade Preparation
Subgrades should be thoroughly compacted to a uniformly firm and unyielding condition on completion of
stripping. We recommend subgrades be evaluated, as appropriate, to identify areas of yielding or soft soil.
Probing with a steel probe rod or proof-rolling with a heavy piece of wheeled construction equipment are
appropriate methods of evaluation.
If soft or otherwise unsuitable subgrade areas are revealed during evaluation that cannot be compacted to
a stable and uniformly firm condition, we recommend: (1) the unsuitable soils be scarified (e.g., with a
ripper or farmer’s disc), aerated and recompacted, if practical; or (2) the unsuitable soils be removed and
replaced with compacted structural fill, as needed.
3.5.6. Subgrade Protection and Wet Weather Considerations
The soils observed in our borings contain a significant amount of fines. These soils will be susceptible to
disturbance during periods of wet weather, sensitive to small changes in moisture and susceptible to
disturbance from construction traffic when wet or if earthwork is performed during wet weather. When the
moisture content of the soil is more than a few percent above the optimum moisture content, the soil can
become muddy and unstable and it will be challenging to meet the required compaction criteria. The wet
weather season generally begins in October and continues through May in western Washington; however,
periods of wet weather can occur during any month of the year. In our opinion, earthwork at the site should
take place during the summer months or during periods of extended dry weather. If wet weather earthwork
is unavoidable, we offer the following recommendations:
■ The ground surface in and around the work area should be sloped so that surface water is directed
away from the work area. The ground surface should be graded so areas of ponded water do not
develop. Measures should be taken by the contractor to prevent surface water from collecting in
excavations and trenches. Measures should be implemented to remove surface water from work areas.
■ Earthwork activities should not take place during periods of heavy precipitation.
■ Slopes with exposed soils should be covered with plastic sheeting.
November 13, 2019 | Page 11
File No. 0410-205-00
■ The contractor should take necessary measures to prevent on-site soils and other soils to be used as
fill from becoming wet or unstable. These measures may include the use of plastic sheeting, sumps
with pumps and grading. The site soils should not be left uncompacted and exposed to moisture.
Sealing exposed soils by rolling with a smooth-drum roller prior to periods of precipitation will help
reduce the extent to which these soils absorb water and become wet or unstable.
■ Construction traffic should be restricted to specific areas of the site, preferably areas that are surfaced
with working pad materials not susceptible to wet weather disturbance.
■ Construction activities should be scheduled so that the length of time that soils are left exposed to
moisture is reduced to the extent practical.
■ Protective surfacing such as placing asphalt-treated base (ATB), cement treated base (CTB), cement
treated subgrades, or haul roads made of quarry spalls or a layer of free-draining material such as well-
graded pit-run sand and gravel may be necessary to protect completed areas from construction traffic.
Typically, minimum gravel thicknesses on the order of 18 inches are necessary to provide adequate
subgrade protection for repeated construction traffic.
3.6. Fill Materials
3.6.1. Structural Fill
Material used for structural fill should be free of debris, organic contaminants and rock fragments larger
than 6 inches in maximum dimension. We recommend structural fill consist of material similar to “Select
Borrow” or “Gravel Borrow” as described in Section 9-03.14 of the WSDOT Standard Specifications, or
“Aggregate for Gravel Base” as described in Section 9-03.10. We recommend crushed rock or select
granular fill (described below) be used for structural fill during the wet season.
3.6.2. Select Granular Fill
If imported fill is needed during wet weather conditions, we recommend select granular fill is used. Select
granular fill should consist of well-graded sand and gravel or crushed rock with a maximum particle size of
6 inches and less than 5 percent fines by weight based on the minus ¾-inch fraction. Organic matter, debris
or other deleterious material should not be present. Material with gradation characteristics similar to
“Aggregates for Ballast and Crushed Surfacing” (Section 9-03.9 of the WSDOT Standard Specifications),
“Gravel Borrow” (Section 9-03.14(1)) or “Select Borrow” (Section 9-03.14(2)) is also suitable for use as
select granular fill, provided the fines content is less than 5 percent (based on the minus ¾-inch fraction)
and the maximum particle size is 6 inches.
3.6.3. Recycled Materials
In our opinion, recycled material (such as asphalt and concrete) may be used as fill material provided the
material is in accordance with WSDOT Standard Specifications Section 9-03.21 “Recycled Material” and
meets requirements for its end use.
Recycled materials may be blended provided the recycled material component included in a blended
product meets the specification requirements for the specified material. We recommend the amount of
recycled material generally not exceed percentages presented in WSDOT Standard Specifications Table
9-03.21(1)E. As an example, Table 9-03.21(1)E allows a maximum 20 percent by weight of hot mix asphalt
November 13, 2019 | Page 12
File No. 0410-205-00
for recycled material to be used as “Gravel Borrow”. Accordingly, about a 3-inch-thick section of hot mix
asphalt would need to be blended with about 12 inches of aggregate to achieve this percentage.
Blending may be achieved as recycled material (e.g., asphalt) is ground in-place and mixed with underlaying
aggregate, windrowing with a bulldozer, or other methods. The final blended product (including the recycled
material component) shall meet the specification requirements for “Gravel Borrow” (WSDOT Standard
Specifications Section 9-03.14(1)). Higher percentages might be allowed on a case-by-case basis as
approved by the engineer. Higher percentages will be evaluated and accepted or rejected in the field during
construction based on quality and proposed location of material.
Recycled materials must not be used as fill below the groundwater table or in drainage applications.
3.6.4. On-Site Soils
Based on our subsurface explorations and experience, it is our opinion that existing site soils including the
existing fill may be considered for use as structural fill, provided that it can be adequately moisture
conditioned, placed and compacted as recommended and does not contain organic or other deleterious
material. The gravel drift contains a significant amount of cobbles and may contain boulders. These
oversized particles (greater than about 6 inches in dimension) can inhibit compaction and fine grading and
might need to be removed before the soil is used as structural fill. The majority of the soils observed in our
explorations contained a significant amount of fines and will be moisture sensitive and very difficult or
impossible to properly compact when wet. In addition, it is possible that existing soils will be generated at
moisture contents above optimum especially in excavations near the elevation of the creek. If earthwork
occurs during a typical wet season, or if the soils are persistently wet and cannot be dried due to prevailing
wet weather conditions, we recommend the use of imported structural fill or select granular fill, as described
above.
3.7. Fill Placement and Compaction
To obtain proper compaction, fill material should be compacted near optimum moisture content and in
uniform horizontal lifts. Lift thickness and compaction procedures will depend on the moisture content and
gradation characteristics of the soil and the type of equipment used. Generally, 12-inch-thick loose lifts are
appropriate for steel-drum vibratory roller compaction equipment. The maximum allowable moisture
content varies with the soil gradation and should be evaluated during construction. Compaction should be
achieved by mechanical means. During fill and backfill placement, sufficient testing of in-place density
should be conducted to verify adequate compaction is being achieved.
Fill placed under structural areas (such as culverts or wingwalls), under pavements, or to raise site grades
should be placed on subgrades prepared as previously recommended. Fill material placed below structural
areas or under pavement sections must be compacted to at least 95 percent of the theoretical maximum
dry density (MDD) per ASTM International (ASTM) D 1557. In landscaping or other non-structural areas, fill
should be compacted to a firm condition that will support construction equipment, as necessary, typically
around 85 to 90 percent of the MDD.
3.7.1. Fill Placement Below the Water Table
Where fill placement is required on wet subgrades below the water table, we recommend fill consist of
angular rock with few fines. In our opinion, material conforming to WSDOT Standard Specification 9-03.9(2)
November 13, 2019 | Page 13
File No. 0410-205-00
“Permeable Ballast” is suitable for this purpose. The rock must be placed in lifts and tamped with an
excavator bucket. A geotextile may be required between the rock and any overlaying fill to prevent material
from being lost into the voids in the rock.
4.0 LIMITATIONS
We have prepared this report for the exclusive use of the City of Kent and their authorized agents for the
Summit Landsburg Road Replacement project in Kent, Washington. City of Kent may distribute copies of
this report to owner and owner’s authorized agents and regulatory agencies as may be required for the
project.
Within the limitations of scope, schedule and budget, our services have been executed in accordance with
generally accepted practices in the field of geotechnical engineering in this area at the time this preliminary
design report was prepared. The conclusions, recommendations, and opinions presented in this report are
based on our professional knowledge, judgment and experience. No warranty or other conditions, express
or implied, should be understood.
Please refer to Appendix B titled “Report Limitations and Guidelines for Use” for additional information
pertaining to use of this report.
µ
SITE
Vicinity Map
Figure 1
Summit Landsburg Road Culvert ReplacementKent, Washington
2,000 2,0000
Feet
Data Source: Mapbox Open Street Map, 2015
Notes:1. The locations of all features shown are approximate.2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document. GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and will serve as the official record of this communication.
Projection: NAD 1983 StatePlane Washington North FIPS 4601 Feet
P:\0\0410205\GIS\MXD\041020500_F01_Vicinity Map.mxd Date Exported: 08/08/19 by syi
B-1
B-2
SE S
u
m
mit L
a
n
ds
b
urg
R
o
a
dRoc
k
C
r
e
e
k
Roc
k
C
r
e
e
k
Approximate Location
of Existing Culvert
Figure 2
Summit Landsburg Road Culvert Replacement
Kent, Washington
Site Plan
W E
N
S
P:\0\0410205\CAD\00\Geotech Report\041020500_F02_Site Plan.dwg TAB:F02 Date Exported: 11/13/19 - 10:44 by syiFeet
020 20
Notes:
1.The locations of all features shown are approximate.
2.This drawing is for information purposes. It is intended to assist in showing
features discussed in an attached document. GeoEngineers, Inc. cannot
guarantee the accuracy and content of electronic files. The master file is stored
by GeoEngineers, Inc. and will serve as the official record of this communication.
Data Source: Aerial from Google Earth Pro dated May 2018.
Vertical Datum: NAVD 88.
Projection: NAD83 Washington State Planes, North Zone, US Foot.
Legend
Boring by GeoEngineers, Inc., 2019B-1
Figure 3
Shallow Foundation Bearing Resistance
Summit Landsburg Road Culvert Replacement
Kent, Washington
0410-205-00 Date Exported: 11/13/19
APPENDIX A
Subsurface Explorations and Laboratory Testing
November 13, 2019 | Page A-1
File No. 0410-205-00
APPENDIX A
SUBSURFACE EXPLORATIONS AND LABORATORY TESTING
Subsurface Explorations
Soil and groundwater conditions at the site were explored by advancing two borings on July 23, 2019.
Locations of the borings were determined via an electronic tablet with global positioning system (GPS)
software and are shown on the Site Plan, Figure 2. The locations and elevations of the explorations should
be considered approximate. Exploration locations were constrained to some degree by site infrastructure.
The borings were completed using truck-mounted drilling equipment provided and operated by Holocene
Drilling, Inc. under subcontract to GeoEngineers. Borings were advanced using hollow-stem auger drilling
methods and advanced to depths between approximately 35.5 and 45 feet below existing site grade (bgs).
Borings were backfilled by the driller in accordance with Washington State Department of Ecology
requirements. Soil cuttings generated from the borings were placed in metal barrels and hauled off site for
disposal.
During the exploration program our field representative continuously monitored the borings, obtained
representative soil samples, classified the soils, maintained a detailed log of each exploration and observed
groundwater conditions. Soil samples were obtained from the borings using a 1.4-inch inner diameter split-
barrel sampler driven into the soil using a 140-pound hammer free-falling a distance of 30 inches. The
number of blows required to drive the sampler the last 12 inches or other indicated distance is recorded
on the logs as the blow count. Our field representative made sample attempts at 2.5- to 5-foot depth
intervals. Samples were retained in sealed plastic bags to prevent moisture loss. The soils were classified
visually in general accordance with ASTM International (ASTM) D 2488 and Figure A-1, which includes a
Key to the Exploration Logs. Summary logs of the explorations are included as Figures A-2 and A-3.
Laboratory Testing
Soil samples obtained from the explorations were transported to the GeoEngineers laboratory.
Representative soil samples were selected for laboratory tests to evaluate the pertinent geotechnical
engineering characteristics of the soils and to confirm our field classification. The following paragraphs
provide a description of tests performed.
Sieve Analysis (SA)
Sieve analyses were performed on selected samples in general accordance with ASTM Test Method D
6913. This test method covers the quantitative determination of the distribution of particle sizes in soils.
Typically, the distribution of particle sizes larger than 75 micrometers (m) is determined by sieving. The
results of the tests were used to verify field soil classifications. Figures A-4 and A-5 present the results of
our sieve analyses.
Percent Fines (%F)
Selected samples were “washed” through the U.S. No. 200 sieve to estimate the relative percentages of
coarse- and fine-grained particles in the soil. The percent passing value represents the percentage by
weight of the sample finer than the U.S. No. 200 sieve (fines). Tests were conducted in general accordance
with ASTM D 1140. Test results are used to aid in soil classification and correlation with other pertinent
engineering soil properties and are presented on the exploration logs at the respective sample depths.
Measured groundwater level in exploration,
well, or piezometer
Measured free product in well or piezometer
Distinct contact between soil strata
Approximate contact between soil strata
Contact between geologic units
SYMBOLS TYPICAL
DESCRIPTIONS
GW
GP
SW
SP
SM
FINE
GRAINED
SOILS
SILTS AND
CLAYS
NOTE: Multiple symbols are used to indicate borderline or dual soil classifications
MORE THAN 50%
RETAINED ON
NO. 200 SIEVE
MORE THAN 50%
PASSING
NO. 200 SIEVE
GRAVEL
AND
GRAVELLY
SOILS
SC
LIQUID LIMIT
LESS THAN 50
(APPRECIABLE AMOUNT
OF FINES)
(APPRECIABLE AMOUNT
OF FINES)
COARSE
GRAINED
SOILS
MAJOR DIVISIONS GRAPH LETTER
GM
GC
ML
CL
OL
SILTS AND
CLAYS
SANDS WITH
FINES
SAND
AND
SANDY
SOILS
MH
CH
OH
PT
(LITTLE OR NO FINES)
CLEAN SANDS
GRAVELS WITH
FINES
CLEAN GRAVELS
(LITTLE OR NO FINES)
WELL-GRADED GRAVELS, GRAVEL -SAND MIXTURES
CLAYEY GRAVELS, GRAVEL - SAND -CLAY MIXTURES
WELL-GRADED SANDS, GRAVELLYSANDS
POORLY-GRADED SANDS, GRAVELLYSAND
SILTY SANDS, SAND - SILT MIXTURES
CLAYEY SANDS, SAND - CLAYMIXTURES
INORGANIC SILTS, ROCK FLOUR,CLAYEY SILTS WITH SLIGHTPLASTICITY
INORGANIC CLAYS OF LOW TOMEDIUM PLASTICITY, GRAVELLYCLAYS, SANDY CLAYS, SILTY CLAYS,LEAN CLAYS
ORGANIC SILTS AND ORGANIC SILTYCLAYS OF LOW PLASTICITY
INORGANIC SILTS, MICACEOUS ORDIATOMACEOUS SILTY SOILS
INORGANIC CLAYS OF HIGHPLASTICITY
ORGANIC CLAYS AND SILTS OFMEDIUM TO HIGH PLASTICITY
PEAT, HUMUS, SWAMP SOILS WITHHIGH ORGANIC CONTENTSHIGHLY ORGANIC SOILS
SOIL CLASSIFICATION CHART
MORE THAN 50%
OF COARSE
FRACTION RETAINED
ON NO. 4 SIEVE
MORE THAN 50%
OF COARSE
FRACTION PASSING
ON NO. 4 SIEVE
SILTY GRAVELS, GRAVEL - SAND -SILT MIXTURES
POORLY-GRADED GRAVELS,GRAVEL - SAND MIXTURES
LIQUID LIMIT GREATER
THAN 50
Continuous Coring
Bulk or grab
Direct-Push
Piston
Shelby tube
Standard Penetration Test (SPT)
2.4-inch I.D. split barrel
Contact between soil of the same geologic
unit
Material Description Contact
Graphic Log Contact
NOTE: The reader must refer to the discussion in the report text and the logs of explorations for a proper understanding of subsurface conditions.
Descriptions on the logs apply only at the specific exploration locations and at the time the explorations were made; they are not warranted to be
representative of subsurface conditions at other locations or times.
Groundwater Contact
Blowcount is recorded for driven samplers as the number of
blows required to advance sampler 12 inches (or distance noted).
See exploration log for hammer weight and drop.
"P" indicates sampler pushed using the weight of the drill rig.
"WOH" indicates sampler pushed using the weight of the
hammer.
Key to Exploration Logs
Figure A-1
Sampler Symbol Descriptions
ADDITIONAL MATERIAL SYMBOLS
NS
SS
MS
HS
No Visible Sheen
Slight Sheen
Moderate Sheen
Heavy Sheen
Sheen Classification
SYMBOLS
Asphalt Concrete
Cement Concrete
Crushed Rock/
Quarry Spalls
Topsoil
GRAPH LETTER
AC
CC
SOD Sod/Forest Duff
CR
DESCRIPTIONS
TYPICAL
TS
Percent fines
Percent gravel
Atterberg limits
Chemical analysis
Laboratory compaction test
Consolidation test
Dry density
Direct shear
Hydrometer analysis
Moisture content
Moisture content and dry density
Mohs hardness scale
Organic content
Permeability or hydraulic conductivity
Plasticity index
Point lead test
Pocket penetrometer
Sieve analysis
Triaxial compression
Unconfined compression
Vane shear
%F
%G
AL
CA
CP
CS
DD
DS
HA
MC
MD
Mohs
OC
PM
PI
PL
PP
SA
TX
UC
VS
Laboratory / Field Tests
Drill chatter 5 to 8 feet
Hard drilling 9 to approximately 30 feet
No recovery with SPT. 2.4-inch sampler driven for
recovery. Groundwater observed at 10 feet
during drilling.
Drill chatter 25 to 30 feet
5
14
4
28
12 inches asphalt concrete
Dark brown medium to coarse sand with gravel and
trace silt (very dense, moist) (fill)
Brown fine to coarse gravel with silt and sand (dense,
moist)
Bluish gray silty fine to coarse sand with gravel (loose,
moist) (glacial drift)
Grades to medium dense
Bluish-gray with iron-oxide staining silty fine to coarse
gravel with sand and occasional cobbles (medium
dense, wet)
Grades to dense
Brown fine to coarse gravel with silt and sand (medium
dense, wet)
Grades to very dense
Brown silty fine to coarse sand with occasional gravel
(medium dense, moist)
1SA
2
3
4
SA
5
6
10
1
0
3
0
0
6
2
50
33
8
15
27
39
29
73
AC
SW
GP-GM
SM
GM
GP-GM
SM
Notes:
45 CJL
BEL Holocene Drilling, Inc. Hollow-stem Auger
Diedrich D120 Truck RigDrilling
Equipment140 (lbs) / 30 (in) Drop
WA State Plane North
WGS84 (feet)
47.3652
-122.014
550
NAVD88
Latitude
Longitude
Start Total
Depth (ft)
Logged By
Checked By
End
Surface Elevation (ft)
Vertical Datum
Drilled
Hammer
Data
System
Datum
Driller Drilling
Method
See "Remarks" section for groundwater observed
7/23/20197/23/2019
Note: See Figure A-1 for explanation of symbols.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.
Sheet 1 of 2Project Number:
Project Location:
Project:
Kent, Washington
0410-205-00
Log of Boring B-1
Summit Landsburg Road Culvert Replacement
Figure A-2
Date:11/13/19 Path:P:\0\0410205\GINT\041020500.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_GEOTECH_STANDARD_%F_NO_GWREMARKS
MoistureContent (%)FinesContent (%)FIELD DATA
MATERIAL
DESCRIPTION
Sample NameTestingRecovered (in)IntervalBlows/footCollected SampleDepth (feet)0
5
10
15
20
25
30 Graphic LogGroupClassificationElevation (feet)545540535530525520
Smoother drilling 30 to 43 feet
Drill chatter at 43 feet; cobble lodged inside
auger
Practical drilling refusal at 45 feet
14 14
Brown fine to medium sand with silt (medium dense,
wet)
Brown silty fine to coarse sand with gravel (dense,
moist) (glacial till)
Grades to with cobbles and very dense
7SA
8
9
18
12
12
0
26
25
47
50/1"
SP-SM
SM
Sheet 2 of 2Project Number:
Project Location:
Project:
Kent, Washington
0410-205-00
Log of Boring B-1 (continued)
Summit Landsburg Road Culvert Replacement
Figure A-2
Date:11/13/19 Path:P:\0\0410205\GINT\041020500.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_GEOTECH_STANDARD_%F_NO_GWREMARKS
MoistureContent (%)FinesContent (%)FIELD DATA
MATERIAL
DESCRIPTION
Sample NameTestingRecovered (in)IntervalBlows/footCollected SampleDepth (feet)30
35
40
45 Graphic LogGroupClassificationElevation (feet)515510505
Vac truck used to excavate 0 to 3½ feet
Gravel in sampler shoe
Drill chatter 6 to 20 feet
Groundwater observed at 19 feet during drilling
Smooth drilling 20 to 25 feet
Driller indicates increasing drilling resistance
between 25 and 36 feet; approximately 1 inch
heave at 25 feet, slurry added to hole
10
7
24
11
14
17
10
9
12 inches asphalt concrete
Brown fine to coarse gravel with silt and sand and
cobbles (dense, moist) (fill)
Brown silty fine to coarse gravel with sand (loose,
moist)
Grades to medium dense
Brown silty fine to coarse gravel with sand (medium
dense, moist) (glacial drift)
Grades to dense
Grades to wet
Brown fine to medium sand with silt and occasional
gravel (medium dense, wet)
Gray fine to coarse sand with silt and gravel (very
dense, wet)
1
SA
2
3
4
5
SA
6%F
7SA
1
3
10
12
10
12
4
18
44
43
16
56
AC
GP-GM
GM
GM
SP-SM
SP-SM
Notes:
36 CJL
BEL Holocene Drilling, Inc. Hollow-stem Auger
Diedrich D120 Truck RigDrilling
Equipment140 (lbs) / 30 (in) Drop
WA State Plane North
WGS84 (feet)
47.3653
-122.0137
554
NAVD88
Latitude
Longitude
Start Total
Depth (ft)
Logged By
Checked By
End
Surface Elevation (ft)
Vertical Datum
Drilled
Hammer
Data
System
Datum
Driller Drilling
Method
See "Remarks" section for groundwater observed
7/23/20197/23/2019
Note: See Figure A-1 for explanation of symbols.
Coordinates Data Source: Horizontal approximated based on Aerial Imagery. Vertical approximated based on Google Earth.
Sheet 1 of 2Project Number:
Project Location:
Project:
Kent, Washington
0410-205-00
Log of Boring B-2
Summit Landsburg Road Culvert Replacement
Figure A-3
Date:11/13/19 Path:P:\0\0410205\GINT\041020500.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_GEOTECH_STANDARD_%F_NO_GWREMARKS
MoistureContent (%)FinesContent (%)FIELD DATA
MATERIAL
DESCRIPTION
Sample NameTestingRecovered (in)IntervalBlows/footCollected SampleDepth (feet)0
5
10
15
20
25
30 Graphic LogGroupClassificationElevation (feet)550545540535530525
Practical drilling refusal at 35½ feet
Brown-gray fine to coarse gravel with silt and sand
(very dense, wet)
8
9
3
3
50/5"
50/6"
GP-GM
Sheet 2 of 2Project Number:
Project Location:
Project:
Kent, Washington
0410-205-00
Log of Boring B-2 (continued)
Summit Landsburg Road Culvert Replacement
Figure A-3
Date:11/13/19 Path:P:\0\0410205\GINT\041020500.GPJ DBLibrary/Library:GEOENGINEERS_DF_STD_US_JUNE_2017.GLB/GEI8_GEOTECH_STANDARD_%F_NO_GWREMARKS
MoistureContent (%)FinesContent (%)FIELD DATA
MATERIAL
DESCRIPTION
Sample NameTestingRecovered (in)IntervalBlows/footCollected SampleDepth (feet)30
35 Graphic LogGroupClassificationElevation (feet)520
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.11101001000PERCENT PASSING BY WEIGHT GRAIN SIZE IN MILLIMETERS
U.S. STANDARD SIEVE SIZE
2”
SAND SILT OR CLAYCOBBLESGRAVEL
COARSE MEDIUM FINECOARSEFINE
Boring Number Depth(feet)Laboratory Soil Description
B-1
B-1
B-1
B-2
1
10
30
2.5
Medium to coarse sand with gravel (SW)
Silty fine to coarse gravel with sand (GM)
Silty fine to coarse sand with occasional gravel (SM)
Silty fine to coarse gravel with sand (GM)
Symbol Moisture(%)
5
14
14
10
3/8”3”1.5”#4 #10 #20 #40 #60 #1003/4”Figure-A-4Sieve Analysis ResultsSummit Landsburg Road Culvert Replacement Kent, Washington0410-205-00 Date Exported: 11/13/19
Note:This report may not be reproduced,except in full,without written approval of GeoEngineers,Inc.Test results are applicable only to the specific sample on which they were
performed,and should not be interpreted as representative of any other samples obtained at other times,depths or locations,or generated by separate operations or processes.
The grain size analysis results were obtained in general accordance with ASTM D 6913.GeoEngineers 17425 NE Union Hill Road Ste 250,Redmond,WA 98052
#2001”#140
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.11101001000PERCENT PASSING BY WEIGHT GRAIN SIZE IN MILLIMETERS
U.S. STANDARD SIEVE SIZE
2”
SAND SILT OR CLAYCOBBLESGRAVEL
COARSE MEDIUM FINECOARSEFINE
Boring Number Depth(feet)Laboratory Soil Description
B-2
B-2
15
25
Silty fine to coarse gravel with sand (GM)
Fine to coarse sand with silt and gravel (SP-SM)
Symbol Moisture(%)
7
11
3/8”3”1.5”#4 #10 #20 #40 #60 #1003/4”Figure-A-5Sieve Analysis Results0410-205-00 Date Exported: 11/13/19
Note:This report may not be reproduced,except in full,without written approval of GeoEngineers,Inc.Test results are applicable only to the specific sample on which they were
performed,and should not be interpreted as representative of any other samples obtained at other times,depths or locations,or generated by separate operations or processes.
The grain size analysis results were obtained in general accordance with ASTM D 6913.GeoEngineers 17425 NE Union Hill Road Ste 250,Redmond,WA 98052
#2001”#140
Summit Landsburg Road Culvert Replacement Kent, Washington
APPENDIX B
Report Limitations and Guidelines for Use
November 13, 2019 | Page B-1
File No. 0410-205-00
APPENDIX B
REPORT LIMITATIONS AND GUIDELINES FOR USE1
This appendix provides information to help you manage your risks with respect to the use of this report.
Read These Provisions Closely
It is important to recognize that the geoscience practices (geotechnical engineering, geology and
environmental science) rely on professional judgment and opinion to a greater extent than other
engineering and natural science disciplines, where more precise and/or readily observable data may exist.
To help clients better understand how this difference pertains to our services, GeoEngineers includes the
following explanatory “limitations” provisions in its reports. Please confer with GeoEngineers if you need to
know more how these “Report Limitations and Guidelines for Use” apply to your project or site.
Geotechnical Services are Performed for Specific Purposes, Persons and Projects
This report has been prepared for City of Kent and for the Project(s) specifically identified in the report. The
information contained herein is not applicable to other sites or projects.
GeoEngineers structures its services to meet the specific needs of its clients. No party other than the party
to whom this report is addressed may rely on the product of our services unless we agree to such reliance
in advance and in writing. Within the limitations of the agreed scope of services for the Project, and its
schedule and budget, our services have been executed in accordance with our Agreement with City of Kent
dated April 22, 2019 and generally accepted geotechnical practices in this area at the time this report was
prepared. We do not authorize, and will not be responsible for, the use of this report for any purposes or
projects other than those identified in the report.
A Geotechnical Engineering or Geologic Report is based on a Unique Set of Project-Specific
Factors
This report has been prepared for the Summit Landsburg Road Culvert Replacement project located in
Kent, Washington. GeoEngineers considered a number of unique, project-specific factors when establishing
the scope of services for this project and report. Unless GeoEngineers specifically indicates otherwise, it is
important not to rely on this report if it was:
■ not prepared for you,
■ not prepared for your project,
■ not prepared for the specific site explored, or
■ completed before important project changes were made.
For example, changes that can affect the applicability of this report include those that affect:
■ the function of the proposed structure;
■ elevation, configuration, location, orientation or weight of the proposed structure;
1 Developed based on material provided by ASFE, Professional Firms Practicing in the Geosciences; www.asfe.org.
November 13, 2019 | Page B-2
File No. 0410-205-00
■ composition of the design team; or
■ project ownership.
If changes occur after the date of this report, GeoEngineers cannot be responsible for any consequences
of such changes in relation to this report unless we have been given the opportunity to review our
interpretations and recommendations. Based on that review, we can provide written modifications or
confirmation, as appropriate.
Environmental Concerns are Not Covered
Unless environmental services were specifically included in our scope of services, this report does not
provide any environmental findings, conclusions, or recommendations, including but not limited to, the
likelihood of encountering underground storage tanks or regulated contaminants.
Information Provided by Others
GeoEngineers has relied upon certain data or information provided or compiled by others in the
performance of our services. Although we use sources that we reasonably believe to be trustworthy,
GeoEngineers cannot warrant or guarantee the accuracy or completeness of information provided or
compiled by others.
Subsurface Conditions Can Change
This geotechnical or geologic report is based on conditions that existed at the time the study was performed.
The findings and conclusions of this report may be affected by the passage of time, by man-made events
such as construction on or adjacent to the site, new information or technology that becomes available
subsequent to the report date, or by natural events such as floods, earthquakes, slope instability or
groundwater fluctuations. If more than a few months have passed since issuance of our report or work
product, or if any of the described events may have occurred, please contact GeoEngineers before applying
this report for its intended purpose so that we may evaluate whether changed conditions affect the
continued reliability or applicability of our conclusions and recommendations.
Geotechnical and Geologic Findings are Professional Opinions
Our interpretations of subsurface conditions are based on field observations from widely spaced sampling
locations at the site. Site exploration identifies the specific subsurface conditions only at those points where
subsurface tests are conducted or samples are taken. GeoEngineers reviewed field and laboratory data
and then applied its professional judgment to render an informed opinion about subsurface conditions at
other locations. Actual subsurface conditions may differ, sometimes significantly, from the opinions
presented in this report. Our report, conclusions and interpretations are not a warranty of the actual
subsurface conditions.
Geotechnical Engineering Report Recommendations are Not Final
We have developed the following recommendations based on data gathered from subsurface
investigation(s). These investigations sample just a small percentage of a site to create a snapshot of the
subsurface conditions elsewhere on the site. Such sampling on its own cannot provide a complete and
accurate view of subsurface conditions for the entire site. Therefore, the recommendations included in this
report are preliminary and should not be considered final. GeoEngineers’ recommendations can be
November 13, 2019 | Page B-3
File No. 0410-205-00
finalized only by observing actual subsurface conditions revealed during construction. GeoEngineers
cannot assume responsibility or liability for the recommendations in this report if we do not perform
construction observation.
We recommend that you allow sufficient monitoring, testing and consultation during construction by
GeoEngineers to confirm that the conditions encountered are consistent with those indicated by the
explorations, to provide recommendations for design changes if the conditions revealed during the work
differ from those anticipated, and to evaluate whether earthwork activities are completed in accordance
with our recommendations. Retaining GeoEngineers for construction observation for this project is the most
effective means of managing the risks associated with unanticipated conditions. If another party performs
field observation and confirms our expectations, the other party must take full responsibility for both the
observations and recommendations. Please note, however, that another party would lack our project-
specific knowledge and resources.
A Geotechnical Engineering or Geologic Report Could Be Subject to Misinterpretation
Misinterpretation of this report by members of the design team or by contractors can result in costly
problems. GeoEngineers can help reduce the risks of misinterpretation by conferring with appropriate
members of the design team after submitting the report, reviewing pertinent elements of the design team’s
plans and specifications, participating in pre-bid and preconstruction conferences, and providing
construction observation.
Do Not Redraw the Exploration Logs
Geotechnical engineers and geologists prepare final boring and testing logs based upon their interpretation
of field logs and laboratory data. The logs included in a geotechnical engineering or geologic report should
never be redrawn for inclusion in architectural or other design drawings. Photographic or electronic
reproduction is acceptable, but separating logs from the report can create a risk of misinterpretation.
Give Contractors a Complete Report and Guidance
To help reduce the risk of problems associated with unanticipated subsurface conditions, GeoEngineers
recommends giving contractors the complete geotechnical engineering or geologic report, including these
“Report Limitations and Guidelines for Use.” When providing the report, you should preface it with a clearly
written letter of transmittal that:
■ advises contractors that the report was not prepared for purposes of bid development and that its
accuracy is limited; and
■ encourages contractors to confer with GeoEngineers and/or to conduct additional study to obtain the
specific types of information they need or prefer.
Contractors are Responsible for Site Safety on Their Own Construction Projects
Our geotechnical recommendations are not intended to direct the contractor’s procedures, methods,
schedule or management of the work site. The contractor is solely responsible for job site safety and for
managing construction operations to minimize risks to on-site personnel and adjacent properties.
November 13, 2019 | Page B-4
File No. 0410-205-00
Biological Pollutants
GeoEngineers’ Scope of Work specifically excludes the investigation, detection, prevention or assessment
of the presence of Biological Pollutants. Accordingly, this report does not include any interpretations,
recommendations, findings or conclusions regarding the detecting, assessing, preventing or abating of
Biological Pollutants, and no conclusions or inferences should be drawn regarding Biological Pollutants as
they may relate to this project. The term “Biological Pollutants” includes, but is not limited to, molds, fungi,
spores, bacteria and viruses, and/or any of their byproducts.
A Client that desires these specialized services is advised to obtain them from a consultant who offers
services in this specialized field.