HomeMy WebLinkAboutPW13-103 - Change Order - #19 - Goodfellow Bros., Inc. - SE 256th St Improvements - 05/30/2014 • III
KENT
W<SMINGTGN
CHANGE ORDER NO. #19
NAME OF CONTRACTOR: Goodfellow Brothers. Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER: SE 256th Street Improvements
ORIGINAL CONTRACT DATE: June 6, 2013
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to;
Work to install new side sewers, work necessary to proceed not in
contract.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $5,208,988.60
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $56,145.52
(incl. applicable WSST)
Current Contract Amount $5,265,134.12
(incl. Previous Change Orders)
Current Change Order $4,476.38
Applicable WSST Tax on this Change $425.26
Order
Revised Contract Sum $5,270,035.76
CHANGE ORDER - 1 OF 3
GL' I 2.
II
Original Time for Completion 300 working days
(insert date)
Revised Time for Completion under 304working days
prior Change Orders
(insert date)
Days Required (t) for this Change 3 calendar days
Order
Revised Time for Completion 307 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
;n1 fY�z�By: By:
11 (sig ature) signature)
Print Nab; 4_rx�' V"A" gyp.) Print Name: Timothy J LaPorte, P.E.
Its G;;:-tA r o., 5 Its Public Works Director
(title) U tiH
DATE: mil' ��II F DATE: Z
CHANGE ORDER - 2 OF 3
I
�, T FILE NO: 200.2
CHANGE ORDER WORKSHEET NO. 19
Construction Management Division - Public Works
Project:. SE 256th Street Improvements Project No.: 09-3012C
Project Engineer: Mark Madfai Fed-Aid No.: N/A
Owners Rep: Phil McConnell Contractor: Goodfellow Brothers
Date: 4/9 & 11/2014
I. PROPOSED CHANGE
I
Work to install new side sewers
II. REASON AND BACKGROUND FOR CHANGE
Work added after contract let t�
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ❑ Not Applicable
Change Order No. I I - I j I I FOR ACCOUNTING USE ONLY
Sch. No. Item Description I Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
9 work to install new side 1 1 Is $4,476.38 $4,476.38
sewers I
Independent Estimate Attached ❑ CREATE PAY ITEM ONLY- Payment to be made i PAY THIS PAY ESTIMATE
� at a. later date upon completion of work
Material Submittals Required - CC: Construction Coordinator i New Sub Reqrd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. i - I I I I FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. _ Item Description _' _ Qty j Unit Unit Price __ Cost of Item
—
-`---_-----�-------- - —'-- - ------- --- ----�' ---------------__--- ------------
Independent Estimate Attached - REQUIRED
!
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. - i FOR ACCOUNTING USE ONLY
Sch, No. B.I. No. ! Item Description Qty _ Unit Unit_Price Cost of Item
I
Independent Estimate Attached -REQUIRED
1 REV. DATE: 4/01/10
• FILE NO: 200.2
KENT
Wn5X1XGiO TOTAL ESTIMATED COST OF CHANGE ORDER * $4,476.38
*Total of the Cost of Item Columns
THIS PAY ESTIMATE $4,476.38
IV. WORKING DAYS
Original Contract 1300 Due This Change Order* 3 Previous Total 304
DATE:_,4 9 2014 , _-______.__---__.___._ DATE�4/11/2014
* •. j x lanation Justification Re uired: additional work erformed taken from critical path
TOTAL WORKING DAYS* 307
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: I tqC "! Date: L
hil cConnell
Construction Supervisor: Date: 'J
Construction Manager: Date:
Pau Ku e
2 REV. DATE: 4/01/10
i
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKED ' - ExT
Project Name: SE 266th Street Improvements Project No: 09-3012
Item No.: 9000 Date: 4/9/2014
Description of Work: Dig and prep for side sewer taps
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OF Rate AMOUNT
Dan foreman 8 63.D1 $ 504.08
Jason operator 8 60A6 $ 481.28
Rob plpelayer 8 48.96 $ 391.68
Rob pipelayer 8 48.96 $ 391.68
i
Jose laborer 8 48.1 $ 384.80
Tom operator 2 60.16 1 $ 120.32I,
SUBTOTAL-LABOR: $ 2,273.84
LABOR OVERHEAD&PROFIT @ 29% $ 659,41
LABORTOTAL $ 2,933.25
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
JD 135G 8 66.51 $ 532.08
f150 8g7G.20
.18 $ 153.44
JD 624 loader 2 $ 140.40
rental dump truck 4 .08 $ 224.32
SUBTOTAL-EQUIPMENT $ 1,050.24
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 220.55
EQUIPMENT TOTAL $ 1,270.79
MATERIALSIS ERVICESIRENTALS
MATERIALS I SERVICES Quantity Units Unit Price DOLLAR AMOUNT
5 -
$
$ - i
$
SUBTOTAL $ -
OVERHEAD&PROFIT@ 21% $
TOTAL $
Verification of Hours Worked: TOTAL: $ 4,204.04
12%MARKUP (for
prime when subcontract work) $ -
Contractors Representative Date SHEET TOTAL: $ 4,204.04
Owners Representative Dale
Comments
i
i
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKED fNT
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No.: 9000 Date: 4/11/2014
Description of Work: uncover, relay side sewer due to water main conflict
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHTTIME OVERTIME DOLLAR
. NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
foreman 0.5 63.01 $ 31.51
operator 0.5 60.16 $ 30.08
operator 0.5 60.16 $ 30.08
plpelayer 0.5 48.96 $ 24.48
plpelayer 0.5 48.96 S 24.48
SUBTOTAL-LABOR: $ 140.63
LABOR OVERHEAD&PROFIT @ 29% $ 40.78I
LABOR TOTAL $ 181.41
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
hitachi 200 0.51 87.01 $ 43.51
JD 624 loader 0.5 14.63 $ 7.32
f150 0.5 19.18 $ 9.59
f450 sere truck 0.5 29,46 $ 14.73
SUBTOTAL-EQUIPMENT $ 75.15
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 15.78
EQUIPMENT TOTAL $ 90.93
MATERIALSISERVIC ES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
5
S -
5 -
SUBTOTAL
OVERHEAD&PROFIT @ 21% $ -
TOTAL $
Verification of Hours Worked: TOTAL: $ 272.34
12%MARKUP (for
prime when subcontract work) $ -
Contractors Representative Date SHEET TOTAL: $ 272.34
Owners Representative Date
Comments