CHANGE ORDER NO. #18
NAME OF CONTRACTOR: Goodfellow Brothers, Inc ("Contractor")
CONTRACT NAME & PROJECT NUMBER: SE 256th Street Improvements
ORIGINAL CONTRACT DATE: June 6, 2013
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect, For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Work to install new storm system, work necessary to complete project.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $5,208,988.60
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $52,361.55
(incl. applicable WSST)
Current Contract Amount $5,261,350.15
(incl. Previous Change Orders)
Current Change Order $3,783.97
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum $5,265,134.12
I
CHANGE ORDER - 1 OF 3
a I
Original Time for Completion 300working days
(insert date)
Revised Time for Completion under 304 working days
prior Change Orders
(insert date)
Days Required (f) for this Change 0 calendar days
Order
i
Revised Time for Completion 304 working days
(insert date)
I
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration; onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
�L
CONTRACTOR: CITYENT:
By: r ?i*-} a l%rl� By;
7 (61gnature) ( gnature)
Print Name: i }r.� Al�.,,�,., J Print Name: Timothy ] LaPorte, P.E.
Its �o4`er Its Public Works Director
(title) jtle
DATE: � ,I i� DATE: S� Z//
CHANGE ORDER - 2 OF 3 j
I
® T FILE NO: 200.2
KEN
CHANGE ORDER WORKSHEET NO. IS
Construction Management Division - Public Works
Project: SE 256In Street Improvements Project No.: 09-3012C
Project Engineer: Mark Madfai Fed-Aid No,: N/A
Owners Rep: Phil McConnell Contractor: . Goodfellow Brothers
Date: Various
I. PROPOSED CHANGE
Work to install new storm system
I
II. REASON AND BACKGROUND FOR CHANGE
Work necessary to complete project
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ® Not Applicable
Change Order No. _ ( FOR ACCOUNTING USE ONLY
Sch. No Item Description Total Est, Qty this Unit Unit Price Total Estimated Cost of 'I
Qty PE Item
Work to install new storm 1 1 LS $3,783.97 $3,783.97
s stem
❑ independent REQ Estimate Attached I-❑ a a titer date uT M ONLY
-nPayment
wor to be made �® i PAY THIS PAY ESTIMATE
�--- -_p_-- - - —--------
❑ Material Submittals Required - cc: Construction Coordinator l New sub Regrd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Sch. No B.I. No, Item Description Qty Unit Unit Price Cost of Item
i
I
❑ I Independent Estimate Attached - REQUIRED ❑
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description Qty Unit Unit Price C
__ t of Item_ ' _.. . ._. .-- - --Ih --' - -- -- - os a
i
❑ I Independent Estimate Attached - REQUIRED ❑
1 REV. DATE: 4/01/10
KE T(T• FILE NO: 200.2
TOTAL ESTIMATED COST OF CHANGE ORDER * $3,783.97
*Total of the cost of Item Columns
THIS PAY ESTIMATE 3783.97
IV. WORKING DAYS
Ori ina�l Contract�__ Due This Change Order* Q� I Previous Total —� -- ---
g 300 t 304 - --
_
* Ex lanat!on Justification Re uired: delay time doesn't warrant additional day
TOTAL WORKING DAYS* 304
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By:
GLti>w Date: f
411 McConnell
Construction Supervisor: / Date:Construction Manager: G Date: +
Pa I Ku hne
I
2 REV. DATE:4/01/1D
i I
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKED ENT
Project Name: SE 256th Street Improvements Project No: 09.3012
Item No.: 2000 Date: 3/26/2014
Description of Work: Incorrect locates created extra and unneccesary ditching
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
foreman 2 83.01 $ 126.02 '..
operator 2 60.16 $ 120.32
pipelayer 2 48.96 $ 97.92
$
SUBTOTAL-LABOR: $ 344.26
LABOR OVERHEAD&PROFIT @ 29% $ 99.84
LABORTOTAL $ 444.10
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT ',..
JD 50D mini excavator 2 26.10 $ 52.20
F150 pickup 2 19.18 $ 38.38
$
SUBTOTAL-EQUIPMENT $ 90.56
EQUIPMENT OVERHEAD&PROFIT @ 21% $ %02
EQUIPMENT TOTAL $ 109.68 ,
MATERIALS/SERVIC ESIRENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
SUBTOTAL $
OVERHEAD&PROFIT @ 21% $ -
TOTAL $ -
Verification of Hours Worked: TOTAL: $ 553.68
12%MARKUP (for
prime when subcontract work) $ -
Contractors Representative Date SHEET TOTAL: $ 553.68
Owners Representative Dale
Comments
FA Sheet No,:
DAILY REPORT OF
FORCE ACCOUNT WORKED '-E�,T
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 3/27/2014
Description of Work: watermain in conflict with storm installation, standby during field redesign
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
foreman 1.5 63.01 $ 94.52
operator 1.5 60.16 $ 90.24
pipelayer 1.5 49,96 $ 74.94 j
laborer 1.5 48.1 $ 72.15
$
SUBTOTAL-LABOR: $ 331.85
LABOR OVERHEAD&PROFIT @ 29% $ 96.24 li
LABOR TOTAL $ 428.09i,
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
JD 135 excavator 1.5 16.73 $ 25.10
F 150 pickup 1.5 1.77 $ 2.66
f 550 sew truck 1.5 3.68 $ 5.52
$
$
SUBTOTAL-EQUIPMENT $ 33.28
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 6.99
EQUIPMENT TOTAL $ 40.27
MATERIALS/SERVICES/RENTALS
MATERIALS I SERVICES Quantity Units Unit Price DOLLAR AMOUNT
SUBTOTAL $ -
OVERHEAD&PROFIT @ 21% S -
TOTAL $ -
Verification of Hours Worked: TOTAL: $ 468.36
12%MARKUP (for
prime when subcontract work) $ -
CDntraclor's Representative Date SHEET TOTAL: $ 468.36
Owner's Representative Date
Comments
I
i
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKED frrr
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 3/2 812 0 1 4
Description of Work: Install 6 inch yard drain to catch basin
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
foreman 4 63.01 $ 252.04
laborer 4 48.1 $ 192.40
operator 2 60.16 $ 120.32
pipelayer 2 48.96 $ 97.92
SUBTOTAL-LABOR: $ 662.68
LABOR OVERHEAD&PROFIT @ 29% $ 192.18
LABOR TOTAL $ 854.86
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
F150 4 19.18 $ 76.72
JD 50mini excavator 2 26.10 $ 52.20
S -
SUBTOTAL-EQUIPMENT $ 128.92
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 27.07
EQUIPMENT TOTAL $ 155.99
MATERIALSIS ERVICES/RENTALS
MATERIALS!SERVICES Quantity Units I Unit Price DOLLAR AMOUNT
6 Inch pvc pipe 75 If $ 2,08 $ 156.00
6 inch pvc 45 band 3 ea $ 14.65 $ 43.95
$
$
SUBTOTAL $ 199.95
OVERHEAD&PROFIT @ 21% $ 41.99
TOTAL $ 241.94
Verification of Hours Worked: TOTAL: $ 1,252.79
12%MARKUP (for
prime when subcontract work) $ -
Contractors Representative Date SHEET TOTAL: $ 1,252.79
Owners Representative Date
Comments
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKED '-�K E;1T
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 3/31/2014
Description of Work: relocate cb 25 remove pipe and reset cb to accomdate revision
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Dan foreman 2 63.01 $ 126.02
Jason operator 2 60A6 $ 120.32
Tom operator 0.5 60.16 $ 30.08
Rob pipelayer 2 48.96 $ 97.92
Jose iaborer 1.5 48.1 $ 72A5
SUBTOTAL-LABOR: $ 446.49
LABOR OVERHEAD&PROFIT @ 29% $ 129.48
LABORTOTAL $ 575.97
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
JD 50 mini excavator 2 26.10 $ 52.20
JD 624K loader 0.5 70.20 $ 35.10
F550 sere truck 2 29.46 $ 58.92
$ - I
SUBTOTAL-EQUIPMENT $ 146.22 III
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 30.71
EQUIPMENT TOTAL $ 176.93
MATERIALSIS ERVICESIRENTALS
MATERIALS 1 SERVICES Quantity Units Unit Price DOLLAR AMOUNT
$ _ I
SUBTOTAL $ -
OVERHEAD&PROFIT @ 21% $ -
TOTAL $
Verification of Hours Worked: TOTAL: $ 752.90
12%MARKUP (for
prime when subcontract work) $ -
contractor's Representative Date SHEET TOTAL: $ 752.90
owner's Representallve Dale
Comments
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT- WORKED \17�K F_NT
Project Name: SE 266th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 4/8/2014
Description of Work: found unknown storm pipe, added cb and tied in found pipe
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
foreman 2 6301 $ 126.02
operator 0.5 60.16 $ 30.08
operator 0.5 60.16 $ 30,08
pipelayer 0.5 48.96 $ 24A8
pipelayer 0.5 48.96 $ 24.48
SUBTOTAL-LABOR: $ 235.14
LABOR OVERHEAD&PROFIT @ 29% $ 68.19
LABORTOTAL $ 303,33
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs I Standby Rate AMOUNT
F150 pickup 2 19.18 $ 38.36
JD 135 excavator 0.5 66.51 $ 33.26
JD 624 loader 0.5 70.20 $ 35.10
F550 sery truck 0.6 29.46 $ 14.73
SUBTOTAL-EQUIPMENT $ 121.45
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 25.50
EQUIPMENT TOTAL $ 146.96
MATERIALS/SERVIC ESIRE NTALS
MATERIALS!SERVICES Quantity Units I Unit Price DOLLAR AMOUNT
i
$ _ I
SUBTOTAL $ -
OVERHEAD&PROFIT @ 21% $ -
TOTAL $
Verification of Hours Worked: TOTAL: $ 450.28
12%MARKUP (for
prime when subcontract work) $ -
Contractors Representative Date SHEETTOTAL: $ 460.28
Owners Representative Date
Comments
I
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKEDNT
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 4/11/2014
Description of Work: adjust storm cb to avoid existing storm manhole
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs I Hourly Rate Hrs OT Rate AMOUNT
foreman 0.5 63.01 $ 31.51
operator E0.5 j48.96
6 $ 30.08
operator 0.5 6 � $ 30.06 i
pipelayer 0.5 $ 24.48
pipelayer 0.5 96 $ 24.48
SUBTOTAL-LABOR: $ 140.63
LABOR OVERHEAD&PROFIT @ 29% $ 40.78
LABORTOTAL $ 181.41
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
hatachi 20OLC 0.5 87.01 $ 43.51
JD 624 loader 0.5 70.20 $ 35.10
F 150 pickup 0.5 19A8 $ 9.59
F550 sere truck 0.5 29A6 $ 14.73
SUBTOTAL-EQUIPMENT $ 102.93
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 21.62
EQUIPMENT TOTAL $ 124.55
MATE RIALS/SE RVI CESIRENTALS
MATERIALS l SERVICES Quantity Units Unit Price DOLLAR AMOUNT
$
$ - I
SUBTOTAL $ -
OVERHEAD&PROFIT @ 21% $ -
TOTAL $ -
Verification of Hours Worked: TOTAL: $ 305.96
12%MARKUP (for
prime when subcontract work) $ -
I
Contractors Representative Date SHEETTOTAL: $ 305.96
Owners Representative Date
Comments