HomeMy WebLinkAboutPW13-103 - Change Order - #17 - Goodfellow Bros., Inc. - SE 256th St Improvements - 05/30/2014 i I
KENT
WP9 MINOTOM
CHANGE ORDER NO. #17
NAME OF CONTRACTOR: Goodfellow Brothers. Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER: SE 256th Street Improvements
ORIGINAL CONTRACT DATE: June 6, 2013
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
- _ .� -
Relocate Ce�^" ntuiyLink c ble, work necessary to complete project. .T�
2. The contract amount nd time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $5,208,988.60
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $51,644.26J
(incl, applicable WSST)
Current Contract Amount $5,260,632.86
(incl. Previous Change Orders)
Current Change Order $717.29
I
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum $5,261,350.15
CHANGE ORDER - 1 OF 3
I I II
Original Time for Completion 300 working days
(insert date)
Revised Time for Completion under 304 working days
prior Change Orders
(insert date)
Days Required (f) for this Change 0 calendar days
Order
Revised Time for Completion 304worki❑g days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warrant P 9 y provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
I
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
I
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below
CONTRACTOR: CITY OF NT:
By: By: L '—O
—T—(si ature) ( nature)
Print Name: A r,t,-- JPk4 ,, Print Name: Timothy 3 LaPorte, P.E.
Its Its Public Works Director
aw
DATE: ��sn/� DATE:_J� 2 L�
CHANGE ORDER - 2 OF 3
FILE NO: 200.2
KE�, T
w. ,wa.aw
CHANGE ORDER WORKSHEET NO. 17
Construction Management Division - Public Works
Project: SE 256tn Street Improvements Project No.: 09-3012C
Project Engineer: Mark Madfai Fed-Aid No.: N/A
Owners Rep: Phil McConnell Contractor: Goodfellow Brothers
Date: Various
I
I. PROPOSED CHANGE
I
Relocate Centur Link cable
II. REASON AND BACKGROUND FOR CHANGE
i
i
Work necessary to complete project
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. Item Description ! Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty f PE (' Item
Relocate Century Ink cable_ —__1 —__ 1 $717.29_ $717,29 _
I I
Independent Estimate Attached CREATE PAY ITEM ONLY- Payment to be made ® �PAY THIS PAY ESTIMATE
_ __ - REQUIRED __ at a later-date upon completion of work
Material Submittals Required - CC: Construction Coordinator New Sub Reqrd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Soh. No, j B.1.No. I Item Description Qty Unit Unit Price i Cost of Item
1 Independent Estimate Attached - REQUIRED
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Sch_-No. B.L No. _ Item Description _ _—Qty Unit Unit Price- -Cost of item_
Independent Estimate Attached - REQUIRED I ❑
1 REV. DATE: 4/01/10
• T FILE NO: 200.2
KEN
TOTAL ESTIMATED COST OF CHANGE ORDER * $717.29
*Total of the Cost of Item columns '.
THIS PAY ESTIMATE $717.29
IV. WORKING DAYS
Original Contract 300 Due This Change Order* p Previous Total
— -----� 1=--- ----L304 —--- — —
DATE: ---`__...__ DATE:
* Explanation Justification Re wired: dela time doesn't warrant additional day
TOTAL WORKING DAYS* 304
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: C 'Vim 0 Date:
Fy�l McCo Hell
Construction Supervisor: /(�/�,2��1 -/ Date:
Construction Manager: P I! - Date:
Paul Kuehne�
2 REV. DATE: 4/01/10
I
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKED ffrT
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 4/15/2014
Description of Work: CenturyLink cable conflict at cb 3....strip and raise cable to avoid storm pipe
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs I Hourly Rate His OT Rate AMOUNT
foreman 1 83.01 $ 63.01
operator 0.5 60,16 $ 30.08
pipelayer 0.5 48.96 $ 24A8
laborer 0.5 48.1 $ 24.05
5 -
SUBTOTAL-LABOR: $ 141.62
LABOR OVERHEAD&PROFIT @ 29% $ 41.07
LABOR TOTAL $ 182.69
EQUIPMENT .
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
F150 0.5 1918. $ 9.59 -
JD 50 0.5 26.10 $ 13.05
CAT 420 backhoe 0.5 42.35 $ 21.18
$
SUBTOTAL-EQUIPMENT $ 43.82
EQUIPMENT OVERHEAD&PROFIT @ 21°/ $ 9.20
EQUIPMENT TOTAL $ 53.02
MATE RIALS/S ERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
$
SUBTOTAL. $ -
OVERHEAD&PROFIT @ 21% $ -
TOTAL $
Verification of Hours Worked: TOTAL: $ 235.71
12%MARKUP (for
prime when subcontract work) $ -
Contractors Representative Date SHEET TOTAL: $ 235.71
Owners Representative Date
Comments
FA Sheet No.:
DAILY REPORT OF �
FORCE ACCOUNT WORKED T
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 4/1/2014
Description of Work: CenturyLink cable in conflict with catch basin location...excavate cable and
relocate to allow catch basin to be set
Work by Subcontractor?:
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Dan foreman 1.5 63.01 $ 94.52
Jason operator 1.5 60.16 $ 90.24
Rob pipelayer 1.5 48.96 $ 73.44
tom operator 0.5 60.16 $ 30.08
SUBTOTAL-LABOR: $ 288.28
LABOR OVERHEAD&PROFIT @ 29% $ 83.60
LABOR TOTAL $ 371.88
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs I Hourly Rate Hrs Standby Rate AMOUNT
JD 50 excavator 1.5 26.10 $ 39,15
F550 Service truck 1.5 29.46 - $ 44.19
624K loader 0.5 14.63 $ 7.32
SUBTOTAL-EQUIPMENT $ 90,66
EQUIPMENT OVERHEAD&PROFIT @ 21°/ $ 19.04
EQUIPMENT TOTAL $ 109.70
MATERIALS/S ERVICESIRE NTALS
MATERIALS 1 SERVICES Quantity Units Unit Price DOLLAR AMOUNT
$
$
$
SUBTOTAL $ -
OVERHEAD&PROFIT @ 21°/ $ -
TOTAL $ -
Verification of Hours Worked: TOTAL: $ 481.58
12%MARKUP (for
prime when subcontract work) $ -
Contractors Representative Dale SHEET TOTAL: $ 491.58
Ovrners Representative Date
Comments