HomeMy WebLinkAboutCAG2019-220 - Change Order - #17 - Scarsella Bros, Inc - 228th St UPRR Grade Separation Bridge & Roadway - 11/18/2020Agreement Routing Form KENT For Approvals, Signatures and Records Management This form combines & replaces the Request for Mayor's Signature and Contract Cover Sheet forms. (Print on pink or cheny colored paper)WasHtNoroN E oLo.c Originator: C. Frame Department: PW Engineering Date Sent: 1t22t2021 Date Required: N/A Authorized to Sign: EI Director or Designee EJ Mayor Date of Council Approval: N/A Budget Account Number R20067.641 1 0.1 20 Budget? ElYes ENo Grant? EYes E No Type: Federal co IG ELo5 E Ptro EooLttl Vendor Name: Scarsella Bros., lnc Category: Contract Vendor Number: 34547 Sub-Category: Change Order #17 Project Name: S. 228th St. Union Pacific Railroad Grade Separation Bridge and Roadway Phase 5 Proiect Details:Create bid item to provide compensation for extra work to install sewer drop at existing KC Metro manhole. Agreement Amount: $9,293.83 Start Date: N/A Basis for Selection of Contractor: $id Termination Date: N/A Local Business? EYes E No* *lf meets requirements per KCC 3.70.100, please complete "Vendor Purchase-Local Exceptions" form on Cftyspace. Notice required prior to disclosureT EYes E No Contract Number: cpa'19-220 olE fl J\o as o=E8t!c .9UI Date Received by city Attorney:Comments: Date Routed to the Mayor's Office Date Routed to the City Clerk's Office: ad(W2217l_l_20 Visit Documents.KentwA.gov to obtain copies of all agreements '$ ....-~ ~KENT WASHINOTON CHANGE ORDER NO. #17 NAME OF CONTRACTOR: S~rsella Bros, Inc. ("Contractor") CONTRACT NAME & PROJECT NUMBER:S. 228th St. Union Pacific Railroad Grade Separation Bridge and~Roadway Phase 5 (19-3022) ORIGINAL CONTRACT DATE: April 19, 2019 This Change Order amends the above-referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: 1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: This Change makes the following revisions to the Contract Documents and provides compensation for the added work: Create a bid item to provide compensation for extra work required to install the sewer drop at existing KC Metro manhole F57 due to an existing steel shoring box found while excavating. 2. The contract amount and time for performance provisions of Section II "Time of Completion," and Section III, "Compensation," are hereby modified as follows: Original Contract Sum, $13,802,146.40 (including applicable alternates and WSST) Net Change by Previous Change Orders $324,230.66 (incl. applicable WSST) Current Contract Amount $14,126,377.06 (incl. Previous Change Orders) Current Change Order $8,448.94 Applicable WSST Tax on this Change $844.90 Order Revised Contract Sum $14,135,670.90 CHANGE ORDER - 1 OF 3 \ Original Time for Completion (insert date) 240 rvorking days Revised Time for Completion under prior Change Orders (insert date) 240 rvorking days Days Required (*) for this Change Order 0 calendar days Revised Time for Completion (insert date) 240 working days In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below, Also, pursuant to the above-referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind oi nature arising from or connected with any work either covered or affected by this Change brder, including,without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve theContractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby ratiiied andaffirmed, and the terms of theAgreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written below. CONTRACTOR: By >,-a (signature) Print Na me i,/z,t47/'/4fa./ S1AN Ett A (title) DATE: // OF KENT: F 'fu ts;^Y (signature) Print Name: Chad Bieren, P.E. Its Inte m Public Works D irector (tiue) f I -18 -262rtDATE t9 CHANGE ORDER - 2 OF 3 ATTEST: Kent Clerk APPROVED AS TO FORM: (applfcable if Mayor's signature required) Kent Law Department P.E,Un lhis field, you may enter the eled.onlc Rlepath where the conlrad has been savedl CHANGE ORDER . 3 OF 3 KENT FILE NO: 2OO.2 CHANGE ORDER WORKSHEET NO. OT7 Construction Management Division - Public Works Project S. 228th St Union Pacific Railroad : Grade Separation Phase 5 Project Engineer: Cameron Bloomer, PE Owners Rep: KBA, Inc Project No.: 07-3022 Fed-Aid No.: Contractor: HLP-FMSTB-L2L6 (00s) Scarsella Bros, Inc. Date: LLl6/2020 I. PROPOSED CHANGE This Change makes the following revisions to the Contract Documents and provides compensation for added work: Create a bid item in Schedule 13 (Sewer) to provide compensation for extra work required to install the sewer drop at existing KC Metro Manhole F57. II. REASON AND BACKGROUND FOR CHANGE While excavating for the sewer drop, an existing steel shoring box was encountered and in conflict with the work. Utilities had since been installed over and near the shoring box, preventing easy removal and forcing the contractor to work around it. This shoring box created additional work to excavate, shore, and install the drop, and a section of the box was cut to allow the cross to be installed. Time and material efforts were tracked for force account reimbursement. III. METHOD OF PAYMENT NEW PAY |TEM(S)Not Applicable ChanSe Order No.FOR ACCOUNT'NG USE ONI.Y Sch. No.ltem Description Total Est. ow Qty this PE Unit Unit Price Total Estimated Cost of Item 13 Sewer Droo Extra Work 1 1 LS $8.448.94 58.448.94 Independent Estimate Attached - REOUIRED CREATE PAY ITEM ONLY - Payment to be made at a later date upon comoletion of work PAY THIS PAY ESTIMATE Material Submiftals Reouired - CC: Construction Coordinator New Sub Reqrd?No DELETE EXISTING PAY ITEM(S) per 1-09.5 Not Applicable 1, Change Order No,FOR ACCOUNT'NG USE ONLY Sch. No.B.l. No.Item Description Qty Unit Unit Price Cost of ltem $$ $$ Independent Estimate Attached - REQUIRED REV. DATE: 3/15/19 FILE NOr 2OO.2T<ENT Change Order No.FOR ACCOUNI'A'G USE O'VI-Y Sch. No.B.l. No.Item Description atv Unit Unit Price Cost of ltem LF $$ Independent Estimate Attached - REQUIRED |NGREASE/DECREASE TO EX|ST|NG pAy tTE Not Applicable TOTAL ESTIMATED COST OF CHANGE ORDER X THIS PAY ESTIMATE IV. WORKING DAYS xTotal of the Cost of Item Columns 44.94 o Original Contract 240 Due This Change Order*o Previous Total 240 DATE DATE:*Exolanation/Justification Required: This Change Order does not impact the critical path, and no change to the working days is being made. TOTAL WORKING DAYS*24(J *This Change Order + Previous Total All work, materials and measurements to be in accordance with the Standard Specifications and Contract Special Provisions for the type of work described. Prepared By:Cameron Bloomer Date: LLl6l2O2O /onttuction Supervisor: {/"P Date:u /a,/za Date rh/zaConstruction Manager: 2 REV. DATE:3/L5/19 IT'T DAILY REPORT OF FORCE ACCOUNT WORKED D l CONTRACTOR Scarsella Bros. lnc DATE 8t31t2020 SUBCONTRACTOR PAY EST# Prcject No.:07-3022 ITEM # Federal Aid No.:wsDoT HLP-1216(0061 DESCRIPTION OF WORK PERFORMED:Vac down and around old shoring FA# Contractor FA# 36 LABOR WORKER'S NAME WORKER'S OCCUPATION REG HRS REG RATE OT HRS OT RATE AMOUNT Operator Foreman 4.00 $ 80.56 1.0 $ 107.94 $430.1 8 Andv Peterson (9/2020)Ooerator Blade. Motor oatrol orade 8.00 $ 75.60 1.0 $ 100.55 $705.35 'ipelaver 8.00 $ 59.18 1.0 $ E0.93 $554.37 Jon Pipelayer 8.00 $ 59.18 1.0 $ 80.93 $554.37 Clint Estes (9/2020)Operator Loader under 6 CY E.00 $ 74.95 1.0 $ 99.58 $699.1 8 LAEOR SUBTOTAL $2,943.45 29% OVERHEAD AND PROFIT, BONDING.INSURANCE AND TAX $853.60 lrorAL s3,797ffi EQUIPMENT TYPE EQUIPMENT SIZE tEG HRS REG RATE JTDBY HRS JTDBY RATI AMOUNT 02-299 Ford F25O PIU (9l2O2O)0 5 s 24.32 $121.60 17-275 Deete 50G Excavator (9/202(0 8 $ 26.81 $$214.48 03-1 31 Ford rool f tuck (7 12020)0 8 $ 26.88 $$215.04 EQUIPMENT SUBTOTAL $551.1 2 21 7O OVERHEAD AND PROFIT, BONDING , INSURANCE AND TAX $1 15.74 VENDOR & INVOICE #MATERIAL SUB TOTAI.tA AMOUNT VPC, lnv# 58458 $1,642.50 $1,842.50 $0.0c $0.00 $0.0c $0.00 MATERIALS SUBTOTAL INCLUDING TAX $1,842.50 21 7O OVERHEAD AND PROFIT, BONDING, INSURANCE AND TAX $386.93 TOTAL MA $2,229.43 VENDOR & INVOICE #WORK DESCRIPTION AMOUNT $0.0c V SUBTOT $0.0c TAX $0.00 SU BCONTRACTOR MARKU P 1 2OlO $0.00 PRIME Subtotal of Labor, Equipment, & Material Work $6,693.34 SUBCONTRACTOR Subtotal of Labor, EquiDment. Material, & Subcontractor lnvoiced Work $0.00 Markups on work performed by Subcontractor: up to $25,000=1 2%, $25,000-$1 00,000 = 1 0% Greater than $1 00,000 = 7%Oo/o Subcontractor Mark-up $0.00 TOTAL COST $6.693.34 lf checked, this work is in dispute. By signing this form, parties are agreeing to the time and effort needed to accomplish the task. Entitlement to be determined at a later date. FomOaleTl202o SR0TlrtRs [Jc.RSELDAILY FORCE ACCOUNT / EXTRA WORK REPORTCONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:*?oP O. Box 68697seatfle, wA 98168-0697Otf,e: (253J872-7173Fax: {253) 395-1209,- l3ttt-2TS7__zrfNO.EQUIP€-lso J-{t*.kPc 5o(-z.so p/<E(IUIPMENTOWN orRENTAL?STDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYSTDBYOPERSTDBYOPEROPER IfSTDBYOPERle,A2ul .<7HOURSHOURLYRATE.D,/ 1r^ t et"LsCw;4f'r,o*/q4{{arn{,1vvf L'onc P*.|-eo/TREGo/TREGo/TREGo/TREGofiREGonREGotTREGo/TREGo/TREGo/TREGTABOR - Name, Classification5G31tI(ItIqtHOURS7o'73qq. <r-vt4.9s'{O,q 74i, lf97. t*'/oo,ss1<' loOI-OADEDHOURLY R.ATE- ba,so'*{tu,ryI$ ffi,c{ 3$L.l?\.4\$ Y77",{"1$ ioa,55s$$$$$eS$$$ 'f?,s7s <sq i,o$ trO "{3EXTENDEDAMOUNTStSsL.ae$ Se ,3i$ bo'l .tCdr-SUBTOTAL LABOR:(rf'UX:fi:nDii:,4*;i,:';,:-SJS.lSUBTOTAL EQUIPMENTt)tpc$UBCONTR^ACTORS$$MATERIALe$QTYSUBTOTAL MATERIALf){Ttr:, }[;:ALqnl, ",iT$?ax.75'? \*)-ilbgt/SUBTOTAL EQUIPMENT/,/?-*{a,?5"-:''/79,G&BROS., INC. REPRESENTATIVESUBTOTAL SUBCONTRACTORS;{- st- aoDATETOTAL THIS REPORT:% MARKUP MATERIALSUBTOTAL MATERIAL}!Lu MARKUP LABoRSUBTOTAL LABOR% MARKUP SUBCONTRACTORSSUBTOTAL SUBCONTRACTORSOWNTgCJ\ITRACiORTIVETEw% MARKUP EQUIPMENTioT.5l Voice: Fax: TftI q/r Ventilation Power Cleaning, lnc. 3914 Leary Way NW Seatfie. WA 98107 llrlv0lGE lnvoice Number: 58458 lnvoice Date: Oct 5, 2020 Page: 1 Duplicate I1i["Ei-*.'.t ft {ffi lrf_ffiErqEft ii i; # POTHOLE T6THAVES&S228THST KENT, WA Net 30 9t1t20 't1t4t20 206434-2750 206-634-2753 73c)a/fuioot 77o c/tro6.oot SCARSELI-A BROTHERS PO BOX 68597 SEATTLE, WA 98168.0697 scA001 03-Ron Christensen 73025 :Etrgpfit,ffqgfi* VPC Truck coMBo vAc TRK WOPEMTOR (PER HOUR) 8.5 HOURS 8/E1,'t1 HOURS 9/'l OPEMTOR OVERTIME PREMIUM PAY PER HOUR FOR HOURS OVER 8 PER DAY.,SHOURS 8/31.3 HOURS SI1 LOAD OF WATER FOR POTHOLING, 1 USED EACH DAY Sales Tax ioiirrnvoice Amount PaymentlCred it_Ap plie d TOTAL 1.00 20.00 3.50 2.04 215,00 30.00 40.00 4,300,00 105.00 80.00 4,485.00 448.50 4,933.50 {103t;50, ill.so l5.ooslzr e'oML( 4 oor W t\ d.so \t v. 2f els,orC = I8SX 0 tx 30. eo e O 21"' '7 5' t'l|SS,5o /qA lo, ?{ qlr p6a ChecklCredit Memo No: I DALY REPORT OF FORCE ACCOUNT WORKEDl{ =7A\ CONTRACTOR Scarsella Bros. lnc.DATE 9t1t2020 SUBCONTRACTOF PAY EST# Project No.:07-3022 ITEM #1355Fedsral Aid No.:wsDoT HLP-1216(006) DESCRIPTION OF WORK PERFORMED:Cut out existing old shoring to perform work on sewer drop FA# Contractol FA# 30 WORKER'S NAME WORKER'S OCCUPATION REG HRS REG RATE OT HRS OT RATE AMOUNT Rob operator Foreman 3.00 $ 80.56 $ 107.94 $241.68 Ty Williams (6/2020)Pioelaver 3.00 $ 59.18 $ 80.93 $177.s4 Pipelaver 3.00 $ 59.18 $ E0.93 $177.54 Andy Peterson (9/202C Operator Blade, Motor patrol grade 3.00 $ 75.60 $ 99.58 $226.80 Jav Ktiet (9l2o2o)Operator Foreman 3.00 $ 80,56 $ 107.94 $241.68 LABOR SUBTOTAL $1,065.24 IN E AND $308.92 ,374.ffi EQUIPMENT ryPE EQUIPMENT SIZE tEG HRT REG RATE STDBY HRS JTDBY RATI AMOUNT 03-122Fotd F450 Flatbed (7/2020)0 3 $ 27.07 $$81.21 03-131 Ford Tool Truck (7/2020)0 3 $ 26.E8 $$80.64 0 3 $ 24.32 $$72.96 0 3 $ 26.81 $$80.43 EQUIPMENT SUBTOTAL $315.24 21% OVERHEAD AND PROFIT, BONDING, INSURANCE AND TAX $66.20 VENDOR & INVOICE #MATERIAL SUB TOTAI.tAx AMOUNT $0.00 $0.00 $0.00 $0.00 $0.0c $0,00 MATERIALS SUBTOTAL INCLUDING TA}$o.oo 21% OVERHEAD AND PROFIT, BONDING, INSURANCE AND TAX $0.00 TOTAL MA INVOICED $0.00 VENDOR & INVOICE #WORK DESCRIPTION AMOUNT $0.00 $0.00 ACTOR INV UBTOTAL $0.00 TAX $0.00 PRIME Subtotal of Labor, Equioment. & Material Work $1,755.60 SUBCONTRACTOR Subtotal of Labor, Equipment, Material, & Subcontractor lnvoiced Work $0.00 Markups on work performed by Subcontractor: up to $25,000=1 2%, $25,000-$1 00,000 = 1 0% Greater than $1 00,000 = 7olo Oo/o Subcontractor Mark-up $0.00 TOTAL COST $1,755.60 lf checked, this wort is in dispute. By signing this form, parties are agreeing to the time and effort needed to accomplish the task. Entitlement to be determined at a later date. Fom Dale 7l2O2O BROTHEftS I}iC.ARSTLfl2.DAILY FORCE ACCOUNT / EXTRA WORK REPORTP O Box 68697seatfle, wA 98168-0697Ofn€: (253) 872-7173Fax: (253)395-1209CONTRACT NAME, NO.:OWNER / CONTRACTOR:DATE:COST CODE:DESCRIPTION OF WORK:DATEHOURLYRATESUBTOTAL EQUIPMENT: l..UNITCOSTSUBTOTAL MATERIALSUBTOTAL SUBCONTRACTORSEXTENDEDAMOUNTS!;,1:;':;;:.r1.!ii.l.. ..1 ,'1rl,Io4L>nt)7SUBTOTAL LABOR:SUBCONTRACTORSb$b$$$SUBTOTAL SUBCONTRACTORS:8f l' 2osCAR#LLA'Bn<F, rr.rc. REeRESENTATIvE% MARKUP SUBCONTMCTORS% I\4ARKUP LABOR:% IVARKUP EQUIPMENTSUBTOTAL MATERIAL:79I-) a"{,RA't ,frr-ar,r,A,,/'r fukrsattotLABOR - Name, Classificationo/TREGo/TREGo/TREGo/TREGo/TREGo/TREGo/TREGoftREGonREGaffREGjjj'4zHOURS7D. q{^1q r-n5q. tKqe. { FqD. <{^LOADEDHOURLY R,ATE5 lfit^€ " )11$$$$bb$ss$$$ Vvl l. (2>$$ ))L 7D$$ i-?7.5"$$117.5r$$ ?qr.ktEXTENDEDAMOUNTS2.zff'7-z7s3- t3tTt27NO.EQUIP{-z9o p./tcS0 sof -"/So ,t"o//*.Kft3j" 1..11h.rtE(IUIPMENTOwtl orRENTAL?STDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERSTDBYOPERi1't3HOURS1t..Yl2b' 7'21 a1,,. T{g/,>,MATERII,LQTYTOTAL THIS REPORT:% MARKUP MATFRIALSUBTOTAL EQUIPMENTSUBTOTAL LABOR: I /OATIl"IE?DATE?a -lL.';. EquipmentWatch www. equipm enlwalch.com All prices slrown in US dollars {{i) Adjustmentslor 17-275 in All Saved Models September 14.2OZQ Deere 50G Crawler ltrounled Compacl Excavalors Size Class: 4,1 - 5,0 MTons Weight: N/A Conliguration lor 50G Operating Weight Power Mode Published Rat6s Adiuslments Fegion ( Washington: e8%) ll4odel Year {2015: 99.0s%) Adjusted Hourly Ownership Cosl {100%) Hourly Operating Cost (100%) Tolal: Non-Aclive Use Rates Slandby Rate ldling Rate Monlhly usD $2,790.00 fusD $55.80) {usD $24.e8} 5.28 mt Diesel Operator Protection Daily usD $195,00 (usD 63.$0.58) {usD s0.26) usD $189.35 uso $28.16 Ope.atlng Cosls Hourly uso $1 1.42 usD $11.42 FHWA Flale" Hourly usD s27.27 usD $26.81 Hou rly usD $s.70 IJSD $18.92 Blue Book Rales " FHWA Rate is equal to the monthly ownership cost divided by 176 plus tho hourly estimated ownership Costs Weekly usD $780.00 {usD $1s.60} (usD $6.98) usD $2,709.22 usD s757 a Rate Element Allocation Elemenl Depreciali0n {ownorship) 0verhaul {ownorship) CFC {ownership) lDdirecl lovrrership) Fuel {operalinqi @ USD 2.40 a Percantage 45% 37% 6% 12% Value USD $1,255.50/.no USD $ 1,032.30hr0 USD $ 1 67.40/rta IJSD $334.B0lrno USD $3.531hr Hevised Dale: znd halt 2OZA These are lhe rnosl accllrate rales lorlh€ selecteiJ Revision Dale(s). However. due lo more frequenl online updales, thase rales ntay nol rnalch Flenlal Rale Blue Book Print. Visil lhe Cosl Becovery Prodrcl Guide cn our Help page lonnore inlormalion" The equipment represented in this report has Lreen exclusively prepared for NICK SCARSELLA {Nick@scarsellabros.com) All rnalerial herein Q20A3-2t120 ln,orma All riQnts reseryed