HomeMy WebLinkAboutCAG2020-239 - Change Order - #2 - SCI Infrastructure, LLC -Reith Road Main Improvements - 12/23/2020December 16, 2020
KENT
CHANGE ORDER NO. # 2
NAME OF CONTRACTOR:
CONTRACT NAME & PROJECT NUMBER:
ORIGINAL CONTRACT DATE:
SCI Infrastructure, LLC ("Contractor")
Reith Road Watermain Improvements
July 23, 2020
This Change Order amends the above -referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
The intercepting and transferring of an existing commercial service on
to the newly underground PSE system.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum,
$615,188.75
(including applicable alternates and
WSST)
Net Change by Previous Change Orders
$68,912.86
(incl. applicable WSST)
Current Contract Amount
$684,101.61
(incl. Previous Change Orders)
Current Change Order
$3,111.75
Applicable WSST Tax on this Change
Order
$311.20
Revised Contract Sum
$687,524.56
CHANGE ORDER - 1 OF 3
12/23/2020
ATTEST:
-k�;U I�R4
Kent City Clerk
IIn Ih1s ne!d, y0e may enter the elecerann: IYepalh where the eonhact has 0aen saved:
CHANGE ORDER = 3 OF 3
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
a
KENT
FILE NO: 200.2
CHANGE ORDER WORKSHEET NO. 2
Construction En ineerin Division — Public Works _
Project: Reith Rd Watermain Project No.: 19-3005
Improvements
Project Engineer: Derek Hawkes Fed -Aid NO.: N/A
Capital Projects Phil McConnell Contractor: SCI Infrastructure
Manager:
Date: Various
I. PROPOSED CHANGE
The intercepting of and transferring of an existing commercial service on to the newly
underQrounded PSE System
II. REASON AND BACKGROUND FOR CHANGE
Additional work related to the undergrounding PSE overhead system and associated work; PSE
Schedule 74 trench necessary for the power undergrounding related to the West Hill Reservoir
Praject - Bill to project # 19-3027
III. METHOD OF PAYMENT
NEW PAY ITEM 5 Not Applicable
Change Order No. ! - FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total City this Unit Unit Price Total Estimated Coat
Est, Qty PE Item
1 Undergrounding of PSE power 1 1 LS $3,111.75 $3,111.75
lines
Independent Estimate Attached �- Payment to be made PAY THIS PAY ESTIMATE
- REQUIRED at a later date upon completion of work
Material Submittals Reg New Sub Reqrd? No
UtLt I t t Alb I INU PAY I I EM(S) per 1-09.5N Not Ap2licable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description City Unit Unit Price Cost of Item
Independent Estimate Attached - REQUIRED _L— —
INCREASE/DECREASE TO EXISTING PAY ITEM(S) [A Not
Change Order No.
Sch. No. T�8,1. No.
3/27/18
Item Descriptlon
FOR ACCOUNTING USE ONLY
oty Unit Unit Price Cast of Item_
1 REV. DATE;
FILE NO: 200.2
Independent Estimate Attached - REQUIRED
TOTAL ESTIMATED COST OF CHANGE ORDER* 3 111.75
*Total of the Cost of Item Columns
THIS PAY ESTIMATE 3. 111.75
IV. WORKING DAYS
Original Contract 45 Due This Change Order* 2 Previous Total 55
DATE: DATE:
* i • Wt)rk added was outside the original scope of work
TOTAL WORKING DAYS* [, 57
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Capital Projects Manager: Phil MDate: ___h �G
cConne
Construction Engineering ¢ Date:
Supervisor: 1 �+� - /� e
Paul Ifuehne
J . r�� � y
Construction Manager: Date:
Eric Connor
2 REV, DATE:
3/27/18
11/1912020, 2:30 PM
PROJECT: Reith Road (OH to Underground night work)
REVISION: Power Connection frorn Fiandhr>1e Vault to existing business.
DESCRIPTION:
Connect existing power to new handhole vault. This work has to take place at night due to
business it will impact while shut off.
Connect Existing power to new handhole vault $ 3,035.85
$
$
Total Cost: $ 3,035.85
Bond & Insurance $ 75.90
TOTAL COR: $ 3,111.75
R PPRO VED
By Phil McConnell at 3:02 pm, Nov 19, 2020
S:IJOBS11200 Job Folder Set Up105 Extra WorkIPRICING - NEW TEMPLATE Public Works
I Labor:
Rate/MH No.
Hours / Day Days Subtotal:
Foreman
87.97
1
8.00
1.00
703.76
Operator
83.14
1
8.00
-
Grade Engineer (0)
83.14
1
8.00
-
Laborer
60.95
1
8.00
Grade Checker W
62.69
1
8.00
-
Pipelayer
62.06
1
8.00
-
Flagger
51.64
1
8.00
Teamster
73.74
1
8.00
-
Subtotal Labor: S 70.3.76
1B Equipment:
D 61 Komatsu Dozer
Hamm Roller
Dump Truck
50 Mini Excavator
140 H Blade
240 Excavator
950 Loader
138 Excavator
Rate/Fir No.
110.69 1
50.55 1
79.79 1
2S.S8 1
76,26 1
106.74 1
59.64 1
71.39 1
Hours / Day
8.00
8.00
8.00
8.00
8.00
8.00
8.00
8.00
Days
Subtotal:
1C Subcontractors quantity
G&G, Inc. I
I
1 D Materials
UM Cost/Unit
LS 1,900.00
LS
LS
Quantity UM Cost/Unit
Subtotal Equipment: $
Subtotal:
1,900.00
Subtotal Subcontractor
Subtotal:
1,900.00
Subtotal Materials:
-
Subtotal Items 1A-11)
S Z603,76
Mark -Up on Labor at 29%:
.f 204.09
Mark- Up on Equipment at 21%:
S -
Mark --Up on Subcontractors at 1 2%:
S 228.00
Mark -Up on Materials at 21%:
S -
: Phone (425) 432-1325
Fox 425) 432-6155
��tI�:�.
NOVEMBER 181-H, 2020
S C I INFRASTRUCTURE LLC
2821 S. 154ST
SEATTLE, WA 98188
RE; REITH ROAD WATER MAIN
CHANGE ORDER REQUEST ON PSE
Gentlemen;
The price to work 1 night shift with a crew of 2 and the 2 1/2" conduit
will be $1,900.00 lump sum. The breakdown is below:
Labor $1,520.00
Material 280.00
Equipment 100.00_
$1, 900.00
Sincerely
81.,j5"3£;7 f" ;v as �
'Eli
KENT
CHANGE ORDER NO. # 2
NAME OF CONTRACTOR:
CONTRACT NAME & PROJECT NUMBER:
ORIGINAL CONTRACT DATE:
SCI Infrastructure, LLC ("Contractor")
Reith Road Watermain Improvements
July 23, 2020
This Change Order amends the above -referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
The intercepting and transferring of an existing commercial service on
to the newly underground PSE system.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum,
$615,188.75
(including applicable alternates and
WSST)
Net Change by Previous Change Orders
$68,912.86
(incl. applicable WSST)
Current Contract Amount
$684,101.61
(incl. Previous Change Orders)
Current Change Order
$3,111.75
Applicable WSST Tax on this Change
Order
$311.20
Revised Contract Sum
$687,524.56
CHANGE ORDER - 1 OF 3
Original Time for Completion 45 working days
(insert date)
Revised Time for Completion under 10 working clays
prior Change Orders
(insert date)
Days Required (f) for this Change Order 2 calendar days
Revised Time for Completion 57 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the I<ent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above -referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order', are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR:
By:
DATE: I I - 01 '- 2O
CHANGE ORDER - 2 OF 3
RE, LLC I CITY OF KENT;
By:--- - —
(signature)
COAL®VD Print Name: Dana Ralph
04 Its Mayor
(title)
DATE:
ATTEST:
Kent City Clerk
iln this held, you may enter the electronic wepalh where the contract has been saved"
CHANGE ORDER - 3 OF 3
APPROVED AS TO FOR
(applicable if Mayors signature re,
owk%ri,I
Kent Law Department
KENT
FILE NO: 200.2
CHANGE ORDER WORKSHEET NO. 2
Construction Engineering Division — Public Works
Project: Reith Rd Watermain Project No.: 19-3005
Improvements
Project Engineer: Derek Hawkes Fed -Aid No.: N/A
Capital Projects Phil McConnell Contractor: SCI Infrastructure
-Manager:
Date: Various
I. PROPOSED CHANGE
111C 111UC[Lepung or and transferring of an existing commercial service on to the newly
undergrounded PSE System
II. REASON AND BACKGROUND FOR CHANGE
Additional work related to the undergrounding PSE overhead system and associated work; PSE
Schedule 74 trench necessary for the power undergrounding related to the West Hill Reservoir
Project Bill to project #19-3027
III. METHOD OF PAYMENT
NEW PAY ITEMS Not Applicable
Change Order No. _ -_ _ _ _ _ _ FOR ACCOUNTING USE ONLY
Sch. Na. Item 1[Jescriptlon — Total Qty this Unit Unit Prise ______To
Estimated Cost of
Est. Qty PE Item
1 Undergrounding of PSE power 1 1 LS $3,111.75 $3,111.75
litres
Independent Estimate Attached Payment to be made n_Z' PA
PAY THIS Y FSTIMATE
- REQUIRE(] at a later date upon completion of work
New Sub Reqrd? No
DELETE EXISTING PAY ITEM(S) eer 1-09.5 M Not A
Change Order No. _
Sch. No. Item Description ~ _66y
Independent Estimate Attached -REQUIRED f��^
INCREASE/DECREASE TO EXISTING PAY ITEMi
ige uriver No.
No. 6 1. No
3/2 7/ 18
FOR ACCOUNTING USE ONLY
Unit Unit Price Cost of Item
Not
Item Oescript I Ion Rty Unit
1
FOR ACCOUNTING USE ONLY
Price Cost of Item
REV. DATE;
KENT
I
Inde{)endent Estimate Attached - REQUIRED
FILE NO: 200.2
TOTAL ESTIMATED COST OF CHANGE ORDER * 3,111.75
*Total of the Cost of Item Columns
THIS PAY ESTIMATE L 3 111.75
IV. WORKING DAYS
Original Contract 45 Due This Change Order* 2 Previous Total 55
DATE' DATE:
fiExVJ i i t Work added was outside the original scope of work
TOTAL WORKING DAYS* 57
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Capital Projects Manager: j Date: AxwWZ0
PhiPMonne
Construction Engineering Date:
Supervisor:
Fes: aul Kuehne — '?
J -
Construction Manager: Date: ,
Eric Connor
2 REV, DATE:
3/27/18
11/19/2.020, 2:30 PM
PROJECT: Reith Road (OH to Underground night work)
REVISION: Lower Connection from Handhole Vault to existing business.
DESCRIPTION:
Connect existing power to new handhole vault. This work has to take place at night due to the
business it will impact while shut off.
Connect Existing power to new handhole vault $ 3,035.85
Total Cost: $ 3,035.85
Bond & Insurance S 75.90
TOTAL COR: $ 3,111.75
APPROVED
By Phil McConnell at 3:02 pm, Nov 19, 2020
S:IJOBS11200 Job Folder Set Up105 Extra Work1PRICING - NEW TEMPLATE Public Works
I Labor:
Rate/MH No.
Hours / Day Days Subtotal:
Foreman
97.97 1
8.00 1.00 703.76
Operator
_
83.14 1
8.00 - -
Grade Engineer (0)
83.14 1
8.00 -
Laborer
60.95 1
8.00
Grade Checker (L)
62.69 1
8.00 -
Pipelayer
62.06 1
8.00 - -
Flagger
51.64 1
8.00 -
Teamster
73.74 1
8.00 -
Subtotal Labor: S 703.76
1B Equipment:
Rate/Hr
No.
Hours / Day
Days Subtotal:
D 61 Komatsu Dozer
110.69
1
8.00
-
Hamm Roller
50.55
1
8.00
Dump Truck
79.79
1
8.00
50 Mlnl Excavator
2S.S8
1
8.00
-
140 H Blade
76,26
1
8,00
-
240 Excavator
106.74
1
8.00
950 Loader
59.64
_
1
8.00
138 Excavator
71.39
1
8.00
-
Subtotal Equipment: S
1C Subcontractors
Quantity
UM
Cost/Unit
Subtotal:
G&G, Inc.
1
LS
1,900.00
_
I
LS
ffI
-
I
LS
LLJ
ma�enais Quantity UM Cost; Umt
S -
S -
3 -
S
S _
S -
Subtotal Subcontractor
Subtotal
1,9oao0
Subtotal Materials: -
Subtotal Items 1A-11) $ 2,603.76
Mark -Up on Labor at 29%: S 204,09
Mark -Up on Equipment at 21%: S -
Mark -Up on Subcontractors at 1 2%: Jr 228.00
Mark -Up on Materials at 21%: 6 -
76tal Cost i A - 1 l7 _0
Phone (425) 432-1325
Fax 425) 432-8155
-.1 A -
& (� Inc. -I
itikJVEMBER 181-H, 2020
S C I INFRASTRUCTURE LLC
2821 S, 154ST
SEATTLE, WA 98188
RE: REITH ROAD WATER MAIN
CHANGE ORDER REQUEST ON PSE
Gentlemen;
The price to work 1 night shift with a crew of 2 and the 2 112" conduit
will be $1,900.00 lump sum. The breakdown is below;
Labor $1,520.00
Material 280.00
Equipment 100'QQ__
$1,900.00
Sincerely
. . . . . . . . . . . . . . . . . . . . . . . . . . . .
KENT
CHANGE ORDER NO. # 2
NAME OF CONTRACTOR:
CONTRACT NAME & PROJECT NUMBER:
ORIGINAL CONTRACT DATE:
SCI Infrastructure, LLC ("Contractor")
Reith Road Watermain Improvements
July 23, 2020
This Change Order amends the above -referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
The intercepting and transferring of an existing commercial service on
to the newly underground PSE system.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum,
$615,188.75
(including applicable alternates and
WSST)
Net Change by Previous Change Orders
$68,912.86
(incl. applicable WSST)
Current Contract Amount
$684,101.61
(incl. Previous Change Orders)
Current Change Order
$3,111.75
Applicable WSST Tax on this Change
Order
$311.20
Revised Contract Sum
$687,524.56
CHANGE ORDER - 1 OF 3
Original Time for Completion
45 working days
(insert date)
Revised Time for Completion under
10 working days
prior Change Orders
(insert date)
Days Required (f) for this Change Order
2 calendar days
Revised Time for Completion
57 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the I<ent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above -referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and ar_knowlc:dges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose narnes appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR:
Srl INFO
W3
DATE: II-
CHANGE ORDER - 2 OF 3
RE, LLC
GDP
CITY OF KENT:
By:
(signature)
Print Name: Dana Ralph
Its Ma r
(tine)
DATE:
ATTEST: APPROVED AS TO FOR$
(applicable if Mayors signature req
f
Kent City Clerk Kent Law Department
IIn this held, you may enter the eledtonic Idepath rchere the contract has seen saved i
CHANGE ORDER - 3 OF 3
•
KE1VT
FILE NO: 200.2
CHANGE ORDER WORKSHEET NO. 2
Construction En ineerin Division — Public Works
Project: Reith Rd Watermain Project No.: 19-3005
Improvements
Project Engineer: Derek Hawkes Fed -Aid No.: N/A
Capital Projects Phil McConnell Contractor: SCI Infrastructure
Manager:
Date: Various
I. PROPOSED CHANGE
1 Me intercepting of and transferring of an existing commercial service on to the newly
undergrounded PSE System
II. REASON AND BACKGROUND FOR CHANGE
Additional work related to the undergrounding PSE overhead system and associated work; PSE
Schedule 74 trench necessary for the power undergrounding related to the West Hill Reservoir
Prole t - Bill to project #19-3027
III. METHOD OF PAYMENT
NEW PAY ITEMS Not Applicable
Change Order No. : - _ FOR ACCOUNTING USE ONLY
Sch. No. Item !]ascription Total Qty_ this Unit T Lin lt Price Total Estimated Co_st of
Est. City PE Item
1 Undergrounding of PSE power 1 1 i_S $3,111.75 $3,111.75
lines
Independent Est)mate Attached EJ I— - Payment to be made PAY THIS PAY ESTIMATE
- REQUrRED ; at a later date upon completion of work
New Sub Regrd7 No
DELETE EXISTING PAY ITEM(S) eer 1-09.5 Not A ficable
ange Order No. - __ FOR ACCOUNTING USE ONLY
h. No. B.1. Na. _ Item Rescriptian Qty T Unit Unit Price Cost of Item
Independent Estimate Attached - REQUIRED Y�_ `-
INCREASE DECREASE TO EXISTING PAY ITEMS NotAppli_cable
nge Order No. - FOR ACCOUNTING USE ONLY
.No. . B.I. No. Item Description Qty Unit Unit Price Cost of Item
1 REV, DATE;
3/27/18
FILE NO: 200.2
Independent Estimate Attacf�t i - REQUZRFD
TOTAL ESTIMATED COST OF CHANGE ORDER * 3,111.75
*Total of the Cost of Item Columns
THIS PAY ESTIMATE $3,111.75.
IV. WORKING DAYS
Original Contract 45 Due This Change Order* ; Z Previous Total 55
DATE: DATE:
* Work added was outside the original scone of work
TOTAL WORKING DAYS* L 57
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Capital Projects Manager: _ I Date:
Phil McCanne
Construction Engineering Date:
Supervisor:
aul Kuehrle -
f
Construction Manager: Date: 1
Eric Connor
2 REV, DATE:
3/27/18
11/19/2020. 2:30 PM
f14Ln,g, Mth&Norhwet
PROJECT: Reith Road (OH to Underground night work)
REVISION: Power Connection from Handhole Vault to existing business.
DESCRIPTION:
jConnect ex- fing power to new handhole vault. This work has to take place at night due to the
business it will impact while shut off.
Connect Existing power to new handhole vault $ 3,035.85
Total Cost: $ 3,035.85
Bond & Insurance $ 75.90
TOTAL COR: $ 3,111.75
APPROVED
By Phil McConnell of 3:02 pm, Nov 19, 2020
S:\JOBS\1200 Job Folder Set Up\05 Extra WOrk\PRICING - NEW TEMPLATE Public Works
I Labor:
Rate/MH No.
Hours / Day Days Subtotal:
Foreman
87.97
1
8.00
1.00
703.76
Operator
83.14
1
8,00
-
-
Grade Engineer (0)
83,14
1
8.00
Laborer
60.95
1
8.00
Grade Checker (L)
62.69
1
8.00
-
-
Pipelayer
62.06
1
8,00
Flagger
51.64
1
8.00
-
Teamster
73.74
1
8•00
Subtotal Labor: $ 703,76
1 B Equipment:
Rate/Hr No.
Hours / Day
Days Subtotal:
D 61 Komatsu Dozer
110.69 1
8.00
Hamm Roller
50.55 1
8.00
_
-
Dump Truck
79.79 1
8.00
-
50 Mlnl Excavator
25.58 1
8.00
-
140 H Blade
76,26 1
8.00
-
240 Excavator
106.74 1
8.00
950 Loader
59.64 1
8.00
138 Excavator
71.39 1
8.00
1C Subcontractors Quantity
GAG, Inc. i
I
_ 1
UM CostlUnit
LS 1.900.00
LS
LS
1 D Materials Quantity UM Cost/Unit
Subtotal Equipment: $
Subtotal:
1,900.00
Subtotal Subcontractor 11900.00
Subtotal
Subtotal Materials: -
Subtotal Items lA-1D 3 Z603,76
Mark -Up on Labor at 29%: $ 204.09
Mark -Up on Equipment at 21%: S
Mark -Up on Subcontractors at 1 2%: S 228.00
Mark -Up on Materials at 21%: $ -
T6W Cast 1 A - 1 D ra
Phone (425) 432-1325
Fax 425) 432-8155
G & G Inc.
NOV EMBER 181-H, 2020
S C I INFRASTRUCTURE LLC
2821 S. 154ST
SEATTLE, WA 98188
RE: REITH ROAD WATER MAIN
CHANGE ORDER REQUEST ON PSE
Gentlemen;
The price to work 1 night shift with a crew of 2 and the 2 1/2" conduit
will be $1,900.00 lump sum. The breakdown is below:
Labor $1,520.00
Material 280.00
Equipment 100,Q0_
$1, 900.00
Sincerely