HomeMy WebLinkAboutCAG2019-220 - Change Order - #3 - Scarsella Bros, Inc - 228th St UPRR Grade Separation Bridge & Roadway - 12/23/2019 104 Agreement Routing Form • For Approvals,Signatures and Records Management KENT This form combines&replaces the Request for Mayor's Signature and Contract Cover Sheet forms. WASHINGTON (Print on pink or cherry colored paper) Originator: Department: S. Anderson PW Engineering Date Sent: Date Required: > 2/24/20 N/A O i O. Authorized to Sign: Date of Council Approval: 0 Director or Designee ❑Mayor N/A Q Budget Account Number: Grant? 0 Yes ❑No Budget? ElYes ❑ No Type: Federal,State,Local Vendor Name: Category: Scarsella Bros, Inc. Contract Vendor Number: Sub-Category: = 34547 Change Order 3 O Project Name: S.228th St. Union Pacific Railroad Grade Separation Bridge and Roadway Phase 5 L 0 Furnish and install a new business entrance sign for Pacific Metals as detailed on the attached drawing at new driveway off 76th Ave South. L. Project Detal ls:Work also includes removal of old building address,fabrication and installation of new building address visible for new driveway approach. 4W C E Agreement Amount: $17,299.84 Basis for Selection of Contractor: Bid O U Start Date: N/A Termination Date: N/A Im Q Local Business? ❑Yes O No* *If meets requirements per KCC 3.70.100,please complete"Vendor Purchase-Local Exceptions"form on Otyspoce. Notice required prior to disclosure? Contract Number: (A-'V' O 1L'&i0 dJ— ❑Yes 0 No c b 19 2— Date Received by City Attorney: Comments: C1 C 3 O 3 � a, IQ C a1 Date Routed to the Mayor's Office: V1 Date Routed to the City Clerk's Office: Visit Documents.KentWA.gov to obtain copies of all agreements • KENT W A S H I N G T O N CHANGE ORDER NO. # 3 NAME OF CONTRACTOR: Scarsella Bros, Inc. ('Contractor") CONTRACT NAME & PROJECT NUMBER:S. 228th St. Union Pacific Railroad Grade Separation Bridge and Roadway Phase 5 ORIGINAL CONTRACT DATE: April 19, 2019 This Change Order amends the above-referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: 1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: This change makes the following revision to the contract documents: Furnish and install a new business entrance sign for Pacific Metals as detailed on the attached drawing at new driveway off 76th Ave South. Work also includes removal of old building address, fabrication and installation of new building address visible for new driveway approach. 2. The contract amount and time for performance provisions of Section II "Time of Completion," and Section III, 'Compensation," are hereby modified as follows: Original Contract Sum, $13,802,146.40 (including applicable alternates and WSST) Net Change by Previous Change Orders $-36,720.00 (incl. applicable WSST) Current Contract Amount $13,765,426.40 (incl. Previous Change Orders) Current Change Order $17,299.84 Applicable WSST Tax on this Change $0.00 Order Revised Contract Sum $13,782,726.24 CHANGE ORDER - 1 OF 3 Original Time for Completion 240 working days (insert date) Revised Time for Completion under 240 working days prior Change Orders (insert date) Days Required (f) for this Change Order calendar days Revised Time for Completion 240 working days (insert date) In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the Contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby ratified and affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written below. CONTRACTOR: CITY OF KENT: By: /470q? By: (signature) (signature) Print Name: JG°/" Print Name: Timothy 3. LaPorte, P.E. Its /✓�taj�"GT -s-�.��//�E,�it "'' Public Works Director (title) (title) DATE: ZVI/ /9 DATE: CHANGE ORDER - 2 OF 3 ATTEST: APPROVED AS TO FORM: (applicable if Mayor's signature required) Kent City Clerk Kent Law Department [In this field,you may enter the electronic filepath where the contract has been saved] CHANGE ORDER - 3 OF 3 • FILE NO: 200.2 KENT CHANGE ORDER WORKSHEET NO. 003 Construction Management Division - Public Works Project S. 2281h St Union Pacific Railroad Project No.: 07-3022 Grade Separation Ph 5 Project Engineer: Cameron Bloomer, PE Fed-Aid No.: HLP 1216 (006) Owners Rep: KBA, Inc Contractor: Scarsella Bros. Inc. Date: 11/13/2019 I. PROPOSED CHANGE This Change makes the following revisions to the Contract Documents: • Furnish and Install a new business entrance sign for Pacific Metals as detailed on the attached drawing at new driveway off 76th Ave So. Sign construction shall be as similar as practical to the existing FloForm sign and as described in the proposal provided by Evergreen Signs. Work also includes removal of old building address and fabrication and installation of new building address visible from new driveway approach. II. REASON AND BACKGROUND FOR CHANGE The project closed the existing driveway to the Pacific Metals property and constructed a new driveway access from 761h Ave S. The existing building has a large sign on it that was easily viewable from the 228th roadway and driveway. New abutment walls limit the visibility of the sign and move it from view of the property's driveway. In an attempt to make the property owner whole, the City agreed to have a new entrance sign installed at the new driveway location and modify the building address to the new street address. III. METHOD OF PAYMENT NEW PAY ITEM(S) ❑ Not Applicable Change Order No. - FOR ACCOUNTING USE ONLY Sch. No. Item Description Total Est. Qty this Unit Unit Price Total Estimated Cost of Qty PE Item .......... ........ ............... .......... ...................... .............................. . . ... .... New Pacific Metals frontage 1 LS $17,299.84 $17,299.84 sign and new street address at buildrng........ ........................... ...............................................................................................e..................................................................................................:......................................................... ......................................................_;................................................................................................................... ....................................................................................._.. ....................._..... ...........;...................................................................................................................................................................................................... ❑ Independent Estimate Attached ❑ CREATE PAY ITEM ONLY— Payment to be made ❑ PAY THIS PAY ESTIMATE - REQUIRED at a later date upon completion of.. work ........... ❑ Material Submittals Reauired — CC. Construction Coordinator New Sub Regrd7 No DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable 1 REV. DATE: 3/15/19 • FILE NO: 200.2 KENT WA=� Change Order No. - FOR ACCOUNTING USE ONLY Sch. No. B.I. No. Item Description Qty Unit Unit Price Cost of Item ......... . . ........ . ........ ......._........_.........__......... ............. ..................__._ ............................................_.._..............-_ .......... .. ......._...... ..._...... . . ...-.... ... .............. .. ._............ ..... .............................:........................................_._...................._......_..........................._.._....._._..........................................................................................._.._._..._.................!............................._.........$...................._.....__........._......... .... __....................... ......................................... Independent Estimate Attached -REQUIRED INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable Change Order No. - FOR ACCOUNTING USE ONLY Sch. No. B.I. No. Item Description Qty Unit Unit Price Cost of Item ...............:..............................:.......................................................e......................._.............._-.................................._.................................................-...._........,.._u......................................_............q......................................................................................................................................u....................................................................__..........._............................._... ................-___......_........._.._..___..._. __...........................i....................................._..._._......_..................._........................................_._......_........................................................i.. . ............................. .........._......................................_....__.__._.._. _........................_....._.._..._............................................................_------- i ......................................_.......................................... , _...................................................._........_...-•--................................_ Independent Estimate Attached -REQUIRED El TOTAL ESTIMATED COST OF CHANGE ORDER * $17,299.84 *Total of the Cost of Item Columns THIS PAY ESTIMATE 0 IV. WORKING DAYS Original Contract 240 Due This Change Order* Q Previous Total 240 _..._........._.. ............. ......... .... .....-- ....... _........... DATE ....... DATE ............ * Ex lanation Justification Re uired. This CO's work scope is not critical ath. No ad ustment to contract time is bein made. TOTAL WORKING DAYS* 240 *This Change Order + Previous Total All work, materials and measurements to be in accordance with the Standard Specifications and Contract Special Provisions for the type of work described. Prepared By: Cameron Bloomer Date: 11/13/19 Construction Supervisor: Date: Id 13 1 Construction Manager: Ti7 Date: 2 REV. DATE: 3/15/19 October 17,2019 City of Kent 220 Fourth Avenue South Kent,WA 98032 Attm Cameron Bloomer Field Engineer KBA, Inc. RE: 07-3022 228th St. UPRR Phase 5 Pacific Metals Signage(FWD 012)Rev 1 SCARSELLA BROS. IS PLEASED TO SUBMIT THE FOLLOWING CHANGE ORDER PROPOSAL FOR THIS PROJECT: ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE BID AMOUNT Clear,Grub,and Grade for Foundation LS 1 S 1,500.00 S 1,500.00 Monument Sign&Address Numbering by Evergreen Sin LS 1 $ 14,670.00 S 14,670.00 114�l'C7 12%Subcontractor Markup LS 1 $ 1.760.40 S 1,760.40 TOTAL $ 17,930.40 NOTES: 1. See exclusions on Evergreen Sign quote. Sincerely, Matthew Scarsella Project Manager Barry, Jason From: Cameron Bloomer <cbloomer@kbacm.com> Sent: Wednesday, November 13, 2019 3:24 PM To: Matthew Scarsella Cc: Shelley K. Skaggs; Barry, Jason Subject: RE: Evergreen Sign Co. EXTERNAL EMAIL Hello Matt, There was a math error in their proposal that lowered the price about 5 bucks total after markups. LS items are as described in their proposal. See below. That work? NEW PAY HWS Nbt6gE!E� cYwlge Order No. - FORACCMN47M USE'ONLY Sulk W. tam UN=="Fbn Total fit. OtY ddo tMt U Prkn Total 4kiapipcI P90 of Otv P€ tem Mongment Fabrication 1 LS $8,890.00 $8,890.00 Monument Installation 1 LS $2,756.06 $2,750.00 _. Address Letters Install $2,017.00 Address Letter Removal 1 LS ,.._ $450.00, _$450 00 Clearing and Sub Markups i $3,192.84 Indepzndent€stamata Attached t`,$FATPAY at, „3NY Y-Payment to be made £, pAV TnIS PAY ESTIMATE 7'.. -RfQUlRFD j.AS.a.l"wit.aGe..uPon co npietioa of work, L!„ .. _.._.. :fAAtbrlAl submittAis 5c onste ttfon oe Inamr hew sub Rggtd! No Cameron Bloomer, PE C 206.819.7148 1 cbloomer@kbacm.com K A, Inc. I Construction Monogement Speciolists I an W*bacm.co From: Matthew Scarsella <matthew.s@SCARSELLABROS.com> Sent:Tuesday, November 5, 2019 10:37 AM To: Cameron Bloomer<cbloomer@kbacm.com> Cc: Shelley K. Skaggs<SheIleyK.S@SCARSELLABROS.com> Subject: Evergreen Sign Co. Hi Cameron, We are setting up Evergreen Sign Co. as a subcontractor for the Pacific Metals Signage Change Order. Do you know how the Change Order will be structured (item numbers, units)? It effects how we structure our subcontractor with them. Thanks, Matt Matthew Scarsella, P.E. I Project Manager 1 EVERGREEI!�O_ Construction Project Department 1(253)862-1354 Ext x 301 Bid#. 1909002 R_1 1513 Central Ave.South Ste 1 Kent Washington 98032 JA License#. EVERGSCS54CO Project Name Scarsella Bros.-City of Kent �ddendum(s) N/A Bid Date: Tuesday,September 24,2019 Bid Sections; NEW MONUMENT SIGN-NON-ILLUMINATED ON •- QUANTITY UNIT COST • COST MONUMENT SIGN- MONUMENT 18'W X 6'h X 10"thick aluminum cabinet mounted to concrete w/J bolts.With 1/4"deep logo 1 $8,890.00 $8,890.00 and name"PM/PACIFIC METAL"painted black applied to face with"ENTRANCE,ARROW& ADDRESS"in black vinyl applied to face. INSTALL INSTALL Installation of monument sign w/multiple deployments including pouring concrete base and 1 $2,750.00 $2,750.00 install of sign cabinet G STY To DIMENSIONAL ADDRESS 3/8"thick,12"tall dimesional letter forms to read"22601 76th Ave South"painted to match 1 $2,017.00 $2,017.00 current address.Mounted to exterior wall with 3/8"spacers REMOVAL Removal existing letter set and fill holes with matched as close as possible silcone 1 $450.00 ­111454100 Total Cost WA Contractor#:EVERGSCS54CO I OR Contractor#:220829 —7 Price does NOT INCLUDE:structural engineer and any applicable taxes,unless noted above --. Price is valid for 60 days from date of bid date Fabrication time frame is scheduled for 2-4 weeks for completion upon approval of submittal drawings&mockups and Permits Bid pricing is put forth based upon good faith and ESC reserves the right to void this proposal CITY OF KENT FEE LISTING *21430* SENT WA5. NGTO (_ ................. PERMIT: RHIi-2194193 Check permit status 'online" at kentwa.gov/permitcenter/forms DATE : 13-NOV-19 10:47:15 SCOPE: FREESTANDING SIGN LESS THAN 6 FEET TALL PROJECT: PERMIT NAME: PACIFIC METALS-FREESTANDING SIGN APN: 3830900060 SITE ADDRESS: 22601 76 AVE S KENT,WA 98032 LOCATION: OWNER: LIFT PARTNERS LLC ADDRESS: 22601 76TH AVE S CITY/STATE/ZIP: KENT,WA 98032 FEE QTY TOTAL PAID INTER-DEPARTMENTAL TRANSFER $399.09 $399.09 SIGN PERMIT - DE $100.31 $100.31 SIGN PERMIT $298.78 $298.78 Customer: I III III IIIII III IIIIII I'I�1111II IIII IIII Total Fees: $0.0 0 (Item 754) Total Paid: $0.0 0 Total Due: $0.00 Page 1 of 1 Barry, Jason From: Madfai, Mark Sent: Thursday, November 14, 2019 10:33 AM To: Cameron Bloomer Cc: Barry, Jason Subject: FW: Pacific Metals freestanding sign permit Attachments: RG11-2194193 PACIFIC METALS.pdf Cameron, Just FYI. The sign permit has been approved. Mark From: King, Kristin Sent: Wednesday, November 13, 2019 11:32 AM To: Madfai, Mark<MMadfai@kentwa.gov> Subject: Pacific Metals freestanding sign permit Good morning, The sign permit for Pacific Metals (permit# 2194193) is now ready for issuance. Attached is the fee listing which reflects the balance has been paid in full. Please be aware this application will expire if not picked up within one hundred eighty (180) days of the date of this e-mail (KCC 12.01.110 / IBC 105.3.2). Kristin King, Permit Technician Economic &Community Development I Permit Center 400 W. Gowe, Kent, WA 98032 Main 253-856-5300 1 Direct 253-856-5314 kkingCcokentwa.aov Operating hours: M,T,Th &F — 9 AM to 5 PM. W — CLOSED CITY OF KENT, WASHINGTON KentWA.com Facebook You'rube OLTA SE CONSIDER TH.F E'Nv:H'.9;.ONMEN1 BEFORE PRMITIN THIS E-MAIL 1 FA Sheet No.: o m Independent Cost Estimate CONSTRUCTION MANAGEMENT Project Name: 228th Ph 4 Project No: 17-3003.2 Item No.: Date: 8.16.19 Description of Work: Entrance Sign at Pac Metals Work by Subcontractor?: (mark'x"if yes) Prime Contractor: Scarsella Bro's, Inc. Sub-Contractor: G and G Incorporated Items/Cost MATERIALS/SERVICE DESCRIPTION QUANTITY UNIT PRICE AMOUNT Clear and Grubb(SBI) 1 LS $ 800.00 $ 800.00 Sign $ - Design 1 LS $ 1,000.00 $ 1,000.00 Carpenter 32 Hr $ 75.00 $ 2,400.00 Laborer 16 Hr $ 60.00 $ 960.00 Crew Truck 16 Hr $ 30.00 $ 480.00 Materials 1 LS $ 1,000.00 $ 1,000.00 Address $ - Carpenter 8 HR $ 75.00 $ 600.00 Crew Truck 8 HR $ 30.00 $ 240.00 Materials 1 LS $ 200.00 $ 200.00 ssume 3 clays for sign(Founciation, Form Sign/Stucco, finis and letters) r $ - SUBTOTAL-MATERIALS $ 7,680.00 Markup @ 21% $ 1,612.80 SUBCONTRACTOR TOTAL 9,292.80 Verification of Hours Worked: TOTAL: $ 9,292.80 12%MARKUP(for prime when subcontract work) ------------------------------------------------------- Contractor's Representative(printed name) SHEET TOTAL: $ 292 8A Contractor's Representative Signature Date V—S i i nn/4-r�_ A SSUM� o �"- Prime Markup on Subcontractor-Lc) � ' � 2Fc7t1 F�FztS �v' w O----ne-r's- -eprese------nta-- a(printed- name---).....---------....----- 12%: <$25,000 R 10%: $25,000 to$100,000 1_ A— Owner' ----- ---------------------------------------- 7%: >$100,000 Owner's Repres ntative Signature Date Pay Estimate Entered: 7 If checked,this work is in dispute. By signing this form, parties Date: are agreeing to the time and effort needed to accomplish the task. By: Entitlement to be determined at a later date. —iti1►T/� c)� ,4_U D�S i6� J E JCX A!-_-) -�`zJ2_ 11,-,-rl,A� �S"i7�tA i� c--�AL�`f' �116C[�sUj Ac'�ok `TG Sogii `�SF�j Bi)Si�SS �TLjAL_ N&J'U S cc)S " S tf<DP /��:D DES►� J u?ao _C, � wXE k_ Ar..►b DE-LA IJ� � z a �71W 9�c.cs�t�D�NGL'�• 1 of 1 C_t `1 4�_F f`^gAj—I P-13 (Rev. 7/12) Barry, Jason From: Matthew Scarsella <matthew.s@SCARSELLABROS.com> Sent: Thursday, October 17, 2019 8:36 AM To: Cameron Bloomer Cc: Nick Venema; Barry,Jason Subject: RE: Floform Sign Attachments: COP 008 Pac Metals Signage Revl.pdf EXTERNAL EMAIL Hi Cameron, I still have not received details on the foundation but wanted to give you the price anyway. I will send the foundation details when I receive it. Thanks, Matt Matthew Scarsella, P.E. I Project Manager From: Cameron Bloomer<cbloomer@kbacm.com> Sent:Thursday, October 3, 2019 2:59 PM To: Matthew Scarsella <matthew.s@SCARSELLABROS.com> Cc: Nick Venema <nick.v@SCARSELLABROS.com>; ibarry@KentWA.gov Subject: FW: Floform Sign Hello Matt, Please have Evergreen include some details on the foundation when their proposal for Pac Metal's sign comes through. See below. Thank you, Cameron Bloomer, PE C 206.819.7148 1 cbloomer@kbacm.com KBA, Inc. I Construction Management Specialists I www lbacm.com From: Madfai, Mark<MMadfai@kentwa.gov> Sent:Thursday, October 3, 2019 2:45 PM To: Cameron Bloomer<cbloomer@kbacm.com> Cc: Barry,Jason <JBarry@kentwa.gov> Subject: Floform Sign Cameron, Can you ask Scarsella to ask Evergreen Sign to provide construction details on the sign. i.e what type of footing or base the sign will sit on. Barry, Jason From: Matthew Scarsella <matthew.s@ SCARS ELLABROS.com> Sent: Thursday, October 17, 2019 2:21 PM To: Cameron Bloomer Cc: Barry, Jason; Nick Venema Subject: FW: Pacific Metal Signage project - Updated Pricing Attachments: Example Monument Sign Permit Drawing.pdf EXTERNAL EMAIL Cameron, Please see email below and attached example of footing. Thanks, Matt Scarsella Bros., Inc. Matthew Scarsella, P.E. I Project Manager P.O. Box 68697 Seattle, Washington 98168-0697 o: (253) 872-7173 1 c: (206) 817-2765 matthew.s@scarsellabros.com From: Nicolas Chavez<nic evergreensign.com> Sent:Thursday, October 17, 2019 8:52 AM To: Matthew Scarsella <matthew.s@SCARSELLABROS.com> Cc:Jeremy Kirchner<Jeremyk@evergreensign:corn>; Debbie Mitzel <Debbiem@evergreensign.com>;Jim Toombs <JimT@evergreensign.com> Subject: Pacific Metal Signage project- Updated Pricing Good morning Matt— Attached is a typical monument sign permit drawing. Once the pricing is approved we can start of the drawing submittals. NOTE: Each sign footing is custom to the projects site conditions. Thank you. Nic Chavez Construction Projects Department 1 253-852-1354 :a evergreen sign co. 1513 Central Ave South Kent, Washington 98032 1 `� .. KEN T WASHINGTON Field Work Directive FWD 012 Project Name: S. 228th St. Union Pacific Railroad PW Project Number: 07-3022 Grade Separation—Ground Improvements and Embankments Contractor: Scarsella Bros., Inc. Federal Aid Number: HLP-FMSIB- 1216(005) Subject: Pacific Metals Entrance Sign Date: 811612019 Scope: Make the following changes to the Contract Documents: • Furnish and Install an entrance sign for Pacific Metals at the location and per the attached drawing. Sign construction to be as similar as practical to the existing FloForm sign on the opposite side of that driveway. Change address letter on building to new address and location on the north/east face of the building at a location determined by the engineer. New address letters to match existing letters. Measurement and Payment: • Track all time and materials necessary to complete this work,submit any cost proposals from specialty sign contractors for City review prior to proceeding. Attachment(s): • Pacific Metals SITE ENTRANCE SIGN 06.2019 Contractor Acknowledgement: By: Date: Matthew Scarsella, Project Manager Owner, pproval: By Date: ason Barry, City of Kent By. Date: 29�y,�/s Eric Connor, City of Kent THIS FIELDWORK DIRECTIVE DOES NOT PROVIDE FOR EITHER ATIME EXTENSION OR A CHANGE IN THE CONTRACT PRICE.LABOR,EQUIPMENT,AND/OR MATERIAL OUTLINED IN THIS FIELDWORK DIRECTIVE SHALL BE PAID BY BID ITEM(S)OR A CHANGE ORDER SHALL BE DEVELOPED FOR TIME EXTENSION OR CONTRACT PRICE INCREASES. ANY PROTEST TO THE FIELD WORK DIRECTIVE SHALL FOLLOW 1-04.5 OF THE WSDOT STANDARD SPECIFICATIONS. As PROPOSED PAC—METALS 8 p- SIGN (MATERIAL TBD) EXISTING SCHRUBS FIA _ 9 EXISTING PROPERTNE ��CIFIC IAE TAL Y LI — )32 - - '�. " 22601�76THAVE S.,KENT.WA 98c ROW EXISTING CURB--j u / EXISTING SIDEWALK � d PACIFIC METALS PROPOSED STREET VIEW KKENT ENTRANCE SIGN CITY OF KENT s NTs DRAWING ENGINEERING DEPARTMENT DATE JUNE. 2019 OPTION 3 S\Design\07-3022 228th UPRR\dwg\Roadway Plan Sheets\Off—Site Improvements\FlowForm\07-3022 Floform Street Vew Entrance.dwg 9/13/2017 6:08:36 AM f 31 53SS t f 5 Ce s A' y Kent Fire Department Fire Prevention internationally Accredited Fire Agency Physical: 400 West Gowe Street Mail To: 220 Fourth Avenue South Kent, WA 98032 b Office: (253) 856-4400 � t►;and King County Fire District 37 Fax: (253) 856-6400 Professionally and Compassionately Helping People ADDRESS CHANGE NOTICE 211412018 The City of Kent is the only agency that has the authority to issue addresses in the city limits of Kent. Addresses are important for emergency response. Our goal is for emergency responders to locate you as soon as possible. If the address does not fit within the City's addressing policy or it is difficult for emergency services to find, the address will be changed. The Post Of will deliver mail to both addresses for one (1) year. The owner, occupant, or tenant of any building or premises shall, upon ten (10) days' notice front the fire c c' Zt1avethe correct address on the building. KCC 13.06.150. EW ADD OLD ADDRESS: TAX LOT#: cific Met Pacific Metals 2260176" th 7416 South 228`h Street 3830900060 Kent, A 9 Kent,WA 98032 nee to parcel due to road/street construction. Tom Williamson, Captain 253-856-4418 lwilliamson@pugetsoundfire.org Cc: Current Resident or Property Owner Comcast Cable Services US Postal Service King County Assessor's Office Puget Sound Energy City of Kent Customer Service Century Link City of Kent Planning King County E911 Valley Communications 7/16 € '_ € - ���11iJJJ W d �a g C of �ig {y}~p Off cooga' N W a a E a 00000 � e O HlVM301S WOai x3v813S.0£ co CA. t \ to Ls v H a W a O ff � o 1, a a 1, low ff j Ak, Ed uj yui x \ .ry0j ry LL ytS� +y� a LU LU uj s y W o a CO) Lo CD r • E � ��� 4 � W�qp dD � W o C� c MH Will 0 W w a .fl clJ v rn - _ g LL o o mz _ .� �v 3 W w J w Q W X C O. m C J O co Q CC,a Q N Z m O LOWWmcr O O O 2 31 LL = co) a 21 Ci C z C of 3 N a R N O � co C xwa v oZ oz tW- Xz " �_ c a c CD _ W v a o o o c o co) = 6�.1 d 6 ? G o .c v61i o ti U 0 0 C .b d330.,9E 1 aZ)t 9b At „8 d8Z •+aZ c�------- — - `------------- - _ - II ., ---------------- ---------------- co I _ I x Lu at ----` 2 NN I ----------------- Z I �_______-___-_- co . I OY - ----- W --- Ili 1 z 0 — — I o -- - - W W W ------ CLu -: r i I ui _ L O �^ z y i aoc�a - G M y _ �\ O aZll t eD ,.OtF O _ .09 N g$�c£W LL ¢m 60 O W w ¢ 0 1�1 w� U -Cc ¢ O L7 E � — Q o 0 N H 4L N w �n 0 0. c0 N C GC V W X¢ Z ¢` 69kh ?r\ O N V V Z OLL Z = x Z LL0 t� 0 0 L U _ G O N o d CS) C) CO) 0 � 0 Q O z F- O O W F W O 00 N I I I ^ I e o o� I I I I I i I I I I i I I I I I I I I � I I i Fa„ W ^ I I I icy G a I I t9 I I I H I I I W CD a I I I W 3 fL crW o o W I ---- I O . I _ W r N I I d 0 N I I 1 C z .Zli W F I I I c y .- M o AL - O y NDIS 301M,.9 t cob ..trZ