HomeMy WebLinkAboutCAG2019-220 - Change Order - #1 - Scarsella Bros, Inc - 228th St UPRR Grade Separation Bridge & Roadway - 12/23/2019 Agreement Routing Form
• For Approvals,Signatures and Records Management
This form combines&replaces the Request for Mayor's Signature and Contract Cover Sheet forms.
KEN T
WASHINGTON (Print on pink or cherry colored paper)
Originator: Department:
S. Anderson PW Engineering
Date Sent: Date Required:
> 2/24/20 N/A
O
16.
C. Authorized to Sign: Date of Council Approval:
a' 0 Director or Designee ❑Mayor N/A
Q
Budget Account Number: Grant? 0 Yes ❑No
Budget? ElYes ❑No Type: Federal,State,Local
Vendor Name: Category:
Scarsella Bros, Inc. Contract
Vendor Number: Sub-Category:
34547 Change Order
O
Project Name: S.228th St. Union Pacific Railroad Grade Separation Bridge and Roadway
E Phase 5
\O Makes revisions to contract documents Special Provision Section 1-0711-Insert attached document titled'1-07.11 Requirements for Non-discrimation'.
Project Details:
C Special Provision Section 1-07.1-Insert the attached document Idled 1-08.1 Subcontracting
E Agreement Amount: $4,680 Basis for Selection of Contractor: Bid
3 Start Date: N/A Termination Date: N/A
Q
Local Business? ❑Yes 0 No*
*Ifineets requirements per KCC3.70.700,please complete"Vendor Purchase-Local Exceptions"form on Cityspace.
Notice required prior to disclosure? Contract Number: oft& 'd
❑Yes 0No CA 2,6I - 27-0
Date Received by City Attorney: Comments:
C
VA
•> i
�1 3
R
C
p$ Date Routed to the Mayor's Office:
in
Date Routed to the City Clerk's Office:
,dc(W22373_1_20 Visit Documents.KentWA.gov to obtain copies of all agreements
•
KENT
WASHINGTON
CHANGE ORDER NO. # 1
NAME OF CONTRACTOR: Scarsella Bros, Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER:S. 228th St. Union Pacific Railroad Grade Separation Bridge
and Roadway Phase 5
ORIGINAL CONTRACT DATE: April 19, 2019
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
This change makes the following revision to the contract documents:
Special Provision Section 1-07.11- Insert attached document titled '1-
07.11 Requirements for Non-discrimation'.
Special Provision Section 1-07.1 - Insert the attached document titled
`1-08.1 Subcontracting'.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $13,802,146.40
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $0.00
(incl. applicable WSST)
Current Contract Amount $13,802,146.40
(incl. Previous Change Orders)
Current Change Order $4,680.00
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum $13,806,826.40
CHANGE ORDER - 1 OF 3
Original Time for Completion 240 working days
(insert date)
Revised Time for Completion under 240 working days
prior Change Orders
(insert date)
Days Required (f) for this Change Order calendar days
Revised Time for Completion 240 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
By: By: L.�. _
(signature) G �p £�sP MAJ (signature)
Print Name: 17111XW,6&1 J-6o' &ZA PP�''int Name: Timothy J. LaPorte, P.E.
Its �icoJ-CGi� iyl/,I M""l /t tt;r"" Public Works Director
(title) (title)
DATE: /V-1y,— 9 DATE: s fi?
CHANGE ORDER - 2 OF 3
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
I
Kent City Clerk Kent Law Department
[In this field,you may enter the electronic filepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
KENT FILE NO: 200.2
CHANGE ORDER WORKSHEET NO. 001
Construction Management Division - Public Works
Project S. 2281h St Union Pacific Railroad Project No.: 07-3022
Grade Separation Phase 5
Project Engineer: Cameron Bloomer, PE Fed-Aid No.: HLP-1216 (006)
Owners Rep: KBA, Inc Contractor: Scarsella Bros. Inc.
Date: 11/21/2019
I. PROPOSED CHANGE
This Change makes the following revisions to the Contract Documents:
Special Provision Section 1-07.11 - Insert the attached document titled '1-07.11 Requirements
for Nondiscrimination'.
Special Provision Section 1-08.1 - Insert the attached document titled '1-08.1 Subcontracting'.
II. REASON AND BACKGROUND FOR CHANGE
Funding for this project is partially provided by Connecting Washington, which calls for certain
non-discrimination and reporting requirements not included in the WSDOT Standard
Specifications. The APWA GSPs noting these requirements were not included in the original
contract package, and are subsequently being added via this change order.
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ❑ Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
i
CO 01 - CNWA 1
........ .....................$4,680.00........ _.........................
$4,680.00
Nondiscrimination Reporting
Requirements
... ................. ...... .............---_............................ ... _..........
......................_........................... ....................................... .........................................................................................._................
❑ Independent Estimate Attached ❑ ; CREATE PAY ITEM ONLY— Payment to be made ❑ PAY THIS PAY ESTIMATE
REQUIRED _ at a later date upon completion of work
.........................._..._.....
❑ Material Submittals Required — CC: Construction Coordinator New Sub Reqrd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description Qty Unit Unit Price Cost of Item
...................
1 REV. DATE: 3/15/19
KENT FILE NO: 200.2
. _w a= o
. .............__.._.................................................................................
Independent Estimate Attached - REQUIRED
�o 0
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description Qty Unit Unit Price Cost of Item
_........._..................__...._................._..._._....................................................................._............._...........................
y.....................................................e..................._......_.._. _.._................... __....._v....._..__.—_.—.._......................................................_....
..............................................................._....................................._....................................................................................................................................................... .. ,.......................--- .........._............................................._................................_._.._...._..
.............................................................................
....
i
Independent Estimate Attached -REQUIRED
TOTAL ESTIMATED COST OF CHANGE ORDER * $4,680
*Total of the Cost of Item Columns
THIS PAY ESTIMATE 0
IV. WORKING DAYS
Original Contract 240 Due This Change Order* 0 Previous Total 240
._..._....... ........ ......... ....... ......... ........ .. ...._....._................................_......................._....._...............................................
...
DATE: DATE:
.............�._........ ......... ........ ....... ...... ...I.._....;.... .......__ ..._. .................................................................................................
* Explanation/Justification Required. This Change Order is administrative in nature and has no effect on the project's critical
ath. No days are being added or deleted with this change order.
TOTAL WORKING DAYS* 240
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: Canneron Bloomer ,Date: 11/21/19
Construction Supervisor: V:rA ALAC pate: 11� r
Construction Manager: Date:
2 REV. DATE: 3/15/19
October 23.2019
City of Kent
220 Fourth Avenue South
Kent,WA 98032
Attn: Cameron Bloomer
Field Engineer
KBA, Inc.
RE: 07-3022 228th St. UPRR Phase 5
Voluntary Goals and DMCS Reporting
SCARSELLA BROS. IS PLEASED TO SUBMIT THE FOLLOWING CHANGE ORDER PROPOSAL FOR THIS PROJECT:
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE BID AMOUNT
Administrative Labor Cost LS 1 S 4,680.00 S 4.680.00
MSVWBE Inclusion Plan HR 4 $ 45.00
MSVWBE Monthly Reporting HR 96 $ 45.00
MSVWBE Reporting HR 4 $ 45.00
TOTAL $ 4,680.00
NOTES:
1. Assume 1/2 day for MSVWBE Inclusion Plan.
2. Assume 1 day per month for MSVWBE Monthly Reporting.
3. Assume 1/2 day for MSVWBE Reporting.
Sincerely,
Matthew Scarsella
Project Manager
1-07.11 Requirements for Nondiscrimination
(July 18, 2016 APWA GSP, Option C)
Supplement this section with the following:
Voluntary Minority, Small, Veteran and Women's Business Enterprise
(MSVWBE) Participation
General Statement
Voluntary goals for minority, small, veteran and women business enterprises
are included in this Contract. The Contractor is encouraged to utilize
MSVWBEs in accordance with these Specifications, RCW 39.19 and Executive
Order 13-01 (issued by the Governor of Washington on May 10, 2013).
No preference will be included in the evaluation of the Contractor's Proposal or
Bid; no minimum level of MSVWBE participation is required as a condition of
award or completion of the Contract; and a Proposal or Bid will not be rejected
or considered non-responsive on that basis.
The goals are voluntary and outreach efforts to provide MSVWBEs maximum
practicable opportunities are encouraged.
Non-Discrimination
Contractors shall not create barriers to open and fair opportunities for all
businesses, including MSVWBEs, to participate in the Work on this Contract.
This includes the opportunity to compete for subcontracts as sources of
supplies, equipment, construction or services.
The Contractor shall make Voluntary MSVWBE Participation a part of all
subcontracts and agreements entered into as a result of this Contract.
Voluntary MSVWBE Participation Goals
Goals for voluntary MSVWBE participation have been established as a
percentage of Contractor's total Bid amount.
The Contracting Agency has established the following voluntary goals:
Minority 10%
Small 5%
Veteran 5%
Women 6%
Amounts paid to an MSVWBE will be credited to every voluntary goal in which
they are eligible. In other words participation may be credited for participation
in more than one category. If the Contractor is a MSVWBE their Work will be
credited to the voluntary goals in which they are eligible.
Definitions
Minority Business Enterprise (MBE) — A minority owned business
meeting the requirements of RCW 39.19 and WAC 326-20 and certified by
the Washington State Office of Minority & Women's Business Enterprises.
Small Business — A business meeting the Washington State
requirements for a "Small business", "Mini business" or "Microbusiness as
defined in RCW 39.26.010 and included on the WSDOT Office of Equal
Opportunity list of Small Businesses at
http://www.wsdot.wa.gov/equalopportunity/bddirectory.htm
Veteran Business —A veteran owned business meeting the requirements
of RCW 43.60A.010 and included on the WSDOT Office of Equal
Opportunity list of Veteran Businesses at
http://www.wsdot.wa.gov/equalopportunity/bddirectory.htm
Women Business Enterprise (WBE) —A women owned business
meeting the requirements of RCW 39.19 and WAC 326-20 and certified by
the Washington State Office of Minority &Women's Business Enterprises.
MSVWBE Inclusion Plan
A MSVWBE Inclusion Plan shall be submitted to the Engineer prior to the start
of Work on the project. The plan is submitted for the Contracting Agency's
information. Approval of the plan is not required; an incomplete plan will be
returned for correction and resubmittal. The plan shall include the information
identified in the guidelines at
http://www.wsdot.wa.gov/EqualOpportunity/MSVWBE.htm.
MSVWBE Reporting
An end of project Report of Amounts Paid to MSVWBEs shall be submitted to
the Engineer after Physical Completion of the Contract. The end of project
report is due 20 calendar days after the physical completion of the project has
been issued.
The end of project report shall include payments to all eligible businesses
regardless of their listing on the MSVWBE Inclusion Plan. If the Contractor is a
MSVWBE the amounts paid by the Contracting Agency for Work performed by
the Contractor shall also be reported.
MSVWBE Payment
All costs for implementation of the requirements for Voluntary MSVWBE
Participation shall be included in the associated items of Contract Work.
1-08.1 Subcontracting
(May 30, 2019 APWA GSP, Option A)
Prior to any subcontractor or lower tier subcontractor beginning work, the Contractor
shall submit to the Engineer a certification (WSDOT Form 420-004) that a written
agreement between the Contractor and the subcontractor or between the subcontractor
and any lower tier subcontractor has been executed. This certification shall also
guarantee that these subcontract agreements include all the documents required by the
Special Provision Federal Agency Inspection.
A Subcontractor or lower tier Subcontractor will not be permitted to perform any work
under the contract until the following documents have been completed and submitted to
the Engineer:
1. Request to Sublet Work (WSDOT Form 421-012), and
2. Contractor and Subcontractor or Lower Tier Subcontractor Certification for
Federal-aid Projects (WSDOT Form 420-004).
The ninth paragraph, beginning with "On all projects, ..." is revised to read:
The Contractor shall certify to the actual amount received from the Contracting
Agency and amounts paid to all firms that were used as Subcontractors, lower tier
subcontractors, manufacturers, regular dealers, or service providers on the Contract.
This includes all Disadvantaged, Minority, Small, Veteran or Women's Business
Enterprise firms. This Certification shall be submitted to the Engineer on a monthly
basis each month between Execution of the Contract and Physical Completion of the
Contract using the application available at: https://wsdot.diversitycompliance.com. A
monthly report shall be submitted for every month between Execution of the Contract
and Physical Completion regardless of whether payments were made or work
occurred.
EE Sheet No.: 1
ENGINEER'S ESTIMATE
Project Name: S. 228th Phase V Project No: 19-3022C
Item No.: Change Order Date: 10/29/2019
Description of Work: Add DBE administration requirements to contract specifications
Work by Subcontractor?: NO
Prime Contractor: Sub-Contractor:
LABOR
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Office Admin(say 6-8 hrs/mo;
12 mo) 80 50 $ 4,000.00
S -
SUBTOTAL-LABOR: $ 4,000.00
LABOR OVERHEAD&PROFIT @ 29% $ 1,160.00
LABOR TOTAL $ 5,160.00
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs I Hourly Rate Hrs Standby Rate AMOUNT
$
SUBTOTAL-EQUIPMENT $
EQUIPMENT OVERHEAD&PROFIT @ 21% $
EQUIPMENT TOTAL $
_" MATERIALS/SERVICES/RENTALS
MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Misc Supplies 1 LS $ 50.00 S 50.00
S -
S -
$
SUBTOTAL $ 50.00
OVERHEAD&PROFIT @ 21% $ 10.50
TOTAL $ 60.50
TOTAL: $ 5,220.50
12%MARKUP (for prime when
subcontract work) $ -
�✓� ct SHEET TOTAL: $ 5,220.50
Owner's Representative Date
Pay A�t, ate Entered:
Date:
By: