HomeMy WebLinkAboutPW18-335 - Change Order - #3 - Quigg Bros., Inc. - Upper Mill Creek Dam Improvement & Diversion Structure Replacement - 11/13/2019 RecordsManagement
\--1L00004
KENT Sanderson Document
W ASHINGTON
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name : Quigg Bros, Inc.
Vendor Number: 160288
JD Edwards Number
Contract Number: PW18-335
Project Name: Upper Mill Creek Dam Improvements & Diversion Structure Replacement
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 8/21/18 Termination Date: 190 Working Days
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Steve Lincoln Department: PW E-igineering
Contract Amount: $5,951,037.95
Approval Authority: (CIRCLE ONE) Department Director Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #3
As of: 08/27/14
•
KENT
WAS H I N G T O,
CHANGE ORDER NO. #3
NAME OF CONTRACTOR: Ouig_a Brothers, Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER: Upper Mill Creek Dam & Diversion Structure Replacement
ORIGINAL CONTRACT DATE: August 21, 2018
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In additionlo work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Install split casing around watermain due to the incorrect depth shown
on the plans.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $5,951,037.95
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $55,233.75
(incl. applicable WSST)
Current Contract Amount $6,006,271.70
(incl. Previous Change Orders)
Current Change Order $20,000.00
Applicable WSST Tax on this Change $2,000.00
Order
Revised Contract Sum $6,028,271.70
CHANGE ORDER - 1 OF 3
Original Time for Completion 190 working days
(insert date)
Revised Time for Completion under 190 working days
prior Change Orders
(insert date)
Days Required (f) for this Change Order 5 calendar days
Revised Time for Completion 195 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
By: By• _ � o
(signature) (signature)
Print Name: g'b j Z,11.ICt2 Print Name: Timothy J. LaPorte, P.E.
Its P963, CcT 04A' y11C1=e_ Its Public Works Director
(title) itle)
DATE: DATE:
CHANGE ORDER - 2 OF 3
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent City Clerk Kent Law Department
CHANGE ORDER - 3 OF 3
• FILE NO: 200.2
KENT
CHANGE ORDER WORKSHEET NO. 3
Construction Engineering Division — Public Works
Project: Upper Mill Creek Dam Project No.: 09-3030
Project Engineer: Steve Lincoln Fed-Aid No.: N/A
Capital Projects Phil McConnell Contractor: Quigg Brothers
Manager:
Date: 9/23/2019
I. PROPOSED CHANGE
Install Watermain Casing
H. REASON AND BACKGROUND FOR CHANGE
The depth of the watermain shown on the plans was incorrect. Requiring the installation of a
split casing around the watermain. The work performed was identical to the work for bid item
3000, sewer casing. This change order will create a bid item in the appropriate schedule for
billing purposes.
III. METHOD OF PAYMENT
NEW PAY ITEM(S) Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Qty this Unit Unit Price Total Estimated Cost of
Est.Qty PE Item
....
_.._..................... ...;........................................................... ... . ................ ._._...........
2 Watermain Casin 1 1 EA 20 000.00
...... ...,.... ..... .. ........9..........._....__...._............................. .............._......._......... .. .. , . _.. $20,000.00
_......................
.........:........_.__ .. ....................... ................ _ ........ ..........
❑ Independent Estimate Attached ❑ ; CREATE PAY ITEM ONLY - Payment to be made ® PAY THIS PAY ESTIMATE
-REQUIRED at a later date upon completion of work
❑ ........ ........ ._ q _
Material Submittals Reauired - CC: Construction Coordinator New Sub Re rd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. B.I. No Item Description Qty Unit Unit Price Cost of Item
❑ Independent Estimate Attached - REQUIRED ❑
INCREASE/DECREASE TO EXISTING PAY ITEM(S) Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch No B.I. No Item Description Qty ! Unit Unit Price Cost of Item
1 REV. DATE:
3/27/18
KENT• FILE NO: 200.2
a .................. ._...................................._......._.__................._........._...._......_............................................................................................I..........
...........
❑
Independent Estimate Attached - REQUIRED
❑
TOTAL ESTIMATED COST OF CHANGE ORDER * $20 000.00
*Total of the Cost of Item Columns
THIS PAY ESTIMATE $20,000.00
IV. WORKING DAYS
Original Contract 190 Due This Change Order* § Previous Total 190
.......... ...
DATE DATE
�.. ...... .............._. _ ------------
_-----------------------------
.............
._....
_......_...................
-----------._..._.._--------
.
* Ex Ianation Justification Re uired: Additonal work impacted the cricial path
TOTAL WORKING DAYS* 195
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Capital Projects Manager: a Date: — —�.�✓
P i Mc onnel
Construction Engineering / Date:
Supervisor: (��J//CCC L' ��
r'
Paul Kuehne
Construction Manager: yv Date: /
Eric Connor
2 REV. DATE:
3/27/18
Quigg .Bros., Inc.
P.O. BOX 1707•ABERDEEN,WA 98520-0281
PHONE 360-533-1530
FAX 360-532-3449
September 17th, 2019
Phillip McConnell
City Of Kent
220 Fourth Ave South
PO Box 1307
Kent, WA 98032
VIA: E-MaiI Serial Letter 005
Re: Upper Mill Creek Dam
Water Line Casing in 1041"Ave
Mr. McConnell
Quigg Bros. Inc_. will perform the water line casing work in 104t' at the culvert crossing for the
same un' sewer price as the sanitary ser line casing (Bid Item 3000) as this work is identical.
l.uinp S n of S20.000.00`7
c2pj
Please contact me if you have any questions or require any further information at(360) 591-5263.
Sincerely,
QUIGG BROS., INC.
led 7w4ca
Project Manager
tedf@quiggbros.coni
Cell# 360-591-5263