HomeMy WebLinkAboutPW18-473 - Change Order - #5 - Scarsella Bros., Inc. - S 228th St UPRR Grade Separation - Adds WSDOT standard bid item Street Cleaning - 08/26/2019 400**
RecordsManagement
KENO Document
WASH N G T O N
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name : Scarsella Bros., Inc.
Vendor Number: 34547
JD Edwards Number
Contract Number: PW18-473
Project Name: Upper Mill Creek Dam Improvements & Diversion Structure Replacement
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 12/2948 Termination Date: 140 Working Days
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Susanne Smith Department: PW Engineering
Contract Amount: $7,760,955.20
Approval Authority: (CIRCLE ONE) Department Director Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #5
As of: 08/27/14
4eo*�
•
KENT
W A 5 H 1 N G T O N
CHANGE ORDER NO. # 5
NAME OF CONTRACTOR: Scarsella Bros., Inc. ('Contractor")
CONTRACT NAME & PROJECT NUMBER:S. 228th St. UPRR Grade Separation Ground Improvements
& Embankments
ORIGINAL CONTRACT DATE: December 20, 2018
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
This change makes the following revision to the contract documents:
This change order adds the WSDOT standard bid item 'Street Cleaning'
to the contract, as described and per the requirements of Section 8-01
of the WSDOT Standard Specifications which was not included in the
contract.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, 'Compensation," are hereby modified as follows:
Original Contract Sum, $7,760,955.20
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $-25,090.69
(incl. applicable WSST)
Current Contract Amount $7,735,864.51
(incl. Previous Change Orders)
Current Change Order $9,500.00
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum $7,745,364.51
CHANGE ORDER - 1 OF 3
Original Time for Completion 140 working days
(insert date)
Revised Time for Completion under 3
prior Change Orders
(insert date)
Days Required (f) for this Change Order 0 calendar days
Revised Time for Completion 143 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
By: 1r »r By
(signature) (signature)
Print Name: /ylflTl�S/F2✓ .Scy4.z alA Print Name: Timothy J. LaPorte, P.E.
Its i°/ItJ1' /s7AN�f6F,� Its Public Works Director
(title) aitl )
DATE:��//7 DATE: 0�ZG 'ZDI�
CHANGE ORDER - 2 OF 3
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent City Clerk Kent Law Department
[In this field,you may enter the electronic filepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
• FILE NO: 200.2
KENT
w,s I T.�
CHANGE ORDER WORKSHEET NO. 005
Construction Management Division - Public Works
Project S. 2281h St Union Pacific Railroad Project No.: 07-3022
Grade Separation Ground
Improvements and
Embankments
Project Engineer: Cameron Bloomer, PE Fed-Aid No.: HLP-FMSIB-1216 (005)
Owners Rep: KBA, Inc Contractor: Scarsella Bros. Inc.
Date: 8/09/2019
I. PROPOSED CHANGE
This Change makes the following revisions to the Contract Documents:
This change order adds the WSDOT standard bid item 'Street Cleaning' to the contract, as
described and per the requirements of Section 8-01 of the WSDOT Standard Specifications.
II. REASON AND BACKGROUND FOR CHANGE
This WSDOT standard bid item was not included in the contract, and the City determined street
cleaning was needed to help maintain adequate business access and erosion control.
III. METHOD OF PAYMENT
NEW PAY ITEM(S) [:] Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE i item
._.._ ..................--.........................._._.._......_._......._..................---...................._.........--- - --.............. ............. _ ...... . - -- .._...._........-- -- ........_._ ...._...---- -- - -.........................
VII Street Cleanln _......_._.__......_....---......._...._..........._._._.I_......_..._50.._._......._..__....._........_0 HRS 190.00_. _.._ _ 9�500.00
_...._......................_........._...._....9 _..._..... _.... .._.._..._.....__._...-- _ ... ._........._...__........_..._...
---......__ _.... _...... _.......-_.... - ....._..........-__.._........_._.............._.._........_............................
❑ Independent Estimate Attached ❑ CREATE PAY ITEM ONLY- Payment to be made ❑ PAY THIS PAY ESTIMATE
- REQUIRED at a later date upon completion of work
....._.._. .......... ...._..._....................._ _... ............-...--....
.................
_.............
_.... ......__.
ElMaterial Submittals Reauired - CC: Construction Coordinator New Sub Regrd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description City Unit Unit Price Cost of Item
..._ ......... ........ ...... ............ ...... . .. _....... .... _ ..................-
e
............... . .............. _........._ ..... ........_....... .._................... ...... ...-- ....................._.__......_....._
❑ Independent Estimate Attached -REQUIRED ❑
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description Qty Unit Unit Price Cost of Item
1 REV. DATE: 3/15/19
KENT FILE NO: 200.2
.............................. ................._............................................................._..........................._.............---............._..........._................................... ...................._......_..._...............................__............_......__...._..._......._....._._.__._._.....__.._...._...._._..._...
LF I $ $
Independent Estimate Attached - REQUIRED
TOTAL ESTIMATED COST OF CHANGE ORDER * $9,500.00
*Total of the Cost of Item Columns
THIS PAY ESTIMATE 0
IV. WORKING DAYS
Original Contract 140 Due This Change Order* 0 Previous Total 143
-.......................—
....._......_.._.. . .:..........---...........--............................._ ................. ..............._...._.. .--......._........._.......--
DATE: DATE:
__... --......._.._.....__._.. ...._ ._..- ._.._._............_..__... ......._.........__........ __...__....._.............._..... --------------
* Explanation/Justification Reauired: Street Cleaning is not a critical path item, and no change to the working days is being
made.
TOTAL WORKING DAYS* 143
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: Cameron §11oorner Date: 8 9 19 _
Construction Supervisor: �'`' Date:
Construction Manager: �-' �'� Date:
2 REV. DATE: 3/15/19