HomeMy WebLinkAboutPW18-473 - Change Order - #4 - Scarsella Bros., Inc. - S 228th St UPRR Grade Separation - Compensation Due to NEPA Permit Delay - 08/26/2019 40,'0'ownv.. Records Management
KEN O Document
W A S HI N G T N
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name : Scarsella Bros., Inc.
Vendor Number: 34547
JD Edwards Number
Contract Number: PW18-473
Project Name: Upper Mill Creek Dam Improvements & Diversion Structure Replacement
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 12/208 Termination Date: 140 Working Days
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Susanne Smith Department: PW Engineering
Contract Amount: $7,760,955.20
Approval Authority: (CIRCLE ONE) Department Director Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #4
As of: 08/27/14
•
KENT
W A 5 H I N G T O N
CHANGE ORDER NO. # 4
NAME OF CONTRACTOR: Scarsella Bros., Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER:S. 228' St. UPRR Grade Separation Ground Improvements
& Embankments
ORIGINAL CONTRACT DATE: December 20, 2018
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
This change makes the following revision to the contract documents:
Create a bid item to provide compensation to the contractor for
inefficiencies due to NEPA permit delaying the start of work on the
FloForm property.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $7,760,955.20
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $-31,988.52
(incl. applicable WSST)
Current Contract Amount $7,728,966.68
(incl. Previous Change Orders)
Current Change Order $6,897.83
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum $7,735,864.51
CHANGE ORDER - 1 OF 3
Original Time for Completion 140 working days
(insert date)
Revised Time for Completion under 3
prior Change Orders
(insert date)
Days Required (f) for this Change Order 0 calendar days
Revised Time for Completion 143 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
By: By: -
(signature) (signature)
Print Name: ?547Tif�� Spa" Print Name: Timothy J. LaPorte, P.E.
Its ZZ&ZZEcjr MArY&i_ Its Public Works Director
(title) iz/�/
DATE: 8'�/f DATE: �S / Tl�
CHANGE ORDER - 2 OF 3
i
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
V�.
Kent City Clerk Kent Law Department
[In this field,you may enter the electronic filepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
KENT FILE NO: 200.2
CHANGE ORDER WORKSHEET NO. 004
Construction Management Division - Public Works
Project S. 2281h St UPRR Grade Project No.: 07-3022
Separation Phase IV
Project Engineer: Cameron Bloomer, PE Fed-Aid No.: HLP-FMSIB-1216
Owners Rep: KBA, Inc Contractor: Scarsella Bros. Inc.
Date: 8/09/2019
I. PROPOSED CHANGE
This Change makes the following revisions to the Contract Documents:
Create a bid item to provide compensation to the contractor for inefficiencies due to a NEPA
permit delaying the start of work on the FloForm property.
H. REASON AND BACKGROUND FOR CHANGE
The Contractor's project schedule shows work on the FloForm and DWF properties being
performed at the same time, providing enough work for trucks and equipment to be used
efficiently. Before beginning work at FloForm, the City directed the contractor to delay work on
FloForm because the project's NEPA permit did not fully cover the footprint of that work. To
meet the project schedule, work on DWF proceeded. Major equipment is needed to perform the
work at the DWF property, but is not needed all the time and would have been split between
FloForm and DWF if the delay did not occur. This delay also caused the 2 properties to be paved
at different times, requiring an additional mobilization of the paving contractor.
III. METHOD OF PAYMENT
NEW PAY ITEM(S) Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
_... ..............
I NEPA Delays at FloForm 1 l LS $6,897 83 $6,897.83
.........
❑ ! Independent Estimate Attached El ' CREATE PAY ITEM ONLY— Payment to be made j ❑ PAY THIS PAY ESTIMATE
REQUIRED at a later date upon completion of work
Material Submittals Reauired — CC:'construction coordinator New Sub Re rd. No
DELETE EXISTING PAY ITEM(S) per "9.5 ® Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description Qty Unit Unit Price Cost of Item
1 REV. DATE: 3/15/19
KENT FILE NO: 200.2
_......
......................... .................w.a..s...�..�..�_r.. .... ......_..._._..-......_........._....__............................_....................................._...._..._...-..._..............
................................_.._._................................. .................._.......................................................................__..............---- — . .... _........---........1..........
Independent Estimate Attached - REQUIRED Ej
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description Qty Unit Unit Price Cost of Item
Independent Estimate Attached -REQUIRED
TOTAL ESTIMATED COST OF CHANGE ORDER * $6,897.83
*Total of the Cost of Item Columns
THIS PAY ESTIMATE 6,897.83
IV. WORKING DAYS
Original Contract 14� Due This Change Order* 0 Previous Total 143
_.. ................... ... . ........ -....... ___ _......_ ....__..._ _............ .._.
DATE DATE.
* Explanation/Justification Required: Work at FloForm was not shown on the cricital path as was completed while work on the
watermain (critical path) was being performed. Therefore this change did not impact the critical path and no working days are
being added with this change.
S r.,- N.cjo's 3 r q FL Aflb4.D �>Avs .
TOTAL WORKING DAYS* 143
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: Cipmeron Bloomer Date: 8 9 19
e��Y 19
_ 1
Construction Supervisor. Date:
Construction Manager: Date: /< /
2 REV. DATE: 3/15/19
Vftshhigt
AF De � TM�on�«, Change Order - Minor Change
Contract Number Contract Title Federal Aid Number
07-3022 S. 228th St. Union Pacific Railroad Grade Separation Ph 4 HLP-FMSIB-1216(005)
Change Order Number Change Description Date
MCO 003 Conflicts with Existing Utilities during Watermain Installation 7/26/19
Region Project Engineer Phone Number
Prime Contractor/Design-Builder
Scarsella Bros., Inc
0 Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications or the RFP
❑ Change proposed by Contractor/ Design-Builder
Change Description
This Change provides compensation for cost incurred due to conflicts with existing utilities while
installing the watermain.
Time and material efforts were tracked for compensation. Total cost of this change is $8,545.22
Original Contract Amount Current Contract Amount Est. Net Change This C.O. Est. Revised Contract Amount
I
$ 7,760,955.20 $ 7,772,917.35 $ 8,545.22 $ 7,781,562.57
Prime Contractor/Design-Builder
Signature or Method of Concurrence: Date U
Project Engineer's Signature for Execute Date
Distribution: Copy of Change Order Page&Memorandum Page w/Backup-Project Engineer
Copy of ONLY Change Order Page -Prime Contractor/Design-Builder
Copy of Change Order Page&Memorandum Page w/o Backup-Region Construction Office
Original of Change Order Page&Memorandum Page w/Checklist and Approval Documentation-State Construction Office
DOT Form 421-005A EF e Change Order Pa
Revised 12/09 g g
TWO Dentofp atio, Change Order - Minor Change
Contract Number Contract Title Federal Aid Number
07-3022 i S. 228th St. Union Pacific Railroad Grade Separation Ph 4 HLP-FMSIB-1216(005)
Change Order Number Change Description Date
MCO 004 Existing Watermain Casing under RRX 7/31/19
Region Project Engineer — Phone Number
Prime Contractor/Design-Builder
Scarsella Bros., Inc
0 Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications or the RFP
❑Change proposed by Contractor/ Design-Builder
Change Description
This minor change order provides compensation for unforeseen efforts associated with removing
the existing watermain pipe from within the 24" casing to be reused under the RRX, along with
addressing changes necessary to meet casing as-built alignment conditions discovered.
Time and material efforts were tracking for reimbursement using standards markups in 1-09.6.
Total cost for this change is: $13,288.77
-r co 14114 I z,of f.og
Original Contract Amount Current Contract Amount Est. Net Change This C.O. Est. Revised Contract Amount
$ 7,760,955.20 Is, 3G3.1 7,77�, s��.yz
$ 7,781 ,562.57 $ $ 7-,794,-75 -
Prime Contractor/Design-Builder
Signature or Method of Concurrence: Date
Project Engineer's Signature for Execution Date
Distribution: Copy of Change Order Page&Memorandum Page w/Backup-Project Engineer
Copy of ONLY Change Order Page -Prime Contractor/Design-Builder
Copy of Change Order Page&Memorandum Page w/o Backup-Region Construction Office
Original of Change Order Page&Memorandum Page w/Checklist and Approval Documentation-State Construction Office
DOT Form 421-005A EF Change Order Page
Revised 12/09