HomeMy WebLinkAboutPW18-473 - Change Order - #2 - Scarsella Bros., Inc. - S 228th St UPRR Grade Separation - Special Structure Excavation Class A - 08/21/2019 Records
Management
KENT Document
W A S H I N G T O N
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name : Scarsella Bros., Inc.
Vendor Number: 34547
JD Edwards Number
Contract Number: PW18-473
Project Name: Upper Mill Creek Dam Improvements & Diversion Structure Replacement
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 12/20P Termination Date: 140 Working Days
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Susanne Smith Department: PW Engineering
Contract Amount: $7,760,955.20
Approval Authority: (CIRCLE ONE) Department Director Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #2
As of: 08/27/14
V�
•
KENT
W A 5 H I N G T 0 N
CHANGE ORDER NO. # 2
NAME OF CONTRACTOR: Scarsella Bros., Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBERS. 228th St. UPRR Grade Separation Ground Improvements
& Embankments
ORIGINAL CONTRACT DATE: December 20, 2018
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
This change makes the following revision to the contract documents:
Add a new bid item to schedule 10 titled 'Special Structure Excavation,
Class A'. This item pays for excavation and stockpiling of native material
for use as backfill in the structural earth walls. Re-use of this native
material saves the City in hauling and disposal costs.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $7,760,955.20
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $0.00
(incl. applicable WSST)
Current Contract Amount $7,760,955.20
(incl. Previous Change Orders)
Current Change Order $-42,739.00
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum $7,718,216.20
CHANGE ORDER - 1 OF 3
Original Time for Completion 140 working days
(insert date)
Revised Time for Completion under 0
prior Change Orders
(insert date)
Days Required (f) for this Change Order 0 calendar days
Revised Time for Completion 140 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
By: 44A00> E-� By:
(signature) (signature)
Print Name: Name: Timothy 1. LaPorte, P.E.
Its A7427- I Its Public Works Director
(title) we)
DATE: Z IZI9 DATE:T 201 g
CHANGE ORDER - 2 OF 3
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
A
Kent City Clerk Kent Law Department
[In this field,you may enter the electronic filepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
FILE NO: 200.2
KENT
CHANGE ORDER WORKSHEET NO. 002
Construction Management Division - Public Works
Project S. 2281h St Union Pacific Railroad Project No.: 17-3003.2
Grade Separation Ground
Improvements and
Embankments
Project Engineer: Cameron Bloomer, PE Fed-Aid No.: HLP-FMSIB-1216 (005)
Owners Rep: KBA, Inc Contractor: Scarsella Bros, Inc.
Date: 7/22/2019
I. PROPOSED CHANGE
This Change makes the following revisions to the Contract Documents:
Add a new bid item to schedule 10 titled 'Special Structure Excavation, Class A'. This item pays
for excavation and stockpiling of native material for use as backfill in the structural earth walls.
II. REASON AND BACKGROUND FOR CHANGE
The existing native material under the roadway was tested and found to be suitable to re-use
onsite as Gravel Borrow for Structural Earth Wall. The City requested a cost proposal from the
contractor to excavate and stockpile the material onsite instead of hauling offsite and disposing
of it. Re-use of this native material saves the City hauling and disposal costs, totaling an
estimated $45,000. The reduction in hauling also reduces carbon emissions, lowering the
projects carbon footprint.
III. METHOD OF PAYMENT
NEW PAY ITEM(S) Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
__ _.._`_...__.._._.......__ ....... __..._..._..........._....-
10 Special Structure Excavation CY
__._.
$10.00 ,9'�0
Class A i222(, C�
------_._ ..... __. ........._ __
- ._....__....._.._....._.._._.. _......... . 22 2tQ z
— ......
Independent Estimate Attached CREATE PAY ITEM ONLY - Payment to be made PAY THIS PAY ESTIMATE
-REQUIRED at a later date upon comp -completion of work
_..-- .__.... - _. _.....__._ ...._....
.._...._..........
Material Submittals Required - Cc' st Conruction Coordinator New-Sub-- Regrd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Sch No B I No. Item Description Qty Unit Unit Price Cost of Item
_.....:..........._........._......._..-_._,._.__... _......._..._................_........:---------------------.._....._.....
-----...._.._...._.._..__....._..
1 REV. DATE: 3/15/19
KENT FILE NO: 200.2
._...._.................... ro�
..............................._...................._.._...._..........__.............._._._..._..._............._._.._.........__.................................._........._......._................-t--..................................._...._ .
Independent Estimate Attached -REQUIRED
INCREASE/DECREASE TO EXISTING PAY ITEM(S) Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Sch. No. B.I.No. Item Description Qty Unit Unit Price Cost of Item
-?-._....-- ..........
_. _ - __:.........._........_..__..__;..__.... . ..._.............. .....
10 _
10000 Structure Excavation -2000 CY 32.50 -$65,000
Class A Incl. Haul
..........--_................... .........._..._......_............... ......_..._.........._�......_..... .._.._._..- - - ....._...-.-.._.... .._---.............................---------------._. _....._..-------..........._._._..._............._. _............_...................................
_...-----
Independent Estimate Attached - REQUIRED
TOTAL ESTIMATED COST OF CHANGE ORDER * $
*Total of the Cost of Item Columns
THIS PAY ESTIMATE 0
IV. WORKING DAYS
Original Contract 140 Due This Change Order* 0 Previous Total 140
DATE:..__.._.......__.............._......... ......._..._..............._...._...._..._ ._._.._....--..._._..._.._..---.................._......_................-----.._.................._.....—.........__._._...._....w-DATE:._._................................__........................_............__...._......_....................._.._.__....--------------------
*-..._.._...__....... .,._--......_..__...__._..._ ...........—.._...._.....--.._..._....._....---.....---............_.._._....__.....__..._..---.._................_...__...._..._._.._..... _ .....__............_._..._.__............._............_.......
..... - - --
Explanation/Iustification Required: Because hauling of material is not critical path, this change has no time effect and no
days are being added or subtracted with this change.
TOTAL WORKING DAYS* l 140
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: CVneron Blo mer Date: 7/22/19
�3 $
7 AAA
Construction Supervisor: - Date:
i
Construction Manager: / k_ /"�-�ryLri' Date:
2 REV. DATE: 3/15/19
June 18,2019
City of Kent
220 Fourth Avenue South
Kent,WA 98032
Attn: Cameron Bloomer
Field Engineer
KBA, Inc.
RE: 07-3022 228th St. UPRR Phase 5
Special Structure Excavation Cl.A
SCARSELLA BROS. IS PLEASED TO SUBMIT THE FOLLOWING CHANGE ORDER PROPOSAL FOR THIS PROJECT:
ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE BID AMOUNT
NEW Special Structure Excavation Cl.A CY 2,000 S 10.00 $ 20,000.00
10050 Structure Excavation Class A Incl. Haul--Delete 2,000 CY CY 2,000 $ 32.50 $ 65,000.00
TOTAL $ (45,000.00)
NOTES:
1. Assume 2,000 CY of suitable native material for reuse onsite. "Special Structure Excavation Cl.A", per cubic yard,
is payment to excavate and stockpile native material. Material placement will be paid by other bid items.
Sincerely,
Matthew Scarsella
Project Manager