HomeMy WebLinkAboutPW18-473 - Change Order - #1 - Scarsella Bros., Inc. - S 228th St UPRR Grade Separation - Additional Work - 06/21/2019 Records M gemen' t,
KENO Document
WASHINGTON
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name : Scarsella Bros., Inc
Vendor Number: 34547
JD Edwards Number
Contract Number: PW18-473
This is assigned by City Clerk's Office
Project Name: S 22811 St. UPRR Grade Separation Ground Improvements & Embankments
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 12/20/2018 Termination Date: 60 Working Days
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Susanne Smith Department: PW Engineering
Contract Amount: $7,760,955.20
Approval Authority: (CIRCLE ONE) Department Director Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #1
As of: 08/27/14
•
KENT
W A 5 H I N G T O N
CHANGE ORDER NO. # 1
NAME OF CONTRACTOR: Scarsella Bros., Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBERS. 228th St. UPRR Grade Separation Ground Improvements
& Embankments
ORIGINAL CONTRACT DATE: December 20, 2018
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled 'Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
This change makes the following revision to the contract documents:
Contract Drawing 2 of 36: Delete Construction Sequencing Note 2. Due
to a delay in the delivery of the earthquake watermain pipe, the
contractor proposed installing a temporary water connection to the
Pacific Coast Fruit Company property. The temporary connection
allowed the existing watermain to be abandoned, and stone column
work to begin while maintaining water service to the property.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $7,760,955.20
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $0.00
(incl. applicable WSST)
Current Contract Amount $7,760,955.20
(incl. Previous Change Orders)
Current Change Order $0.00
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum $7,760,955.20
CHANGE ORDER - 1 OF 3
Original Time for Completion 140 working days
(insert date)
Revised Time for Completion under 0
prior Change Orders
(insert date)
Days Required (f) for this Change Order 0 calendar days
Revised Time for Completion 140 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
2��a /
By: By:
(signature) (signature)
Print Name: Print Name: Timothy J. LaPorte, P.E.
Its ,�iLoSEq' ..�wyA6E.� Its Public Works Director
(title) Aitle)
DATE: //�//9 DATE: l>,�2_��
CHANGE ORDER - 2 OF 3
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent City ClerkL-01 Kent Law Department
[In this field,you may enter the electronic fileDath where the contract has been saved]
CHANGE ORDER - 3 OF 3
KENT FILE NO: 200.2
CHANGE ORDER WORKSHEET NO. 001
Construction Management Division - Public Works
Project S. 228th St Union Pacific Railroad Project No.: 17-3003.2
Grade Separation Ground
Improvements and
Embankments
Project Engineer: Cameron Bloomer, PE Fed-Aid No.: HLP-FMSIB-1216 (005)
Owners Rep: KBA, Inc Contractor: Scarsella Bros, Inc.
Date: 5/28/2019
I. PROPOSED CHANGE
This Change makes the following revisions to the Contract Documents:
Contract Drawing 2 of 36: Delete Construction Sequencing Note 2.
II. REASON AND BACKGROUND FOR CHANGE
Due to a delay in the delivery of the earthquake watermain pipe, the contractor proposed
installing a temporary water connection to the Pacific Coast Fruit Company property. The
temporary connection allowed the existing watermain to be abandoned, and stone column work
to begin, while maintaining water service to the property. This is a no cost change.
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
Independent Estimate Attached j CREATE PAY ITEM ONLY — Payment to be made PAY THIS PAY ESTIMATE
REQUIRED at a later date upon completion of work
.............................................................................................................._............ ............_....................__......_...
Material Submittals Required — CC. Construction Coordinator New Sub Reqrd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description i Qty Unit Unit Price Cost of Item
.................._.................._............................__....i_...................._............_..........._.................................__._._........._.._..._.__.-_..........5...__._....._............................._............................................................._. ..._................_......_....__.........................._..._....................._............_.
......... ....... _......-.-___.__ ................_...._......................._.-......_.._...._ ..............................................................._...__.......................................
:
El
Independent Estimate Attached - REQUIRED
1 REV. DATE: 3/15/19
KENT FILE NO: 200.2
W-HI.OTO.
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description Oty Unit Unit Price Cost of Item
Independent Estimate Attached - REQUIRED
TOTAL ESTIMATED COST OF CHANGE ORDER * $0
*Total of the Cost of Item Columns
THIS PAY ESTIMATE 0
IV. WORKING DAYS
Original Contract 140 Due This Change Order* 0 Previous Total 140
........ ....... ._..._.........................._........`-`_.......____..._._..._._......_.._.. .i.__T..._.......... ... F..._..........__............. .. ..._........._....__..._�. ........._............._......--............_.......-......-._...__...._....
DATE: DATE:
_...._.. _.._...._..._......__......_......—-...... ---..........__................... ......__._....._........... - -—- -_..._....._....._.._..._..-- --..._............
* Explanation/Justification Required: This Change Order has no effect on the project's critical path. No days are being added
or deleted with this change order.
TOTAL WORKING DAYS* 140
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: Cameron Bloomer Date: 5/28/19
Construction Supervisor: Date:
Construction Manager: ''f/sv��/'��"1 1�td' Date:
2 REV. DATE: 3/15/19
Anderson, Stephanie
From: Cameron Bloomer <cbloomer@kbacm.com>
Sent: Friday, May 31, 2019 10:18 AM
To: Anderson, Stephanie
Subject: FW: 73022 Phase 4 Schedule Update 1
EXTERNAL EMAIL
Hello Stephanie,
Please see below.Sorry for the delay in forwarding.
Thank you,
Cameron Bloomer, PE
C 206.819.7148 1 cbloomer@kbacm.com
KBA, Inc. I Construction Management Specialists I www.kbacm.com
From: Cameron Bloomer
Sent: Friday, May 31, 2019 10:18 AM
To: 'Matthew Scarsella'<matthew.s@SCARSELLABROS.com>
Cc: Barry,Jason <JBarry@kentwa.gov>
Subject: RE: 73022 Phase 4 Schedule Update 1
Hello Matt,
This proposal is accepted.A CO is being processed to officially allow the sequencing change.
Thank you,
Cameron Bloomer, PE
C 206.819.7148 1 cbloomer@kbacm.com
KBA, Inc. I Construction Management Specialists I www.kbacm.com
From: Matthew Scarsella <matthew.s@SCARSELLABROS.com>
Sent:Wednesday, May 8, 2019 3:30 PM
To:Cameron Bloomer<cbloomer@kbacm.com>
Cc: Bryant,Jason<JBryant@kentwa.gov>
Subject: 73022 Phase 4 Schedule Update 1
Cameron,
Attached is Schedule Update 1 for 73022 Phase 4 2281h St. UPRR Grade Separation. SBI requests a No Cost Change Order
to revise the construction sequencing in the Contract. Sheet 2 Note 2 and 3 specify the water main sequence around
the stone column and drilled shaft installation. SBI proposes a temporary water service connection near 17+00 prior to
installation of the stone columns and drilled shafts. Then all earth quake water main will be installed after the drilled
shafts and prior to embankment construction.
1
Thanks,
Matt
Scarsella Bros., Inc.
Matthew Scarsella, P.E. I Project Manager
P.O. Box 68697
Seattle, Washington 98168-0697
o: (253) 872-7173 1 c: (206) 817-2765
matthew.s@scarsellabros.com
2