HomeMy WebLinkAboutCAG2019-184 - Amendment - #4 - Sound Transit - GA0183-17 Federal Way Link Extension Project: Task Order 1 - 05/24/2019 Amendment 4
To
Task Order 1
Agreement GA 0183-17
City Services Agreement Between the City of Kent and Sound Transit for City
Costs Related to Sound Transit Project Review and Permitting
In accordance with Section 19.9 of the Agreement, this Amendment 4 to Task Order 1 is entered into by
and between Sound Transit and the City.
The purpose of this Amendment is to modify: Attachment 3 "Cost Estimate" of Task Order 1. Now,
therefore,the parties agree to amend the Task Order as follows:
1. Attachment 3 "Cost Estimate" is deleted in its entirety and replaced with the attached
Attachment 3 "Cost Estimate".
All other provisions of Task Order 1 shall remain in full force and effect.
This Amendment 4 to Task Order 1 shall be effective as of the date signed by Sound Transit.
Approved Approved
Sound Transit City of Kent
Act,
Signature Signature Z�tRXZf Dl FIC-�-GTCV— IECb.
�-)C c LkAA c/L-
(� t00-G_y t-L�
�y 43 C L�.J ;K•� �i ft c Cm MA—C`C
Print or Type Name, Title Print or Type Name, Title
Date: 5/•Z,4 1 i y Dater ,.
GA 0183-17
Task Order 1 Amendment 4
Task Order 1 Attachment 3
Cost Estimate
Task Hours labor Rate O/H Rate Original Revised
Payment Payment
Schedule Schedule
Task 1.0(TO 1 Ongoing 3,240 $80 Incl. $230,400 $259,200
Sections A, B, C, D) Review and
Coordination
Task 2.0(TO 1 Section Formal 720 $80 Incl. $57,600 $57,600
B.2) Submittal
Review
Subtotal 2,339 $288,000 $316,800
Other Direct Costs $0 $0
(ODCs)
Contingency $28,800 $0
Total Estimated Costs $316,800 $316,800
Task Order 1 Attachment 3