HomeMy WebLinkAboutCAG2019-184 - Amendment - #3 - Sound Transit - GA0183-17 Federal Way Link Extension Project: Task Order 1 - 08/16/2018 Amendment 3
To
Task Order 1
Agreement GA 0183-17
City Services Agreement Between the City of Kent and Sound Transit for City
Costs Related to Sound Transit Project Review and Permitting
In accordance with Section 19.9 of the Agreement, this Amendment 3 to Task Order 1 is entered into by
and between Sound Transit and the City.
The purpose of this Amendment is to modify Attachment 1 "RFP Preparation Scope of Work" and
Attachment 2 "Estimated Schedule"of Task Order 1. Now, therefore,the parties agree to amend the Task
Order as follows:
1. Attachment 1 "RFP Preparation Scope of Work"is deleted in its entirety and replaced with the
attached Attachment 1 "Scope of Work".
2. Attachment 2 "Estimated Schedule" is deleted in its entirety and replaced with the attached
Attachment 2 "Estimated Schedule".
All other provisions of Task Order 1, as previously amended, shall remain in full force and effect.
This Amendment 3 to Task Order 1 shall be effective as of the date signed by Sound Transit.
Approved Approved
Sound Transit City of Kent
Signature Signatu
1
Print or Type Name, Title Print or Type Name,Titl
Date: o, ► ! Date: r ��
PO 164233 GA 0183-17
Task Order 1 Amendment 3
Task Order i Attachment 1—Scope of Work.
A. Proiect Administration.
A.I.Coordination and Communication. The key purpose of coordination and communication
during this phase is to identify and resolve key issues that need to be addressed in the Design-
Build RFP and, upon publication of the RFP to the shortlisted firms,to support Sound Transit's
Design-Build Contractor procurement process. Activities include participating in regularly
scheduled (weekly or bi-weekly as needed) project coordination meetings with Sound Transit
and preparing for and/or following up on key topics to advance resolution of issues for inclusion
in the Project Requirements, Development Agreement,Transit Way Agreement,and other
agreements and plans, as appropriate. Identification and discussion regarding projects and/or
proposals(e.g. utility, public works projects, or private development projects)that present
partnership opportunities or the potential to conflict with Sound Transit's Project is also
included.
Deliverables
• Attend Sound Transit project coordination meetings.
A.2 Management and Administration. The key purpose of this task is to provide accurate and
timely project administration and production of quality work products. This task will be
continuous throughout the duration of this phase and includes the work necessary to set up and
staff the City's participation in meetings and design review, monthly or quarterly invoicing,
monitoring and reporting progress, preparing for future Project phases, and providing overall
project coordination.
Deliverables
• Provide monthly or quarterly invoicing and progress reporting and on-going project
management acitivites.
A.3 Agreements.The key purpose of this task is to provide for timely approval of task orders and
other relevant agreements.
Deliverables
• The City will work with Sound Transit to approve task orders and other agreements as
requested by Sound Transit.
B. Design Review.
B.1. Over-the-Shoulder(OTS Review)—RFP and Agreements. The key purpose of OTS review
during this phase is to ensure that the Project Requirements in the RFP and terms in the
Development Agreement capture City codes and regulations and describe where and how
deviations from codes and regulations may be granted. Close coordination,through the
regularly scheduled meetings referenced in A.1 and additional meetings as needed, will be
necessary to advance,review and communicate design developments with Project team
members and to seek feedback or concurrence from the City.
PO 164233 GA 0183-17
Task Order 1 Amendment 3
Deliverables
Provide input on Project Requirements and Agreements as requested by Sound Transit.
B.2 Over-the-Shoulder(OTS) Review—Design-Build Contractor Coordination. The key purpose
of this task is to involve the City in elements of the developing Design-Build Contractor
proposals(in accordance with procurement processes)to ensure that the design is consistent
with City codes and regulations. Close coordination,through regularly scheduled meetings
referenced in Section A of this Task Order and additional meetings as needed,will be necessary
to advance, review and communicate issues with the City and to seek feedback or concurrence
from the City. The City will be responsible for performing reviews of documents within a
timeframe mutually agreed upon with Sound Transit staff. If for any reason the City requires
additional review time,the City will notify Sound Transit as soon as possible.
Deliverables
• Provide input on plans and documents as requested by Sound Transit to support Design-
Build notice to proceed.
C. Planning and Design Coordination. Includes all Project elements that interface with City codes,
permitting, inspection,etc. Specific areas of focus include:
C.1 Station Access Improvements.The purpose of coordination between the City and Sound
Transit during this phase is to support safe and convenient multi-modal access to the stations.
This will be accomplished through close coordination to develop project requirements for
station access improvements, such as kiss and ride, bus, pedestrian and bicycle facilities. If
needed,this task would be used by the City to provide input into station access improvements
that may be proposed by the Design-Build Contractor.
Deliverables
• Provide input on access improvements proposed by Design-Build Contractor.
C.2 Right of Way(ROW). The purpose of coordination between the City and Sound Transit
during this phase is to ensure that plans in the ROW are consistent with City codes and
regulations.This will include working with Sound Transit to identify and streamline processes for
ROW vacations and dedications, confirm city requirements for ROW easements and facilitate
City approvals as appropriate.
Deliverables
• Agreement on processes for ROW vacations and dedications.
C.3 Joint Projects or Partnerships.The purpose of coordination on joint projects or partnerships,
is to support collaboration on related City projects that Sound Transit may be contributing to as
mitigation or project enhancement,third party projects(private,WSDOT, utility)that require
PO 164233 GA 0183-17
Task Order 1 Amendment 3
Sound Transit-City collaboration, or additional project elements that need to be incorporated
into the Sound Transit Project.
D. Permits and Approvals.
D.1. Establish Permit Process. A key activity during this project phase is to jointly develop a
Preliminary Project Permitting Plan that supports the project schedule and provides the City
with the information and time needed to provide approvals. City and Sound Transit staff will
work together to establish mutually agreeable procedures and to streamline processes where
possible. These processes and procedures will be documented in the Project Requirements
and/or Development Agreement, as appropriate. The Preliminary Project Permitting Plan will
be used by the Design-Build contractor as guidance to develop a Permitting Plan as one of the
earliest critical activities.
Deliverables
• Develop a Preliminary Project Permitting Plan in coordination with Sound Transit.
D.2. Permitting and Inspection Activities. Not Used. Permitting and inspection activities will be
undertaken in a subsequent project phase and addressed through a later task order.
D.3.Staffing Plan. Building on progress to date, including the Perliminary Project Permitting
Plan,the City and ST staff will work together to develop a Staffing Plan that supports the project
schedule and helps inform the level of City staffing needed to meet the schedule.
Deliverables
• Develop a staffing plan to support the Preliminary Permitting Plan and overall Project
schedule.
D.4. Design-Build Procurement Process. City subject matter experts(SMEs) may be requested
by Sound Transit staff to participate in the Design-Build procurement process to ensure that
design proposals are consistent with City codes and regulations. During the RFP Phase city SMEs
may be requested to review/research Alternative Technical Concepts, participate in one-on-one
meetings with proposers and/or review proposals submitted by the shortlisted firms. The key
purpose of this activity is to provide SME support for Sound Transit's Design-Build procurement
process as requested by Sound Transit staff.
Deliverables
• Assist Sound Transit, as requested, by providing information,documentation,or other
assistance to aid Sound Transit in reviewing and/or responding to Design-Build
Contractor qualifications, proposals, RFIs and ATC proposals.
E. Other Work. Not used.
PO 164233 GA 0183-17
Task Order 1 Amendment 3
Task Order Attachment 2: Estimated Schedule.
Task Estimated Start Month Estimated End Month
A.1 Coordination and Communication January 2017 August 2019
A.2 Management and Administration January 2017 August 2019
A.3 Agreements January 2017 August 2019
B.1 OTS Review—RFP and Agreements January 2017 August 2019
B.2 OTS Review—Design-Build Contractor November 2018 August 2019
C.1 Station Access Improvements January 2017 August 2019
C.2 Right-of-Way January 2017 August 2019
C.3 Joint Projects or Partnerships July 2018 August 2019
D.1 Establish Permit Process July 2018 August 2019
D.2 Permitting and Inspection Activities NA NA
D.3 Staffing Plan I July 2018 August 2019
D.4 Design-Build Contractor Selection Process I July 2018 August 2019
PO 164233 GA 0183-17