The purpose of this Amendment is to modify Attachment 2 "Estimated Schedule" of Task Order 1. Now,
therefore, the parties agree to amend the Task Order as follows:
1. Attachment 2 "Estimated Schedule" is deleted in its entirety and replaced with the attached
Attachment 2 "Estimated Schedule".
2, Attachment 3 "Cost Estimate" is deleted in its entirety and replaced with the attached
Attachment 3 "Cost Estimate".
All other provisions of Task Order 1 shall remain in full force and effect.
This Amendment 1 to Task Order 1 shall be effective as of the date signed by Sound Transit,
Approved Approved
Sound Transit City of Kent
Signature Signature
Dan Abernathy, FWLE Executive Project Ben Wolters, Economic and Community
Director, Sound Transit Development Director, City of Kent
Date: ► L �� 1 7 Date: 12' '(�1 ' '
GA 0183-17
Task Order 1 Amendment 1
Task Order Attachment 2:Estimated Schedule.
Task Estimated Start Estimated End
Month Month
A.1. Coordination and Communication January 2017 April 2018
A.2. Management and Administration January 2017 April 2018
A.3 Agreements January 2017 April 2018
8.1. OTS Review January 2017 April 2018
8.2. Formal Submittals November 2017 April 2018
C.1.Station Access W FT January 2017 April 2018
C.2.Transit Oriented Development January 2017 April 2018
C.3. Right-of-Way January 2017 April 2018
C.4.Joint Projects or Partnerships TBD TBD
D.1 Establish Permit Process June 2017 April 2018
D.2. Permitting and Inspection Activities NA NA
�- --- `--�^ -- GA 0183-17
Task Order 1 Amendment 1
Task Order Attachment 3:Cost Estimate.
Contract contingency will be used per Sound Transit discretion and in accordance with signature
authority procedures.
Task _ Hours Labor Rate O/H Rate Total
Ongoing Review
Task 1.0 (TO 1 and
Sections A, B.1, C, Coordination 2,880 _ $80 Incl. m _ $230 400
Formal
Task 2.0 (TO 1 Submittal
Section 8.2} Review 720 $80 Incl. $67,600
Subtotal 3.600 $288.000
Other Direct Costs ODCs} _! $0
Contingency $28,800
Total Estimated Cost
through 4130/2018 316,800
GA 0183-17
Task Order 1 Amendment 1