Vendor Name: Jacobs Engineering Group Inc.
Vendor Number (JDE):
Contract Number (City Clerk): 20-1
Category: -Contract Agreement
Sub-Category (if applicable): Amendment
Project Name: Green River Natural Resource Area South Pump Station
Mayor's signaturE L4111)I01 12/31/20
Contract Execution Date: Termination Date:
Contract Manager: Steve Lincoln Department: PVV. Engineering
Contract Amount: $98,900.00
Budgeted: IV-/] Grant?
Part of NEW Budget: Local: 1-1 State: 1-1 Federal: F-1
Related to a New Position:
Basis for Selection of Contractor? Other
Approval Authority: r_1 Director FV/ Mayor City Council
Other Details: Provide additional design engineering services for the project.
r
KENT
WASHINGTON
AMENDMENT NO. 1
NAME OF CONSULTANT OR VENDOR: Jacobs Engineering Group Inc
CONTRACT NAME & PROJECT NUMBER: Green River Natural Resource Area South Pump
Station
ORIGINAL AGREEMENT DATE: September 24, 2018
This Amendment is made between the City and the above-referenced Consultant or
Vendor and amends the original Agreement and all prior Amendments. All other provisions of
the original Agreement or prior Amendments not inconsistent with this Amendment shall remain
in full force and effect. For valuable consideration and by mutual consent of the parties,
Consultant or Vendor's work is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, the Consultant or Vendor shall:
Provide additional design engineering services for the project.
For a description, see the Consultant's Scope of Work, which is
attached as Exhibit A-1 and incorporated by this reference.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, 'Compensation," are modified as follows:
Original Contract Sum, $327,900.00
including applicable WSST
Net Change by Previous Amendments $0
including applicable WSST
Current Contract Amount $327,900.00
including all previous amendments
Current Amendment Sum $98,900.00
Applicable WSST Tax on this $0
Amendment
Revised Contract Sum $426,800.00
AMENDMENT - 1 OF 2
Original Time for Completion 12/31/19
(insert date)
Revised Time for Completion under n/a
prior Amendments
(insert date)
Add'I Days Required (f) for this 366 calendar days
Amendment
Revised Time for Completion 12/31/20
(insert date)
The Consultant or Vendor accepts all requirements of this Amendment by signing below,
by its signature waives any protest or claim it may have regarding this Amendment, and
acknowledges and accepts that this Amendment constitutes full payment and final settlement of
all claims of any kind or nature arising from or connected with any work either covered or
affected by this Amendment, including, without limitation, claims related to contract time,
contract acceleration, onsite or home office overhead, or lost profits. This Amendment, unless
otherwise provided, does not relieve the Consultant or Vendor from strict compliance with the
guarantee and warranty provisions of the original Agreement.
All acts consistent with the authority of the Agreement, previous Amendments (if any),
and this Amendment, prior to the effective date of this Amendment, are hereby ratified and
affirmed, and the terms of the Agreement, previous Amendments (if any), and this Amendment
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this Amendment, which is binding on the parties of this contract.
IN WITNESS, the parties below have executed this Amendment, which will
become effective on the last date written below.
CONSULTANT/VENDOR: CITY OF KENT:
By: ,., ?ir
(signature) (signature)Print Name: �G'-� Lt' r' - Pme: Dana nature)
It`s_ r'�+.fE�, � ' �,°: �c Its Mayor
(title) J (title)
DATE: A ( `2-c� 2 DATE:
ATTEST: APPROVED AS TO FORM:
(applicable if Mayor's signature required)
vVYv
Kent City Clerk Kent Law Department
Jacobs-GRNRA South PS Amd 3/Uncoln
AMENDMENT - 2 OF 2
Exhibit A-1
AMENDMENT NO. 1
SCOPE OF SERVICES
City of Kent
GRNRA South Stormwater Pump Station
Engineering Design Services
Jacobs Engineering Group Inc.
March 2019
1. SCOPE OF SERVICES
The proposed scope of services to be performed by Jacobs Engineering Group Inc.
(Consultant) for this Amendment No. 1 to the Engineering Design Services for this project
includes the following services:
• Additional project management and administration associated with amendment work
• Design of garage building
• Gravity block wall design
• Design of permanent irrigation system
• Design of alarming and security for garage building
2. ASSUMPTIONS
This scope of services for Amendment No. 1 is based on the following assumptions:
• City will provide information on technical and other preferences for the garage building
within two working days of requests from Consultant.
• Garage building will include the following features and components:
o Standing seam pitched metal roof
o CMU exterior
o False windows (darker CMU blocks)
o Insulation
o Simple ventilation system consisting of fan/blower and louver
o Lighting system
o Convenience outlets
o Thermostat controlled natural gas heater
o Thermostat controlled exhaust fan with manual override
o Single occupant restroom with toilet (standard with tank), sink, and point-of-use
water heater. Restroom will also include small ventilation fan activated with light
switch. Power will be added for the fan, water heater, and lighting.
o A mop station and utility sink (assumed to be adjacent to restroom, with shared
water heater).
March 2019 Page 1 of 5 Jacobs Engineering Croup Inc.
o Internal potable water plumbing to sinks and toilets, floor drains and a connection
to the sanitary sewer system in 64« Avenue South.
o Four roll-up garage doors, with openers and 14-foot minimum door height and 4-
foot edge-to-edge spacing between garage doors
o One personnel access door
• Garage building will not include windows, skylights, or interior rooms/walls, other than a
restroom.
• The irrigation system will be designed as a long-term system, with a hard-wired
controller. Irrigation system will include a new irrigation service and meter and will
feature aboveground perforated piping.
• A new water service providing potable water to the garage will be provided and will
include a yard hydrant and a wall spigot on the exterior of garage.
• A new fire hydrant will be provided within the right-of-way, adjacent to the garage
building.
• Drainage for the garage building will include an oil/water separator, and connection to
the proposed on-site storm drainage system. There will also be floor drains with
connection to the City's sewer system.
• Alarming will be added for the garage building, including access alarms for the roll-up
garage doors and personnel access door, conduits for future smoke and carbon
monoxide detectors, and a security camera system.
• A gravity block wall will be installed north of the proposed generator shelter, to eliminate
the need to provide fill material and grading within the wetland buffer. The wall will likely
be subject to loading from the adjacent generator shelter and will require a geotechnical
evaluation.
• Energy code compliance calculations will not be required for the building, since it will not
be normally occupied.
• City will lead and prepare the submittals of all City permit applications relating to the
garage building. City permitting support from Consultant is not included in this scope of
services.
3. DETAILED SCOPE OF SERVICES ADDED FOR AMENDMENT NO. 1
Below are the identified tasks for this amendment. Before the start of each task, Jacobs will
obtain written or verbal notice to proceed from the City's Project Manager prior to initiating the
additional work associated with this amendment.
Task 100— Project Management
The purpose of this task is to provide oversight and management of the additional work
associated with this amendment.
Activities:
Provide scope and budget contract amendment for additional design and coordination efforts
described below. Provide additional project management associated Amendment No. 1 work,
including managing staff and coordinating with the City. Coordinate additional work with
multiple disciplines including civil/utility, electrical, instrumentation/controls, architectural,
structural, HVAC, plumbing, geotechnical, and landscaping teams. Prepare and process
amendments to current subconsultant agreements.
March 2019 Page 2 of 5 Jacobs Engineering Group Inc.
Deliverables:
The following Deliverables are included in this Task:
• Amendment No. 1 scope and budget.
• Updated schedule identifying significant tasks and anticipated durations.
• Additional status reporting for amendment work.
Task 200—Geotechnical Engineering Services
The purpose of this task is to provide additional geotechnical recommendations associated with
the garage foundation and the gravity block wall. The subcontract with HWA Geosciences, Inc.
will be amended for the work associated with this task.
Activities:
Make recommendations for backfill and foundation requirements for the garage building.
Review proposed gravity block wall, including loading for adjacent generator shelter and
roadway, and make recommendations for any special provisions for wall.
Deliverables:
The following deliverables are included in this Task:
• Amended final geotechnical report previously submitted for the GRNRA South
Stormwater Pump Station project, incorporating recommendations for garage foundation
and gravity block wall (electronic PDF copy).
Task 300— Peer Review and Calculations
No changes.
Task 400 — 50 Percent Design
The purpose of this task is to provide 50% level design drawings of the garage building.
Activities:
Perform structural calculations for garage building and foundation.
Provide 50% level structural and architectural drawings for garage building including the
following sheets:
• Garage Plan Views
• Garage Section Views
• Garage Exterior Elevations
Deliverables:
• Electronic (PDF) version of half-size 50% design drawings (11 x 17-inch). Up to three
new drawing sheets total assumed for this amendment.
Task 500 —90 Percent Design
March 2019 Page 3 of 5 Jacobs Engineering Group Inc.
The purpose of this task is to provide 90% level design drawings, specifications/contract
documents, and OPCC for the work associated with this amendment.
Activities:
The drawings identified in this amendment for the 50% stage will be further progressed and
refined to the 90% design level. Additional drawings and information will include the following:
• Add utility services and fire hydrant to site plan
• Add utility service and fire hydrant details
• Add storm drainage features associated with garage building to grading/drainage and
site plans
• Add indoor plumbing, restroom, and mop station with utility sink.
• Add storm drainage details associated with garage building, including floor drains, and
oil/water separator
• Add gravity block wall plan to grading/drainage and site plans
• Add gravity block wall details
• Structural/architectural detail sheets for garage
• Electrical and lighting plan for garage
• Blowers and ventilation equipment plan and schedule for garage
• Irrigation system plan
• Irrigation system details
Components associated with the garage will be added to the 90% technical specifications and
OPCC.
Deliverables:
• Electronic (PDF) version of half-size 90% design drawings (11 x 17-inch) for the garage
building and site improvements. Six to eight total new drawing sheets assumed for this
amendment.
• Electronic copy (Microsoft Word) of 90% technical specifications, incorporating additional
sections and technical information associated with amendment. Up to four new CSi
specification sections assumed to be added for this amendment.
• Electronic copy (Microsoft Excel) of 90% OPCC, incorporating garage and other
components associated with amendment.
Task 600 — Final Design
The purpose of this task is to finalize the design drawings, specifications, and OPCC for the
added work associated with this amendment.
Deliverables:
• The deliverables will be consistent with the original scope and will incorporate the
additional items associated with this amendment and will advance each of the items
identified in the 90 Percent Design task.
Task 700 — Control System, Instrumentation, SCADA, and Telemetry Design
March 2019 Page 4 of 5 Jacobs Engineering Group Inc.
The purpose of this task is to add alarming and security measures for the proposed garage
building. The subcontract with Systems Interface, Inc. will be amended for the work associated
with this task.
Activities:
Add alarming for four roll-up garage doors, one personnel access door for the garage, fire
alarms, and carbon monoxide detector. Add security cameras with DVR recording for the
garage and the rest of the site. The alarms and security measures will be added to the
drawings and technical specifications at the 90% and final design stages, for incorporation with
the overall design packages.
Deliverables:
• Design input (plans and technical specifications) incorporated to overall Consultant 90%,
and final design packages.
4. PROPOSED SCHEDULE FOR AMENDMENT NO. 1
The following proposed schedule supersedes the schedule for the overall project, incorporating
the amendment work.
Amendment No. 1 notice to proceed from City: April 9, 2019
Submit 50% garage drawings for City review: April 24, 2019
City complete review of 50% garage drawings: May 1, 2019
Complete amended geotechnical report: May 1, 2019
Submit 90% garage design for City review: May 22, 2019
City complete 90% design review: May 29, 2019
Submit final garage design (complete package for bidding) June 12, 2019
END OF SCOPE OF WORK FOR AMENDMENT NO. 1