HomeMy WebLinkAbout942RESOLUTION NO. (~~f~~~~-------
A RESOLUTION of the City of Kent,
Washington, adopting as City Policy, Procedures
for Project Control and Review.
WHEREAS, a Project Control and Review Procedure has
been developed and is contained in the attached Appendix "A• and;
WHEREAS, said Control and Review Procedures have been
reviewed by City council and Council workshop session, NOW,
THEREFORE,
THE CITY COUNCIL OF THE CITY OF KENT, WASHINGTON, DO
HEREBY RESOLVE AS FOLLOWS:
Section 1. The Project Control and Review Procedure is
hereby adopted as official policy of the City of Kent.
PASSED by the City Council
Washington at a regular meeting this
lrf6j_.
ATTEST:
ERK
AS TO FORM:
MIRK, CITY ATTORNEY
of the City of Kent,
7 day of ~-> ..... ' -"<""-=----
APPENDIX A
PROJECT CONTROL AND REVIEW PROCEDURE
I. CONTRACT AWARD
Without special recommendation and approval by the City
council, no contract award will be made on construction
projects unless adequate provisions have been made for cost
overruns. Preferably, funds in the amount of 110 percent of
the bid should be available. Following review with the
Finance Department,
project must submit
the department responsible for a given
a written declaration to the City
Administrator that funds in the required amount are in fact
available. The department will advise the City
Administrator's office if these funds are or are not being
realized.
II. LEVEL OF AUTHORITY
A. Department directors are authorized to approve:
1. Any of the following, in an amount not to exceed
2-1/2 percent of the total contract amount.
a. Contract change orders for:
1. Increase in unit bid item
2. Change in scope
3. Design revision
4. Extra work
5. Force account
b. Quantity overruns
2. cumulative project cost increases up to one-half of
the contingency amount, e.g. ' 105 percent of the
total contract if 110 percent of bid amount is
available.
B. The City Administrator is authorized to approve:
1. Up to 5 percent of the total contract amount for
items identified in A.l. above.
2. cumulative project cost increases up to the full
amount of the contingency (e.g., 110 percent of the
total contract if 110 percent of bid amount is
available).
c. Full City Council review and approval.
The City Council will be notified of any change in scope
on a given project.
though a project may
In addition, when it appears as
exceed the total project budget
plus the contingency, the City Council will be notified
and presented with a complete review of the project
status and alternatives for future funding. At that
time the City Council will establish the financial and
construction parameters for completion of the project
and thereafter all change orders will require City
council approval. This provision shall not be construed
as to require City Council approval of all progress
payments after the new direction for the project is
established.
D. Time of authorization for all the above:
I II.
A.
Approval should be granted by the appropriate level of
authority prior to the work being done, however, to
avoid project delay and for expediency, such prior
approval may be waived provided that written
documentation follows. In no case shall payment be made
until all necessary approval documents are attached to
the payment voucher.
CAPITAL PROJECTS COMMITTEE
Membership: To consist of representatives from the
following departments:
1. Public Works
2. Parks
3. Finance
4. City Administrator
5. Other departments with projects for review.
B. Responsibilities: To meet on a monthly basis to review
the status of each capital project including schedules,
change orders and over-runs. such review shall be in
writing and made available to members of the committee
at the meeting. A verbal report shall accompany the
narrative and should include:
1. A report of project activity which has taken place
since the last report was prepared.
2. A report of the anticipated work for the next month.
IV. REPORTING PROCEDURES OF THE RESPONSIBLE DEPARTMENT
A. Distribute the monthly project narrative to the full
City Council (or its designated committee), with
additional documentation as required.
B. Prepare and submit a financial summary of each project
at the time final project acceptance is being requested
of the City Council.