HomeMy WebLinkAbout1444RESOLUTION NO.
A RESOLUTION of the City Council of the
City of Kent, Washington, adopting the 1996-
2001 Six Year Transportation Improvement
Plan.
WHEREAS, after proper notice, the City Council of the
City of Kent held a public hearing at the regular meeting of the
City Council held at 7:00p.m. on September 19, 1995, to consider
public testimony on the proposed Transportation Improvement Plan
for the City and having considered public testimony to the Plan;
NOW THEREFORE,
THE CITY COUNCIL OF THE CITY OF KENT, WASHINGTON DOES
HEREBY RESOLVE AS FOLLOWS:
Section 1. The 1996 through 2001 Six Year
Transportation Improvement Plan, set forth in the Exhibit A
attached hereto and herewith filed with the City Clerk, is hereby
adopted.
Passed at a regular meeting of the city Council of the
City of Kent, Washington this /9 day of ~JH._"-' , 1995.
Concurred in by the Mayor of the City of Kent, this
,J...o day of c4t1i~,J~"L , 1995.
ATTEST:
BRENDA JACOBER,
l
APPROVED AS TO FORM:
I hereby certify that this is a true and correct copy
of Resolution No. !Lftf tf
of Kent, Washington, the
sixyear.res
, passed by
/9 day
the City Council
of .. d'j21i*vJ'{YL.
of the City
1 1995.
/, . J~;~D~;1o;~R, CITY CLERK (SEAL)
2
TO:
FROM:
SUBJECT:
DEPARTMENT OF PUBLIC WORKS
September 13, 1995
City Council ~
Don Wickstr~, Public Works Director
SIX-YEAR TRANSPORTATION IMPROVEMENT PROGRAM
1996-2001
Each year, the City has been mandated by state law to prepare and adopt a Six-Year Transportation
Improvement Program. Beginning this past year, GMA has required that the City prepare a Capital
Facilities Plan, as well.
Although the Capital Facilities Plan [ CFP ] is now the more critical document from a planning
standpoint; the requirement to prepare a Six-Year Transportation Improvement Program which
matches the CFP, remains.
Earlier this year, the City adopted its Capital Facilities Plan for the 1996 through 2001 time period.
Attached, is the matching Six-Year Transportation Improvement Program for your consideration.
This current Six-Year TIP is very similar to that for previous years that the Council has reviewed
and approved. There are fewer projects identified than in previous years, however, since, as with the
Capital Facilities Plan, only those project which are funded, or capable of being funded, may be
included.
In summary, this Plan programs to spend almost $84,000,000 over the six year period on
transportation improvements and enhancements. Of that total, $61,000,000 is to spent on the City's
Corridor projects, and $17,944,000 for other arterial roadway improvements. $9,588,000 of the
arterial roadway improvement budget is directly related to providing High Occupancy Vehicle lanes
on three important regional corridors [ including the improvements currently under construction on
South 212th Street]. $1,442,000 is programmed to be spent for bicycle and pedestrian facility
projects, and another $1,920,000 is budgeted for upgrading the City's pedestrian facilities --
including compliance with the Americans With Disabilities Act. A cumulative total of $935,000 is
budgeted for pavement rehabilitation upon East Valley Highway, between South 192nd Street and
South 212th Street, and upon South Central Avenue between Willis Street and the Green River
Bridge. Finally, working with METRO, the City has $503,000 ( $419,000 of which is being provided
by the Federal Government] budgeted for the equipment purchase and operation of a Flexible Route
small bus system for the downtown area.
Recommendation: Adopt Six-Year Transportation improvement Program.
EXHIBJl f}
CITY OF KENT, WASHINGTON
SIX-YEAR TRANSPORTATION IMPROVEMENT
PROGRAM
1996-2001
Don E. Wickstrom, P .E.
Director of Public Works
EXHIBIT A
Prepared By:
Transportation Engineering Section
Public Works Department
Edward White, City Transportation Engineer
Kristen Langley, Assistant Transportation Engineer
Assisted By:
Kurt Palowez, Mapping/ GIS Coordinator
1996 to 2001
(Project Costs in Thousands of Dollars)
MPO : PSRC Puget Sound Reg. Council
Agency : Kent
County : King County
I Phase Data
Func Project Imp Total Uti I Start __ Federal --RAP,etc. Local/
Cl Pri Identification Type Length Codes Date Fund Code Cost Code Cost State
City Kent 01 0.000 G C P S T W Funding Secured Revision:
16 1 South 272nd/ 277t~orridor Pro]eCf
So 272nd, So 277th, 116th Ave SE Auburn Way to Kent-Kangley Rd. ( SR 516)
Construct new 5-lane arterial to full urban improvements Construct new 5
PE 8/1995 0 TIA 584 1,316
RW 8/1995 0 TIA 983 2,217
CN 10/1997 0 TIA 6,574 14,826
PROJECT TOTAL 0 8,141 18,359
City Kent 04 0.000 G C P S T W Funding Secured Revision:
16 2 So. 196th/ 200th Sf Corndor-:-wE!st
So 200th St/ Russell Rd/ So 196th St Orillia Road to West Valley Highway
Widen existing roads, Construct new bridge over Green River
PE 8/1995 0 TIA 200 581
RW 10/1995 0 TIA 595 1,724
CN 10/1996 0 TIA 2,410 6,990
PROJECT TOTAL 0 3,205 9,295
City Kent 01 0.000 G C P S T W Funding Secured Revision:
16 3 So. 196th/200th Srcofr1dor --MR:fleg-
So 196th St. West Valley Hwy. to East Valley Road
Construct new bridge over RR tracks, widen existing section of streets
PE 8/1995 0 TIA 716 784
RW 1011995 0 TIA 2,243 2,457
CN 5/1996 0 TIA 7,540 8,260
PROJECT TOTAL 0 10,499 11,501
City Kent 12 0.000 ' c 0 Funding Secured Revision:
00 4 Reith/ Meeker at Kent-Des Moines Road
Reith Road/ Meeker St./ Kent-Des Moines N/A
Widen Reith Road and Meeker St and construct walkways.
PE 111995 STP(U) 3 0 1
CN 10/1995 STP(U) 10 0 43
PROJECT TOTAL 13 0 44
City Kent 04 1.900 G C P S T W Funding Secured Revision:
14 5 South 212th Street HOV Lanes
South 212th Street West Valley Highway to SR 167
Widen roadway to construct HOV lanes, sidewalks, and Class II bicycle facility
PE 111995 0 UATA 304 76
G Gas 0 Other
C Cable TV
6YRTIP.FRX S!W Rev: 2.00 05/08/95 Form Rev Date: 04/26/95
Total
0 PE
RW
CN
Total
1,900
3,200
21,400
26,500
0 PE
RW
CN
Total
781
2,319
9,400
12,500
0 PE
RW
CN
Total
1,500
4,700
15,800
22,000
0 PE
RW
CN
Total
4
53
57
0 PE
RW
CN
Total
380
Hearing Date
Adoption Date
Resolution Number
Page
Expenditure Schedule
(Local Agency Use)
1st 2nd 3rd 4th-6th
1,900 0 0
300 2,900 0
0 4,900 10,000
2,200 7,800 10,000
781 0 0
2,319 0 0
2,900 6,500 0
6,000 6,500 0
1,500 0 0
3,500 1,200 0
2,900 6,800 9,000
7,900 8,000 9,000
4 0 0
0 0 0
53 0 0
57 0 0
380 0 0
250 0 0
3,270 0 0
3,900 0 0
0
0
6,500
6,500
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
MPO
Agency
County
Func
Cl Pri
City
14 5
City
16 6
City
17 7
City
00 8
City
14 9
1996 to 2001
(Project Costs in Thousands of Dollars)
PSRC Puget Sound Reg. Council
Kent
King County
Phase Data
Project Imp Total Uti I Start __ Federal --RAP,etc.
Identification Type Length Codes Date Fund Code Cost Code Cost
Kent 04 1.900 G C P S T W Funding Secured
South 212th StreefRDV Lanes · --
RW 111995 0 0
CN 6/1995 0 UATA 2,616
PROJECT TOTAL 0 2,920
Kent 03 1.250 G C P S T W Funding Secured
East Valley Highway PavemenfRehab.
East Valley Highway ( 84th Avenue So. ) So 192nd St. to So. 212th Street
Remove and replace deteriorated pavement and base material, rehabilitate drainage systems
PE 8/1995 STP(U) 17 0
CN 3/1996 STP(U) 301 0
PROJECT TOTAL 318 0
Kent 12 0.000 -Funding Secured
Russell Rd at Meel<er St TfafflcSigl1al
Russell Road, Meeker Street N/A
Install multi-phase traffic signalization system
PE 8/1995 0 0
RW 12/1995 0 0
CN 5/1996 0 0
PROJECT TOTAL 0 0
Kent 32 0.000 Funding Secured
City-wide Bicycle Improvements
Citywide Citywide
Improve Bicycle and Pedestrian facilties in various locations around the City of Kent
PE 111996 STP(U) 32 0
RW 11 196 0 0
CN 6/1996 STP(U) 312 0
PROJECT TOTAL 344 0
Kent 04 0.290 G C P S T W Subject to Selection
Washington Ave ( SR'rBTTROV [anes
Washington Avenue ( SR 181) Harrison Street to Green River Bridge
Local/
State
Revision:
250
654
980
Revision:
1
191
192
Revision:
10
10
180
200
Revision:
8
0
48
56
Revision:
Widen Washington Avenue to provide HOV lanes north of SR 516, general purpose lanes south of SR 516, and
concrete sidewalks where missing.
PE 8/1995 0 UATA 96 64
GGas 0 Other
C Cable TV
6YRTIP.FRX S/W Rev: 2.00 05/08/95 Form Rev Date· 04/26/95
Total
0 PE
RW
CN
Total
250
3,270
3,900
0 PE
RW
CN
Total
18
492
510
0 PE
RW
CN
Total
10
10
180
200
0 PE
RW
CN
Total
40
0
360
400
0 PE
RW
CN
Total
160
Hearing Date
Adoption Date
Resolution Number
Page
Expenditure Schedule
(Local Agency Use)
1st 2nd 3rd
380 0
250 0
3,270 0
3,900 0
5 0
0 0
505 0
510 0
10 0
10 0
180 0
200 0
10 0
0 0
90 0
100 0
160 0
0 300
0 540
160 840
2
4th-6th
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
I
10 30 I
0 0
90 270
100 300
0 0
0 0
0 0
0 0
1996 to 2001
(Project Costs in Thousands of Dollars)
MPO : PSRC Puget Sound Reg Council
Agency : Kent
County : King County
Phase Data
__ Federal Local/ Func Project Imp Total Util Start --RAP,etc.
Cl Pri Identification Type Length Codes Date Fund Code Cost Code Cost State
City Kent 04 0.290 .G C P S T W 1 Subject to Selection Revision:
14 9 Washington Ave ( SR-181 TRQVlanes
RW 111997 0 UATA 180 120
CN 4/1997 0 UATA 324 216
PROJECT TOTAL 0 600 400
City Kent 04 0.450 G C P S T W Subject to Selection Revision:
14 10 Pacific Highway So.~VTanes
Pacific Highway So. ( SR 99 ) Kent-Des Moines Road to So 252nd Street
Widen Pacific Highway South ( SR 99) to provide HOV lanes, curbs, gutters, sidewalks, and Class II bicycle
facilities
PE 411996 STP 187 TIA 191 88
RW 4/1997 STP 26 TIA 322 152
CN 4/1998 STP 1,037 TIA 1,831 854
PROJECT TOTAL 1,250 2,344 1,094
City Kent 01 0.630 G C T Funding Secured Revision:
16 11 64th Avenue South E.Xfensfon
64th Avenue South So. 216th Street to So. 226th Street
Construct new 5-lane arterial with full urban improvements incl. landscaped median
PE 2/1996 0 0 104
RW 8/1996 0 0 148
CN 5/1997 0 0 1,948
PROJECT TOTAL 0 0 2,200
City Kent 12 0.000 Funding Secured Revision:
16 12 Valley Traffic Signal Coofd1nat1on Proj
West Valley Highway, So. 180th Street SR 516 to So. 180th, SR 181 to SR 515
Optimize signal timing and coordination among Green River Valley jurisdictions
PE 8/1995 0 0 5
PROJECT TOTAL 0 0 5
City Kent 04 0.000 c p T Planning Purposes Revision:
00 13 James Stat Centra!Ave Intersection lmp
James St., Central Avenue N/A
Widen James Street at Central Avenue to provide an exclusive right turn lane for westbound traffic
PE 111997 0 UATA 20 5
G Gas 0 Other
C Cable TV
6YRTIP.FRX SMJ Rev: 2.00 05/08/95 Form Rev Date: 04/26/95
Total
0 PE
RW
CN
Total
300
540
1,000
0 PE
RW
CN
Total
466
500
3,722
4,688
0 PE
RW
CN
Total
104
148
1,948
2,200
0 PE
RW
CN
Total
5
5
0 PE
RW
CN
Total
25
Page
Hearing Date
Adoption Date
Resolution Number
Expenditure Schedule
(Local Agency Use)
1st 2nd 3rd
160 0
0 300
0 540
160 840
466 0
0 500
0 0
466 500
104 0
148 0
0 1,948
252 1,948
5 0
0 0
0 0
5 0
0 25
0 100
0 225
0 350
3
I
4th-6th I
0 0 !
0 0
0 0 I
0 0 !
I
0 0
0 0
3,722 0
3,722 0
0 0
0 0
0 0
0 0
0 01
0 0
0 o I
0 o I
0 0
0 0
0 0
0 0
1996 to 2001
(Project Costs in Thousands of Dollars)
MPO : PSRC Puget Sound Reg. Council
Agency : Kent
County : King County
Phase Data
Func Project Imp Total Uti I Start __ Federal --RAP,etc. Local/
Cl Pri Identification Type Length Codes Date Fund Code Cost Code Cost State Total
City Kent 04 0.000 c p T Planning Purposes Revision: 0
00 13 James St at Centranwe Intersection Imp
RW 411997 0 UATA 80 20 100
CN 6/1997 0 UATA 180 45 225
PROJECT TOTAL 0 280 70 350
City Kent 01 0.000 Funding Secured Revision: 0
00 14 METRO ADA Walkway Program --
Washington Avenue, Smith Street
Construct walkway improvements to support regional transit stops
PE 6/1996 0 10 2 12
CN 10/1996 0 86 22 108
PROJECT TOTAL 0 96 24 120
City Kent 04 0.690 G C P S T W Planning Purposes Revision: 0
16 15 Southeast 256th Street VVK:Iening
SE 256th Street Kent-Kangley Road to 116th Avenue SE
Widen SE 256th Street to 5-lane configuration with full urban improvements and Class II bicycle facility
PE 2/1997 0 UATA 217 217 434
RW 411997 0 UATA 464 464 928
CN 3/1998 0 UATA 769 769 1,538
PROJECT TOTAL 0 1,450 1,450 2,900
City Kent 32 0.000 Funding Secured Revision: 0
00 16 ADA Compliance Program ---rufpa.lrlRehab
Citywide Citywide
Rehabiltate/ repair pedestrian facilities to comply with ADA requirements
PE 8/1995 0 0 24 24
RW 8/1995 0 0 13 13
CN 111996 0 0 206 206
PROJECT TOTAL 0 0 243 243
City Kent 22 0.000 Funding Secured Revision: 0
00 17 Flex./ Intelligent Shuttle Bus Demo PrOj
N/A N/A
Provide shuttle bus running on a combination of fixed-routing with route deviation capability in the Downtown Kent
area.
CN 7/1997 CMAQ 419 0 84 503
--
GGas 0 Other
C Cable TV
6YRTIP.FRX S/W Rev: 2.00 05/08/95 Form Rev Date: 04/26/95
PE
RW
CN
Total
PE
RW
CN
Total
PE
RW
CN
Total
PE
RW
CN
Total
PE
RW
CN
Total
Hearing Date
Adoption Date
Resolution Number
Page
Expenditure Schedule
(Local Agency Use)
1st 2nd 3rd
0 25
0 100
0 225
0 350
12 0
0 0
108 0
120 0
0 434
0 928
0 0
0 1,362
30 30
17 17
253 253
300 300
0 0
0 0
0 503
0 503
4
4th-6th
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
1,538 0
1,538 0
30 90
17 49
253 761
300 900
0 0
0 0
0 0
0 0
1996 to 2001
(Project Costs in Thousands of Dollars)
MPO : PSRC Puget Sound Reg. Council
Agency : Kent
County ~ King County
Phase Data
Func Project Imp Total Util Start __ federal --RAP,etc. Local/
Cl Pri Identification Type Length Codes Date Fund Code Cost Code Cost State Total
"'"' .. ~.;T TOTAL 419 0 84 503
City Kent 12 0.000 Funding Secured Revision: 0
00 18 Neighborhood Traffic-Control Program
Citywide Citywide
Construct minor improvements to local streets to enhance traffic safety
PE 8/1997 0 0 4 4
CN 8/1997 0 0 36 36
PROJECT TOTAL 0 0 40 40
City Kent 32 0.220 Planning Purposes Revision: 0
14 19 Canyon Dr. Bike ana"PeifFacilities
Canyon Drive ( SR 516 ) Alvord Avenue to 94th Avenue South
Construct concrete sidewalk, widen for bike lane, along southerly side of roadway
PE 8/1997 STP(E) 43 0 7 50
CN 6/1997 STP(E) 642 0 100 742
PROJECT TOTAL 685 0 107 792
City Kent 04 0.170 c p T Planning Purposes Revision: 0
16 20 West Meeker StreetWiOeniilg --Pnase I
West Meeker Street SR 516 to East side Green River Bridge
Widen West Meeker Street to 5 lane configuration with full urban improvements
PE 8/1997 BR 150 UATA 150 76 376
RW 1/1998 BR 30 UATA 30 0 60
CN 6/1999 BR 1,000 UATA 716 414 2,130
PROJECT TOTAL 1,180 896 490 2,566
City Kent 06 1.000 Funding Secured Revision: 0
16 21 Central Avenue Pavement RehaJ:JITita.fiOn
Central Avenue Willis Street to Green River Bridge
Reconstruct/ rehabilitate existing pavement deficiencies, reconstruct existing minor drainage structure, selectively
rehabiltate sidewalks
PE 2/1998 STP(U) 15 0 3 18
CN 6/1998 STP(U) 341 0 66 407
PROJECT TOTAL 356 0 69 425
City Kent 01 0.130 G C P S T W ! Funding Secured Revision: 0
17 22 72nd Avenue Sout~ EXIension ---
?2nd Avenue South South 194th St to South 196th Sr
Construct new roadway with full urban improvements
PE 2/1998 0 0 80 80
GGas 0 Other
C Cable TV
6YRTIP.FRX SNJ Rev: 2.00 05/08/95 Form Rev Date: 04/26/95
PE
RW
CN
Total
PE
RW
CN
Total
PE
RW
CN
Total
PE
RW
CN
Total
PE
RW
CN
Total
Hearing Date
Adoption Date
Resolution Number
Page
Expenditure Schedule
(Local Agency Use)
1st 2nd 3rd
0 2
0 0
0 18
0 20
0 50
0 0
0 742
0 792
0 376
0 0
0 0
0 376
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
5
4th-6th
0 2
0 0
0 18
0 20
0 0
0 0
0 0
0 0
0 0
60 0
0 2,130
60 2,130
18 0
0 0
407 0
425 0
80 0
216 0
0 244
296 244
1996 to 2001
{Project Costs in Thousands of Dollars)
MPO : PSRC Puget Sound Reg Council
Agency : Kent
County : King County
Phase Data
Func Project Imp Total Uti I Start __ Federal --RAP,etc. Local/
Cl Pri Identification Type Length Codes Date Fund Code Cost Code Cost State
City Kent 01 0. 130 G C P S T W Funding Secured Revision:
17 22 72nd Avenue Souti1ExtensiOn-
RW 4/1998 0 0 216
CN 10/1999 0 0 244
PROJECT TOTAL 0 0 540
City Kent 05 1.400 G C P S T W Planning Purposes Revision:
16 23 Military Road Wide-ning-----
Military Road Reith Road to Kent-Des Moines Road
Widen Military Road to provide left turn lanes and paved shoulders at selected intersections
PE 2/1998 0 UATA 20 20
CN 8/1998 0 UATA 55 55
PROJECT TOTAL 0 75 75
TOTAL for the Agency of Kent 4,565 30,506 47,518
TOTAL for the County of King County 4,565 30,506 47,518
GRAND TOTAL 4,565 30,506 47,518
G Gas 0 Other
C Cable TV
6YRTIP.FRX SNV Rev: 2.00 05/08/95 Form Rev Date: 04/26/95
Total
0 PE
RW
CN
Total
216
244
540
0 PE
RW
CN
Total
40
110
150
82,589
82,589
82,5891
Hearing Date
Adoption Date
Resolution Number
Page
Expenditure Schedule
{Local Agency Use)
1st 2nd 3rd
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
6
4th-6th
80 0
216 0
0 244
296 244
40 0
0 0
110 0
150 0
I
Project
Number
CITY OF KENT, WASHINGTON
SIX-YEAR TRANSPORTATION IMPROVEMENT PROGRAM
Project Name Page
1 South 272"d/ 277th Street Corridor Project ....................... 7
Auburn Way North to Kent-Kangley Road (State Route 516)
2 South 196th/ 200th Street Corridor Project ....................... 8
Orillia Road to West Valley Highway (State Route 181)
3 South 196thJ 200th Street Corridor Project ....................... 9
West Valley Highway (State Route 181) to East Valley Highway
4 Reith Road/ West Meeker at Kent-Des Moines Road
(State Route 516) Intersection Improvement Project ............ 10
Reith Road/ Meeker Street at Kent-Des Moines Road (State Route 516)
5 South 212th Street High Occupancy Vehicle Lanes Project ........ 11
West Valley Highway (State Route 181) to State Route 167
6 East Valley Highway Pavement Rehabilitation Project ........... 12
South 192nd Street to South 212 1
" Street
7 Russell Road at West Meeker Street Traffic Signal System ....... 13
Russell Road at West Meeker Street
8 Citywide Bicycle and Pedestrian Improvements
Interurban Trail at South 212th Street Signal System ............ 14
Interurban Trail at South 212 1
" Street
9 Washington Avenue (State Route 181) High Occupancy Vehicle
Lanes Project ............................................. 15
Harrison Street to Green River Bridge
10 Pacific Highway South ( State Route 99) High Occupancy
Vehicle Lanes Project ...................................... 16
Kent-Des Moines Road (State Route 516) to South 252nJ Street
11 64th Avenue South Extension Project .......................... 17
South 2161
" Street to South 2261
" Street
12 Green River Valley Traffic Signal Coordination Project .......... 18
West Valley Highway--Kent-Des Moines Road to South 1801
" Street
South 1801
" Street--West Valley Highway to Benson Highway
13 James Street at Central Avenue Intersection Improvement
Project ................................................... 19
James Street at Central Avenue
14 METRO Americans' with Disabilities Act [ ADA ]
Improvements Project ...................................... 20
Washington Avenue (State Route 181 }, Harrison Street, Smith
Street, Lincoln Avenue
15 Southeast 256th Street Widening Project ....................... 21
Kent-Kangley Road (State Route 516) to 1161
" Avenue Southeast
Project
Number
CITY OF KENT, WASHINGTON
SIX-YEAR TRANSPORTATION IMPROVEMENT PROGRAM
Project Name Page
16 Americans' with Disabilities Act Compliance Sidewalk Repair
and Rehabilitation Program Project .......................... 22
Citywide
17 Flexible/ Intelligent Shuttle Bus Demonstration Project .......... 23
Downtown
18 Neighborhood Traffic Control Program ....................... 24
Citywide
19 Canyon Drive Bicycle and Pedestrian Facilities Project .......... 25
Alvord Avenue to 94th Avenue South
20 West Meeker Street Widening Project--Phase I ................ 26
Kent-Des Moines Road (State Route 516) to Green River Bridge
21 Central Avenue Pavement Rehabilitation Project ............... 27
Willis Street to (State Route 516) to Green River Bridge
22 72nd Avenue South Extension Project .......................... 28
South 194'h Street to South 196'h Street
23 Military Road Widening Project ............................. 29
Reith Road to Kent-Des Moines Road (State Route 516)
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded, LID Pending,
TIA, City of Kent, LID
South 272nd/ 277 1h Street Corridor Project
Auburn Way North to Kent-Kangley Road (State Route 516)
Construct a new five-lane roadway from Auburn Way to the Kent-Kangley
Road (State Route 516 ), via South 277th Street, Southeast 274th Street, and
116th Avenue Southeast, including a new bridge over the Green River, and a
modification to the traffic signals at the intersections of South 277th Street and
Auburn Way North and at 116th Avenue Southeast and the Kent-Kangley
Road (State Route 516 ). Project will include the construction of full-width
paving, concrete curbs, gutters and sidewalks, street lighting, storm drainage,
bike paths, landscaping, utilities and appurtenances.
Preliminary Engineering ............ $1,900,000
Right of Way Acquisition ........... $3,200,000
Construction ................... $21,400,000
TOTAL ................... $26,500,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, VAT A --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro"ect No. 1 Pa e-7-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded, LID Pending
South 196th/200th Street Corridor Project
Orillia Road to West Valley Highway (State Route 181)
Construct a new five-lane roadway from Orillia Road to Russell Road, and
widen Russell Road/ South 196th Street to West Valley Highway ( State
Route 181 ), including a new bridge over the Green River, signalization of the
intersection of South 200th Street at Orillia Road, and a modification to the
traffic signal at the intersection of South 196th Street at West Valley Highway.
Project will include the construction of full-width paving, concrete curbs,
gutters and sidewalks, street lighting, storm drainage, bike paths, landscaping,
utilities and appurtenances.
Preliminary Engineering . . . . . . . . . . . . . $781,000
Right of Way Acquisition ........... $2,323,000
Construction ................... $ 9,396,000
TOTAL ................... $12,500,000
TIA, King County, City of Kent, LID
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA
--Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro"ect No.2 Pa e-8-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded, LID Pending
TIA, City of Kent, LID
South 196 1h/ 2001h Street Corridor Project
West Valley Highway (State Route 181) to East Valley Highway
Construct a new five-lane roadway from West Valley Highway to East Valley
Road, including a new bridge over the Union Pacific and the Burlington
Northern Railroads' mainlines; widen South 196th Street between West Valley
Highway and 72nd A venue South, signalization of the intersection of South
196th Street at East Valley Road. Project will include the construction of full-
width paving, bridges, concrete curbs, gutters and sidewalks, street lighting,
storm drainage, bike paths [ from West Valley Highway to the Interurban
Trail ], landscaping, utilities and appurtenances.
Preliminary Engineering ............ $1,500,000
Right of Way Acquisition ........... $4,700,000
Construction ................... $15,800,000
TOTAL ................... $22,000,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA
--Urban Arterial Trust Account [State of Washington]; LID--Local improvement District
Pro· ect No. 3 Pa e-9-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded
STP (U), City of Kent
Reith Road/ W. Meeker Street at Kent-Des Moines Road Intersection
Improvement Project
Widen Reith Road and West Meeker Street from a point 500 feet west of the
Kent-Des Moines Road to the Frager Road. Construct paving, concrete curbs,
gutters and sidewalks, street lighting, storm drainage, bike paths, landscaping,
utilities and appurtenances.
Preliminary Engineering ............... $4,000
Right of Way Acquisition ................ $ -0-
Construction ...................... $53,000
TOTAL ...................... $57,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements,(CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro'ect No.4 Pa e-10-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
South 212 1h Street High Occupancy Vehicle Lanes
West Valley Highway to State Route 167
Widen South 212th Street to provide a pair of High Occupancy Vehicle lanes
from West Valley Highway ( State Route 181 ) to State Route 167, reconstruct
existing sidewalks, provide a ten-foot wide concrete sidewalk/ bicycle path,
and modify the existing traffic signal systems at West Valley Highway, 72nd
Ave. S., 76th/ 77th Ave. S., 84th Ave. S./ East Valley Highway; install
signalization system at the Interurban Trail crossing, and modify the existing
grade crossing protection systems at the Union Pacific and Burlington
Northern Railroad mainlines .
Preliminary Engineering ............. $380,000
Right of Way Acquisition ............ $250,000
Construction .................... $3,270,000
TOTAL .................... $3,900,000
FUNDING SOURCE(S)
Funded, Construction Underway
UATA, City ofKent, LID
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Locallmprovement District
Pro· ect No. 5 Pa e-11 -
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded
STP (U), City of Kent
East Valley Highway Pavement Rehabilitation Project
South 192"d Street to South 212 1h Street
Remove and rehabilitate the existing roadway pavement to add additional
lifespan to the roadway, between South 192nd Street and South 212th Street.
Project will include the removal and replacement of the existing pavement in
the curb ( #2 ) travel lanes in both directions, and a full-width asphaltic
concrete overlay of the entire roadway. Project will also include the selective
replacement of catch basin inlets and aprons, driveways, and curbs and gutters.
Preliminary Engineering .............. $18,000
Right of Way Acquisition ................ $ -0-
Construction ..................... $492,000
TOTAL ..................... $510,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account , UAT A --
Urban Arterial Trust Account [ State of Washington ] ; Ll D --Local Improvement District
Pro· ect No.6 Pa e-12-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded, LID Pending
City of Kent, LID
Russell Road at West Meeker Street Traffic Signal System
Install a multi-phase traffic signalization system at the intersection of Russell
Road at West Meeker Street. Project will include the minor widening on West
Meeker Street and reconstruction of the curb returns on the northerly side of
Meeker Street.
Preliminary Engineering . . . . . . . . . . . . . . $10,000
Right of Way Acquisition ............. $10,000
Construction . . . . . . . . . . . . . . . . . . . . . $180,000
TOTAL . . . . . . . . . . . . . . . . . . . . . $200,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro·ect No.7 Pa e-13-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded
STP (E), City of Kent
Citywide Bicycle and Improvements
Interurban Trail at South 2121h Street Signal System
Install a span-wire signal system to provide safe pedestrian and cyclist access
across South 212th Street at the Interurban Trail. Project to be constructed in
conjunction with the South 212th Street High Occupancy Vehicle Lanes
Project. After 1996, make miscellaneous improvements to the City's Bicycle
Route System.
1996 . 1998-2001
Preliminary Engineering . . . . . . . . . . . . . . $10,000 $40,000
Right of Way Acquisition ................ $ -0-$ -0-
Construction ...................... $90,000 $360,000
TOTAL ..................... $100,000 $400,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Locallmprovement District
Pro·ect No.8 Pa e-14-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
UATA, City ofKent, LID
Washington Avenue (State Route 181) High Occupancy Vehicle Lanes
Project
Harrison Street to Green River Bridge
Widen Washington Avenue (State Route 181) to seven lanes [two general
purpose lanes each direction, one H.O.V. lane in each direction, plus turn
lanes ] from Harrison Street to State Route 516 ( Kent -Des Moines Road ),
and four lanes south to the Green River Bridge, and modify the existing traffic
signal systems at the intersections of Washington Avenue at West Meeker
Street and Kent-Des Moines Road (State Route 516 ). Project will include the
construction of full-width paving, concrete curbs, gutters and sidewalks, street
lighting, storm drainage, bike paths, landscaping, utilities and appurtenances.
Preliminary Engineering . . . . . . . . . . . . . $160,000
Right of Way Acquisition ............ $300,000
Construction $640,000
TOTAL .................... $1,000,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA
--Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro· ect No. 9 Pa e-15-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Pacific Highway South (State Route 99) H.O.V. Lanes
Kent-Des Moines Road (State Route 516) to South 252nd Street
( Southerly City Limits )
Widen Pacific Highway South to provide a pair of High Occupancy Vehicle
lanes from the Kent -Des Moines Road ( State Route 516 ) to South 252nd
Street, reconstruct existing sidewalks, provide a ten-foot wide concrete
sidewalk I bicycle path, and modify the existing traffic signal systems at the
Kent-Des Moines Road, South 240th Street, and at South 252nd Street.
Project will include paving, concrete curbs, gutters, and sidewalks, storm
drainage systems, utilities, landscaping, and appurtenances.
Preliminary Engineering ............. $466,000
Right of Way Acquisition ............ $500,000
Construction .................... $3,772,000
TOTAL .................... $4,688,000
STP (U), TIA, UATA, City ofKent, LID
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Locallmprovement District
Pro· ect No. 10 Pa e-16-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded, LID Pending
City of Kent, LID
64 1h Avenue South Extension Project
South 2161h Street to South 226 1h Street
Construct new five-lane roadway from South 216th Street to South 226th
Street. Project will include the construction of full-width paving, concrete
curbs, gutters, and sidewalks; street lighting, storm drainage, median
improvements, utilities and appurtenances.
Preliminary Engineering . . . . . . . . . . . . . $104,000
Right of Way Acquisition ............ $148,000
Construction .................... $1,948,000
TOTAL .................... $3,900,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; T!A --Transportation Improvement Account , UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro·ect No. 11 Pa e-17-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded, Project Ongoing
City of Kent
Green River Valley Traffic Signal Coordination Project
West Valley Highway--Kent-Des Moines Road to South 180th Street
South 180th Street--West Valley Highway to Benson Highway
Complete the design report for the Inter-agency traffic signal coordination
project involving the Cities of Kent, Tukwila, and Renton, King County, and
the Washington State Department of Transportation. Signal coordination
recommendations to be made for West Valley Highway, from Kent-Des
Moines Road to Interstate 405, and on South 180th Street from West Valley
Highway to Benson Highway ( State Route 515 ), implement the
recommendations, therein, and monitor the net level-of-service improvements.
Administration and Analysis ............ $5,000
Right of Way Acquisition ................ $ -0-
Construction ......................... $ -0-
TOTAL ....................... $5,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation! Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [ State of Washington ]; LID--Local Improvement District
Pro· ect No. 12 Pa e-18-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
UATA, City of Kent
James Street at Central Avenue Intersection Improvement Project
Widen the east leg of the James Street at Central A venue intersection to
provide an exclusive right-tum lane for westbound traffic on James Street, and
modify the existing traffic signalization system. Project will include the
construction of paving, concrete curbs, gutters, and sidewalks; street lighting,
storm drainage, utilities and appurtenances.
Preliminary Engineering .............. $25,000
Right of Way Acquisition ............ $100,000
Construction $225,000
TOTAL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $350,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [ State of Washington ]; LID--Local improvement District
Pro·ect No. 13 Pa e-19-
CITYOFKENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded
METRO, City of Kent
METRO Americans With Disabilities Act Improvements Project
Washington Avenue, Harrison Street, Smith Street, Lincoln Avenue
Construct walkway improvements at various locations to improve disabled-
person access to regional transit facilities. Project will include the construction
of concrete sidewalks, and pedestrian ramps at intersections.
Preliminary Engineering . . . . . . . . . . . . . . $12,000
Right of Way Acquisition ................ $ -0-
Construction . . . . . . . . . . . . . . . . . . . . . $108,000
TOTAL ..................... $120,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TJA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [ State of Washington ]; LID --Local Improvement District
Pro· ect No. 14 Pa e-20-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
UATA, City ofKent, LID
Southeast 256 1h Street Widening Project
Kent-Kangley Road (State Route 516) to 1161h Avenue Southeast
Widen Southeast 256th Street to provide a five-lane roadway, including four
general-purpose travel lanes, a center left-turn lane, and a Class II bicycle
facility, and modify the existing traffic signal systems at the intersections of
SE 256th Street/ Kent-Kangley Road and SE 256th Street/ 116th Avenue
Southeast. Project will include the construction of full-width paving, concrete
curbs, gutters, and sidewalks; street lighting, storm drainage, median
improvements, utilities and appurtenances.
Preliminary Engineering ............. $434,000
Right of Way Acquisition ............ $928,000
Construction .................... $1,538,000
TOTAL .................... $2,900,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro·ect No. 15 Pa e-21 -
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded
City ofKent
Americans With Disabilities Act Compliance Sidewalk Repair
and Rehabilitation Program Project
Reconstruct and repair existing sidewalks and pedestrian ramps, and install
new hard-surfaced sidewalks to implement the requirements of the Federal
Government's Americans With Disabilities Act. Project will include an
inventory of the City's sidewalk/ walkway facilities, identification and
correction of existing deficiencies. Project will include the construction of
concrete curbs, gutters, and sidewalks; minor storm drainage, and
appurtenances.
Preliminary Engineering . . . . . . . . . . . . . $180,000
Right of Way Acquisition ................ $ -0-
Construction .................... $1,620,000
TOTAL .................... $1,800,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; T!A --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro·ect No. 16 Pa e-22-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded
Flexible/ Intelligent Shuttle Bus Demonstration Project
Provide enhanced transit service in the Downtown Kent business area through
the use of a fixed route shuttle service, with demand-responsive routing
capabilities. Service route points to include Aukeen District Court, South King
County Activity Center [ SKCAC ], South King County Regional Justice
Center, and DSHS.
Preliminary Engineering . . . . . . . . . . . . . . . . . $ -0-
Right of Way Acquisition ................ $ -0-
Operation and Equipment Purchase ..... $503,000
TOTAL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $503,000
STP ( CMAQ ), Metro, City of Kent
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro"ect No. 17 Pa e-23-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded
City ofKent
Neighborhood Traffic Control Program
-Citywide-
Construct minor improvements: roadway signage and channelization, sight
distance improvements, etc., in the City's residential neighborhoods to
promote pedestrian and resident safety, divert non-local traffic, and encourage
driver compliance with the existing traffic laws.
Preliminary Engineering ............... $4,000
Right of Way Acquisition ................ $ -0-
Construction . . . . . . . . . . . . . . . . . . . . . . $36,000
TOTAL ...................... $40,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TJA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro·ect No. 18 Pa e-24-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
STP (E), City of Kent
Canyon Drive Bicycle and Pedestrian Facilities Project
Alvord Avenue to 94th Avenue South
Improve Canyon Drive ( State Route 516 ) by extending the ex1stmg
sidewalks along the northerly side of Canyon Drive, and construct new
concrete sidewalks along the southerly side of Canyon Drive, between Alvord
Avenue and 94th Avenue South, and widen the pavement along the southerly
side of the roadway to provide a Class II bicycle facility. Project will include
the construction of paving, concrete curbs, gutters, and sidewalks; street
lighting, minor storm drainage, and appurtenances.
Preliminary Engineering .............. $50,000
Right of Way Acquisition ................ $ -0-
Construction ..................... $742,000
TOTAL . . . . . . . . . . . . . . . . . . . . . $792,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro'ect No. 19 Pa e-25-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
West Meeker Street Widening Project--Phase I
Kent-Des Moines Road (State Route 516) to Green River
Bridge
Widen West Meeker Street to provide a five-lane roadway, including four
general-purpose travel lanes, a center left-tum lane, and a Class II bicycle
facility, and modify the existing traffic signal system at the intersection of
West Meeker Street/ Kent-Des Moines Road, and construct a second, parallel
span to the existing bridge over the Green River. Project will include the
construction of full-width paving, concrete curbs, gutters, and sidewalks; street
lighting, storm drainage, utilities and appurtenances.
Preliminary Engineering . . . . . . . . . . . . . $3 76,000
Right of Way Acquisition ............. $60,000
Construction .................... $2,130,000
TOTAL .................... $2,566,000
STP (BR), UATA, City ofKent
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro·ect No. 20 Pa e-26-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded
STP (U), City of Kent
Central Avenue Pavement Rehabilitation Project
Willis Street (State Route 516) to Green River Bridge
Remove and rehabilitate the existing roadway pavement to add additional
lifespan to the roadway, between Willis Street ( State Route 516) and the
Green River Bridge. Project will include the removal and replacement of the
upper two inches ( 2" ) of the existing pavement in the curb ( #2 ) travel lanes
in both directions, and a full-width asphaltic concrete overlay of the entire
roadway. Project will also include the selective replacement of catch basin
inlets and aprons, driveways, and curbs and gutters.
Preliminary Engineering . . . . . . . . . . . . . . $18,000
Right of Way Acquisition ................ $ -0-
Construction . . . . . . . . . . . . . . . . . . . . . $407,000
TOTAL . . . . . . . . . . . . . . . . . . . . . $425,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro·ect No. 21 Pa e-27-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
Funded, LID Pending
City of Kent, LID
72nct Avenue South Extension Project
South 194 1h Street to South 196 1h Street
Construct new five-lane roadway from South I 94th Street to South I 96th
Street. Project will include the construction of full-width paving, concrete
curbs, gutters, and sidewalks; street lighting, storm drainage, landscaping,
utilities and appurtenances.
Preliminary Engineering .............. $80,000
Right of Way Acquisition ............ $216,000
Construction $244,000
TOTAL ..................... $540,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro· ect No. 22 Pa e-28-
CITY OF KENT, WASHINGTON
SIX YEAR TRANSPORTATION IMPROVEMENT PROGRAM
PROJECT:
DESCRIPTION:
PROJECT COST
SUMMARY:
FUNDING SOURCE(S)
UATA, City of Kent
Military Road Widening Project
Reith Road to Kent-Des Moines Road (State Route 516)
Widen Military Road to provide an interim three-lane roadway, including two
general-purpose travel lanes, and a center left-tum lane, and a Class II bicycle
facility at selected intersections Project will include the construction of
paving, concrete curbs, gutters, and sidewalks; street lighting, utilities and
appurtenances.
Preliminary Engineering .............. $40,000
Right of Way Acquisition ................ $ -0-
Construction ..................... $110,000
TOTAL ..................... $150,000
STP --Surface Transportation Program [Federal], (U) Urban, (C) Statewide Competitive, (BR) Bridge Replacement,
(E) Enhancements, (CMAQ) Congestion Mitigation/ Air Quality; TIA --Transportation Improvement Account, UATA --
Urban Arterial Trust Account [State of Washington]; LID--Local Improvement District
Pro·ect No. 23 Pa e-29-