HomeMy WebLinkAboutCity Council Committees - Public Works/Planning - 11/18/1992 CITY OF KENT
PUBLIC WORKS COMMITTEE
NOVEMBER 18, 1992
PRESENT: JIM WHITE TIM HEYDON
JIM BENNETT NORM ANGELO
PAUL MANN KEN CHATWIN
DON WICKSTROM KEVIN LINDELL
TOM BRUBAKER TIM LA PORTE
GARY GILL TONY MC CARTHY
ED WHITE CYNTHIA STEWART
MR & MRS RUST
Pedestrian Crossing Farrington Court
Jim White stated that he and Paul Mann, along with the Traffic
Engineers, met on-site to review the situation 'and came to the
conclusion that a 4-way stop would be necessary at Kennebeck and a
3-way stop at the bottom of Reiten Rd. Wickstrom explained that
staff would be very uncomfortable with that recommendation; this is
not a residential street with 2,000-3, 000 vehicles per day; this is
a street with 21,000 vehicles per day. The 4 way stop location has
a site distance problem on the westbound direction. Installing
stops there would allow pedestrians to feel "protected" and a
serious injury to a pedestrian could occur. Wickstrom stated his
concern with the volume of traffic and the education of vehicle
drivers to learn of the stop signs. Serious injuries could occur
either to pedestrian or vehicle/driver. Wickstrom said that a
pedestrian signal would be the best operation for the safety
aspect; both for the drivers and pedestrians.
Wickstrom responded to White that there is an unencumbered balance
left in the capital street fund. This pedestrian signal would cost
approximately $56,000 and would be located at Reiten and Jason
Streets. Wickstrom stated this would be a pedestrian activated
signal similar to the one at Reith Rd and West Fenwick Park.
Wickstrom stated that addressing the signal at Reiten would solve
the needs of the residents at Farrington Court going to the Senior
Center. Further discussion followed regarding the number of
pedestrians crossing Jason. Wickstrom stated that if a signal is
provided at Reiten, than essentially we have provided access and
some re-routing would have to be made by the pedestrians.
1
a
White asked if the pedestrian signal could be converted to an auto
activated signal, if this was warranted in the future. Ed White
responded that it could be constructed in such a way that the same
poles and mast arms could be used. Ed White again expressed
concerns regarding the safety element of this situation. However,
he stated that the pedestrian signal would be expensive but from
the liability standpoint with the City, it would be much cheaper.
Wickstrom concurred with this point. Ed then explained the
synchronization of the signal.
Ed responded to Jim White that the installation would take a
minimum of six months. Wickstrom stated that this would need to be
moved to the top of the priority list and other things would have
to shift. Ed clarified that the signal would not benefit the
vehicular traffic coming down Reiten Rd.
Mann stated that he found it difficult to accept the argument for
not installing the 4-way stop signs. Mann feels that the City has
a responsibility to the citizens and if an intersection demands
action in the form of a traffic sign or light it is the City's
responsibility to install same, whatever the consequences may be.
Wickstrom stated that staff is expressing professional opinion of
what has happened in other similar situations and staff is trying
to watch out for the liability of the City. If there is a serious
accident, the City will definitely be involved in a lawsuit.
Wickstrom explained that this is a high volume street and if
something needs to be done, the pedestrian signal is what should be
installed, in order to protect the City's liability. This is a
professional opinion and would protect the pedestrian, the motorist
and the City. Committee unanimously agreed to authorize the
installation of a pedestrian activated signal at Reiten & Jason
Streets.
King County Solid Waste Management
Cynthia Stewart, Assistant Manager of the King County Solid Waste
Division made a presentation on the 1992 Comprehensive Solid Waste
Management Plan. The Comp Plan will be adopted by all the
jurisdictions within King County with the exception of Seattle.
Stewart summarized the briefing packet handed out to the Committee
starting with the waste volumes generated in King County,
indicating that only includes the planning area which does not
include Seattle. In order to develop strategies, the County looked
at what is in the waste stream; the last major waste analysis was
done in 1987. Referring to the packet, Stewart indicated the
comparisons between 187 and 191, explaining that the wood and yard
, waste, glass and paper have declined proportionately. Plastics,
textiles and 'other' have increased. Six categories picked to be
the target of this next phase are paper, wood and yard waste,
plastics, textiles, glass and 'other' . While Seattle was in the
2
a
system, a ratio of about 60% of the waste was generated by the
commercial sector and about 40% by the residentiAl sector. With
Seattle leaving the system, the reverse of that is now happening.
At this time, Stewart explained how the Comp Plan is organized
beginning with background information; relationships between '
jurisdictions; and finally, to the operating environment. The
subsequent chapters are broken down into specific categories of the
waste handling system.
Referring to the packet, Stewart further explained the major
recommendations of the Comp Plan, requesting that staff review the
Draft Plan and recommend comments to King County. Stewart stated
that the Solid Waste Division's recommendation is to coordinate
with all jurisdictions to put out a stronger, more effective
message for the need to reduce waste and consumption.
Stewart went on to discuss the adoption process. Right now they
are in the Public Comment Period noting that the Public Comments
are accepted until November 30th. During December and January the
plan will be edited based on the comments receiv6d.' ' In addition,
the Suburban Cities Association has appointed a Staff Policy Group
to help resolve any issues between Cities and the County.
Susan! Property - 94th & James
Kevin Lindell stated that staff has found a barricade systep which
would be an appropriate solution for this problem. " In concept, it
is identical to the Navy's barricades on aircraft carriers. Cost
is approximately $9000; it can be installed by City personnel.
Literature is forthcoming. Wickstrom stated that the money would
come from the $300, 000 in the Safety Improvements for James Street.
White requested this item be brought back to Committee for review,
after receipt of the literature. White requested that the SusanjIs
are made aware of the proposal to make sure they are in concurrence
with this barricade system.
1993 Engineering Work Program
Referring to the Work Program table, White asked about the 104th &
256th intersection project and inquired if anything is being done
about eastward movement. Wickstrom noted that the design does
address the eastward movement. Wickstrom indicated the high
priority items need to be addressed; those being'-approximately 50
projects for a total of $54,000, 000. These have been' reduced down
from 60+ projects for a total of $88,000,000. Mann stated that the
Watershed Fencing project should be a higher priority since it
deals with the safety of our drinking water.
Wickstrom explained that essentially to do all the requested top
priority projects, 30 FTEs are needed. We have a total of 20
available FTEs to do this work. Technically there is a need for
3
S �
10; however by getting 4 additional FTE's and making the existing
part-time clerical full-time, we can address a significant amount
of this work. When we get into the construction phase, we would
use these same technical people to assist therein. These people
would all be funded from the Street Utility fund. The cost of this
is approximately $199, 000 but since the Street Utility funds go
solely toward financing the corridor projects, the respective
project budgets already included these engineering costs.
Wickstrom explained that we either pay these in-house people to do
the work or hire consultants to do same, which would then double
the cost and could create- budget problems. The money is shown as
project costs such as the $20, 000, 000 for the 272nd Corridor
project and that project cost includes all the engineering costs.
As such, all the money for these people is there within the project
funds which are already budgeted. It is just a matter of pitting
these people on the project and charging those projects.
White noted that he would like the "downtown" removed from downtown
in-city transit project. Also, "downtown" removed from downtown
sidewalks. White stated that in the category of downtown parking,
a recommendation will probably be forthcoming from the Budget
Committee; - that money be put into sidewalks.
Committee unanimously agreed to adopt the Engineering Project
Priority List.
Comment added from Wickstrom was that to get these people, we have
to go thru an advertising and we have some candidates within house
which, if they were the successful candidate, would mean no net
gain. As such, if we get vacancies in house with the existing
people who may qualify for these positions, we would like to be
able to fill those too. The Committee voted that McCarthy and
Wickstrom would work on this issue. Wickstrom added that this
proposal does result in a net reduction in the general fund by
$12, 000. We would transfer one of our existing engineers into our
Drainage Section and fund him out- of the Drainage Utility.
Property Acauisition - Johnson
Wickstrom explained that this i-s the property below the Ramstead
property. An offer has been made to Mrs. Johnson; we haven't got
a response as yet. The property was appraised at $181, 000.
Wickstrom noted that the reason we are looking at it is that it
gives us much better access all along the road; it enhances the
property (Ramstead) we just purchased. Also, the biggest cost of
the corridor project is the fill material. This purchase would
allow us to get an early start on the filling and cutting
operation. The offer was made at'the appraisal price of $181, 000.
If Johnson does accept we can't close and bring back to Council
until after January. If we get an acceptance within 10%, than we
can go right to Council at the next formal Council meeting.
4
Mann said he made a mistake by voting for acquiring the Ramstead
property. Mann stated that if the motion were amonded to insure
that general funds would never be used for this project, than he
would vote for it. Mann strongly expressed his feeling that he did
not want his city taxes going into this project.
Committee unanimously agreed to direct staff to proceed with the
purchase of the Johnson property and allow them to bring it
directly to Council if the acquisition is within 10% of the
appraisal.
North Park Sewer Rebuild: West Hill Storm Drainage; LID 338; and
LID 339
Committee unanimously agreed to accept all of these contracts as
complete.
Garrison Heights; Canterbury Place; Pine Tree Elem nq_tary Bills of
Sale
Committee unanimously agreed to approve all of the above Bills of
Sale.
Adopt a Street Program
Wickstrom explained that REI wanted to take over the cleaning up of
228th Street next to their complex. They want to take care of the
landscaping along 228th and are willing to do so having their own
staff work on company time. They have about $400 to spend on vests
and safety equipment. Wickstrom said they need formal action
before the end of the year.
Ken Chatwin stated that we would follow the State's adopted program
and amend it somewhat, using the City Attorney. REI is willing to
do this at their cost and time. Chatwin proposed at the same time
we get into this same type of program with other organizations.
Committee unanimously agreed to approve the Adopt a Street Program.
Everson Annexation
Wickstrom stated that the City received a lot petition for
annexation of 60 acres in the vicinity of 93rd Ave So and So 222nd
St. , depicting the area on a map.
Committee unanimously agreed to set the public meeting at the
January 5th regularly scheduled Council meeting with the
petitioners.
5
Equipment Rental
Discussion followed with Chief Angelo regarding the vehicle
equipment issue. Angelo stated that if the issue is money, than
with outside funds which have become available, the costs can be
covered for 5 of the 20 vehicles originally requested.
White stated he is in more interested in the dollar figures rather
than the number of vehicles. Angelo noted that 4 of the 5 vehicles
in question are Public Works vehicles that support Fire.
McCarthy stated he would work out the vehicle issue and reconfirmed
that 15 vehicles would be cut, not 20. Committee unanimously
concurred that they were more interested in the money saving rather
than the number of vehicles to be reduced.
6