HomeMy WebLinkAboutCity Council Committees - Operations - 07/13/1989 S
OPERATIONS COMMITTEE MINUTES
July 13 , 1989
COUNCIL MEMBERS PRESENT: Christi Houser
Steve Dowell
STAFF PRESENT: Ed Chow
Jim Hansen
Mike Webby
Tony McCarthy
Lori Brown
Mimi Castillo
Nancy Woo
Priscilla Shea
Alana McIalwain
Charlie Lindsey
Jan Banister
Loralynn Young
Candi Faupell
Teri Mertes
GUESTS PRESENT:
APPROVAL OF VOUCHERS
All claims for the period ending July 13, 1989 in the amount of
$1, 538, 596.48 were approved for payment.
RENEWAL OF CONTRACT FOR WORKER'S COMPENSATION ADMINIQTRATION
Personnel Director Webby addressed the renewal of the city's
workers compensation claims administration service agreement. The
city has managed the self-funded program since July 1979 and Scott
Wetzel Services has provided claim services during that period.
The cost of claim services will be approximately $10,750 which is
contained in the 1989 budget. The city has saved about $875,000
since moving to self-insurance.
Webby requested the city continue their relationship with Scott
Wetzel Services and asked that the Mayor be authorized to sign the
renewal agreement for 1989 . The Committee recommended this request
to the Consent Calendar by a 2-0 vote.
CONTACT WITH SEATTLE KING COUNTY EDC
SEATTLE KING COUNTY EDC
Finance Director McCarthy informed the Committee that the Seattle-
King County EDC has asked the city to sign a service agreement
authorizing the expenditure of $3,235 in 1989 for various services
as detailed in the service agreement. The agreement is for 1989
and quarterly payments have already been made. The funds are
included in the city's EDC budget for this purpose.
Councilmember Dowell questioned the sale of items pledged to the
EDC, which were auctioned off, as to whether the funds received
0
were allocated to the EDC corporation. McCarthy informed the
Committee he would research this issue.
McCarthy asked for the Mayor's signature on the service agreement
and at a future time the city staff will analyze the contract
benefits and propose a 1990 budget recommendation that may include
alternative recommendations. The Committee recommended this
request to Consent Calendar by a vote of 2-0.
UTILITY BILLING SYSTEM RFP UPDATE
Finance Director McCarthy informed the Committee that the Utility
Billing System request for proposal went out last week to 10
vendors. The proposals are due back by 7/31/89 at which time a
staff evaluation will occur and a recommendation will be presented
to the Committee. Funds for this system are already budgeted
within the automation plan budget.
1990 BUDGET PRESENTATIONS
LIBRARY: Librarian Young discussed their 1990 Budget Presentation
with the Committee. She first stated some of the Libraries recent
significant accomplishments and then stated issues impacting the
Library mainly the building of the new library. She is requesting
a reader/printer $9000 due to increase in size of library.
ADMINISTRATION: Executive Assistant McIalwain, Community Events
Coordinator Woo and Public Information Coordinator Castillo
presented the 1990 Budget Presentation for Administration. See
attached list of budget objectives.
CIVIL SERVICE: Candi Faupell presented the 1990 Budget Presentation
for Civil Service to the Committee. She mentioned that the budget
request is up 71% due mainly to increased testing for Fire and
Police. See attached list of objectives.
LID 327 BOND ISSUE UPDATE
Finance Director McCarthy informed the Committee the original
ordinance for LID327 indicated a 10 year assessment payment period
when the proper period was promised to the property owners at 20
years. The bonds had already been sold by Shearson Lehman & Hutton
so they had to go back and resell some bonds with a longer maturity
date and the city had to pay additional compensation to the broker.
The appropriate prepayment period has been held and the bond issue
amount totals $2,296, 074. The bonds will now be 4asu.ed at 7. 68%
instead of 7.55% net interest cost. The higher interest rate is
due to the longer bond interest period. The gross underwriting
spread will go from 20.25 to 24.28 per $1,000 in bonds due to
additional work that needed to be done.