CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name: Scarsella Brothers, Inc
Vendor Number:
JD Edwards Number
Contract Number: PW18-294
This is assigned by City Clerk's Office
Project Name: East Valley Highway Preservation
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
D �
Contract Effective Date: _7/18/2018 Termination Date: 60 working Days
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Carla Maloney Department: PW Enaineerino
Contract Amount: $2,247,843.75
Approval Authority: (CIRCLE ONE)'-.Department_Directorr. Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #3
As of: 08/27/14
V
Wnrinuiuii
CHANGE ORDER NO. #3
NAME OF CONTRACTOR: Scarsella Bros. Inc ("Contractor")
CONTRACT NAME & PROJECT NUMBER: East Valley Highway Preservation Preservation
ORIGINAL CONTRACT DATE: Jul�,17,2018
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Add 12 working days to the contract time for completion, section 1-08.5
of the contract, extending the time for physical completion to 72 working
days due to the 302 local operators union going on strike August 21,
2018 through September 7, 2018.
2. The contract amount and time for performance provisions of Section fI "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
.........................................
Original Contract Sum, $2,247,843.75
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $-5,000.00
(incl. applicable WSST)
Current Contract Amount $2,242,843.75
(incl. Previous Change Orders)
Current Change Order $0.00
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum _ $2,242,843.75
CHANGE ORDER - 1 OF 3
__._.........._.._ ............_._..........._.
Original Time for Completion 60 working days
(insert date)
Revised Time for Completion under 0
prior Change Orders
(insert date)
Days Required (t) for this Change Order 12 working days
Revised Time for Completion 72 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
..............
CONTRACTOR; CITY KENT:
By: By
nature) (stgri..ture).
Print Name: Print Name: Timothv J. LaPorte. P.E.
Its 1r Its Public Works Director
(title)
DATE: _ DATE: i b A'
CHANGE ORDER - 2 OF 3
...............____._............... ............. .........._..............._....._..._............ .............—...............
..._
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
[In this field,YOU may enter the electronic f lepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
•�,w�T FILE NO: 200.2
KEN
CHIANGE ORDER WORKSHEET NO. 003
Construction Management Division - Public Works
Project: East Valley Highway Preservation Project No.: 17-3003.2
S. 180" St. to S. 196`h St
Project Engineer: Cameron Bloomer, PE Fed-Aid No.: STPUL-1073 (005)
Owners Reo: KBA, Inc Contractor: Scarsella Bros. Inc.
Date: 10/24/2018
I. PROPOSED CHANGE
This Change makes the following revisions to the Contract Documents:
Add 12 working days to the contract Time for Completion, Section 1-08.5 of the Contract,
extending the time for Physical Completion to 72 working days.
II. REASON AND BACKGROUND FOR CHANGE
The 302 local operators union went on strike on Tuesday, August 21, 2018. The strike ended on
September 7, 2018, 12 working days after the strike began. WSDOT Standard Specification
Section 1-08.8 states the authorized time for Physical Completion will be extended in the event
of a delay of work due to strikes. The work on this project was delayed for the full duration of
the strike. This is a no cost change.
III. METHOD OF PAYMENT
NEW PAY ITENI(S) ® Not Applicable
Change Order No. - I IFOR ACCOUNTING USE ONLY
—— ----- ---
Sch. No. Item Description Total Est '.. Qty this Unit Unit Price ` Total Estimated Cost of
Qty PE Item
Independent Estimate Attached R ATE LAY TIEM QNLY — Payment to be made PAY THIS PAY ESTIMATE
-REQUIRED i at a later date upon completion of work i
ElN ri .til ... . u n r r New Sub Regrd? I No -._...
DELETE EXISTING PAY ITENI(S) per 1-09.5 Z Not Applicable
Change Order No. _ J FOR ACCOUNTING USE ONLY
Sch. No. B 1 No Item Description Qty Unit Unit Price Cost of Item
Independent Estimate Attached - REQUIRED _- w--
1 REV. DATE:4/01/10
FILE NO: 200.2
KE�41T
INCREASE/DECREASE TO EXISTING PAY ITEM(S) M Not Applicable
Change Order No. _ 1 FOR ACCOUNTING USE ONLY
Sch No B.I.No ,) Item Description Oty i Unit Unit Price Cost of Item
'',-Independent Estimate Attached - REQUIRED
TOTAL ESTIMATED COST OF CHANGE ORDER * O
*Total of the Cost of Item Columns
THIS PAY ESTIMATE 0
IV. WORKING DAYS
Original Contract 60 Due This Change Order* 12 Previous Total 60
.DATE: _.. ,.
* Ex2lanatieI313u,5tification • This Change Order has no effect on the project's critical path. No days are being added
or deleted with this change order.
TOTAL WORKING DAYS* 72
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
e
Prepared By:
Construction Supervisor: , �� , Date: P ?y
Construction Manager: Date: n r
2 REV. DATE: 4/01/10
Heavy-Highway a
Construction s i An Equal
a
4
Oppopum l
gp F Employer
w .
August 28, 2018
City of Kent
Public Works Department
400 West Gowe
Kent, WA 98032
Attention: Mr. Eric Connor, Construction Engineering Manager
Mr. Cameron Bloomer, P.E.
Reference: Contract#17-3003.2/ STPUI:1073(005)
East Valley Highway Preservation
S. 1801h St. to S. 19611 St.
Request for Extension of Time
Dear Mr. Connor& Mr. Bloomer:
In accordance with Section 1-08.8 Scarsella Bros., Inc. is requesting an extension of time
due to the strike by International Union of Operating Engineers Local 302. The strike
began on August 21"t, 2018 and is ongoing.
The strike has impacted the sidewalk and curb ramp demolition which are critical items
of work. Scarsella had initially planned to perform the saw cutting in preparation for the
demolition but decided that there was no benefit to the project in doing so. The strike is
ongoing so the total impact to the critical path cannot be determined at this time.
Should you have any additional questions or concerns, please do not hesitate to gall.
Sincerely,
Michael Wilson
Project Manager
P.O.Box 68697 • Seattle,Washington 98168-0697 • Tel: (253) 972-7173 • Fax: (253) 395-1209
AK Lie #34714 • AZ Lie. #ROC249216 • CA Lie #779354 • ID Lie. #10394-Unlimited-L-2
Nrr Lie 0146627 • ND Lic.#44607 - OR Lie#96884 • UT Lie.#7646 9 1 7-5 55 1 • WA Lic#SCARSBI L83BS
WEEKLY STATEMENT OF
CONSTRUCTION WORKING DAYS
MANAGEMENT
Pro ect: East Valtlaly tli8hwa V Preservation S-18111 7ttr to 5.19&: ;Stal'Cmr+nt NO 7
Owner: City of Kent Week Ending; 9/29/2018
Contractor. Scarsella Bros. Date Pfeoared: 4/28/2019
Project Noj 17-3003.2 Fed Aid No: sTPut 1073 (oos)
The tollomirig statement shows the number of croaking days charged to the Contract for the week indicated.
Comment.
Working Day (DescPbe reasmi(ornomworkin[gdeyorpadialday-
Date i Day (0,0.5, or 1.0) type o(wealher,holiday suparosion,etc,)
9/23/2018 Sunday
9/24/2018 Monday 1
9/25/2018 Tuesday 1
9/26/2018 Wednesday 1
9/27/2018 Thursday 1.
9/28/2018 Friday 1
9/29/2018 Saturday
Working days charged this week: 5
Working days previously reported (from previous report): 28
Total working days to date.- 33
Starting date specified in Notice to Proceed, 8/15/2018
.Working days specified in contract: 60
Change Order Days Granted: 0
Current Contract Working Days: 60
Contract Completion Date -Estimated: 11/7/18
Work days remaining to complete contract: 27
Remarks:
No Work Performed
(Owner Representaiwe's PoWoo hYarne;i sfgnWare Dale
(Contractor Representetive'S Pnoted Name) signature Date
Copies to: Contractor(hard copy&PDF)
Project File(hard copy&POF)
Owner(POF)