CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name: Scarsella Brothers Inc.
Vendor Number:
JD Edwards Number
Contract Number: PW18-312 - 0o3
This is assigned by City Clerk's Office
Project Name: Downey and Naden Clearing and Grading
Description: ❑ Interlocal Agreement M Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 8/1/2018 Termination Date: 35 Working Days
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Thomas Levrer Department: PW Engineering
Contract Amount: $857,754.81
Approval Authority: (CIRCLE ONE) Department Director Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #2
As of: 08/27/14
`' +�K EN*Ti
wA�„i ,r.r�,.
CHANGE ORDER NO. # 2
NAME OF CONTRACTOR: Scarsella Bros. Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER: Downev and Naden Clearing and Grading
ORIGINAL CONTRACT DATE; August 1, 2018
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add
additional work or revise existing work as follows:
In addition to work required under the original Agreement and any prior
Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
This change order removes an additional 36,000 cubic yards of soil from
the Downey Farmstead site and places it at Naden site. King County
Flood Control District has made available additional King County
Cooperative Watershed Management grant in the amount of $780,000
to perform this additional work.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Ori inal Contract Sum,
$857,754.81
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $21,030.68
(incl. applicable WSST)
Current Contract Amount $878,785.49
(incl. Previous Change Orders)
....._........._ ._........
_._._
Current Change Order $720335.00
......._..... ...............
Applicable WSST Tax on this Change $72,033.50
Order
Revised Contract Sum $1,671,153.99
CHANGE ORDER - 1 OF 3
Original Time for Completion 35 working days
(insert date)
— ..._.............................
Revised Time for Completion under 0
prior Change Orders
(insert date)
— __.v_............._......_
Days Required (f) for this Change Order 20 calendar days
..................................... --
Revised Time for Completion 55 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order, including,
without limitation, claims related to contract time, contract acceleration, onsite or home office
overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the
Contractor from strict compliance with the guarantee and warranty provisions of the original
contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order
shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this project
to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
..................................
__w
CONTRACTOR: CITY OF KENT:
By. J A2f , By
(signature) (signature)
Print Name: rtvv-) I(x_ Print Name: Dana Ralph
Its w ice, Rre6i de ii Its Mayor
(title) (title)
DATE: i0.L1-Ifs DATE to 11 1
CHANGE ORDER - 2 OF 3
.._......._........................................... .......................................................
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
Mayor[In mis field,you may enter the electronic filepatn where the contract has been saved[
CHANGE ORDER - 3 OF 3
TT FILE NO: 200.2
CHANGE ORDER WORKSHEET NO. 2
Construction Engineerin Dlwslon — Public Works
Project: Downey/Naden Clearing&Grading Project No.: 18-3007.1
Project Engineer: Thomas Leyrer Fed-Aid No.:
Capital Projects Paul Kuehne Contractor: Scarsella Bros.
Manager:
Date: 9/25/2018
I. PROPOSED CHANGE
This change removes an additional 36,000 cubic yards of soil from the Downey Farmstead site
and places it at the Naden site.
II. REASON AND BACKGROUND FOR CHANGE
The Downey excavation is part of a habitat enhancement project to create a new Green River
side channel. King County Flood Control District has made available additional King County
Cooperative Watershed Management Grant in the amount of $780,000 to performing this
additional work. Naden proves to be a less expensive alternative to other soil dump sites.
III. METHOD OF PAYMENT
All Costs For This Change Are Paid Via Increases To Bid Item Quantities. See
Attached Revised Bid Tab Quantities Spreadsheet.
TOTAL ESTIMATED COST OF CHANGE ORDER
W*Total of the Cost of Item Columns
THIS PAY ESTIMATE 0
IV. WORKING DAYS
Original Contract 35 Due This Change Order* 20 Previous Total 35
TOTAL WORKING DAYS* 55
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
1 REV. DATE;
3/27/18
NT FILE NO: 200.2
KE
Capital Projects Manager: Date:
Construction Engineering Date:
Supervisor: ��� ✓�Q
Construction Manager: Date:
2 REV. DATE;
3/27/18
1 �
Downey and Naden Clearing and Grading CHANGE ORDERS Scarsella Brothers,Inc.
ITEM UNIT ORIGINAL CONTRACT CHANGE ORDER IINCREASE NEW CONTRACT TOTALS
NO. _ DESCR2PTION PRICE OUANTITY AMOUNT QUANTITY AMOUNT QUANTITY AMOUNT
SCHEDULE B(ALTERNATE): EARTHWORK-DOWNEY
2000 Mobilization 28,500.U0i 1 LS $ 28,500 LS $ 1 LS , 00
2005 Clearing &Grading 4,UQ(D0.(7R 1 IS ; 44,000 LS $ 1 IS $ 44 99,0o0
2007 Salvage Trees 100,00 200 EA $ 20,000 EA $ 200 EA s 20,000
2009 Remove&Chip Trees 100.00 250 EA $ 25,000 EA 0 EA ; 25,000
2011 Excavation,Including Haul&Compaction 1760 19,000 BCY g 334,400 36,000 BCY $ 633,600 55,00000 BCY $ 9686B,DDD
2012 Excavation&Haul of Unsuitable Material 23,30 1,000 BCY $ 23,300 BCY $ 1,000 BCY $ 23,300
2013 Aeration 40,000.00 1 FA $ 40,000 1 FA $ 40,000 2 FA $ 60,000
2015 Removal of Debris is Garbage 100.001 30U CY $, 30,000 CY $ 300 CY $ 30,000
2018 Remove&Relocate Cement Concrete Jersey Barrier 125.00 25 EA J; 3,125 EA $, 25 EA a 3,125
2025 Water 0,01.' 500 MEAL $ 5 MGAL 5 500 MGAL $ 5
2055 Minor Changes 15,000.00 1 CALC $. 15,000 CALC t. 1 CALC $ 15,000
2060 Health&Safety Plan 1,750.00 1 IS $ 1,750 LS $ 1 LS & 1,750
2065 Traffic Control Labor 59.75 200 HIS A 11,950 100 HR $ 5,975 300 HR $ 17,925
2070 Construction Signs Class A 20.00 100 SF $ 2,000 SF $, 150 SF $' 2,(153
2080 Traffic Control Supervisor 67.75 301 LS $. fi,500 50 HR $ 3,260 152 I S $ 10 760
2080 Temporary Traffic Control Devices 500,0r1 1 LS $ SDD 0.52 ITS
y. 260 14.7 S g, 760
2095 Seeding, Fertilizing, &Mulching 1,570..00 14.7 AC g 23,079 AC ; 19.7 AC g, 23,m9
2100 Filter Fabric Fence 5,0Q 2,600 IF $ 13,000 LF $ 2,600 IF $ 13,000
2115 ESC Lead 75,0D 60 HR $ 4,500 HE
2120 Street Cleaning 0.01 320 HR $ 3 160 HR $ 2- 8060 HR 5 4,50 5
0 HR $.. 5
2125 Stabilized Construction Entrance 16.00 400 SY ; 7,200 ' 400 SY $ 7,200 '' 800 SY 5. 14,400
2130 SPCC Plan 500,00 1 LS $ 500 IS 5 1 ITS $ 00
2135 Erasion/Water Pollute in Control 15,000.00 1 FA S 15,000 FA 9 1 FA ; 15,0000
SCHEDULE B TOTAL $ 649,587 $ 690,424 $ 1,340,011
SCHEDULE C(ALTERNATE): NADEN SITE IMPROVEMENTS
3000 Mobilization 10,000n0 1 IS % 10,CDO IS $ 1 IS $ 10,000
3005 Naden Site Clearing&Grubbing 20,000.00 1 LS $ 20,000 LS $ 1 IS 5 20,000
3008 Salvage Evergreen Trees with Rootvads from Nader 500,00 12 EA 1 6,000 1 EA $ Soo 13 EA $ 6,500
3015 Removal of Debris&Garbage 100,(IO. 100 CY $ 10,000 100 CY $ 10,000 200 CY $ 20,000
3020 Remove Cement Concrete Sidewalk 20.00, 10 SY $ 200 SY $ 10 SY 5 200
3025 Water 0.01'' 500 MGAL $ 5 MGAL $ 500 MGAL 9 5
3055 Minor Changes 10,000,00 1 CALC $ 10,000 CALC $ 1 CALC $ 10,000
3060 Naden Heath&Safety Plan 1,750.00 1 IS $. 1,750 IS $ 1 LS $ 1,750
3065 Traffic Control Labor 59.75 100 HR $ 5,975 50 HR $ 2,9B8 150 HR
S 8,963
3070 Construction Signs Class A 20.00 100 SF $ 2,000 SF g 100 SF B 2,000000
3075 Traffic Control Supervisor 67,75 50 HR 5 3,388 30 HR $ 2,033 00 HR $ 5,420
3060 Temporary Traffic Control Devices 500 on 1 IS 500 LS500
$ 1 LS 5 775
3095 Seeding, Fertilizing,&Mulching 1,5Y0,DU 4.5 AC $ 7,065 3 AC $ 4,]10 ]5 AC �$ 11,]75
3100 Filter Fabric Fence 5-0Q: 1,700 LF S 8,500 1,000 IF $ 5,000 2,700 LF S 13,500
3115 ESC Lead 75,00 60 HR § 4,500 HR $ 60 HR $ 4,500
3120 Street Cleaning 0.01 240 HR 5 2 120 HR $ 1 360 HR $, 4
3125 Stabilized Construction Entrance 18.00 260 SY $ 4,680 260 SY $ 4,680 520 SY $ 9,360
313C SPEC Plan 500.00 1 LS $ 500 LS $ 1 IS $ Soo
3135 Erosion/Water Pollution Control I5,000.0Q 1 FA $ 15,000 FA $ 1 FA $ 15,000
3200 Inlet Protection 125.00 10 EA $ 1,250 EA $ 10 EA $, 1,250
3205 Sediment Pond 10,000.UQ 1 IS $ 10,000 IS $ 1 IS $ 10,000
3210 Storm Sewer Pipe, 12 Inch D.I. 100.on 60 IF $ 6,00D IF $ 60 IF $ 6,000
3215 Foundation Material,Class I&II 75,00 5 TON $ 375 ION $ 5 TON $ 375
3220 Crushed Surfacing Top Course, 5/81nch Minus 75,00 20 TON $ 1,500 TON $ 20 TON ; 1,500
3230 Cement Concrete Sidewalk 100.00 10 SY $ 1,000 SY $ 10 SY $ 1,000
SCHEDULE C TOTAL $ 130,190 $ 29,911 $ 160,101
....-.�.... .__._....._............ ...................
CONTRACT SUMMARY
SUMMARY
SCHEDULE B(ALrERNATE). EARTHWORK-DOWNEY $ 649,587 $ 690,424 $ 1,340,011
#REF' $ 130,190 $ 29,911 $ 160,101
TOTAL SCHFDUI IS $ 779,777 $ 720,335 $ 1,500,112
SAIFS TAX... f0.OY/ $ , JISE //,( M F I Ai 011
-__.�_ ...._._... ._... ...............
'........ AWARDED AMOUNT y 057,755 New CGnibir TDtatl N „, „ 650,y,1Y4.
DOW aev Increase 4 759.467
..._..................�
NaUen Increase $ 32,902
ff.... .... ..._...... .-.._
....
Combined Clan$e5,,,-$__ 792,3�b9
PAGE 1 18-3007.1 B/01/2019-8/31/2018
n
Kuehne, Paul
From: Mason Dhanens <Mason.D@SCARSELLABROS.ccm>
Sent: Monday, September 24, 2018 11:49 AM
To: Kuehne, Paul
Subject: RE: Change Order 1 - Downey Naden
I!f ERNALE AIL
Paul—
I've reviewed Change Order 1 and I don't have any issues with the quantities or pricing. I do have a question regarding
how the pond is going to change with the additional excavation. Is the plan to go deeper than the original plan or will
we end up just making the footprint larger? Either way, we'll need to know so that we can get the correct slope stakes
put in for the pond. Could you also clarify when we'll have the topo and slope stakes for the Downey site?
Thank you,
Mason Dhanens
Scarsella Bros., Inc.
Office-253.872.7173
Fax-253,395.1209
maso n.d @sca rsellabros.com
estimating@scarsellabros.com
From: Kuehne, Paul [mailto:PKuehne@kentwa.gov]
Sent: Wednesday, September 19, 2018 2:28 PM
To: Mason Dhanens <Mason.D@SCARSELLABROS.com>
Subject: RE: Change Order 1 - Downey Naden
I will change it to twenty days.
Maybe you could haul it fast while restoration could be more relaxed,
Paul Kuehne, construction Engineering supervisor
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5543 1 Cell 253-740-5015
PK.ul-3T 1g.LK.entWA oav
CITY OF KENT, WASHINGTON
From: Mason Dhanens [mailto;Mason.D SCARSELLABROS.com]
Sent: Wednesday, September 19, 2018 2:21 PM
To: Kuehne, Paul <P'Kuehne; kentwa.gov>
Subject: RE: Change Order 1 - Downey Naden
EERNAL AIL
Paul—
1 got your message. I have had a chance to go through it but have not had a chance to review it with Bob. Once I do that
I'll get back to you. I do feel like we'll probably need more like 20 additional days on the contract.
Thank you,
Mason Dhanens
Scarsella Bros., Inc.
From: Kuehne, Paul [mailto:PKuehne 0kentwa.Bov]
Sent: Tuesday, September 18, 2018 4:21 PM
To: Mason Dhanens <Mason.DtESgARSELLABROS.Com>
Cc: Bobby Scarsella <bobb�5�SCARSE.LLABROs,com>; Connor, Eric <EConnor 'kenkwa.eeav>; Knox, Matthew
<l IKitox@kentwa.gov>; Leyrer, Thomas<TLeyrer eakentwa.8oy>
Subject: Change Order 1 - Downey Naden
Hello Mason,
Please review the attached preliminary change order and confirm that you agree to bid item
pricing for the proposed work. I have it mostly vetted on my end. Might have some minor
tweaks but this should be pretty close.
Paul Kuehne, Construction Engineering Supervisor
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5543 1 Cell 253-740-5015
FKu; h NK.t2n.;W-my
CITY OF KENT, WASHINGTON
2
Kuehne, Paul
From: Mason Dhanens <Mason.D@SCARSELLABROS.com>
Sent: Wednesday, September 19, 2018 4:15 PM
To: Kuehne, Paul
Subject: RE: Change Order 1 - Downey Naden
EXTERNAL EMAIL
Paul—
I agree with you. I have a couple ideas to make it go a little quicker but I'm going to run them by the boss before I
present them to you guys. I'll hopefully have a response on the CO in the morning.
Thank you,
Mason Dhanens
Scarsella Bros., Inc.
From: Kuehne, Paul [mailto:PKuehne@kentwa.gov]
Sent: Wednesday, September 19, 2018 2:28 PM
To: Mason Dhanens<Mason.D@SCARSELLABROS.com>
Subject: RE: Change Order 1 - Downey Nader
I will change it to twenty days.
Maybe you could haul it fast while restoration could be more relaxed.
Paul Kuehne, Construction Engineering Supervisor
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5543 I Cell 253-740-5015
EKM!Zl-irLe-@Kg!QtWLA.gov
CITY OF KENT, WASHINGTON
From: Mason Dhanens [rnailto,,Mason D SCARSELLABR05 c°omj
Sent: Wednesday, September 19, 2018 2:21 PM
To: Kuehne, Paul <PKueh 7eCkentwa.Rav>
Subject: RE: Change Order 1 - Downey Naden
EXTERNAL EMAIL
Paul—
a
I got your message. I have had a chance to go through it but have not had a chance to review it with Bob. Once I do that
I'll get back to you. 1 do feel like we'll probably need more like 20 additional days on the contract.
Thank you,
Mason Dhanens
Scarsella Bros., Inc.
From: Kuehne, Paul (ntailto.PKuehne a@kenl
Sent:Tuesday, September 18, 2018 4:21 PM
To: Mason Dhanens <Mason.D[@SCARSELLABROS.corn>
Cc: Bobby Scarsella <bgt}bV.s&SCARSELLAGROS.coM>; Connor, Eric<EConnor kentwa. ov>; Knox, Matthew
<MKnoxQkentwa.gov>; Leyrer,Thomas<TLe rer kentwa.gov>
Subject: Change Order 1 - Downey Naden
Hello Mason,
Please review the attached preliminary change order and confirm that you agree to bid item
pricing for the proposed work. I have it mostly vetted on my end. Might have some minor
tweaks but this should be pretty close.
Paul Kuehne, Construdiuri Engineering Supervisor
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5543 1 Cell 253-740-5015
eK,wehne c)KQntWA,,gav
CITY OF KENT, WASHINGTON
2
Kuehne, Paul
From: Kuehne, Paul
Sent: Tuesday, September 25, 2018 9:42 AM
To: 'Mason Dhanens'
Cc: Leyrer, Thomas
Subject: RE: Downey
Hello Mason,
The revised plan sheet will be available the day after topo. It will show the same top excavation
perimeter and slope contours the only difference will be the bottom depth.
Paul Kuehne, Construction Engineering Supervisor
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5543 1 Cell 253-740-5015
pKge-hano CP.fnt ciq—v
CITY OF KENT, WASHINGTON
From: Kuehne, Paul
Sent: Tuesday, September 25, 2018 8:44 AM
To: 'Mason Dhanens' <Mason.D@SCARSELLABROS.com>
Cc: Connor, Eric<EConnor@kentwa.gov>; Leyrer,Thomas<TLeyrer@kentwa.gov>; Knox, Matthew
<MKnox@kentwa.gov>; Hansen, Kit<KHansen@kentwa.gov>; George Hunkin <george.h@SCARSELLABROS.com>
Subject: Downey
Hello Mason,
Downey will have the same footprint... just deeper. We should have revised plan sheet for you
today.
Paul Kuehne, construction Engineering Supervisor
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5543 1 Cell 253-740-5015
PK4!.0ritLd Kff tWA ggw
CITY OF KENT, WASHINGTON
From: Mason Dhanens [mailtoWason.Dt?SCARSELLABROS coral
Sent:Tuesday, September 25, 2018 8:25 AM
To: Kuehne, Paul <PKtaehneC&kentwa.gov>
Cc: Connor, Eric <EConnor@kentwa,&cv>; Leyrer,Thomas<TLeyrer@kentwa pov>; Knox, Matthew
<MKnikentwa.Zov>; Hansen, Kit<KHansenC.2kentwa.pnv>; George Hunkin < efi�„h a�SCARSELLABROS,com>
Subject: RE: Naden Revision 2 DRAFT
1
I, w
MIMIMIMMXI IIIIFnMMMMM
EXTERNAL E AIL
Paul —
Thank you for getting me the revised Naden plan. Do you have an idea what we're going to do at the Downey site?
Thank you,
Mason Dhanens
Scarsella Bros., Inc.
Office -253.872.7173
Fax - 253,395.1209
mason.d@scarsellabres.com
estinnating@scarsellabros.com
From: Kuehne, Paul [ntallto:PKuehne@kerttwa.eov]
Sent: Monday, September 24, 2018 1:16 PM
To: Mason Dhanens<Mason D SCARSELLABRQS.com>
Cc: Connor, Eric<EConnor@ktgIAa.gm>; Leyrer,Thomas<TLeyrer@ken KtLgov>; Knox, Matthew
<MKnox kentwa. ov>; Hansen, Kit<KHansen r kentwa.go_v>
Subject: FW: Naden Revision 2 DRAFT
Hello Mason,
Please see attached DRAFT Naden revised grading plan. We should have this stamped for
construction tomorrow.
Paul Kuehne, construction Engineering supervisor
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5543 1 Cell 253-740-5015
P:KV_17r_tg.ILtibdentWA.ggy
CITY OF KENT, WASHINGTON
From: Leyrer, Thomas
Sent: Monday, September 24, 2018 1:12 PM
To: Kuehne, Paul <PKP uehn kentwa &ov>
Subject: FW: Naden Revision 2 DRAFT
From: Nagamatsu, Mark
Sent: Monday, September 24, 2018 1:10 PM
To: Leyrer, Thomas
Subject:
See attached,
z
Kuehne, Paul
From: Leyrer, Thomas
Sent: Tuesday, September 25, 2018 9:22 AM
To: Connor, Eric; Bieren, Chad
Cc: Maloney, Carla; Kuehne, Paul
Subject: Naden Site Improvements - Revision No. 2
Hi Eric and Chad,
The Naden Site Improvements Revision No. 2 plan is in the copy room for your review (and
signature if no changes are required).
Thank you,
Thomas
Thomas Leyrer, P.E. Design Engineerll
Design Engineering I Public Works Department
400 West Gowe Street, Kent, WA 98032
Phone 253-856-5562
t l ev re r tm k e n tw a.a u'v
Ct"V"N 0IF° IK IF:.'IN'r, WA$aHINiG"IfIC"N
KentVWA& 'F.1&Lqh9( k : '93c Vkft
PM?: ., , i"d^;MV f3 IHY I ,YtV4,MNN 14ti . VOM 4'kMdV'v,no 7wv1 t 1imii.
t
Kuehne, Paul
From: Bieren, Chad
Sent: Thursday, September 20, 2018 6:15 PM
To: Connor, Eric; Kuehne, Paul
Cc: Knox, Matthew; Leyrer, Thomas; Maloney, Carla; Mactutis, Mike
Subject: RE: Change Order 1 - Downey Naden
Thanks everyone for keeping this Change Order moving. I think it would be good to huddle up
for a few minutes once the plan sheets are done and see if there are any outstanding
issues/next steps.
Carla/Thomas - can you give us a heads up when you have a final ETA on the plans?
From: Kuehne, Paul
Sent: Tuesday, September 18, 2016 4:21 PM
To: 'Mason Dhanens'
Cc: 'Bobby Scarsella'; Connor, Eric; Knox, Matthew; Leyrer, Thomas
Subject: Change Order 1 - Downey Naden
Hello Mason,
Please review the attached preliminary change order and confirm that you agree to bid item
pricing for the proposed work. I have it mostly vetted on my end. Might have some minor
tweaks but this should be pretty close.
Paul Kuehne, Construction Engineering Supervisor
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5543 1 Cell 253-740-5015