HomeMy WebLinkAboutPW16-217 - Change Order - #6 - Pivetta Brothers Construction, Inc. - Kent Regional Trails Connector - 12/15/2017 lixecords M
�/�l,�m 1
wa� NT
o,o �yqr Document
��„f-r
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to the City Clerk's Office. All portions are to be completed.
If you have questions, please contact the City Clerk's Office at 253-856-5725.
Vendor Name: Pivetta Brothers Construction
Vendor Number: 34846
JDEdwards Number�r p
Contract Number: f
This is assigned by City Clerk's Office
Project Name: Kent Regional Trails
Description: ❑ Interlocal Agreement ] Change Order ❑ Amendment ❑ Contract
❑ Other: J�
Contract Effective Date: 5/23/2016 Termination Date:
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Jason Bryant Department: Engineering
Contract Amount: .js_ J;qN.p _
Approval Authority: ❑ Director ❑ Mayor ❑ City Council Meeting Date
Detail: (i.e. address, location, parcel number, tax id, etc.):
Attached is change order #5 for $4,577 74 and change order #6 for $9408.40
11 14
CHANGE ORDER NO. 6
NAME OF CONTRACTOR: Pivetta Brothers Construction ("Contractor")
CONTRACT NAME & PROJECT NUMBER: Kent Regional Trails Connector
ORIGINAL CONTRACT DATE: May 23,2016
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Compensate for demolition and disposal of concrete sidewalk and
driveway so driveways could be reconstructed as curb ramps to ADA
standards. Per contract plans, the trail sections approaching 64m 68th
and 72"d Ave were constructed to standards established for vehicular
driveway approaches. However, to allow pedestrian access they had
to meet ADA standards. As a result, these driveways and adjacent
sidwalks had to be removed and reconstructed. Removal of sidewalk
and driveways was not accounted for in the original contract pay items
or measurement and payment contract language. Removal and
replacement was directed to proceed in the field via field directive
under the agreement the cost for the work could be compensated via
change order.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $1,186,225.00
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $91,782.41
(incl. applicable WSST)
C t Am urrent Contracount $1,278,007.41
(incl. Previous Change Orders)
Current Change Order $9,408.40
Applicable WSST Tax on this Change $0.00
Order
Revised Contract Sum $1,284,415.81
CHANGE ORDER - 1 OF 3
Original Time for Completion 120 working days
(insert date)
__Revised Time for Completion under 27 working days
prior Change Orders
(insert date)
Days Required (f) for this Change 0 calendar days
Order
Revised Time for Completion 147workingdays
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CI Y OF KENT:
By: ~ �:._ fir•; � B 1 .
s(g` ure)u re)
Print Name: Print Name:
7.
Its PM
Ja��^fr
Its ,b/ate �� G
(title) ( !fe)
DATE: p b -I DATE:—,'
CHANGE ORDER - 2 OF 3
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
7
Kent Law Department
[In this field,you may enter olb electranlc fllepath where the contract haz been Saved]
CHANGE ORDER - 3 OF 3
/ NT FILE NO: 200.2
"^�✓'' KE
CHANGE ORDER 'III ORKSHEET NO. 6
_Construction Management Division - Public Works
Project: Kent Regional Trails Connector Project No.:] 9 t No.: 13-3006
Project Engineer: Mark Madfai Fed-Aid No.: CM-0615(008)
�.�Owners Re dw Jason „�. .,..0 Contractor' Pivetta Brothers
...,,, ...,..,.., ......
Date: 11/6/17
I. PROPOSED CHANGE
Compensation for demolition and disposal of concrete sidewalk and driveway so driveways could
be reconstructed as curb ramps to ADA standards
II. REASON AND BACKGROUND FOR CHANGE
Per contract plans, the trail sections approaching 64"', 68th and 72n"d ave„ were constructed to
standards established for vehicular driveway approaches. However, to aUlow pedestrian access
they had to meet ADA standards. As a result, these Driveways and adjacent sidewalks had to be
removed and reconstructed. Removal of sidewalk and driveways was not accounted for in the
original contract pay items or Measurement and Payment contract language. Removal and
replacement was di',rected to proceed in the field via Field Directive under the agreement that
the cost for the work would be compensated via change order.
III.. METHOD OF PAYMENT
NEW PAY ITEM(S) ❑ Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Est Qty this ' Unit Unit Price Total Estimated Cost of
0ty PE item
._....... ... .. ..
Demo Sidewalk/Driveway and 1 1 FA $9,408.40 $9,4 11 08.40
replace
Independent Estimate Attached CRIEATE PAY ITEPH ONLY Payment to be made f PAY THIS PAY ESTIMATE
REQUIRED at.a later date upon completion of work
_07MNatenial Submittals Required CC' CanslourNon Coor i ntor New Sub Reqrd? No
DELETE EXISTING PAY ITEM(S) per 109.5 Not Applicable
Change Order No. FOR ACCOUNTING USE ONLY
Sch. No B.I. No. Item Description Qty Unrt Unit Price � Cast of Item ...mm
n IndependentEstimate Attached - REQUIRED �
1 REV. DATE: 4/01/10
TFILE NO: 200.2
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. L _ !"OFI ACCOCINTiNG USE ONi Y
Sch No B.I. No. Item Description City Unit Unit Price Cost of Item
-. ....... _...—. ._.. _ ... �........ ._
Independent Estimate Attached - REQUIRED
TOTAL ESTIMATED COST OF CHANGE ORDER * $9/408 40
*Total of the Cost of Item Columns
THIS PAY ESTIMATE $9 40$ 40
IV. WORKING DAYS
Original Contract 1 120 D 11 ue This Change Order* p Previous Total 127
DATE: 11/6/2017 DATE: 11l6/201/201„7
* Ex la i n Ju if tion Re ui : On critical path for pr2joct completion
TOTAL WORKING DAYS* 127
This Change Order + Previous �* Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: Jasd" y a� far t" . Date: "
s� r1 p
a p
Construction Supervisor; , Date: �
Peur R I
ne
Construction Manager: Date: !°t":.. ,'/" ...J'r,
N«ric Connor
2 REV. DATE: 4/01/10
Page 1 of 1 Proposal for:
Kent Regional Trail Connector-COR 026
Bid Date: 10/4/2017 From
Time: 5MPM Pivetta Brothers Construction, Inc.
1812 Pease Ave. POB 370, Sumner, WA 98390
LN: PIVETBC063139 Type: General Contractor
Quote Number 2016144A Phone: (253) 862-7890 Fax:(253) 470-5008
City Of Kent
220 4th Ave. South
Kent, WA 98032-5895 Protect No 13 3006
Item Descnption Quantity Unit Unit Price Total Pnce
Demo Trail Approach
Vol Demo Crew COOLS 3,094.0000 3,094.00 ✓
✓02 Trucking & Dump Fees MOLD 1,500.0000 1,500.00 ✓
Total: 4,594.00
Form. Repar& Pour Approach &Curb
Vol 8"Approach Reinforced +Curb 177.00SF 27.2000 4,814.40 ✓
Total 4.814.40
Added Detectable.Warning Surfacing
Vol Truncated Domes 24.00SF 134.4000 3,225.60 ✓
ALT- Pavement Repair
,a
Vol Repair Asphalt Trail 1,600.00SF 2,8000 4,480.00 ✓
Total w/o ptsrnateg: 12,634A0
1 ---7'
Ll 0
w i Y lJ. ._...___...
=Locked Bid-Item --
EngineerlArch Mark Madfai
=Zero Total Price
Estimator: Jeremy Fudge ebror Generated by a SharpeSofr Pmdael
Bryant, Jason
From: Bryant, Jason
Sent: Thursday, October 19, 2017 7:44 AM
To: 'Jeremy Fudge'
Cc: Connor, Eric
Subject: RF: KRTC - COR 026
Jeremy,
Please proceed with the work.
Thank you,
Jason Bryant, Capita!Projects Manager
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5541 1 Cell 253-261-5663
7gr1"faeltC7KeAntWF1.C�Ov_
ClITY OF pa,,lf:NT, BWA'AS11 INQa"tl'4' N
Ke n1tWA.u9¢onv Fascelhoulk YouTnube
mu „� i r„ MAI[
From: Jeremy Fudge [mgitr:ieremypvekt<°a com]
Sent: Thursday, October 19, 2017 7:51 AM
To: Connor, Eric; Bryant, Jason
Subject: FW; KRTC - COR 026
Hey Guys,
Got a verbal from Jason that we are okay to proceed with this CO work. Can you please confirm?
Thank you,
➢ereeny Fudge
t; tllMa'l'Oa/il Manager
Ofllice: 253�862-7890 Ext, 104
Celli: 206-396-552 5
Fax:25:3-470-5008
jtaremwlvaatta com 1 rwr,plvetta.t;om
PIVETTAU
lTYETtp��A$C�1i$TAUIOW IBC
From:Jeremy Fudge
Sent: Wednesday, October 04, 2017 11:53 AM
t
To: 'Connor, Eric' <L_Conngr LLgLtwa.Gov>; 'Bryant,Jason' <JB }andakcrrt av>
Subject: KRTC- COR 026
Eric/Jason,
COR 026 is attached for your review&approval. This CO includes; the Conc. trail approach demo & re-pour at 68th,
added domes @ the islands, boardwalk bridge caulk, sidewalk patch @ 64th, &the trail pavement rework.
Thank you,
lererny Fudge
09'ffaoes 253-862-7890 Ext.. 104
Calk 206-396-55 m
Fax: 25 "701.•61008
j�rem �Iv_�tt�.csarrr i wrrwvuu�•plv�t4�.am_rrd
PIVETT&
PMY�`I'���IlTll��$C�IiSTNIN�'fION�NIC
z
b
wti Fyy�if;ri�%
"`neiierue^eVre ✓ K E N T
WA5HINGION
PUBLIC WORKS
Kent Regional Trails Connector I Project Number: 13-3006
INSPECTION WALK-THRU PUNCH LIST
To: Eric Connor, Construction Manager I Jason Bryant, Capital Projects Manager
From: PW Ops, Parks, Survey, Transportation; WSDOT
Date Due: June 29, 2017
PAVEMENT MGMT/STREET Date Inspected;, 6/28/17 _ Inspected By, J.Araucto
.
LOCATION Defect
s: _ _.., m..........
Defect
• Curb Ramps—(Please refer to attached diagram for curb ramp locations) Pleasee see the
attached curb ramp inventory summary identifying the deficiencies that are required to be the
corrected curb ramps required to have justification for not meeting requirements.
• Trail Cross Slopes:The design plans for this project required the trail to be constructed with cross
slopes at 1.5%. The AASHTO Guideline for the development of Bicycle Facilities(2012)(Section
5.2.5) recommends 1.0%cross slope while the PROWAG proposed guidelines(R302.6) requires
pedestrian access routes to be 2%maximum.
Generally the trail cross slope was constructed exceeding the requirements of the construction plan.
We have identified on the attached marked up plan sheets, the sections of the trail where the cross
slope of the entire width of the trail exceeds 2%and sections of the trail where portions of the cross
slopes exceeding 2%.
SIGNS Date Inspected 6/27/17 _. YYk Inspected By T. Rusbuldt
_.—_
LOCATIO . ..—___ _ ........
N
_.... Defects:
72 AVE S.
• All pedestrian signs need to meet city standards being 3m electric cut.
• All telespar bases need to meet city standards being no more than 4"above surface. They range
up to about 7.5".
• North bound stop here sign and stop bar location in question do to a sight distance problem with
the bike/ped crossing sign. Possibly adjust lateral offset of stop here sign to enhance bike/ped
sign sight distance.
• All duct tape residue to be removed from signs.
• All 36"signs need to meet city standards by being corner bolted to post.
• No advance crosswalk signs and ahead plaques.
• Arrow and ahead plaques should be 30"x 18" not 24"x 12"
68 AVE S:
• All pedestrian signs need to meet city standards being 3m electric cut.
* All telespar bases need to meet city standards being no more than 4"above surface. They range
up to about 9".
• All duct tape residue to be removed from signs.
• All 36"signs need to meet city standards by being corner bolted to post.
• Arrow and ahead plaques should be 30"x 18" not 24"x 12"
64 AVE S:
• All pedestrian signs need to meet city standards being 3m electric cut.
• All telespar bases need to meet city standards being no more than 4".
• All duct tape residue to be removed from signs.
• All 36' signs need to meet city standards by being corner bolted to post.
\\ E
\ \�\ \\\ \ \\}
(( ) / �
71
I ti
i
tl bppy g fi E
d C
s F
a
ff
s � I
r � ;
wo ..
;e
y 95
�Va N y
¢
m m
E G o
`u
� fp � aoEa
v v
E t I o««
e
m q
FA Sheet No.: CO#6
ENGINEERS
ESTIMATE 14
Project Name: Kent Regional Trails Connector Project No. 13-3006 CM-0615(008)
Item No.: Change Order#6 Date: 11/l/2017
Description of Work. Remove and replace driveway and sidewalks to meet ADA
Work by Subcontractor?: yes
Prime Contractor: Pivetta Brothers Sub-Contractor: G&G
LABOR,
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION HitsHourly Rate FirsOT Rate AMOUNT
Dane I Foreman 15 69,58 $ 1,043,70
f`ihristian Laborer 15 53.08 $ 795,20
SUBTOTAL-LABOR. $ 1,839,90
LABOR OVERHEAD&PROFIT @ 29% $ 533,57
LABOR TOTAL $ 2,373.47
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Descuppiprl HP5 Hourly Rate Pro Standby Reto AMOUNT
EX-123 Hitachi 135 excavator 15 6D.00 $ 900.00
$
$
SUBTOTAL-EQUIPMENT $ 900.00
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 189.00
EQUIPMENT TOTAL $ 1,089.00
gAT E RIALSI S E RV I C E SIR E N TALE
MATERIALS I SERVICES Quantity Units Unit Price DOLLAR AMOUNT
Dump Fees 1 LS $ 1.000.00 $ 1,000.00
Highmark 1 LS $ 5,200.00 $ 5.200.00
$
$
SUBTOTAL $ 6,200.00
OVERH EAD&PROFIT @ 21% $ 1,302.00
TOTAL $ 7,502.00
Verification of Hours Worked TOTAL $ 10,964.47
12%MARKUP (for prime when
subcontract work) $ 1,315.74
Corlraclars Repmsenlai Date SHEET TOTAL: $ 12,280.21
0wnuPS Representative Datef t-
Pay Estim�lte E nteretd
By: