HomeMy WebLinkAboutPW17-267 - Change Order - #1 - Road Construction Northwest, Inc. - Lake Meridian Estates Storm Drainage Repair - 12/05/2017 Records M KENT Document WASXING�ON � �//� CONTRACT COVER SHEET This is to be completed by the Contract Manager prior to submission to the City Clerk's Office. All portions are to be completed. If you have questions, please contact the City Clerk's Office at 253-856-5725. Vendor Name: Road Construction Northwest Inc. Vendor Number: ]D Edwards Number Contract Number: PW 11- 217 — �0 2- This is assigned by City Clerk's Office Project Name: Lake Meridian Estates Storm Drainage Repair Description: ❑ Interlocal Agreement 5Z Change Order ❑ Amendment [] Contract ❑ Other: Contract Effective Date: 8/24/2017 Termination Date: Contract Renewal Notice (Days): Number of days required notice for termination or renewal or amendment Contract Manager: Richard Schleicher Department: Engineering Contract Amount: $4,373.97 Approval Authority: ❑ Director ❑ Mayor ❑ City Council Meeting Date Detail: (i.e. address, location, parcel number, tax id, etc.): Remove and dispose of existing pipe T CHANGE 'ORDER NO. #1 NAME OF CONTRACTOR: Road Construction Northwest Inc ("Contractor") CONTRACT NAME & PROJECT NUMBER: Lake Meridian Estates Storm Draina e Re air ORIGINAL CONTRACT DATE: August 24, 2017 This Change Order amends the above-referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: 1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: Remove and dispose of existing storm pipe. The contract stated storm pipe removal would be paid per linear foot, however the bid item was omitted in error. 2. The contract amount and time for performance provisions of Section II "Time of Completion," and Section III, "Compensation," are hereby modified as follows: _._...__ Ori final Contract Sum 9 $307,230.00 (including applicable alternates and WSST) —._....._ .m................... Net Change by Previous Change Orders $0.00 (incl. applicable WSST) .................... _._......._ Current Contract Amount $0.00 (incl. Previous Change Orders) .. Current Change Order $4373.97 Applicable WSST Tax on this Change $437.40 Order ...... _........ i ......................_ Revised Contract Sum $312,041.37 CHANGE ORDER - 1 OF 3 .._.._......_ Original Time for Completion 20 working days (insert date) .._.____...... Revised Time for Completion under 0 prior Change Orders (insert date) Days Required (f) for this Change o calendar days Order Revised Time for Completion 20 working days (insert date) In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the Contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby ratified and affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written below. ------- ..................... ..._......._ ......... ......� CONTRACTOR:.. CITY OFmKENT: By: By. //'(siq ' re " (signature) Print Name: YeffreyM. PM9kW Print Name: Timothy J. LaPorte. P.E. Its Its Public Worl s Director DATE: lhtie)li-Z(- 1 7 DATE: ( ZGticy7/j" CHANGE ORDER - 2 OF 3 .._........_ .. __..... ....._... -- APPROVED AS TO FORM: (applicable if Mayor's signature required) Kent Law Department [IIi Unto field,you inoy enter the electronic riilepath where the contract has been saved] CHANGE ORDER - 3 OF 3 TFILE NO: 200.2 KEN CHANGE ORDER WORKSHEET NO. 1 Construction Management Division - Public Works Project• Lake Meridian Estates Storm Project No.: 16-3017 Drainge Repair Project Engineer: Richard Schleicher Fed-Aid No.: N/A Project Manager: Phil McConnell Contractor: Road Constrcution NW Date: 10/9/2017 I. PROPOSED CHANGE Remove and dispose of existing storm pipe II. REASON AND BACKGROUND FOR CHANGE Contract stated storm pipe removal would be paid per linear foot, yet bid item was omitted in error. III. METHOD OF PAYMENT NEW PAY ITEM(S) Lf Not Applicable Change Order No. - I FOR ACCOUNTING USE ONLY _.�_.... — ---- _ -- -- Sch No Item Description Total Est Cty this Unit Unit Price Total Estimated Cost of city PE Item 4 Remove and Dispose of 1 1 LS $4,373.97 $4,373.97 Existinq Storm Pipe Independent Estimate Attached ® CREATE PAY ITEM ONLY— Payment to be made ^�I PAY THIS PAY ESTIMATE - REOUIRED at a later date nDon com Dletlon of work Material SwbmikkaVs Re aired — CQ Constructi on.Coordinator New Sub Regrd? I No DELETE EXISTING PAY ITEM(S) per 1-09.5 Not Applicable Change Order No. _ I IFOR ACCOUNTING USE ONLY Sch. No. B 1 No. Item Description city Unit i Unit Price Cost of Item ................ ... ....I �L... .. .__...__l L .._ . .......... Independent Estimate Attached - REQUIRED INCREASE/DECREASE TO EXISTING PAY ITEM(S) ( ] Not Applicable Change Order No - FOR ACCOUNTING USE ONLY Sch No, B I No Item Description city Unit ( Unit Price ,Cost of Item . ... .- ... 1 REV. DATE: 4/01/10 T FILE NO: 200.2 "`�•�•� KEN TOTAL ESTIMATED COST OF CHANGE ORDER * 4 373.97 *Total of the Cost of Item Columns THIS PAY ESTIMATE $4,373.97 IV. WORKING DAYS Original Contract Zp Due This Change Order* I 0 Previous Total Zp DATE: .. DATE: .. .. ... * j Explanation/Justification Reauired: TOTAL WORKING DAYS* *This Change Order + Previous Total All work, materials and measurements to be in accordance with the Standard Specifications and Contract Special Provisions for the type of work described. Capital Projects Manager: � A✓ . . ....... Date: AQ--"L:+°x o f Phil McConnell' Construction Supervisor: �' \ ' - v--'"'°'""" Date: Paul Kuehne ..., Construction Manager: '"'" ,� - ^ �- L c�^^"` e�?' �^"' Date: Eric Connor 2 REV. DATE: 4/01/10 FA Sheet No,,: DAILY REPORT OF Engineers Estimate Project Name. Lk Meridian Estates Storm Real Project No: 16-3017 Item No.: Date: Description of Work: Estimate for pipe removal Work by Subcontractor?: N Prime Contractor. RCNW Sub-Contractor: LABOR ' STRAIGHT TIME OVERTIME DOLLAR NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT Foreman 6 56,37 $ 398.22 operator 6 67.26 $ 403.56 Laborer 6 52,79 $ 316.74 pipelayer 6 53.38 $ 320,28 truck driver 4 61 36 $ 24544 $ SUBTOTAL-LABOR: $ 1,684.24 LABOR OVERHEAD&PROFIT @ 29% $ 488.43 LABOR TOTAL $ 2,172.67 EQUIPMENT EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT excavtor 6 71.52 $ 429,12 loader 6 47,01 $ 282.06 tractor peterlott 4 79,50 $ 318.00 enddump trailer 4 14,63 $ 58.52 crew trucks(2) 12 42,63 $ 511.56 SUBTOTAL-EQUIPMENT $ 1„599.26 EQUIPMENT OVERHEAD&PROFIT @ 21% $ 335.84 EQUIPMENT TOTAL $ 1,935.10 MATERIALS/SERVIC ESIRENTALS MATERIALS!SERVICES Quantity Units Unit Price DOLLAR AMOUNT dumb fees 2 TINS $ 110.00 $ 220.00 SUBTOTAL $ 220.00 OVERHEAD&PROFIT @ 21% $ 46.20 TOTAL $ 266.20 Verification of Hours Worked. TOTAL: $ 4,373.97 12%MARKUP (for prime when subcontract work) $ - Contractors Representative Date SHEET TOTAL: $ 4,373.97 Owner's Representative Date Comments McConnell, Phillip From: McConnell, Phillip Sent: Tuesday, September 26, 2017 10:31 AM To: Gordon Lee (gordon@rcnw,com) Subject: FW: 1717 Kent - Lake Meridian / Cost Proposal (Storm Pipe Removal) Attachments: RCNW Rev. Pipe Removal Estimate.xls Gordon, See the email below. The City has accepted the cost proposal for existing pipe removal. There will be no additional working days. I will put together a change order for RCNW signature. Phil McConnell, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5542 1 Cell 253-261-5685 pmccannelKenCW 4,cgny c3""I3f tflw' Ilflm:IN"f', WA,SIHT k03110N KeinlJWA,,fo)r lalcelbook YoO.d.NAiae °.Ik, w t 'r3,Ef O'Rr. -VU& T.Mr+A�11 From: Connor, Eric Sent: Tuesday, September 26, 2017 9:43 AM To: McConnell, Phillip Cc: Bieren, Chad Subject: RE: 1717 Kent - Lake Meridian / Cost Proposal (Storm Pipe Removal) Phil, The proposed amount of$4,373.97 to compensate RCNW for all "Removing Existing Storm Sewer Pipe" work shown on the contract plans for Lake Meridian Estates Storm Drainage Repair is acceptable. Though identified in the contract plans and specifications, a pay item for"Removing Existing Storm Sewer Pipe" was not included in the contract's bid schedule for the contractor to provide pricing at bid time. It is understood that this compensation is payment for crew time (labor and equipment), trucking, and dump fees associated with the scope of work. Given this work is clearly identified on the contract plans and was always required to be performed by the contractor, it is not added scope of work. As a result, additional working days will not be granted in conjunction with the acceptance of the proposed pricing. Please let me know if there are any questions, or if any additional discussion is required. Thank you, Eric t Eric Connor, Construction Engineering Manager Construction Management I Public Works Department Phone 253-856-5533 1 Cell 253-797-0693 CITY OF KENT, WASHINGTON 114. m,i Tn nsau ,t a eitv':r e t+srrttxrnt r ire I`404RL From: McConnell, Phillip Sent: Tuesday, September 26, 2017 8:51 AM To: Connor, Eric Subject: FW: 1717 Kent - Lake Meridian / Cost Proposal (Storm Pipe Removal) Eric, After our phone conversation, they sent me this. A little different then what the RCNW talked about on the phone. Thoughts? If I had more time I would love to track it force account at this point. Phil McConnell, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5542 1 Cell 253-261-5685 pmccaanne1l arKentWA.gov CJ TY 01111F WKIII',!IHII"111"'s A,'S111-11:IMi':;"Ir't'.1M Ka*llr'm9:W&,gov Iaar;;#,,h' ok YOU T"mibe LEASE 4 H:V U, .onl, i'i'8, d,Hl. rNV1R,0fl'V'4V+l"I k.',iiFOltdti: lPFUPUHNGi uVU'r &ie...TI$";I:L From: Gordon Lee [rroalto:c2arcjan .rcrwmcorn] Sent: Tuesday, September 26, 2017 8:46 AM To: McConnell, Phillip Cc: 'Brian Menard'; grlsorILcgM,con; 'Matt Wagester'; 'Jeff Kanyer'; 'Ty Ribera'; 'Arlene Schuchard' Subject: RE: 1717 Kent - Lake Meridian / Cost Proposal (Storm Pipe Removal) Hi Phil—Attached is the revised cost estimate per our phone conversation. Essential we are going from 8-hours to 6- hours of field crew time. Gordon lee Project Manager Road Construction Northwest.,hrr,. effig M)D Molly Drive,4uite 210, Eveielt,WA982Utl 110 Box 2229,Renton WA 9805b Tel4 , 1/1 1123, I ax41.-228 7 (0,125 531t-0104 gordon Lorenw'.Com Notl<r 161s mess'aye,Induding attar honer ts,roof non,riu+,flJerdttrl mid privNeged infornra[ian for she exclusive u,a nJ Fhe inter lNd rec�P3ent('sJ.My unauthcrrzed use L proludrtad.7f tYris i.rf nk is not fu;you please nor,)L the ender ar then destrt y[t ur-sagas, you. From: McConnell, Phillip [11ailto:PMcControell@kentwa.gov] Sent: Tuesday, September 26, 2017 8:11 AM To: Gordon Lee (Rordon_@rcnw.com) <aordon@rcaw!.carn> Subject: FW: 1717 Kent- Lake Meridian/ Cost Proposal (Storm Pipe Removal) Gordon, 2 I left you a voice mail on this earlier this morning. My managers thinks the hours are heavy for removing pipe that is in the same excavation as the pipe being installed. I put together an estimate more in line with his thoughts. Please review and get back to me. Phil McConnell, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5542 1 Cell 253-261-5685 pmcconnell(a)KenkWA,g_y CITY OF IIKIG::IN"Ir,. WASIHICING rON Kent A.9ov IFacelboolk Y ouu"Iruull e 1-"LE—AS . "W5, il¢r F THE EIN VIP,CHI ltdrl^f'r BIE' t.9R THIS iE; ii11AIL From: Gordon Lee [mailto;wgordon@rcnw.c®gn] Sent: Monday, September 25, 2017 9:13 AM To: McConnell, Phillip Cc: Schleicher, Richard; Kuehne, Paul; 'Brian Menard'; solson arrcnw.,gom; 'Matt Wagester'; 'George Tucker'; 'Jake Boose'; 'Matt Wagester'; 'Ty Ribera' Subject: RE: 1717 Kent - Lake Meridian / Cost Proposal (Storm Pipe Removal) Good Morning Phil— Please see attached Unit Price Request to add bid item to cover the cost of removing the existing 24-inch Storm Sewer Pipe. I have also requested the invoice from Ferguson for the SIX(6) 24-inch PVC Manhole Adapters they dropped off last week but have not seen it yet. We will forward upon receipt. Very truly yours, Gordon Lee rlrrirrc:t Nl,lllag(!1 Road Consttr uctlon Northwest,fink REA)J Al, Dave,Sail M Everett 1VA)fl"1,0't V(}Nmr IZ2<' keilton WA 9d(h6 rW 42', /// 7 i23, 1)9 loll s„", i R 7.-0104 , R()on o)rcnw.CCYI1A NoGl lh,,ires3n,<,im uOry"M"l"N W ,eoniam,ronJidcnbol onilinvrle0cr7 afarrrrntlonto (hw exduvv, ru o^(he in(auJ("o r col)(ent(,I P,ny unaI,imuf eduse ,,prrhrO fud if lhr, v,ol.urt tcw) r,plrrfenco,l ri? iumfErand fheudeMov[hrrnesnges lrrrnk you . From: Gordon Lee [rnailto: org donCaorcnw.gam] Sent: Thursday, September 21, 2017 4:31 PM To: 'McConnell, Phillip' <PMcConnell@a kenlwa.Rov> Cc: 'Schleicher, Richard' <RSchleicher'r?a kentwa.gov>; 'Kuehne, Paul <PK,uehne@kentwa.goy>; 'Brian Menard' <brian x rcnvv.carrn>; 'solson@rcnw.com' <solson@rcnw.corn>; 'Matt Wagester' <Matt RCNW,com>; 'George Tucker' <gcorae@rcnw.com>; 'Jake Boose' <Jake2RCNW.conr>; 'Matt Wagester' <Mattj2RCNW.coru>; 'Ty Ribero' <THRtRCNW.corn> Subject: RE: 1717 Kent - Lake Meridian/ RFI #002 Reverse Flow Hi Phil—Please see attached RFI #002 regarding negative water flows between Existing Type II CB at westend and CB- 1. Please review, respond and return, Thank you. Very truly yours, 3 Gordon Lee Project Manager Road Constructlorr Northwest,Inc,:. RE 85IC HoIty Drive, Suite 2..1b, Ev%r(tL,Alt it?82(N F 0(ne)22.r,Renton 0/A 98056 I eI4,2S !U / 2i I ,x 12" )28 1 (.eli 425 ,{1 01In, Q40ii<yM r[f,1,yy,;,,ovv Rralrra H'i wessalr,m<1, ingotiahrnents,m,l()rn1lool")..nt ul and yrivileg,dinjorma6on,ar the exclusive . eof0" ftltcnd"l'recrpiea(/sf,Any uaaotha,red use is grohlild"l,If till rniu116 not Jor y, , nose n,rfy h .ende'U"Ofoen desho, t,,v,es,o9e4 rhwiw,ou From: Gordon Lee [rnaiIto:Rordon@rcnw.cOm] Sent: Thursday, September 21, 2017 8:42 AM To: 'McConnell, Phillip' <PMcConnelk[ kentwa.Roy> Cc: 'Schleicher, Richard' <RSchleicl�erca)kerttwa.gov>; 'Kuehne, Paul' <PKuehne kentwa.gov>; 'BrianMenard' <brian@bbIrcnw.com>; 'solson@rcnw.com' <y_olso cnw.corrr>; 'Matt Wagester' <Matt EDRCNW.com>; 'George Tucker' <geor Ieb"tarE enw.com>; 'Jake Boose' <Jake RCNW.com>; 'Matt Wagester' <Matt@RC,NW.Com>; 'Ty Ribera' <TH RCNW.com> Subject: 1717 Kent - Lake Meridian / Non-Work Request Good Morning Phil—With the torrential rains earlier this week and the heavy water flows running through our drainage system, Road Construction Northwest Inc. (RCNW) requests that both Tuesday (Sept. 19th) and yesterday Wednesday (Sept. 20") be considered unworkable weather days. We are drying out the site and setting up, however it is unlikely we will be able to dig this week. Please call either myself or our General Superintendent Brian Menard cell (425) 531-1624 with any further questions. Thank you. Very truly yours, 6cvdon Lee Piolecl:rvi tanag;e.r Road Construction Northvaesv:,Inc. or= 8l)e b H,IIy Drive,Slllrl,110, Eves,[t WAI)iiZ(Rt Po i,x 2.mi,Rena r WA M(YA, 1e14), f,i 11)3 tn, 4; t28-rIS/,I r11415 it (Illl4 fyY(�!JVY,t !'4:�Yi4N.CUti1 IVUI er 4U,one;sog,,a rlpdfr n?a(r.,.1t,n-ut3,cnr¢i r :mtflr,'enttul and(uivileyrd q,forrnofian for l hr, du lrve i.,r of the intend,d,c ipient(sf.Any unouthrn¢ed use r5prnhtbfed lfihls em>if nor ju nx,please Hotly the sender and Hien destroy P4r rnecsuges.Thank you. From: McConnell, Phillip [rnailta;P'IMcConnells kentwa. ov] Sent: Tuesday, September 19, 2017 3:37 PM To: Gordon Lee (gordonC Ia rcnw.com) <gordon @rcnw.com> Subject: RAM Gordon, RAM 010 is attached for your use,. Phil McConnell, Capital Projects Manager Construction Management I Public Works Department 220 Fourth Avenue South, Kent, WA 98032 Phone 253-856-5542 1 Cell 253-261-5685 pm 1Cprinel k(nr Kerat WA..3U`2 CITY OF KE:147 WA511-n[NGTON IlGabni I:!aa„i:SL ook You rube eLe r }p�,�.COGM Y.(" [RtB£4TMPP Mr k:19EPrJ+!( rnatlV Y'S IN Y.; YI9 t' 6.-Prd193d. 4