CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name: Rodarte Construction, Inc.
Vendor Number:
JD Edwards Number
Contract Number: PW 16-067 -- Mp
This is assigned by City Clerk's Office
Project Name: James Street Pump Station
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 2/29/16 Termination Date:
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Garrett Inouye Department: PW Engineering
Contract Amount: $2,329,398.98
Approval Authority: (CIRCLE ONE) Department Director Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #5
As of: 08/27/14
f
T
CHANGE ORDER NO. #5
NAME OF CONTRACTOR: Rodarte Construction, Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER: James Street Pump Station
ORIGINAL CONTRACT DATE: February 29, 2016
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Apply sealant to building masonry since it wasn't part of the contract,
but determined to be necessary.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $2,329,398.98
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $-7,128.21
(incl. applicable WSST)
Current Contract Amount $2,322,270.77
(incl. Previous Change Orders)
Current Change Order $3,403.20
Applicable WSST Tax on this Change $323.30
Order
Revised Contract Sum $2,325,997.27
CHANGE ORDER - 1 OF 3
Original Time for Completion 120 working days
(insert date)
Revised Time for Completion under 0
prior Change Orders
(insert date)
Days Required (f) for this Change o calendar days
Order
Revised Time for Completion 120 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: C T1 OF KENT:
By: /� - _ y /
1
(signature) C ignature)
Print Name: 4'y;t-1 mYy_ Print Name:Sn- -T t.-c c k e.
Its Its l?t, %%C, etc r# ` tre c h-c-
(tit/e)�, p ,� I�
DATE: DATE: �' l ;�c1/G
CHANGE ORDER - 2 OF 3
APPROVED AS TO FORM:
(applicable if Mayor's signature required) '..
Kent Law Department
[In this Win,you may enter the eleRronic filepath where the cont,.d has been savebJ
CHANGE ORDER - 3 OF 3
i
• FILE NO: 200.2
KENT
CHANGE DER WORKSHEET NO.
Construction Management Division - Public Works
Project: James Street Pump Station Project No.: 10-3009
Project Engineer: Garrett Inouye Fed-Aid No.: N/A
Owners Rep: Phil McConnell Contractor: Rodarte Construction
Date: TBD
I. PROPOSED CHANGE
Apply sealant to building masonry
II. REASON AND BACKGROUND FOR CHANGE
Sealing masonry wasn't part of the contract but determined to be necessary
III. METHOD OF PAYMENT
NEW PAYITEM(S) ❑ Not Applicable
Change Order No. FOR ACCOUNTING USE ONLY
Sch. No. Item Description !! Total Est. ! Qty this;. Unit j Unit Price j Total Estimated Cost of
Qty PE I Item
4 Applying masonry sealant to 1 1 LS $3,403 20 $3,403 20
shelters [ ,
--- --- .
._, ... ......_ . -_- ........ _. ..._... .. .,..
❑ l Independent Estimate Attached ❑ I CREATE PAY ITEM ONLY Payment to be made ® ; PAY THIS PAY ESTIMATE
REQUIRED .....,.. ,.,,_„_,.,,, at a later.date upon,.completion of work _ j
..._.... ... ................ .. .-------_..__...-.__...-_
❑ Material Submittals Required CC: Construction Coordinator New Sub Reqrd? No
DELETE EXISTING PAY ITEM(S) per :li 09.5 ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
,Sch No B 1 No Item Description ! Qty Unit Unit Price i Cost of Item
.I._... . ... .-.-.-. .. .. .. ..... ...... .._.., -...... ..
_....-. ....... ....._ ................................. ... ..._..- ......._ ..
......-.... j......... ... . . . ......... .......... . .. . . ......� . ................. ............ ... .. .... ...... ....... ........-
I
❑ Independent Estimate Attached -REQUIRED ❑
INCREASE/DECREASE TO EXISTING PAY ITEM(S) �] Not Applicable
Change Order No. I i _ i a IFOR ACCOUNTING USE ONLY
Sch No j B I No Item Description i Qty Unit Unit Price Cost of Item
-.-.- ...... ..... ..... .. ...... ... .,.
.-.-.- ............ .i... ... . .... .. ........ ............... .. ........_.. ...... .. ..-.-.. . .. ...
.......... . ......i.,...., .., .. . . �..-. . . ....-.-...... .-......-.-.....- ..........-.-...� ................ : . .,............ ........ ....... ....... ...,......
I
❑ 1 Independent Estimate Attached -REQUIRED ❑
1 REV. DATE: 4/01/10
i
7:111 0 _1 FILE NO: 200.2
(GENT
TOTAL ESTIMATED COST OF CHANGE ORDER * L-$3,-403.-2-0---]
*Total of the Cost of Item Columns
THIS PAY ESTIMATE '. $3,403.20
IV. WORKING DAYS
Original Contract r* J 0 Previous Total 120
.................
...... ........ . DATE:_.[L.
—----------------------------------------------------------------------- .........
ExDla nation/justification Reguired. No jmp�"t"o" t'h"e—c"r'tit"ical path
TOTAL WORKING DAYS* 120
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: Date:
Phil"" c nnell
Construction Supervisor: Date:
Paul �ne Date:Construction Manager:
Eric Connor
2 REV. DATE:4/01/10
I'
McConnell, Phillip
From: Connor, Eric
Sent: Tuesday, August 23, 2016 9:56 AM
To: Shields, Brian
Cc: McConnell, Phillip
Subject: FW:James Street Pump Station Brick Sealing recommendation
Attachments: WS Siloxane WB Concentrate PDS 062013 C.PDF
Brian,
Yes we want the sealing. Below is the last email I have on the topic...Kevin owes us some pricing with a credit for not
installing PVC.
Eric Connor, Construction Engineering Manager
Construction Management I Public Works Department
Phone 253-856-5533 1 Cell 253-797-0693
CITY OF KENT,WASHINGTON
PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL
From: McConnell, Phillip
Sent: Friday, August 19, 2016 1:34 PM
To: Kevin Durrant <Keviniabrodarteconstruction.com> (Kevin@rodaiteconstruction.com)
Cc: Connor, Eric; Kuehne, Paul; Shields, Brian
Subject: FW: James Street Pump Station Brick Sealing recommendation
Kevin,
A follow up to our phone conversation this morning. With consideration that the PVC damp proof course wasn't
installed per the plans. The City would like to see a price for cleaning and sealing the masonry,to include a credit for
accepting the masonry without the damp proof course.
Phil McConnell, Owners Representative
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5542 1 Cell 253-261-5685
pmcconnell@KentWA.00v
CITY OF KENT, WASHINGTON
KentWA.gov Facebook YouTube
PLEASE CONSIDER THE ENVIRONMENT BEFORE PRINTING THIS E-MAIL
From: Kevin Durrant [mailto:l<evin arodarteconstruction.com]
Sent: Friday, August 19, 2016 10:00 AM
To: McConnell, Phillip; Shields, Brian
Subject: Fwd: James Street Pump Station Brick Sealing recommendation
L
attached is the product Cascade uses. I will get you pricing for,both this product and the one mutual materials
recomends
Sent from my T-Mobile 4G LTE Device
-------- Original message --------
From: Ron Adams <radarns,a�caseadeconstoom>
Date: 8/19/2016 8:50 AM (GMT-08:00)
To: Kevin Durrant<.'evin�ia�rodarteconstruction.com>
Subject: RE: James Street Pump Station Brick Sealing recommendation
Kevin,
The brick should be sealed, our go to sealer is the Prosoco Siloxane WB.
Attached is the data sheet on the product for review.
Ron Adams I Cascade Construction 1253.531.7835
From: Kevin Durrant [mailto:Kevin@rodarteconstruction.corn]
Sent:Thursday, August 18, 2016 1:39 PM
To: Ron Adams<radams@cascadeconst.com>
Subject:James Street Pump Station Brick Sealing recommendation
Ron
The James Street Pump Station does not have a spec for sealing or graffiti coating for the Clay-All Brick. Does the Clay-All
brick need to be sealed? What is your recommendation for the product to use?
Thanks
Kevin
2
RODARTE CONSTRUCTION, INC.
P,O, BOX 1875
AUBURN,WA 98071-1875
ph 253.939.0532 fax 253-939.0557 Change Order
PROPOSAL
PG 1
Customer '..
Name Phil McConnell Date 812912016
Company The City of Kent _ Job Name: James Street Pump Statio
Address 220 Fourth Ave South State WA Zip 98032
Phone 253 856.5542 Fax
We hereby submit speatficatons and estimates fbr the felowicg items:
ITEM Description Quantity Unit UNIT PRICE AMOUNT
1 Seal Brick b Cascade Construction 1 LS $ 3,485.00 $ 3,485.00
P3
2 General Contractor Mark u at 12% 1 LS $ 418.20 $ 41820
Credit 1 LS $ (500.00) $ 500.00
4
TOTAL $ 3,403.20 '..
NOTES:
Please see 3 pages attached
17 E. Valley Highway East — Auburn, WA 98092
August 19,2016
Phil McConnell
City at'Kent
220 4"Ave S
Kent,Wa98032
RE:James Street Pump Station Masonry Damp Proof Course
Phil McConnell
1 received your entail requesting a credit hack for not installing a"Damp Proof CoursC'in the masomn that is called out in the
Architectural sheets.The Masonn Kqc installed per the structural demiI(section detail Bon Sheet C3.05)and the structural notes
on sheet C3.04,.The specifications do nut specify a"Damp Proof Course There is no detail shoeing material to use or how to
install the"Damp Proof Course'-.The%sal is are structural and vcere built using the structural notes,structural details,and
specifications,The Architectuml dmaings,core referenced for sill height,twit height,and other Architectural details and
dimensions. I believe that per the contract documents a"Damp Proof Course"rras not required.Even though it is Rodanc
Construction's position that the"Damp Proof Course"is not required I would like to offer a$500.00 credit to be applied to the
pending proposal to seal the Masonry.
Kevin Durrant
Rodate Construction
Project Manager
Office (253)939-0532 Fax (253) 939-0557
RODARTE*225D9
Date: ######## Cascade Construction Company, Inc.
10215 Park Ave 5
General: Rodarte Construction Tacoma WA 98444
Phone (253) 531-7835
Pax(253) 548-2170
Change Order Proposal
Project: James Street Pump Station
Reference: Seal Brick
Description of work:
Seal Brick with Siloxane WB
COP Cost: $3,485
COP Time: 1 Day
This change order is submitted based on the inclusions and exclusions in the masonry subcontract for the project
unless additional scope items are specifically priced as part of this change order on page 2 of the proposal.
i
Project: .flames Street Pump Station
Date: 8/28/2016
Description: Sea] Brick
Additional Time: 1 Day
A Administration Rate Amount
Project Manager $150.00 $0.00
B Labor Cost
Craft Hours
8 Site Foreman Wage/Benefits $64.97 $519.76
8 Bricklayer Wage/Benefits $54.97 $439,76
Hodcarder Wage/Benefits $47.76 $0.00
16 Industrial Insurance $4.28 $68,48
FICA 6.20% $59.49
Medicare 1.45% $13.91
Employment Security 6.83% $65.54
Superintendent(10% PLR) 10% $95,95
Safety(3% DLR) 3% $28.79
Total Labor $1,291.68
2 MateriallEquipment Delivery $95.00 $190.00
C Material Sealer $1,045.60
Masking Materials $200,00
$0,00
$0.00
Total $1,245.60
Sales Tax on Materials 0.00% $0.00
D Equipment
Truck ($10.00 Per Hour) $10.00 $0.00
Forklift($40.00 Per Hour) $40,00 $0.00
Mixer($10.00 Per Hour) $10.00 $0.00
1 Spray Equipment $150.00 $150.00
Total Equipment $150.00
E Small Tools 5%ofLabor 5% $64.58
Subtotal Subcontractors Work $2,941.86
Overhead I Profit 15% $441.28
Subtotal $3,383.14
Insurance 2.5% $84.58
$3,467.72
B&O Tax 0.00484 $16.78
Total Change Order $3,484.50