HomeMy WebLinkAboutPW15-240 - Change Order - #10 - Marshbank Construction, Inc.- Central Ave S Pavement Preservation and Utility Improvements - 06/27/2016 ,-,w�v e m en,
Kecords Man'
KENT
9WASHINGTON Document
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed..
If you have questions, please contact City Clerk's Office.
Vendor Name: Marshbank. Construction, Inc.
Vendor Number:
JD Edwards Number
Contract Number: P'WV 15-240 t
This is assigned by City Clerk's Office
Project Name: Central Ave S Pavement Preservation and Utility Improvements
Description: ❑ Interlccal Agreement N Change Order ❑ Amendment ❑ Contract
Other:
Contract Effective late: ? 6 20 5 Termination late:
Contract Renewal Notice ([days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Mark Madfai Department: PWV Engineering
Contract Amount: $5,819,698.74
Approval Authority: (CIRCLE ONE) Department Director Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order #10
As of: 08/27/14
•
KENT
W A S H I N O T O N
CHANGE ORDER NO. 10
NAME OF CONTRACTOR: Marshbank Construction, Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER: Central Avenue S Pavement Preservation and Utility Imp.
ORIGINAL CONTRACT DATE: July 6, 2015
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Provide compensation to the contractor for production losses due to
encountering large and unforeseen existing utilities while connecting
the new 12 inch water main to the existing 16 inch water main within
the Willis intersection.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $5,819,698.74
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $79,833.70
(incl. applicable WSST)
Current Contract Amount $5,899,532.44
(incl. Previous Change Orders)
Current Change Order , $8,174.67
Applicable WSST Tax on this Change $776.59
Order
Revised Contract Sum $5,908,483.70
CHANGE ORDER - 1 OF 3
Original Time for Completion 180 working days
25
(insert date)
Revised Time for Completion under 5
prior Change Orders
(insert date)
Days Required (±) for this Change 0 calendar days
Order
Revised Time for Completion 185 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY-1 OF KENT:
By: By:
e"'o" (sig�ature)
Print Nam... (signat re)JA-StW Print Name- kimnk��% 7' . L-A(k Q'E .
Its PM- its P-oo\6c, k-A-)2)Cy-6'J c-
(title) ftitle)
DATE: DATE: / 2
CHANGE ORDER - 2 OF 3
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
MNflIn this field,you may enter the electronic filepath where the contract has been saved]
CHANGE ORDER - 3 OF 3
KENT FILE NO: 200.2
W.,�,.
CHANGE ORDER WORKSHEET NO. 10
Construction Management Division - Public Works
Project: Central Ave. S. Pavement Project No.: 13-3004
Preservation and Utility
Improvement Project
Project Engineer: Cameron Bloomer, PE Fed-Aid No.: STPUL-1071(006)
Owners Rep: KBA, Inc Contractor: Marshbank Construction, Inc
Date: 5/16/2016
I. PROPOSED CHANGE
This Change provides compensation to the contractor for production losses due to encountering
large and unforeseen existing utilities while connecting the new 12 Inch water main to the
existing 16 Inch water main within the Willis intersection.
II. REASON AND BACKGROUND FOR CHANGE
On the night of 3/9/2016 the contractor began excavating to connect the new water main to the
existing water system in the Willis St intersection. During this work, the contractor encountered
two separate large utilities that were not shown on the plans or marked by locates. The first was
a 6" steel casing wrapped in timber. This utility slowed excavation and caused additional effort
to shore the trench. A second unforeseen utility, a 12 inch steel pipe, was encountered a just
few feet from the water main the contractor was to connect to. This utility was in conflict with a
12 inch gate valve they were to install. Because this work was at night, they could not readily
obtain fittings to allow the movement of the gate valve. The contractor's supplier had similar
fittings and gate valves that could be used to successfully complete the connection at a store in
Marysville. The contractor sent a runner to obtain the materials from Marysville, and completed
the connection. The contractor and City discussed the additional impacts and agreed the city
would pay for four hours of crew time and additional materials on force account.
III. METHOD OF PAYMENT
NEW PAY ITEM(S) 0 Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch.No. Item Description Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
B2 Co 010-01 1 1 LS_ 8 174.67 $8,174.67
I 0
Independent Estimate Attached ❑ CREATE PAY ITEM ONLY— Payment to be made PAY THIS PAY ESTIMATE
_ REQUIRED I at a later date upon completion of work
Material Submittals Required—CC: Construction Coordinator New Sub Regrd? I No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. _ I i FOR ACCOUNTING USE ONLY
Sch.No. I B.1.No. Item Description Qty Unit Unit Price Cost of Item
1 REV. DATE:4/01/10
0VTO/t,:31V( 'A32 z
:aa6eueW uoponajsuo:)
:a4ea :iosinaadnS uol:pna;suo:)
:ajea ------ :A aaedaa
9 6 0Z/L 619 a p d
-pagla:)sap )l.lonn;o adAl 944 aoI suolsiAoad lepads 13ealuo:) pue
suolleDijpads paepuelS a4l 441nr► aouepao:):)e ul aq of sluawa.inseaua pue slepalew >Iiom IIV
le;ol snolna.Id +aapap a6ue4Z)slyl*
58I *SAVa ONI MOM 1V1O1
:p ji as uol;ea!1l4snr of;eue x3
:31dU _ I :31t/a
58T , lewi snolnaad 0 *.aapap a6ue4:)s141 ana , OST j Iaea;uo:) leui5po
SAd(3 ONI INO/A 'Al
IF L9'tiL'[ 8$ 31HWI1S3 "d SIHl
suwnlo:) wa;I;o;soD ay;;o le;ol*
L9'tiLI'8$ * d3a21O 3JNVH0 30 15O0 a31t/WI.LS3 IVIO1
I ❑ aaamcpa?l-pay:,e:ay 94ewils3;uapuadapul ❑
well fo;soo aoud im I muff uoi;duosaQ wad 'ON T9 -ON'4oS
A7N0 3Sn SN1lM033d HO-4 - •oN 0,7=43
a/gegijddd;oN ® (S)WRI Add ONLLSIX3 013Sd3M33a/3SV3H3NI
i fI ❑ i a-quznb32!-Papeaay ajewps3 auapuedepuj I ❑
Z'o0Z :ON 31Id t N331
Chapter 52 Local Administered Projects
Appendix 52.106 Change Order
Checklist
Change Order
Question Yes No.' NIA
1. Does the change order alter the termini,character,or scope of the work? 0 Z 0
If yes,you must have H &LP approval to be eligible for federal finds. 0 0 0
If yes,you must submit a revised Page 1 of the prospectus. 0 0 0
2. Is the Change Order over$7,500.00 and outside the scope of work? 0 0
If yes,the change cannot be a change order and must be an independent work. 0 0 0
3. Does the Change Order detail all items involved with the change? 0 0
4. Does the Change Order include an adjustment in working days'? 0 0
If yes,the time extension must be stated in the Change Order. 0 0 0
If yes,an independent engineer's estimate of time must be included to document the 0 0 0
extension.
If no,that must be stated in the Change Order. 0 0 0 tit
5, Does the Changc Order alter the DBE Condition of Award? lr 0 0
If yes,you must obtain concurrence form Local Programs. 0 0 0
If yes,you must obtain the DBE's signature on the Change Order. 0 0 0
G. Does the Change Order involve a material substitution? d 0 0
If yes,you must determine if a material credit is appropriate. 0 0 0
7. If Change Order work started prior to it's execution,prior verbal approval by the 0 0
Approving Authority must be granted and documented.
S. Has the Change Order been signed by the contractor? 0 0 0
9. Has the Change Order been executed by the Approving Authority? 0 0 0
If you are a"non CA Agency",you must have the acting CA Authority's approval. 0 0 0
10.Has an independent engineer's estimate justifying the costs and time extensions been 0 0 ®'
completed and documented?
1].Has a detailed menho outlining the chronology of events,basis of need,costs and d 0 0
working days been prepared and placed in the file accompanying the Change Order?
4�
Appendix 52.106 Change Order Page 1 of 1 �'
Revised 413012014
r7
r�'�" .5"�+¢q'����f'exrT ,�'�M1s".'..Y'..;�"s..as^r.^u, '"h'-,�"�`�^�'�'�'�'z•Mpx. .."?..::�':t�,+r,'.�: ,`i :.T`e.`�'i.3 :'�"-a"w,��.��'._ '�"- #�",�,,et ,�.,.:�'.
WSDOT Local Agency Guidelines M 36-63.27 Page 52-19
April 2015
CONSTRUCTION
KENT MANAGEMENT
WASHINGTON
MEmo To FILE
Central Ave.S. Pavement Preservation and Utility
Project Name: Central
5/16/2016
Improvements
Contractor: Marshbank Construction, Inc, Contract No: 13-3004
Owner: City of Kent Federal Aid No: STPU L-1071(006)
Subject: Change Order 010 Chronology of Events
Message
3/9/2016—During the installation of the water main connection in the intersection of Willis and Central Ave S,the
contractor encountered 2 unmarred utilities which caused production losses..
3/10/2.016—The City and MCI agreed to a production impact of 4 totals hours.
4/22/201G MCI provided material supplier invoices
5/13/2016—City reviewed and agreed to pricing as fair and reasonable.
Cameron Bloomer,PE_ ResidewntEngineer 5/16/2016------ ----------
1 of 1 P-11 (Rev. 8/11)
Cameron Bloomer
From: McConnell, Phillip <PMcConnell@kentwa.gov>
Sent: Thursday, March 10, 2016 11:54 AM
To: 'Jason Heide'; Cameron Bloomer
Cc: Eric Arntson;JC Brown; Connor, Eric
Subject: RE: Willis Connection
All,
I'm in agreement with the 4 hours of additional effort due to unforeseen conditions.
Phil McConnell, Owners Representative
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5542 1 Cell 253-261-5685
prncconnellna KentWA.00v
CITY OF KENT, WASHINGTON
KentWA.gov Facebook You'rube
F!.Enio_...h':.i3'r.4:.1',-t: S'.CJV[l:+.Jt4rdi1:;Y1'FSt'i'ri;;.. Pik iFJ'i;i•!!; r'Fi!.,c Ph71!.
From: Jason Heide [mailto:jason@marshbankconst.com]
Sent: Thursday, March 10, 2016 7:18 AM
To: Cameron Bloomer
Cc: Eric Arntson; JC Brown; McConnell, Phillip; Connor, Eric
Subject: Willis Connection
Cameron,
Eric and I have been discussing the events of the connection at Willis last night. My understanding is that it was
established that we had a change of conditions with the unknown ductbank and CI 16".
We'd like to proceed with payment on the change under force account. The changes affected production and planning
to complete the work. The report I am getting is that we lost about 4 hours to revisions, plus the cost of additional
materials.
We will write up a FA sheet for your review and signature later today.
Thanks
Jason
1
Cameron Bloomer
From: JC Brown <brown@marshbankconst.com>
Sent: Friday, April 22, 2016 9:16 AM
To: Cameron Bloomer
Cc: Steve Cox;Jason Heide
Subject: RE: FA invoices for PE 8
Attachments: Kentox Side Sewer HD Supply.pdf, HD Supply Willis Water Connection.pdf; Provac
Cleaning out Baker Tank.pdf
Importance: High
Cameron,
Please see the attached invoices for the Willis Intersection water line connection, provac to clean out the baker
tank for 2hrs, & HD supply for the coupler needed for the kentox side sewer repair. HD Supply will not take the 12"
valve that was purchased per plan for the Willis intersection tie-in due to the fact that the valve was bolted to fittings
and then unbolted for the different style valve. Please let me know if you have any questions.
Thank you,
JC Brown
Project Engineer
Marshbank Construction, Inc.
P.O. Box 97
3304 Old Hartford Road
Lake Stevens,WA 98258-0097
(425)499-6651 Cell
(425) 377-9708 Office
(425) 377-0709 Fax
From:Cameron Bloomer[mailto:cbloomer@kbacm.com]
Sent:Tuesday,April 19, 2016 3:08 PM
To:JC Brown <brown@marshbankconst.com>
Subject: FA invoices for PE 8
JC,
I am missing the pro vac invoice for the baker tank and the HD supply invoice from the Willis connection.
Thanks,
Cameron
Sent from rm Vcrizon Wircicss 4G LTE smartphone
1
FA Sheet No.:
c DAILY REPORT OF
MANAGEMENT
CONSTRUCTIONFORCE ACCOUNT '(ORKEL�....
GEMENT
Project Name: central Ave S. Pavement Preservation and Utility Impro,Project No: 13-3004
Item No.: Date: 3/9/2016
Description of Work: Premium Time for Flaggers due to change of conditions during water main connection in the Willis
Intersection.
Work by Subcontractor?: (mart, ""if yes)
Prime Contractor: Marshbank Sub-Contractor:
r
Over Time Double Time DOLLAR
FIRST NAME OCCUPATION HOURS VVWR HOURS WWR AMOUNT
Laura R Flagger/TCS 2 16.66 2 33.32 $ 99.96
Heather 0 General Laborer 2 18.97 2 37.94 $ 113.82 I
Jody B Nagger 2 15.21 2 30.42 $ 91,26
Tamara H Flagger 2 15.21 2 30.42 $ 91.26
$
$ -
SUBTOTAL-LABOR: $ 396.30
LABOR OVERHEAD&PROFIT o@ 29% $ 114.93
LABOR TOTAL $ 511.23
pnommommmom
HOURS HOURS ADJUSTED STANDBY DOLLAR
EQUIPMENT AND ATTACHMENTS WORKING STANDBY RATE RATE AMOUNT
MCI-0105 F150 4 $ 23.74 $ 94,96
#N/A $ -
HN/A $ -
SUBTOTAL-EQUIPMENT $ 94.96
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 19.94
EQUIPMENT TOTAL '$ 114.90
MATERIALS!SERVICE DESCRIPTION QUANTITY UNIT PRICE AMOUNT
SUBTOTAL-MATERIALS $
MATERIALS OVERHEAD&PROFIT cru�ii 21%n $ -
MATERIALS TOTAL $ -
Verification of Hours Worked: TOTAL: $ 626.13
12%MARKUP(for prime when subcontract work) $ -
I
Contractors Representative(pnnted name) i
SHEET TOTAL: $ 626.13
Contractor's Representative Signature Date
sentative(,printed name)
Prime Markup on Subcontractor:
12 : <$25,000
owner`s Re resentative Si nature Date 10%: $25,000 to$100,000
Pay Estimate Entered: 7%: >$100„000
Date: El If checked,this work is in dispute. By signing this form, parties are
By:
agreeing to the time and effort needed to accomplish the task. Entitlement
. � . .
FA Sheet Wo :
MANAGEMENT FORCE ACCOUNT WORKED
Project Name: central Ave S. Pavement Preservation and Utility Impro,Project No� 13-3004
CONSTRUCTION
Item No.: CO xx Date: 3/9/2016
Description of Work: Production Impacts for due to confficts with unforseen utilities during the water main connection in
the Willis St Intersection
Work by Subcontractor?: (mark"x"if yes)
Prime Contractor: Marshbank Sub-Contractor
S RAIGHT TIME OVERTIME DOLLAR
FIRST NAME OCCUPATION H 07UI R S WWR HOURS WWR AMOUNT
Debbie W Operator Eng Grp2 - 4 64.33777
LABOR TOTAL $ 3,10307.
HOURS HOURS ADJUSTED STANDBY DOLLAR
EQUIPMENT AND ATTACHMENTS WORKING STANDBY RATE RATE AMOUNT
IT, - EQUIPMENT TOTAL 1,714.921
MATERIALS SERVICE DESCRIPTION QUANTITY IT PRICE
MATERIALS TOTAL $ 2,730.55
Verification of Hours Worked: TOTAL: $ 7,548.54
12%MARKUP(for prime when subcontract work) $ -
oes Representative(prinled name)
Ownei's Representative(printed name) Prime Markup on Subcontractor:
Date: ❑ If checked,this work is in dispute. By signing this form, parties are
By: agreeing to the time and effort needed to accomplish the task. Entitlement
2 of 2
Invoice# F233517
HOPSUPPLY Invoice Date 3111/16
WATERWORKS INVOICE Account# 111581
Sales Rep JOEYTAYLOR
1830 Craig Park Court Phone# 360-651-1147
St.Louis,MO 63146 Branch# 588 Marysville,WA
(2 Total Amount Due $2,256.65
Remit To:
HD SUPPLY WATERWORKS,LTD.
P.O.BOX 6039
CYPRESS,CA 90630
298 1 SP 0.485 E0298X 10459 D1664321869 P3160309 0001:0001
II�II�e�1111llrl1 1111111111111'1111111111111°II�1[�I'l�llv�l'' Shipped to:
MARS,HBANK CONSTRUCTION INC CENTRAL AVE&S 259TH ST
ACCOUNTS PAYABLE KENT,WA
PO BOX 97
LAKE STEVENS WA 98258-0097
------------ ----------------------- ---------------- -----------------------------------------CUSTOMER JOB- 1568-05 KENT CENTRAL AV
-------------------------------------------------------------------------------
Thank you for the opportunity to serve youl We appreciate your prompt payment,
Date Ordered mate Shipped Customer PO# Job Name Job# Bill of Lading, Shipped Via
3/10/16 3/10/16 1568-05 KENT CENTRAL AV 1568-05 OUR TRUCK
Quantity
Product Code Description Ordered Shipped B/O Price UM Extended Price
5112A236123 12 A2361-23 IVJ RW GV OL L/ACC 1 1 1754.07000 EA 1,754.07
21112AF 12 MJXFLG ADPT(1)CP DI C153 1 1 186.63000 EA 186.63
21AMF812RGAP RM 12RGAP 121N ROMAGRIP DI 3 3 93.76000 EA 281,28
24AFGFR12A 12X118 FLG FF RR GASKET 1 1 7.16000 EA 7.16
24AFBNKZ12 12 ZINC PLTD HEX BOLT&NUT KIT 1 1 27.51000 EA 27.51
SEE ATTACHED FOR POD
yt
..........
InvoicesbyEmail 0SUPPLY
Save time. WATERWORKS
Save trees. Local Knowledge
Go paperiess. Local Experience
• Local Service,Nationwide'
Freight Delivery Handling Restock Misc. Subtotal: 2,256.65
Other: 0.00
Terms: NET 30 Ordered Sy:ERIC Tax: Mo
Invoice Total: $2,256.65
This transaction Is governed by and subject to HD Supply Waterworks'standard terms and conditions,which are rated by reference and
accepted. To review these terms and conditions,please visit:www.waterworks.hdsupply.col000'po C.
m/Tand