HomeMy WebLinkAboutPW13-103 - Change Order - #22 - Goodfellow Bros., Inc. - SE 256th St Improvements - 07/28/2014 ` SY
Records on
KENT z Ey� Document
SY
CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name. Good Fellow Brothers, Inc.
Vendor Number:
]D Edwards Number
Contract Number: PW13-103
This is assigned by City Clerk's Office
Project Name: SE 256th Street Improvements
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other: #22
Contract Effective Date: 06/6/2013 Termination Date: 12/31/2014
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Phil McConnell Department: PW - ENGINEERING
Detail: (i.e. address, location, parcel number, tax id, etc.):
S:Public\RecordsManagement\Forms\ContractCover\adcc7832 1 11/08
K A6 T
WqS NINOTON /� /� ® �y �® ,�¢ /�
CHANGE ®R®ER N . ##22
NAME OF CONTRACTOR: Goodfellow Brothers. Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER: SE 256t" Street Improvements
ORIGINAL CONTRACT DATE: June 6 2013
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Remove and salvage existing PSE vault, bid item omitted in error. To
be reimbursed in full by PSE.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $5,208,988.60
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $61,342.73
(incl, applicable WSST)
Current Contract Amount $5,270,331.33
(incl. Previous Change Orders)
Current Change Order $1,395.43
Applicable WSST Tax on this Change $132.57
Order
Revised Contract Sum $5,271,859.33
i
i
CHANGE ORDER - 1 OF 3
I
i
Original Time for Completion 300worldngdays
(insert date)
Revised Time for Completion under 304 worldng days
prior Change Orders
(insert date)
Days Required (t) for this Change 0 calendar days
=_ - -Order—
Revised - — - -- --
Time for Completion 304worldngdays
(insert date)
In accordance with Sections 1-04A and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
L
CONTRACTOR: CI , i KENT:
By
(signature)
Print Name: cvi Print Name: Timothy 3ture LaPorte P.E.
Its U'ro ecy- may;., — Its Public Works Director
(title)
DATE: (title)
�,ZQ�/1 DATE:
CHANGE ORDER - 2 OF 3
® T FILE NO: 200.2
KIEN
CHANGE ORDER WORKSHEET NO. 22
Construction Management Division - Public Works
Project: SE 256th Street Improvements Project No.: 09-3012C
Project Engineer: Mark Madfai Fed-Aid No.: N/A
Owners Rep: Phil McConnell Contractor: Goodfellow Brothers
Date: 6/10/2014 -
I. PROPOSED CHANGE
Remove and salvage existing PSE vault
II. REASON AND BACKGROUND FOR CHANGE
Bid item omitted in error
III. METHOD OF PAYMENT
NEW PAY ITEM(S) [] Not Applicable
Change Order No. I I _ I 11 ( FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
10 Remove and dispose of 1 1 FA $1,395.43 $1,395.43
______—_existing PSE vault
--------- ----- —--- -- ——T— —--- ---
® Independent Estimate Attached CREATE PAY ITEM ONLY- Payment to be made I ® PAY THIS PAY ESTIMATE
- REQUIRED J____L at a later date upon com IP etion of we _ __ _
❑ Material Submittals Required - CC: Construction Coordinator New Sub Regrd_? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
_Sch..No. E31 No. Item Description---�— Qty _ Unit Unit Price Cost of Item
Independent Estimate Attached -REQUIRED
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. _ I ! FOR ACCOUNTING USE ONLY
Sch,_No._J a.[. No. _ Item_ Description Qty Unit I Unit Price Cost of Item
Independent Estimate Attached - REQUIRED
1 REV, DATE: 4/01/10
i.
K€NT FILE NO: 200.2
I
TOTAL ESTIMATED COST OF CHANGE ORDER * $1,395.43
*Total of the cost of Item columns
THIS PAY ESTIMATE $1,395.43
IV. WORKING DAYS
Original Contract L300 1 'Due This Change Order* 4 Previous Total
--- --- ----- - --- ---- 304
-DATE
DATE: �------ ---- � _
* I Explanation Justification Re wired: -- ---------- '..
TOTAL WORKING DAYS* 304
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: [t yw Date: 'r
Phil Wc-Co Hell
Construction Supervisor: Date:
Construction Manager: Date: 7 )`-( - ,LI
P ul Kuehne
i
I
2 REV. DATE: 4/01/10
FA Sheet No,:
DAILY REPORT WORKED
�!
FORCE ACCOUNT vVORKED KENT
Project Name: SE 256th Street Improvements Project No: 09.3012
Item No.: 10000 Date: 6/10/2014 -
Description of Work: Remove and dispose of PSE vault J04 at ST+/-6+M
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs I Hourly Rate Hrs OT Rate AMOUNT
jay foreman 3 63.01 $ 189.03
Mike operator 3 60,16
$ 180.48
Phil operator 3 59.6 $ 178 80
Steve opertor 2 60.16 $ 120.32
SUBTOTAL-LABOR: $ 668.63
LABOR OVERHEAD&PROFIT @ 29% $-,93 90
LABORTOTAL $ 862.53
EQUIPMENT,a
EQUIPMENT ORATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
hitachi 200 2 87.01 $ 174.02
JD 624 loader 2 70.20 $ 140,40
CAT 420 backhoe 1 42.35 $ 42.35
JD 50 mini excavator 1 26.10 $ 26.10
F150 pickup 3 19.18 $ 57.54
SUBTOTAL-EQUIPMENT $ 440.41
EQUIPMENT OVERHEAD 8,PROFIT @ 21% $ 92.49
EQUIPMENT TOTAL $ 532.90
MATERIALS./SERVICES/RENTALS : .
MATERIALS!SERVICES Quantity Units Unit Price DOLLAR AMOUNT
$
SUBTOTAL $ -
OVERHEAD&PROFIT @ 21% $ -
TOTAL $
Verification of Hours Worked: TOTAL: $ 1,395.43
12%MARKUP (for
Prime when subcontract work) $ -
Contractor's Representative Date SHEET TOTAL: $ 1,395.43
Owner's Representative Date
Comments
i