Loading...
HomeMy WebLinkAboutPW14-203 - Change Order - #9 - SCI Infrastructure, LLC - SR 516 to S 231st Way Levee Improvements - 03/16/2015 � Records Man ` Document CONTRACT COVER SHEET This is to be completed by the Contract Manager prior to submission to City Clerks Office. All portions are to be completed. If you have questions, please contact City Clerk's Office. Vendor Name: SCI, Infrastructure, LLC. Vendor Number: JD Edwards Number Contract Number: PW14-203- ;pO This is assigned by City Clerk's Office Project Name: SR 516 to S 231't Way Levee/Rusell Road Upper Levee Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract ❑ Other: Contract Effective Date: 8/27/2014Termination Date: Contract Renewal Notice (Days): Number of days required notice for termination or renewal or amendment Contract Manager: Toby Hallock Department: PW Engineering Contract Amount: 2,176,334.02 Approval Authority: (CIRCLE ONE) Department Director Mayor City Council Detail: (i.e. address, location, parcel number, tax id, etc.): Change Order#9 As of: 08/27/14 LA G I V ® CHANGE ORDER NO. #9 NAME OF CONTRACTOR: SCI Infrastructure, LLC. ("Contractor") CONTRACT NAME & PROJECT NUMBER:SR 516 to S 231st Way Levee Imp./Russell Road Upper Levee ORIGINAL CONTRACT DATE: August 27, 2014 This Change Order amends the above-referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: 1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: Add 19 each, 10" wide x 4' tall galvanized plate steel to Operations' property side of CIP retaining wall so the restoration of Operations' property wouldn't be delayed for the 6-month settlement period. 2. The contract amount and time for performance provisions of Section II "Time of Completion," and Section III, "Compensation," are hereby modified as follows: Original Contract Sum, $2,176,334.02 (including applicable alternates and WSST) Net Change by Previous Change Orders $77,474.69 (incl. applicable WSST) Current Contract Amount $2,253,808.71 (incl. Previous Change Orders) Current Change Order $1,90655 Applicable WSST Tax on this Change $181.12 Order Revised Contract Sum $2,255,896.38 I CHANGE ORDER - 1 OF 3 Original Time for Completion 120 working days (insert date) Revised Time for Completion under 127workin-days prior Change Orders (insert date) Days Required (f) for this Change 0 calendar days Order Revised Time for Completion 127working days (insert date) In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the Contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby ratified and affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written below. CONTRACTOR: CITY OF KENT ' (signature) @. signature) Print Name: `711S,,A LXA4J Print Name`.: ,m :S. 1 L2x " ter Its / ' J Its R&\'(, ,, \, S (title) (title) DATE: ""7-ti'— / DATE: _3 CHANGE ORDER - 2 OF 3 7APPRO�VEDTO FORM; signature required) ment II [In this field,you may enter the eleRronlc filepath where the contract has been saved] III CHANGE ORDER 3 OF 3 i �' T FILE NO: 200.2 w„ CHANGE ORDER WORKSHEET NO. 9 Construction Management Division - Public Works Project: SR 516 to S. 2315t Way Levee Project No.: 09-3006.2 Improvements - James/Russell Project Engineer: Toby Hallock Fed-Aid No.: Owners Rep: Jason Barry Contractor: SCI Infrastructure, LLC Date: 1/26/14 I. PROPOSED CHANGE Add 19 each, 10 inch wide x 4 foot tall galvanized plate steel to Operations property side of CIP retaining wall. II. REASON AND BACKGROUND FOR CHANGE Without addition of backfill plates restoration of Operations property would have been delayed for the duration of the 6 month settlement period required by specification. See SCI DCR #011970 and attached redline detail. III. METHOD OF PAYMENT NEW PAY ITEM(S) [] Not Applicable Change Order No. i i i _ i I FOR ACCOUNTING USE ONLY _Tc_h­N`­o._1 Item Description Total Qty this Unit Unit Price Total Estimated Cost of Est. city PE Item I 1 Additional Backflll Plates 1 1 LS $1 906.55 $1,906.55 _ -- --- —-— -. -- -- — - -- ---- ® Independent Estimate Attached ❑ CREATE PAY ITEM ONLY Payment to be made ® PAY THIS PAY ESTIMATE - REQUIRED __- __-- _I at a later,date upon completion_of_work .-_ ---I-_ --_---_-_.. Material Submittals Reauired - CC: Construction Coordinator - New Sub Reclrd? No DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable Change Order No. 1 1 _ i IFOR ACCOUNTING USE ONLY Sch No. item Description - „ 1 city_ Unit I Unit Price I. Cost of Item ❑ 1 Independent Estimate Attached -REQUIRED INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable Change Order No. iFOR ACCOUNTING USE ONLY SO- No. B I No. _ m Ite Description -Qty_ Unit- Unit Price i Cost of Item - - -- - - - -- 1 REV, DATE: 4/01/10 I �' T FILE NO: 200.2 w.�w ..a.o. Independent Estimate Attached - REQUIRED TOTAL ESTIMATED COST OF CHANGE ORDER * $1,906.55 *Total of the Cost of Item Columns THIS PAY ESTIMATE $1,906.55 J IV. WORKING DAYS Original Contract 120 Due This Change Order* 0 Previous Total -127 - -- —- J= DATE 7 16 14 _- -.-_. _ __. , DATE: * � Ex la nation Justification Re wired: - TOTAL WORKING DAYS* 127 *This Change Order + Previous Total All work, materials and measurements to be in accordance with the Standard Specifications and Contract Special Provisions for the type of work described. Prepared By: .i / _ Date: J n Barry Construction Supervisor: Date: Paul ehne Construction Manager: , . ,�j �,�, « Date; 7�/S Eric Connor II I' 2 REV. DATE: 4/01/10 - APPROXIMATE U �- SEE TYP JOINT DETAIL I SEE EL ECT CAL I III FILL PLATE (SEE IL JOINT PLACE AFTER ST 1/7 AND BEFORE BAI . FLATTEN ANY GP i BACK FACE a i FRONT FACE I 1" CHAMFER STRIP _ FULL HEIGHT OF JOINT 3" OPEN JOINT GROUT JOINT M0 T..S AT ¶FORMING E OF AlL TYP EACH SIDE VILL AFTER WALL CONSTRUCTION SECTION A SR 516 T LEVEE CONCRETE RETAINING WALL JAMES ST/RUS: I SCI Infrastructure, L L C Dafly Chst Rectxcl 011970 Project: SR516 to S 231st, Kent Job#1414 Date: 01/22/16 Descripliom Fill plates-I had to buy 114"x 10"x 20'steel and take it to get Galvanized at Ace;pick up steel and take to Job and cul into 4'long and them install onto face side of wall at every joint. HOURS DETAIL COST RECORD CODE S.T. O.T. D.T. I Total RATE EXTENSION Dick Daiker CA 5 5 58.54 292.70 Dick Daiker CA OT 0 79.95 0.00 '.. Gary Oliverson FM 4 4 58,54 234.16 Gary Oliverson FM OT 0 79.95 0.00 Trov Braun GE 0 61.33- Troy Braun GE OT 0 82.25 0.00 Kelly Braun TM 0 55.86 0.00 o� Kelly Braun TM OT 0 74.39 0.00 O Greg Letts OP 0 61,33 0.00 m Greq Letts OP OT 0 22.25 0.00 Jose Olvera LA 0 49.07 0.00 Jose Olvera LA OT 0 67.35 0.00 Sub-Total 526,86 Travel Time 0.00 Labor Markuo 152,79 Total Labor Costs 5879.65 w 1/2 Ton Truck w/small Tools 4 4 15.09 60.36 1 Ton Truck w/tools 0 19.40 0.00 O 138 Excavator 0 70.27 1 0.00 O Uu-mp Truck&Trailer 0 94.251 0.00 F- Backhoe w/Hoeoack 0 47.70 0.00 T300 Skid Steer Loader 0 37.44 0.00 PC 200 Excavator 0 86.41 1 0,00 Rental Trucking 0 130,00 0.00 460 Excavator 0 179.43 - 0.00 F- Double Drum Roller 0 22.90 0.00 z 0 0.00 u, 0 0.00 0 0.00 a 0 OM => Sub-Total 60,36 cs Equipment Markup !:: 12,68 w Total Equipment&Tools Costs 73.04 Dump Fees CY 0 3.00 F 0.00 '. 2x4 Spells Cadman tons 0 l5.25 0,00 1-1/4"Rock tons 0.0 7.50 0.00 w Bloch Steel#236032 1 1 565.98 565.98 0� Ace Galvanizina#181823 1 1 387.63 387.63 w 0 0.00 x F- Sub-Total 953.61 0 Sale Tax if a alicable 0,00 Markup 200.26 Other Costs $1,153.87 Contractor's Representative Sub-Total 1,906,56 Sales Tax on Rented Equipment Sub-Total 1,906.55 Subcontractor's Representative Owner's Representative No. Sheet 1 of 1 TOTAL $1 9a 6.65 Daily Cost Record 160E VALENTINE AVE SE PACIFIC,WA 26047• (253)218-0444 FAX:(253)218-0454- ^° Project P:CA; /�1 T_-UC. Job tl 141-14 Date �J�ci� Description must be com lele)•_ ` ��u Weather uuIS a �6 � y v n Fw�'F e { G. cr1- wG (a G 1 DETAIL COST RECORD CODE _HOURS S.T, O.T. D.T. TOTAL RATE EXTENSION J — Sub-Total - - `--"--' Labor Taxes& Fringe Benefits - ------- — -- Travel Time --- -- ---- —'-- — -- LaborMarkup -- -"-- -- Total Labor Costs ---- --`-�- - -- o - 0 LU -- - - - a — Sub Total Equipment Markup Total Equipment Costs 69 ' � _xl L9UU �1N� _WL6) GtASSV3 w -- �— � Sub-Total "- -.- - - ----- SalesTax(If applicable) Material Markup -- - Total Material Costs A - w Total Q he Costs Bond Insurance Taxes Miscellaneous Costs - / Contractor's Representative Sub-Total Overhead Subcontractor's Representatve _—__ LL--•_mom--y-�_ -- nor's Representative Sub-Total - Sales Tax No. Sheet of TOTAL -- — i W _ I r 05 CA CL CO a w F� ) .V W W ir ir >. Q ❑ ` y ExS ,�( 6� ,"tea i � \ W ° t a �r� Eea,°� a �o ti LU uj 4- CC o O -r N S :o •v ! q U W cm LL� [ 6{�{•F F-c ap 0 LL N T m LCm y' 8 uN F V r T�♦ � Q gyp' �! fi" q dzCL UO Z `fir�t N Cyu M p+M Vi s= 4f1�Js i� r- 3 r Fti fL;- ttl- O z IL `,il o T w� El El ❑ ❑ ❑ N 4f. _ 'LU W ree � J xa. O LLI ® F N l � � l N a 'QJa ® m d G r d iu r;taa p I�[iyC3 lE, C6 LU ul � O <o m y.�2f elk. SCI Infrastructure,L L G Daily Gust Tally Proioct: SR516 to S 231 st Job#1414 DATE DCR AMOUNT 01/20/15 21053 $ 647.74 01/22/15 11970 $ 1,906.55 << -- 01/22/15 21054 $ 8,823.88 01/23/15 21055 $ 1,854.67 01123/16 21056 $ 322,54 W c� TOTAL $ 13,555.28 it L l i r S � ii J t - IC1, f y.j I i