CHANGE ORDER NO. ##2
i
NAME OF CONTRACTOR: Tapani, Inc. ("Contractor")
CONTRACT NAME & PROJECT NUMBER: Briscoe Desimone Levee Improvements Reach 2 and 3
ORIGINAL CONTRACT DATE: January 30, 2014
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Install Coir 900 netting in lieu of jute matting on river side slope to
assist in protection against scour & erosion. The netting will enhance
stabilization of the slopes.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $6,709,555.56
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $54,750.00
(Incl. applicable WSST)
Current Contract Amount $6,764,305.56
(incl. Previous Change Orders)
Current Change Order $118,965.00
Applicable WSST Tax on this Change $11,301.68
Order
Revised Contract Sum $6,894,572.24
CHANGE ORDER - 1 OF 3
Original Time for Completion 200 working days
(insert date)
Revised Time for Completion under 200 working days
prior Change Orders
(insert date)
Days Required {f) for this Change 0 calendar days
Order
Revised Time for Completion 200 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below.
CONTRACTOR: CITY OF KENT:
r} I
By: By; 'i�i
—,y (signature) (signature) !
Print Name: . r`r(>j ��? Print Name:^ a,,,/ &'�ro�m
Its_ r, = Its4 �s9 a3i Pad
DATE: DATE: (title)
CHANGE ORDER - 2 OF 3
APPROVED AS TO FORM:
(applicable if Mayor's signature required)
Kent Law Department
I
[in this field,you may enter the efiedronic hlepath where the contract has been saved]
I
CHANGE ORDER 3 OF 3
i
i
_17KENT FILE NO: 200.2
CHANGE ORDER WORKSHEET NO. 2
Construction Management Division - Public Works
Project: Briscoe Desimone Levee Improve Project No.: 09-3010
Project Engineer: Kelly Casteel Fed-Aid No.: N/A
Owners Rep: Jason Bryant Contractor: Tapani Inc
Date: 8/6/2014
I. PROPOSED CHANGE
Install Coir 900 netting in lieu of jute matting on river side slopes
I
II. REASON AND BACKGROUND FOR CHANGE
Coir 900 netting is stronger.Coir netting will assist in protection against scour and erosion and
will enhance stabilization of the slopes.
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ® Not Applicable
Change Order No. 1 - I i i FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Est city this I Unit i Unit Price I Total Estimated Cost of
icity PE I Item
--
8 Coir 900 nettin Reach 2 6000 5520 i S — --
- --- — — _.._Y_. _$5 15 i $30,900 00
8 Coir 900 nettin Reach 3 14625 1.2_ 004 �_ __S _ T —
_ 9 _ — $75,318 75 —
8 Prime contractor mark up 1 1 LS $10,829 83 T $12,746.25
I Material Submittals Re ulred'- CC�Const�
® I Independent
P UI_REDEstimate Attached i ❑ ' CREATE PAY ITEM ONLY - Payment to be made ® PAY THIS PAY ESTIMATE
_ _ _ —later date ypon completion of work __ _
a ruction Coordinator `-_—`- ------------
New Sub Reqrd? ; No
i
DELETE EXISTING PAY, ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. 1 ! _ i iFOR ACCOUNTING USE ONLY
Sch No I B 1 No. I Item DescriP tic
----- n Cost of Item '
-- ...—__— ... __ ..QtY _ I Unit 'Unit Pnce ,
❑ Independent Estimate Attached -REQUIRED ❑ j
INCREASE/DECREASE TO EXISTING PAY ITEM(S) Not Applicable
Change Order No. ! - i ; FOR ACCOUNTING USE ONLY
Sch No B I. Na... t Item Description _ Oty Unit I Unit Price Cost of Item
i
❑ , Independent Estimate Attached -REQUIRED i ❑
1 REV. DATE: 4/01/10
KENT FILE NO: 200.2
TOTAL ESTIMATED COST OF CHANGE ORDER _!_ $l�18,965�00
*Total of the Cost of Item Columns
THIS PAY ESTIMATE �$101�,078.43 �
IV. WORKING DAYS
Original Contract 1 200 Due This Change Order* 0 i Previous Total 200
PATE: 1 8/612010
DATE:
a:n—a —c�r t-icW completion
EXP —�Vion Jusnu
TOTAL WORKING DAYS* �20O
*This Change order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: Date;
Jas Br an�tz
Construction Supervisor: �q Date:
Paul K hne'
Construction Manager: Date:
Eric Conner
2 REV. DATE:4/01/10
i
Kuehne, Paul
From: Bieren, Chad
Sent: Wednesday,August 06, 2014 5:18 PM
To: LaPorte, Tim; Kuehne, Paul
Subject: RE: Everything Everything - Coir Netting Net Change $92K - Briscoe Levee
I
Paul,
As we discussed earlier today, thank you for proceeding with this change order . I've spoken
with both Matt Knox and Jason Bryant, and agree the price is reasonable.
I
Chad
From: LaPorte,Tim
Sent: Tuesday, August 05, 2014 8:32 PM
To: Kuehne, Paul
Cc: Bieren, Chad
Subject: RE: Everything Everything - Coir Netting Net Change $92K - Briscoe Levee
Hi Paul: Chad and I were at the Council meeting that started at 5:00 p.m, and then National Night Out. I have just
returned. I am good with whatever decision that you and Chad come up with and will discuss with Tom tomorrow in
terms of change order implications.
Thanks,
Tim
From: Kuehne, Paul
Sent: Tuesday, August 05, 2014 5:30 PM
To: Bieren, Chad; Casteel, Kelly
Cc: Barry, Jason; Bryant, Jason; LaPorte, Tim; Howlett, Mark; Langholz, Ken; Gilbertson, Shawn; Knox, Matthew
Subject: RE: Everything Everything - Coir Netting Net Change $92K - Briscoe Levee
Hello,
Alter attempting to contact Kelly and Chad in person, via the phone and via email.., and after
briefly chatting with Howlett and chatting at length with Bryant; Z have allowed the Contractor to
continue landscape work tomorrow. Coir netting will begin tomorrow and added cost will be
incurred to switch back to jute.
Chad or Tim may need to talk to the Mayor regarding the $92K change.
Paul Kuehne, Construction Management Supervisor
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5543 1 Cell 253-740-5015
PKuehne@KentWA.00v
CITY OF KENT, WASHINGTON
KentWA.gov Facebook YouTube
1
From: Kuehne, Paul
Sent: Tuesday, August 05, 2014 4:14 PM
To: Bieren, Chad; Casteel, Kelly
Cc: Barry, Jason; Bryant, Jason; LaPorte, Tim; Howlett, Mark; Langholz, Ken; Gilbertson, Shawn; Knox, Matthew
Subject: Everything Everything - Coir Netting Net Change $92K - Briscoe Levee
Attached is the Contractor's price for Coir netting, Less the cost of the jute the bottom line for
this change is is an additional $92K.
From: Bryant, Jason
Sent: Tuesday, August 05, 2014 3:42 PM
To: Kuehne, Paul
Cc: Casteel, Kelly
Subject: RE: Call the Mayor- Coir Netting Net Change $81,675 - Briscoe Levee
Paul,
C&R tractor informed they were off a little on their quote. The actual price for the Coir and
stakes is $5.15SY. We will need to pay Tapani an additional 12% prime contractor mark up on
top of that. That being said the new total for both Reach2&3 will be $118,965. Let me know if
we are still a go with the new price.
I spoke with the landscaping contractor and he agreed no additional money was needed to
install the plantings.
Thank you,
Jason Bryant, Owners Representative
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5541 1 Cell 253-261-5663
K G N T ibrvantCa�KentwA gov
h.a ^.�,•. » www.KentWA.00v91 [,
rL@A}X Cc,IJGrpgg THE ENVXNOM 4LrgT OEFokE P Kn,R.-iINI THis E-MAIL
From: Knox, Matthew
Sent: Tuesday, August 05, 2014 3:30 PM
To: Kuehne, Paul; Bieren, Chad
Cc: Barry, Jason; Bryant, Jason; LaPorte, Tim; Howlett, Mark; Langholz, Ken; Casteel, Kelly
Subject: RE: Call the Mayor- Coir Netting Net Change $81,675 - Briscoe Levee
For what it's worth, I called Northwest Linings and cost out the Coir 900 product with 2"x2"x2'
stakes (approximately 2 per SY) and ended up with a material cost of $3.27JSY ($1.85JSY for
Coir 900 and $1.42/SY for stakes). With this information, the $4.35/SY ($5.26/SY including
contractor markup) including installation seems like a reasonable number to me (as long as it's
"all-inclusive" as we discussed, no additional costs for planting through this stuff or
hydroseeding under it).
Matt. j
2
I
From: Kuehne, Paul
Sent: Tuesday, August 05, 2014 12:11 PM
To: Bieren, Chad
I
Cc: Barry, Jason; Bryant, Jason; LaPorte, Tim; Howlett, Mark; Langholz, Ken; Casteel, Kelly; Knox, Matthew
Subject: Call the Mayor - Coir Netting Net Change $81,675 - Briscoe Levee
Importance: High
Hello Chad,
Attached is the Contractor's price for Coir netting. Less the cost of the jute the bottom line for
this change is is an additional $81,675,
We need to know today to stop the placement of jute beginning tomorrow, Cost are increasing
with time.
Paul Kuehne
From: Bryant, Jason
Sent: Tuesday, August 05, 2014 11:59 AM
To: Casteel, Kelly
Cc: Kuehne, Paul
Subject: FW: Change order for Jute Matting
Kelly,
The new price for Geo coir is $5.26 per SY. Our current bid price is $1.30 per SY.
Bid price:
Reach 2 6000 SY =$7800.00
Reach 3 14625 SY =$19,012,50
Total- $26812.50
New Price
Reach 2 6000 SY=$31,560
Reach 3 14625 SY=$76,927,50
Total- $108,487.50
i
Let me know what you think. j
Thank you,
Jason Bryant, Owners Representative
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-5541 1 Cell 253-261-5663
& tbrvant@KentWA.gov
ENT www.KentWA.aov
w . ,.
L :'� -0 z 1,LR THE rpui'bEtii. i.U,.- r'.a Ti - rt!ES @
From: Derek Kemppainen [mailto:derekk@tapaniunderground.com]
Sent: Tuesday, August 05, 2014 11:26 AM
To: Bryant, Jason
Cc: Justin McClellan; Ryan Nelson
Subject: Re: Change order for Jute Matting
3
i
Jason,
I believe the price does include the longer stakes. I just got this email forwarded from Al @ C&R.
i
MIKE,
THE NEW UNIT PRICE BASED ON GEO-COIR 900 AND WOOD STAKES FOR BID ITEM
8025 IS $ 4.351SY.
i
AL
Derek Kemppainen
Tapani Inc.
P: (360)-687-1148
C: (360) 975-2011
On Tue, Aug 5, 2014 at 11:15 AM,Bryant, Jason <JBrna kentwa. ov> wrote:
Derek,
Does that include the price of the longer stakes as well?
Jason Bryant, Owners Representative
Construction Management I Public Works Department
220 Fourth Avenue South, Kent, WA 98032
Phone 253-856-SS41 I Cell 253-261-5663
KENT
��-6lJorva ntCal KentWA.poV
www.KentWA.aov
LZAM, ,C'e u q rrryYPo .Ycl"c .L_r F iMTI - -
4
i
i
From: Derek Kemppainen [mailto:derekk@tapaniunderaround com]
Sent: Tuesday, August 05, 2014 11:02 AM j
To: Bryant, Jason
Cc: Ryan Nelson; Justin McClellan
Subject: Change order for Jute Matting
Jason,
The new Jute matting from C& R tractor is $4.351SY+21%markup is $5.26JSY.
Let me know if you have any questions!
Derek Kemppainen
Tapam Inc.
P: (360)-687-1148
C: (360) 975-2011
5
I
i
Invoics,No. 10189479
i Dale 81812014 I
Order No. W0088028
WESTING, Shipper Is S0209083
G E O S Y N T H E T I C PRODUCTS Order Type Woodinville Sales Order
Customer ID CRT100
ACF West,Inc.Is a D.B.A.name for N.W.Geosynthelles,Inc.
8951 S.E. 76th Drive, Portland, OR 97206 503.771.6115 800-878.5115(tax)503-771.1161 PAGE 1
I
III
{
C&R TRACTOR AND LANDSCAPING Mike 360-431-6786 -
3829 PLEASANT HILL ROAD C&R TRACTOR AND LANDSCAPING
KELSO,WA 98626 19201 SOUTH 62ND
Kent,WA 98626
OUR TRUCK MIKE (360)577-8286 Stock
i
Nile 0
I
8/4/2014 Net 3D Days Aaron Schmidt TAG
7�7
502109005 13.00 ROLL 13.00 0.00 460.800 0,00 5,990.400
900g Coir Fabric 4M x 50M
521500053 20.00 EACH 2O.00 0.00 92,000 0,00 1,840.000
North American Green 12"Eco-STAKE,500e1.
1 r
r01
' _ 5
i
FREIGHT Freight Charge J 500.00 J
Sales Total 7,830,40
Please pay flnm this invoice
Shipping&Handling 0,00
Misc.Charges 50000
Statements by request only Tax Total 0.00
8,330.40
Less Palo Amount 0,00
Thank you for your business
- 0 8,330.40
i
l
ppp ,..... ...-..n.c�•vGR'F}.. ACFw
. Invoice No. I0189481
Dote8t8/2014
Order No, W0088069
E TIN,, Shipper ID S0209120
• G E O S Y N T H E T I C PRODUCTS order Type Woodinville Sales Order
ACF West,Inc,is a D.BA,name for N.W.Geosynthelics,Inc. Customer ID CRT100
8961 S,E, 76th Drive, Portland, OR 97206 603.771.6116 800.878-5116(fax) 503-771-1161 PAGE 1
C&R TRACTOR AND LANDSCAPING Mike 360-431-6786
3829 PLEASANT HILL ROAD C&R TRACTOR AND LANDSCAPING
KELSO,WA 98026 19201 SOUTI I62ND
Kent,WA 98626
0 • •'1 1 1 _ f B 0
OUR TRUCK MIKE (360)577-8288 Stock
T-:
816v 1�2014 Net 30 Days Aaron Schn TAC
__'-. • P'1 1 P 1 • 1 _ III
502109005 12.00 ROLL 12.00 0.00 460,800 0,00 5,529.600
900g Coir Fabric 4M x 50M
521500053 5.00 EACH 5.00 0.00 92.000 0,00 460.000 .l
North American Green 12"Eco-STAKE,500cI, i
f
I
NFC NO FREIGHT CHARGE 0,00
I�
Sales Total 6,989.60
Please pay from this invoice
Shipping&Handling 0.00
Misc.Charges 0.00
S(alernenls by request on y - --- _ Tax ToTal —0:00-
5,989.60
Less Paid Amount 0.00
-Thank you for your business
u 5,989.60
Invoice No, 10189481
[)are 8/812014
Order No, W0088069
ESTINC, Shipper ID S0209120
A
G E O S Y N T H E TIC P R O D U C T S Order Type Woodinville Sales Order
Customer ID CRT100
ACFV%vm1k Inc,Is a D,BA,name for NW Goosynthecres,Inc,
8951 S.E. 76th Drive, Portland, OR 97208 603-771-5115 800-878-6116(fax) 503-771-1161 PAGE 1
01i
C&R TRACTOR AND LANDSCAPING Mike 360 431-6786
3829 PLEASANT HILL ROAD C&R TRACTOR AND LANDSCAPING
KELSO,WA 98626 19201 SOUTH 62ND
Kent WA 98626
EjER'T1 MIKE (360)577-8288 Stock
N I
502109005 12.00 ROLL 12.00 0.00 400.800 0.00 5,529.600
9009 Coir Fabric 4M x 60M
521500053 5,00 EACH 5.00 0100 92.000 0,00 460.000
North American Green 12"Eco-STAKE,500c1,
NEC NO FREIGHT CHARGE 0,00
Sales Total ,98
9.60
Please pay fi-0111 this invoice Shipping&Handling 0.00
Misc.Charges 0.00
Tax Tool— 0.00
8,989.60
Less Paid Amount 0,00
Thank you for your business �VE3� 8'989m
Shipper ID S0210496
Sales Order No. W0088461
+ _ _ OrY L WGtj,� - Order Type Woodinville Sales Ordel I
._.._.._.... Yf'N;-4ET4G PF3;OD:U C.'I^
-- Customer ID CRT100
ACF West Inc,Seattle
15540 Woodinville-Redmond Road,Bldg.A#400, Woodinville,WA 98072
Ph: 425.415-6115 800-423-4567 (fax)425-415-6126 PAGE 1
II
C &R TRACTOR AND LANDSCAPING Mike 360-431-6786
3829 PLEASANT HILL ROAD C &R TRACTOR AND LANDSCAPING
KELSO, WA 98626 19201 SOUTH 62ND
Kent, WA 98626
OUR TRUCK 1 (360)577-8288 Stock
8 225/2014 Net 30 Days Jeremy Schoenrock SEA Yes .
Ill I ME
00001 502109001 4.00 ROLL 4.00 0.00 MAIN 4.00
900g Coir Fabric 2M/!x SOM y
Notes:
j
i
i
Notes: NEEDS ASAP
NFC NO FREIGHT CHARGE CCCsss"'
RECEIVED BY:
We appreciate your business.
*Receiving Document only-Invoice to follow**All returns must be approved and are subject to restocking fee*
Invoice No. 10190225
Date 812012014 1
Order No. W0088235
Shipper ID S0209661
G E O S Y N T H E T I C PRODUCTS Order Type Woodinville Sales Order
ACP West,Inc,is a D.B.A.name for N.W.Geosynlhellcs,Inc. Customer ID CRT100
8951 &E. 76th Drive, Portland,OR 97206 603-771.5115 800.878-5115(fax)503.771.1161 PAGE 1
I
I �
i
C&R TRACTOR AND LANDSCAPING Mike 360.431-6786
3829 PLEASANT HILL ROAD C&R TRACTOR AND LANDSCAPING
KELSO,WA 98626 19201 SOUTH 62ND
Kent,WA 98626
90 'n("7
L
a •e o•r P P ♦ y. e
OURTRUCK MIKE (360)577-828B Stock
I
8/13/2014 Net 30 Days Aaron Schmid! TAG
502109005 26.00 ROLL X00 0.00 400.800 0,00 . 11,980,800
900g Coir Fabric 4M x 50M
r I
l
i
! 1
NFC NO FREIGHT CHARGE 0.00
I
Noses. Deliver Tuesday 8-19-14
Sales Total 11;980.80
Please pay from this invoice
Shipping&Handling 0,00
Miso.Charges 0.00
Statements 6y request only-- _ -Tax Talat
11,980.80
Less Paid Amount 0.00
Thank you for your business
- e 11,980.80
r
Invoice No. 10190338
F - Dale 8121/2014
Order No. W0088326
W
ESTINC. Shipper lD S0210006
AC° a a Order Type Woodinville Sales Order t
GE05YNTHETIC PRODUCTS Customer ID CRT100
ACF West,Inc.is a D.e A.name for N.W.Geosynn ics,Inc. PAGE 1
8951 S.E.76th Drive, Portland, OR 97206 503-771.5115 800-II76.5115(fax) 503.771.116
I
°
7Mike 360 431-6786
C 8 R TRACTOR AND LANDSCAPING C g R TRACTOR AND LANDSCAPING
3829 PLEASANT HILL ROAD ' 19201 S 620d at
�aI a� f y;
KELSO,WA 96626 (- Ken4,WA 98626
fir.7—
P-r P
MIKE (360)577-8268 Ken(levees
OURTRUCK
Aaron Schmidt SEA
81 612014 Net 30 Days
P PP r
2000 ROLL 20.00 ° 0.00 460.800 0.00 9,216.000
502109005
goog Colr Fabric 4M x 50M
0.00
NFC NO FREIGHT CHARGE
Saes Total 9,216.00
Please)ray Dom this invoice
Shipping 8 Handling 0.00
Misc.charges 0,00
Tax Total 0.00
Statements by request 01111), �9,2woo
Less Paid Amount 0.00
9.215.00
o )obusessThank you r ur n _ a
I
I
i
l OE
Invoice No. 10189858
t tl=l Date 8/14/2014
Order No. F0085258 I,
E 9INC, Shipper l0 S0209647
G E O S Y N T H E T I C PRODUCTS order Type Fife Sales Order
-. .- - CustomeriD CUM
ACT West,Inc,is a D.B.A.name for N.W.Geosynthetics,Inc.
8951 S.E.76th Drive, Portland, OR 97206 503-771-5116 800.878-5115 (fax) 603.771.1161 PAGE 1
i
C&R TRACTOR AND LANDSCAPING C&R TRACTOR AND LANDSCAPING
3829 PLEASANT HILL ROAD 3829 PLEASANT HILL ROAD j
KELSO,WA 98626 KELSO,WA 98626
i
L.
_ _ e•� i e - _. e a e P
WiII Call MIKE (360)577.8268
Stock
• e
811 31 2 0 1 4 Net 30 Days - Scott Etzkorn
TAG
682220025 100.00 EACH 100.00. 0.00 0.590 0.00 59.000
Fir Stakes, 2'x2"x2"
i
i
i
0.00
NFC NO FREIGHT CHARGE
Sales Total 59.00
Please pay from this invoice Shipping&Handling 0.00
Misc.-Charges ------
Tax Total 0.00
Statements by request only 69.00
Less Paid Amount 0.00
i
Thank you for your business 59.00