Loading...
HomeMy WebLinkAboutPW14-138 - Change Order - #2 - R.L. Alia Company - 64th Ave S Channel Improvements - 11/17/2014 Records Managerne" 6t - KEI�!Y Document CONTRACT COVER SHEET This is to be completed by the Contract Manager prior to submission to City Clerks Office. All portions are to be completed. If you have questions, please contact City Clerk's Office. Vendor Name: R.L. Alia Company Vendor Number: 36810 ID Edwards Number Contract Number: -"" " ' Q• 11171®/YF— 6oj This is assigned by City Clerk's Office Project Name: 64th Avenue South Channel Improvements UPRR Description: ❑ Interlocal Agreement M Change Order ❑ Amendment [I Contract ❑ Other: Contract Effective Date: 6/16/2014 Termination Date: Contract Renewal Notice (Days): Number of days required notice for termination or renewal or amendment i Contract Manager: Garrett Inouye Department: PW Engineering i Contract Amount: Approval Authority: (CIRCLE ONE) Department Director Mayor City Council Detail: (i.e. address, location, parcel number, tax id, etc.): Change Order #2 As of: 08/27/14 i I i wnsnnoroN CHANGE ORDER NO. # 2 NAME OF CONTRACTOR: R.L. Alia Company ("Contractor") CONTRACT NAME & PROJECT NUMBER: 64th Avenue South Channel Improvements UPRR i ORIGINAL CONTRACT DATE: June 16, 2014 This Change Order amends the above-referenced contract; all other provisions of the contract that are not inconsistent with this Change Order shall remain in effect. For valuable consideration and by mutual consent of the parties, the project contract is modified as follows: 1. Section I of the Agreement, entitled "Description of Work," is hereby modified to add additional work or revise existing work as follows: In addition to work required under the original Agreement and any prior Amendments, Contractor shall provide all labor, materials, and equipment necessary to: Additional storm work required to install system due to existing pipe being 24" not 12" per plans and existing pipe is deeper than plans placing the pipe below the ditch water elevation. 2. The contract amount and time for performance provisions of Section II "Time of Completion," and Section III, "Compensation," are hereby modified as follows: Original Contract Sum, $1,176,550.13 (including applicable alternates and WSST) Net Change by Previous Change Orders $1,591.66 (incl. applicable WSST) Current Contract Amount $1,178,141.79 (incl. Previous Change Orders) Current Change Order $4,105.52 Applicable WSST Tax on this Change $390.02 Order Revised Contract Sum $1,182,637.33 CHANGE ORDER - 1 OF 3 Original Time for Completion 120 working days (insert date) Revised Time for Completion under 121 working days prior Change Orders (insert date) Days Required (t) for this Change 1 calendar days Order Revised Time for Completion 122 working days (insert date) In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor agrees to waive any protest it may have regarding this Change Order and acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, contract acceleration, onsite or home office overhead, or lost profits. This Change Order, unless otherwise provided, does not relieve the Contractor from strict compliance with the guarantee and warranty provisions of the original contract, particularly those pertaining to substantial completion date. All acts consistent with the authority of the Agreement, previous Change Orders (if any), and this Change Order, prior to the effective date of this Change Order, are hereby ratified and affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change Order shall be deemed to have applied. The parties whose names appear below swear under penalty of perjury that they are authorized to enter into this contract modification, which is binding on the parties of this contract. 3. The Contractor will adjust the amount of its performance bond (if any) for this project to be consistent with the revised contract sum shown in section 2, above. i IN WITNESS, the parties below have executed this Agreement, which will become effective on the last date written belo . CONTRACTOR: CITY O T:-" 41 tJEF' .m By: f ` _,_ (srgnatur r Pr nt Nalrt :� f t`Hato e tr r Print Name: 1u .' Its ,dw Its C7' a_ (title) f (title) DATE: i DATE: ` CHANGE ORDER - 2 OF 3 ® FILE NO: 200.2 KEN_ T I CHANGE ORDER WORKSHEET NO. 2 Construction Management Division - Public Works Project: 64th Channel Improvements Project No.: 10-3030 Project Engineer: Garrett Inouye Fed-Aid No.: N/A Owners Rep: Phil McConnell Contractor: RL Alia Date: 10/10/2014 i I. PROPOSED CHANGE Additonal storm work required to install system II. REASON AND BACKGROUND FOR CHANGE (1) existing pipe 24" not 12 " per plans - Increased structure size from type 1 to type 2; IE of exisitng pipe 1.67 deeper than plans placing pipe below ditch water elevation - dewatering for storm installation III. METHOD OF PAYMENT NEW PAY ITEM(S) Not Applicable Change Order No. _ FOR ACCOUNTING USE ONLY Sch, No. Item Description i Total Est, Qty this Unit Unit Price Total Estimated Cost of city PE Item I i 4 Additonal storm work I 1 j 1 FA $4,105.52 j $4,105.52 _ {_required to install system - -- -------------- ��- I Independent Estimate Attached CREATE PAY ITEM ONLY- Payment to be made j PAY THIS PAY ESTIMATE -REQUIRED_--_—_--_— —_ at a_later date upon com�etion of work Material Submittals Required - CC' Construction Coordinator ( New Sub Reqrd? I No DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable Change Order No. I _ FOR ACCOUNTING USE ONLY Sch No B.I. No. _ — _Item Description_ Qty Unit - Unit Price _I Cost of Item - _ --_- --- _- Independent Estimate Attached -REQUIRED ! ❑ I INCREASE/DECREASE TO EXISTING PAYITEM(S) Not Applicable Change Order No. j _ I FOR ACCOUNTING USE ONLY ,Sch No 8.1.No, Item Description Qty Unit Unit Price ! Cost of Item . .-- --- ------ — ---- -- -..._ t_.- -_-.. I - Independent Estimate Attached - REQUIRED ' ❑ 1 REV. DATE: 4/01/10 i �K:E'•NT FILE NO: 200.2 TOTAL ESTIMATED COST OF CHANGE ORDER !*J:1�4�,1(05.52Z$ 4__ *Total of the Cost of Item Columns —-1 THIS PAY ESTIMATE $4:, .52 IV. WORKING DAYS Original Contract L120 Due This Change Order I 1 Pre-vious-Total ta 21 DATE- :j -16­/I-0-L2:0-14.- __L- --� ---—-----— --i-RATE: 1 10-10-2014 -*--t--fii lanationIJustification Re wired: TOTAL WORKING DAYS* L 22-�� = � *This Change Order + Previous Total All work, materials and measurements to be in accordance with the Standard Specifications and Contract Special Provisions for the type of work described, Prepared By: Date: Phil McConnel Construction Supervisor: It J, J/ Date: Paul K,u'6hn-e Construction Manager: Date: Eric Connor 2 REV. DATE:4/01/10 i FA Sheet No.: DAILY REPORT OF FORCE ACCOUNT WORKED j KENT Project Name: SE 256th Street Improvements Project No: 09-3012 Item No,: 3000 Date: 1 01912 0 1 4 Description of Work: discrepencies in storm plans, large pipe required type 2 manhole over depth required dewatering and extra effort Work by Subcontractor?: Prime Contractor: Goodfellow Brothers Sub-Contractor: LABOR' STRAIOHTTIME OVERTIME DOLLAR NAME CODE OCCUPATION Hrs Hrs OT Rate AMOUNT Rick owner t foreman 5 80.74 If 403.70 Paul operator 5 65.39 $ 326.95 Vito foreman 1 58.61 $ 58.61 Bobby operator 1 65.39 $ 65.39 Bill teamster 3 58.22 $ 174.66 SUBTOTAL-LABOR: $ 1,029.31 LABOR OVERHEAD&PROFIT @ 29% $ 298.50 LABOR TOTAL $ 1,327.81 EQUIPMENT EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT Komatsu 200 3 65.29 $ 195,87 Komatsu 650 1.5 190.08 $ 285.12 3/4 pickup 5 10.05 $ 50.25 pumps and generator 36 25.00 $ 900.00 10yd dumptruck 3 35.96 $ 107.88 SUBTOTAL-EQUIPMENT $ 1,539.12 EQUIPMENT OVERHEAD&PROFIT @ 21% $ 323,22 EQUIPMENT TOTAL $ 1,862,34 MAT E RIALSIS E RVIC ES/RENTALS MATERIALS/SERVICES Quantity Units Unit Price DOLLAR AMOUNT delmar saw cutting 1 Is $ 600.00 $ 600.00 aggregate 10 yd $ 15.65 $ 156.50 SUBTOTAL $ 756.60 OVERHEAD&PROFIT @ 21% $ 158.87 TOTAL $ 916.37 Verification of Hours Worked: TOTAL: $ 4,105.62 12%MARKUP (for prime when subcontract work) $ - i Contractor's Representative Date SHEET TOTAL: $ 4,105.62 Owners Representative Date Comments I Installation of 24" DIP Elevation of 24" DIP was 1.67' lower than plan design This placed the invert of the 24" DIP V below the mean water level in the ditch. The following is an accounting of additional costs/efforts that occurred to due to the invert of the 24" DIP being below the water level: 1) Construct a steel sheet plate coffer dam 2) Construct 3 below grade pump points 2A)10 Tons of 1.5"washed rock+$5/Ton to haul from Miles 3) Install 2 each 3"and 1 each 2" pump with 60 KW genset and pump for 36 hours to draw water level down near invert-Alia 4) Employ sawcutter to cut pipe to catch basin below knockout to enable 24" DIP to be set at proper grade - 10/3 invoice S)Dissassemble coffer dam and pumping system Paul 5 Rick 5 200 Komatsu 2 3/4 Ton 5 650 Komatsu 1.5 Added Type 2 CB on West Side Planned type 1 CB was too small for existing pipe.Alia directed to furnish and install type 2 CB at that location Added cost beyond bid items: 1) Solo dump truck and driver-go to Shope to pickup Type 2 CB and go to site 2) enlarge exacavation to set pipe to CB (vs type 1 CB)This includes additional base section bedding material 3) Return deleted type 1 CB and risers to Shope Concrete , Bill 3 Solo 3 Vito 1 Bobby 1 200 Komatsu 1 I i R. L. Alia Company Work for City of Kent 64th Ave South UPRR Culvert Installation of 24" DIP- Elevation of 24"DIP was 1.67'lower than plan design. This placed the invert of the 24" DIP 1' below the mean water level in the ditch. Additional costs/efforts due to invert of 24" DIP being below water level: 1)Construct steel sheet plate cofferdam; 2)Construct 3 below grade pump points; 2A) 10 Tons of 1.5"washed rock+$5/Ton to haul; 3) Install 2 each 3"and 1 each 2" pump with 60 KW genset and pump for 36 hours to draw water level down near invert; 4) Employ sawcutter to cut pipe to catch basin below knockout to enable 24"DIP to be set at proper grade; 5)Disassemle cofferdam and pumping system. LABOR Hrs/Units Rate Subtotal Total Rick Alia 5 $80.74 $403.70 Foreman $58.61 $0.00 Operator 5 $65.39 $326.95 Pipelayer $52.96 $0.00 Truck Driver $58.22 $0.00 Flagger $44.66 $0.00 Carpenter $62.66 $0.00 Cement Mason $62.47 $0.00 Laborer $52,09 0.00 $730.66 29% markup $211.89 $942.54 COMPANY EQUIPMENT 200 Komatsu 2 $65.29 $130.58 938 Loader $52.79 $0.00 650 Komatsu 1.5 $190.08 $285,12 10 CY Dump Truck $35,96 $0.00 1-Ton $12.39 $0.00 3/4 Ton pickup 5 $10.05 $50.25 JD 160 $58.17 $0.00 Alia pumps and genset 36 $25.00 $900.00 Rex Roller $9.86 $0.00 Compressor and Jackhammer $0.00 21%markup $1,365.95 286.85 $1,652.80 SUCONTRACTORS Del Mar Concrete Cutting 1 $600.00 $600.00 $0.00 0.00 $600.00 12% markup $72.00 $672.00 i MATERIALS RENTALS OTHER Washed Rock, Miles, Tons 10 $15.65 $156.50 $0.00 $0.00 0.00 o $156,50 21 /o markup 32.87 189.37 Total $3,456.70 i Mark Miller/Dal Mar 360-458-7551 P.1 DEL-MAR CONCRETE CUTTING & CORING Invoice .35820 152 100th St. S. Tacoma, WA 98444 Ph # (253) 537-0109FAX # (253) 535-0507 TO !�/ �"� DATE /0_ " / / JOB NO. I 7 � ,r c^ � .L j-Q � AWZO ? � CONTACT PERSON � �)• ( � ' JOB LOCATION TERMS: NET 30 DAYS, UNLESS OTHERWISE NOTED. ,' ,� S--• / �7' ,S� M i e { '�7 f � ✓�FVIi� � p if Intent I Affi avit of revailing wa es Paid PIC241se add 380,00 III i A FINANCE CHARGE OF 1.5% ON THE UNPAID PREVIOUS BALANCE WILL BE ' COMPUTED AT THE END OF EACH MONTH, IF CUSTOMER DEFAULTS OR IF SUIT ,�� IS BROUGHT TO COLLECT ANY OF THE PRINCIPAL OR INTEREST DUE OR OWING p\O V UNDER THIS BILL, DEL-MAR MAY CHARGE CUSTOMER REASONABLE ATTORNEY FEES AND COLLECTION COSTS. INVOICE pp pO p,�_°v. _ SAND GRAVEL COMPANY �. 400 VALLEY AVE NE • PUYALLUP,WA 98372-2616 • (253)833--3705 �CUSTOMER NO, PATE INVOICE NO. PAGE t:-wtuMilasSandandGravel.com 001910 08/lb/2U14 976198 1 MN McEO?.OSds c3t2p.TEORMRS mD 6 C4$l.p.^u^i.5 3lllp d(R{Va,m6 60iA@lLP,3L SALES 1r:ivx:*=oa Tiros.tr2s L ttvnto. I.,Z"' " Ru;;ry lefts L".,0, I253I8?3•]755 1 g3)E33-3700 t350i 491-7777 (253)53ff dtU� 060141$-7777 ` RL ALIA COMPAI4Y AUG 2 5 2014 10V WILLIAMS AVE, S RENTON, WA 98057 I I - 'DATE JOHNUMBER- JOB LOCATION ADDRESS TICKET NO.. ' QUANTITY' UNIT DESCRIPTION PRICE 7, UNT TAX . 'TOTAL 000162 64TH AVE SO CHANNEL IIKPRV. SPUR CULVERT KENT 08/18 211-277567 15 , 28 TN 1 3/8 " WASHED ROCK 10 . 6SO' 162 . 73 08/18 211-277574 14 . 15 TN 1 3/8a WASHED ROCK 10 . 650 150 . 70 JOB TOTAL LINE 313 . 43 PRODUCT RECAP 29 . 43 1130 1 3/8" WASHED ROCK N �U i f I AMOUNT DUE A 313 . 43 Form 140,24t47 COS 253-933-3131 i R. L. Alia Company Work for City of Kent 64th Ave South UPRR Culvert Added Type 2 CB on West Side Planned Type 1 CB was too small for existing pipe, Alia was directed to furnish and install a Type 2 at j that location. Additional costs beyond bid Items include: 1)Solo dump truck and driver to go to Shope to pickup a Type 2 CB and go to site; 2) Enlarge excavation to set pipe to CB (vs Type 1 CB). This includes additional base section bedding material; 3) Return deleted Type 1 CB & risers to Shope (Possible Restock Charge) LABOR Hrs/Units Rate Subtotal Total Rick Alia $80.74 $0.00 Foreman 1 $58.61 $58.61 Operator 1 $65.39 $65.39 Pipelayer $52.96 $0.00 Truck Driver 3 $58.22 $174,66 Flagger $44.66 $0.00 Carpenter $62,65 $0.00 Cement Mason $62.47 $0.00 Laborer $52.09 $0,00 $298.66 29% markup $86.61 $386.27 COMPANY EQUIPMENT 200 Komatsu 1 $65.29 $65.29 938 Loader $62.79 $0.00 650 Komatsu $190.08 $0.00 10 CY Dump Truck 3 $35.96 $107,88 1-Ton $12.39 $0.00' 314 Ton pickup $10.05 $0.00 JD 160 $58.17 $0.00 Alia pumps and genset $25,00 $0.00 Rex Roller $9.86 $0.00 Compressor and jackhammer $0.00 $173.17 21% markup $36.37 $209.54 SUCONTRACTORS $0.00 $0.00 0.00 $0.00 12% markup $0.00 $0.00 MATERIALS, RENTALS. OTHER $0.00 $0.00 $0.00 0.00 $0,00 21% markup $0.00 $0.00 Total $594,81