CONTRACT COVER SHEET
This is to be completed by the Contract Manager prior to submission
to City Clerks Office. All portions are to be completed.
If you have questions, please contact City Clerk's Office.
Vendor Name: R.L. Alia Company
Vendor Number: 36810
JD Edwards Number
Contract Number: ys a izrn /113y-Dpt
This is assigned by City Clerk's Office
Project Name. 64th Avenue South Channel Improvements UPRR
Description: ❑ Interlocal Agreement ® Change Order ❑ Amendment ❑ Contract
❑ Other:
Contract Effective Date: 6/16/2014 Termination Date:
Contract Renewal Notice (Days):
Number of days required notice for termination or renewal or amendment
Contract Manager: Garrett Inouye Department: PW Engineering
Contract Amount:
Approval Authority: (CIRCLE ONE) Department Director Mayor City Council
Detail: (i.e. address, location, parcel number, tax id, etc.):
Change Order#ly
As of: 08/27/14
i
W 43HINGTOn I
i
CHANGE ORDER NO. # 1
i
NAME OF CONTRACTOR: R.L. Alia Company ("Contractor")
CONTRACT NAME & PROJECT NUMBER: 64th Avenue South Channel Improvements UPRR
ORIGINAL CONTRACT DATE: June 16, 2014
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Lower existing irrigation due to irrigation in the railroad profile.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $1,176,550.13
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $0.00
(incl. applicable WSST)
Current Contract Amount $1,176,550.13
(incl. Previous Change Orders)
Current Change Order $1,453.57
Applicable WSST Tax on this Change $138.09
Order
I
Revised Contract Sum $1,178,141.79
I
j
CHANGE ORDER - 1 OF 3
Original Time for Completion 120 working days
(insert date)
Revised Time for Completion under 120 working days
prior Change Orders
(insert date)
Days Required (t) for this Change 1 calendar days
Order
Revised Time for Completion 121 working days
(insert date)
In accordance with Sections 1-04A and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written belo�r�� �7
CONTRACTOR: CITY K-ENT:
r � I
By 1 By
{signatur )
Print Name. rl;w., ACC Print Name. _ »
Its � .��.;� Its
DATE: 7 DATE: 4L// 7
I
CHANGE ORDER - 2 OF 3
• FILE NO: 200.2
KENT
CHANGE ORDER WORKSHEET NO. 1
Construction Management Division - Public Works
Project: 641h Channel Improvements Project No.: 10-3030
Project Engineer: Garrett Inouye Fed-Aid No.: N/A
Owners Rep: Phil McConnell Contractor: RL Alia
Date: 10-13/2014
I. PROPOSED CHANGE
Lowered existing irrigation
II. REASON AND BACKGROUND FOR CHANGE
Existing irrigation in the railroad profile
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ❑ Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch.No. Item Description Total Est. I Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
.-. j_.............. ---- —.... ___ --.__. 3 -_... ._-........... 1 -' ''----"1 '__ ---------------------
1 Lowered exlstina irrigatlon-_ 1 I _ 1 FA $1,453 57 _ $_1,453 57
— — --- --- _... _ _..—_.. __
Independent Estimate Attached ❑ CREATE PAY ITEM ONLY- Payment to be made 1 ® PAY THIS PAY ESTIMATE
... _REQUIRED__ -,---_ I at a later date upon,completion of
Material Submittals Required CC Construction Coordinator I New Sub Reqrd? No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change Order No. - FOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description Qty Unit Unit Price 1 Cost of Item
... .---� -- i - -- .-- -__ --
I
- - --- ------------ - —
i I
Independent Estimate Attached -REQUIRED
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. I FOR ACCOUNTING USE ONLY
Sch.No. B I No - Item Description City Unit _ Unit Price Cost of Item
_............ .__ .... ' - ---
------- ---'
-- ---- ..... _.y .. _ _ ---
--
..-- j-- ____ -—______ __- --- ..-.-
❑ i Independent Estimate Attached -REQUIRED
1 REV. DATE:4/01/10
i
• FILE NO: 200.2
KENT
" TOTAL ESTIMATED COST OF CHANGE ORDER * $1,453.57
*Total of the Cost of Item Columns
THIS PAY ESTIMATE $1,453.57
I
IV. WORKING DAYS
Original Contract 120 Due This Change Order* 1 Previous Total 120
_ I_- __
DATE _[_10/1 3 2014_ �__ ,____ _LDATE: � 10 13 2014 _
* Ex kmation Justification Re wired: work Interr6 ted critical path
TOTAL WORKING DAYS* 121
*This Change Order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
{ ; ! f
Prepared By: t 'lt ,, � Date: tf` ` '
Phil, "cCo r{ ll, /n
Construction Supervisor: h, •^{ Date:
Pal ehne
Construction Manager: Date: if A _
Eric Connor
(
i
I
2 REV. DATE: 4/01/10
I
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKED
Project Name: SE 266th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 10/13/2014
Description of Work: lower irrigation line below RR grade
I
Work by Subcontractor?: NO
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION He Hourly Rate Hrs OT Rate AMOUNT
operator 1.5 65.39 $ 98.09
carpenter 2.25 62.65 $ 140.96
carpenter 2,25 62.65 $ 140.96
teamster 2 58.22 $ 116A4
SUBTOTAL-LABOR: $ 496.45
LABOR OVERHEAD&PROFIT @ 29% $ 143.97
LABOR TOTAL $ 640.42
EQUIPMENT x
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
Kamotsu 200 1.5 64,86 $ 97.29
ii
10 yd dump truck 2 35.9B $ 71.92
1 ton service truck 1 10.28 $ 10.28
$
SUBTOTAL-EQUIPMENT $ 179.49
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 37.69
EQUIPMENT TOTAL $ 217.18
MATERIALSISE RVICESJRENTALS
MATERIALS!SERVICES Quantity Units Unit Price DOLLAR AMOUNT
McLendon 1 LS $ 79.12 $ 79,12
McLendon 1 LS $ 38,68 $ 38.68
NW Barricade 1 LS $ 19.96 $ 19.96
4 Inch DI pipe 18 LF $ 19.71 $ 354.78
$
SUBTOTAL $ 492.54
OVERHEAD&PROFIT @ 21% $ 103.43
TOTAL $ 696.97
Verification of Hours Worked: TOTAL: $ 1,453.57
12%MARKUP (for
prime when subcontract work) $ -
Contractors Representative Date SHEETTOTAL: $ 1,463.67
Owners Representative Date
Comments