CHANGE ORDER NO. #5
NAME OF CONTRACTOR: SCI Infrastructure, LLC ("Contractor")
CONTRACT NAME & PROJECT NUMBER: Hawley Rd Levee Improvements Phase II
ORIGINAL CONTRACT DATE: 8/28/2013
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Place yard drain, work required to complete project.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $442,679.76
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $35,430.60
(incl. applicable WSST)
Current Contract Amount $478,110.36
(incl. Previous Change Orders)
Current Change Order $410.31
Applicable WSST Tax on this Change $38.98
Order
Revised Contract Sum $478,559.65
CHANGE ORDER - 1 OF 3
Original Time for Completion 60 working days
(insert date)
Revised Time for Completion under 0
prior Change Orders
(insert date)
Days Required (t) for this Change 0 calendar days
Order
Revised Time for Completion 60 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authority of the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
protect to be consistent with the revised contract sum shown in section 2, above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written below
I�
CONTRACTOR: _ CiTy ENT:
By: By,
natur (signature)
Print Naari� r, {? S ec- 1 e Print Name: Tim LaPorte, P.E.
Its rG,U-ific-i f-1 � Its Public Works. Director
(title)
DATE: fib- —7 6 DATE: � f`f-
CHANGE ORDER - 2 OF 3
��• FILE NO: 200.2
`� KENT
w., .oro.
CHANGE ORDER WORKSHEET NO. 5
Construction Management Division — Public Works _
Project: Hawley Road Levee Project No.: 10-3010.5
Improvements Phase 2
Project Engineer: Kelly Casteel Fed-Aid No.:
Owners Rep: Alan Chau Contractor: SCI Infrastructure, LLC
Date: 4/14/2014
I. PROPOSED CHANGE
Place yard drain.
II. REASON AND BACKGROUND FOR CHANGE
Required to complete the project.
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ❑ Not Applicable
Change Order No. j ; - FOR ACCOUNTING USE ONLY
Sch No. Item Description Total Qty this Unit Unit Price Total Estimated cost Of
Est. Qty PE Item
_ 1 Yard drain 1 1 Sum $410.31 !l;410.31
i
Independent Estimate Attached I I CREATE PAY ITEM ONLY- Payment to be made ® I PAY THIS PAY ESTIMATE
_, -REQUIRED _ _ _, at a_later date upon co nDletion of work_____ --__-________— __-__--.— --_—
❑ Material Submittals Reauired -CC, Construction Coordirator New Sub Reqrd? T No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ❑ Not Applicable
Change Order No. - j j FOR ACCOUNTING USE ONLY
Sch. No. B 1. No_— Item DescriEtion _Qty Y—Umt—� Unit Price - Cost of Item--
-------- -- --- --- ---- —
❑ I Independent Estimate Attached -REQUIRED
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ❑ Not Applicable
Change Order No. _ FOR ACCOUNTING USE ONLY
Sch. No B.I. No. Item Description Qtym
Unit Unit Price — Cost of Ite --_-
--;----- -- ---- -
_
❑ Independent Esitimate Attached -REQUIRED ❑
1 REV. DATE- 4/01/10
40
� KEN,r FILE NO: 200.2
TOTAL ESTIMATED COST OF CHANGE ORDER * $410.31
*Total of the Cost of Item Columns
THIS PAY ESTIMATE $410.31
IV. WORKING DAYS
Original Contract i 6Q Due This Change Order* 0 Previous Total ! 60
DATE: _1_12 20 13 — DATE: 12 20 13 _
* Explanation Justification Required:
TOTAL WORKING DAYS* 60
*This Change Order+ Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared By: ;,! �;. Date:
Alan hau ' �Q�
Construction Supervisor: Pau -./P Date:
l r Date:
Construction Manager: � Date:
2 REV. DATE: 4/01/10
FA Sheet No
DAILY REPORT OF
FORCE ACCOUNT WORKED �N r
Project Name Hawley Rd Levee Improvements Phase 2 Project No 10-3010 5
Item No Date 4/14/2014
Descnption of Work Formed, placed, finishes and striped Holmes sidewalk piece where yard drain discharge
to parking lot
Work by Subcontractor? NO
Prime Contractor SCI Infrastructure, LLC Sub-Contractor
LABOR
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Gary 011verson Foreman 4 $55 74 $ 22296
Is
$
SUBTOTAL-LABOR $ 22296
LABOR OVERHEAD&PROFIT @ 29% $ 6466
LABOR TOTAL $ 23762
EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate His Standby Rate AMOUNT
335.130 1/2 ton truck 4 $19 37 $ 7748
Is -
SUBTOTAL-EQUIPMENT $ 7748
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 1627
EQUIPMENT TOTAL $ 9375
MATERIALSISERVICESIRENTALS -
MATERIALS/SERVICES Quantity Units Unit Price DOLLARAMOUNT
601b Sakrete Concrete Mix 8 EA $ 299 $ 23 92
$
SUBTOTAL $ 2392
OVERHEAD&PROFIT @ 21% $ 502
TOTAL $ 2894
Verification of Hours Worked TOTAL $ 41031
12%MARKUP(for prime when subcontract work) $ -
Contractor's Representative Date�L t SHEET TOTAL, $ 41031
owners Representative f Date-1 t�(I