CHANGE ORDER NO. #15
NAME OF CONTRACTOR: Goodfellow Brothers Inc ("Contractor")
CONTRACT NAME & PROJECT NUMBER: SE 256th Street Improvements
ORIGINAL CONTRACT DATE: June 6, 2013
This Change Order amends the above-referenced contract; all other provisions of the
contract that are not inconsistent with this Change Order shall remain in effect. For valuable
consideration and by mutual consent of the parties, the project contract is modified as follows:
1. Section I of the Agreement, entitled "Description of Work," is hereby modified to
add additional work or revise existing work as follows:
In addition to work required under the original Agreement and any
prior Amendments, Contractor shall provide all labor, materials, and
equipment necessary to:
Remove and reinstall storm pipe, design change required due to field
conflicts.
2. The contract amount and time for performance provisions of Section II "Time of
Completion," and Section III, "Compensation," are hereby modified as follows:
Original Contract Sum, $5,208,988.60
(including applicable alternates and
WSST)
Net Change by Previous Change Orders $46060.51
(incl. applicable WSST)
Current Contract Amount $5,255,049.11
(incl. Previous Change Orders)
Current Change Order $5060.07
Applicable WSST Tax on this Change_ $0.00 .
Order
Revised Contract Sum $5,260,109.18
CHANGE ORDER - 1 OF 3
Original Time for Completion 300 working days
(insert date)
Revised Time for Completion under 304worlcingdays
prior Change or
(insert date)
Days Required (t) for this Change 2 calendar days
Order
Revised Time for Completion 306 working days
(insert date)
In accordance with Sections 1-04.4 and 1-04.5 of the Kent and WSDOT Standard
Specifications, and Section VII of the Agreement, the Contractor accepts all requirements of this
Change Order by signing below. Also, pursuant to the above-referenced contract, Contractor
agrees to waive any protest it may have regarding this Change Order and acknowledges and
accepts that this Change Order constitutes final settlement of all claims of any kind or nature
arising from or connected with any work either covered or affected by this Change Order,
including, without limitation, claims related to contract time, contract acceleration, onsite or
home office overhead, or lost profits. This Change Order, unless otherwise provided, does not
relieve the Contractor from strict compliance with the guarantee and warranty provisions of the
original contract, particularly those pertaining to substantial completion date.
All acts consistent with the authorityof the Agreement, previous Change Orders (if any),
and this Change Order, prior to the effective date of this Change Order, are hereby ratified and
affirmed, and the terms of the Agreement, previous Change Orders (if any), and this Change
Order shall be deemed to have applied.
The parties whose names appear below swear under penalty of perjury that they are
authorized to enter into this contract modification, which is binding on the parties of this
contract.
3. The Contractor will adjust the amount of its performance bond (if any) for this
project to be consistent with the revised contract sum shown in section 2; above.
IN WITNESS, the parties below have executed this Agreement, which will
become effective on the last date written beW.
CONTRACTOR: CITY OF E(ENT:
By. lgnature) By:
n (sig ture)
Print me: Print Name: Timothy J LaPorte P E
Its f w- Its Public Works Director
(title)
DATE: DATE: 4/- 2,1
CHANGE ORDER - 2 OF 3
® I
KENT FILE NO: 200.2
w.. ,.a.o. CHANGE ORDER WORKSHEET NO. 15
Construction Management Division - Public Works
Project: SE 256th Street Improvements Project No.: 09-3012C
Project, Engineer: Mark Madfai Fed-Aid No.: N/A
Owners Rep: Phil McConnell Contractor: Goodfellow Brothers
Date: Various
I. PROPOSED CHANGE
Remove and reinstall storm pipe
II. REASON AND BACKGROUND FOR CHANGE
b� ��yro �n �@ ele,� Meld conk ; ct5
III. METHOD OF PAYMENT
NEW PAY ITEM(S) ® Not Applicable
Change,Order No. I - I I FOR ACCOUNTING USE ONLY
Sch. No. Item Description Total Est. Qty this Unit Unit Price Total Estimated Cost of
Qty PE Item
Storm system changes 1 1 FA 5 060.07—( 5,060,07 _
Independent Estimate Attached n CREATE PAY ITEM ONLY- Payment to be made M PAY THIS PAY ESTIMATE
_ -RE_ UIRED at a later datep—u on comQletlon of work __ _
--
❑ Material Submittals Reouired -CC: Construction Coordinator New Sub Reqrd? I No
DELETE EXISTING PAY ITEM(S) per 1-09.5 ® Not Applicable
Change.Order No. I I _ I I IFOR ACCOUNTING USE ONLY
Sch. No. B.I. No. Item Description _ Qty Unit _ Unit Price----- Cost of Item
Independent Estimate Attached -REQUIRED
INCREASE/DECREASE TO EXISTING PAY ITEM(S) ® Not Applicable
Change Order No. _ ( FOR ACCOUNTING USE ONLY
No. --- Item Description _ _ Qty j Unit Unit Price Cost of Item
Independent Estimate Attached - REQUIRED
1 REV. DATE: 4101110
® T FILE NO: 200.2
KEN
W S TOTAL ESTIMATED COST OF CHANGE ORDER
*Total of the Cost of Item Columns
THIS PAY ESTIMATE [—$5,060.07
IV. WORKING DAYS
Original Contract 300 Due This Change Order* Z Previous Total 304
_DATE_ ____ /2014 �--- --
- ----`_---- �DATE:_�3j18 2014 ___
*—T Ex lanation justification Re wired: additional work Im acted the crltical oath
TOTAL WORKING DAYS* C —
*This Change order + Previous Total
All work, materials and measurements to be in accordance with the Standard Specifications
and Contract Special Provisions for the type of work described.
Prepared BY: Date:
Ptril McConnell
Construction Supervisor: Date:
Paul Kuehne '
Construction Manager: Date:
2 REV. DATE: 4/01/10
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKED
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 3/24/2014
Description of Work: Lowered storm run and picked up private 6 inch drain pipe
Work by Subcontractor?: no
Prime Contractor: Goodfellow Brothers Sub-Contractor:
LABOR"
STRAIGHTTIME OVERTIME DO LLAR�
NAME CODE OCCUPATION HIS Hourly Rate Hrs OT Rate AMOUNT
Dan foreman 2.51 63011 1 1 $ 157.53
Jason operator 2.5 60.16 $ 150.40
Rob pipelayer 2.5 48.96 $ 122.40
Jose laborer 2.6 48.1 $ 120.25
operator 1 60.16 $ 60.16
SUBTOTAL-LABOR: $ 610.74
LABOR OVERHEAD&PROFIT @ 29% $ 177.11
LABORTOTAL $ 787.85
EQUIPMENT. .
EQUIPMENT OR ATTACHMENTS OPERATED STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Mrs Standby Rate AMOUNTi,
JD 135G excavator 1.5 66.51 1 16.73 $ 116,50
JD 624 loader 1 14.63 $ 14.63
F150 pickup 2.5 19.18 $ 47.95
F550 sew truck -2.5 20.46 $ 73.65
$
SUBTOTAL-EQUIPMENT $ 252.73
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 53.07
EQUIPMENT TOTAL $ 305.80
MATERIALS/SERVICES/RENTALS
MATERIALS l SERVICES Quantity Units Unit Price DOLLAR AMOUNT
6 Inch pvc 2 If $ 2.08 $ 4.16
6 inch 22.5 bend 1 ea- $ 14.86 $ 14.86
1 foot catch basin dsed 1 as $ 37,82 $ 37,82
5
SUBTOTAL $ 56.84
OVERHEAD&PROFIT @ 21% $ 11.94
TOTAL $ 68.78
Verification of Hours Worked: TOTAL: $ 1,162.43
12%MARKUP (for
prime when subcontract work) $ -
contractors Representative Date SHEET TOTAL: $ , 1,162.43
Owners Representative Date'
Comments
i
i
FA Sheet No.:
DAILY REPORT OF ^
FORCE ACCOUNT WORKED >
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No,: 4000 Date: 3/18 & 19/2014
Description of Work: Conflict with new storm pipe elevations. Backfill and redesign
Work by Subcontractor?: no
Prime Contractor: Goodfellow Brothers Sub-Contractor: .
LABOR =
STRAIGHT TIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Dan - foreman 5 63.01 - $ 315.05
Jason - operator 5 59.6 $ 298.00
Tom operator 3 59.6 $ 178.80
Robert pipelayer 5 48.96 $ 244.80
SUBTOTAL-LABOR: $ 1,036.65
LABOR OVERHEAD&PROFIT @ 29% $ 300.63
LABOR TOTAL $ 1,337.28
'. EQUIPMENT!
EQUIPMENT OR ATTACHMENTS OPERATEDSTANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Mrs Standby Rate AMOUNT
JD 135 G excavator 4 66.51 1 18.73 $ 282.77
JD 624K loader -' 1 70.20 2 14.63 $ 99.46
F150 pickup 4 19.15 1 1.80 $ 78.52
F550 Flatbed truck 4 29.46 1 3.68 $ 121 52
$ i
SUBTOTAL-EQUIPMENT $ 582.27
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 122,28
EQUIPMENT TOTAL $ 704.55
MATERIALS/SERVICES/RENTALS
MATERIALS SERVICES Quantity Units Unit Price DOLLARAMOUNT
$
SUBTOTAL $ -
OVERHEAD&PROFIT @ 21% $
TOTAL $
Verification of Hours Worked: TOTAL: $ 2,041.83
12%MARKUP (for
prime when subcontract work) $ -
Contractors Representative Dale SHEET TOTAL: $ 2,041.83
Owners Representative Date
Comments
i
FA Sheet No.:
DAILY REPORT OF
FORCE ACCOUNT WORKED �/ ICENT
Project Name: SE 256th Street Improvements Project No: 09-3012
Item No.: 4000 Date: 3/17/2014
Description Of Work: Conflict with new and existing storm pipe elevations. Backfill and redesign
Work by Subcontractor?: no
Prime Contractor: Goodfellow Brothers Sub-Contractor: .
LABOR'''
STRAIGHTTIME OVERTIME DOLLAR
NAME CODE OCCUPATION Hrs Hourly Rate Hrs OT Rate AMOUNT
Dan foreman 4 63.01 $ - 252.04
Jason operator 4 59,6 $ 238.40
Tom operator - 2 59.6 $ 11920 i
Robert plpelayer 4 48.96 - $ 195.84
Jose laborer 4 481 $ 19240
SUBTOTAL-LABOR: $ 997.88
LABOR OVERHEAD&PROFIT @ 29% $ 289.39
LABOR TOTAL $ 1,287.27
' EQUIPMENT
EQUIPMENT OR ATTACHMENTS OPERATED. STANDBY DOLLAR
Equipment# Equipment Description Hrs Hourly Rate Hrs Standby Rate AMOUNT
JD 135 G excavator - 3 66.51 1 16.73 $ 216.26
JO 624K loader 1 70.20 1 14.63 $ 84.83
F150 pickup 4 19.18 $ 76.72
F550 Flatbed truck - 3 -29.46 1 3.68 $ 92.06
$
SUBTOTAL-EQUIPMENT $ 469.87
EQUIPMENT OVERHEAD&PROFIT @ 21% $ 98.67
EQUIPMENTTOTAL $ 688.54
''` ''=- MATERIALSISERVICESfRENTALS -
MATERIALS I SERVICES Quantity Units Unit Price DOLLAR AMOUNT
$
$
$
SUBTOTAL $ -
OVERHEAD&PROFIT @ 21% $ -
TOTAL $
Verification of Hours Worked: TOTAL: $ 1.855.81
12%MARKUP (for
prime when subcontract work) $ -
contractors Representative Dale
SHEET TOTAL: $ 1,855.81
Owners Representative Data
Comments